Lecture - Quantity Takeoff

November 9, 2017 2:45 PM

Counted items
Linear items
Sheets & Rolls of items
Volumetric Items

7 - Quantity Takeoff Page 1


Assume that the studs will be needed for both sides - if
not specified
Number =
Number = 5 studs

If the wall has openings


- First: assume the wall doesn’t have any openings and
count the number of studs
- Then: Double the studs only where the openings are

7 - Quantity Takeoff Page 2


Number = + 1 = 4.33 = 5

Using conventional rules of rounding, one would round


down to 4, leaving the estimate 1 stud short of the
needed number of studs

Rounding this up, one should get 5 studs, the number of


studs needed to complete this wall

Effective length LAP

7 - Quantity Takeoff Page 3


7 - Quantity Takeoff Page 4
7 - Quantity Takeoff Page 5
(Lap Joint)

Number
There is slightly more than the required amount
The 1st piece will start 3 inches from the end of the footing and end 20 feet, 3inches from the end of the
footing

Order an extra piece L = 3' 6''


3'' 20'3''
20' piece
2'' lap 20' piece

38'3''
2'' lap | 3'6'' piece
3''

40''

7 - Quantity Takeoff Page 6


7 - Quantity Takeoff Page 7
Center to centre of mortar

7 - Quantity Takeoff Page 8


7 - Quantity Takeoff Page 9
7 5/8 in.

15 5/8 inch.

1) Joint type: spaced joint

Three rows of blocks are needed

Using Eq. 13 to get the number of column, we get the following

7 - Quantity Takeoff Page 10


Three columns of blocks are needed
Using equation 14, we calculate the number of blocks needed as
follows:

=
= 3 rows x 3 columns = 9 blocks

7 - Quantity Takeoff Page 11


Volume = LWH =
Volume in yd3 =

7 - Quantity Takeoff Page 12


V = 123.5
Using Eq 16, we add the waste:

7 - Quantity Takeoff Page 13


The waste percentage is calculated using Eq 17

7 - Quantity Takeoff Page 14


7 - Quantity Takeoff Page 15
7 - Quantity Takeoff Page 16
7 - Quantity Takeoff Page 17
7 - Quantity Takeoff Page 18
7 - Quantity Takeoff Page 19
See Pages

7 - Quantity Takeoff Page 20


7 - Quantity Takeoff Page 21
7 - Quantity Takeoff Page 22
1) Quantity of Materials
Total Surface area:

Number of columns placed simultaneously:

SFCA of columns built:

Columns to be erected and removed = 5800 SFCA

Average values from table 2 will be used for quantities

Plywood
Lumber 165 bf per 100 SFCA

Carpenter Helper
Make the form 3.5 hr 1.5 hr
Erect and remove the form 6.5 hr 5 hr

From table 2, the quantity will be:


Plywood:

Number of sheets:

Lumber:

** Assume 10 clamps per column


** clamps are REUSABLE

Form Oil:

Nails:
First use: 15lb per 1000 bf = 36 lb
2nd, 3rd, and 4th use: 10lb per 1000 bf = 72 lb
Total (nails) = 108 lb
2) Labour Hours:
Making Forms:
Carpenter:

Helper:

Erecting and removing forms:


Carpenter:

Helper:
5800 SFCA x (5hr/100SFCA) = 290 hr
Foreman time based on carpenter time:
(50.8 + 377)/4 = 106.95 hrs
3) Summary of materials

7 - Quantity Takeoff Page 23


7 - Quantity Takeoff Page 24
7 - Quantity Takeoff Page 25
Example 8
November 9, 2017 5:03 PM

1) Quantity of Materials
Forms to be erected and removed:

** 1/3 of this will be built

Forms to be built =
From labour hours table (1)
** use median values for quantities of material
For 12 ft wall height
Plywood = 105
Lumber = 225
Ties:
Labour Hours:
Make the form Carpenter Helper
Make the form 2.25 1.75
Per 100SFCA
Erect and remove 4.75 4.25

Plyform Sheathing :

2) Lumber:

3) Ties

Oil
1Gallon of oil --> 300 to 500 SFCA (use avg 400SFCA)
1Gallon of oil = 400 SFCA
- for wall, columns, or slabs
Form oil =

Nails
For walls and columns:
First: use 10 lb per 1000 bf to 20 lb per 1000 bf
(average: 15lb per 1000 bf)
Second and more: use 5 to 10 lb per 1000 bf
(for accuracy, you can use the average, but 10 lb wont
cost much more and there will be waste)
Slab:
First: 5lb to 10lb per 1000 bf
Nails for first use:
Nails for 2 reuses:

7 - Quantity Takeoff Page 26


Total (Nails) = 53.9 lb
4) Labour - hours required
Making forms:
Carpenter:

Helper:

Erecting and removing forms:


Carpenter:

Helper;

Foreman time =

5) Summary of materials"
Plywood = 23 sheets
Lumber = 1539 bf
Oil = 6 gallons
Ties = 370
6) Summary of Labour
Carpenter = 15.4 hr + 97.5hours = 113 hours
Helper = 12 hr + 87.2 hr = 99.2 hours
Foreman = 28.2 hours

7 - Quantity Takeoff Page 27


Example 9

November 9, 2017 5:22 PM

1) Quantity of Materials
Total Surface area:

Number of columns placed simultaneously:

SFCA of columns built:

Columns to be erected and removed = 5800 SFCA

Average values from table 2 will be used for quantities

Plywood
Lumber 165 bf per 100 SFCA

Carpenter Helper
Make the form 3.5 hr 1.5 hr
Erect and remove the form 6.5 hr 5 hr

From table 2, the quantity will be:


Plywood:

Number of sheets:

Lumber:

** Assume 10 clamps per column


** clamps are REUSABLE

Form Oil:

Nails:
First use: 15lb per 1000 bf = 36 lb
2nd, 3rd, and 4th use: 10lb per 1000 bf = 72 lb
Total (nails) = 108 lb
2) Labour Hours:

7 - Quantity Takeoff Page 28


2) Labour Hours:
Making Forms:
Carpenter:

Helper:

Erecting and removing forms:


Carpenter:

Helper:
5800 SFCA x (5hr/100SFCA) = 290 hr
Foreman time based on carpenter time:
(50.8 + 377)/4 = 106.95 hrs
3) Summary of materials
OYO