ETAP

Project: Ginebra Cabuyao Plant 14.1.0C Page: 1


Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Electrical Transient Analyzer Program

Load Flow Analysis

Loading Category (1): Design

Generation Category (1): Design

Load Diversity Factor: None

Swing V-Control Load Total

Number of Buses: 1 0 32 33

XFMR2 XFMR3 Reactor Line/Cable Impedance Tie PD Total

Number of Branches: 16 0 0 12 0 4 32

Method of Solution: Newton-Raphson Method

Maximum No. of Iteration: 99

Precision of Solution: 0.0001000

System Frequency: 60.00 Hz

Unit System: English

Project Filename: ginebra_analysisv2

Output Filename: C:\ETAP 1410\Ginebra\loadflow_utility_nocapacitor.lfr

54 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 2
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent
Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: No

Cable Length: No

Apply Individual
Temperature Correction Adjustments /Global Degree C

Transmission Line Resistance: Yes Individual

Cable Resistance: Yes Individual

55 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 3
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Bus Input Data

Load
Bus Initial Voltage Constant kVA Constant Z Constant I Generic

ID kV Sub-sys % Mag. Ang. MW Mvar MW Mvar MW Mvar MW Mvar

Bus1 0.480 1 89.3 -5.2

Bus2 0.480 1 89.3 -5.2

Bus3 0.480 1 89.3 -5.2

Bus14 34.500 1 100.0 0.0

Bus15 0.480 1 92.8 -4.4

Bus16 0.480 1 91.7 -4.7

Bus17 0.480 1 89.3 -5.2

Bus18 0.480 1 89.1 -5.2

Bus19 0.240 1 85.5 -6.4 0.036 0.022 0.012 0.007

Bus20 0.240 1 87.6 -5.6 0.009 0.006 0.003 0.002

Bus21 0.240 1 87.1 -5.9 0.033 0.020 0.011 0.007

Bus22 0.240 1 85.4 -7.1 0.086 0.053 0.029 0.018

Bus23 0.240 1 85.2 -6.1 0.034 0.021 0.011 0.007

Bus24 0.240 1 86.3 -6.7 0.140 0.087 0.093 0.058

Bus25 0.240 1 87.0 -6.3 0.094 0.058 0.063 0.039

Bus26 0.240 1 85.3 -6.4 0.038 0.024 0.025 0.016

Bus27 0.240 1 85.3 -6.4 0.049 0.030 0.032 0.020

Bus28 0.240 1 87.2 -6.3 0.085 0.053 0.028 0.018

Bus29 0.240 1 82.9 -7.4 0.066 0.041 0.022 0.014

Bus30 0.240 1 81.7 -8.3 0.112 0.069 0.037 0.023

Bus31 0.240 1 80.5 -9.1 0.153 0.095 0.051 0.032

Bus32 0.240 1 85.7 -6.6 0.052 0.032 0.013 0.008

Bus36 0.480 1 88.3 -5.4 0.011 0.007 0.004 0.002

Bus37 0.480 1 88.3 -5.4

Bus38 0.480 1 87.9 -5.2 0.117 0.073 0.039 0.024

Bus39 0.480 1 88.2 -5.4 0.004 0.002 0.002 0.002

Bus40 0.480 1 87.3 -5.2

Bus41 0.480 1 88.0 -5.5 0.358 0.222 0.119 0.074

Bus42 0.480 1 88.8 -5.2 0.003 0.002 0.001 0.001

Bus43 0.480 1 84.6 -6.2 0.069 0.043 0.023 0.014

Bus44 0.240 1 87.9 -6.1

Bus45 0.480 1 88.6 -5.4

56 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 4
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Load
Bus Initial Voltage Constant kVA Constant Z Constant I Generic

ID kV Sub-sys % Mag. Ang. MW Mvar MW Mvar MW Mvar MW Mvar

Bus46 0.240 1 87.8 -5.9 0.055 0.034 0.036 0.023

Total Number of Buses: 33 1.603 0.994 0.656 0.407 0.000 0.000 0.000 0.000

Generation Bus Voltage Generation Mvar Limits


ID kV Type Sub-sys % Mag. Angle MW Mvar % PF Max Min

Bus14 34.500 Swing 1 100.0 0.0

0.000 0.000

57 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 5
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Line/Cable Input Data

Ohms or Siemens/1000 ft per Conductor (Cable) or per Phase (Line)


Line/Cable Length

ID Library Size Adj. (ft) % Tol. #/Phase T (C) R X Y

C1 15MCUS3 500 328.1 0.0 18 75 0.030000 0.039400

C2 15MCUS3 500 328.1 0.0 8 75 0.030000 0.039400

C3 15MCUS3 500 328.1 0.0 2 75 0.030000 0.039400

C4 15MCUS3 4/0 328.1 0.0 2 75 0.065000 0.044600

C5 15MCUS3 500 328.1 0.0 3 75 0.030000 0.039400

C6 15MCUS3 4/0 328.1 0.0 1 75 0.065000 0.044600

C7 15MCUS3 500 328.1 0.0 3 75 0.030000 0.039400

C8 15MCUS3 4/0 328.1 0.0 3 75 0.065000 0.044600

C9 15MCUS3 500 328.1 0.0 1 75 0.030000 0.039400

C10 15MCUS3 500 328.1 0.0 3 75 0.030000 0.039400

C11 15MCUS3 500 328.1 0.0 1 75 0.030000 0.039400

C12 15MCUS3 500 328.1 0.0 1 75 0.030000 0.039400

Line / Cable resistances are listed at the specified temperatures.

58 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 6
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted Phase Shift


ID Phase MVA Prim. kV Sec. kV % Z1 X1/R1 + 5% - 5% % Tol. Prim. Sec. %Z Type Angle

T1 3-Phase 2.000 34.500 0.480 7.25 7.10 0 0 0 0 0 7.2500 Dd 0.000

T2 3-Phase 0.150 0.480 0.240 4.00 3.45 0 0 0 0 0 4.0000 Dd 0.000

T3 3-Phase 0.100 0.480 0.240 2.60 1.92 0 0 0 0 0 2.6000 Dd 0.000

T4 3-Phase 0.050 0.480 0.240 2.60 1.69 0 0 0 0 0 2.6000 Dd 0.000

T5 3-Phase 0.050 0.480 0.240 2.60 1.69 0 0 0 0 0 2.6000 Dd 0.000

T6 3-Phase 0.050 0.480 0.240 2.60 1.69 0 0 0 0 0 2.6000 Dd 0.000

T7 3-Phase 0.500 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

T8 3-Phase 0.500 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

T9 3-Phase 0.150 0.480 0.240 4.00 3.45 0 0 0 0 0 4.0000 Dd 0.000

T10 3-Phase 0.113 0.480 0.240 4.00 3.45 0 0 0 0 0 4.0000 Dd 0.000

T11 3-Phase 0.300 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

T12 3-Phase 0.225 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

T13 3-Phase 0.225 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

T14 3-Phase 0.225 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

T15 3-Phase 0.225 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

T16 3-Phase 0.500 0.480 0.240 4.80 4.70 0 0 0 0 0 4.8000 Dd 0.000

59 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 7
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVA Base


ID Type From Bus To Bus R X Z Y

T1 2W XFMR Bus14 Bus15 50.57 358.96 362.50

T2 2W XFMR Bus36 Bus22 742.39 2561.24 2666.67

T3 2W XFMR Bus37 Bus21 1201.03 2305.98 2600.00


T4 2W XFMR Bus37 Bus20 2648.07 4475.24 5200.00

T5 2W XFMR Bus36 Bus19 2648.07 4475.24 5200.00

T6 2W XFMR Bus38 Bus23 2648.07 4475.24 5200.00


T7 2W XFMR Bus39 Bus24 199.78 938.98 960.00

T8 2W XFMR Bus39 Bus25 199.78 938.98 960.00

T9 2W XFMR Bus40 Bus27 742.39 2561.24 2666.67


T10 2W XFMR Bus40 Bus26 985.47 3399.88 3539.82

T11 2W XFMR Bus42 Bus28 332.97 1564.97 1600.00

T12 2W XFMR Bus43 Bus29 443.96 2086.63 2133.33

T13 2W XFMR Bus43 Bus30 443.96 2086.63 2133.33

T14 2W XFMR Bus43 Bus31 443.96 2086.63 2133.33

T15 2W XFMR Bus18 Bus44 443.96 2086.63 2133.33

T16 2W XFMR Bus45 Bus46 199.78 938.98 960.00

C1 Cable Bus15 Bus16 23.73 31.17 39.18

C2 Cable Bus16 Bus17 53.40 70.13 88.15

C3 Cable Bus3 Bus36 213.60 280.52 352.59

C4 Cable Bus3 Bus38 462.79 317.55 561.26


C5 Cable Bus3 Bus39 142.40 187.02 235.06

C6 Cable Bus3 Bus40 925.58 635.09 1122.52

C7 Cable Bus3 Bus41 142.40 187.02 235.06


C8 Cable Bus3 Bus42 308.53 211.70 374.17

C9 Cable Bus3 Bus43 427.19 561.05 705.17

C10 Cable Bus3 Bus18 142.40 187.02 235.06

C11 Cable Bus44 Bus32 1708.77 2244.19 2820.69


C12 Cable Bus3 Bus45 427.19 561.05 705.17

CB2 Tie Breakr Bus17 Bus1

CB4 Tie Breakr Bus1 Bus2


CB5 Tie Breakr Bus1 Bus3

CB24 Tie Breakr Bus36 Bus37

60 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 8
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

LOAD FLOW REPORT

Bus Voltage Generation Load Load Flow XFMR


ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

Bus1 0.480 89.316 -5.2 0 0 0 0 Bus17 -2.142 -1.400 3446.0 83.7

Bus2 0.000 0.000 0.0 0.0


Bus3 2.142 1.400 3446.0 83.7

Bus2 0.480 89.316 -5.2 0 0 0 0 Bus1 0.000 0.000 0.0 0.0

Bus3 0.480 89.316 -5.2 0 0 0 0 Bus36 0.223 0.146 358.4 83.7


Bus38 0.194 0.121 307.7 84.8

Bus39 0.362 0.237 582.7 83.7


Bus40 0.133 0.086 213.0 83.9

Bus41 0.456 0.286 724.9 84.7


Bus42 0.112 0.072 179.3 84.0
Bus43 0.517 0.358 846.3 82.2

Bus18 0.063 0.041 101.0 83.7

Bus45 0.083 0.053 133.1 84.4

Bus1 -2.142 -1.400 3446.0 83.7

* Bus14 34.500 100.000 0.0 2.247 1.777 0 0 Bus15 2.247 1.777 47.9 78.4
Bus15 0.480 92.761 -4.4 0 0 0 0 Bus16 2.205 1.483 3446.0 83.0

Bus14 -2.205 -1.483 3446.0 83.0


Bus16 0.480 91.699 -4.7 0 0 0 0 Bus15 -2.186 -1.457 3446.0 83.2

Bus17 2.186 1.457 3446.0 83.2


Bus17 0.480 89.316 -5.2 0 0 0 0 Bus16 -2.142 -1.400 3446.0 83.7

Bus1 2.142 1.400 3446.0 83.7

Bus18 0.480 89.130 -5.2 0 0 0 0 Bus3 -0.063 -0.041 101.0 83.7

Bus44 0.063 0.041 101.0 83.7

Bus19 0.240 85.483 -6.4 0 0 0.045 0.028 Bus36 -0.045 -0.028 147.8 85.0

Bus20 0.240 87.632 -5.6 0 0 0.011 0.007 Bus37 -0.011 -0.007 36.2 85.0
Bus21 0.240 87.079 -5.9 0 0 0.041 0.026 Bus37 -0.041 -0.026 133.9 85.0

Bus22 0.240 85.368 -7.1 0 0 0.107 0.066 Bus36 -0.107 -0.066 354.6 85.0
Bus23 0.240 85.179 -6.1 0 0 0.042 0.026 Bus38 -0.042 -0.026 140.5 85.0

Bus24 0.240 86.327 -6.7 0 0 0.209 0.130 Bus39 -0.209 -0.130 685.7 85.0
Bus25 0.240 86.958 -6.3 0 0 0.142 0.088 Bus39 -0.142 -0.088 461.9 85.0

Bus26 0.240 85.266 -6.4 0 0 0.056 0.035 Bus40 -0.056 -0.035 187.0 85.0

Bus27 0.240 85.344 -6.4 0 0 0.072 0.045 Bus40 -0.072 -0.045 238.9 85.0

Bus28 0.240 87.154 -6.3 0 0 0.106 0.066 Bus42 -0.106 -0.066 345.0 85.0

Bus29 0.240 82.885 -7.4 0 0 0.081 0.050 Bus43 -0.081 -0.050 278.2 85.0

Bus30 0.240 81.656 -8.3 0 0 0.136 0.085 Bus43 -0.136 -0.085 472.6 85.0
Bus31 0.240 80.493 -9.1 0 0 0.186 0.115 Bus43 -0.186 -0.115 654.1 85.0 61 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 9
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Bus Voltage Generation Load Load Flow XFMR


ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

Bus32 0.240 85.650 -6.6 0 0 0.061 0.038 Bus44 -0.061 -0.038 202.1 85.0
Bus36 0.480 88.326 -5.4 0 0 0.014 0.009 Bus3 -0.221 -0.143 358.4 83.9

Bus22 0.109 0.072 177.3 83.4


Bus19 0.046 0.029 73.9 84.1

Bus37 0.053 0.033 85.1 84.6


Bus37 0.480 88.326 -5.4 0 0 0 0 Bus21 0.042 0.026 67.0 84.6

Bus20 0.011 0.007 18.1 84.8


Bus36 -0.053 -0.033 85.1 84.6

Bus38 0.480 87.881 -5.2 0 0 0.147 0.091 Bus3 -0.191 -0.119 307.7 84.8
Bus23 0.043 0.028 70.2 84.1

Bus39 0.480 88.244 -5.4 0 0 0.006 0.003 Bus3 -0.359 -0.232 582.7 84.0
Bus24 0.211 0.137 342.9 83.8

Bus25 0.143 0.091 230.9 84.2


Bus40 0.480 87.329 -5.2 0 0 0 0 Bus3 -0.130 -0.084 213.0 83.9

Bus27 0.073 0.047 119.5 83.9


Bus26 0.057 0.037 93.5 83.9

Bus41 0.480 87.991 -5.5 0 0 0.451 0.279 Bus3 -0.451 -0.279 724.9 85.0
Bus42 0.480 88.758 -5.2 0 0 0.004 0.003 Bus3 -0.111 -0.072 179.3 84.0

Bus28 0.107 0.069 172.5 84.0


Bus43 0.480 84.611 -6.2 0 0 0.086 0.053 Bus3 -0.496 -0.330 846.3 83.2

Bus29 0.082 0.053 139.1 83.9


Bus30 0.138 0.093 236.3 83.1

Bus31 0.189 0.131 327.1 82.3


Bus44 0.240 87.868 -6.1 0 0 0 0 Bus32 0.062 0.039 202.1 84.5

Bus18 -0.062 -0.039 202.1 84.5


Bus45 0.480 88.584 -5.4 0 0 0 0 Bus3 -0.083 -0.052 133.1 84.5

Bus46 0.083 0.052 133.1 84.5


Bus46 0.240 87.845 -5.9 0 0 0.083 0.051 Bus45 -0.083 -0.051 266.3 85.0

* Indicates a voltage regulated bus (voltage controlled or swing type machine connected to it)
# Indicates a bus with a load mismatch of more than 0.1 MVA

62 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 10
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Bus Loading Summary Report

Directly Connected Load Total Bus Load

Bus Constant kVA Constant Z Constant I Generic


Percent
ID kV Rated Amp MW Mvar MW Mvar MW Mvar MW Mvar MVA % PF Amp Loading

Bus1 0.480 0 0 0 0 0 0 0 0 2.559 83.7 3446.0


Bus2 0.480 0 0 0 0 0 0 0 0 0 0.0 0.0

Bus3 0.480 0 0 0 0 0 0 0 0 2.559 83.7 3446.0


Bus14 34.500 0 0 0 0 0 0 0 0 2.865 78.4 47.9

Bus15 0.480 0 0 0 0 0 0 0 0 2.658 83.0 3446.0


Bus16 0.480 0 0 0 0 0 0 0 0 2.627 83.2 3446.0

Bus17 0.480 0 0 0 0 0 0 0 0 2.559 83.7 3446.0


Bus18 0.480 0 0 0 0 0 0 0 0 0.075 83.7 101.0

Bus19 0.240 0.036 0.022 0.009 0.005 0 0 0 0 0.053 85.0 147.8


Bus20 0.240 0.009 0.006 0.002 0.001 0 0 0 0 0.013 85.0 36.2

Bus21 0.240 0.033 0.020 0.008 0.005 0 0 0 0 0.048 85.0 133.9


Bus22 0.240 0.086 0.053 0.021 0.013 0 0 0 0 0.126 85.0 354.6

Bus23 0.240 0.034 0.021 0.008 0.005 0 0 0 0 0.050 85.0 140.5


Bus24 0.240 0.140 0.087 0.069 0.043 0 0 0 0 0.246 85.0 685.7

Bus25 0.240 0.094 0.058 0.048 0.029 0 0 0 0 0.167 85.0 461.9


Bus26 0.240 0.038 0.024 0.018 0.011 0 0 0 0 0.066 85.0 187.0

Bus27 0.240 0.049 0.030 0.024 0.015 0 0 0 0 0.085 85.0 238.9


Bus28 0.240 0.085 0.053 0.021 0.013 0 0 0 0 0.125 85.0 345.0

Bus29 0.240 0.066 0.041 0.015 0.009 0 0 0 0 0.096 85.0 278.2


Bus30 0.240 0.112 0.069 0.025 0.015 0 0 0 0 0.160 85.0 472.6

Bus31 0.240 0.153 0.095 0.033 0.020 0 0 0 0 0.219 85.0 654.1


Bus32 0.240 0.052 0.032 0.009 0.006 0 0 0 0 0.072 85.0 202.1

Bus36 0.480 0.011 0.007 0.003 0.002 0 0 0 0 0.263 83.9 358.4


Bus37 0.480 0 0 0 0 0 0 0 0 0.062 84.6 85.1

Bus38 0.480 0.117 0.073 0.030 0.019 0 0 0 0 0.225 84.8 307.7


Bus39 0.480 0.004 0.002 0.002 0.001 0 0 0 0 0.428 84.0 582.7

Bus40 0.480 0 0 0 0 0 0 0 0 0.155 83.9 213.0


Bus41 0.480 0.358 0.222 0.092 0.057 0 0 0 0 0.530 85.0 724.9

Bus42 0.480 0.003 0.002 0.001 0.001 0 0 0 0 0.132 84.0 179.3


Bus43 0.480 0.069 0.043 0.017 0.010 0 0 0 0 0.595 83.2 846.3

Bus44 0.240 0 0 0 0 0 0 0 0 0.074 84.5 202.1


Bus45 0.480 0 0 0 0 0 0 0 0 0.098 84.5 133.1

Bus46 0.240 0.055 0.034 0.028 0.017 0 0 0 0 0.097 85.0 266.3

63 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 11
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

* Indicates operating load of a bus exceeds the bus critical limit ( 100.0% of the Continuous Ampere rating).

# Indicates operating load of a bus exceeds the bus marginal limit ( 95.0% of the Continuous Ampere rating).

64 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 12
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Branch Loading Summary Report

Transformer
CKT / Branch Cable & Reactor
Ampacity Loading Capability Loading (input) Loading (output)
(Amp) Amp (MVA)
ID Type % MVA % MVA %

* C2 Cable 3145.97 3445.99 109.54

C3 Cable 786.49 358.38 45.57

C4 Cable 504.29 307.73 61.02

C5 Cable 1179.74 582.74 49.40

C6 Cable 252.15 212.96 84.46

C7 Cable 1179.74 724.88 61.44

C8 Cable 756.44 179.32 23.71

* C9 Cable 393.25 846.30 215.21

C10 Cable 1179.74 101.04 8.56

C11 Cable 393.25 202.09 51.39

C12 Cable 393.25 133.13 33.85

* T1 Transformer 2.000 2.865 143.2 2.658 132.9

T2 Transformer 0.150 0.130 86.8 0.126 83.9

T3 Transformer 0.100 0.049 49.2 0.048 48.5

T4 Transformer 0.050 0.013 26.6 0.013 26.4

* T5 Transformer 0.050 0.054 108.5 0.053 105.0

T6 Transformer 0.050 0.051 102.6 0.050 99.5

T7 Transformer 0.500 0.252 50.3 0.246 49.2

T8 Transformer 0.500 0.169 33.9 0.167 33.4

T9 Transformer 0.150 0.087 57.8 0.085 56.5

T10 Transformer 0.113 0.068 60.1 0.066 58.7

T11 Transformer 0.300 0.127 42.4 0.125 41.7

T12 Transformer 0.225 0.098 43.5 0.096 42.6

T13 Transformer 0.225 0.166 73.9 0.160 71.3

T14 Transformer 0.225 0.230 102.3 0.219 97.3

T15 Transformer 0.225 0.075 33.3 0.074 32.8

T16 Transformer 0.500 0.098 19.6 0.097 19.4

* Indicates a branch with operating load exceeding the branch capability.

65 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 13
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Branch Losses Summary Report

Vd
CKT / Branch From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop
ID MW Mvar MW Mvar kW kvar From To in Vmag

C3 0.223 0.146 -0.221 -0.143 1.9 2.5 89.3 88.3 0.99

C4 0.194 0.121 -0.191 -0.119 3.0 2.1 89.3 87.9 1.43

C5 0.362 0.237 -0.359 -0.232 3.3 4.4 89.3 88.2 1.07

C6 0.133 0.086 -0.130 -0.084 2.9 2.0 89.3 87.3 1.99

C7 0.456 0.286 -0.451 -0.279 5.2 6.8 89.3 88.0 1.32

C8 0.112 0.072 -0.111 -0.072 0.7 0.5 89.3 88.8 0.56

C9 0.517 0.358 -0.496 -0.330 21.1 27.8 89.3 84.6 4.70

C10 0.063 0.041 -0.063 -0.041 0.1 0.1 89.3 89.1 0.19

C12 0.083 0.053 -0.083 -0.052 0.5 0.7 89.3 88.6 0.73

T1 2.247 1.777 -2.205 -1.483 41.5 294.6 100.0 92.8 7.24

C1 2.205 1.483 -2.186 -1.457 19.5 25.6 92.8 91.7 1.06

C2 2.186 1.457 -2.142 -1.400 43.8 57.6 91.7 89.3 2.38

T15 0.063 0.041 -0.062 -0.039 0.3 1.5 89.1 87.9 1.26

T5 -0.045 -0.028 0.046 0.029 1.0 1.7 85.5 88.3 2.84

T4 -0.011 -0.007 0.011 0.007 0.1 0.1 87.6 88.3 0.69

T3 -0.041 -0.026 0.042 0.026 0.4 0.7 87.1 88.3 1.25

T2 -0.107 -0.066 0.109 0.072 1.6 5.6 85.4 88.3 2.96

T6 -0.042 -0.026 0.043 0.028 0.9 1.5 85.2 87.9 2.70

T7 -0.209 -0.130 0.211 0.137 1.6 7.6 86.3 88.2 1.92

T8 -0.142 -0.088 0.143 0.091 0.7 3.5 87.0 88.2 1.29

T10 -0.056 -0.035 0.057 0.037 0.6 2.1 85.3 87.3 2.06

T9 -0.072 -0.045 0.073 0.047 0.7 2.5 85.3 87.3 1.98

T11 -0.106 -0.066 0.107 0.069 0.7 3.2 87.2 88.8 1.60

T12 -0.081 -0.050 0.082 0.053 0.6 2.8 82.9 84.6 1.73

T13 -0.136 -0.085 0.138 0.093 1.7 8.1 81.7 84.6 2.95

T14 -0.186 -0.115 0.189 0.131 3.3 15.4 80.5 84.6 4.12

C11 -0.061 -0.038 0.062 0.039 1.2 1.6 85.7 87.9 2.22

T16 0.083 0.052 -0.083 -0.051 0.2 1.2 88.6 87.8 0.74

159.3 483.5

66 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 14
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Alert Summary Report

% Alert Settings
Critical Marginal
Loading
Bus 100.0 95.0
Cable 100.0 95.0
Reactor 100.0 95.0
Line 100.0 95.0
Transformer 100.0 95.0
Panel 100.0 95.0
Protective Device 100.0 95.0
Generator 100.0 95.0
Inverter/Charger 100.0 95.0

Bus Voltage
OverVoltage 105.0 102.0
UnderVoltage 95.0 98.0

Generator Excitation
OverExcited (Q Max.) 100.0 95.0
UnderExcited (Q Min.) 100.0

Critical Report

Device ID Type Condition Rating/Limit Unit Operating % Operating Phase Type

Bus1 Bus Under Voltage 0.48 kV 0.43 89.3 3-Phase

Bus15 Bus Under Voltage 0.48 kV 0.45 92.8 3-Phase

Bus16 Bus Under Voltage 0.48 kV 0.44 91.7 3-Phase

Bus17 Bus Under Voltage 0.48 kV 0.43 89.3 3-Phase

Bus18 Bus Under Voltage 0.48 kV 0.43 89.1 3-Phase

Bus19 Bus Under Voltage 0.24 kV 0.21 85.5 3-Phase

Bus2 Bus Under Voltage 0.48 kV 0.43 89.3 3-Phase

Bus20 Bus Under Voltage 0.24 kV 0.21 87.6 3-Phase

Bus21 Bus Under Voltage 0.24 kV 0.21 87.1 3-Phase

Bus22 Bus Under Voltage 0.24 kV 0.20 85.4 3-Phase

Bus23 Bus Under Voltage 0.24 kV 0.20 85.2 3-Phase

Bus24 Bus Under Voltage 0.24 kV 0.21 86.3 3-Phase

Bus25 Bus Under Voltage 0.24 kV 0.21 87.0 3-Phase

Bus26 Bus Under Voltage 0.24 kV 0.20 85.3 3-Phase

Bus27 Bus Under Voltage 0.24 kV 0.20 85.3 3-Phase 67 | P a g e


ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 15
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

Critical Report

Device ID Type Condition Rating/Limit Unit Operating % Operating Phase Type

Bus28 Bus Under Voltage 0.24 kV 0.21 87.2 3-Phase

Bus29 Bus Under Voltage 0.24 kV 0.20 82.9 3-Phase

Bus3 Bus Under Voltage 0.48 kV 0.43 89.3 3-Phase

Bus30 Bus Under Voltage 0.24 kV 0.20 81.7 3-Phase

Bus31 Bus Under Voltage 0.24 kV 0.19 80.5 3-Phase

Bus32 Bus Under Voltage 0.24 kV 0.21 85.7 3-Phase

Bus36 Bus Under Voltage 0.48 kV 0.42 88.3 3-Phase

Bus37 Bus Under Voltage 0.48 kV 0.42 88.3 3-Phase

Bus38 Bus Under Voltage 0.48 kV 0.42 87.9 3-Phase

Bus39 Bus Under Voltage 0.48 kV 0.42 88.2 3-Phase

Bus40 Bus Under Voltage 0.48 kV 0.42 87.3 3-Phase

Bus41 Bus Under Voltage 0.48 kV 0.42 88.0 3-Phase

Bus42 Bus Under Voltage 0.48 kV 0.43 88.8 3-Phase

Bus43 Bus Under Voltage 0.48 kV 0.41 84.6 3-Phase

Bus44 Bus Under Voltage 0.24 kV 0.21 87.9 3-Phase

Bus45 Bus Under Voltage 0.48 kV 0.43 88.6 3-Phase

Bus46 Bus Under Voltage 0.24 kV 0.21 87.8 3-Phase

C2 Cable Overload 3,145.97 Amp 3,445.99 109.5 3-Phase

C9 Cable Overload 393.25 Amp 846.30 215.2 3-Phase

CB20 LV CB Overload 600.00 Amp 724.88 120.8 3-Phase

CB22 LV CB Overload 800.00 Amp 846.30 105.8 3-Phase

CB23 LV CB Overload 150.00 Amp 177.31 118.2 3-Phase

CB45 LV CB Overload 400.00 Amp 508.19 127.0 3-Phase

CB48 LV CB Overload 300.00 Amp 327.07 109.0 3-Phase

CB5 LV CB Overload 3,200.00 Amp 3,445.99 107.7 3-Phase

CB51 LV CB Overload 125.00 Amp 143.95 115.2 3-Phase

T1 Transformer Overload 2.00 MVA 2.66 132.9 3-Phase

T5 Transformer Overload 0.05 MVA 0.05 105.0 3-Phase

Marginal Report

Device ID Type Condition Rating/Limit Unit Operating % Operating Phase Type

CB44 LV CB Overload 225.00 Amp 216.69 96.3 3-Phase

T14 Transformer Overload 0.23 MVA 0.22 97.3 3-Phase

T6 Transformer Overload 0.05 MVA 0.05 99.5 3-Phase

68 | P a g e
ETAP
Project: Ginebra Cabuyao Plant 14.1.0C Page: 16
Location: Canlubang, Laguna Date: 02-14-2019
Contract: OTI-10125191514 SN: 312114912121
Engineer: JRC Study Case: Load Flow Revision: Base
Filename: ginebra_analysisv2 Config.: Normal

In compliance with Philippine Electrical Code-2017, Article 1.3.2.1 (f)

SUMMARY OF TOTAL GENERATION , LOADING & DEMAND

MW Mvar MVA % PF

Source (Swing Buses): 2.247 1.777 2.865 78.43 Lagging

Source (Non-Swing Buses): 0.000 0.000 0.000

Total Demand: 2.247 1.777 2.865 78.43 Lagging

Total Motor Load: 1.603 0.994 1.886 85.00 Lagging

Total Static Load: 0.484 0.300 0.570 85.00 Lagging

Total Constant I Load: 0.000 0.000 0.000

Total Generic Load: 0.000 0.000 0.000

Apparent Losses: 0.159 0.484

System Mismatch: 0.000 0.000

Number of Iterations: 1