You are on page 1of 2

Hitung Bobot (%) Pekerjaan

HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME (Rp)

1 Mobilisasi ls 1 150,000,000
2 Galian Saluran Drainase m3 3,500 40,000
3 Galian Biasa m3 12,000 45,000
4 Timbunan Pilihan m3 5,750 300,000
5 Lapis Pondasi Kelas B m3 3,000 700,000
6 Lapis Pondasi Kelas A m3 2,250 1,200,000
7 Lapis Pengikat Liter 6,750 11,000
8 Laston AC-BC Ton 1,725 2,200,000
9 Penyiapan Badan Jalan M2 20,000 3,000
TOTAL
kerjaan
JUMLAH HARGA BOBOT
(Rp) (%)

150,000,000 1.33
140,000,000 1.24
540,000,000 4.79
1,725,000,000 15.29
2,100,000,000 18.61
2,700,000,000 23.93
74,250,000 0.66
3,795,000,000 33.63
60,000,000 0.53
11,284,250,000 100.00