Chapter 1 Preparation procedures prior to the Kiln Shutdown Plan
Observance of proper preparation procedures prior to the
shutting down of Kiln for maintenance schedule is one of the important procedures in ensuring the efficiency of the shutdown process, as well as to ensure that the time span involved and budgets are in accordance to the established Operation and Maintenance Plan (Manual). The processes involved prior to the shutting down of Kiln require advance preparation of at least one month, by observing and implementing the following tasks:
1.1 Inspection of Kiln Migration
- For the cement Kiln, both migration and ovality
values of the Kiln shall be measured and compared with each other prior to its shutdown. The respective values of both migration and ovality must be within the allowable range. - The Kiln migration values shall be monitored and recorded weekly. The data of kiln migration shall be used together with the kiln ovality values, which are vital indicators prior to the shutting down of Kiln, and during the full production capacity. The observed data of both kiln migration values and kiln ovality values should be at least 1 month prior to the shutting of the Kiln. Thus, if any value deviate from the standards (acceptable range), the refractory lining under the tyre areas could have been affected from the excessive external compressive stress thereby creating cracks or spalling effect which will consequently reduce the service life of refractory lining. - The migration and ovality values are to be jointly evaluated in drawing conclusion and setting a Kiln REFRACTOTRY INSTALLATION TECHNIQUES 2 IN CEMENT INDUSTRY
Stop Plan which would set the adjustment target of
the migration value of each tyre.
1.2 Allocation of Refractory Maintenance Area
- The previous refractory maintenance records of each
zone in the Rotary Kiln, as shown in the past Kiln maintenance schedule are important inputs in determining the present refractory maintenance operations. - The current condition of the Kiln operating prior to the implementation of maintenance schedule must be monitored whether there has any abnormalities occurred in the refractory. For example, the outside shell temperature of the Rotary Kiln, Cyclone Preheater and Clinker Cooler should be checked whether any of their surface areas have been experiencing raised in temperature values beyond the normal standards. These data are necessary inputs in determining the refractory maintenance plan of each area. - For the outside surface wall of the Cyclone Preheater, Hot Air Duct, Calciner and various Down Pipes, where the damages of the refractory had been temporarily repaired by the use of box welding (Fig. 1.1), they must be included in the present Kiln Stop Plan by replacing its steel wall surface and the refractory should be repaired/replaced by inside maintenance approach, which is more appropriate. - To enhance the efficiency of refractory installation tasks, there must be an agreed scope of work between the two working teams, the Cement Production Team and the Refractory Installation Team. This will ensure that there will be no conflicts and problems occur during the Kiln maintenance operations, and the scope REFRACTOTRY INSTALLATION TECHNIQUES 3 IN CEMENT INDUSTRY
of the refractory maintenance tasks have been
properly defined and planned and therefore achieving the objective of best quality of work within the required timeframe. REFRACTOTRY INSTALLATION TECHNIQUES 4 IN CEMENT INDUSTRY
Fig. 1-1: Pictures of the refractory installation in Hot Air
Duct, refractory repaired by box welding [outside maintenance approach]
1.3 Inspection of the refractory inventory, condition and
quantity
- The planner shall monitor the quantity and conditions
of all available refractory in the warehouse and compare them with the estimated quantity required in the schedule/plan (the quantity can be estimated based on the previous record of the area to be replaced or repaired) for at least 3 months in advance to give the refractory manufacturer sufficient time to deliver the products, based on the Kiln Stop Plan. - The preparation or estimates of the quantity of refractory for the Cyclone Preheater and Clinker Cooler can be obtained from the average number of REFRACTOTRY INSTALLATION TECHNIQUES 5 IN CEMENT INDUSTRY
refractory used during each of the previous Kiln
maintenance schedule. - During 2-4 weeks prior to the kiln shutdown, the quantity and conditions of the refractory shall be again re-checked to confirm their availability in the warehouse and readiness for use. - In addition, the routine inspection on the conditions and quantity of refractory shall also include inspection of other accessory materials to be used with the refractory; such as various grades of Anchors for each corresponding areas, Welding Electrode, Card Board, Plywood, Wax, and etc. - The proactive preparation and systematically storage of materials and establishment of efficient material withdrawal system will contribute to the reduction of materials loss/wastage.
1.4 Inspection of tools and equipment
- An inspection of the tools and equipment, which are
to be used for removing and installing the refractory, in terms of their usage condition, availability, quantity, and quality to sufficiently meet the bulk of work should be done at least one month prior to the scheduled Kiln shutdown. These tools and equipment include: o Demolishing Car o Cavo Car o Mult-O-Ring o Air Breaker o Pan Mixer; the gap/distance between the propeller and the floor bed should not be less than 0.5 mm. and not more than 10 mm. to the wall. If the distance exceeds the standard, a corresponding adjustment can be done by REFRACTOTRY INSTALLATION TECHNIQUES 6 IN CEMENT INDUSTRY
installing steel plate (through welding) to
adjust the distance. The Pan mixer must also be cleaned. o Hydraulic Jack; hydraulic supports lining during the movement of Mult-O-Ring to install the refractory in the proceeding rings. o Vibrator o Refractory brick cutter and a diamond blade; the brick cutter shall be a non-water cooling type, since the basic bricks should not be wet or hydrated.
Fig. 1-2: Picture of a brick cutter with the blade
o Hacksaw and Wood Saw; for preparation of
wooden forms/ moulds for castable installation. REFRACTOTRY INSTALLATION TECHNIQUES 7 IN CEMENT INDUSTRY
Fig. 1-3: Picture of a hacksaw
o Air Compressor; to be used during the
installation of rotary kiln refractory bricks in the upper half portion. - The aforementioned tools and equipment must be inspected and certified by the safety department to prevent any possible danger during the usage. - The handling equipment/ machine/ vehicle such as Lift, Folk Lift, Truck, Hand Lift, Crane, Hoist, and Belt Conveyer are necessary to be checked and inspected for their efficiency and capability to effectively hold the weight of the refractory to be handled or lifted. - Prepare sufficient number of the personal protective equipment, for example Safety Shoes (heat steel head, heat resistance and heel covered safety shoes are necessary for refractory inspection in the kiln during immediate shutdown given that the kiln is still hot), Dust Filler Mask, Goggle (protection of dusts and tiny objects into the eyes), Safety Belts (for working in high elevated areas, for instance, Cyclone Preheater), and Safety Helmet. Also, make use of personal REFRACTOTRY INSTALLATION TECHNIQUES 8 IN CEMENT INDUSTRY
protective equipment and install safety signs to
control and ensure safety awareness.
Fig. 1-4: Picture of the personal protective equipment
Fig. 1-5: Picture of the required personal protective
equipment and safety signs to control and ensure safety awareness before engaging in the work REFRACTOTRY INSTALLATION TECHNIQUES 9 IN CEMENT INDUSTRY
1.5 Preparation of workforce plan for refractory
maintenance work
- The exact timetable in the Kiln Stop Plan, including
the allowable working time and amount of work to remove and install refractory on various areas, must be notified to the responsible persons who are directly in-charge of refractory works, at least 1 month in advance, to be able to prepare adequate manpower that correspond to the amount of work. - A capacity building or training on refractory knowledge for the operators; both in theory and implementation, and by evaluating their understanding and skills prior to the scheduled Kiln maintenance will enhance the ability of the operators/ workers to achieve better efficiency, quality, and accuracy. - There must also be training provided on work guidelines, safety in workplace, first aid procedures, and evacuation plan in case of emergency. After the training, workers must be evaluated for their knowledge and understanding in order to be documented as certified personnel and allowed to work.
1.6 Preparation of storage areas layout for the refractory
and tools and equipment
- There must be an arrangement of the storage area for
the refractory and tools and equipment in the working areas so as to ensure convenience and efficiency in mobilizing the materials. - The storage area within the working areas must be under the shade and away from rainstorm; for instance the area below Cyclone Preheater for REFRACTOTRY INSTALLATION TECHNIQUES 10 IN CEMENT INDUSTRY
refractory, the area below Clinker Cooler for the
refractory to be used in the Rotary Kiln and Clinker Cooler. - In the absence of adequate storage area, refractory and tools and equipment may be laid in the ground yard but shall be fully covered with water-proof cover sheets. - The laying of the refractory in the storage areas shall be systematically arranged by their quality, and shapes or sizes and sequence of their usage, especially in close areas.