Pakistan EPCL PVC Ⅲ Expansion Project

Checklist for Scaffold Inspection and Acceptance


脚手架验收检查清单
分包商 Subcontractor: 日期和时间 Date &Time:

使用区域 Use Area: 脚手架编号 Scaffold No:

Inspection results
No. CHECK POINTS
Accept Not accept

1 Scaffolding components and fittings conforming to required specifications. 部件配件材质规格负荷要求

2 Scaffolding components and fittings showing no signs of deterioration by rusting. 部件配件无锈蚀损坏迹象

Scaffolding maintains correct safe distance from external power lines (if any) 脚手架与外电线路保持安全
3
距离(如果有)
Built per specification. (Straight and square). 按规范搭设 (横平竖直);Foot-ties correctly installed. 扫
4 地 杆 设 置 正 确 ; Bay and lift correct 步 距 、 跨 距 合 理 ; Standards plumb and placed at their correct
distances from each other. 立杆垂直、间距正确。
Proper diagonal/cross bracings in place and in sufficient numbers. 脚手架斜撑/剪刀撑系统设置正确、数量
5 足够;Tie-ins correctly installed and in sufficient numbers to ensure the stability of the scaffold. 锚固点设
置正确、数量足够
6 Sill timbers and base plates properly provided. 脚手架基础设有垫木和底座

Over-span in right distance. 跳板跨度合适;Overhang in right length. 跳板探头长度合格;Over-laps at


least 300mm. 跳板搭接长度至少 30 公分;If butt-connected, the overhanged parts shall be secured to 2
7 transoms and the overhanging length of both planks shall be 13-15cm. The overhanged length sum shall
not exceed 30cm. 跳板如果对接,对接接头处须设两根小横杆,脚手板外延 13-15cm, 两板外延长度之和
不应大于 30 公分;
8 Toe-boards provided and securely fastened in position. 踢脚板安装到位且固定牢固。

9 Scaffolding properly grounded where necessary 必要时,对脚手架架体进行接地

10 All working platform completely decked out. 所有操作平台满铺

11 Guardrails and mid-rails fitted and connected to standards 上、中护栏安装到位,并且是连接在立杆上面

12 Safety net of close-mesh wire or a fan of boards properly erected 架体防护密目网安装正确

Proper ladders/walkways provided to give access to every working platform. 每层操作平台上都设有合适的


13 上下通道;There shall be an opposite platform every 3 or 4 m for vertical ladder.如有直爬梯,每隔 3~4
米设置一个转换平台。
Working platforms, access ways and landings cleared off any obstructions, loose objects and tripping
14
hazards.脚手架操作平台、通道及着陆点没有任何障碍物、松散物和羁绊物。

15 It shall be installed by qualified scaffolding men.合格架子工搭设。

16 The planks shall be over 35mm thick.跳板厚度不低于 35mm.

Other 其他
17

 Qualified Check by
Inspection and assessment
comments  Unqualified Date

第1页共2页
Pakistan EPCL PVC Ⅲ Expansion Project

第2页共2页