Number
There is slightly more than the required amount
The 1st piece will start 3 inches from the end of the footing and end 20 feet, 3inches from the end of the
footing
38'3''
2'' lap | 3'6'' piece
3''
40''
15 5/8 inch.
=
= 3 rows x 3 columns = 9 blocks
Plywood
Lumber 165 bf per 100 SFCA
Carpenter Helper
Make the form 3.5 hr 1.5 hr
Erect and remove the form 6.5 hr 5 hr
Number of sheets:
Lumber:
Form Oil:
Nails:
First use: 15lb per 1000 bf = 36 lb
2nd, 3rd, and 4th use: 10lb per 1000 bf = 72 lb
Total (nails) = 108 lb
2) Labour Hours:
Making Forms:
Carpenter:
Helper:
Helper:
5800 SFCA x (5hr/100SFCA) = 290 hr
Foreman time based on carpenter time:
(50.8 + 377)/4 = 106.95 hrs
3) Summary of materials
1) Quantity of Materials
Forms to be erected and removed:
Forms to be built =
From labour hours table (1)
** use median values for quantities of material
For 12 ft wall height
Plywood = 105
Lumber = 225
Ties:
Labour Hours:
Make the form Carpenter Helper
Make the form 2.25 1.75
Per 100SFCA
Erect and remove 4.75 4.25
Plyform Sheathing :
2) Lumber:
3) Ties
Oil
1Gallon of oil --> 300 to 500 SFCA (use avg 400SFCA)
1Gallon of oil = 400 SFCA
- for wall, columns, or slabs
Form oil =
Nails
For walls and columns:
First: use 10 lb per 1000 bf to 20 lb per 1000 bf
(average: 15lb per 1000 bf)
Second and more: use 5 to 10 lb per 1000 bf
(for accuracy, you can use the average, but 10 lb wont
cost much more and there will be waste)
Slab:
First: 5lb to 10lb per 1000 bf
Nails for first use:
Nails for 2 reuses:
Helper:
Helper;
Foreman time =
5) Summary of materials"
Plywood = 23 sheets
Lumber = 1539 bf
Oil = 6 gallons
Ties = 370
6) Summary of Labour
Carpenter = 15.4 hr + 97.5hours = 113 hours
Helper = 12 hr + 87.2 hr = 99.2 hours
Foreman = 28.2 hours
1) Quantity of Materials
Total Surface area:
Plywood
Lumber 165 bf per 100 SFCA
Carpenter Helper
Make the form 3.5 hr 1.5 hr
Erect and remove the form 6.5 hr 5 hr
Number of sheets:
Lumber:
Form Oil:
Nails:
First use: 15lb per 1000 bf = 36 lb
2nd, 3rd, and 4th use: 10lb per 1000 bf = 72 lb
Total (nails) = 108 lb
2) Labour Hours:
Helper:
Helper:
5800 SFCA x (5hr/100SFCA) = 290 hr
Foreman time based on carpenter time:
(50.8 + 377)/4 = 106.95 hrs
3) Summary of materials