Recently Paste Plant 1 experienced a failure to one of their supply transformers.
When the Substation team heard that the Paste Plants were suffering from issues that impacted on production, a
decision was made to fast track the replacement of the transformer.
With a new transformer still needing work to adapt to the location, the team decided that the best option would be
to utilise an existing transformer which would be a direct replacement and needed no modification.
The team wasted no time once the decision was made and clearance given to use the transformerthe standby
unit at the AT Substation near the Apprentice Training Workshop. Wayne Masters took a lead role and the unit
was disconnected and installed at the Substation over a two shift period.
While the transformer was not required to be used for any of the immediate issues within the Paste Plant, it did
give the area a back-up option should a new issue arise.
It was a great example of Blue Bus thinking and our Trades stepping up and taking control of the situation.
Thank you to all those involved including Downer, Boom, Johan Kruger & labourers and Mal Muddle.
Special mention goes to the Substation team and Wayne Masters who looked after almost every aspect of the re-
moval and installation. Story submitted by: Scott Badman
BEFORE AFTER
Click on the light bulb icon above & submit your idea online at the Good Ideas Page.
Baby Baldwin
Some of you may be aware that Kristy Baldwin (Administration AssistantCarbon) & husband Michael welcomed a beautiful
baby girl in to the world on 22 March 2017, Lyla Anne Baldwin, weighing in at a tiny 5 pound 4 oz.
Mum & baby are doing extremely well, adapting to the no sleeping schedule of newborn life!
Happy Easter
Tomago Aluminium would like to wish all its
employees a very
Happy Easter
Please stay safe on the roads over the holiday period & remember Double Demerits apply from
Thursday 13Monday 17 April