OBJECTIVE
The objective of this method statement is to describe the specifications and different
stages involved for the safe and proper construction of pile caps, water sump and
ground floor related to the “Greenpath City Hotel Development Project”.
SCOPE OF WORK
a) Pile hacking
b) Lean concrete
c) Form work
d) Water proofing
e) Reinforcement
f) Concreting
RESPONSIBILITIES
REFERENCES
Drawings
Specifications
PILE HACKING
LEAN CONCRETE
NCRETE
FORM WORK
WATER PROOFING
PROTECTING BED
REINFORCEMENT
CONCRETING
CURING
PILE HACKING
All the pile will be concrete additional 1 m length from the pile cutoff level. After
excavation carried out addition 1m length of the pile from the pile cutoff level will be
hacked and cleaned.
BED ROCK
LEAN CONCRETE
After the excavation soil surface will be leveled roughly and if the soil condition is
muddy thin layer of laterite soil will be placed on pile cap area, water sump and ground
floor bed. The bed will be compacted to the required level. A 75mm lean concrete of
grade 15 shall be placed over the soil surface.
FORM FORM
WORK PILE CAP AREA WORK
AREA AREA
SETTING OUT
After completion of lean concrete, setting out for pile caps, water sump and ground
floor will be carried out in according to the layout drawings.
FORM WORK
Thereafter Form work around the pile caps, water sump and ground floor will be
carried out with 12 mm thk plywood, 2”x2” timber and GI Pipe, Pipe supports, T jack,
and Form Ties.
REINFORCEMENT
Reinforcement will be carried out as specified in the structural drawings for pile cap,
water sump & ground floor. (Refer Annexure – II) For more details about reinforcement
refer “Method Statement on Reinforcement”.
CONCRETING
Concreting will be carried out with relevant grade of concrete as specified in design. For
more details about concreting refer “Method Statement on Concreting”