Professional Documents
Culture Documents
SEP-OPE-OBNG1-SC03-00018
SCOPE OF WORK
JULY 2019
Revision Philosophy
All draft documents for review will be issued at R01, with subsequent R02, R03, etc. as required.
All revisions approved for issue / implementation will be issued at A01, with subsequent A02, A03, etc. as
required.
All revisions approved for design will be issued at D01, with subsequent D02, D03, etc. as required.
Documents approved for Construction will be issued at C01, C02, and C03 respectively.
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc.
Narrative sections revised from previous approved issues are to be noted in the table below and/or highlighted
in the RH margin (using the appropriate revision status) thus: | A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas and
using a triangle containing the revision status.
Revision History
TABLE OF CONTENTS
7.3 Provision of Instrument Air supply line to the New Gas driven Generator. ................................................. 11
7.6 Provision of Flare Line, Manual Depressurization Line and Blow Down Line. .............................................. 13
1.0 INTRODUCTION
SEPLAT Petroleum Development Company presently operates OML 4, 38 & 41 in the Western Assets besides
other OMLs being operated in the Eastern Asset. SEPLAT’s plan is to aggressively develop the fields in the Land
and Swamp areas available in the above listed OMLs.
Oben Power Plant has three (3) gas gensets installed each rated 600 kVA/480 kW; two genset usually run on
duty while one unit on standby to meet the power requirements.
Gas genset, G3, installed during Oben Gas Plant Extension (OGPE) project is highly sensitive to fuel gas quality
compared with the older units, G1 and G2, installed during West African Gas Pipeline (WAGP) project
execution.
To improve overall power availability and eliminate issues associated with Gas genset G3, a new 1.2MVA gas
driven generator with all the necessary accessories shall be installed alongside existing Gas genset G1 and G2 to
cater for entire plant load and new FLB facility. A full detail of CONTRACTOR’s scope of work is as detailed
below.
2.0 OBJECTIVE
The purpose of this document is to define the scope of work for the decommissioning of Gas gen set G3, an
existing 600KVA generator in Oben gas plant and to replace it with a new 1.2MVA gas driven generator. This
scope shall also cover the installation of a 750kVA step-up transformer to supply the new FLB facility. This is to
cater for load requirement of the new FLB and to improve general reliability of power infrastructure in Oben
gas plant. The decommissioning, installation and commissioning activities will involve Electrical, Civil,
Mechanical, Process, Instrumentation and Piping
This scope also covers all necessary material sourcing, installation, testing, delivery, handling, required to hook-
up the Gas generator to the existing 4000A switchgear.
This document is not an exhaustive description of the works to be performed. Contractor shall provide all
necessary documents, procedures, labor, equipment etc. in order to undertake, finalize and commission the
installation.
Installation works shall comply with all relevant international codes and standards applicable.
In addition, the Electrical CONTRACTOR shall be required to carry out the following activities:
a) Isolation of the existing 600KVA generator incomers breakers on the 4000A switchgear prior to
commencement of work.
b) Disconnection, excavation and removal of existing generator feeder cables and auxiliary cable to the
existing 600KVA generator Gas genset G3.
c) Disconnection of earthing cable connections to the existing generator including equipotential bonding
conductors.
d) Laying of the new feeder cable 3(3 X 1C X 630 sq.mm) + 1C X 630 sq.mm to the new generator. Cable
testing and termination at both ends including installation of control cables and earthing cables.
e) Laying of new feeder cable 3(2 X 1C X 630 sq.mm) + 1C X 630 sq.mm from the 4000A LV switchgear to
750kVA step-up transformer. Cable testing and termination at both ends including installation of earthing
cables.
f) Pre-commissioning and commissioning of the entire electrical installation.
a) 3(3 X 1C x 630sq.mm) + 1C X 630 sq.mm armored cable (PVC/SWA/XLPE/Cu) and all required accessories
(glands, lugs, sleeves) etc. quantities are as detailed in electrical bulk MTO connection between the existing
4000A switchgear located in the Electrical room and 750KVA step-up transformer. CONTRACTOR shall
install and terminate this cable at both ends in line with Seplat specifications. (Reference drawing nos. A-
005-L07-00001-001 OBEN Key Single Line Diagram).
b) 3(2 X 1C x 630sq.mm) + 1C X 630 sq.mm armored cable (PVC/SWA/XLPE/Cu) and all required accessories
(glands, lugs, sleeves) etc. quantities are as detailed in electrical bulk MTO connection between the existing
4000A switchgear located in the Electrical room and the new 1.2MVA Gas Generator. CONTRACTOR shall
install and terminate this cable at both ends in line with Seplat specifications. (Reference drawing nos. A-
005-L07-00001-001 OBEN Key Single Line Diagram).
c) 7C x 2.5sq.mm armored cable (PVC/SWA/XLPE/Cu) and all required accessories (glands, lugs, sleeves) etc.
quantities are as detailed in electrical bulk MTO between the new 1.2MVA Gas generator and the existing
4000A switchgear for the auxiliary control circuit interconnections.
➢ CONTRACTOR to note that cable joints shall not be permitted except where the route length exceeds
commercially available cable drum lengths. Also, no Teed cable joints shall be used,
Equipotential bonding of both generator and step-up transformer shall be carried out using 2(1C x
70 sq.mm) G/Y PVC earthing conductor.
Earthing pit and Neutral earthing resistor connection must comply with the requirement of the
new generator and must conform to the minimum recommended earth resistance for combined
system or single earth pits value of less than 4 Ohms.
• Generator and Transformer Test: An acceptance test shall be done prior to delivery to site
and after installation has been concluded.
• Cable Test: This test shall be done prior to permanent termination of cables in line with
International Standards and Industry best practices.
• Earth Test: The earthing system shall be tested to conform to Seplat approved electrode
resistance values. The earth resistance of the combined system or single earth pit shall not be
greater than 4 Ohms.
Upon completion of all required electrical installations, CONTRACTOR shall ensure full
commissioning of the entire electrical system before handover to Seplat.
All CONTRACTORS must carry out site Familiarization / Pre-bid site visits in which all questions pertaining to
any phase of the contract and project at large will be attended to by the accompanying SEPLAT
representative.
As the structure is containerized, the need for maintenance structures including Gantries and laydown
areas are to be to the discretion of the equipment end users and subject to space requirements within the
site.
The dimensions of the foundation are subject to space availability within the site.
2. The CONTRACTOR is responsible for providing access to the Equipment and is responsible for
carting away demolition spoil to a site approved by SEPLAT.
3. The CONTRACTOR must provide a report on the redesign of the supports to relocated elements,
and the design of the new supports and foundations as required.
4. The CONTRACTOR must carry out a site familiarization visit to identify challenges to the execution
of the works, and to understand the site peculiarities including potential hazards and working space
requirements.
5. The CONTRACTOR must allow for the provision of a temporary access road to the existing and
proposed relocation location. If need be, carry out the design of earthworks to facilitate equipment
movement. The CONTRACTOR must allow for the demolition and carting away of minor structures
which would enable access, lifting and repositioning of any structures marked for demolition and
relocation.
2. The CONTRACTOR is to remove the topsoil within the site, blinding the intended area with weak
concrete, bending reinforcement and casting Grade 30 concrete to the Engineers specification.
3. The CONTRACTOR handles carrying out tests on the concrete including the slump test and concrete
cube crushing test.
4. The CONTRACTOR is responsible for the earthworks and other enabling works required for the
installation of the foundation.
5. The CONTRACTOR must ensure that the critical stages of the project including the casting of
concrete, laying of reinforcement and site cleanup should be checked and approved by a SEPLAT
QA/QC representative.
6. Relevant site material tests must adhere to SEPLAT QA/ QC standards and must be submitted for
approval by SEPLAT.
NOTE:
1. Any damage resulting from the installation must be communicated with SEPLAT and would be
at the cost of the CONTRACTOR.
2. Any auxiliary works shall be communicated to, and approved by, a SEPLAT representative.
A section of the existing 2’’x 150# Carbon Steel fuel gas supply line from the secondary fuel gas system to
Oben NAG Booster Compressor shall be demolished.
Existing Fuel Gas Supply Line from the Secondary Demolition/Tie-in Section for the Fuel Gas supply
Fuel Gas System to the AG Booster Compressor to the New Gas driven generator.
Tie-in:
A new 2’’x 150# Carbon Steel fuel gas line shall be connected from the demolished section of the AG
Booster Compressor fuel gas supply line and laid to the location of the New gas engine driven generator. A
shutdown valve shall be located on the line close to the new Generator. Two pressure gauges shall be
provided and located upstream and downstream of the shutdown valve.
The Flanged point on the existing 3’’x 150# Galvanized Low Temperature Carbon Steel Utility Air supply
headed located close to the Water Bath and Glycol Regeneration Unit shall be demolished.
Existing Fuel Gas Supply Line from the Secondary Existing Diesel Tank shall be relocated to allow for
Fuel Gas System to the AG Booster Compressor the installation of the New Gas Engine Generator
Tie-in:
A new 2’’x 150# Galvanized Low Temperature Carbon Steel Utility Air supply line shall be connected from
the demolished 3’’x 150# Galvanized Low Temperature Carbon Steel Flanged Utility Air supply header and
laid to the location of the New gas engine driven generator. Manual isolation valves shall be provided on
the line.
Note: The above-mentioned tie-in point for the Utility Air supply is a temporary pending the
implementation of the Instrument Air and Utility Air segregation Project, where the Utility Air supply line to
the Generator shall be tied to a new dedicated 4’’x 150# Utility Air Header.
The final tie-in point/location has been marked up on the P&ID (A-002-G04-0001-031-001) for the
Instrument Air and Utility Air segregation Project.
7.3 Provision of Instrument Air supply line to the New Gas driven Generator.
Demolition:
The Flanged point on the existing 1’’x 150# Galvanized Low Temperature Carbon Steel Instrument Air
supply headed located at the Generator shield shall be demolished.
Existing 1’’x 150# Flanged Instrument Air Header for Demolition & Tie-in
Tie-in:
A new 2’’x 150# Galvanized Low Temperature Carbon Steel Instrument supply line shall be connected from
the demolished 1’’x 150# Galvanized Low Temperature Carbon Steel Flanged Instrument Air supply header
and laid to the location of the New gas engine driven generator. Manual isolation valves shall be provided
on the lines
The end of the freshwater piping at the new gas driven Generator location, shall be provided with a
coupling for Hose connection
The new line shall be tied-in to exiting Drain header closer to the new Generator location.
7.6 Provision of Flare Line, Manual Depressurization Line and Blow Down Line.
7.6.1 Flare Line:
A 2’’x 150# Carbon Steel flare line shall be provided at the at the new gas driven Generator location. The
new line shall be tied-in to the exiting flare header closer to the new Generator location.
The line downstream of the Globe valve shall be 2’’ x 150# Low Temperature Carbon Steel material. It shall
be tied-in to the new flare header to be located close to the new Generator.
1. Install main field instruments; Shutdown Valve (70-ESD-002), Blowdown valve (70-BDV-001), Pressure
gauges (70-PG-OO1 & 002), and Emergency Push bottom (70-HS-00) with their complete accessories as
per the attached datasheets. Ensure, the new instruments are calibrated and tested before installation
and Hook up.
2. Install and hook up materials such as cable trays, cables and cable accessories; tubing and fittings as per
attached bill of materials. Wire up the instruments to a junction box (JB) and from the JB to the Input /
Output modules of the (SGS AND PCS) CHARMS Panels.
3. Installation of all field instrument devices (ESDV, BDV, PG, and Manual call point), junction boxes and
supports shall be carried out by the contractor according to standard procedures under the supervision
of Seplat Representative.
4. Carryout hot and cold loop test and properly document them.
5. Procure Instrument cables, install/lay same along existing route to identify field junction box and ensure
correct termination as per approved termination drawings/sketch. Tie-in and configuration of all input
signals into Delta V, F&G control panel in the control room via field marshalling (This job shall be carried out
by AOS Orwell).
6. Inspection checks/Test of all instruments and signal cables prior to installation is very important.
7. Liaise with Electrical team for the implementation of generators status indication on main control system.
8. Also, review other requirements with Electrical team to verify all considerably standard monitoring systems
for tie-in into control systems.
9. All internal wiring in the CHARMS panel shall be done by the contractor under the supervision of AOS
DCS expert.
10. The DCS expert shall be involved in the programming and configuration of the field instruments I / O
into the Delta–V DCS system and the workstation.
11. Tubing runs shall also be connected to the instruments accordingly as per the hook up drawing. ½” tubing
may be required to provide air supply from the nearest source to the instruments (shutdown valves and
blowdown valves). Impulse line shall be connected from the piping via double block and bleed valve to the
pressure instrument mounted on an instrument stand.
12. The contractor shall be ready to carry out any other instrumentation works not mentioned here but
necessary for the delivery of this project.
UNIT TOTAL
RATE RATE
S/No Material Description Quantity ($) ($)
1 FIELD INSTRUMENTS
2” x 150# Actuated Shutdown Valve (as per data
1.1 sheet. Tag: 70-ESDV-002)---Fuel Gas ESDV 1
2” x 150# Actuated Blowdown Valve (as per data
1.2 sheet. Tag: 70-BDV-001)---Fuel Gas BDV 1
Pressure Gauge. 5" face, Liquid filled, side entry, 1/2"
1.3 NPTM (0 - 16bar) 2
1.4 Manual Call Point. ( As per datasheet attached) 1
1.5 Restriction orifice Plate (As per datasheet attached) 1
3 CABLE GLANDS
M20 Stainless Steel Compressible cable gland 25 Pcs
3.1 (Eexd)
3.2 M40 Stainless Steel (Eexd) 6 Pcs
4 JUNCTION BOX
450mm x 600mm Junction Box (Stainless Steel 1
4.1 Eex(i) or Eex(d)) with terminals numbered.
6 TUBING/FITTINGS
6.1 1/2"OD Tubing 0.065"
SEP-OPE-OBNG1-SC03-00018 5 Lengths
SoW For Installation of Gas Engine
Security Classification: Restricted Generator at Oben Gas plant.
6.2 3/8" OD Tubing 0.065" 15 Lengths
This Document is Controlled Electronically and Uncontrolled if Printed
Page15 of 18
Document No. SEP-OPE-OBNG1-SC03-00018 Rev. A01
INSTALLATION OF 1.2MVA GAS ENGINE GENERATOR
Document Title AT OBEN GAS PLANT SCOPE OF WORK Page 16 of 18
The CONTRACTOR shall have overall responsibility for the co-ordination with their sub-Contractors, and for the
proper execution of any accessory item assembly, testing, delivery and any other service defined herein.
9.1 Utilities
The new generator set will be installed adjacent to existing Power Plant (TBC) and will be integrated into
the existing facilities. The Contractor will investigate the requirements for integrating the gen set with the
existing utilities. The scope of the integration will include:
• A new 2’’x 150# carbon steel fuel gas line to the generator’s flanged inlet. Inlet gas line shall be as per
generators OEM requirements.
• A new 2’’x 150# galvanized low temperature carbon steel utility air for motor starter.
• 2’’x 150# carbon steel fresh water supply line for hose connection.
• 2’’x 150# carbon steel closed drain line to the existing header.
• 2” x 150# carbon steel flare line, manual depressurization and blow down line.
• Mechanical Layout
• Piping Isometric drawings
• Bulk MTO
• Pipe support drawings.
The new gen set will have a dedicated fuel gas system. Key components of the system shall have
redundancy. A new 2’’x 150# Carbon Steel fuel gas line shall be connected from the AG Booster Compressor
fuel gas supply line and laid to the location of the new gas engine generator.
The new gen set will be sharing instrument air system with the existing generators. Capacity of the existing
instrument air (2x 100%) is considered adequate for both the new and existing users. A new 2’’x 150#
Galvanized Low Temperature Carbon Steel Instrument supply line shall be connected from the demolished
1’’x 150# Galvanized Low Temperature Carbon Steel Flanged.
The new generator drain will be connected to the saver pit via existing open drain header. A 2’’ x 150# Blind
Flange shall be provided on the new drain line for connecting the flexible horse drain line from the
generator package. The new line shall be tied-in to exiting Drain header closer to the new Generator
location.
11.0 DOCUMENTATION
CONTRACTOR shall be required to provide the following:
• As-built piping drawings, instrumentation cable route and termination drawings and electrical drawings
both native and pdf copies (two sets each).
• All NDT and pressure test results
• Pre-commissioning and commissioning reports as necessary.
• All test results (power & control cables, earthing, generator, etc...)
• Test equipment with up-to-date calibration certificates.
12.0 ATTACHMENTS
• Electrical Bulk MTO.
• Overall Key Single Line drawing.