Doc.No.

RE/HSE/PTCL/FM 362

Pressure Test Check List Date issued: 10/02/2011

Revision No. 000

Project Name: Equipment # Date:


Sr.
Items for checking Yes No N/A Remarks
No.
Appropriate permit is available for pressure test and
1
toolbox meeting conducted. Leakages if any.
Barricading and signage provided around the
2
pressurized area.
3 Subcontractor Supervision/HSE Officer are present
No other activities and personnel present with in
4
pressure test area other than pressure test crew.

5 All the hose connections having whip check arrestor.

Drain the water in approved pit or collect in a


6
container or as accecpted.
The access to the pressure is clear and not causing
7
any hindering to the movement of workmen.

10