AMEC/OB-03/AL RUMAIS, BARKA

Date: - 11 -09-2019

To,
Dr. Sulaiman Al Harthy,
Plot 142 a , Al Rumais,
Barka,
Sultanate of Oman.

After Compliments,

Project: - Consultant Supervision for Office Building for Dr. Sulaiman Al Harthy at Al
Rumais, Barka.

Subject: - Delay in Work Progress.

Dear Sir,

It has been observed in our site visits during 16-02-2019 to 09-03- 2019, that the progress of
work on above mentioned site is extremely slow. The major works such as flooring, Electrical
cabling and fittings, fixing of Doors and windows etc, are still balance to complete the project.

The delay is occurred due to following reasons:

1. Changes of ceiling finishes from painting to gypsum work.


2. Changes of split unit Air conditions to centralized ducted Air conditions.
3. Provision of column in all the center of windows.
4. Additional interior changes.

The changes mentioned above leads to additional cost and time. We hereby request you to kindly
finalize the changes, at the earliest in order to avoid further delay in completion of this project.

This is for your kind information and necessary action please.

Thanking you and assuring our best services at all times.

Fasil S.
General Manager

For, Al Manarah Engineering Consultancy,


Muscat
AMEC/OB-02/AL RUMAIS, BARKA
Date: - 11.12.2018

To,
M/s Jawaharat Bosher Trd. & Cont.
P. O. Box:- 336, P.C. :-131
Sultanate of Oman.

Project: - Construction of Office Building at Al Rumais, Barka for Dr. Sulaiman Al Harthy.

Subject:- Approval of Concreting of Slab

Dear Sir,

This has reference to inspection of Shuttering and Reinforcement of Slab on above mentioned
work. We would like to inform you that we will issue approval letter to Municipality on
completion of following works.
1. Approval to be taken from MEDC for the Electrical Layout and load calculations.
2. Extra bars to be provided for opening as instructed to you on site.
3. Staircase opening for pent house is to be discussed and finalized with the client.
4. Chemical is to be applied to existing slab joints before concreting.
5. Reinforcement is to be fixed Dowel Chemical
6. Contractor will be held solely responsible for the crack, if any appear in joints in future.

You are advice to complete the work and inform us.

This is for your information and necessary action.

For, Al Manarah Engineering Consultancy,


Muscat

Manoj Kumar
Deputy General Manager

Copy to:- Dr. Sulaiman Al Harthy.

AMEC/OB-01/AL RUMAIS, BARKA


Date :- 25.11.2018
To,
Dr. Sulaiman Al Harthy,
Plot 142 a , Al Rumais,
Barka,
Sultanate of Oman.

After Compliments,

Project: - Supervision for Office Building at Al Rumais, Barka.

Subject:-Structural Work of Staircase

Dear Sir,

We would like to bring to your kind attention that as per design drawings, the staircase is to be
constructed to first floor by providing beam support on adjacent wall for stair flights and landing
slab.

During the inspections before the concreting of Staircase, we observed that staircase flight and
landing slab are supported by HILTI dowel chemical fix method. The Contractor informed that it
has been proposed by the designer (MA Consultant) as the staircase was not constructed from
ground floor.

We would like to inform you that in our opinion as the Supervision Consultant, staircase should
be constructed as per initial design with proper structural beam supports for flights and mid
landings for stability.
If the work is not done as mentioned above, we would regret to inform you that, we will not be in
position to take the responsibility of the structure for any settlement or failure in future.

This is for your kind information and necessary action.

Thanking you and assuring our best services at all times.

Thanking You,

For, Al Manarah Engineering Consultancy,

Muscat

Manoj Kumar .C
Deputy General Manager
AMEC/WH-01/2019
Date :- 02.01.2019

The Director,
Barka Municipality,
Sultanate of Oman

After Complements,

Project: - Construction of Proposed Warehouse Shade for Dr. Sulaiman Al Harthy on Plot
no. 02, Rumais, Barka .
Dear Sir,
We would like to inform you that the contractor M/s Mazaya National United LLC. has
completed the shuttering and reinforcement work for Footings, for above mentioned project.
We have inspected the site and found that the contractor has done all the reinforcement &
shuttering works according to the Municipality approved Drawings and Specifications.
This is for your information and necessary action.
Yours truly,
Thanking You,

For, Al Manarah Engineering Consultancy,


Muscat

Manoj Kumar .C
Deputy General Manager

AMEC/WH-02/2019
Date :- 21.01.2019

The Director,
Barka Municipality,
Sultanate of Oman

After Complements,

Project: - Construction of Proposed Warehouse Shade for Dr. Sulaiman Al Harthy on Plot
no. 02, Rumais, Barka .
Dear Sir,
We would like to inform you that the contractor M/s Mazaya National United LLC. has
completed the shuttering and reinforcement work for Plinth Beam, for above mentioned project.
We have inspected the site and found that the contractor has done all the reinforcement &
shuttering works according to the Municipality approved Drawings and Specifications.
This is for your information and necessary action.
Yours truly,
Thanking You,
For, Al Manarah Engineering Consultancy,
Muscat

Manoj Kumar
Deputy General Manager