Work Method Statement Project Prepared by Location
Work Method Statement Project Prepared by Location
PROJECT PREPARED BY
LOCATION
ALL WORKERS INVOLVED IN THE WORKS MUST HAVE THE WORK METHOD STATEMENT EXPLAINED AND COMMUNICATED TO THEM PRIOR TO
THE START OF WORKS.
Page 1 of 3
Details description of works
3. Shut off isolation valves and 3.1 Shut off all isolation valves. (Qty: ??)
drain water from the pipe line. 3.2 Drain off the water at the lower ground area.
3.3 Drain off the water to the temporary water tanks and subsequently to the drainage system.
4. Dismantle and removed 4.1 Secure the flow meter by mean of lifting belt & chain block.
existing flow meter. 4.2 Remove and secure the power/signal cable of the existing flowmeter.
4.3 Dismantle all bolts/nuts.
4.4 Removed and lower down the existing flow meter to the ground.
4.5 Removed the existing gaskets & residual from the pipe flange.
5. Install new flow meter with 5.1 Lift the new flow meter using lifting belt & chain block.
new sets of bolts/nuts and 5.2 Install the new flow meter into location.
gaskets. 5.3 Insert new gaskets for both flange end.
5.4 Install with new set of bolts/nuts.
5.5 Confirm bolts/nuts tightness by hammer & ring spanner.
6. Line pressure test by opening 6.1 Fill up the water & vent out the air.
Isolation valves. 6.2 Open the isolation valves slowly.
6.3 Conduct line pressure test and check for tightness.
DAY 3
7. Install new PU injection 7.1 Install new metal sheet lining. (spec, 0.4mm Aluminium)
insulation and metal sheet 7.2 Install new insulation by mean of PU injection.
8. Completion & Hand Over 8.1 Conduct joint inspection for completion and hand over.