3 Check foundation bolts for same size, thread & proper washers. Vendor GA Drawing Spirit Level / Visual Check Verify
4 Check foundation, eyebolt & grease nipples. Vendor GA Drawing Visual Check Verify
5 Check & match motor nameplate details & tag number. Datasheet Physical Verification Mandatory Check Mandatory Check
14 CABLING
16 Check for motor terminal connections wrt terminal diagrams. Wiring Diagram Physical Verification Check Verify
Check for double earthing from two distinct earths & size of earth
17 Visual Check Verify
conductor.
18 Check shim condition (if used) under the motor foundation legs. Visual Check Verify
19 Check all openings are covered / plugged. Visual Mandatory Check Verify
20 Coupling guard are fitted on the coupling. Visual Check Verify
21 Check for canopy provided wherever required. Visual Check Verify
22 Check for presence of small bag of silica gel in the MTB. Physical Verification Check Verify
25.1 Check Low Voltage Motor Insulation resistance Test Datasheet Physical Verification Mandatory Check Verify
25.2 H V Motor High Voltage Test. Datasheet Physical Verification Mandatory Check Verify
25.4 Polarization Index Test for H V Motors Datasheet Physical Verification Mandatory Check Verify
26 Motor operated Valve and Motor Insulation Resistance Test. Datasheet Physical Verification Mandatory Check Verify
CLIENT : M/S GUJARAT FLOUROCHEMICALS LIMITED
PROJECT : MICRO POWDER PLANT
DOCUMENT NO. : APPENDIX C TO PE-3155-EL-QAP-01
DOCUMENT TITLE : INSTALLATION CHECKLIST FOR MOTORS
REV. NO. : R0
PLANT
UNIT
REFERENCE DRAWINGS A) GA DRAWING B) WIRING DIAGRAM C) OEM OPERATION AND MAINTAINANCE MANUAL
REMARKS / OBSERVATIONS
INSPECTION ENGINEER
DATE AND SIGNATURE