S NO PLANT Major Jobs Struct jobs Near Misses Total Jobs Quantity Completed Pending Status Target date
(SRE) 16-17 (Ton) (Ton) (Ton) for Completion
(a) (b) (a + b)
1 SAP-1&2 Inspection Recommendations (as per List) 32 13 45 10 6 4
2 PAP/FRU Inspection Recommendations (as per List) 33 24 57 10 2 8
3 COMPLEX A-Tr Inspection Recomm (as per List) 39 27 66 23 12 11 In Progress
A-Tr Main-Sump area platforms & Materials expected by 5th 12-Feb-18
Gratings replacement Feb 18
Cont: M/s Parameswari
5 COMPLEX C-Tr Inspection Recomm (as per List) 32 34 66 10 3 7 Materials expected by 6th 25-Feb-18
Feb 18
Cont: M/s Divya Engg
9 COMPLEX JD1451 Pipe Conveyor struct (Phase-II) 0 12 12 Materials & Service ATA-18
PRs raised
10 BAGGING Inspection Recommendations (as per List) 19 19 9 7 2 In Progress
Old Bagging staircase replacement Fabrication completed 10-Feb-18
(High risk job) Erection pending
M/s Toshita Engg