You are on page 1of 604

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(1) Clearing & Grubbing (with Stripping)


Unit of Measurement : ha
Output per hour : 0.05

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Dump Truck (12 cu.yd.) 2 1 1,420.00 2,840.00


b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Bulldozer, D6H SERIES II PSDS/DD 1 1 3,379.00 3,379.00

*Hauling Distance - within 3 km


*Assumed 150mm cut

Sub-Total for B 7,952.00


C. Total (A + B) 8,153.22
D. Output per hour = 0.05 ha
E. Direct Unit Cost (C ÷ D) 163,064.40
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 163,064.40
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 14,675.80
I. Contractor's Profit (CP) 8% of G 13,045.15
J. Value Added Tax (VAT) 5% of (G + H + I) 9,539.27
K Total Unit Cost (G + H + I + J) 200,324.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)a Individual Removal of Trees (small a, 150-300 mm. ø)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0.33 95.10 31.38


b.Skilled Labor 1 0.33 69.01 22.77
c.Unskilled Labor 2 0.33 53.06 35.02

Sub-Total for A 89.18


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b.Dump Truck(12 cu.yd.) 1 0.17 1,420.00 241.40
c. Chain Saw 1 0.17 75.36 12.81
Minor Tools (5% of labor) 4.46

* Boom Truck - if necessary for trimming in


Urban Areas

Sub-Total for B 642.92


C. Total (A + B) 732.10
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 732.10
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Rope, 1" dia. -5 uses m. 20.00 3.50 70.00

Sub-Total for F 70.00


g. Direct Unit Cost ( E + F ) 802.10
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 72.19
I. Contractor's Profit (CP) 8% of G 64.17
J. Value Added Tax (VAT) 5% of (G + H + I) 46.92
K Total Unit Cost (G + H + I + J) 985.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)b Individual Removal of Trees (small b, ab0ve 300-500 mm. ø)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 0.67


b.Skilled Labor 1 0.67
c.Unskilled Labor 2 0.67

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50


b.Dump Truck(12 cu.yd. 1 0.33
c. Chain Saw 1 0.33
Minor Tools (5% of labor)

* Boom Truck - if necessary for trimming in


Urban Areas

Sub-Total for B
C. Total (A + B)
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Rope, 1" dia. - 5 uses m. 20.00


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

ve 300-500 mm. ø)

Hourly Rate Amount

95.10 63.72
69.01 46.24
53.06 71.10

181.05
Hourly Rate Amount

1,537.00 768.50
1,420.00 468.60
75.36 24.87
9.05

1,271.02
1,452.08

1,452.08 603.12
Unit Cost Amount

3.50 70.00
70.00
1,522.08
of G 136.99
of G 121.77
of (G + H + I) 89.04
(G + H + I + J) 1,869.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(4)a Individual Removal of Trees (small


s large
b,a,above
301-500500-750
mm. ø) mm
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 3.33 95.10 316.68


b. Skilled Labor 1 3.33 69.01 229.80
c.Unskilled Labor 2 3.33 53.06 353.38

Sub-Total for A 899.87


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 2.50 1,537.00 3,842.50


b. Dump Truck (12 cu.yd.) 1 1.67 1,420.00 2,371.40
c. Chain Saw 1 1.67 75.36 125.85
Minor Tools (5% of labor) 44.99

* Boom Truck - If necessary for trimming in


Urban Areas

Sub-Total for B 6,384.74


C. Total (A + B) 7,284.61
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 7,284.61
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Rope, 1" dia. - 5 uses m. 20.00 3.50 70.00

Sub-Total for F 70.00


g. Direct Unit Cost ( E + F ) 7,354.61
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 661.91
I. Contractor's Profit (CP) 8% of G 588.37
J. Value Added Tax (VAT) 5% of (G + H + I) 430.24
K Total Unit Cost (G + H + I + J) 9,035.14
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(4)b Individual Removal of Trees (large b,above 750-900 mm. ø)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 6.67


b. Skilled Labor 1 6.67
c.Unskilled Labor 2 6.67

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 5.00


b. Dump Truck (12 cu.yd.) 1 3.33
c. Chain Saw 1 3.33
Minor Tools (5% of labor)

* Boom Truck - If necessary for trimming in


Urban Areas

Sub-Total for B
C. Total (A + B)
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Rope, 1" dia. m. 20.00


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

e 750-900 mm. ø)

Hourly Rate Amount

95.10 634.32
69.01 460.30
53.06 707.82

1,802.43
Hourly Rate Amount

1,537.00 7,685.00
1,420.00 4,728.60
75.36 250.95
90.12

12,754.67
14,557.10

14,557.10
Unit Cost Amount

3.50 70.00
70.00
14,627.10
of G 1,316.44
of G 1,170.17
of (G + H + I) 855.69
(G + H + I + J) 17,969.40
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1) Removal of Structures and Obstruction


Unit of Measurement : ls
Output per hour : 1.00 ls

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

-
-
See derivations for Item Nos.101(1)a to 101(1)d -

Sub-Total for A -
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

-
-
See derivations for Item Nos.101(1)a to 101(1)d -
-

Sub-Total for B -
C. Total (A + B) -
D. Output per hour = 1.00 ls ls
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

-
See derivations for Item Nos.101(1)a to 101(1)d

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) of G #VALUE!
I. Contractor's Profit (CP) of G #VALUE!
J. Value Added Tax (VAT) of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)a Removal of Concrete Bridge Structure


Unit of Measurement : cu.m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b.Skilled Labor 2 1
c.Unskilled Labor 4 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50


b.Jackhammer 2 1.00
c.Air Compressor (356-450 cfm) 1 1.00
d.Dump Truck(12 cu.yd. 1 0.13
e.Payloader (1.50 cu.m) 1 0.13
f.Truck Mounted Crane (31-35 mt) 1 0.25
g.Cutting Outfit 1 1.00

* Hauling distance - within 3km

Sub-Total for B
C. Total (A + B)
D. Output per hour = 1.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Oxy/Acetylene set 0.10

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.10 95.10
69.01 138.02
53.06 212.24

445.36
Hourly Rate Amount

1,537.00 768.50
150.00 300.00
965.00 965.00
1,420.00 177.50
1,733.00 216.63
1,861.00 465.25
45.45 45.45

2,938.33
3,383.69

3,383.69
Unit Cost Amount

3.50 0.35

0.35
3,384.04
of G 304.56
of G 270.72
of (G + H + I) 197.97
(G + H + I + J) 4,157.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)b Removal of Steel Bridge Structures


Unit of Measurement : kg
Output per hour : 1000.00 kg

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Skilled Labor 2 1 69.01 138.02
c.Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Truck Mounted Crane(31-35 mt) 1 1 1,861.00 1,861.00


b. Service Truck/Cargo Truck(2-5 mt) 1 1 783.00 783.00
c. Welding Machine (300 A),Gas/Diesel Driven 1 1 371.00 371.00
d.Cutting Outfit 1 1 45.45 45.45
Minor Tools(10% of Labor Cost) 44.54

Sub-Total for B 3,104.99


C. Total (A + B) 3,550.35
D. Output per hour = 1000.00 kg
E. Direct Unit Cost (C ÷ D) 3.55
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Oxy/Acetylene set 0.00 -


b.Welding Rod kg 0.002
c.Rope 1" Ø m 0.05

*Include shoring materials if needed based on actual field condition

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 3.55
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 0.32
I. Contractor's Profit (CP) 8% of G 0.28
J. Value Added Tax (VAT) 5% of (G + H + I) 0.21
K Total Unit Cost (G + H + I + J) 4.36
Item No./Description : 101(1)c Removal of Stone Masonry Lined Drainage Structures
Unit of Measurement : cu.m
Output per hour : 10.000

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
c.Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Backhoe with Breaker (0.80 cu.m) 1 1


b.Backhoe (0.80 cu.m)-for loading 1 1
c.Dump Truck (12 cu.yd) 1 1

*Hauling distance- within 3 km

Sub-Total for B
C. Total (A + B)
D. Output per hour = 10.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
ge Structures

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

1,998.10 999.05
1,537.00 768.50
1,420.00 1,420.00

3,187.55
3,388.77

338.88
Unit Cost Amount

-
0.00
338.88
of G 30.50
of G 27.11
of (G + H + I) 19.82
(G + H + I + J) 416.31
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)d Removal of Concrete Drainage Structures


Unit of Measurement : cu.m
Output per hour : 2.00 cu.m.

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c.Unskilled Labor 2 1 53.06 106.12

*Hauling distance is 3km

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe with Breaker (0.80 cu.m.) 1 1 1,998.10 999.05


b. Backhoe (0.80 cu.m)-for loading 1 0 1,537.00 384.25
c.Dump Truck (12 cu.yd) 1 1 1,420.00 710.00
d.Cutting Outfit 1 1 75.36 75.36

*Hauling distance - within 3 km

Sub-Total for B 2,168.66


C. Total (A + B) 2,438.89
D. Output per hour = 2.00 cu.m
E. Direct Unit Cost (C ÷ D) 1,219.45
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Oxy/Acetylene set 0.10

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 1,219.45
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 109.75
I. Contractor's Profit (CP) 8% of G 97.56
J. Value Added Tax (VAT) 5% of (G + H + I) 71.34
K Total Unit Cost (G + H + I + J) 1,498.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)a Removal of RCPC (24" Ø)-610 mmØ


Unit of Measurement : ea
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. UnSkilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00


b.Boom Truck(2-5 mt) 1 1
Minor tools ( 10% of Labor Cost)

*Hauling distance -within 3km.

Sub-Total for B
C. Total (A + B)
D. Output per hour = 6.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12
-

201.22
Hourly Rate Amount

1,537.00 1,537.00
1,017.90 508.95
20.12
-
-
-
-

2,066.07
2,267.29

377.88
Unit Cost Amount

-
0.00
377.88
of G 34.01
of G 30.23
of (G + H + I) 22.11
(G + H + I + J) 464.23
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)b Removal of RCPC (30" Ø)-760 mmØ


Unit of Measurement : ea
Output per hour : 5.00 ea

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12
-

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b.Boom Truck(2-5 mt) 1 1 1,017.90 508.95
Minor tools ( 10% of Labor Cost) -
-
*Hauling distance -within 3km. -
-
-

Sub-Total for B 2,045.95


C. Total (A + B) 2,247.17
D. Output per hour = 5.00 ea
E. Direct Unit Cost (C ÷ D) 449.43
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 449.43
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 40.45
I. Contractor's Profit (CP) 8% of G 35.95
J. Value Added Tax (VAT) 5% of (G + H + I) 26.29
K Total Unit Cost (G + H + I + J) 552.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)c Removal of RCPC (36" Ø)-910 mmØ


Unit of Measurement : ea
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00


b.Boom Truck(2-5 mt) 1 1
Minor tools ( 10% of Labor Cost)

*Hauling distance - within 3km.

Sub-Total for B
C. Total (A + B)
D. Output per hour = 4.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12
-

201.22
Hourly Rate Amount

1,537.00 1,537.00
1,017.90 508.95
20.12
-
-
-
-

2,066.07
2,267.29

566.82
Unit Cost Amount

-
0.00
566.82
of G 51.01
of G 45.35
of (G + H + I) 33.16
(G + H + I + J) 696.34
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)d Removal of RCPC (42"Ø)-1070 mm Ø


Unit of Measurement : ea
Output per hour : 4.00 ea

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. UnSkilled Labor 2 1 53.06 106.12
-

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a.Backhoe (0.80 cu.m) 1 1 1,537.00 1,537.00


b. Boom Truck (2-5 mt) 1 1 1,017.90 508.95

Minor Tools (10% of Labor) 20.12

*Hauling distance -within 3km

Sub-Total for B 2,066.07


C. Total (A + B) 2,267.29
D. Output per hour = 4.00 ea
E. Direct Unit Cost (C ÷ D) 566.82
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

-
-
-

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 566.82
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 51.01
I. Contractor's Profit (CP) 8% of G 45.35
J. Value Added Tax (VAT) 5% of (G + H + I) 33.16
K Total Unit Cost (G + H + I + J) 696.34
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)e Removal of RCPC (48"Ø)-1220 mm Ø


Unit of Measurement : ea
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Laborer 2 1 53.06 106.12
-

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a.Backhoe (0.80 cu.m) 1 1.00 1,537.00 1,537.00


b. Boom Truck (2-5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10% of Labor Cost) 20.12

*Hauling distance-within 3 km

Sub-Total for B 2,066.07


C. Total (A + B) 2,267.29
D. Output per hour = 3.00 ea
E. Direct Unit Cost (C ÷ D) 755.76
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 755.76
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 68.02
I. Contractor's Profit (CP) 8% of G 60.46
J. Value Added Tax (VAT) 5% of (G + H + I) 44.21
K Total Unit Cost (G + H + I + J) 928.46
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)f Removal of RCPC (60"Ø-1520 mmØ


Unit of Measurement : ea
Output per hour : 2.00 ea

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00


b.Boom Truck(2-5 mt) 1 0.50 1,017.90 508.95
Minor Tools (10% of Labor Cost) 20.12
-

* Hauling distance- within 3km.

Sub-Total for B 2,066.07


C. Total (A + B) 2,267.29
D. Output per hour = 2.00 ea
E. Direct Unit Cost (C ÷ D) 1,133.65
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 1,133.65
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 102.03
I. Contractor's Profit (CP) 8% of G 90.69
J. Value Added Tax (VAT) 5% of (G + H + I) 66.32
K Total Unit Cost (G + H + I + J) 1,392.68
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200 mm dia)
Unit of Measurement : ea
Output per hour : 2.00 ea

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m) 1 1.00


b.Boom Truck(2-5 mt) 1 0.50
Minor Tools (10% of Labor Cost)

* Hauling distance- within 3km.

Sub-Total for B
C. Total (A + B)
D. Output per hour = 2.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

s (PVC/GI/Asbestos, up to 200 mm dia), L=10 f

Hourly Rate Amount

95.1 95.10
53.06 106.12
-

201.22
Hourly Rate Amount

922.00 922.00
1,017.90 508.95
20.12
-

1,451.07
1,652.29

826.15
Unit Cost Amount

-
0.00
826.15
of G 74.35
of G 66.09
of (G + H + I) 48.33
(G + H + I + J) 1,014.92
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a.1 Removal of Existing Concrete Pavement (0.23 m thk)


Unit of Measurement : sq.m.
Output per hour : 40.00 sq.m.

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/Pavement Breaker (0.80 cu.m) 1 1 1,998.10 1,998.10


b. Payloader (1.50 cu.m) LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (12 cu.yd.) 1 0.50 1,420.00 710.00
Minor Tools(10% of labor Cost) 20.12

*Hauling distance is 3km.

Sub-Total for B 4,461.22


C. Total (A + B) 4,662.44
D. Output per hour = 40.00 sq.m. sq.m.
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a.2 Removal of Existing PCC Pavement (0.23 m thk) for Reblocking at intermittent s
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe w/Pavement Breaker (0.80 cu.m) 1 1


b. Payloader (1.50 cu.m) LX80-2C 1 1.00
c. Dump Truck (12 cu.yd.) 1 0.50
d.Concrete Saw (7.5 hp), 14"dia Blade 1 0.50
Minor Tools(10% of labor Cost)

*Hauling distance -within 3km.

Sub-Total for B
C. Total (A + B)
D. Output per hour = 30.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
a.Concrete Saw (Diamond Blade 14" dia) pc 0.00

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

m thk) for Reblocking at intermittent section

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

1,998.10 1,998.10
1,733.00 1,733.00
1,420.00 710.00
32.63 16.32
20.12

4,477.54
4,678.76

155.96
Unit Cost Amount
0.00
155.96
of G 14.04
of G 12.48
of (G + H + I) 9.12
(G + H + I + J) 191.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)b Removal of Existing Asphalt Pavement (100 mm thk)


Unit of Measurement : sq.m
Output per hour : 60.00 sq.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader w/Scarifier,G710A 1 1 2,173.00 2,173.00


b. Payloader (1.50 cu.m.),LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (12 cu.yd.) 1 0.50 1,420.00 710.00
Minor Tools (10% of Labor Cost) 20.12

*Hauling distance-within 3km.

Sub-Total for B 4,636.12


C. Total (A + B) 4,837.34
D. Output per hour = 60.00 sq.m sq.m
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)c Removal of Sidewalk (100 mm thk)


Unit of Measurement : sq.m
Output per hour : 75.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe w/Pavement Breaker (0.80 cu.m) 1 1


b. Payloader (1.50 cu.m.), LX80-2C 1 1.00
c. Dump Truck (12 cu.yd.) 1 0.50
Minor Tools (10% of Labor Cost)

*Hauling distance-within 3km.

Sub-Total for B
C. Total (A + B)
D. Output per hour = 75.00 sq.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

1,998.10 1,998.10
1,733.00 1,733.00
1,420.00 710.00
20.12

4,461.22
4,662.44

62.17
Unit Cost Amount
0.00
62.17
of G 5.59
of G 4.97
of (G + H + I) 3.64
(G + H + I + J) 76.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)a Removal of Curb


Unit of Measurement : m
Output per hour : 50.00 m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe w/Breaker (0.80 cu.m.) 1 1 1,998.10 999.05


b. Backhoe (0.80 cu.m) 1 0.50 1,537.00 768.50
c.Dump Truck (12 cu.yd) 1 0.50 1,420.00 710.00

*Hauling distnace -within 3km

Sub-Total for B 2,477.55


C. Total (A + B) 2,678.77
D. Output per hour = 50.00 m m
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)b Removal of Curb & Gutter


Unit of Measurement : m
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe w/Breaker (0.80 cu.m.) 1 1


b. Backhoe (0.80 cu.m) 1 0.50
c.Dump Truck (12 cu.yd) 1 0.50

*Hauling distnace -within 3km

Sub-Total for B
C. Total (A + B)
D. Output per hour = 30.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

1,998.10 999.05
1,537.00 768.50
1,420.00 710.00

2,477.55
2,678.77

89.29
Unit Cost Amount
0.00
89.29
of G 8.04
of G 7.14
of (G + H + I) 5.22
(G + H + I + J) 109.70
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(1) Roadway Excavation (Unsuitable)


Unit of Measurement : cu.m
Output per hour : 20.00 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Dump Truck (12 cu.yd) 2 1 1,537.00 3,074.00


b. Backhoe (0.80 cu.m) 1 1.00 961.20 961.20
c. Payloader (1.50 cu.m) at disposal site 1 0.10 25.43
Minor Tools (10 % of Labor Cost)

*Hauling distance- within 3km

Sub-Total for B 4,060.63


C. Total (A + B) 4,314.91
D. Output per hour = 20.00 cu.m
E. Direct Unit Cost (C ÷ D) 215.75
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 215.75
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 19.42
I. Contractor's Profit (CP) 8% of G 17.26
J. Value Added Tax (VAT) 5% of (G + H + I) 12.62
K Total Unit Cost (G + H + I + J) 265.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)a Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. UnskilledLabor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Bulldozer ,D6H SERIES II PSDS/DD 1 1


b. Payloader (1.50 cu.m) 1 1.00
c.Payloader (1.50 cu.m)-at disposal area 1 0.25
d.Dump Truck (12 cu.yd) 2 1

*Hauling distance -within 3km

Sub-Total for B
C. Total (A + B)
D. Output per hour = 60.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

3,379.00 3,379.00
1,733.00 1,733.00
1,733.00 433.25
1,420.00 2,840.00

8,385.25
8,586.47

143.11
Unit Cost Amount
0.00
143.11
of G 12.88
of G 11.45
of (G + H + I) 8.37
(G + H + I + J) 175.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)b RoadwayExcavation (Surplus Common)


Unit of Measurement : cu.m
Output per hour : 80.00 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer,D6H SERIES II PSDS/DD 1 1 3,379.00 3,379.00


b. Payloader (1.50 cu.m) 1 1.00 1,733.00 1,733.00
c.Payloader (1.50 cu.m)-at disposal area 1 0.30 1,733.00 519.90
d.Dump truck (12 cu.yd) 3 1 1,420.00 4,260.00
e.Backhoe (0.80 cu.m) 1 1.000 1,537.00 1,537.00

*Hauling distance- within 3 km

Sub-Total for B 11,428.90


C. Total (A + B) 11,630.12
D. Output per hour = 80.00 cu.m cu.m
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)a Roadway Excavation (Surplus Sof Rock)


Unit of Measurement : cu.m
Output per hour : 56.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. UnskilledLabor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Bulldozer w/Ripper,D6H SERIES II PSDS/DD 1 1


b. Payloader (1.50 cu.m) 1 1.00
c.Payloader (1.50 cu.m)-at disposal area 1 0.25
d.Dump Truck (12 cu.yd) 2 1
e.Backhoe (0.80 cu.m)w/attachment 1 1.000
*Hauling distance -within 3km

Sub-Total for B
C. Total (A + B)
D. Output per hour = 56.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

3,885.85 3,885.85
1,733.00 1,733.00
1,733.00 433.25
1,420.00 2,840.00
1,537.00 1,537.00

10,429.10
10,630.32

189.83
Unit Cost Amount
0.00
189.83
of G 17.08
of G 15.19
of (G + H + I) 11.10
(G + H + I + J) 233.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)b Roadway Excavation (Surplus Sof Rock)


Unit of Measurement : cu.m
Output per hour : 42.00 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. UnskilledLabor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bulldozer w/Ripper,D6H SERIES II PSDS/DD 1 1 1,537.00 1,537.00


b. Payloader (1.50 cu.m) 1 1.00 961.20 961.20
c.Payloader (1.50 cu.m)-at disposal area 1 0.20 961.20 192.24
d.Dump Truck (12 cu.yd) 2 1 961.20 1,922.40

*Hauling distance -within 3km

Sub-Total for B 4,612.84


C. Total (A + B) 4,814.06
D. Output per hour = 42.00 cu.m cu.m
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)c Roadway Excavation(Surplus Hard Rock)- Blasting


Unit of Measurement : cu.m
Output per hour : 4.20

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman (Drilling) 1 0.4


b. Skilled Labor 2 0.4
c. Unskiled Labor 4 0.4
a. Construction Foreman (Blasting) 1 0.2
b. Skilled Labor 1 0.2
c. Unskiled Labor 2 0.2
a. Construction Foreman (Disposal) 1 0.4
b. Skilled Labor 2 0.4

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m) 1 0.2


b.Payloader (1.50 cu.m) 1 0.15
c.Payloader (1.50 cu.m)-at disposal area 1 0
d.Dump Truck (12 cu.yd) 1 0.400
e.Pneumatic Drilling Machine 2 0
f.Air Compressor (161-185 cfm) 1 0.4

*Hauling distance-within 3 km

Sub-Total for B
C. Total (A + B)
D. Output per hour = 4.20 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Dynamite kg 0.40
b.Detonatin Cord m 2
c.Detonator pc 0.15
d.Ammonium Sulfate kg 0.2
e.Blasting cap pc 0.4
f.Safety Fuse m 0.1

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 38.04
69.01 55.21
53.06 84.90
95.1 19.02
69.01 13.802
53.06 21.224
95.10 38.04
69.01 55.208

#VALUE!
Hourly Rate Amount

1,537.00 307.40
1,733.00 259.95
1,733.00 86.65
1,420.00 568.00
170.00 136.00
502.00 200.80

1,558.80
#VALUE!

#VALUE!
Unit Cost Amount
0.00
#VALUE!
of G #VALUE!
of G #VALUE!
of (G + H + I) #VALUE!
(G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)d Roadway Excavation(Surplus Hard Rock)- Blasting (Tunnel Excavation)
Unit of Measurement : cu.m
Output per hour : 1.65 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman (Drilling) 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskiled Labor 4 1 53.06 212.24
a. Construction Foreman (Blasting) 1 1 95.1 95.10
b. Skilled Labor 1 1 69.01 69.01
c. Unskiled Labor 2 1 53.06 106.12
a. Construction Foreman (Disposal) 1 0.5 95.10 47.55
b. Skilled Labor 2 0.5 69.01 69.01

Sub-Total for A 832.15


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m) 1 0.5 1,537.00 768.50


b.Backhoe w/Chipping Hammer (0.80 cu.m) 1 0.10 1,537.00 153.70
c.Dump Truck(12 cu.yd) 1 0.50 1,420.00 710.00
d.Pneumatic Drilling Machine 2 1 170.00 340.00
e.Air Compressor (161-185 cfm) 1 1.000 502.00 502.00
f.Payloader(1.50 cu.m) 1 0 1,733.00 346.60
g.Payloader (1.50 cu.m)-at disposal area 1 0.03 1,733.00 51.99
h.Water Truck/Pump (16000 L) 1 0.05 2,450.00 122.50

Sub-Total for B 2,995.29


C. Total (A + B) 3,827.44
D. Output per hour = 1.65 cu.m cu.m
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Dynamite kg 2.00
b.Detonatin Cord m 1.4
c.Detonator pc 2
d.Ammonium Sulfate kg 1
e.Blasting cap pc 0.45
f.Safety Fuse m 0.1

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(4) Roadway Excavation (Surplus Unclassified)


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. UnskilledLabor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Bulldozer,D6H SERIES II PSDS/DD 1 1


b. Payloader (1.50 cu.m) 1 1.00
c.Payloader (1.50 cu.m)-at disposal area 1 0.20
d.Dump Truck (12 cu.yd) 2 1

*Hauling distance-within 3km

Sub-Total for B
C. Total (A + B)
D. Output per hour = 50.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

3,379.00 3,379.00
1,733.00 1,733.00
1,733.00 346.60
1,420.00 2,840.00

8,298.60
8,499.82

170.00
Unit Cost Amount
0.00
170.00
of G 15.30
of G 13.60
of (G + H + I) 9.94
(G + H + I + J) 208.84
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)a Structure Excavation (Common Soil)


Unit of Measurement : cu.m
Output per hour : 20.00 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Dumptruck (12 cu.yd) 2 1 1,420.00 2,840.00


b.Backhoe (0.80 cu.m) 1 1 1,537.00 1,537.00
Minor Tools (10% of Labor) 25.43

Sub-Total for B 4,402.43


C. Total (A + B) 4,656.71
D. Output per hour = 20.00 cu.m
E. Direct Unit Cost (C ÷ D) 232.84
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 232.84
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 20.96
I. Contractor's Profit (CP) 8% of G 18.63
J. Value Added Tax (VAT) 5% of (G + H + I) 13.62
K Total Unit Cost (G + H + I + J) 286.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)b Structure Excavation (Sof Rock)


Unit of Measurement : cu.m
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Dump Truck (12 cu.yd) 2 1


b.Backhoe (0.80 cu.m) 1 0.5
c.Backhoe w/Breaker(0.80 cu.m) 1 0.50

Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 14.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 159.18

254.28
Hourly Rate Amount

1,420.00 2,840.00
1,537.00 768.50
1,998.10 999.05
25.43

4,632.98
4,887.26

349.09
Unit Cost Amount

8,000.00 -
0.00
349.09
of G 31.42
of G 27.93
of (G + H + I) 20.42
(G + H + I + J) 428.86
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)c Structure Excavation (Solid Rock)


Unit of Measurement : cu.m
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a.Dump Truck (12 cu.yd) 1 1 1,420.00 1,420.00


b.Backhoe (0.80 cu.m) 1 0.25 1,537.00 384.25
c.Backhoe w/Breaker(0.80 cu.m) 1 0.75 1,998.10 1,498.58

Minor Tools (10% of Labor Cost) 25.43

Sub-Total for B 3,328.25


C. Total (A + B) 3,582.53
D. Output per hour = 4.00 cu.m
E. Direct Unit Cost (C ÷ D) 895.63
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 895.63
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 80.61
I. Contractor's Profit (CP) 8% of G 71.65
J. Value Added Tax (VAT) 5% of (G + H + I) 52.39
K Total Unit Cost (G + H + I + J) 1,100.29
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)a Bridge Excavation (Common Soil)


Unit of Measurement : cu.m
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b.Skilled Labor 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Backhoe (0.80 cu.m) 1 1


b.Dump Truck (12 cu.yd) 2 1
Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 20.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
a. Concrete Saw (diamond blade 14") pc. 0.00015

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
69.01 69.01
53.06 106.12

270.23
Hourly Rate Amount

1,537.00 1,537.00
1,420.00 2,840.00
27.02

4,404.02
4,674.25

233.71
Unit Cost Amount
8,000.00 1.20

1.20
234.91
of G 21.14
of G 18.79
of (G + H + I) 13.74
(G + H + I + J) 288.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)b Bridge Excavation (Sof Rock)


Unit of Measurement : cu.m
Output per hour : 14.00 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m) 1 0.5 1,537.00 768.50


b. Backhoe w/Breaker (0.80 cu.m) 1 0.5 1,998.10 999.05
c.Dump Truck (12 cu.yd) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 4,634.57


C. Total (A + B) 4,904.80
D. Output per hour = 14.00 cu.m cu.m
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)c Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 1 1
c. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m) 1 0.5


b. Backhoe w/Breaker (0.80 cu.m) 1 1
c.Dump Truck (12 cu.yd) 1 0.50
Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 4.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
69.01 69.01
53.06 106.12

270.23
Hourly Rate Amount

1,537.00 768.50
1,998.10 1,998.10
1,420.00 710.00
27.02

3,503.62
3,773.85

943.46
Unit Cost Amount
0.00
943.46
of G 84.91
of G 75.48
of (G + H + I) 55.19
(G + H + I + J) 1,159.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)d Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m
Output per hour : 1.50 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Jack Hammer 2 1.00 150.00 300.00


b. Air Compressor (356-450 cfm) 1 1.00 965.00 965.00
c. Backhoe (0.80 cu.m) 1 0.15 1,537.00 230.55
d.Dump Truck (12 cu.yd) 1 0.15 1,420.00 213.00
Minor tools (10% of Labor Cost) 27.02

Sub-Total for B 1,735.57


C. Total (A + B) 2,005.80
D. Output per hour = 1.50 cu.m
E. Direct Unit Cost (C ÷ D) 1,337.20
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 1,337.20
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 120.35
I. Contractor's Profit (CP) 8% of G 106.98
J. Value Added Tax (VAT) 5% of (G + H + I) 78.23
K Total Unit Cost (G + H + I + J) 1,642.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(3) Foundation Fill


Unit of Measurement : cu.m
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
c. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Plate Compactor (5 hp) 1 1.00


b.Water Truck/Pump (16000L) 1 0.01
Minor tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 1.25 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Filling Materials cu.m. 1.15000


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06

95.10
Hourly Rate Amount

123.00 123.00
2,450.00 24.50
9.51

157.01
252.11

201.69
Unit Cost Amount
0.00
201.69
of G 18.15
of G 16.14
of (G + H + I) 11.80
(G + H + I + J) 247.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(4) Excavation ordered below Plan Elevation


Unit of Measurement : cu.m
Output per hour : 20.00 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Dump Truck (12 cu.yd) 2 1.00 1,420.00 2,840.00


b. Backhoe (0.80 cu.m.) 1 1.00 1,537.00 1,537.00
Minor Tools (10% of Labor Cost) 25.43

Sub-Total for B 4,402.43


C. Total (A + B) 4,656.71
D. Output per hour = 20.00 cu.m
E. Direct Unit Cost (C ÷ D) 232.84
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 232.84
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 20.96
I. Contractor's Profit (CP) 8% of G 18.63
J. Value Added Tax (VAT) 5% of (G + H + I) 13.62
K Total Unit Cost (G + H + I + J) 286.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)a Shoring


Unit of Measurement : ls
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

Sub-Total for B
C. Total (A + B)
D. Output per hour = 1.00 ls
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.404- Reinforcing Steel Bar kg *


b.405- Structural Concrete cu.m *
c.509- Steel Sheet Pile m *

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

-
-

-
Hourly Rate Amount

-
-
-

-
-

-
Unit Cost Amount
0.00
-
of G -
of G -
of (G + H + I) -
(G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)b Cribbing/Cofferdamming


Unit of Measurement : ls
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 160 95.1 15,216.00


b. Skilled Labor 2 160 69.01 22,083.20
c. Unskilled Labor 4 160 53.06

Sub-Total for A 37,299.20


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Crawler Crane (36-40 mt) 1 160.00 1,902.00 304,320.00


b. Vibro hammer (Hydraulic Operated) 1 160.00 2,123.00 339,680.00
c. Welding Machine (300 A),Gas/Diesl Driven 1 40.00 371.00 14,840.00
d.Cutting Outfit 1 40.000 45.45 1,818.00
e.Water Pump,100 mm suctionØ 1 160.000 266.25 42,600.00

Sub-Total for B 703,258.00


C. Total (A + B) 740,557.20
D. Output per hour = 1.00 ls
E. Direct Unit Cost (C ÷ D) 740,557.20
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Steel Sheet Pile kg 69120.00


b.Walling,Bracing,Diagonal,etc. kg 7,323.77
Miscellaneous (1% of Materials Cost)

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 740,557.20
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 66,650.15
I. Contractor's Profit (CP) 8% of G 59,244.58
J. Value Added Tax (VAT) 5% of (G + H + I) 43,322.60
K Total Unit Cost (G + H + I + J) 909,774.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(6) Pipe Culvert and Drainage Excavation


Unit of Measurement : cu.m
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Dump Truck (12 cu.yd) 2 1.00


b. Backhoe (0.80 cu.m.) 1 1.00
Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 20.00 cu.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 159.18

254.28
Hourly Rate Amount

1,420.00 2,840.00
1,537.00 1,537.00
25.43

4,402.43
4,656.71

232.84
Unit Cost Amount
0.00
232.84
of G 20.96
of G 18.63
of (G + H + I) 13.62
(G + H + I + J) 286.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)a Embankment (from Borrow)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 mt), SD100DC 1 1 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
Minor Tooks (10% of Labor) 20.12

Sub-Total for B 4,651.62


C. Total (A + B) 4,852.84
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 97.06
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Common Borrow (w 25% Shrinkage Factor) cu.m. 1.25 275.00 343.75


Sub-Total for F 343.75
g. Direct Unit Cost ( E + F ) 440.81
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 39.67
I. Contractor's Profit (CP) 8% of G 35.26
J. Value Added Tax (VAT) 5% of (G + H + I) 25.79
K Total Unit Cost (G + H + I + J) 541.53
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1b) Embankment from Roadway Excavation


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor
For Excavation Work:
a. Construction Foreman 1 0.83
b. Unskilled Labor 2 0.83

Spreading and Compaction:


a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment
For Excavation Work:
a.Bulldozer, D6H SERIES II PSDS/DD 1 0.83
b.Payloader (1.50 cu.m.) 1 0.83
c.Dump Truck (12 cu.yd.) 2 0.83

Spreading and Compaction:


a. Motorized Road Grader (140 hp), G710A 1 1
b.Vibratory Roller (10 mt),SDC100DC 1 1
c.Water Truck/Pump (16000L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 78.93
53.06 88.08

95.1 95.10
53.06 106.12

368.23
Hourly Rate Amount

3,379.00 2,804.57
1,733.00 1,438.39
1,420.00 2,357.20
-

2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50

11,231.66
11,599.89

232.00
Unit Cost Amount
0.00
232.00
of G 20.88
of G 18.56
of (G + H + I) 13.57
(G + H + I + J) 285.01
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(2) Selected Borrow for topping,case 1


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a.Motorized Road Grader (140 hp), G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 mt), SD100DC 1 1 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
-

Sub-Total for B 4,631.50


C. Total (A + B) 4,832.72
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 96.65
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Selected borrow (w/25% Shrinkage Factor) cu.m 1.25

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 96.65
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.70
I. Contractor's Profit (CP) 8% of G 7.73
J. Value Added Tax (VAT) 5% of (G + H + I) 5.65
K Total Unit Cost (G + H + I + J) 118.74
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(3) Selected Borrow for topping, case 2


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 hp),G710A 1 1


B.Vibratory Roller(10 mt), SD100DC 1 1
c. Water Truck/Pump (16000 L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Selected Borrow (w/25% Shrinkage Factor) cu.m. 1.25


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50
-
-

4,631.50
4,832.72

96.65
Unit Cost Amount
0.00
96.65
of G 8.70
of G 7.73
of (G + H + I) 5.65
(G + H + I + J) 118.74
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(4) Earth Berm


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 307.34


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor (5 hp) 1 1 123.00 123.00


b. Water Truck/Pump (16000 L) 1 0.01 2,450.00 24.50
Minor Tools (10% of Labor Cost) 30.73
-
-

Sub-Total for B 178.23


C. Total (A + B) 485.57
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 388.46
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Filling Materials cu.m 1.25

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 388.46
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 34.96
I. Contractor's Profit (CP) 8% of G 31.08
J. Value Added Tax (VAT) 5% of (G + H + I) 22.72
K Total Unit Cost (G + H + I + J) 477.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(1) Subgrade Preparation (Common Material)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 hp),G710A 1 1


B.Vibratory Roller(10 mt), SD100DC 1 1
c. Water Truck/Pump (16000 L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 300.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50
-
-

4,631.50
4,832.72

16.11
Unit Cost Amount
0.00
16.11
of G 1.45
of G 1.29
of (G + H + I) 0.94
(G + H + I + J) 19.79
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(2) Subgrade Preparation (Existing Pavement)


Unit of Measurement : cu.m.
Output per hour : 300.00 cu.m

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 hp),G710A 1 1 2,173.00 2,173.00


B.Vibratory Roller(10 mt), SD100DC 1 1 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
-
-

Sub-Total for B 4,631.50


C. Total (A + B) 4,832.72
D. Output per hour = 300.00 cu.mcu.m.
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(3) Subgrade Preparation (Unsuitable Material)


Unit of Measurement : sq.m
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 hp),G710A 1 1


b. Vibratory Roller (10 mt),SD100DC 1 1
c. Water Truck/Pump (16000 L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 300.00 sq.m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50
-

4,631.50
4,832.72

16.11
Unit Cost Amount
0.00
16.11
of G 1.45
of G 1.29
of (G + H + I) 0.94
(G + H + I + J) 19.79
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200 Aggregate Subbase Course


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 hp),G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 mt),SD100DC 1 1 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
-

Sub-Total for B 4,631.50


C. Total (A + B) 4,832.72
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 96.65
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Subbase Course cu.m 1.15 475.00 546.25


(w/15% Shrinkage Factor)
Sub-Total for F 546.25
g. Direct Unit Cost ( E + F ) 642.90
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 57.86
I. Contractor's Profit (CP) 8% of G 51.43
J. Value Added Tax (VAT) 5% of (G + H + I) 37.61
K Total Unit Cost (G + H + I + J) 789.81
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200(1) Aggregate Subbase Course(for Intermittent Reblocking)


Unit of Measurement : cu.m.
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt),SD100DC 1 1.00
c.Plate Compactor(5 hp) 1 0.25
d. Water Truck/Pump (16000 L) 1 0

Sub-Total for B
C. Total (A + B)
D. Output per hour = 40.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
a.Aggregate Base Course cu.m 1.15
(w/15% Shrinkage Factor)

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

nt Reblocking)

Hourly Rate Amount

95.1 95.10
53.06 106.12
-
-
-
-
-
-

201.22
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
123.00 30.75
2,450.00 612.50
-
-
-

4,662.25
4,863.47

121.59
Unit Cost Amount
280.00 322.00
-
-
-
-
-

322.00
443.59
of G 39.92
of G 35.49
of (G + H + I) 25.95
(G + H + I + J) 544.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201 Aggregate Base Course


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12
-
-
-
-
-
-

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 hp),G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00 1,846.00 1,846.00
c.Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
-
-
-

Sub-Total for B 4,631.50


C. Total (A + B) 4,832.72
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 96.65
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Base Course cu.m 1.15 280.00 322.00


(w/15% Shrinkage Factor) -
-
-
-
-
Sub-Total for F 322.00
g. Direct Unit Cost ( E + F ) 418.65
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 37.68
I. Contractor's Profit (CP) 8% of G 33.49
J. Value Added Tax (VAT) 5% of (G + H + I) 24.49
K Total Unit Cost (G + H + I + J) 514.32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201(1) Aggregate Base Course(for Reblocking)


Unit of Measurement : cu.m.
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt),SD100DC 1 1.00
c.Plate Compactor(5 hp) 1 0.25
d. Water Truck/Pump (16000 L) 1 0

Sub-Total for B
C. Total (A + B)
D. Output per hour = 40.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials
a.Aggregate Base Course cu.m 1.15
(w/15% Shrinkage Factor)

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12
-
-
-
-
-
-

201.22
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
123.00 30.75
2,450.00 612.50
-
-
-

4,662.25
4,863.47

121.59
Unit Cost Amount
280.00 322.00
-
-
-
-
-

322.00
443.59
of G 39.92
of G 35.49
of (G + H + I) 25.95
(G + H + I + J) 544.95
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202 Crushed Aggregate Base Course


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12
-
-
-
-
-
-

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 mt),SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0 2,450.00 612.50
-
-
-

Sub-Total for B 4,631.50


C. Total (A + B) 4,832.72
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 96.65
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Crushed Aggregate Base Course cu.m 1.15 280.00 322.00


(w/15% Shrinkage Factor) -
-
-
-
-

Sub-Total for F 322.00


g. Direct Unit Cost ( E + F ) 418.65
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 37.68
I. Contractor's Profit (CP) 8% of G 33.49
J. Value Added Tax (VAT) 5% of (G + H + I) 24.49
K Total Unit Cost (G + H + I + J) 514.32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 203 Lime Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 10 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1


b. Vibratory Roller (10 mt), SD100DC 1 1
c. Water Truck/Pump (16000 L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Hydrated Lime, Type N (Normal) bag 2.80


b.Aggregate Base Course cu.m 1.15

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.10 95.10
53.06 530.60

625.70
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50
-

4,631.50
5,257.20

350.48
Unit Cost Amount
0.00
350.48
of G 31.54
of G 28.04
of (G + H + I) 20.50
(G + H + I + J) 430.56
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 204 Portland Cement Stabilized Road Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Unskilled Labor 10 1 53.06 530.60

Sub-Total for A 625.70


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Rad Grader (140 hp), G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 mt), SD100DC 1 1 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
-

Sub-Total for B 4,631.50


C. Total (A + B) 5,257.20
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D) 350.48
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Cement bag 3.00


b.Aggregate Base Course cu.m 1.15

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 350.48
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 31.54
I. Contractor's Profit (CP) 8% of G 28.04
J. Value Added Tax (VAT) 5% of (G + H + I) 20.50
K Total Unit Cost (G + H + I + J) 430.56
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 205 Asphalt Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 10 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Rad Grader (140 hp), G710A 1 1


b. Vibratory Roller (10 mt), SD100DC 1 1
c. Water Truck/Pump (16000 L) 1 0.25
d.Asphalt Distributor 1 1

Sub-Total for B
C. Total (A + B)
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Emulsified Asphalt SS-1 mt 0.07


b.Aggregate Base Course cu.m 1.15

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.10 95.10
53.06 530.60

625.70
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
2.45 0.61
936.00 936.00

4,955.61
5,581.31

372.09
Unit Cost Amount
0.00
372.09
of G 33.49
of G 29.77
of (G + H + I) 21.77
(G + H + I + J) 457.11
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06

Sub-Total for A 233.12


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Batch Plant (30 cu.m) 1 1 1,759.50 879.75


b. Dump Truck(12 cu.yd) 3 1 1,420.00 2,130.00
c. Motorized Road Grader (140 hp), G710A 1 1 2,173.00 1,086.50
d.Vibratory Roller (10 mt),SD100DC 1 1 1,846.00 923.00
e.Payloader (1.50 cu.m),LX80-2C 1 1 1,733.00 866.50
f.Water Truck/Pump (16000 L) 1 0 2,450.00 612.50
g.Asphalt Distributor, 10f wide (5 ton) 1 0.1 936.00 93.60

Sub-Total for B 6,591.85


C. Total (A + B) 6,824.97
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D) 455.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 3.00


b.Aggregate Base Course cu.m 1.15
c.MC 70 Cut-back Asphalt mt 0.01

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 455.00
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 40.95
I. Contractor's Profit (CP) 8% of G 36.40
J. Value Added Tax (VAT) 5% of (G + H + I) 26.62
K Total Unit Cost (G + H + I + J) 558.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(1) Gravel Surface Course(Uncrushed)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 2 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1


b. Vibratory Roller (10 mt),SD100DC 1 1.00
c.Water Truck/Pump(16000 L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Uncrushed Aggregate Surface Course cu.m 1.15


w/ 15% Shrinkage Factor)

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 106.12

201.22
Hourly Rate Amount

2,173.00 2,173.00
1,846.00 1,846.00
2,450.00 612.50

4,631.50
4,832.72

96.65
Unit Cost Amount
0.00
96.65
of G 8.70
of G 7.73
of (G + H + I) 5.65
(G + H + I + J) 118.74
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(2) Crushed Aggregate Surface Course


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 mt),SD100DC 1 1.00 1,846.00 1,846.00
c.Water Truck/Pump(16000 L) 1 0.25 2,450.00 612.50

Sub-Total for B 4,631.50


C. Total (A + B) 4,832.72
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 96.65
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Aggregate Surface Course cu.m 1.15


w/ 15% Shrinkage Factor)

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 96.65
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.70
I. Contractor's Profit (CP) 8% of G 7.73
J. Value Added Tax (VAT) 5% of (G + H + I) 5.65
K Total Unit Cost (G + H + I + J) 118.74
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor,10 f wide (5 ton) 1 1 936.00 936.00


b. Power Broom (2 m wide) 1 1.00 130.54 130.54

Sub-Total for B 1,066.54


C. Total (A + B) 1,320.82
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D) 4,402.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. MC 70 Cut-back Asphalt (w/5% wastage) mt 1.05


Sub-Total for F 0.00
g. Direct Unit Cost ( E + F ) 4,402.73
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 396.25
I. Contractor's Profit (CP) 8% of G 352.22
J. Value Added Tax (VAT) 5% of (G + H + I) 257.56
K Total Unit Cost (G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor,10 f wide (5 ton) 1 1 1,352.00 1,352.00


b. Power Broom (2 m wide) 1 1.00 1,537.00 1,537.00
2,074.95 -
25.43

Sub-Total for B 2,914.43


C. Total (A + B) 3,168.71
D. Output per hour = 0.30 mt mt
E. Direct Unit Cost (C ÷ D) #VALUE!
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt (w/5% wastage) mt 1.05

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) #VALUE!
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G #VALUE!
I. Contractor's Profit (CP) 8% of G #VALUE!
J. Value Added Tax (VAT) 5% of (G + H + I) #VALUE!
K Total Unit Cost (G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Disributor,10 f wide (5 ton) 1 1


b. Power Broom (2m wide) 1 1

Sub-Total for B
C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. RC Cut-back Asphalt (w/5% wastage) mt 1.05


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 159.18
-

254.28
Hourly Rate Amount

936.00 936.00
130.54 130.54

1,066.54
1,320.82

4,402.73
Unit Cost Amount
0.00
4,402.73
of G 396.25
of G 352.22
of (G + H + I) 257.56
(G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18
-

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Disributor,10 f wide (5 ton) 1 1 936.00 936.00


b. Power Broom (2m wide) 1 1 130.54 130.54

Sub-Total for B 1,066.54


C. Total (A + B) 1,320.82
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D) 4,402.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Emulsified Asphalt SS-1(w/5% wastage) mt 1.05


Sub-Total for F 0.00
g. Direct Unit Cost ( E + F ) 4,402.73
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 396.25
I. Contractor's Profit (CP) 8% of G 352.22
J. Value Added Tax (VAT) 5% of (G + H + I) 257.56
K Total Unit Cost (G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(1) Bituminous Seal Coat (Cover aggregates)


Unit of Measurement : mt
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Laborer 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Tandem Steel Roller (10.1 mt), CC421 1 1.00


b.Water Truck/Pump (16000L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 16.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Cover Aggregates mt 1.15


(w/ 15% Shrinkage Factor)

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 159.18
-

254.28
Hourly Rate Amount

1,652.00 1,652.00
2,450.00 612.50
-

2,264.50
2,518.78

157.42
Unit Cost Amount
0.00
157.42
of G 14.17
of G 12.59
of (G + H + I) 9.21
(G + H + I + J) 193.40
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(2) Bituminous Seal Coat ( MC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Laborer 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor,10f wide (5 ton) 1 1.00


b. Power Broom (2m wide) 1 1.00

Sub-Total for B
C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.MC Cut-back Asphalt mt 1.05


(w/5% Wastage)

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 159.18
-

254.28
Hourly Rate Amount

936.00 936.00
130.54 130.54

1,066.54
1,320.82

4,402.73
Unit Cost Amount
0.00
4,402.73
of G 396.25
of G 352.22
of (G + H + I) 257.56
(G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Laborer 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor,10f wide (5 ton) 1 1.00


b. Power Broom (2m wide) 1 1.00

Sub-Total for B
C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.RC Cut-back Asphalt mt 1.05


(w/5% Wastage)

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 159.18
-

254.28
Hourly Rate Amount

936.00 936.00
130.54 130.54
-

1,066.54
1,320.82

4,402.73
Unit Cost Amount
0.00
4,402.73
of G 396.25
of G 352.22
of (G + H + I) 257.56
(G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(4) Bituminous Sea Coat (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Laborer 3 1 53.06 159.18
-

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor,10f wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (2m wide) 1 1.00 130.54 130.54

Sub-Total for B 1,066.54


C. Total (A + B) 1,320.82
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D) 4,402.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Asphalt Cement Penetration Grade 120-150 mt 1.05


(w/5% Wastage)

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 4,402.73
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 396.25
I. Contractor's Profit (CP) 8% of G 352.22
J. Value Added Tax (VAT) 5% of (G + H + I) 257.56
K Total Unit Cost (G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate Grading)


Unit of Measurement : mt
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Laborer 20 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Vibratory Roller, (10 mt), SD100DC 1 1.00


b.Water Truck/Pump (16000L) 1 0.25

Sub-Total for B
C. Total (A + B)
D. Output per hour = 16.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Aggregates mt 1.15
(w/5% Wastage)

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 1,061.20
-

1,156.30
Hourly Rate Amount

1,846.00 1,846.00
2,450.00 612.50

2,458.50
3,614.80

225.93
Unit Cost Amount
0.00
225.93
of G 20.33
of G 18.07
of (G + H + I) 13.22
(G + H + I + J) 277.55
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18
-

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor,10 f wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (2m wide) 1 1.00 130.54 130.54

Sub-Total for B 1,066.54


C. Total (A + B) 1,320.82
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D) 4,402.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Asphalt Cement Penetration Grade 120-150 mt 1.05


(w/5% Wastage)

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 4,402.73
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 396.25
I. Contractor's Profit (CP) 8% of G 352.22
J. Value Added Tax (VAT) 5% of (G + H + I) 257.56
K Total Unit Cost (G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor,10 f wide (5 ton) 1 1


b. Power Broom (2m wide) 1 1.00

Sub-Total for B
C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. MC Cut-back Asphalt (w/5% Wastage) mt 1.05


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

ack Asphalt)

Hourly Rate Amount

95.1 95.10
53.06 159.18

254.28
Hourly Rate Amount

936.00 936.00
130.54 130.54

1,066.54
1,320.82

4,402.73
Unit Cost Amount

465.00 488.25
488.25
4,890.98
of G 440.19
of G 391.28
of (G + H + I) 286.12
(G + H + I + J) 6,008.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Distributor,10 f wide (5 ton) 1 1 936.00 936.00


b. Power Broom (2m wide) 1 1.00 130.54 130.54

Sub-Total for B 1,066.54


C. Total (A + B) 1,320.82
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D) 4,402.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt (w/5% Wastage) mt 1.05 465.00 488.25

Sub-Total for F 488.25


g. Direct Unit Cost ( E + F ) 4,890.98
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 440.19
I. Contractor's Profit (CP) 8% of G 391.28
J. Value Added Tax (VAT) 5% of (G + H + I) 286.12
K Total Unit Cost (G + H + I + J) 6,008.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(5) Bituminous Surface Treatment( Emulsified Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor,10 f wide (5 ton) 1 1


b. Power Broom (2m wide) 1 1.00

Sub-Total for B
C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Emulsified Asphalt SS-1 (w/5% Wastage) mt 1.05


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
53.06 159.18

254.28
Hourly Rate Amount

936.00 936.00
130.54 130.54

1,066.54
1,320.82

4,402.73
Unit Cost Amount

465.00 488.25
488.25
4,890.98
of G 440.19
of G 391.28
of (G + H + I) 286.12
(G + H + I + J) 6,008.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(1) Bituminous Penetration Macadam Pavement (Aggregates)


Unit of Measurement : mt
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 109.19 109.19


b. Unskilled Labor 20 1 61.44 1,228.80

Sub-Total for A 1,337.99


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Vibratory Roller (10 mt),SD100DC 1 1 1,846.00 1,846.00


b. Water Truck/Pump (16000 L) 1 0.25 2,450.00 2,450.00

Sub-Total for B 4,296.00


C. Total (A + B) 5,633.99
D. Output per hour = 16.00 mt
E. Direct Unit Cost (C ÷ D) 352.12
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Aggregates (w/15% Shrinkage Factor) mt 1.15

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 352.12
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 31.69
I. Contractor's Profit (CP) 8% of G 28.17
J. Value Added Tax (VAT) 5% of (G + H + I) 20.60
K Total Unit Cost (G + H + I + J) 432.58
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(2) Bituminous Penetratio Macadam Pavement (Asphalt Cement)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a.Construction Foreman 1 1
b.Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Asphalt Distributor,10 f wide (5 ton) 1 1


b.Power Broom (2m wide) 1 1

Sub-Total for B
C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Asphalt Cement (w/5% Wastage) mt 1.05


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

ent (Asphalt Cement)

Hourly Rate Amount

95.1 95.10
53.06 159.18

254.28
Hourly Rate Amount

936.00 936.00
130.54 130.54

1,066.54
1,320.82

4,402.73
Unit Cost Amount
0.00
4,402.73
of G 396.25
of G 352.22
of (G + H + I) 257.56
(G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(3) Bituminous Penetratio Macadam Pavement (RC Cut-back Asphalt)
Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a.Construction Foreman 1 1 95.1 95.10


b.Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 254.28


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a.Asphalt Distributor,10 f wide (5 ton) 1 1 936.00 936.00


b.Power Broom (2m wide) 1 1 130.54 130.54
-
-

Sub-Total for B 1,066.54


C. Total (A + B) 1,320.82
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D) 4,402.73
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. RC 70 Cut-back Asphalt(w/5% Wastage) mt 1.05

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 4,402.73
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 396.25
I. Contractor's Profit (CP) 8% of G 352.22
J. Value Added Tax (VAT) 5% of (G + H + I) 257.56
K Total Unit Cost (G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt)


Unit of Measurement : mt
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a.Construction Foreman 1 1
b.Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Asphalt Distributor,10 f wide (5 ton) 1 1


b.Power Broom (2m wide) 1 1

Sub-Total for B
C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Emulsified Asphalt SS-1 (w/5% wastage) mt 1.05


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

ment (Emulsified Asphalt)

Hourly Rate Amount

95.1 95.10
53.06 159.18

254.28
Hourly Rate Amount

936.00 936.00
130.54 130.54
-
-

1,066.54
1,320.82

4,402.73
Unit Cost Amount
0.00
4,402.73
of G 396.25
of G 352.22
of (G + H + I) 257.56
(G + H + I + J) 5,408.76
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(a) Bituminous Road Mix Surface Course


Unit of Measurement : mt
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 323.29


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader w/Scarifier, G710A 1 1 2,173.00 2,173.00


b. Tandem Steel Roller (10.1 mt),CC421 1 1 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
d. Asphalt Distributor,10 f wide (5 ton) 1 1 936.00 936.00
e.Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 32.33

Sub-Total for B 5,966.83


C. Total (A + B) 6,290.12
D. Output per hour = 12.00 mt
E. Direct Unit Cost (C ÷ D) 524.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Crushed Gravel mt 1.15 48.00 55.20


b. MC Cut-back Asphalt (7%) mt 0.07 48.00 3.36
c. Hydrated Lime (0.75 %) bag 0.30 0.59

Sub-Total for F 59.15


g. Direct Unit Cost ( E + F ) 583.32
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 52.50
I. Contractor's Profit (CP) 8% of G 46.67
J. Value Added Tax (VAT) 5% of (G + H + I) 34.12
K Total Unit Cost (G + H + I + J) 716.61
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(b) Bituminous Road Mix Surface Course


Unit of Measurement : mt
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 1 1
c. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader w/Scarifier, G710A 1 1


b. Tandem Steel Roller (10.1 mt),CC421 1 1
c. Pneumatic Tire Roller (10 mt) 1 1
d. Asphalt Distributor,10 f wide (5 ton) 1 1
e.Water Truck/Pump (16000 L) 1 0.25
Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 12.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Crushed Gravel mt 1.15


b. MC Cut-back Asphalt (7%) mt 0.10
c. Hydrated Lime (0.75 %) bag 0.30

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
69.01 69.01
53.06 159.18

323.29
Hourly Rate Amount

2,173.00 2,173.00
1,652.00 1,652.00
561.00 561.00
936.00 936.00
2,450.00 612.50
32.33

5,966.83
6,290.12

524.18
Unit Cost Amount

48.00 55.20
48.00 4.80
0.60

60.60
584.78
of G 52.63
of G 46.78
of (G + H + I) 34.21
(G + H + I + J) 718.40
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(1) Aggregates for Bituminos Road Mix surface Course
Unit of Measurement : mt
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b.Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 3 1 53.06 159.18

Sub-Total for A 323.29


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Motorized Road Grader w/Scarifier, G710A 1 1 2,173.00 2,173.00


b. Tandem Steel Roller (10.1),CC421 1 1 1,652.00 1,652.00
c.Pneumatic Tire Roller (10 mt) 1 1.00 561.00 561.00
d.Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 32.33

Sub-Total for B 5,030.83


C. Total (A + B) 5,354.12
D. Output per hour = 12.00 mt
E. Direct Unit Cost (C ÷ D) 446.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Crushed Gravel mt 1.15

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 446.18
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 40.16
I. Contractor's Profit (CP) 8% of G 35.69
J. Value Added Tax (VAT) 5% of (G + H + I) 26.10
K Total Unit Cost (G + H + I + J) 548.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(2) Bituminous Material for Bituminos Road Mix Surface Course
Unit of Measurement : mt
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b.Skilled Labor 1 1
c. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Asphalt Distributor 1 1

Sub-Total for B
C. Total (A + B)
D. Output per hour = 1.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.MC Cut-back Asphalt mt 1.05


Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Mix Surface Course

Hourly Rate Amount

95.1 95.10
69.01 69.01
53.06 159.18

323.29
Hourly Rate Amount

936.00 936.00

936.00
1,259.29

1,259.29
Unit Cost Amount

1.15
0.00
1,259.29
of G 113.34
of G 100.74
of (G + H + I) 73.67
(G + H + I + J) 1,547.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50 mm thk)
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
Laying & Compaction
a. Construction Foreman 1 1 95.1 95.10
b.Skilled Labor 4 1 69.01 276.04
c.Unskilled Labor 8 1 53.06
Batching/Mixing Operation
a.Batching Plant Engineer 1 1.00
b.Mechanical Engineer 1 1.00
c.Electrical Engineer 1 1
d.Unskilled Laboratory Technician 1 1
e.Unskilled Labor 4 1
Sub-Total for A 371.14
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 hp),NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 mt),CC421 1 1 1,652.00 1,652.00
d.Dump Truck (12 cu.yd) 2 1.00 1,420.00 2,840.00
e.Asphalt Batch Plant (60-80 tph) 1 1 4,286.63 4,286.63
f.Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
g.Payloader (1.50 cu.m),LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 37.11

Sub-Total for B 15,392.74


C. Total (A + B) 15,763.88
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 92.03
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Bituminous Material (8%) mt 0.01 400.00 3.92


b.Aggregates,Sand (79%) cu.m. 0.041
c.Aggregates,3/8 (19%) cu.m. 0.010
d.Mineral Filler (7%) bag 0.130
e.Diesel L 1.165

Sub-Total for F 3.92


g. Direct Unit Cost ( E + F ) 95.95
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.64
I. Contractor's Profit (CP) 8% of G 7.68
J. Value Added Tax (VAT) 5% of (G + H + I) 5.61
K Total Unit Cost (G + H + I + J) 117.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(a) Cold Asphalt Plant Mix (50 mm thk)


Unit of Measurement : sq.m.
Output per hour : 171.30 sq.m.

Designation No. of Person No. of Hours Hourly Rate


A. Labor
Laying & Compaction
a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 8 1
Batching/Mixing operation
a. Batching Plant Engineer 1 1
b. Mechanical Engineer 1 1
c.Electrical Engineer 1 1
d.Unskilled Laboratory Technician 1 1
e. Unskilled Labor 4 1
Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Paver (80 hp),NF220BIIVDM 1 1


b. Pneumatic Tire Roller (10 mt) 1 1
c. Tandem Steel Roller (10.1 mt),CC421 1 1
d.Dump Truck (12 cu.yd.) 2 1.00
e.Asphalt Batch Plant (60-80 tph) 1 1
f.Water Truck/Pump (16000 L) 1 1
g.Payloader (1.50 cu.m.),LX80-2C 1 1
Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 171.30 sq.msq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.Emulsified Asphalt (10%) mt 0.01


b.Aggregates,Sand (79%) cu.m. 0.041
c.Aggregates,3/8 (19%) cu.m. 0.010
d.Mineral Filler (7%) bag 0.130
e.Diesel L 1.165

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06

-
-

371.14
Hourly Rate Amount

2,299.00 2,299.00
1,733.00 1,733.00
1,352.00 1,352.00

2,173.00 2,173.00
1,507.00 1,507.00
-

9,064.00
9,435.14

#VALUE!
Unit Cost Amount
0.00
#VALUE!
of G #VALUE!
of G #VALUE!
of (G + H + I) #VALUE!
(G + H + I + J) #VALUE!
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(b) Cold Asphalt Plant Mix (50 mm thk)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
Laying & Compaction
a. Construction Foreman 1 1 95.1 95.10
b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06
Batching/Mixing operation
a. Batching Plant Engineer 1 1 -
b. Mechanical Engineer 1 1 -
c.Electrical Engineer 1 1
d.Unskilled Laboratory Technician 1 1
e. Unskilled Labor 4 1
Sub-Total for A 371.14
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 hp),NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 mt),CC421 1 1 1,652.00 1,652.00
d.Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e.Asphalt Batch Plant (60-80 tph) 1 1 4,286.63 4,286.63
f.Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
g.Payloader (1.50 cu.m.),LX80-2C 1 1 2,173.00 2,173.00
Minor Tools (10% of Labor Cost) 37.11

Sub-Total for B 15,832.74


C. Total (A + B) 16,203.88
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 94.59
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.MC-70 Cut-back Asphalt (7%) mt 0.01


b.Aggregates,Sand (79%) cu.m. 0.041
c.Aggregates,3/8 (19%) cu.m. 0.010
d.Mineral Filler (7%) bag 0.130
e.Diesel L 1.165

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 94.59
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.51
I. Contractor's Profit (CP) 8% of G 7.57
J. Value Added Tax (VAT) 5% of (G + H + I) 5.53
K Total Unit Cost (G + H + I + J) 116.21
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 309 Bituminous Plant Mix (Stockpile Maintenance Mixture)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor
Laying & Compaction
a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 8 1
Batching/Mixing operation
a. Batching Plant Engineer 1 1
b. Mechanical Engineer 1 1
c.Electrical Engineer 1 1
d.Unskilled Laboratory Technician 1 1
e. Unskilled Labor 4 1
Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a.Dump Truck (12 cu.yd.) 2 1.00


b.Asphalt Batch Plant (60-80 tph) 1 1
c.Water Truck/Pump (16000 L) 1 1
d.Payloader (1.50 cu.m.),LX80-2C 1 1
Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a.MC-70 Cut-back Asphalt (7%) mt 0.01


b.Aggregates,Sand (79%) cu.m. 0.041
c.Aggregates,3/8 (19%) cu.m. 0.010
d.Mineral Filler (7%) bag 0.130
e.Diesel L 1.165

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

ance Mixture)

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06

-
-

371.14
Hourly Rate Amount

1,420.00 2,840.00
42,896.63 42,896.63
2,450.00 2,450.00
1,733.00 1,733.00
37.11

49,956.74
50,327.88

293.80
Unit Cost Amount
0.00
293.80
of G 26.44
of G 23.50
of (G + H + I) 17.19
(G + H + I + J) 360.93
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.1) Bituminous Concrete Surface Course (30 mm thk)


Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c.Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 795.62


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 hp),NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 mt),CC421 1 1 1,652.00 1,652.00
d. Water Truck/Pump(16000 L) 1 1.00 2,450.00 2,450.00

Sub-Total for B 6,496.00


C. Total (A + B) 7,291.62
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 25.54
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Bituminous Concrete Surface Course mt 0.07 420.00 31.08


thickness=30mm (w/5% wastage)

Sub-Total for F 31.08


g. Direct Unit Cost ( E + F ) 56.62
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 5.10
I. Contractor's Profit (CP) 8% of G 4.53
J. Value Added Tax (VAT) 5% of (G + H + I) 3.31
K Total Unit Cost (G + H + I + J) 69.56
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.2) Bituminous Concrete Surface Course (40 mm thk)


Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 795.62


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 hp),NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 mt),CC421 1 1 1,652.00 1,652.00
d.Water Truck/Pump (16000 L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost) 79.56

Sub-Total for B 6,575.56


C. Total (A + B) 7,371.18
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 34.42
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Bituminous Concrete Surface Course mt 0.10 420.00 41.16


thickness= 40 mm (w/5% wastage)

Sub-Total for F 41.16


g. Direct Unit Cost ( E + F ) 75.58
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 6.80
I. Contractor's Profit (CP) 8% of G 6.05
J. Value Added Tax (VAT) 5% of (G + H + I) 4.42
K Total Unit Cost (G + H + I + J) 92.85
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.3) Bituminous Concrete Surface course (50 mm thk)


Unit of Measurement : sq.m.
Output per hour : 171.300

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 795.62


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1.00 561.00 561.00
c.Tandem Steel Roller (10.1 mt), CC421 1 1 1,652.00 1,652.00
d. Water Truck/Pump (16000 L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost) 79.56

Sub-Total for B 6,575.56


C. Total (A + B) 7,371.18
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 43.03
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Bituminous Concrete Surface Course mt 0.12 420.00 51.66


thickness = 50 mm (w/5% wastage)
Sub-Total for F 51.66
g. Direct Unit Cost ( E + F ) 94.69
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.52
I. Contractor's Profit (CP) 8% of G 7.58
J. Value Added Tax (VAT) 5% of (G + H + I) 5.54
K Total Unit Cost (G + H + I + J) 116.33
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.1) Bituminous Concrete Surface Course (30 mm thk)


Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount


A. Unskilled Labor
ing Laying & Compaction
a. Construction Foreman 1 1 95.1 95.10
b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48
Batching/Mixing Operation
a. Batching Plant Engineer 1 1.00
b.Mechanical Engineer 1 1.00
c.Electrical Engineer 1 1
d.Unskilled Laboratory Technician 1 1
e.Unskilled Labor 4 1
Sub-Total for A 795.62
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1 1,652.00 1,652.00
d.Dump Truck (12 cu.yd) 2 1.00 1,420.00 2,840.00
e.Asphalt Batch Plant (60-80 tph) 1 1 4,286.63 4,286.63
f.Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
g.Payloader(1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools(10% of Labor Cost) 79.56

Sub-Total for B 15,435.19


C. Total (A + B) 16,230.81
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 1 56.85
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Asphalt Cement (8%) mt 0.01


b.Aggregates,Sand (79%) cu.m. 0.025
c.Aggregates,3/8 (19%) cu.m. 0.006
d.Mineral Filler (7%) bag 0.078
e.Diesel L 0.699

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 56.85
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 5.12
I. Contractor's Profit (CP) 8% of G 4.55
J. Value Added Tax (VAT) 5% of (G + H + I) 3.33
K Total Unit Cost (G + H + I + J) 69.84
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.2) Bituminous Concrete Surface Course


Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
Laying & Compaction
a. Construction Foreman 1 1 95.1 95.10
b. Skilled Labor 4 1 69.01 276.04
c.Unskilled Labor 8 1 53.06
Batching/Mixing Operation
a.Batching Plant Engineer 1 1.00
b.Mechanical Engineer 1 1.00
c.Electrical Engineer 1 1
d.Unskilled Laboratory Technician 1 1
e.Unskilled Labor 4 1
Sub-Total for A 371.14
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80hp),NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 mt) ,CC421 1 1 1,652.00 1,652.00
d.Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e.Asphalt Batch Plant(60-80 tph) 1 1 4,286.63 4,286.63
f.Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
g.Payloader (1.50 cu.m.),LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 37.11

Sub-Total for B 15,392.74


C. Total (A + B) 15,763.88
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 73.62
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Asphalt Cement (8%) mt 0.01


b.Aggregates,Sand (79%) cu.m 0.033
c.Aggregates,3/8 (19%) cu.m 0.008
d.Mineral Filler (7%) bag 0.104
e.Diesel L 0.932

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 73.62
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 6.63
I. Contractor's Profit (CP) 8% of G 5.89
J. Value Added Tax (VAT) 5% of (G + H + I) 4.31
K Total Unit Cost (G + H + I + J) 90.44
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.3) Bituminous Concrete Surface Course (50 mm thk)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor
Laying & Compaction
a. Construction Foreman 1 1 95.1 95.10
b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06
Batching/Mixing Operation
a.Batching Plant Engineer 1 1.00
b.Mechanical Engineer 1 1.00
c.Electrical Engineer 1 1
d.Unskilled Laboratory Technician 1 1
e.Unskilled Labor 4 1
Sub-Total for A 371.14
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Paver (80 hp),NF220BIIVDM 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 mt) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1 1,652.00 1,652.00
d.Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e.Asphalt Batch Plant(60-80 tph) 1 1 4,286.63 4,286.63
f.Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
g.Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 37.11

Sub-Total for B 15,392.74


C. Total (A + B) 15,763.88
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 92.03
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a.Asphalt Cement (8%) mt 0.01


b.Aggregates,Sand (79%) cu.m. 0.041
c.Aggregates,3/8(19%) cu.m. 0.010
d.Mineral Filler(7%) bag 0.130
e.Diesel L 1.165

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 92.03
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.28
I. Contractor's Profit (CP) 8% of G 7.36
J. Value Added Tax (VAT) 5% of (G + H + I) 5.38
K Total Unit Cost (G + H + I + J) 113.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1 PCC Pavement (Plain)- Conventional Method,150 mm thk


Unit of Measurement : sq.m.
Output per hour : 107.33

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c.Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Transit Mixer (5 cu.m.) 4 1


b. Concrete Vibrator 2 1
c. Concrete Batch Plant (30 cu.m.) 1 1
d.Payloader (1.50 cu.m), LX80-2C 1 1.00
e.Concrete Screeder (5.5 hp) 1 1
f.Water Truck/Pump (16000 L) 1 1
g.Concrete Saw (7.5 hp),14" Blade Ø 1 1
h.Bar Cutter,Single Phase 1 1
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 107.33 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg 0.33


b.Curing Compound L 0.290
c.Asphalt Sealant L 0.120
d.Steel Forms (Rental) m 0.460
e.Sand cu.m 0.083
f.Gravel cu.m 0.15
g.Cement bag 1.43
h.Concrete Saw (Diamond Blade 14"Ø) pc 0.00015
i.Pipe Sleeve,1 "Ø m 0.0078
j.Grease/Tar L 0.0015

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

hod,150 mm thk

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

1,318.00 5,272.00
91.25 182.50
1,759.50 1,759.50
1,733.00 1,733.00
545.00 545.00
2,450.00 2,450.00
32.63 32.63
219.75 219.75
50.39

12,244.77
13,252.63

123.48
Unit Cost Amount

580.00 191.40
191.40
314.88
of G 28.34
of G 25.19
of (G + H + I) 18.42
(G + H + I + J) 386.82
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c.1 PCC Pavement (Plain) - Conventional Method, 150 mm. thick
Unit of Measurement : sq.m.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 8 1
c. Unskilled Labor 16 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 2 1
b. Bar Cutter, Single Phase 1 0.05
c. Concrete Saw, Blade ø 14" (7.5 hp) 1 0.10
Minor Tools (5% of Labor)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 12.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.33


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.12
d. Steel Forms (Rental) m 0.46
e. Ready Mix Concrete, 3500 psi cu.m. 0.1500
f. Concrete Saw (diamond blade 14") pc. 0.00015
g. Pipe Sleeve, 1" dia. m 0.0078
h. Grease/Tar L 0.0015

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

thod, 150 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 552.08
53.06 848.96

1,496.14
Hourly Rate Amount

91.25 182.50
219.75 10.99
32.63 3.26
74.81

271.56
1,767.70

147.31
Unit Cost Amount

40.00 13.20
28.00 8.12
44.00 5.28
50.00 23.00
850.00 127.50
8,000.00 1.20
34.33 0.27
300.00 0.45

179.02
326.33
of G 29.37
of G 26.11
of (G + H + I) 19.09
(G + H + I + J) 400.89
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : sq.m.
Output per hour : 107.33

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 2 1
b. Concrete Screeder (5.5 hp) 1 1
c. Concrete Saw (7.5 hp),14" Blade Ø 1 1
d.Bar Cutter, Single Phase 1 0.1
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 107.33 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg 0.33000


b.Curing Compound L 0.29000
c.Asphalt Sealant L 0.12000
d.Steel Forms (Rental) m 0.46000
e.Ready Mix Concrete,3500 psi cu.m 0.15000
f.Concrete Saw (Diamond Blade 14"Ø pc 0.00015
g.Pipe Sleeve,1"Ø m 0.00780
h.Grease/Tar L 0.00150

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

thod, 150 mm thk

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

91.25 182.50
545.00 545.00
32.63 32.63
219.75 21.98
50.39

832.50
1,840.36

17.15
Unit Cost Amount

580.00 191.40
191.40
208.55
of G 18.77
of G 16.68
of (G + H + I) 12.20
(G + H + I + J) 256.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c PCC Pavement (Plain) - Conventional Method, 150 mm. thick
Unit of Measurement : sq.m.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 8 1 69.01 552.08
c. Unskilled Labor 16 1 53.06 848.96

Sub-Total for A 1,496.14


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Concrete Vibrator 2 1 91.25 182.50
d. Bar Cutter, Single Phase 1 0.05 219.75 10.99
e. Concrete Saw, Blade ø 14" (7.5 hp) 1 0.10 32.63 3.26
Minor Tools (5% of Labor Cost) 74.81

Sub-Total for B 566.06


C. Total (A + B) 2,062.20
D. Output per hour = 12.00 sq.m.
E. Direct Unit Cost (C ÷ D) 171.85
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
j. Grease/Tar L 0.0015 300.00 0.45

Sub-Total for F 533.74


g. Direct Unit Cost ( E + F ) 705.59
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 63.50
I. Contractor's Profit (CP) 8% of G 56.45
J. Value Added Tax (VAT) 5% of (G + H + I) 41.28
K Total Unit Cost (G + H + I + J) 866.82
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200 mm. thick
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00


b. Concrete Vibrator 2 1 91.25 182.50
c. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
g. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 12,047.00


C. Total (A + B) 13,054.86
D. Output per hour = 80.50 sq.m.
E. Direct Unit Cost (C ÷ D) 162.17
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.39 40.00 15.60


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.110 850.00 93.50
f. Gravel cu.m. 0.20 650.00 130.00
g. Cement bag 1.90 220.00 418.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1 1/2" dia. m 0.0086 67.67 0.58
j. Grease/Tar L 0.0056 300.00 1.68

Sub-Total for F 696.96


g. Direct Unit Cost ( E + F ) 859.13
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 77.32
I. Contractor's Profit (CP) 8% of G 68.73
J. Value Added Tax (VAT) 5% of (G + H + I) 50.26
K Total Unit Cost (G + H + I + J) 1,055.45
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2.1 PCC Pavement (Plain) - Conventional Method, 200 mm. thick
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 2 1
b. Concrete Screeder (5.5 Hp) 1 1
c. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 80.50 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.39


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.12
d. Steel Forms (Rental) m 0.46
e.Ready Mix Concrete, 3500 psi cu.m. 0.200
f. Concrete Saw (diamond blade 14") pc. 0.00015
g. Pipe Sleeve, 1 1/2" dia. m 0.0086
h. Grease/Tar L 0.0056

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

thod, 200 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

91.25 182.50
545.00 545.00
32.63 32.63
219.75 21.98
50.39

832.50
1,840.36

22.86
Unit Cost Amount

40.00 15.60
28.00 8.12
44.00 5.28
50.00 23.00
850.00 170.00
8,000.00 1.20
67.67 0.58
300.00 1.68

225.46
248.32
of G 22.35
of G 19.87
of (G + H + I) 14.53
(G + H + I + J) 305.07
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230 mm. thick
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00


b. Concrete Vibrator 2 1 91.25 182.50
c. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
g. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 12,047.00


C. Total (A + B) 13,054.86
D. Output per hour = 70.00 sq.m.
E. Direct Unit Cost (C ÷ D) 186.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1265 850.00 107.53
f. Gravel cu.m. 0.23 650.00 149.50
g. Cement bag 2.19 220.00 481.80
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0071 97.00 0.69
j. Grease/Tar L 0.0087 300.00 2.61

Sub-Total for F 796.92


g. Direct Unit Cost ( E + F ) 983.42
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 88.51
I. Contractor's Profit (CP) 8% of G 78.67
J. Value Added Tax (VAT) 5% of (G + H + I) 57.53
K Total Unit Cost (G + H + I + J) 1,208.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3.1 PCC Pavement (Plain) - Conventional Method, 230 mm. thick
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 2 1
b. Concrete Screeder (5.5 Hp) 1 1
c. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 70.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.43


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.12
d. Steel Forms (Rental) m 0.46
e. Ready Mix Concrete, 3500 psi cu.m. 0.2300
f. Concrete Saw (diamond blade 14") pc. 0.00015
g. Pipe Sleeve, 2" dia. m 0.0071
h. Grease/Tar L 0.0087

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

thod, 230 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

91.25 182.50
545.00 545.00
32.63 32.63
219.75 21.98
50.39

832.50
1,840.36

26.29
Unit Cost Amount

40.00 17.20
28.00 8.12
44.00 5.28
50.00 23.00
850.00 195.50
8,000.00 1.20
97.00 0.69
300.00 2.61

253.60
279.89
of G 25.19
of G 22.39
of (G + H + I) 16.37
(G + H + I + J) 343.84
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250 mm. thick
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00


b. Concrete Vibrator 2 1 91.25 182.50
c. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
g. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 12,047.00


C. Total (A + B) 13,054.86
D. Output per hour = 64.40 sq.m.
E. Direct Unit Cost (C ÷ D) 202.72
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1375 850.00 116.88
f. Gravel cu.m. 0.25 650.00 162.50
g. Cement bag 2.38 220.00 523.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
j. Grease/Tar L 0.0095 300.00 2.85

Sub-Total for F 863.50


g. Direct Unit Cost ( E + F ) 1,066.22
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 95.96
I. Contractor's Profit (CP) 8% of G 85.30
J. Value Added Tax (VAT) 5% of (G + H + I) 62.37
K Total Unit Cost (G + H + I + J) 1,309.85
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4.1 PCC Pavement (Plain) - Conventional Method, 250 mm. thick
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 2 1
b. Concrete Screeder (5.5 Hp) 1 1
c. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 64.40 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.45


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.15
d. Steel Forms (Rental) m 0.46
e.Ready Mix Concrete, 3500 psi cu.m. 0.2500
f. Concrete Saw (diamond blade 14") pc. 0.00015
g. Pipe Sleeve, 2" dia. m 0.0078
h. Grease/Tar L 0.0095

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

thod, 250 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

91.25 182.50
545.00 545.00
32.63 32.63
219.75 21.98
50.39

832.50
1,840.36

28.58
Unit Cost Amount

40.00 18.00
28.00 8.12
44.00 6.60
50.00 23.00
850.00 212.50
8,000.00 1.20
97.00 0.76
300.00 2.85

273.03
301.60
of G 27.14
of G 24.13
of (G + H + I) 17.64
(G + H + I + J) 370.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280 mm. thick
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00


b. Concrete Vibrator 2 1 91.25 182.50
c. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
g. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 12,047.00


C. Total (A + B) 13,054.86
D. Output per hour = 57.50 sq.m.
E. Direct Unit Cost (C ÷ D) 227.04
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.154 850.00 130.90
f. Gravel cu.m. 0.28 650.00 182.00
g. Cement bag 2.66 220.00 585.20
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
j. Grease/Tar L 0.0078 300.00 2.34

Sub-Total for F 961.00


g. Direct Unit Cost ( E + F ) 1,188.04
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 106.92
I. Contractor's Profit (CP) 8% of G 95.04
J. Value Added Tax (VAT) 5% of (G + H + I) 69.50
K Total Unit Cost (G + H + I + J) 1,459.50
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5.1 PCC Pavement (Plain) - Conventional Method, 280 mm. thick
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 2 1
b. Concrete Screeder (5.5 Hp) 1 1
c. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 57.50 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.50


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.17
d. Steel Forms (Rental) m 0.46
e. Ready Mix Concrete, 3500 psi cu.m. 0.280
f. Concrete Saw (diamond blade 14") pc. 0.00015
g. Pipe Sleeve, 2" dia. m 0.0078
h. Grease/Tar L 0.0078

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

thod, 280 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

91.25 182.50
545.00 545.00
32.63 32.63
219.75 21.98
50.39

832.50
1,840.36

32.01
Unit Cost Amount

40.00 20.00
28.00 8.12
44.00 7.48
50.00 23.00
850.00 238.00
8,000.00 1.20
97.00 0.76
300.00 2.34

300.90
332.90
of G 29.96
of G 26.63
of (G + H + I) 19.47
(G + H + I + J) 408.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300 mm. thick
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00


b. Concrete Vibrator 2 1 91.25 182.50
c. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
g. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 12,047.00


C. Total (A + B) 13,054.86
D. Output per hour = 53.67 sq.m.
E. Direct Unit Cost (C ÷ D) 243.24
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.165 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0094 97.00 0.91
j. Grease/Tar L 0.0094 300.00 2.82

Sub-Total for F 1,028.22


g. Direct Unit Cost ( E + F ) 1,271.46
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 114.43
I. Contractor's Profit (CP) 8% of G 101.72
J. Value Added Tax (VAT) 12% of (G + H + I) 178.51
K Total Unit Cost (G + H + I + J) 1,666.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6.1 PCC Pavement (Plain) - Conventional Method, 300 mm. thick
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 2 1
b. Concrete Screeder (5.5 Hp) 1 1
c. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 53.67 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.55


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.18
d. Steel Forms (Rental) m 0.46
e. Ready Mix Concrete, 3500 psi cu.m. 0.300
f. Concrete Saw (diamond blade 14") pc. 0.00015
g. Pipe Sleeve, 2" dia. m 0.0094
h. Grease/Tar L 0.0094

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

thod, 300 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

91.25 182.50
545.00 545.00
32.63 32.63
219.75 21.98
50.39

832.50
1,840.36

34.29
Unit Cost Amount

40.00 22.00
28.00 8.12
44.00 7.92
50.00 23.00
850.00 255.00
8,000.00 1.20
97.00 0.91
300.00 2.82

320.97
355.26
of G 31.97
of G 28.42
of (G + H + I) 20.78
(G + H + I + J) 436.44
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1 PCC Pavement (Plain) - Using Concrete Pavement, 230 mm. thick
Unit of Measurement : sq.m.
Output per hour : 90.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 10 1 53.06 530.60

Sub-Total for A 901.74


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50


b. Concrete Paver, COM.III, FOUR-TRACK 1 1 6,765.00 6,765.00
c. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
f. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub-Total for B 18,043.23


C. Total (A + B) 18,944.97
D. Output per hour = 90.00 sq.m.
E. Direct Unit Cost (C ÷ D) 210.50
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Sand cu.m. 0.1265 850.00 107.53
e. Gravel cu.m. 0.23 650.00 149.50
f. Cement bag 2.19 220.00 481.80
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0071 97.00 0.69
i. Grease/Tar L 0.0087 300.00 2.61

Sub-Total for F 773.92


g. Direct Unit Cost ( E + F ) 984.42
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 88.60
I. Contractor's Profit (CP) 8% of G 78.75
J. Value Added Tax (VAT) 5% of (G + H + I) 57.59
K Total Unit Cost (G + H + I + J) 1,209.36
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1.1 PCC Pavement (Plain) - Using Concrete Pavement, 230 mm. thick
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 10 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Paver, COM.III, FOUR-TRACK 1 1


b. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
c. Concrete Vibrator 1 0.10
d. Bar Cutter, Single Phase 1 0.10

Sub-Total for B
C. Total (A + B)
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.43


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.12
d.Ready Mix Concrete, 3500 psi cu.m. 0.23
e. Concrete Saw (diamond blade 14") pc. 0.00015
f. Pipe Sleeve, 2" dia. m 0.0071
g. Grease/Tar L 0.0087

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

avement, 230 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 530.60

901.74
Hourly Rate Amount

6,765.00 6,765.00
32.63 32.63
91.25 9.13
219.75 21.98

6,828.73
7,730.47

77.30
Unit Cost Amount

40.00 17.20
28.00 8.12
44.00 5.28
650.00 149.50
8,000.00 1.20
97.00 0.69
300.00 2.61

184.60
261.90
of G 23.57
of G 20.95
of (G + H + I) 15.32
(G + H + I + J) 321.75
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250 mm. thick
Unit of Measurement : sq.m.
Output per hour : 82.80

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 10 1 53.06 530.60

Sub-Total for A 901.74


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50


b. Concrete Paver, COM.III, FOUR-TRACK 1 1 6,765.00 6,765.00
c. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
f. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub-Total for B 18,043.23


C. Total (A + B) 18,944.97
D. Output per hour = 82.80 sq.m.
E. Direct Unit Cost (C ÷ D) 228.80
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Sand cu.m. 0.1375 850.00 116.88
e. Gravel cu.m. 0.25 650.00 162.50
f. Cement bag 2.38 220.00 523.60
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
i. Grease/Tar L 0.0095 300.00 2.85

Sub-Total for F 840.50


g. Direct Unit Cost ( E + F ) 1,069.31
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 96.24
I. Contractor's Profit (CP) 8% of G 85.54
J. Value Added Tax (VAT) 5% of (G + H + I) 62.55
K Total Unit Cost (G + H + I + J) 1,313.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2.1 PCC Pavement (Plain) - Using Concrete Paver, 250 mm. thick
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 10 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Paver, COM.III, FOUR-TRACK 1 1


b. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
c. Concrete Vibrator 1 0.10
d. Bar Cutter, Single Phase 1 0.10

Sub-Total for B
C. Total (A + B)
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.45


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.15
d. Ready Mix Concrete, 3500 psi cu.m. 0.2500
e. Concrete Saw (diamond blade 14") pc. 0.00015
f. Pipe Sleeve, 2" dia. m 0.0078
g. Grease/Tar L 0.0095

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

aver, 250 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 530.60

901.74
Hourly Rate Amount

6,765.00 6,765.00
32.63 32.63
91.25 9.13
219.75 21.98

6,828.73
7,730.47

77.30
Unit Cost Amount

40.00 18.00
28.00 8.12
44.00 6.60
850.00 212.50
8,000.00 1.20
97.00 0.76
300.00 2.85

250.03
327.33
of G 29.46
of G 26.19
of (G + H + I) 19.15
(G + H + I + J) 402.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280 mm. thick
Unit of Measurement : sq.m.
Output per hour : 73.93

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 10 1 53.06 530.60

Sub-Total for A 901.74


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50


b. Concrete Paver, COM.III, FOUR-TRACK 1 1 6,765.00 6,765.00
c. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
f. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub-Total for B 18,043.23


C. Total (A + B) 18,944.97
D. Output per hour = 73.93 sq.m.
E. Direct Unit Cost (C ÷ D) 256.26
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Sand cu.m. 0.154 850.00 130.90
e. Gravel cu.m. 0.28 650.00 182.00
f. Cement bag 2.66 220.00 585.20
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
i. Grease/Tar L 0.0078 300.00 2.34

Sub-Total for F 938.00


g. Direct Unit Cost ( E + F ) 1,194.25
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 107.48
I. Contractor's Profit (CP) 8% of G 95.54
J. Value Added Tax (VAT) 5% of (G + H + I) 69.86
K Total Unit Cost (G + H + I + J) 1,467.14
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3.1 PCC Pavement (Plain) - Using Concrete Paver, 280 mm. thick
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 10 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Paver, COM.III,FOUR-TRACK 1 1


b. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
c. Concrete Vibrator 1 0.10
d. Bar Cutter, Single Phase 1 0.10

Sub-Total for B
C. Total (A + B)
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.50


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.17
d.Ready Mix Concrete, 3500 psi cu.m. 0.280
e. Concrete Saw (diamond blade 14") pc. 0.00015
f. Pipe Sleeve, 2" dia. m 0.0078
g. Grease/Tar L 0.0078

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

aver, 280 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 530.60

901.74
Hourly Rate Amount

6,765.00 6,765.00
32.63 32.63
91.25 9.13
219.75 21.98

6,828.73
7,730.47

77.30
Unit Cost Amount

40.00 20.00
28.00 8.12
44.00 7.48
850.00 238.00
8,000.00 1.20
97.00 0.76
300.00 2.34

277.90
355.20
of G 31.97
of G 28.42
of (G + H + I) 20.78
(G + H + I + J) 436.36
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300 mm. thick
Unit of Measurement : sq.m.
Output per hour : 69.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 10 1 53.06 530.60

Sub-Total for A 901.74


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Batch Plant (30 cu.m.) 1 1 1,759.50 1,759.50


b. Concrete Paver, COM. III, FOUR-TRACK 1 1 6,765.00 6,765.00
c. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
f. Concrete Saw, Blade ø 14" (7.5 hp) 1 1 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub-Total for B 18,043.23


C. Total (A + B) 18,944.97
D. Output per hour = 69.00 sq.m.
E. Direct Unit Cost (C ÷ D) 274.56
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Sand cu.m. 0.165 850.00 140.25
e. Gravel cu.m. 0.30 650.00 195.00
f. Cement bag 2.85 220.00 627.00
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0094 97.00 0.91
i. Grease/Tar L 0.0094 300.00 2.82

Sub-Total for F 1,005.22


g. Direct Unit Cost ( E + F ) 1,279.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 115.18
I. Contractor's Profit (CP) 8% of G 102.38
J. Value Added Tax (VAT) 5% of (G + H + I) 74.87
K Total Unit Cost (G + H + I + J) 1,572.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4.1 PCC Pavement (Plain) - Using Concrete Paver, 300 mm. thick
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 10 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

b. Concrete Paver, COM III,FOUR-TRACK 1 1


f. Concrete Saw, Blade ø 14" (7.5 hp) 1 1
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

Sub-Total for B
C. Total (A + B)
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 0.55


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.18
d. Ready Mix Concrete, 3500 psi cu.m. 0.300
e. Concrete Saw (diamond blade 14") pc. 0.00015
f. Pipe Sleeve, 2" dia. m 0.0094
g. Grease/Tar L 0.0094

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

aver, 300 mm. thick

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 530.60

901.74
Hourly Rate Amount

6,765.00 6,765.00
32.63 32.63
91.25 9.13
219.75 21.98

6,828.73
7,730.47

77.30
Unit Cost Amount

40.00 22.00
28.00 8.12
44.00 7.92
850.00 255.00
8,000.00 1.20
97.00 0.91
300.00 2.82

297.97
375.28
of G 33.77
of G 30.02
of (G + H + I) 21.95
(G + H + I + J) 461.03
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2) PCC Pavement (Reinforced), 230 mm. thick


Unit of Measurement : sq.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Batch Plant (30 cu.m.) 1 0.10 1,759.50 175.95


b. Concrete Screeder (5.5 Hp) 1 0.10 545.00 54.50
c. Transit Mixer ( 5 cu.m.) 2 0.10 1,318.00 263.60
d. Payloader (1.50 cu.m.), LX80-2C 1 0.10 1,733.00 173.30
e. Water Truck/Pump (16000L) 1 0.10 2,450.00 245.00
f. Concrete Vibrator 1 0.10 91.25 9.13
g. Bar Cutter, Single Phase 1 0.25 219.75 54.94
h. Bar Bender 1 0.25 351.50 87.88
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 1,114.68


C. Total (A + B) 2,122.54
D. Output per hour = 6.00 sq.m.
E. Direct Unit Cost (C ÷ D) 353.76
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reinforcing Steel Bar kg. 54.21 40.00 2,168.40


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m. 0.46 50.00 23.00
e. Sand cu.m. 0.1650 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. # 16 GI Tie Wire (2% of RSB) kg. 1.084 47.00 50.95

Sub-Total for F 3,220.64


g. Direct Unit Cost ( E + F ) 3,574.39
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 321.70
I. Contractor's Profit (CP) 8% of G 285.95
J. Value Added Tax (VAT) 5% of (G + H + I) 209.10
K Total Unit Cost (G + H + I + J) 4,391.14
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2)1 PCC Pavement (Reinforced), 300 mm. thick


Unit of Measurement : sq.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Skilled Labor 4 1
c. Unskilled Labor 12 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Screeder (5.5 Hp) 1 0.10


b. Concrete Vibrator 1 0.10
c. Bar Cutter, Single Phase 1 0.25
d. Bar Bender 1 0.25
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 6.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reinforcing Steel Bar kg. 54.21


b. Curing Compound L 0.29
c. Asphalt Sealant L 0.18
d. Steel Forms (Rental) m. 0.46
e. Ready Mix Concrete,3500 psi kg. 0.300
f.#16 GI Tie Wire (2% of RSB) kg. 1.084

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.1 95.10
69.01 276.04
53.06 636.72

1,007.86
Hourly Rate Amount

545.00 54.50
91.25 9.13
219.75 54.94
351.50 87.88
50.39

256.83
1,264.69

210.78
Unit Cost Amount

40.00 2,168.40
28.00 8.12
44.00 7.92
50.00 23.00
47.00 14.10
2,221.54
2,432.32
of G 218.91
of G 194.59
of (G + H + I) 142.29
(G + H + I + J) 2,988.11
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 404 Reinforcing Steel Bar, Grade 40 (Minor Structures)


Unit of Measurement : kg.
Output per hour : 180.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Cargo Truck (9-10 mt) 1 0.15 1,212.00 181.80

Sub-Total for B 467.43


C. Total (A + B) 1,125.03
D. Output per hour = 180.00 kg.
E. Direct Unit Cost (C ÷ D) 6.25
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Tie Wire (2% of RSB) kg. 0.021 47.00 0.99


b. Reinforcing Steel Bar, Grade 40 kg. 1.05 40.00 42.00
(w/ 5% Wastage)

Sub-Total for F 42.99


g. Direct Unit Cost ( E + F ) 49.24
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 4.43
I. Contractor's Profit (CP) 8% of G 3.94
J. Value Added Tax (VAT) 5% of (G + H + I) 2.88
K Total Unit Cost (G + H + I + J) 60.49
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 405 Structural Concrete Class A (Minor Structures)


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48

Installation/Removal of Formworks
b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 1,496.14


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 1 1 91.25 91.25
c. Water Truck/Pump (16000L)) 1 0.10 2,450.00 245.00
Minor Tools (5% of Labor Cost) 74.81

Sub-Total for B 583.06


C. Total (A + B) 2,079.20
D. Output per hour = 1.40 cu.m.
E. Direct Unit Cost (C ÷ D) 1,485.14
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Lumber, Good - 4 uses bd.f. * 70.00 38.00 665.00


b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. * 1.60 735.00 294.00
c. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. * 0.70 50.00 35.00
d. Cement bag 9.50 220.00 2,090.00
e. Sand cu.m. 0.50 325.00 162.50
f. Gravel cu.m. 1 725.00 725.00

Note:
* Quantities for lumber, plywood and CWN
are dependent on the type of minor structure.
The above-computed quantities are based on
box culvert

Sub-Total for F 3,971.50


g. Direct Unit Cost ( E + F ) 5,456.64
H. Overhead, Contingencies and Miscellaneous (OCM) 7% of G 381.96
I. Contractor's Profit (CP) 8% of G 436.53
J. Value Added Tax (VAT) 5% of (G + H + I) 313.76
K Total Unit Cost (G + H + I + J) 6,588.89
70.00 4
1.60 4
0.70
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)a Pipe Culverts, 610mm dia. (24" Ø)


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 97.78 97.78


b. Skilled Labor 2 0.44 70.64 62.16
c. Unskilled Labor 4 0.44 54.49 95.90

Sub-Total for A 255.85


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.22 1,537.00 338.14


b. Plate Compactor (5 Hp) 1 0.22 123.00 27.06
Minor Tools (10% of Labor Cost) 25.58

Sub-Total for B 390.78


C. Total (A + B) 646.63
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 646.63
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.774 220.00 170.28


b. Sand cu.m. 0.044 325.00 14.30
c. R.C. Pipes (610 mm. dia.) pc. 1 1,000.00 1,000.00
d. Sand Bedding / Selected Sandy Soil cu.m. 0.088 325.00 28.60
Sub-Total for F 1,213.18
g. Direct Unit Cost ( E + F ) 1,859.81
H. Overhead, Contingencies and Miscellaneous (OCM) 15% of G 278.97
I. Contractor's Profit (CP) 10% of G 185.98
J. Value Added Tax (VAT) 5% of (G + H + I) 116.24
K Total Unit Cost (G + H + I + J) 2,441.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)b Pipe Culverts, 760mm dia. (30" Ø)


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 47.55


b. Skilled Labor 2 0.5 69.01 69.01
c. Unskilled Labor 4 0.5 53.06 106.12

Sub-Total for A 222.68


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Plate Compactor (5 Hp) 1 0.25 123.00 30.75
Minor Tools (10% of Labor Cost) 22.27

Sub-Total for B 437.27


C. Total (A + B) 659.95
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 659.95
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.918 220.00 201.96


b. Sand cu.m. 0.052 850.00 44.20
c. R.C. Pipes (760 mm. dia.) pc. 1 1,750.00 1,750.00
d. Sand Bedding / Selected Sandy Soil cu.m. 0.108 850.00 91.80

Sub-Total for F 2,087.96


g. Direct Unit Cost ( E + F ) 2,747.91
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 247.31
I. Contractor's Profit (CP) 8% of G 219.83
J. Value Added Tax (VAT) 5% of (G + H + I) 160.75
K Total Unit Cost (G + H + I + J) 3,375.80
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)c Pipe Culverts, 910mm dia. (36" Ø)


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 54.21


b. Skilled Labor 2 0.57 69.01 78.67
c. Unskilled Labor 4 0.57 53.06 120.98

Sub-Total for A 253.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.29 1,537.00 445.73


b. Plate Compactor (5 Hp) 1 0.29 123.00 35.67
Minor Tools (10% of Labor Cost) 25.39

Sub-Total for B 506.79


C. Total (A + B) 760.64
D. Output per hour = 1.00 m
E. Direct Unit Cost (C ÷ D) 760.64
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.080 220.00 237.60


b. Sand cu.m. 0.061 850.00 51.85
c. R.C. Pipes (910 mm. dia.) pc. 1 2,170.00 2,170.00
d. Sand Bedding / Selected Sandy Soil cu.m. 0.128 850.00 108.80

Sub-Total for F 2,568.25


g. Direct Unit Cost ( E + F ) 3,328.89
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 299.60
I. Contractor's Profit (CP) 8% of G 266.31
J. Value Added Tax (VAT) 5% of (G + H + I) 194.74
K Total Unit Cost (G + H + I + J) 4,089.54
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)d Pipe Culverts, 1070mm dia. (42" Ø)


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 63.72


b. Skilled Labor 2 0.67 69.01 92.47
c. Unskilled Labor 4 0.67 53.06 142.20

Sub-Total for A 298.39


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.33 1,537.00 507.21


b. Plate Compactor (5 Hp) 1 0.33 123.00 40.59
Minor Tools (10% of Labor Cost) 29.84

Sub-Total for B 577.64


C. Total (A + B) 876.03
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 876.03
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.242 220.00 273.24


b. Sand cu.m. 0.070 850.00 59.50
c. R.C. Pipes (1070 mm. dia.) pc. 1 2,900.00 2,900.00
d. Sand Bedding / Selected Sandy Soil cu.m. 0.149 850.00 126.65

Sub-Total for F 3,359.39


g. Direct Unit Cost ( E + F ) 4,235.42
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 381.19
I. Contractor's Profit (CP) 8% of G 338.83
J. Value Added Tax (VAT) 5% of (G + H + I) 247.77
K Total Unit Cost (G + H + I + J) 5,203.21
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)e Pipe Culverts, 1220mm dia. (48" Ø)


Unit of Measurement : m
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 76.08


b. Skilled Labor 2 0.8 69.01 110.42
c. Unskilled Labor 4 0.8 53.06 169.79

Sub-Total for A 356.29


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.40 1,537.00 614.80


b. Plate Compactor (5 Hp) 1 0.40 123.00 49.20
Minor Tools (10% of Labor Cost) 35.63

Sub-Total for B 699.63


C. Total (A + B) 1,055.92
D. Output per hour = 1.00 m
E. Direct Unit Cost (C ÷ D) 1,055.92
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.404 220.00 308.88


b. Sand cu.m. 0.080 850.00 68.00
c. R.C. Pipes (1220 mm. dia.) pc. 1 3,800.00 3,800.00
d. Sand Bedding / Selected Sandy Soil cu.m. 0.170 850.00 144.50

Sub-Total for F 4,321.38


g. Direct Unit Cost ( E + F ) 5,377.30
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 483.96
I. Contractor's Profit (CP) 8% of G 430.18
J. Value Added Tax (VAT) 5% of (G + H + I) 314.57
K Total Unit Cost (G + H + I + J) 6,606.01
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)f Pipe Culverts, 1520mm dia. (60" Ø)


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. UnskilledLabor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00 768.50


b. Plate Compactor (5 Hp) 1 0.50 123.00 61.50
Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 874.54


C. Total (A + B) 1,319.90
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 1,319.90
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.710 220.00 376.20


b. Sand cu.m. 0.097 850.00 82.45
c. R.C. Pipes (1520 mm. dia.) pc. 1 6,175.00 6,175.00
d. Sand Bedding / Selected Sandy Soil cu.m. 0.210 850.00 178.50

Sub-Total for F 6,812.15


g. Direct Unit Cost ( E + F ) 8,132.05
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 731.88
I. Contractor's Profit (CP) 8% of G 650.56
J. Value Added Tax (VAT) 5% of (G + H + I) 475.72
K Total Unit Cost (G + H + I + J) 9,990.22
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(1) Underdrain


Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 76.08


b. Unskilled Labor 4 0.8 53.06 169.79

Sub-Total for A 245.87


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor (5 Hp) 1 0.40 123.00 49.20


Minor Tools (10% of Labor Cost) 24.59

Sub-Total for B 73.79


C. Total (A + B) 319.66
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 319.66
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coarse Aggregates cu.m. 0.20 900.00 180.00


b. Fine Aggregates cu.m. 0.39 850.00 331.50
c. Filter Cloth sq.m. 2 275.00 550.00
d. 150 mm dia. Concrete Perforated Pipe pc. 1.05 230.00 241.50

Sub-Total for F 1,303.00


g. Direct Unit Cost ( E + F ) 1,622.66
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 146.04
I. Contractor's Profit (CP) 8% of G 129.81
J. Value Added Tax (VAT) 5% of (G + H + I) 94.93
K Total Unit Cost (G + H + I + J) 1,993.44
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(2) Blind Drain


Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 307.34


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor Cost) 30.73

Sub-Total for B 30.73


C. Total (A + B) 338.07
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D) 270.46
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coarse Aggregates cu.m. 0.22 900.00 198.00


b. Fine Aggregates cu.m. 0.39 850.00 331.50
c. Filter Cloth sq.m. 2 275.00 550.00

Sub-Total for F 1,079.50


g. Direct Unit Cost ( E + F ) 1,349.96
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 121.50
I. Contractor's Profit (CP) 8% of G 108.00
J. Value Added Tax (VAT) 5% of (G + H + I) 78.97
K Total Unit Cost (G + H + I + J) 1,658.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(3) Granular Backfill filter material for Underdrains


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 307.34


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor (5 Hp) 1 1 123.00 123.00


Minor Tools (10% of Labor Cost) 30.73

Sub-Total for B 153.73


C. Total (A + B) 461.07
D. Output per hour = 1.250 cu.m.
E. Direct Unit Cost (C ÷ D) 368.86
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coarse Aggregates (Granular Backfill Materials) cu.m. 1.15 900.00 1,035.00


(w/ 15% Shrinkage Factor)

Sub-Total for F 1,035.00


g. Direct Unit Cost ( E + F ) 1,403.86
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 126.35
I. Contractor's Profit (CP) 8% of G 112.31
J. Value Added Tax (VAT) 5% of (G + H + I) 82.13
K Total Unit Cost (G + H + I + J) 1,724.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502 Manhole / Catch Basin / Inlet


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

-
-
-

Sub-Total for A -
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

-
-
-
-
-
-
-

Sub-Total for B -
C. Total (A + B) -
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) -
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 103(3) - Foundation Fill cu.m. -


b. 404 - Reinforcing Steel Bar bag -
c. 405 - Structural Concrete cu.m. -

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) -
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G -
I. Contractor's Profit (CP) 8% of G -
J. Value Added Tax (VAT) 5% of (G + H + I) -
K Total Unit Cost (G + H + I + J) -
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(4) Concrete Covers


Unit of Measurement : ea.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 0.50 172.00 86.00


b. Bar Cutter, Single Phase 1 0.50 219.75 109.88
c. Concrete Vibrator 1 0.50 91.25 45.63
d. Welding Machine (300 A), Gas/Diesel Driven 1 0.25 371.00 92.75
e. Water Truck 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 501.29


C. Total (A + B) 946.65
D. Output per hour = 5.00 ea.
E. Direct Unit Cost (C ÷ D) 189.33
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Dimension: 1.29m x 0.57m x 0.20m w/Flat Bar Frame


a. Portland Cement bag 1.43 220.00 314.60
b. Sand cu.m. 0.08 850.00 63.75
c. Gravel cu.m. 0.15 650.00 97.50
d. Reinforcing Steel Bar kg. 46.46 40.00 1,858.40
e. #16 G.I. Tie Wire (2% of RSB) kg. 0.93 47.00 43.71
f. 6mm thk. Steel Plate kg. 73.58 48.00 3,531.84
g. 16mm thk. Steel Plate kg. 2.97 48.00 71.28
h. 1/2" Ordinary Plywood - 2 uses pc. 0.33 620.00 102.30
i. 16mm dia. U-bolt & knot set. 2.00 250.00 250.00
j. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.04 90.00 1.80

Sub-Total for F 6,335.18


g. Direct Unit Cost ( E + F ) 6,524.51
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 587.21
I. Contractor's Profit (CP) 8% of G 521.96
J. Value Added Tax (VAT) 5% of (G + H + I) 381.68
K Total Unit Cost (G + H + I + J) 8,015.36
2
2
2
2
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(5) Metal Frames and Gratings


Unit of Measurement : pair
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0.50 95.1 47.55


b. Skilled Labor 1 0.50 69.01 34.51
c. Unskilled Labor 1 0.50 53.06 26.53

Sub-Total for A 108.59


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

-
-
-
-
-
Minor Tools (10% of Labor Cost) 10.86

Sub-Total for B 10.86


C. Total (A + B) 119.44
D. Output per hour = 1.00 pair
E. Direct Unit Cost (C ÷ D) 119.44
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 410mm x 660mm x 60mm, C.I. Cover with set 1.00 4,700.00 4,700.00
frame

Sub-Total for F 4,700.00


g. Direct Unit Cost ( E + F ) 4,819.44
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 433.75
I. Contractor's Profit (CP) 8% of G 385.56
J. Value Added Tax (VAT) 5% of (G + H + I) 281.94
K Total Unit Cost (G + H + I + J) 5,920.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(6) Metal Frames and Covers (Circular)


Unit of Measurement : pair
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0.50 95.1 47.55


b. Skilled Labor 1 0.50 69.01 34.51
c. Unskilled Labor 1 0.50 53.06 26.53

Sub-Total for A 108.59


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

-
-
-
-
-
Minor Tools (10% of Labor Cost) 10.86

Sub-Total for B 10.86


C. Total (A + B) 119.44
D. Output per hour = 1.00 pair
E. Direct Unit Cost (C ÷ D) 119.44
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 580 mm dia. C.I. Manhole Cover with Frame set 1.00 5,700.00 5,700.00

Sub-Total for F 5,700.00


g. Direct Unit Cost ( E + F ) 5,819.44
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 523.75
I. Contractor's Profit (CP) 8% of G 465.56
J. Value Added Tax (VAT) 5% of (G + H + I) 340.44
K Total Unit Cost (G + H + I + J) 7,149.19
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(a) Drainage Steel Grating with Frame (675mm x 975mm Sump Grating)
Unit of Measurement : set
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 4 95.1 380.40


b. Skilled Labor 1 4 69.01 276.04
c. Unskilled Labor 1 4 53.06 212.24

Sub-Total for A 868.68


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bar Cutter, Single Phase 1 2.00 219.75 439.50


b. Welding Machine (300 A), Gas/Diesel Driven 1 4 371.00 1,484.00

Sub-Total for B 1,923.50


C. Total (A + B) 2,792.18
D. Output per hour = 1.00 set
E. Direct Unit Cost (C ÷ D) 2,792.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 65mm x 5mm Flat Bar kg. 62.657 48.00 3,007.54


b. 6mm dia. X 975mm Twisted Cross Rod kg. 1.244 48.00 59.71
c. 75mm x 75mm x 9mm Angle Bar kg. 38.36 48.00 1,841.28
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.051 90.00 4.59

Sub-Total for F 4,913.12


g. Direct Unit Cost ( E + F ) 7,705.30
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 693.48
I. Contractor's Profit (CP) 8% of G 616.42
J. Value Added Tax (VAT) 5% of (G + H + I) 450.76
K Total Unit Cost (G + H + I + J) 9,465.96
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(b) Drainage Steel Grating with Frame (715mm x 2000mm Trench Grating)
Unit of Measurement : set
Output per hour : 1.000

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 8 95.1 760.80


b. Skilled Labor 1 8 69.01 552.08
c. Unskilled Labor 1 8 53.06 424.48

Sub-Total for A 1,737.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Bar Cutter,Single Phase 1 4.00 219.75 879.00


b. Welding Machine (300 A), Gas/Diesel Driven 1 8 371.00 2,968.00

Sub-Total for B 3,847.00


C. Total (A + B) 5,584.36
D. Output per hour = 1.000 set
E. Direct Unit Cost (C ÷ D) 5,584.36
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 65mm x 5mm Flat Bar kg. 127.066 48.00 6,099.17


b. 6mm dia. X 975mm Twisted Cross Rod kg. 3.174 48.00 152.35
c. 75mm x 75mm x 9mm Angle Bar kg. 41.64 48.00 1,998.72
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.086 90.00 7.74

Sub-Total for F 8,257.98


g. Direct Unit Cost ( E + F ) 13,842.34
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 1,245.81
I. Contractor's Profit (CP) 8% of G 1,107.39
J. Value Added Tax (VAT) 5% of (G + H + I) 809.78
K Total Unit Cost (G + H + I + J) 17,005.31
Amount

Amount

Amount
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)a Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (24" dia.) - 610 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0 95.1 31.38


b. Skilled Labor 2 0 69.01 45.55
c. Unskilled Labor 4 0 53.06 70.04

Sub-Total for A 146.97


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.17 1,537.00 261.29


b. Boom Truck (2-5 mt) 1 0.17 1,017.90 173.04
c. Water Truck/Pump (16000 L) 1 0.08 2,450.00 196.00
Minor Tools (10% of Labor Cost) 14.70

Sub-Total for B 645.03


C. Total (A + B) 792.00
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 792.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 792.00
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 71.28
I. Contractor's Profit (CP) 8% of G 63.36
J. Value Added Tax (VAT) 5% of (G + H + I) 46.33
K Total Unit Cost (G + H + I + J) 972.97
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)b Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (30" dia.) - 760 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0 95.1 38.04


b. Skilled Labor 2 0 69.01 55.21
c. Unskilled Labor 4 0 53.06 84.90

Sub-Total for A 178.14


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.20 1,537.00 307.40


b. Boom Truck (2-5 mt) 1 0.20 1,017.90 203.58
c. Water Truck/Pump (16000 L) 1 0.10 2,450.00 245.00
Minor Tools (10% of Labor Cost) 17.81

Sub-Total for B 773.79


C. Total (A + B) 951.94
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 951.94
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 951.94
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 85.67
I. Contractor's Profit (CP) 8% of G 76.16
J. Value Added Tax (VAT) 5% of (G + H + I) 55.69
K Total Unit Cost (G + H + I + J) 1,169.46
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)c Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (36" dia.) - 910 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 47.55


b. Skilled Labor 2 1 69.01 69.01
c. Unskilled Labor 4 1 53.06 106.12

Sub-Total for A 222.68


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Boom Truck (2-5 mt) 1 0.25 1,017.90 254.48
c. Water Truck/Pump (16000 L) 1 0.13 2,450.00 318.50
Minor Tools (10% of Labor Cost) 22.27

Sub-Total for B 979.49


C. Total (A + B) 1,202.17
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 1,202.17
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 1,202.17
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 108.20
I. Contractor's Profit (CP) 8% of G 96.17
J. Value Added Tax (VAT) 5% of (G + H + I) 70.33
K Total Unit Cost (G + H + I + J) 1,476.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)d Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (42" dia.) - 1070 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 47.55


b. Skilled Labor 2 1 69.01 69.01
c. Unskilled Labor 4 1 53.06 106.12

Sub-Total for A 222.68


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00 384.25


b. Boom Truck (2-5 mt) 1 0.25 1,017.90 254.48
c. Water Truck/Pump (16000 L) 1 0.13 2,450.00 318.50
Minor Tools (10% of Labor Cost) 22.27

Sub-Total for B 979.49


C. Total (A + B) 1,202.17
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 1,202.17
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 1,202.17
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 108.20
I. Contractor's Profit (CP) 8% of G 96.17
J. Value Added Tax (VAT) 5% of (G + H + I) 70.33
K Total Unit Cost (G + H + I + J) 1,476.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)e Removing, Cleaning, Stockpilling Salvaged Culvert Pipe (48" dia.) - 1220 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 63.72


b. Skilled Labor 2 1 69.01 92.47
c. Unskilled Labor 4 1 53.06 142.20

Sub-Total for A 298.39


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.33 1,537.00 507.21


b. Boom Truck (2-25 mt) 1 0.33 1,017.90 335.91
c. Water Truck/Pump (16000 L) 1 0.17 2,450.00 416.50
Minor Tools (10% of Labor Cost) 29.84

Sub-Total for B 1,289.46


C. Total (A + B) 1,587.85
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 1,587.85
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 1,587.85
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 142.91
I. Contractor's Profit (CP) 8% of G 127.03
J. Value Added Tax (VAT) 5% of (G + H + I) 92.89
K Total Unit Cost (G + H + I + J) 1,950.67
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" dia.) - 610 mm
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 63.72


b. Skilled Labor 2 1 69.01 92.47
c. Unskilled Labor 4 1 53.06 142.20

Sub-Total for A 298.39


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.40 1,537.00 614.80


b. Plate Compactor (5 Hp) 1 0.33 123.00 40.59
c. Water Truck/Pump (16000 L) 1 0.10 2,450.00 245.00
Minor Tools (10% of Labor Cost) 29.84

Sub-Total for B 930.23


C. Total (A + B) 1,228.62
D. Output per hour = 1.50 l.m.
E. Direct Unit Cost (C ÷ D) 819.08
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.774 220.00 170.28


b. Sand cu.m. 0.044 850.00 37.40
c. Sand Bedding cu.m. 0.088 850.00 74.80

Sub-Total for F 282.48


g. Direct Unit Cost ( E + F ) 1,101.56
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 99.14
I. Contractor's Profit (CP) 8% of G 88.12
J. Value Added Tax (VAT) 5% of (G + H + I) 64.44
K Total Unit Cost (G + H + I + J) 1,353.27
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" dia.) - 760 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 76.08


b. Skilled Labor 2 1 69.01 110.42
c. Unskilled Labor 4 1 53.06 169.79

Sub-Total for A 356.29


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.48 1,537.00 737.76


b. Plate Compactor (5 Hp) 1 0.40 123.00 49.20
c. Water Truck/Pump (16000 L) 1 0.12 2,450.00 294.00
Minor Tools (10% of Labor Cost) 35.63

Sub-Total for B 1,116.59


C. Total (A + B) 1,472.88
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 1,472.88
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.918 220.00 201.96


b. Sand cu.m. 0.052 850.00 44.20
c. Sand Bedding cu.m. 0.108 850.00 91.80

Sub-Total for F 337.96


g. Direct Unit Cost ( E + F ) 1,810.84
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 162.98
I. Contractor's Profit (CP) 8% of G 144.87
J. Value Added Tax (VAT) 5% of (G + H + I) 105.93
K Total Unit Cost (G + H + I + J) 2,224.61
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" dia.) - 910 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 hp) 1 0.50 123.00 61.50
c. Water Truck/Pump (16000 L) 1 0.15 2,450.00 367.50
Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 1,395.74


C. Total (A + B) 1,841.10
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 1,841.10
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.080 220.00 237.60


b. Sand cu.m. 0.061 850.00 51.85
c. Sand Bedding cu.m. 0.128 850.00 108.80

Sub-Total for F 398.25


g. Direct Unit Cost ( E + F ) 2,239.35
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 201.54
I. Contractor's Profit (CP) 8% of G 179.15
J. Value Added Tax (VAT) 5% of (G + H + I) 131.00
K Total Unit Cost (G + H + I + J) 2,751.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070 mm
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00 922.20


b. Plate Compactor (5 hp) 1 0.50 123.00 61.50
c. Water Truck/Pump (16000 L) 1 0.15 2,450.00 367.50
Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 1,395.74


C. Total (A + B) 1,841.10
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 1,841.10
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.242 220.00 273.24


b. Sand cu.m. 0.070 850.00 59.50
c. Sand Bedding cu.m. 0.149 850.00 126.65

Sub-Total for F 459.39


g. Direct Unit Cost ( E + F ) 2,300.49
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 207.04
I. Contractor's Profit (CP) 8% of G 184.04
J. Value Added Tax (VAT) 5% of (G + H + I) 134.58
K Total Unit Cost (G + H + I + J) 2,826.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220 mmØ
Unit of Measurement : m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 126.48


b. Skilled Labor 2 1 69.01 183.57
c. UnskilledLabor 4 1 53.06 282.28

Sub-Total for A 592.33


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.80 1,537.00 1,229.60


b. Plate Compactor (5 hp) 1 0.67 123.00 82.41
c. Water Truck/Pump (16000 L) 1 0.20 2,450.00 490.00
Minor Tools (10% of Labor Cost) 59.23

Sub-Total for B 1,861.24


C. Total (A + B) 2,453.57
D. Output per hour = 1.00 m.
E. Direct Unit Cost (C ÷ D) 2,453.57
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.404 220.00 308.88


b. Sand cu.m. 0.080 850.00 68.00
c. Sand Bedding cu.m. 0.170 850.00 144.50

Sub-Total for F 521.38


g. Direct Unit Cost ( E + F ) 2,974.95
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 267.75
I. Contractor's Profit (CP) 8% of G 238.00
J. Value Added Tax (VAT) 5% of (G + H + I) 174.03
K Total Unit Cost (G + H + I + J) 3,654.73
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610 mm dia.) - Half Silted
Unit of Measurement : m.
Output per hour : 8.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (9-10 mt) 1 1 1,212.00 1,212.00


b. Steel Wheel with Nylon Rope 1 1.00 300.00 300.00
c. Improvised Bamboo with Bucket 1 1.00 200.00 200.00
Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 1,756.54


C. Total (A + B) 2,201.90
D. Output per hour = 8.00 m.
E. Direct Unit Cost (C ÷ D) 275.24
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 275.24
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 24.77
I. Contractor's Profit (CP) 8% of G 22.02
J. Value Added Tax (VAT) 5% of (G + H + I) 16.10
K Total Unit Cost (G + H + I + J) 338.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760 mm dia.) - Half Silted
Unit of Measurement : m.
Output per hour : 5.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (9-10 mt) 1 1 1,212.00 1,212.00


b. Steel Wheel with Nylon Rope 1 1.00 300.00 300.00
c. Improvised Bamboo with Bucket 1 1.00 200.00 200.00
Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 1,756.54


C. Total (A + B) 2,201.90
D. Output per hour = 5.25 m.
E. Direct Unit Cost (C ÷ D) 419.41
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 419.41
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 37.75
I. Contractor's Profit (CP) 8% of G 33.55
J. Value Added Tax (VAT) 5% of (G + H + I) 24.54
K Total Unit Cost (G + H + I + J) 515.24
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910 mm dia.) - Half Silted
Unit of Measurement : m.
Output per hour : 3.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (9-10 mt) 1 1 1,212.00 1,212.00


Minor Tools (10% of Labor) 44.54

Sub-Total for B 1,256.54


C. Total (A + B) 1,701.90
D. Output per hour = 3.75 m.
E. Direct Unit Cost (C ÷ D) 453.84
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 453.84
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 40.85
I. Contractor's Profit (CP) 8% of G 36.31
J. Value Added Tax (VAT) 5% of (G + H + I) 26.55
K Total Unit Cost (G + H + I + J) 557.54
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070 mm dia.) - Half Silted
Unit of Measurement : m.
Output per hour : 2.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (9-10 mt) 1 1 1,212.00 1,212.00


Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 1,256.54


C. Total (A + B) 1,701.90
D. Output per hour = 2.75 m.
E. Direct Unit Cost (C ÷ D) 618.87
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 618.87
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 55.70
I. Contractor's Profit (CP) 8% of G 49.51
J. Value Added Tax (VAT) 5% of (G + H + I) 36.20
K Total Unit Cost (G + H + I + J) 760.28
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220 mm dia.) - Half Silted
Unit of Measurement : m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (9-10 mt) 1 1 1,212.00 1,212.00


Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 1,256.54


C. Total (A + B) 1,701.90
D. Output per hour = 2.00 m.
E. Direct Unit Cost (C ÷ D) 850.95
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 850.95
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 76.59
I. Contractor's Profit (CP) 8% of G 68.08
J. Value Added Tax (VAT) 5% of (G + H + I) 49.78
K Total Unit Cost (G + H + I + J) 1,045.39
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520 mm dia.) - Half Silted
Unit of Measurement : m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (9-10 mt ) 1 1 1,212.00 1,212.00


Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 1,256.54


C. Total (A + B) 1,701.90
D. Output per hour = 1.50 m.
E. Direct Unit Cost (C ÷ D) 1,134.60
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 1,134.60
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 102.11
I. Contractor's Profit (CP) 8% of G 90.77
J. Value Added Tax (VAT) 5% of (G + H + I) 66.37
K Total Unit Cost (G + H + I + J) 1,393.85
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(4) Reconditioning Drainage Structures


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 0.50 95.1 47.55


b. Skilled Labor 1 0.50 69.01 34.51
c. Unskilled Labor 2 0.50 53.06 53.06

Sub-Total for A 135.12


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (9-10 mt) 1 0.25 1,212.00 303.00


b. Bamboo with Bucket - 4 uses 1 1 200.00 25.00
Minor Tools (10% of Labor Cost) 13.51

Sub-Total for B 341.51


C. Total (A + B) 476.63
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 476.63
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

* If some repair is needed, component


materials required and corresponding man
hour will be added to DUPA

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 476.63
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 42.90
I. Contractor's Profit (CP) 8% of G 38.13
J. Value Added Tax (VAT) 5% of (G + H + I) 27.88
K Total Unit Cost (G + H + I + J) 585.54
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(1) Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (5% of Labor Cost) 32.88

Sub-Total for B 32.88


C. Total (A + B) 690.48
D. Output per hour = 1.50 cu.m.
E. Direct Unit Cost (C ÷ D) 460.32
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Boulders (15 - 25 kg.) cu.m. 1.05 920.00 966.00


Miscellaneous (1% of Materials Cost) 9.66

Sub-Total for F 975.66


g. Direct Unit Cost ( E + F ) 1,435.98
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 129.24
I. Contractor's Profit (CP) 8% of G 114.88
J. Value Added Tax (VAT) 5% of (G + H + I) 84.00
K Total Unit Cost (G + H + I + J) 1,764.10
2
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(2) Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 0.50 922.00 461.00


Minor Tools (5% of Labor Cost) 22.27

Sub-Total for B 483.27


C. Total (A + B) 928.63
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 742.90
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Boulders (30 - 70 kg.) cu.m. 1.05 810.00 850.50


Miscellaneous (1% of Materials Cost) 8.51

Sub-Total for F 859.01


g. Direct Unit Cost ( E + F ) 1,601.91
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 144.17
I. Contractor's Profit (CP) 8% of G 128.15
J. Value Added Tax (VAT) 5% of (G + H + I) 93.71
K Total Unit Cost (G + H + I + J) 1,967.94
2
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(3) Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 0.75 922.00 691.50


Minor Tools (5% of Labor Cost) 22.27

Sub-Total for B 713.77


C. Total (A + B) 1,159.13
D. Output per hour = 1.00 cu.m.
E. Direct Unit Cost (C ÷ D) 1,159.13
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Boulders (50 - 100 kg.) cu.m. 1.05 740.00 777.00


Miscellaneous (1% of Materials Cost) 7.77

Sub-Total for F 784.77


g. Direct Unit Cost ( E + F ) 1,943.90
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 174.95
I. Contractor's Profit (CP) 8% of G 155.51
J. Value Added Tax (VAT) 5% of (G + H + I) 113.72
K Total Unit Cost (G + H + I + J) 2,388.08
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(4) Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) 1 1.00 922.00 922.00


Minor Tools (5% of Labor Cost) 22.27

Sub-Total for B 944.27


C. Total (A + B) 1,389.63
D. Output per hour = 0.75 cu.m.
E. Direct Unit Cost (C ÷ D) 1,852.84
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Boulders (100 - 200 kg.) cu.m. 1.05 650.00 682.50


Miscellaneous (1% of Materials Cost) 6.83

Sub-Total for F 689.33


g. Direct Unit Cost ( E + F ) 2,542.16
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 228.79
I. Contractor's Profit (CP) 8% of G 203.37
J. Value Added Tax (VAT) 5% of (G + H + I) 148.72
K Total Unit Cost (G + H + I + J) 3,123.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(5) Grouted Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskillled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
Minor Tools (5% of Labor Cost) 32.88

Sub-Total for B 327.38


C. Total (A + B) 984.98
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 787.98
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 3.00 220.00 660.00


b. Sand cu.m. 0.25 850.00 212.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders ( 15 - 25 kg.) cu.m. 1.05 920.00 966.00
Miscellaneous (1% of Materials Cost) 18.96

Sub-Total for F 1,914.73


g. Direct Unit Cost ( E + F ) 2,702.72
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 243.24
I. Contractor's Profit (CP) 8% of G 216.22
J. Value Added Tax (VAT) 5% of (G + H + I) 158.11
K Total Unit Cost (G + H + I + J) 3,320.29
1,895.78
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(6) Grouted Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.50 922.00 461.00
Minor Tools (5% of Labor Cost) 22.27

Sub-Total for B 777.77


C. Total (A + B) 1,223.13
D. Output per hour = 1.00 cu.m.
E. Direct Unit Cost (C ÷ D) 1,223.13
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 2.50 220.00 550.00


b. Sand cu.m. 0.21 850.00 178.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders ( 30 - 70 kg.) cu.m. 1.05 810.00 850.50
Miscellaneous (1% of Materials Cost) 16.36

Sub-Total for F 1,652.64


g. Direct Unit Cost ( E + F ) 2,875.77
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 258.82
I. Contractor's Profit (CP) 8% of G 230.06
J. Value Added Tax (VAT) 5% of (G + H + I) 168.23
K Total Unit Cost (G + H + I + J) 3,532.88
1,636.28
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(7) Grouted Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck/Pump ( 16000L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.75 922.00 691.50
Minor Tools (5% of Labor Cost) 22.27

Sub-Total for B 1,008.27


C. Total (A + B) 1,453.63
D. Output per hour = 0.75 cu.m.
E. Direct Unit Cost (C ÷ D) 1,938.17
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 2.20 220.00 484.00


b. Sand cu.m. 0.18 850.00 153.00
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders ( 60 - 100 kg.) cu.m. 1.05 730.00 766.50
Miscellaneous (1% of Materials Cost) 14.61

Sub-Total for F 1,475.38


g. Direct Unit Cost ( E + F ) 3,413.55
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 307.22
I. Contractor's Profit (CP) 8% of G 273.08
J. Value Added Tax (VAT) 5% of (G + H + I) 199.69
K Total Unit Cost (G + H + I + J) 4,193.55
2
4

1,460.78
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(8) Grouted Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 1 922.00 922.00
Minor Tools (5% of Labor Cost) 22.27

Sub-Total for B 1,238.77


C. Total (A + B) 1,684.13
D. Output per hour = 0.50 cu.m.
E. Direct Unit Cost (C ÷ D) 3,368.26
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 1.80 220.00 396.00


b. Sand cu.m. 0.15 850.00 127.50
c. Gravel Fill cu.m. 0.015 650.00 9.75
d. Weep Holes (PVC) m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders ( 100 - 200 kg.) cu.m. 1.05 650.00 682.50
Miscellaneous (1% of Materials Cost) 12.63

Sub-Total for F 1,275.91


g. Direct Unit Cost ( E + F ) 4,644.16
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 417.97
I. Contractor's Profit (CP) 8% of G 371.53
J. Value Added Tax (VAT) 5% of (G + H + I) 271.68
K Total Unit Cost (G + H + I + J) 5,705.36
1,263.28
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(9) Filter Layer of Granular Material


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor Cost)

Sub-Total for B
C. Total (A + B) 270.23
D. Output per hour = 1.00 cu.m.
E. Direct Unit Cost (C ÷ D) 270.23
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Granular Materials cu.m. 1.05 900.00 945.00

Sub-Total for F 945.00


g. Direct Unit Cost ( E + F ) 1,215.23
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 109.37
I. Contractor's Profit (CP) 8% of G 97.22
J. Value Added Tax (VAT) 5% of (G + H + I) 71.09
K Total Unit Cost (G + H + I + J) 1,492.91
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 506 Stone Masonry


Unit of Measurement : cu.m.
Output per hour : 1.6000

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck ( 1000 gal.) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 922.00 92.20
Minor Tools (10% of Labor) 65.76

Sub-Total for B 452.46


C. Total (A + B) 1,110.06
D. Output per hour = 1.6000 cu.m.
E. Direct Unit Cost (C ÷ D) 693.79
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 5.50 220.00 1,210.00


b. Sand cu.m. 0.30 850.00 255.00
c. Gravel Fill cu.m. 0.02 650.00 13.00
d. Weep Holes (PVC) m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders cu.m. 1.05 920.00 966.00
Miscellaneous (1% of Materials Cost) 24.92

Sub-Total for F 2,516.44


g. Direct Unit Cost ( E + F ) 3,210.23
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 288.92
I. Contractor's Profit (CP) 8% of G 256.82
J. Value Added Tax (VAT) 5% of (G + H + I) 187.80
K Total Unit Cost (G + H + I + J) 3,943.77
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 507 Rubble Concrete


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 922.00 92.20
Minor Tools (10% of Labor Cost) 65.76

Sub-Total for B 452.46


C. Total (A + B) 1,110.06
D. Output per hour = 1.40 cu.m.
E. Direct Unit Cost (C ÷ D) 792.90
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 4.20 220.00 924.00


b. Sand cu.m. 0.2625 850.00 223.13
c. Gravel Fill cu.m. 0.02 650.00 13.00
d. Weep Holes (PVC) m. 0.30 144.67 43.40
e. Filter Cloth sq.m. 0.015 275.00 4.13
f. Boulders cu.m. 0.63 810.00 510.30
g. Gravel cu.m. 0.525 650.00 341.25
Miscellaneous (2% of Materials) 36.72

Note: 60% Boulder


50% Class "B" Concrete (w/ side forms only)

Sub-Total for F 2,095.92


g. Direct Unit Cost ( E + F ) 2,888.82
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 259.99
I. Contractor's Profit (CP) 8% of G 231.11
J. Value Added Tax (VAT) 5% of (G + H + I) 169.00
K Total Unit Cost (G + H + I + J) 3,548.92
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 508 Hand Laid Rock Embankment


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor Cost) 65.76

Sub-Total for B 65.76


C. Total (A + B) 723.36
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 231.48
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Boulders cu.m. 1.05 920.00 966.00

Sub-Total for F 966.00


g. Direct Unit Cost ( E + F ) 1,197.48
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 107.77
I. Contractor's Profit (CP) 8% of G 95.80
J. Value Added Tax (VAT) 5% of (G + H + I) 70.05
K Total Unit Cost (G + H + I + J) 1,471.10
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(a) Timber Sheet Pile


Unit of Measurement : m
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Truck Mounted Crane (41-45 mt) 1 1 2,606.00 2,606.00


b. Drop Hammer ( 15 mt ) 1 1 200.00 200.00
Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 2,833.02


C. Total (A + B) 3,103.25
D. Output per hour = 4.00 m
E. Direct Unit Cost (C ÷ D) 775.81
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Timber Sheet Piles, ave. dia. 395mm bd.f. 52.25 40.00 2,090.00
b. Coco Log - 2 uses m. 1.00 350.00 175.00
c. Lumber (Falsework) 4 - uses bd.f. 16.00 40.00 160.00
d. Nail/Spike (1 kg./100 bd.f. of Lumber) kg. 0.16 68.00 10.88

Sub-Total for F 2,435.88


g. Direct Unit Cost ( E + F ) 3,211.69
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 289.05
I. Contractor's Profit (CP) 8% of G 256.94
J. Value Added Tax (VAT) 5% of (G + H + I) 187.88
K Total Unit Cost (G + H + I + J) 3,945.57
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b) Steel Sheet Pile (Slope Protection)


Unit of Measurement : m
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Crawler Crane ( 36 - 40 mt ) 1 1 1,902.00 1,902.00


b. Vibro Hammer (Hydraulic Operated) 1 1 2,123.00 2,123.00
c. Welding Machine(300 A),Gas/Diesel Driven 1 0.25 371.00 92.75
d. Cutting Outfit 1 0.25 45.45 11.36
-

Sub-Total for B 4,129.11


C. Total (A + B) 4,574.47
D. Output per hour = 10.00 m
E. Direct Unit Cost (C ÷ D) 457.45
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Steel Sheet Piles (48 kg./m. kg. 48.00 48.00 2,304.00


c. Miscellaneous (3% of Materials Cost) 23.04

Sub-Total for F 2,327.04


g. Direct Unit Cost ( E + F ) 2,784.49
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 250.60
I. Contractor's Profit (CP) 8% of G 222.76
J. Value Added Tax (VAT) 5% of (G + H + I) 162.89
K Total Unit Cost (G + H + I + J) 3,420.74
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven - 0.50 mx 0.35 m
Unit of Measurement : m
Output per hour : 1.38

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 6 1 69.01 414.06
c. Unskilled Labor 6 1 53.06 318.36

Sub-Total for A 827.52


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a.Truck Mounted Crane (41-45 mt) 1 0.23 2,606.00 599.38


b. Diesel Hammer (K25 or equivalent 1 0.13 172.00 22.36
c. One Bagger Mixer 1 0.15 172.00 25.80
d.Concrete Vibrator 1 0.15 91.25 13.69
e.Water Truck/Pump (16000L) 1 0.01 219.75 2.20
f.Bar Cutter, Single Phase 1 0.20 351.50 70.30
g.Bar Bender 1 0.20 351.50 70.30
h.Drop Hammer 1 0.13 200.00 26.00
i.Jack Hammer 2 0.01 150.00 3.00
j.Air Compressor (356-450 cfm) 1 0.01 965.00 9.65
k.Plate Compactor (5 hp) 1 0.01 123.00 1.23
Minor Tools (5% of Labor Cost)

Sub-Total for B 843.91


C. Total (A + B) 1,671.43
D. Output per hour = 1.38 m
E. Direct Unit Cost (C ÷ D) 1,211.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
a.Coco Log m 0.71
b. Reinforcing Steel Bar kg. 41.64 40.00 1,665.60
c. Cement bag 1.66 220.00 365.20
d. Sand cu.m. 0.09 850.00 76.50
e. Gravel cu.m. 0.18 650.00 117.00
f. Marine Plywood, 1/2" x 4' x 8' -4 uses pc. 0.24 700.00 168.00
g. Good Lumber -4 uses bd.f. 18.59 40.00 743.60
h. # 16 GI Tire Wire (2% of RSB) kg. 0.830 47.00 39.01
i.Spike (1 kg/100 bd.f.of Lumber) kg. 0.060
j. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.19 68.00 12.92
Casting Bed
a. Ready Mix Concrete cu.m. 0.030 2,840.00 85.20
b. Coco Lumber - 4 uses bd.f. 1.500 20.00 7.50
c. Base Course cu.m. 0.030 530.00 15.90

Sub-Total for F 3,296.43


g. Direct Unit Cost ( E + F ) 4,507.61
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 405.68
I. Contractor's Profit (CP) 8% of G 360.61
J. Value Added Tax (VAT) 5% of (G + H + I) 263.70
K Total Unit Cost (G + H + I + J) 5,537.60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(1) Bed Course Granular Material


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 307.34


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor 1 1 123.00 123.00


Minor Tools (10% of Labor Cost) 30.73

Sub-Total for B 153.73


C. Total (A + B) 461.07
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 368.86
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00 667.00


(w/ 15% Shrinkage Factor)

Sub-Total for F 667.00


g. Direct Unit Cost ( E + F ) 1,035.86
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 93.23
I. Contractor's Profit (CP) 8% of G 82.87
J. Value Added Tax (VAT) 5% of (G + H + I) 60.60
K Total Unit Cost (G + H + I + J) 1,272.55
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(2) Concrete Slope Protection


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48
Installation of Formworks & Rebars
a. Skilled Labor 2 1 69.01 138.02
b. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 1,145.88


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Water Truck/Pump (16000 L) 1 0.05 2,450.00 122.50
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 922.00 92.20
d. Concrete Vibrator 1 0.50 91.25 45.63
e. Bar Cutter,Single Phase 1 0.05 219.75 10.99
f. Bar Bender 1 0.05 351.50 17.58
Minor Tools (10% Labor Cost) 114.59

Sub-Total for B 575.48


C. Total (A + B) 1,721.36
D. Output per hour = 1.00 cu.m.
E. Direct Unit Cost (C ÷ D) 1,721.36
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 8.40 220.00 1,848.00


b. Sand cu.m. 0.50 850.00 425.00
c. Weep Holes (PVC) m. 0.21 144.67 30.38
d. Filter Cloth sq.m. 0.015 275.00 4.13
e. Gravel cu.m. 1 650.00 650.00
f. Granular Filter cu.m. 0.016 650.00 10.40
g. Reinforcing Steel Bar kg. 26.03 40.00 1,041.20
h. Marine Plywood 1/2" x 4' x 8' - 4 uses pc. 0.48 700.00 84.00
i. Lumber - 4 uses bd.f. 18.76 40.00 187.60
j. # 16 GI Tie Wire (2% of RSB) kg. 0.521 47.00 24.49
k. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.188 68.00 12.78
Sub-Total for F 4,317.98
g. Direct Unit Cost ( E + F ) 6,039.33
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 543.54
I. Contractor's Profit (CP) 8% of G 483.15
J. Value Added Tax (VAT) 5% of (G + H + I) 353.30
K Total Unit Cost (G + H + I + J) 7,419.32
* Note: RSB quantity is variable based on approved plan
*26.03
4
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(1) Gabions


Unit of Measurement : cu.m.
Output per hour : 2.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be
separate as the quantity is variable

Sub-Total for B -
C. Total (A + B) 657.60
D. Output per hour = 2.50 cu.m.
E. Direct Unit Cost (C ÷ D) 263.04
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Gabion Wire Mesh ( 1m x 1m x 2m ) pc. 0.50 2,900.00 1,450.00


(with complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub-Total for F 2,416.00


g. Direct Unit Cost ( E + F ) 2,679.04
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 241.11
I. Contractor's Profit (CP) 8% of G 214.32
J. Value Added Tax (VAT) 5% of (G + H + I) 156.72
K Total Unit Cost (G + H + I + J) 3,291.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(2) Mattresses


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be
separate as the quantity is variable.

Sub-Total for B -
C. Total (A + B) 657.60
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D) 210.43
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Mattresses ( 6m x 2m x 0.3m ) pc. 0.28 5,000.00 1,400.00


(with complete accessories)
b. Boulders cu.m. 1.05 920.00 966.00

Sub-Total for F 2,366.00


g. Direct Unit Cost ( E + F ) 2,576.43
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 231.88
I. Contractor's Profit (CP) 8% of G 206.11
J. Value Added Tax (VAT) 5% of (G + H + I) 150.72
K Total Unit Cost (G + H + I + J) 3,165.15
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(3) Filter Cloth


Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt) 1 0.25 1,212.00 303.00

Sub-Total for B 303.00


C. Total (A + B) 960.60
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D) 9.61
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Filter Cloth sq.m. 1.05 275.00 288.75


Miscellaneous (5% of Materials Cost) 14.44

Sub-Total for F 303.19


g. Direct Unit Cost ( E + F ) 312.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 28.15
I. Contractor's Profit (CP) 8% of G 25.02
J. Value Added Tax (VAT) 12% of (G + H + I) 43.92
K Total Unit Cost (G + H + I + J) 409.88
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(1) Concrete Curb (Cast in place) - 0.45m x 0.15/0.20m


Unit of Measurement : m
Output per hour : 17.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 795.62


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 1 91.25 91.25


b. One Bagger Mixer 1 1 172.00 172.00
c. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 79.56

Sub-Total for B 465.31


C. Total (A + B) 1,260.93
D. Output per hour = 17.50 m
E. Direct Unit Cost (C ÷ D) 72.05
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 0.72 220.00 158.40


b. Sand cu.m. 0.04 850.00 34.00
c. Gravel cu.m. 0.08 650.00 52.00
d. Plywood Marine, 1/2" thk. X 4' x 8 - 4 uses pc. 0.28 700.00 49.00
e. Form Lumber - 4 uses bd.f. 12.16 40.00 121.60
f. Assorted CWN (1 kg./100 kg. bd.f. of Lumber) kg. 0.12 68.00 8.16

Sub-Total for F 423.16


g. Direct Unit Cost ( E + F ) 495.21
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 44.57
I. Contractor's Profit (CP) 8% of G 39.62
J. Value Added Tax (VAT) 5% of (G + H + I) 28.97
K Total Unit Cost (G + H + I + J) 608.37
4
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(2) Concrete Gutter (Cast in place) - 0.50m x 0.15m


Unit of Measurement : m
Output per hour : 17.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 795.62


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 1 91.25 91.25


b. One Bagger Mixer 1 1 172.00 172.00
c. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 79.56

Sub-Total for B 465.31


C. Total (A + B) 1,260.93
D. Output per hour = 17.50 m
E. Direct Unit Cost (C ÷ D) 72.05
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 0.72 220.00 158.40


b. Sand cu.m. 0.04 850.00 34.00
c. Gravel cu.m. 0.08 650.00 52.00
d. Good Lumber - 4 uses bd.f. 3.28 40.00 32.80
e. Assorted CWN (1 kg./100 kg. bd.f. of Lumber) kg. 0.03 68.00 2.04
f.Reinforcing Steel bar kg. 0.84

Sub-Total for F 279.24


g. Direct Unit Cost ( E + F ) 351.29
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 31.62
I. Contractor's Profit (CP) 8% of G 28.10
J. Value Added Tax (VAT) 5% of (G + H + I) 20.55
K Total Unit Cost (G + H + I + J) 431.56
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road
Unit of Measurement : m
Output per hour : 10.30

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 795.62


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 1 91.25 91.25


b. One Bagger Mixer 1 1 172.00 172.00
c. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 79.56

Sub-Total for B 465.31


C. Total (A + B) 1,260.93
D. Output per hour = 10.30 m
E. Direct Unit Cost (C ÷ D) 122.42
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 1.29 220.00 283.80


b. Sand cu.m. 0.07 850.00 59.50
c. Gravel cu.m. 0.14 650.00 91.00
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc. 0.24 700.00 42.00
e. Form Lumber - 4 uses bd.f. 11.47 40.00 114.70
f. Assorted CWN (1 kg./100 kg. bd.f. of Lumber) kg. 0.11 68.00 7.48
Miscellaneous (2% of Materials) 11.97

Sub-Total for F 610.45


g. Direct Unit Cost ( E + F ) 732.87
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 65.96
I. Contractor's Profit (CP) 8% of G 58.63
J. Value Added Tax (VAT) 5% of (G + H + I) 42.87
K Total Unit Cost (G + H + I + J) 900.33
4
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(4) Concrete Curb (Precast)


Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 1 1 53.06 53.06

Sub-Total for A 217.17


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Boom Truck (2-5 mt) 1 0.50 1,017.00 508.50


Minor Tools (10% of Labor Cost) 21.72

Sub-Total for B 530.22


C. Total (A + B) 747.39
D. Output per hour = 4.00 pc.
E. Direct Unit Cost (C ÷ D) 186.85
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Concrete Curb m 1.00 690.00 690.00


Miscellaneous (5% of Materials Cost) 34.50

Sub-Total for F 724.50


g. Direct Unit Cost ( E + F ) 911.35
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 82.02
I. Contractor's Profit (CP) 8% of G 72.91
J. Value Added Tax (VAT) 5% of (G + H + I) 53.31
K Total Unit Cost (G + H + I + J) 1,119.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(5) Concrete Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 1 1 53.06 53.06

Sub-Total for A 217.17


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Boom Truck (2-5 mt) 1 0.50 1,017.00 508.50


Minor Tools (10% of Labor Cost) 21.72

Sub-Total for B 530.22


C. Total (A + B) 747.39
D. Output per hour = 4.00 pc.
E. Direct Unit Cost (C ÷ D) 186.85
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Concrete Gutter m 1.00 680.00 680.00


Miscellaneous (5% of Materials Cost) 34.00

Sub-Total for F 714.00


g. Direct Unit Cost ( E + F ) 900.85
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 81.08
I. Contractor's Profit (CP) 8% of G 72.07
J. Value Added Tax (VAT) 12% of (G + H + I) 126.48
K Total Unit Cost (G + H + I + J) 1,180.47
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(6) Concrete Curb and Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 1 1 53.06 53.06

Sub-Total for A 217.17


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Boom Truck (2-5 mt) 1 0.50 1,017.00 508.50


Minor Tools (10% of Labor Cost) 21.72

Sub-Total for B 530.22


C. Total (A + B) 747.39
D. Output per hour = 3.00 pc.
E. Direct Unit Cost (C ÷ D) 249.13
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Concrete Curb and Gutter m 1.00 1,750.00 1,750.00


Miscellaneous (5% of Materials Cost) 87.50

Sub-Total for F 1,837.50


g. Direct Unit Cost ( E + F ) 2,086.63
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 187.80
I. Contractor's Profit (CP) 8% of G 166.93
J. Value Added Tax (VAT) 5% of (G + H + I) 122.07
K Total Unit Cost (G + H + I + J) 2,563.42
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(a) Sidewalk (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 161.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Transit Mixer ( 5 cu.m.) 4 1 1,318.00 5,272.00


b. Concrete Vibrator 2 1 91.25 182.50
c. Batching Plant (30 cu.m.) 1 1 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
f. Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 32.63 32.63
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 12,025.02


C. Total (A + B) 13,032.88
D. Output per hour = 161.00 sq.m.
E. Direct Unit Cost (C ÷ D) 80.95
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Curing Compound L 0.29 28.00 8.12


b. Asphalt Sealant L 0.12 44.00 5.28
c. Forms m 0.46 250.00 115.00
d. Sand cu.m 0.055 850.00 46.75
e. Gravel cu.m 0.10 650.00 65.00
f. Cement bag 0.95 220.00 209.00

Note: Bed Course excluded

Sub-Total for F 449.15


g. Direct Unit Cost ( E + F ) 530.10
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 47.71
I. Contractor's Profit (CP) 8% of G 42.41
J. Value Added Tax (VAT) 12% of (G + H + I) 74.43
K Total Unit Cost (G + H + I + J) 694.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(b) Sidewalk (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 4 1 69.01 276.04
c. Unskilled Labor 12 1 53.06 636.72

Sub-Total for A 1,007.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 2 1 91.25 182.50
c. Water Truck/Pump (16000 L) 1 0.125 2,450.00 306.25
d. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 32.63 32.63
Minor Tools (5% of Labor Cost) 50.39

Sub-Total for B 743.77


C. Total (A + B) 1,751.63
D. Output per hour = 20.00 sq.m.
E. Direct Unit Cost (C ÷ D) 87.58
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Curing Compound L 0.29 28.00 8.12


b. Asphalt Sealant L 0.12 44.00 5.28
c. Forms m 0.46 250.00 115.00
d. Sand cu.m 0.055 850.00 46.75
e. Gravel cu.m 0.10 650.00 65.00
f. Cement bag 0.95 220.00 209.00

Note: Bed Course excluded

Sub-Total for F 449.15


g. Direct Unit Cost ( E + F ) 536.73
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 48.31
I. Contractor's Profit (CP) 8% of G 42.94
J. Value Added Tax (VAT) 5% of (G + H + I) 31.40
K Total Unit Cost (G + H + I + J) 659.37
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)a Right-of-Way Monument


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 0.20 91.25 18.25


b. Cargo Truck ( 9-10 mt ) 1 0.05 1,212.00 60.60
Minor Tools ( 10% of Labor Cost ) 27.02

Sub-Total for B 105.87


C. Total (A + B) 376.10
D. Output per hour = 2.00 ea.
E. Direct Unit Cost (C ÷ D) 188.05
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Class "A" cu.m 0.03 3,538.78 106.16


b. Reinforcing Steel Bar, Grade 40 kg. 7.15 40.00 286.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00 38.50
d. Form Lumber, Good - 4 uses bd.f. 13.53 40.00 135.30
e. Reflectorized Paint, Marker L 0.10 475.00 47.50
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
g. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.14 68.00 9.52

Sub-Total for F 629.56


g. Direct Unit Cost ( E + F ) 817.61
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 73.59
I. Contractor's Profit (CP) 8% of G 65.41
J. Value Added Tax (VAT) 5% of (G + H + I) 47.83
K Total Unit Cost (G + H + I + J) 1,004.44
4
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)b Right-of-Way Monument (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labo 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt ) 1 0.05 1,212.00 60.60


Minor Tools ( 10% of Labor Cost) 27.02

Sub-Total for B 87.62


C. Total (A + B) 357.85
D. Output per hour = 4.00 ea.
E. Direct Unit Cost (C ÷ D) 89.46
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Right-of-Way Monument ea. 1 3,320.00 3,320.00


(delivered at site)

Sub-Total for F 3,320.00


g. Direct Unit Cost ( E + F ) 3,409.46
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 306.85
I. Contractor's Profit (CP) 8% of G 272.76
J. Value Added Tax (VAT) 5% of (G + H + I) 199.45
K Total Unit Cost (G + H + I + J) 4,188.53
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)a Maintenance Marker Post


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Concrete Vibrator 1 0.20 91.25 18.25


b. Cargo Truck ( 9-10 mt ) 1 0.05 1,212.00 60.60
Minor Tools ( 10% of Labor Cost ) 27.02

Sub-Total for B 105.87


C. Total (A + B) 376.10
D. Output per hour = 2.00 ea.
E. Direct Unit Cost (C ÷ D) 188.05
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Class "A" cu.m 0.03 3,400.00 102.00


b. Reinforcing Steel Bar, Grade 40 kg. 7.00 40.00 280.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00 38.50
d. Form Lumber, Good - 4 uses bd.f. 13.53 40.00 135.30
e. Reflectorized Paint, Marker L 0.10 475.00 47.50
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
g. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.14 68.00 9.52

Sub-Total for F 619.40


g. Direct Unit Cost ( E + F ) 807.45
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 72.67
I. Contractor's Profit (CP) 8% of G 64.60
J. Value Added Tax (VAT) 5% of (G + H + I) 47.24
K Total Unit Cost (G + H + I + J) 991.95
4
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)b Maintenance Marker Post (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt ) 1 0.05 1,212.00 60.60


Minor Tools ( 10% of Labor Cost) 27.02

Sub-Total for B 87.62


C. Total (A + B) 357.85
D. Output per hour = 4.00 ea.
E. Direct Unit Cost (C ÷ D) 89.46
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Maintenance Marker Post ea. 1 1,650.00 1,650.00


(delivered at site)

Sub-Total for F 1,650.00


g. Direct Unit Cost ( E + F ) 1,739.46
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 156.55
I. Contractor's Profit (CP) 8% of G 139.16
J. Value Added Tax (VAT) 5% of (G + H + I) 101.76
K Total Unit Cost (G + H + I + J) 2,136.93
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)a Kiliometer Post


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1.50 95.1 142.65


b. Skilled Labor 1 1.50 69.01 103.52
c. Unskilled Labor 2 1.50 53.06 159.18

Sub-Total for A 405.35


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt ) 1 0.50 1,212.00 606.00


b. Concrete Vibrator 1 0.10 91.25 9.13
Minor Tools ( 10% of Labor Cost) 40.53

Sub-Total for B 655.66


C. Total (A + B) 1,061.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 1,061.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Concrete Class "A" cu.m 0.184 3,400.00 625.60


b. Reinforcing Steel Bar kg. 7.59 40.00 303.60
c. Plywood, 1/2" x 4' x 8' - 2 uses pc. 0.604 700.00 211.40
d. Lumber- 2 uses bd.f. 7.15 20.00 71.50
e. Portland Cement bag 0.775 220.00 170.50
f. Pebble cu.m. 0.044 900.00 39.60
g. Reflectorized Paint, Marker L 0.20 475.00 95.00
h. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00 6.58
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.07 68.00 4.76

Sub-Total for F 1,528.54


g. Direct Unit Cost ( E + F ) 2,589.54
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 233.06
I. Contractor's Profit (CP) 8% of G 207.16
J. Value Added Tax (VAT) 5% of (G + H + I) 151.49
K Total Unit Cost (G + H + I + J) 3,181.26
2
2
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)b Kiliometer Post (Precast)


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1.50 95.1 142.65


b. Skilled Labor 1 1.50 69.01 103.52
c. Unskilled Labor 2 1.50 53.06 159.18

Sub-Total for A 405.35


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt ) 1 0.50 1,212.00 606.00


b. Concrete Vibrator 1 0.05 91.25 4.56
Minor Tools ( 10% of Labor Cost) 40.53

Sub-Total for B 651.10


C. Total (A + B) 1,056.44
D. Output per hour = 2.00 ea.
E. Direct Unit Cost (C ÷ D) 528.22
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fabricated Kilometer Post eac. 1 4,150.00 4,150.00


b. Concrete Class "A" cu.m. 0.095 3,400.00 323.00
c. Reflectorized Paint, Marker L 0.20 475.00 95.00

Sub-Total for F 4,568.00


g. Direct Unit Cost ( E + F ) 5,096.22
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 458.66
I. Contractor's Profit (CP) 8% of G 407.70
J. Value Added Tax (VAT) 5% of (G + H + I) 298.13
K Total Unit Cost (G + H + I + J) 6,260.71
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(4) Guide Post


Unit of Measurement : ea.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools ( 10% of Labor Cost) 20.12

Sub-Total for B 20.12


C. Total (A + B) 221.34
D. Output per hour = 50.00 ea.
E. Direct Unit Cost (C ÷ D) 4.43
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Guide Post (Portable) ea. 1 1,240.00 1,240.00


b. Post Reflector ea. 1 85.00 85.00
Miscellaneous (5% of Materials Cost) 66.25

Sub-Total for F 1,391.25


g. Direct Unit Cost ( E + F ) 1,395.68
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 125.61
I. Contractor's Profit (CP) 8% of G 111.65
J. Value Added Tax (VAT) 5% of (G + H + I) 81.65
K Total Unit Cost (G + H + I + J) 1,714.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(1) Cable Wire Guardrail


Unit of Measurement : m.
Output per hour : 1.15

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 657.60


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 1 0 91.25 22.81
c. Water Truck/Pump (16000 L) 1 0.10 2,450.00 245.00
d. Cargo Truck ( 2-5 mt ) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost) 65.76

Sub-Total for B 701.32


C. Total (A + B) 1,358.92
D. Output per hour = 1.15 m.
E. Direct Unit Cost (C ÷ D) 1,181.67
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 4.18 220.00 919.60


b. Sand cu.m. 0.22 850.00 187.00
c. Gravel cu.m. 0.43 650.00 279.50
d. Guardrail Post set 0.27 1,800.00 486.00
e. Galvanized Wire Rope (1.21 kg./m.) kg. 4.92 186.44 917.28
f. Check Rope set 0.22 750.00 165.00
g. Hook Bolt ea. 0.33 350.00 115.50
h. Anchor Bracket unit 0.11 1,200.00 132.00
i. Wire Mesh sq.m. 0.11 295.00 32.45
j. Tension Fittings set 0.65 1,000.00 650.00
Miscellaneous (5% of Materials Cost) 194.22

Sub-Total for F 4,078.55


g. Direct Unit Cost ( E + F ) 5,260.22
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 473.42
I. Contractor's Profit (CP) 8% of G 420.82
J. Value Added Tax (VAT) 5% of (G + H + I) 307.72
K Total Unit Cost (G + H + I + J) 6,462.18
1,107
2
2
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Post
Unit of Measurement : m.
Output per hour : 4.20

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 0.50 172.00 86.00


b. Concrete Vibrator 1 0.50 91.25 45.63
c. Water Truck/Pump (16000 L) 1 0.05 2,450.00 122.50
d. Cargo Truck ( 9-10 mt ) 1 0.25 1,212.00 303.00
Minor Tools (5% of Labor Cost) 22.27

Sub-Total for B 579.39


C. Total (A + B) 1,024.75
D. Output per hour = 4.20 m.
E. Direct Unit Cost (C ÷ D) 243.99
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 0.33 220.00 72.60


b. Sand cu.m. 0.018 850.00 15.30
c. Gravel cu.m. 0.036 650.00 23.40
d. Metal Beam Guardrail m. 1 1,950.00 1,950.00
e. Plywood Marine, 1/2 thk. X 4' x 8' - 4 uses pc. 0.25 700.00 43.75
f. Lumber - 4 - uses bd.f. 8 40.00 80.00
g. Reinforcing Steel Bars, Grade 40 kg. 4 40.00 160.00
h. Tie Wire (2% of RSB) kg. 0.08 47.00 3.76
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44
j. Bolt, Nut & Washer 5/8" dia. x 9" pc. 0.50 28.00 14.00
k. Bolt, Nut & Washer 5/8" dia. X 1" pc. 2 21.00 42.00

Sub-Total for F 2,410.25


g. Direct Unit Cost ( E + F ) 2,654.24
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 238.88
I. Contractor's Profit (CP) 8% of G 212.34
J. Value Added Tax (VAT) 5% of (G + H + I) 155.27
K Total Unit Cost (G + H + I + J) 3,260.73
4
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3)b Metal Beam End Piece


Unit of Measurement : ea.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Skilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt ) 1 1 1,212.00 1,212.00


Minor Tools (5% of Labor Cost) 13.51

Sub-Total for B 1,225.51


C. Total (A + B) 1,495.74
D. Output per hour = 6.00 ea.
E. Direct Unit Cost (C ÷ D) 249.29
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Metal Guardrail End Piece ea. 1.00 1,350.00 1,350.00

Sub-Total for F 1,350.00


g. Direct Unit Cost ( E + F ) 1,599.29
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 143.94
I. Contractor's Profit (CP) 8% of G 127.94
J. Value Added Tax (VAT) 5% of (G + H + I) 93.56
K Total Unit Cost (G + H + I + J) 1,964.73
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(4) Guardrail (Timber)


Unit of Measurement : l.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 4 1 53.06 212.24

Sub-Total for A 445.36


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt ) 1 0.50 1,212.00 606.00


Minor Tools (10% of Labor Cost) 44.54

Sub-Total for B 650.54


C. Total (A + B) 1,095.90
D. Output per hour = 5.00 l.m.
E. Direct Unit Cost (C ÷ D) 219.18
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Lumber 8" x 8" x 5.5' Treated Post (Tanguile) bd.f. 14.67 90.00 1,320.30
b. Lumber, 3" x 8" Plank (Tanguile) Untreated bd.f. 6.67 55.00 366.85
c. Carriage Bolt, 1/2"Ø x 12" pc. 1.60 350.00 560.00
Miscellaneous (5% of Materials) 112.36

Note: Exclude Excavation Works

Sub-Total for F 2,359.51


g. Direct Unit Cost ( E + F ) 2,578.69
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 232.08
I. Contractor's Profit (CP) 8% of G 206.29
J. Value Added Tax (VAT) 5% of (G + H + I) 150.85
K Total Unit Cost (G + H + I + J) 3,167.92
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(1) Fencing (Barbed Wire) - Type 1


Unit of Measurement : m
Output per hour : 18.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Welding Machine (300 A), Gas/Diesel Driven 1 0.10 371.00 37.10


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 64.12


C. Total (A + B) 334.35
D. Output per hour = 18.00 m
E. Direct Unit Cost (C ÷ D) 18.58
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 3-Standard Galvanized Barbed Wire, Ga 12.5 m. 1 15.00 15.00


b. 50mm x 50mm x 6m Angle Bar kg. 0.58 48.00 27.84
c. Ga. 9 Twisted Wire Fastener pc. 0.39 81.15 31.65
Miscellaneous (2% of Materials Cost, Welding Rod & etc.) 1.49

Sub-Total for F 75.98


g. Direct Unit Cost ( E + F ) 94.55
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.51
I. Contractor's Profit (CP) 8% of G 7.56
J. Value Added Tax (VAT) 5% of (G + H + I) 5.53
K Total Unit Cost (G + H + I + J) 116.16
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(2) Fencing (Chain Link Fence Fabric) - Type 1


Unit of Measurement : m
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Welding Machine(300 A), Gas/Diesel Driven 1 0.50 371.00 185.50


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 212.52


C. Total (A + B) 482.75
D. Output per hour = 6.00 m
E. Direct Unit Cost (C ÷ D) 80.46
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cyclone Wire 8' Ga 10 m 1.000 220.00 220.00


b. 38 mm x 38 mm x 4mm Angle Bar kg 9.250 850.00 7,862.50
c.Welding Rod (1 kg/2000 kg of Steel) kg 0.005 650.00 3.25
404.29

Sub-Total for F 8,490.04


g. Direct Unit Cost ( E + F ) 8,570.50
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 771.34
I. Contractor's Profit (CP) 8% of G 685.64
J. Value Added Tax (VAT) 5% of (G + H + I) 501.37
K Total Unit Cost (G + H + I + J) 10,528.85
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(3) Fencing (Post) - Type 1


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1.50 95.1 142.65


b. Skilled Labor 2 1.50 69.01 207.03
c. Unskilled Labor 2 1.50 53.06 159.18

Sub-Total for A 508.86


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. One Bagger Mixer 1 0.75 172.00 129.00


b. Bar Cutter,Single Phase 1 0.50 219.75 109.88
c. Bar Bender 1 0.50 351.50 175.75
d. Water Truck/Pump ( 16000 L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor Cost) 50.89

Sub-Total for B 588.01


C. Total (A + B) 1,096.87
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 1,096.87
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Cement bag 5.680 220.00 1,249.60


b. Sand cu.m. 0.300 850.00 255.00
c. Gravel cu.m. 0.600 650.00 390.00
d. Reinforcing Steel Bar kg. 22.070 40.00 882.80
e. # 16 Tie Wire (2% of RSB) kg. 0.440 47.00 20.68
f. Plywood 1/4' x 4' x 8' - 2 uses pc. 1.940 350.00 339.50
g. Lumber - 2 uses bd.f. 28.670 20.00 286.70
h. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.290 68.00 19.72

Sub-Total for F 3,444.00


g. Direct Unit Cost ( E + F ) 4,540.87
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 408.68
I. Contractor's Profit (CP) 8% of G 363.27
J. Value Added Tax (VAT) 5% of (G + H + I) 265.64
K Total Unit Cost (G + H + I + J) 5,578.46
2
2
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(4) Fencing (Gates) - (Height 3m. & Length 4.24m.)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 3 95.1 285.30


b. Skilled Labor 1 3 69.01 207.03
c. Unskilled Labor 2 3 53.06 318.36

Sub-Total for A 810.69


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Welding Machine (300 A), Gas/Diesel Driven 1 2 371.00 742.00


Minor Tools (10% of Labor Cost) 81.07

Sub-Total for B 823.07


C. Total (A + B) 1,633.76
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 1,633.76
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. 50 mm. Ø G.I. Pipe, Schedule 40 pc. 5 1,550.00 7,750.00


b. Cyclone Wire Galvanized 10' Gauge 10 m 4.24 3,300.00 13,992.00
d. 6mm Ø Plain Bar kg. 3.370 -
Miscellaneous (3% of Materials Cost,Gate Lock,Hinge & etc. -
-

Sub-Total for F 21,742.00


g. Direct Unit Cost ( E + F ) 23,375.76
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 2,103.82
I. Contractor's Profit (CP) 8% of G 1,870.06
J. Value Added Tax (VAT) 5% of (G + H + I) 1,367.48
K Total Unit Cost (G + H + I + J) 28,717.12
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1)a Danger/Warning Signs ( 60cm Triangle )


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b.Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 2,800.00 2,800.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 4,903.79


g. Direct Unit Cost ( E + F ) 5,396.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 485.71
I. Contractor's Profit (CP) 8% of G 431.74
J. Value Added Tax (VAT) 5% of (G + H + I) 315.71
K Total Unit Cost (G + H + I + J) 6,629.96
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1)b Danger/Warning Signs ( 90cm Triangle )


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b.Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 4,200.00 4,200.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 6,303.79


g. Direct Unit Cost ( E + F ) 6,796.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 611.71
I. Contractor's Profit (CP) 8% of G 543.74
J. Value Added Tax (VAT) 5% of (G + H + I) 397.61
K Total Unit Cost (G + H + I + J) 8,349.86
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)a Regulatory Signs (60cm. Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b.Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 2,800.00 2,800.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 4,903.79


g. Direct Unit Cost ( E + F ) 5,396.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 485.71
I. Contractor's Profit (CP) 8% of G 431.74
J. Value Added Tax (VAT) 5% of (G + H + I) 315.71
K Total Unit Cost (G + H + I + J) 6,629.96
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)b Regulatory Signs (90cm. Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b.Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 4,200.00 4,200.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 6,303.79


g. Direct Unit Cost ( E + F ) 6,796.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 611.71
I. Contractor's Profit (CP) 8% of G 543.74
J. Value Added Tax (VAT) 5% of (G + H + I) 397.61
K Total Unit Cost (G + H + I + J) 8,349.86
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)c Regulatory Signs (60cm. Octagon)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b.Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 70.78 141.56
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 4,500.00 4,500.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 6,649.35


g. Direct Unit Cost ( E + F ) 7,142.35
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 642.81
I. Contractor's Profit (CP) 8% of G 571.39
J. Value Added Tax (VAT) 5% of (G + H + I) 417.83
K Total Unit Cost (G + H + I + J) 8,774.38
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)d Regulatory Signs (90cm. Octagon)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b.Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 7,500.00 7,500.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 9,603.79


g. Direct Unit Cost ( E + F ) 10,096.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 908.71
I. Contractor's Profit (CP) 8% of G 807.74
J. Value Added Tax (VAT) 5% of (G + H + I) 590.66
K Total Unit Cost (G + H + I + J) 12,403.91
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)a Informative Signs (12" x 24")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.320 220.00 290.40


b.Sand cu.m. 0.073 850.00 62.05
C. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 2,750.00 2,750.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 5,141.14


g. Direct Unit Cost ( E + F ) 5,634.14
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 507.07
I. Contractor's Profit (CP) 8% of G 450.73
J. Value Added Tax (VAT) 5% of (G + H + I) 329.60
K Total Unit Cost (G + H + I + J) 6,921.54
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)b Informative Signs (12" x 48")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Uskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.320 220.00 290.40


b.Sand cu.m. 0.073 850.00 62.05
C. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 5,450.00 5,450.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 7,841.14


g. Direct Unit Cost ( E + F ) 8,334.14
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 750.07
I. Contractor's Profit (CP) 8% of G 666.73
J. Value Added Tax (VAT) 5% of (G + H + I) 487.55
K Total Unit Cost (G + H + I + J) 10,238.49
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)c Informative Signs (18" x 24")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. UnskilledLabor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.320 220.00 290.40


b.Sand cu.m. 0.073 850.00 62.05
C. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 3,750.00 3,750.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 6,141.14


g. Direct Unit Cost ( E + F ) 6,634.14
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 597.07
I. Contractor's Profit (CP) 8% of G 530.73
J. Value Added Tax (VAT) 5% of (G + H + I) 388.10
K Total Unit Cost (G + H + I + J) 8,150.04
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)d Informative Signs (18" x 48")


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Laborer 1 1 69.01 69.01
c. Laborer 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 5 T ) 1 0.25 712.00 178.00


Minor Tools (10% of Labor) 27.02

Sub-Total for B 205.02


C. Total (A + B) 475.25
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 475.25
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 1.320 220.00 290.40


b.Sand cu.m. 0.073 850.00 62.05
C. Gravel cu.m. 0.145 650.00 94.25
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 3"Ø G.I. Pipe m. 3.10 530.00 1,643.00
f. Plate kg. 2 48.00 96.00
g. Bolts, 5mm Ø pc. 12 10.00 120.00
h. Sing Face, 3mm thk. Aluminum Sheet pc. 1 8,200.00 8,200.00
i. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44

Sub-Total for F 10,591.14


g. Direct Unit Cost ( E + F ) 11,066.39
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 995.98
I. Contractor's Profit (CP) 8% of G 885.31
J. Value Added Tax (VAT) 12% of (G + H + I) 1,553.72
K Total Unit Cost (G + H + I + J) 14,501.40
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(1) Pavement Marking (Premix Reflectorized)


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2- 5 mt ) 1 0.05 783.00 39.15


Minor Tools (5% of Labor Cost) 13.51

Sub-Total for B 52.66


C. Total (A + B) 322.89
D. Output per hour = 10.00 sq.m.
E. Direct Unit Cost (C ÷ D) 32.29
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Pavement Markings (White) L 1.00 450.00 450.00


Miscellaneous (5% of Materials Cost) 22.50

Sub-Total for F 472.50


g. Direct Unit Cost ( E + F ) 504.79
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 45.43
I. Contractor's Profit (CP) 8% of G 40.38
J. Value Added Tax (VAT) 5% of (G + H + I) 29.53
K Total Unit Cost (G + H + I + J) 620.13
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)a Pavement Marking (Reflectorized Traffic Paint - White)


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.05 783.00 39.15


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 66.17


C. Total (A + B) 336.40
D. Output per hour = 10.00 sq.m.
E. Direct Unit Cost (C ÷ D) 33.64
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reflectorized Traffic Paint (White) L 1.00 450.00 450.00


Miscellaneous (5% of above) 22.50

Sub-Total for F 472.50


g. Direct Unit Cost ( E + F ) 506.14
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 45.55
I. Contractor's Profit (CP) 8% of G 40.49
J. Value Added Tax (VAT) 5% of (G + H + I) 29.61
K Total Unit Cost (G + H + I + J) 621.79
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)b Pavement Markings (Reflectorized Traffic Paint - Yellow)


Unit of Measurement : sq.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.05 783.00 39.15


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 66.17


C. Total (A + B) 336.40
D. Output per hour = 10.00 sq.m.
E. Direct Unit Cost (C ÷ D) 33.64
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Reflectorized Traffic Paint (Yellow) L 1.00 475.00 475.00


Miscellaneous (5% of Materials Cost) 23.75

Sub-Total for F 498.75


g. Direct Unit Cost ( E + F ) 532.39
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 47.92
I. Contractor's Profit (CP) 8% of G 42.59
J. Value Added Tax (VAT) 5% of (G + H + I) 31.14
K Total Unit Cost (G + H + I + J) 654.04
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 607(1) Reflective Pavement Studs (4" RPM)


Unit of Measurement : ea.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Diamond Drill, CP-8 with attachment 1 1


b. Cargo Truck ( 2-5 mt ) 1 0.25
c. Air Compressor (15-35 cfm) 1 1
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 10.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reflective Stud Catcheye Raised Surface pc. 1


100mm x 100mm (type depends on the req.)
b. Concrete Epoxy A & B L 0.012

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.10 95.10
53.06 159.18

254.28
Hourly Rate Amount

201.25 201.25
783.00 195.75
205.00 205.00
12.71

614.71
868.99

86.90
Unit Cost Amount

3,465.00 3,465.00
1,200.00 14.40

3,479.40
3,566.30
of G 320.97
of G 285.30
of (G + H + I) 208.63
(G + H + I + J) 4,381.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 607(2) Reflective Pavement Studs (4" RPM)


Unit of Measurement : ea.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1
b. Unskilled Labor 3 1

Sub-Total for A
Name and Capacity No. of Units No. of Hours Hourly Rate
B. Equipment

a. Diamond Drill, CP-8 with attachment 1 1


b. Cargo Truck ( 2-5 mt) 1 0.25
c. Air Compressor (15-35 cfm) 1 1
Minor Tools (5% of Labor Cost)

Sub-Total for B
C. Total (A + B)
D. Output per hour = 10.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Reflective Stud Catcheye Raised Surface pc. 1


100mm x 100mm (type depends on the req.)
b. Concrete Epoxy A & B L 0.012

Sub-Total for F
g. Direct Unit Cost ( E + F )
H. Overhead, Contingencies and Miscellaneous (OCM) 9%
I. Contractor's Profit (CP) 8%
J. Value Added Tax (VAT) 5%
K Total Unit Cost
S (DUPA)

Hourly Rate Amount

95.10 95.10
53.06 159.18

254.28
Hourly Rate Amount

201.25 201.25
783.00 195.75
205.00 205.00
12.71

614.71
868.99

86.90
Unit Cost Amount

3,465.00 3,465.00
1,200.00 14.40

3,479.40
3,566.30
of G 320.97
of G 285.30
of (G + H + I) 208.63
(G + H + I + J) 4,381.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(1) Furnishing and Placing Topsoil


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 339.24


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor (5 hp) 1 1 123.00 123.00


Minor Tools (10% of Labor Cost) 33.92

Sub-Total for B 156.92


C. Total (A + B) 496.16
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 396.93
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Topsoil cu.m. 1.05 490.00 514.50

Sub-Total for F 514.50


g. Direct Unit Cost ( E + F ) 911.43
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 82.03
I. Contractor's Profit (CP) 8% of G 72.91
J. Value Added Tax (VAT) 5% of (G + H + I) 53.32
K Total Unit Cost (G + H + I + J) 1,119.69
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(2) Placing Topsoil


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 339.24


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Plate Compactor 1 1 123.00 123.00


Minor Tools (10% of Labor) 33.92

Sub-Total for B 156.92


C. Total (A + B) 496.16
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D) 396.93
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 396.93
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 35.72
I. Contractor's Profit (CP) 8% of G 31.75
J. Value Added Tax (VAT) 5% of (G + H + I) 23.22
K Total Unit Cost (G + H + I + J) 487.63
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 609 Sprigging


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 339.24


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Water Truck/Pump ( 16000 L) 1 0.25 2,450.00 612.50


Minor Tools (10% of Labor Cost) 33.92

Sub-Total for B 646.42


C. Total (A + B) 985.66
D. Output per hour = 35.00 sq.m.
E. Direct Unit Cost (C ÷ D) 28.16
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Sprigs sq.m. 1.05 89.00 93.45


b. Fertilizer kg. 0.10 26.00 2.60

Sub-Total for F 96.05


g. Direct Unit Cost ( E + F ) 124.21
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 11.18
I. Contractor's Profit (CP) 8% of G 9.94
J. Value Added Tax (VAT) 5% of (G + H + I) 7.27
K Total Unit Cost (G + H + I + J) 152.59
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 610 Sodding


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 519.58


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Water Truck ( 16000 L) 1 0.50 2,450.00 1,225.00


Minor Tools (10% of Labor Cost) 51.96

Sub-Total for B 1,276.96


C. Total (A + B) 1,796.54
D. Output per hour = 25.00 sq.m.
E. Direct Unit Cost (C ÷ D) 71.86
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Sods sq.m. 1.05 89.00 93.45

Sub-Total for F 93.45


g. Direct Unit Cost ( E + F ) 165.31
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 14.88
I. Contractor's Profit (CP) 8% of G 13.22
J. Value Added Tax (VAT) 5% of (G + H + I) 9.67
K Total Unit Cost (G + H + I + J) 203.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 611(1) Trees (Furnishing and Transplanting), 150 mm. dia or less
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt ) 1 1 1,212.00 1,212.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
c. Water Truck ( 16000L) 1 0.50 2,450.00 1,225.00
Minor Tools (10% of Labor Cost) 27.02

Note: includes watering for three (3) months

Sub-Total for B 4,001.02


C. Total (A + B) 4,271.25
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 4,271.25
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Trees (Delivered at Site) pc. 1 400.00 400.00


b. Fertilizers kg. 3 26.00 78.00
c. Bamboo Pole pc. 3 50.00 150.00
d. Polyethylene Sheets sq.m. 3 10.00 30.00
e. Tie Wire kg. 0.25 46.67 11.67

Sub-Total for F 669.67


g. Direct Unit Cost ( E + F ) 4,940.92
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 444.68
I. Contractor's Profit (CP) 8% of G 395.27
J. Value Added Tax (VAT) 5% of (G + H + I) 289.04
K Total Unit Cost (G + H + I + J) 6,069.92
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 611(2) Trees (Transplanting), 150 mm dia. or less


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 9-10 mt) 1 1 1,212.00 1,212.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00 1,537.00
c. Water Truck ( 16000 L) 1 0.50 2,450.00 1,225.00
Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 4,001.02


C. Total (A + B) 4,271.25
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 4,271.25
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Fertilizers kg. 3 26.00 78.00


b. Bamboo Pole pc. 3 50.00 150.00
c. Polyethylene Sheets sq.m. 3 10.00 30.00
d. Tie Wire kg. 0.25 46.67 11.67

Sub-Total for F 269.67


g. Direct Unit Cost ( E + F ) 4,540.92
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 408.68
I. Contractor's Profit (CP) 8% of G 363.27
J. Value Added Tax (VAT) 5% of (G + H + I) 265.64
K Total Unit Cost (G + H + I + J) 5,578.52
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(1) Reflectorized Thermoplastic Pavement Markings (White)


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 6 1 53.06 318.36

Sub-Total for A 551.48


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck/Delivery Truck ( 2-5 mt) 1 1 783.00 783.00


b. Applicator Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10% of Labor) 55.15

Sub-Total for B 1,119.40


C. Total (A + B) 1,670.88
D. Output per hour = 25.00 sq.m.
E. Direct Unit Cost (C ÷ D) 66.84
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Thermoplastic Paint (White) bag 0.325 1,565.00 508.63


b. Glass Beads bag 0.033 650.00 21.45
c. Primer L 0.120 160.00 19.20
d. LPG (50 kg.) cyl. 0.004 3,800.00 15.20
e. LPG (12 kg.) cyl. 0.002 735.00 1.47
f. Calsumine kg. 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 28.32

Sub-Total for F 594.64


g. Direct Unit Cost ( E + F ) 661.47
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 59.53
I. Contractor's Profit (CP) 8% of G 52.92
J. Value Added Tax (VAT) 5% of (G + H + I) 38.70
K Total Unit Cost (G + H + I + J) 812.62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)


Unit of Measurement : sq.m.
Output per hour : 25.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Skilled Labor 2 1 69.01 138.02
c. Unskilled Labor 6 1 53.06 318.36

Sub-Total for A 551.48


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck/Delivery Truck ( 2-5 mt) 1 1 783.00 783.00


b. Applicator Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10% of Labor Cost) 55.15

Sub-Total for B 1,119.40


C. Total (A + B) 1,670.88
D. Output per hour = 25.00 sq.m.
E. Direct Unit Cost (C ÷ D) 66.84
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Thermoplastic Paint (Yellow) bag 0.325 1,780.00 578.50


b. Glass Beads bag 0.033 650.00 21.45
c. Primer L 0.120 175.00 21.00
d. LPG (50 kg.) cyl. 0.004 3,800.00 15.20
e. LPG (12 kg.) cyl. 0.002 735.00 1.47
f. Calsumine kg. 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.90

Sub-Total for F 669.89


g. Direct Unit Cost ( E + F ) 736.73
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 66.31
I. Contractor's Profit (CP) 8% of G 58.94
J. Value Added Tax (VAT) 5% of (G + H + I) 43.10
K Total Unit Cost (G + H + I + J) 905.07
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Unit of Measurement : kg
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Unskilled Labor 6 1 53.06 318.36

Sub-Total for A 413.46


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Asphalt Kettle/Drum 1 1 10.00 10.00


Minor Tools (5% of Labor Cost) 20.67

Sub-Total for B 30.67


C. Total (A + B) 444.13
D. Output per hour = 20.00 kg
E. Direct Unit Cost (C ÷ D) 22.21
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Blown Asphalt kg. 1.05 250.00 262.50


Miscellaneous (5% of Materials Cost) 13.13

Sub-Total for F 275.63


g. Direct Unit Cost ( E + F ) 297.83
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 26.80
I. Contractor's Profit (CP) 8% of G 23.83
J. Value Added Tax (VAT) 5% of (G + H + I) 17.42
K Total Unit Cost (G + H + I + J) 365.89
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 620(a) Chevron Signs (450mm x 600mm)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b.Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 75mm Ø G.I. Pipe m. 3.25 530.00 1,722.50
f. G.I. Flat Bar, 1 1/2" x 1/8" kg. 5 48.00 240.00
g. G.I. Bolts w/ Nuts and Washer, 5mm Ø pc. 3 10.00 30.00
h. G.I. Bolts w/ Nuts and Washer, 2mm Ø pc. 12 10.00 120.00
i. Sign Face, 3mm thk. Aluminum Sheet pc. 2 3,750.00 7,500.00
j. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44
Miscellaneous (0.3% of Materials) 29.57

Sub-Total for F 9,886.86


g. Direct Unit Cost ( E + F ) 10,379.86
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 934.19
I. Contractor's Profit (CP) 8% of G 830.39
J. Value Added Tax (VAT) 5% of (G + H + I) 607.22
K Total Unit Cost (G + H + I + J) 12,751.66
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 620(b) Chevron Signs (600mm x 800mm)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.10 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck ( 2-5 mt ) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 27.02

Sub-Total for B 222.77


C. Total (A + B) 493.00
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D) 493.00
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Portland Cement bag 0.48 220.00 105.60


b. Sand cu.m. 0.025 850.00 21.25
C. Gravel cu.m. 0.050 650.00 32.50
d. Form Lumber, Good - 4 uses bd.f. 8 40.00 80.00
e. 75mm Ø G.I. Pipe m. 3.45 530.00 1,828.50
f. G.I. Flat Bar, 1 1/2" x 1/8" kg. 5 48.00 240.00
g. G.I. Bolts w/ Nuts and Washer, 5mm Ø pc. 3 10.00 30.00
h. G.I. Bolts w/ Nuts and Washer, 2mm Ø pc. 12 10.00 120.00
i. Sign Face, 3mm thk. Aluminum Sheet pc. 2 7,500.00 15,000.00
j. Assorted CWN (1 kg./100 bd.f. of Lumber) kg. 0.08 68.00 5.44
Miscellaneous (0.2% of Materials) 34.93

Sub-Total for F 17,498.22


g. Direct Unit Cost ( E + F ) 17,991.22
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 1,619.21
I. Contractor's Profit (CP) 8% of G 1,439.30
J. Value Added Tax (VAT) 5% of (G + H + I) 1,052.49
K Total Unit Cost (G + H + I + J) 22,102.21
4
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)a Bio-Engineering Solutions (Coco-net)


Unit of Measurement : sq.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 519.58


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Water Truck (16000 L) 1 0.25 2,450.00 612.50


Minor Tools (10% of Labor Cost) 51.96

Sub-Total for B 664.46


C. Total (A + B) 1,184.04
D. Output per hour = 50.00 sq.m.
E. Direct Unit Cost (C ÷ D) 23.68
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Erosion Control Net CGN 400 w/ 5% wastage sq.m. 1.05 110.00 115.50
(Price includes bamboo pegs)

Sub-Total for F 115.50


g. Direct Unit Cost ( E + F ) 139.18
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 12.53
I. Contractor's Profit (CP) 8% of G 11.13
J. Value Added Tax (VAT) 5% of (G + H + I) 8.14
K Total Unit Cost (G + H + I + J) 170.98
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)b Bio-Engineering Solutions (Coco-net)


Unit of Measurement : sq.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 519.58


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Water Truck (16000 L) 1 0.25 2,450.00 612.50


Minor Tools (10% of Labor Cost) 51.96

Sub-Total for B 664.46


C. Total (A + B) 1,184.04
D. Output per hour = 50.00 sq.m.
E. Direct Unit Cost (C ÷ D) 23.68
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Erosion Control Net CGN 700 w/ 5% wastage sq.m. 1.05 156.00 163.80
(Price includes bamboo pegs)

Sub-Total for F 163.80


g. Direct Unit Cost ( E + F ) 187.48
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 16.87
I. Contractor's Profit (CP) 8% of G 15.00
J. Value Added Tax (VAT) 5% of (G + H + I) 10.97
K Total Unit Cost (G + H + I + J) 230.32
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)a Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : l.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 519.58


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor Cost) 51.96

Sub-Total for B 51.96


C. Total (A + B) 571.54
D. Output per hour = 15.00 l.m.
E. Direct Unit Cost (C ÷ D) 38.10
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coco Fiber Roll (CGR 200) l.m. 1.05 388.00 407.40


(Price includes nylon ropes and live stakes)

Sub-Total for F 407.40


g. Direct Unit Cost ( E + F ) 445.50
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 40.10
I. Contractor's Profit (CP) 8% of G 35.64
J. Value Added Tax (VAT) 5% of (G + H + I) 26.06
K Total Unit Cost (G + H + I + J) 547.30
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)b Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : l.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 519.58


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

Minor Tools (10% of Labor Cost) 51.96

Sub-Total for B 51.96


C. Total (A + B) 571.54
D. Output per hour = 15.00 l.m.
E. Direct Unit Cost (C ÷ D) 38.10
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Coco Fiber Roll (CGR 300) l.m. 1.05 509.00 534.45


(Price includes nylon ropes and live stakes)

Sub-Total for F 534.45


g. Direct Unit Cost ( E + F ) 572.55
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 51.53
I. Contractor's Profit (CP) 8% of G 45.80
J. Value Added Tax (VAT) 5% of (G + H + I) 33.49
K Total Unit Cost (G + H + I + J) 703.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)a Bio-Engineering Solutions (Vegetation)


Unit of Measurement : sq.m.
Output per hour : 62.50

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 201.22


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Hydroseeding Machine 1 1 952.00 952.00


b. Water Truck/Pump (16000 L) 1 1 2,450.00 2,450.00
(including maintenance time)

Sub-Total for B 3,402.00


C. Total (A + B) 3,603.22
D. Output per hour = 62.50 sq.m.
E. Direct Unit Cost (C ÷ D) 57.65
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Grass Cover sq.m. 1.05 45.00 47.25


(Price includes grass seeds, mulch, cocopeat
& binding agent for hydroseeding)

Sub-Total for F 47.25


g. Direct Unit Cost ( E + F ) 104.90
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 9.44
I. Contractor's Profit (CP) 8% of G 8.39
J. Value Added Tax (VAT) 5% of (G + H + I) 6.14
K Total Unit Cost (G + H + I + J) 128.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)b Bio-Engineering Solutions (Vegetation)


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 8 1 53.06 424.48

Sub-Total for A 519.58


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Water Truck (16000 L) 1 0.50 1,065.00 532.50


Minor Tools (10% of Labor Cost) 51.96

Sub-Total for B 584.46


C. Total (A + B) 1,104.04
D. Output per hour = 35.00 sq.m.
E. Direct Unit Cost (C ÷ D) 31.54
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Vetiver Grass System sq.m. 1.05 70.00 73.50


(Price includes cocopeat fertilizer)

Sub-Total for F 73.50


g. Direct Unit Cost ( E + F ) 105.04
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 9.45
I. Contractor's Profit (CP) 8% of G 8.40
J. Value Added Tax (VAT) 5% of (G + H + I) 6.15
K Total Unit Cost (G + H + I + J) 129.05
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 2(a) Crack and Seat


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Backhoe with Breaker (0.80 cu.m.) 1 1 2,074.95 2,074.95


b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25
c. Water Truck/Pump (16000 L) 1 0.10 1,065.00 106.50

Sub-Total for B 3,311.70


C. Total (A + B) 3,581.93
D. Output per hour = 35.00 sq.m.
E. Direct Unit Cost (C ÷ D) 102.34
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 102.34
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 9.21
I. Contractor's Profit (CP) 8% of G 8.19
J. Value Added Tax (VAT) 5% of (G + H + I) 5.99
K Total Unit Cost (G + H + I + J) 125.73
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 2(b) Crack and Seat


Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Skilled Labor 1 1 69.01 69.01
c. Unskilled Labor 2 1 53.06 106.12

Sub-Total for A 270.23


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Arrow Master D 500 1 1 1,485.84 1,485.84


(Additional 35% for Oil and Lubricants)
b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00 1,130.25
c. Water Truck/Pump (16000 L) 1 0.10 1,065.00 106.50

Sub-Total for B 2,722.59


C. Total (A + B) 2,992.82
D. Output per hour = 30.00 sq.m.
E. Direct Unit Cost (C ÷ D) 99.76
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

Sub-Total for F 0.00


g. Direct Unit Cost ( E + F ) 99.76
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 8.98
I. Contractor's Profit (CP) 8% of G 7.98
J. Value Added Tax (VAT) 5% of (G + H + I) 5.84
K Total Unit Cost (G + H + I + J) 122.56
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3(a) Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 10 1 53.06 530.60

Sub-Total for A 625.70


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


a. Water Truck/Pump (16000 L) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 62.57

Sub-Total for B 506.82


C. Total (A + B) 1,132.52
D. Output per hour = 60.00 pc.
E. Direct Unit Cost (C ÷ D) 18.88
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Saplings pc. 1 50.00 50.00


b. Coco Lumber bd.f. 8 20.00 160.00
c. Assorted CWN (1 kg./100 bd.f.) kg. 0.08 68.00 5.44
d. Fertilizers kg. 0.10 50.00 5.00

Sub-Total for F 220.44


g. Direct Unit Cost ( E + F ) 239.32
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 21.54
I. Contractor's Profit (CP) 8% of G 19.15
J. Value Added Tax (VAT) 5% of (G + H + I) 14.00
K Total Unit Cost (G + H + I + J) 294.00
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3(b) Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate Amount


A. Labor

a. Construction Foreman 1 1 95.1 95.10


b. Unskilled Labor 10 1 53.06 530.60

Sub-Total for A 625.70


Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00 178.00


a. Water Truck/Pump (16000 L) 1 0.25 1,065.00 266.25
Minor Tools (10% of Labor) 62.57

Sub-Total for B 506.82


C. Total (A + B) 1,132.52
D. Output per hour = 60.00 pc.
E. Direct Unit Cost (C ÷ D) 18.88
Name and Specification Unit Quantity Unit Cost Amount
F. Materials

a. Saplings pc. 1 50.00 50.00


b. Fertilizers kg. 0.10 26.00 2.60

Sub-Total for F 52.60


g. Direct Unit Cost ( E + F ) 71.48
H. Overhead, Contingencies and Miscellaneous (OCM) 9% of G 6.43
I. Contractor's Profit (CP) 8% of G 5.72
J. Value Added Tax (VAT) 5% of (G + H + I) 4.18
K Total Unit Cost (G + H + I + J) 87.81
VARIATION ORDER NO. 1 VARIATION ORDER NO. 1
QUANTITIES QUANTITIES

222,551.00 222,551.00

80,299.00 80,299.00

884.00 884.00

14,599.00 14,599.00

3,855.00 3,855.00

14,599.00 14,599.00

27,553.00 27,553.00

2,505.00 2,505.00

1,700.00 1,700.00

340.00 340.00

255.00 255.00

534.00 534.00

28.00 28.00

1,707.00 1,707.00

696.00 696.00

30.00 30.00

17.00 17.00

168.00 168.00

779.00 779.00

78.00 78.00

153.00 153.00

588.00 588.00

You might also like