TYPE-1

Total nos. of Segments: 556


Segmental width 2.5 mtr., Segmental length=18 mtr., Segmental Height=3.80mtr.
CYCLE TIME – SEGMENT PRECASTING

 Soffit Align and fix outside shutter panel 0.5 days


 Positioning re-bar cage & fixing cable Ducts, guide cone,
bursting bar, 1.0 days
 Checking and inspection 0.5 days
 Fixing end forms, Inside shutter & Inspection 1.0 days
 Concreting 0.5 days
 Curing in bed (Till 25 N/mm2 strength) 2.5 days
 Removal from bed 0.5 days
Total 6.5 days

TYPE-2
Total nos. of Segments: 824 Nos.
Segmental width=2.5m, Segmental Length=11.0m, Segmental Height=2.5m
CYCLE TIME – SEGMENT PRECASTING

 Align and fix outside shutter panel Positioning re-bar cage 1.0 days
 fixing cable Ducts Checking and inspection, guide cone,
bursting rebar 1.0 days
 Fixing end forms, Inside shutter & Inspection 0.5 days
 Concreting 0.5 days
 Curing in bed (Till 25 N/mm2 strength) 2.5 days
 Removal from bed 0.5 days
Total 6 days

Note: (1) Outer shutter panel moved to next segment after concrete in segments
attains 10N/mm2 (Approx 1.5 days after concreting)
(2) Inside shutter panel moved to next segment (Approx 2.5 days after
concreting)