Professional Documents
Culture Documents
CORRIDOR
PUNE-MUMBAI-AHMEDABAD Pre-Feasibility Study
Final Report
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
2
PUNE-MUMBAI-AHMEDABAD
High Speed Rail
• States: Maharashtra/ Dadra- Nagar- Haveli (UT)/ Gujarat
• Length: Approx 640km double track.
• Maharashtra – 328 km
• Dadra – Nagar – Haveli(UT) – 5.5 km
• Gujarat – 306.5 km
• Earthworks: 549 km
• Rail Structures: 72 km
• Road Over Bridges: 130 in no,
• Tunnels: 19.085km
• Earthworks Materials: 76 millions cu.m
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
6
PUNE-MUMBAI-AHMEDABAD
High Speed Rail- Main features
• Tunnel between Lonavla and Karjat – 18.3 km
• Mumbai HSR Trans Harbour Link bridge – 17.2 km
• 3 main Terminal stations in Mumbai, Pune and
Ahmedabad
• 3 main intermediate stations in Navi Mumbai, Airport,
Surat and Vadodara
• 2 depots: Main depot Geratpur (Ahmedabad) / Auxiliary
Depot (Pune)
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
7
2. CRITERIA
• Minimum horizontal radius 6425m
• Maximum gradient 35mm/m
• Minimization of the height of embankment
• Intermediate stations in suburbs of the cities to avoid costly works
to reach city centres which do not provide sufficient traffic.
• Viaducts in urban areas.
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
8
Possible Alignments
ITEM MUMBAI-PUNE SECTION MUMBAI OUTER AREA MUMBAI AHMEDABAD SECTION
Total length in kilometres 86.5 83.6 413
No. of tunnels 1 1 -
Length of tunnels 18.7 1.3 -
Viaducts 1(35m deep) 7 -
length of viaducts 1.5 3.4 -
Relocation of houses/properties(km
along alignment) 10 1.25 6
radius of sharpest curve(m) 6425 6425 5000
Speed restriction no speed restriction at 1 place at 1 place
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
10
Proposed
Perception
Transport Study of City
Network Development
authority
Availability
of optimum
land area
Land
Matrix struct
ownership
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
11
TRAFFIC FORECAST
CONCEPT DESIGN
• Signalling
ETCS-european train
Control system
Level 2 with GSMR
• Telecommunications
GSMR- global system for mobile communication-railways
• Power Supply
2 x 25 KV PS- 8 sub stations
• OCS 2 X 25 KV
• Either French, German / Chinese
technology
• Each arrangement consists of a
Messenger, Contact Wire, Negative
feeder, Aerial Earth Conductor and a 25000V Sub-Station
Droppler Cable.
• Maximum span- 63m
• Contact wire height-5.08m
• Catenary encumbrance-1.4m
• Maximum tension height-1400m
• Sub- station at every 50 to 70km
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
24
ROLLING STOCK
• 1676mm gauge Rolling Stock.
• 3300mm car body
• EMU
• Fleet size- 38 train sets in 2021
• Investment costs- Rs 6783 crores
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
25
INFRASTRUCTURE MAINTENANCE
• Maintenance head office in Navi Mumbai
• 7 maintenance bases
• 3 main track operational units
• 2 main signalling/ Telecom/ OCS/ PS Units
• Approximately 330-340 number staff
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
26
Systems 12327
Depots 523
Project management/Risks 8092
Total 49075 Cr
• Operation Costs
• Rs. 205 Cr. In year 2021
• Maintenance Costs
• Rolling Stock – Rs. 145 Cr., in year 2021
• Infrastructure – Rs. 254 Cr., in year 2021
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
28
Fare Evolution
• 4% /year + 5% every 5 years (over and above)
FINANCIAL ANALYSIS
OPTION 2
Unbundling the project into different components so as to attract
private players from the perspective of affordability in terms of
size and risk allocation.
A. Build & Transfer (B&T) of Civil Works (Earthwork,
Tunnel, Bridges, fence, etc.)
B. Design, Finance, Operate and Transfer(DFOT) of
systems, stations, trains and depots
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
31
ROAD-HSR COMPARISON
BASIS ROADS vs HIGH SPEED RAIL
Government Funding Viability gap funding, normally upto 40% of the total
project cost is provided to the PPP road projects.
Whereas, the high speed rail project under discussion
requires a VGF of only 17% of the total project cost.
Environmental Impact High speed rail has the potential to be the lowest
energy consumer and greenhouse gas emitter.
Rail services, including slower regional trains,
produce on average
• 5 times less carbon than comparable car journeys
• 4 times less than short haul air travel
• 3 times less than long haul air travel.
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
32
ENVIRONMENTAL EXAMINATION
• Afforestation will be done for compensation of loss of bio
mass and to develop a buffer zone as noise barrier.
• Mitigation measures for mitigation of noise and vibration
during operation requires Engineering consideration
during design.
• Rehabilitation and Re-settlements of project affected
families.
• Estimated Environmental cost : Rs.270 crores.
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
34
CARBON FOOTPRINT
The construction of a high speed line:
• Generates CO2 emissions depending on the context
(construction and conception of the line).
• Also avoids some CO2 emissions thanks to modal
transfer of passengers from more polluting transport
modes.
• The carbon footprint would be defined as the total set of
Green house gases(GHG) emissions a high speed line
would emit during its life cycle(conception, construction,
operation and rolling stock).
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
35
IMPLEMENTATION SCHEDULE(Integrated)
Pune-Mumbai-Ahmedabad HSR Pre- Feasibility Study
Final Report
36
CONCLUSION
• The HSR line between Pune-Mumbai-Ahmedabad can
stop the decline of the railway on the long distance
transport segment along this corridor.
• It provides an attractive transport offer in terms of
reduced travel times and connectivity with the existing
networks
• Despite the high investment cost, it is financially and
economically sustainable.