Pipe Trench
Measurement Detail and Bill of Quantitie
It.No. Particular Length Width (m) Height (m) Quantity Remark
Items (m) (Cum)
1 Excavation: 20000 upvc
Extra over "excavation" items for excavation of topsoil Pipe Trench 45000 1 0.3 13500 14017.2 top soil
Trench excavation of subsoil to a depth not exceeding 1.75m 45000 1 1.3 58500 60450.4 subsoil
Extra over item "trench excavation" for excavation of rock 0 20 rock
0 74487.6
Extra over "excavation" items for excavation of topsoil 600 0.9 0.3 162
Trench excavation of subsoil to a depth not exceeding 1.75m 600 0.9 1.2 648
Extra over item "trench excavation" for excavation of rock 0
0
Extra over "excavation" items for excavation of topsoil 1480 0.8 0.3 355.2
Trench excavation of subsoil to a depth not exceeding 1.75m 1480 0.8 1.1 1302.4
Extra over item "trench excavation" for excavation of rock 0
0
Extra over item "trench excavation" for excavation of rock
Total 74467.6
2 Backfilling.
It.No. Particular Length Width (m) Height (m) Quantity Remark
Items (m) (Cum)
1 Excavation: 20000 upvc total
Pipe bedding with selected excavated material Pipe Trench 45000 1 0.1 4500 4672.4
Side and initial backfill with selected excavated material 45000 1 0.8 8550 27450 28418.4
Main backfill with selected excavated material 45000 1 0.7 31500 32233.2
0 65324
Pipe bedding with selected excavated material 600 0.9 0.1 54
Side and initial backfill with selected excavated material 600 0.9 0.7 75.6 302.4
Main backfill with selected excavated material 600 0.9 0.7 378
0
Pipe bedding with selected excavated material 1480 0.8 0.1 118.4
Side and initial backfill with selected excavated material 1480 0.8 0.6 44.4 666
Main backfill with selected excavated material 1480 0.8 0.3 355.2
0
Total 65324
butt-weld flanges
35
21
32
0 1 4,000.00
30
0 1 1,000.00
14
0 1 229.00
30
34
34
1 1,400.00
34
0 1 300.00
23
32
30
32
1 550.00
Weight (kg)
Total
21
0 1 300.00
0 1 229.00
21
50.4
28
16
0 1 100.00
0 1 1,700.00
1 20.00
0 1 300.00
0 1 229.00
28
42
28
616 708.4 3,000.00
12 20.00
677.6
125
802.6
1300
14,110.40
15% 2,116.56
16,226.96
Legend:
pipes inlet 20
outlet 14
overflow 26
flanges inlet
outlet
overflow
2 653.00
2 2,500.00
2 150.00
2 653.00
2 2,500.00
2 653.00
2 500.00
2 200.00
2 200.00
2 200.00
2 200.00
2 300.00
2 200.00
DN400
DN400 1,000 3.00
DN400 700 3.00
DN400 1,300 3.00
DN400 10 284.44
DN400 10 284.44
DN400 10 284.44
35,351.20
15% 5,302.68
40,653.88
Item Description DN PN
No.
System F
A New suction header of System "A" 500 10
C New delivery header for System "A" varies 16
E Pump discharge line for System "A" 300 16
pipes suction 15
delivery 10
delivery 26
flanges suction 3
delivery 5
delivery 12
System A
31 Pump motor - System "A" (existing)
32 Pump - System "A" (existing)
33 Double flanged reducer (existing) 200/100 10
34 Dismantling joint (existing) 200 10
35 Butterfly valve with hand drive (existing) 200 10
37 Double flanged reducer (existing) 150/80 16
38 Nozzle check valve, Dresser/Entech -Type DRV-Z 150 16
or equivalent (to replace existing non-return valve)
39 Double flanged bend 90° (existing) 150 16
40 Double flanged pipe with installed pessure gauge (existing) 150 16
41 Dismantling joint (existing) 150 16
42 Gate valve with hand drive (existing) 150 16
43 Double flanged pipe (existing) 150 16
44 Pipe supports
pipes suction 7
delivery 4
delivery 0
flanges suction 3
delivery 5
delivery 0
Quan-
tity
1
1
1
1
1 1 1,000
2 2 3,500
3
3
3 x
3 3 400
3 3 1,500
3
3 3 2,000
3
1 100
3 3 20
3 3 450
3 3 1,400
3
3
DN500 70 750 3
DN300 36 500 3
DN200 20 1,300 3
DN500 3 556
DN300 5 120
DN200 12 36
35,760
50% 17,880
53,640
3
3
3
3
3
3
3 3 2,000
3
3
3
3
3
2
1
1 1 500
1
1
1 500
1 2,000
1
1 450
1
1 450
3 2,000
1
1 100
1 5,000
1 750
1
1
1 3,000
1
1
1 100
1 1 500
1
1
1
1
1
1 1
1 1 2,200
1
1
1
1 1 100
1 1 200
1 1 100
1 1 2,500
1 1 200
1 1 50
1 1 200
1 1 100
2
DN500 70 350 3
DN300 36 200 3
DN200 20 0 3
DN500 3 556
DN300 5 120
DN200 0 36
16,768
50% 8,384
25,152
P1+P2
Item Description DN
No.
All fittings, valves and specials rated for PN 16)
1 Submersible well pump including check valve
2 Raiser pipe 250
3 Well - head 700
4 Fabricated steel pipe # 1, including 90° bend w 250
5 Woltman type flow meter 250
6 Dismantling joint, adjustable type 250
7 Butterfly valve with hand drive EN 588-1, series 14 250/80
8 Fabricated steel pipe # 2, including 90° bend an 250
9 Dismantling joint, adjustable type 250
10 Double flanged taper 300/250
11 Existing double flanged pipe 300
12 Existing double flanged pipe 300
13 Existing double flanged pipe, short piece 300
14 Existing valve 300
15 Existing double flanged taper 750/300
16 Existing tee of discharge header 1200/750
21 Gate valve with hand drive EN 588-1, series 14 80
22 Air valve, Type VAG Duojet 264 or equivalent 80
23 Drain pipe from air valve, steel 50
Item Description DN
No.
All fittings, valves and specials rated for PN 16)
31 Submersible well pump including check valve
32 Raiser pipe 250
33 Well - head 700
34 Fabricated steel pipe # 3, including 90° bend w 250
35 Woltman type flow meter 250
36 Dismantling joint, adjustable type 250
37 Butterfly valve with hand drive EN 588-1, series 14 250/80
38 Fabricated steel pipe # 4, including 90° bend an 250
39 Double flanged pipe 250
40 Dismantling joint, adjustable type 250
41 Double flanged taper 300/250
42 Existing butterfly valve with hand drive 750
43 Existing tee of discharge header 1200/750
51 Gate valve with hand drive EN 588-1, series 14 80
52 Air valve, Type VAG Duojet 264 or equivalent 80
53 Drain pipe from air valve, steel 50
54 Pressure gauge with stop - valve 3/8"
55 Tap with 10 m PE - hose 3/4"
56 Tap for taking water samples 1/2"
1 2000
1 443
1 2220
1 443
1 150
1 2000
1
36 150 3
27 150 3
3 120
3 69
8,516
50% 4,258
12,774
1500
0
1 2000
1 443
1 2220
1 443
0
0
0
1 150
1 2000
1 200
1 150
1 150
1 100
36 150 3
27 150 3
3 120
3 69
9,323
50% 4,662
13,985
Page 24
1.02 Provision of a fully furnished site office with two office rooms, of a total floor area not less than 60 m² for
the Engineers including sanitary facilities, air conditioning, heating, electricity, refrigerator,
telephone/internet connections.
Gravel Packing from sorted gravel 2 - 8mm round washed grave based on sieve analysis.
Back filling for casing pipe should be imperviouse clay soil without gravel stone
Compressor test for Cleaning of Well and determination of Hydro geological Parameters for 72 hrs.
Supply 'Installation of 16 inch PVC class - E. Bill plug in the bottom of well
2.01.01 Construction of 30m defth new wells lump
8
sum
3 CIVIL WORKS
3.01 STANDARD STRUCTURES
Construction of buildings for new wells
The works shall comprise the supply of all material and complete civil works for construction of structures
for new wells as per relevant Drawings Nos. STD-1.02, . The works shall include, in particular, but not be
limited to the following: The unit rate shall include all materials, labour, equipment, tools and other
incidental costs required to complete the works.
3.01.01 Earthworks including excavation, backfilling, compaction, transport and disposal of surplus material to
Contractor's deposit within a radius of 1 km from the execution site, cu.m 95
3.01.13 - supply and installation of roof drain spout 22 gauge GI sheet including soakpits, lump sum 8
for well
3.01.14 - supply and installation of floor drain with odour trap including drain pipes, lump sum 8
for well
3.01.16 - supply and placing of sleeves for electric cables, lump sum 8
for well
3.01.17 - plastering of internal walls and ceiling,with cement/sand 1:2 sq.m 1084
3.01.18 - plastering and painting of the basin for diesel holding tanks with special diesel resistant mortar and paint lump sum 8
respectively, for well
4.01.01 - earthworks including excavation, backfilling, compaction, transport and disposal of surplus material to cu.m 72
Contractor's deposit within a radius of 5 km from the execution site,
4.01.02 - placing of plan concrete, Mark 150 cu.m 26
4.01.03 - supply and placing of all formworks reinforcement bars, placing of reinforced concrete for , base slab, cu.m 80
roof slab, cross beams, parapet, etc. C30/37
4.01.04 compacted gravel cu.m 41
4.01.05 -supply and placing of stone masonary works, 1:4 cu.m 90
4.01.06 -supply and placing of brick masonary works, fair-faced of hard burnt bricks Mortar mix (cement:sand) - cu.m 248
1:4
4.01.07 - supply and installation of PVC doors (high quality) cu.m 75
4.01.08 - supply and installation of PVC windows(high quality) sq.m 115
4.01.09 - supply and installation of roof drain pipes including soakpits, lump sum 8
4.01.10 - supply and installation of sanitary fixtures, as required, for kitchen, and/or washroom, including water lump sum 8
connection.
4.01.11 - plastering of internal walls and ceiling,with cement/sand 1:2:9 1127
4.01.12 Wash painting sq.m 1127
4.01.13 Tar Insolation sq.m 36
4.01.14 Construction of air vent chamber of internal cross-sectional area up to 3.20m² and height up to 2.80m pce. 22 0.00 0.00
The unit price shall include all labour, materials, products, equipment, plant and tools,
concrete batching, and all other incidental costs required to complete the work
as specified.
Payment shall be made per cubic meter of different type of concrete based on the dimensions shown on
the Drawings, carried out, verified and approved by the Engineer.
Excacvation cu.m 613
8.01.01 Supply and placing of plain concrete C8/10 cu.m 19
8.02 Supply and placing of reinforced concrete
The works shall include the supply of all material and placing of renforcement concrete in accordance with
Technical Specification and drawings, including:
- preparation all steel bar according to the drawing.
- preparation, mixing and transport of concrete,
- placing of concrete including all formworks, steel bar and compaction,
- taking of concrete samples and execution of concrete tests according to the Technical Specification,
9.02.01 Trench excavation of subsoil to a depth not exceeding 1.6m cu.m 60450
9.03 trench excavation for excavation of rock
Extra over item "trench excavation" for excavation of rock. Payment shall be made per cubic meter. The
unit rates shall include the excess cost only for excavation of rock and subsequent handling of such
material, over and above that of item "trench excavation".
9.03.01 Extra over item "trench excavation" for excavation of rock cu.m 20
10 Backfilling of trenches with selected excavated material
10.01 The works shall include:
- placing and compaction of pipe bedding with selected excavated material
- placing and compaction of side and initial backfill with selected excavated material
- placing and compaction of main backfill with selected excavated material
Backfilling of trenches shall be carried out by hand or by plant and equipment in accordance with EN1610,
Technical Specifications, Standard Drawing STD-4.01 and as directed by the Engineer and shall also
include loading, handling, transport along the trench of selected material and unloading.
The unit rates shall include all materials, labour, equipment, tools, and all other incidental costs required to
complete the works.
Payment for pipe bedding, side and initial backfill and main backfill shall be made per cubic meter
applying the following payment limits:
- width: minimum width according to the Technical Specifications and Standard Drawing STD-4.01
Supply of pump and pump riser pipe is not included in this item and shall be paid under seperate item/s.
The unit rate shall include all materials, labour, equipment, tools, execution of shop-drawings, fabrication
of steel pipes and fittings and other incidental costs required to complete the works. Payment shall be
made for the complete supply of pipes, fittings, hydraulic equipment, etc. per each well.
Also included in the works is the execution of hydrostatic pressure test, flushing and disinfection in
accordance with EN 805 and the Technical Specifications.
Pipe joints shall be of flexible push-fit collar type with rubber gaskets according to the Technical
Specifications.
The unit rate shall include all material, labour, equipment, tools and other incidental costs required to
complete the works.
Payment shall be made per linear meter based on the useful length of the pipe, i.e. excluding sockets.
16.01.01 Supply of PVC-U socket pipes, OD22'' 558/ PN10, SDR26 lin. m. 22000
16.01.02 Supply of PVC U socket pipes OD 20'' 507/PN 10 SDR26 lin. m. 23000
16.02 Supply of double socket 90° bends, DI
The works shall be as described under item 15, but for double socket 90° bends of ductile iron according
to EN 545. The unit rate shall include all material, labour, equipment, tools and other incidental costs
required to complete the works. Payment shall be made per piece.
16.05.01 Supply of flanged branch on double socket tee, DI, DN 300/200, PN10 pce. 2
16.05.02 Supply of flanged branch on double socket tee, DI, DN 4000/200, PN10 pce. 2
16.05.03 Supply of flanged branch on double socket tee, DI, DN 450/200, PN10 pce. 6
16.05.04 Supply of Spigot socket taper, DI, DN 300/200 pce. 1
16.05.05 Supply of Spigot socket taper, DI, DN 400/300 pce. 1
16.05.06 Supply of Spigot socket taper, DI, DN 450/400 pce. 1
16.06 Supply of flange sockets, DI, PN10 or PN16
The unit rate shall include the supply of flange sockets of ductile iron according to EN 545, PN10 or PN16,
including transport, unloading, handling, storage at storage sites in accordance with the manufacturers
instructions and good workmanship, supply of rubber gaskets including 2% reserve, lubricating paste,
stainless steel bolts and nuts, denso tape or similar approved material for wrapping buried flange
connections, all accessories necessary for installation, etc.
Socket joints shall be push-on Tyton joints, internal lining shall be of cement mortar, external coating shall
of polyethilene on zinc rich coating, all according to the Technical Specifications.
Unit rate shall include all material, labour, equipment, tools and other incidental costs required to complete
the works.
Payment shall be made per piece.
16.06.1 Supply of flange socket, DI, DN200, PN10/PN16 pce. 8
16.06.2 blank flanges DI, DN200, PN10/PN16 5
17 INSTALLATION OF PIPES, FITTINGS, VALVES & ACCESSOIRES
17.01 Laying of ductile iron pipes in trenches
The works shall include:
- loading, handling, transport from storage site to the execution site, unloading, etc. of pipes, fittings,
warning tape, etc.
The unit price shall include all labour, materials, products, equipment, plant and tools
and all other incidental costs required to complete the work as specified.
Payment shall be made per complete unit of a battery of 3 tanks of total capacity not less than 4.50 m³.
18.01,01 Supply of diesel storage tanks for generators of capacity 4,500 lt. pce. 8
18.02 Installation of diesel storage tanks for generators
The works shall include the installation of diesel storage tank as described above in Item 18.01 in
accordance with Drwg. No. STD-, Technical Specifications or as directed by the Engineer and shall
include all fuel lines and connections
The unit price shall include all labour, materials, products, equipment, plant and tools and all other
incidental costs required to complete the installation works. Payment shall be made per complete unit of a
battery of 3 tanks of total capacity not less than 4.500 l.
18.02.01 Installation of battery of diesel storage tanks for generators and connections pce. 8
19 DOORS, WINDOWS AND METALWORKS
19.01 Supply and installation of cover grid for manholes and pipe channels in floor slabs
Supply and installation of hot dip galvanizes steel grid to be sized for single load of
500kg on 200x 200 mm as indicated at a deformation not to exceed 1/200 of span.
Frames sharp-edged, to guarantee complete linear seat of grid.
For installation on manholes and pipe channels in floor slabs or elesewhere
The unit price shall include all labour, materials, products, equipment, plant and tools
and all other incidental costs required to complete the work as specified,
including including fixing of frame to the roof/or floor slab.
Payment shall be made based on the square meter of grid installed, verified and approved by the
Engineer.
19.01.01 Supply and installation of cover grid for manholes and pipe channels for up to 60 cm channel width, main
bar size 25 x 3 mm, spaced 35mm, mass not less than 24kg/m2 sq.m 8
The unit rate shall include all material, labour, equipment, tools and other incidental costs required to
complete the works.
Payment shall be made per roll.
20.01.01 Supply of pipe warning tape for water main in rolls of 250m pce. 180
21 SUPPLY OF PUMPS SETS AND ACESSORIES
21.01 Supply and instalation of submersible borehole motor pumps
In general the pump motors shall conform to the following technical criteria:
Rated Voltage: 400 V ( + 5% - 20%)
Min. Operating Voltage: 320 V
Frequency : 50 [Hz]
RPM: 2930 [1/min]
Number of poles: 2 p
max. cooling Temperatur {v = 0 m/sec } 22 [°C]
Max. Starts: 5 per hr with 3 min. delay
The motor winding shall be protected against overheating by a PT 100 thermistor probe.
The unit rate shall include all materials including accessories, labour, equipment, tools and other
incidental costs like testing, handling, transporting, safe storage, etc. required to complete the supply.
Payment shall be made per complete unit of pump including motor and accessories.
The unit rate shall include the supply of pump, check-valve, pump motor, extension cable
and accessories in accordance with Technical Specifications. The pumps shall be
submersible borehole pumps (Type: KSB-UPA 250C-150/2a + UMA 150D 30/21
22.01.01 Supply of diesel generator, rated power @ 50Hz: 53kW / 66 kVA pce. 8
23 SUPPLY OF SURGE PROTECTION EQUIPMENT
23.01 Supply of surge vessels
The surge vessels shall be in accordance with the Technical Specification, fitted with bladder (membrane)
of material suitable for drinking water, shall be of vertical type fitted with a bottom flange outlet and 3 to 4
supporting legs. Nominal pressure shall be PN 16. The vessel shall be of steel material with corrosion
protection and paint as specified.
The unit rate shall include all materials including accessories, labour, equipment, tools and other
incidental costs like handling, transporting, safe storage, etc. required to complete the supply. Payment
shall be made per complete unit of of surge vessel including accessories supplied.
25.01.03 Installation of typical electrical installation for well site acc. to Drawing STD- pce. 8
25.01.04 Installation of typical electrical installation for well house with generator room acc. to Drawing STD-
pce. 8
25.01.05 Installation of typical electrical installation for well, operator house acc. to Drawing STD- pce. 8
25.02 INSTALLATION OF BUILDING LIGHTNING AND GROUNDING SYSTEM
25.02.01 Installation of building lightning and grounding system for well - and generator house pce. 8
25.02.02 Installation of building lightning and grounding system for operator house pce. 8
Total
Name of Bidder
Signature of Bidder
excavation
long wall 2 9.6 0.5 0.6 5.76
short wall 4 2.7 0.5 0.6 3.24
1 Total 9
PCC work
foundation long wall 2 9.6 0.5 0.05 0.48
Mark 1:6 foundation short wall 4 2.7 0.5 0.05 0.27
floor bed room 1 3 3 0.1 0.9
floor of living room 1 3.55 3 0.1 1.065
Mark 1:2:9 floor of bath 1 2 1.5 0.1 0.3
floor of kitchen 1 2 1.3 0.1 0.26
2 Total 3.275
stone masonry
foundation of long wa 2 9.6 0.5 0.75 7.2
foundation of short w 4 2.7 0.5 0.75 4.05
3 Total 11.25
compacted gravel
under floor 1 8.5 2 0.3 5.1
4 Total 5.1
burn brick work
long wall 2 9.6 0.35 2.97 19.9584
short wall of side 2 3 0.35 2.97 6.237
short wall of inside 2 3 0.2 2.97 3.564
short wall in bath 1 2 0.2 2.97 1.188
5 Total 30.9474
deduction of burn brick
2m window 2 2 0.35 1.8 2.52
1 m window 4 1 0.35 1.8 2.52
0.9 m door 1 0.9 0.35 2.77 0.87255
0.9 m door inside 1 0.9 0.2 2.77 0.4986
0.8 m door inside 2 0.8 0.2 2.77 0.8864
6
6 Total 7.29755
Clear Burn brick 23.6499
RCC
RCC slab 1 9.6 3.7 0.12 4.2624
Ring on long wall 2 9.6 0.35 0.35 2.352
ring on short wall ou 2 3 0.35 0.35 0.735
M 1:2:9 ring on inside short w 2 3 0.2 0.35 0.42
(7.1 + 4.25)2 = 22.7 ring on bath wall 1 2 0.2 0.35 0.14
pick long wall 2 10.625 0.15 0.45 1.434375
pick short wall 2 4.4 0.15 0.45 0.594
7 Total 9.93778
door
1084.368 0.9 m door 2 0.9 1 2.77 4.986
0.8 m door inside 2 0.8 1 2.77 4.432
8 Total 9.418
window
2m window 2 2 1 1.8 7.2
1 m window 4 1 1 1.8 7.2
9 Total 14.4
plester work
bed room 1 12 1 3 36
living room 1 13 1 3 39
Kitchen 1 6.6 1 3 19.8
bath 1 7 1 3 21
roof of bed 1 3 3 1 9
roof of living room 1 3.5 3 1 10.5
roof of kitchen 1 2 1.3 1 2.6
1 2 1.5 1 3
10 Total 140.9
11 painting of the insid same the inside plaster 140.9
total for 8 house
72 200 1800
90 4000 45000
247.579
58.3804
189.199 4500 106424.3
35.52
Mark 1:6
115.28
Mark 1:2:9
283.6
180.984
10.376
M 1:2:9
(7.1 + 4.25)2 = 22.7
1084.368
Estimation for 600 Cum RCC Water Reservair
Item No. Work Items Nos Length (m) Width (m) Depth (m) Vol. Cum Rmark
1 Excavation Work:
Foundation 1 21.5 9.5 1.5 306.375
Total 306.375
2 RCC Work:
door 4 1.5 3 0.25 -4.50
Bottom Slab Plate 1 20.6 8.3 0.3 51.29
Reservoir walls (Lo 2 20.6 0.3 4.1 50.68
Reservoir walls (Sh 2 8 0.3 4.1 19.68
Reservoir walls (Sho 4 8 0.25 3.8 30.40
Fillet (Long directio 2 20 0.2 0.2 0.80 0.5x0.2x0.2
Fillet (Short walls in 10 8 0.2 0.2 1.60 0.5x0.2x0.2
Roof Slab 1 20.6 8.6 0.2 35.43
Total 185.38
PCC Work:
Bottom Slab Plate 1 21.5 9 0.05 9.68
tar isolotion
Roof Slab 1 21 9 189.00
3 BRICK MASONRY Work:
Reservoir walls (Lo 2 21.5 0.35 4.8 72.24
Reservoir walls (Sh 2 8.8 0.35 4.8 29.57
Total 101.81
4 ISOLATION MATERIAL
Bottom Slab Plate 1 20.7 8.8 182.16
Reservoir walls (Lo 2 20.7 4.8 198.72
Reservoir walls (Sh 2 8.7 4.8 83.52
Total 464.40
Plaster
Work:INTEIAL
SURFACE+PADL
5 OW PODER
Bottom Slab Plate 1 20 8 160.00
Reservoir walls (Lo 2 20 3.8 152.00
Reservoir walls (Sh 2 8 3.8 60.80
Total 372.80
: Supply and Installation of Pipelines and Equipment for Wellfields
Well plot boundary
Measurement Detail and Bill of Quantities
Item Particular Items No. Length Width Height Quantity Remarks
No. (m) (m) (m) Cum
1 Excavation:
Walls found 2 29.4 0.6 0.6 21.168
Walls found 2 29.4 0.6 0.6 21.168
0
Total 42.336 338.688
2 Stone Masonry:
Walls found 2 29.4 0.6 1.4 49.39 Mark 1:6
Walls foun 2 29.4 0.6 1.4 49.39
Total 98.78 790.24
3 Pointing. Mark 1:3
Walls found 4 29.4 0.85 99.96
Walls foun 4 29.4 0.85 99.96
Total 199.92 1599.36
4 P.C.C. ceme/sand Mark 1:2:4
Top of wall 2 29.4 0.6 0.1 3.528
Botham of 2 29.4 0.7 0.05 1.029
Schedule No. 2.1: Plant, Equipment and Mandatory Spare Parts Supplied from within the Employer's Country
#REF!
#REF!
Pipe Trench
Measurement Detail and Bill of Quantitie
It.No. Particular Length Width (m) Height (m) Quantity Remark
Items (m) (Cum)
1 Excavation: 20000 upvc
Extra over "excavation" items for excavation of topsoil Pipe Trench 45000 1 0.3 13500 14017.2 top soil
Trench excavation of subsoil to a depth not exceeding 1.75m 45000 1 1.3 58500 60450.4 subsoil
Extra over item "trench excavation" for excavation of rock 0 20 rock
0 74487.6
Extra over "excavation" items for excavation of topsoil 600 0.9 0.3 162
Trench excavation of subsoil to a depth not exceeding 1.75m 600 0.9 1.2 648
Extra over item "trench excavation" for excavation of rock 0
0
Extra over "excavation" items for excavation of topsoil 1480 0.8 0.3 355.2
Trench excavation of subsoil to a depth not exceeding 1.75m 1480 0.8 1.1 1302.4
Extra over item "trench excavation" for excavation of rock 0
0
Extra over item "trench excavation" for excavation of rock
Total 74467.6
2 Backfilling.
It.No. Particular Length Width (m) Height (m) Quantity Remark
Items (m) (Cum)
1 Excavation: 20000 upvc total
Pipe bedding with selected excavated material Pipe Trench 45000 1 0.1 4500 4672.4
Side and initial backfill with selected excavated material 45000 1 0.8 8550 27450 28418.4
Main backfill with selected excavated material 45000 1 0.7 31500 32233.2
0 65324
Pipe bedding with selected excavated material 600 0.9 0.1 54
Side and initial backfill with selected excavated material 600 0.9 0.7 75.6 302.4
Main backfill with selected excavated material 600 0.9 0.7 378
0
Pipe bedding with selected excavated material 1480 0.8 0.1 118.4
Side and initial backfill with selected excavated material 1480 0.8 0.6 44.4 666
Main backfill with selected excavated material 1480 0.8 0.3 355.2
0
Total 65324