You are on page 1of 7

METHOD STATEMENT

OBJECTIVE

The objective of this method statement is to describe the specifications and different
stages involved for the safe and proper construction of pile caps, water sump and
ground floor related to the “Greenpath City Hotel Development Project”.

SCOPE OF WORK

This item includes the followings;

a) Pile hacking
b) Lean concrete
c) Form work
d) Water proofing
e) Reinforcement
f) Concreting

RESPONSIBILITIES

Site Organization Chart

REFERENCES

Drawings

Specifications

Greenpath City Hotel Development Project, Colombo 03 1


METHOD STATEMENT

WORK DESCRIPTION FLOW CHART

PILE HACKING

LEAN CONCRETE

SETTING OUT FOR PILE CAPS,


WATER SUMP & GROUND FLOOR

NCRETE

FORM WORK

WATER PROOFING

PROTECTING BED

REINFORCEMENT

CONCRETING

CURING

Greenpath City Hotel Development Project, Colombo 03 2


METHOD STATEMENT

PILE HACKING

All the pile will be concrete additional 1 m length from the pile cutoff level. After
excavation carried out addition 1m length of the pile from the pile cutoff level will be
hacked and cleaned.

PILE CUTOFF LEVEL PILE HACKING LENGTH

BED ROCK

Figure 1: Pile Hacking Length

Greenpath City Hotel Development Project, Colombo 03 3


METHOD STATEMENT

LEAN CONCRETE

After the excavation soil surface will be leveled roughly and if the soil condition is
muddy thin layer of laterite soil will be placed on pile cap area, water sump and ground
floor bed. The bed will be compacted to the required level. A 75mm lean concrete of
grade 15 shall be placed over the soil surface.

Pile Cap Area

Lean Concrete Area

Figure 2: Lean Concrete on Pile Cap

Greenpath City Hotel Development Project, Colombo 03 4


METHOD STATEMENT

FORM FORM
WORK PILE CAP AREA WORK
AREA AREA

Figure 3: Section of Lean Concrete on Pile Cap Area

SETTING OUT

After completion of lean concrete, setting out for pile caps, water sump and ground
floor will be carried out in according to the layout drawings.

FORM WORK

Thereafter Form work around the pile caps, water sump and ground floor will be
carried out with 12 mm thk plywood, 2”x2” timber and GI Pipe, Pipe supports, T jack,
and Form Ties.

REINFORCEMENT

Reinforcement will be carried out as specified in the structural drawings for pile cap,
water sump & ground floor. (Refer Annexure – II) For more details about reinforcement
refer “Method Statement on Reinforcement”.

CONCRETING

Concreting will be carried out with relevant grade of concrete as specified in design. For
more details about concreting refer “Method Statement on Concreting”

Greenpath City Hotel Development Project, Colombo 03 5


METHOD STATEMENT

Greenpath City Hotel Development Project, Colombo 03 6


METHOD STATEMENT

Greenpath City Hotel Development Project, Colombo 03 7

You might also like