Professional Documents
Culture Documents
Rev - 15 - MS - Installation of Earthing System
Rev - 15 - MS - Installation of Earthing System
FOR
INSTALLATION OF EARTHING SYSTEM
TABLE OF CONTENTS
3. LOCATION OF ACTIVITY
6. OPERATION
7. INSTALLATION
8. FIXATION
9. RESPONSIBILITIES
16. DISTRIBUTION
1. INTRODUCTION AND SCOPE
This method of statement covers the on-site installation of Earthing
System as defined in the General Specification.
This procedure will define the method to be used to ensure that the
Earthing System is correct and acceptable and shall conform to the
Contract Documents and Specification.
Division: Installation
3. LOCATION OF ACTIVITY
Earthing System for the whole building .
6. OPERATION
Material: Material used will be as approved by the Engineer. The sizes
and routes routing will be as per the approved Shop Drawings.
7. INSTALLATION
Pre-Installation:
All materials and documentation relevant to this particular section of
works will be checked and verified ensuring that these are correct and
approved type.
Prior to the commencement of works, ensure that the areas for
permanent installation are ready, accessible and in suitable condition.
Installation:
1. Coordinate installation of earthing system system with installation of
other building systems and components, including electrical wiring,
supporting structures, metal bodies requiring bonding to earthing
system, and building finishes.
2. Install conductors with direct paths from ground pits to ground
connections.
3. When different metal to be connected, a bimetallic clamp shall be used.
4. Bond roof vents, flashing and any other metal masses projecting
through the roof to the grid.
5. Thermo weld all connections between cables and ground rods.
Compression type connectors may be used where approved by the
Consultant.
6. Measure the resistance of the complete installation and submit for
review to the Consultant.
7. Test clamps shall be provided in each inspection pit to allow for testing
and commissioning.
8. Concrete inspection pits with cover shall be installed flush with finished
floor level and be fully accessible.
9. The complete installation shall be tested and inspected to ensure that it
complies with the requirements of the Specification and the Local
Authorities. The tests shall be carried out in accordance with the
Regulations and to the satisfaction of the Consultant.
8. FIXATION
Inspection, testing and commissioning:
1. The inspection and tests shall be carried out in the same sequence as
set out in the Regulations, Local Authorities and the Consultant
requirements and in such time as to allow any remedial work to be
completed prior to Practical Completion.
2. All instruments necessary for inspection and testing shall be supplied
and shall be properly calibrated and operated by personnel skilled in
their use.
3. Allowance shall be made for disconnection or similar operations to
satisfy the requirements for testing, etc., and the reinstatement of the
installation.
4. Measure earth resistance not less than two full days after the last trace
of precipitation and without the soil being moistened by any means
other than natural drainage or seepage and without any chemical
treatment or other artificial means of reducing natural earth resistance.
5. Where resistance to earth exceeds specified values, notify the
Consultant the same and include recommendations to reduce earth
resistance and to accomplish recommended work.
6. Restore surface features at areas disturbed by work of this section.
7. Restore areas disturbed by trenching, storing or dirt, cable laying, and
other activities to their original condition..
9. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
1. Hand Tools
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
16. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer