You are on page 1of 32

PROJECT : SPLENDOR PLACE

OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (REBARS)

As per Contract As per Foreman Richard


Items

Particular/Description Unit Cost


Qty Qty
Labor Total Cost

From Foundation to URD

Pile cap 10,282.00 kgs 5.00 51,410.00 10,512.72 kgs


Footing Tie Beam 13,511.00 kgs 5.00 67,555.00 12,600.65 kgs
Wall Footing 526.00 kgs 5.00 2,630.00 479.52 kgs
Column 84,945.00 kgs 5.00 424,725.00 85,707.18 kgs
Beam 147,295.00 kgs 5.00 736,475.00 136,685.28 kgs
Slab 58,923.00 kgs 5.00 294,615.00 29,489.87 kgs
Stair 25,667.00 kgs 5.00 128,335.00 6,856.59 kgs
Slab on Grade 2,557.00 kgs 5.00 12,785.00 1,485.18 kgs
RC Walls 29,048.00 kgs 5.00 145,240.00 6,530.87 kgs
Elevator pit and Shear 16,652.00 kgs 5.00 83,260.00 16,712.89 kgs
Concrete ledge 3,180.00 kgs 5.00 15,900.00 1,478.40 kgs
Cistern Tank 12,734.00 kgs 5.00 63,670.00 7,467.53 kgs
Septic Tank 7,861.00 kgs 5.00 39,305.00 3,663.67 kgs
Drop wall 1,869.00 kgs 5.00 9,345.00 1,804.80 kgs
Sump Pit 3,193.00 kgs 5.00 15,965.00 2,728.74 kgs
Concrete saddle 1,163.00 kgs 5.00 5,815.00 532.00 kgs
Concrete pads 627.00 kgs 5.00 3,135.00 690.00 kgs
Stiffener beams and c 6,219.00 kgs 5.00 31,095.00 6,192.53 kgs
RC Canopy 78.00 kgs 5.00 390.00 73.92 kgs
Counter top 451.00 kgs 5.00 2,255.00 221.76 kgs
Concrete gutter 418.00 kgs 5.00 2,090.00 369.60 kgs
Trench drain 518.00 kgs 5.00 2,590.00 319.68 kgs
Zocalo 661.00 kgs 5.00 3,305.00 295.68 kgs
Ramps 2,798.00 kgs 5.00 13,990.00 2,061.27 kgs

431176.00 kgs - 334,960.33 kgs

TOTAL = Total contract amount 2,155,880.00


Prepared by: Checked by: Confirmed by:

Manuelito Zapata Angel del Rosario Richard Caderao


Foreman-Steelman
As per Foreman Richard
Unit Cost Remarks

Labor Total Cost

-
-
-
-
-

-
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (Foundation)

As per contract As per Foreman Rich


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Pile cap 10,282.00 kgs - 10,512.72 kgs


Footing Tie Beam 13,511.00 kgs - 12,600.65 kgs
Wall Footing 526.00 kgs - 479.52 kgs
Column 13,157.54 kgs - 13275.60 kgs
RC Walls 29,048.00 kgs 6,530.87 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by;

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-
-
-

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (Tanks)

As per contract As per Foreman Rich


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Cistern Tank 12,734.00 kgs - 7,467.53 kgs


Septic Tank 7,861.00 kgs - 3,663.67 kgs
Sump pit 3,193.00 kgs - 2,728.74 kgs
-
Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by;

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-
-
-

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (LGF)

As per contract As per Foreman Richa


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Slab on Grade 2,557.00 kgs - 1,472.50 kgs


Column 6,074.98 kgs 6,129.49 kgs
Stair 1,736.23 kgs - 463.81 kgs
Ramps 1125.23 kgs - 828.95 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (UGF)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 12,174.33 kgs - 11,297.41 kgs


Slab 3,929.47 kgs - 1,966.63 kgs
Column 10,445.56 kgs 10,539.28 kgs
Stair 6,685.96 kgs - 1,786.06 kgs
Elevator 3,303.65 kgs - 3,315.73 kgs
Ramps 1125.23 kgs - 1,232.32 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (2F)

As per contract As per Foreman Richa


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 7,025.19 kgs - 6,519.16 kgs


Slab 1,305.20 kgs - 653.23 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (2F)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 13,559.11 kgs - 12,582.44 kgs


Slab 5,734.58 kgs - 2,870.05 kgs
Column 7,432.61 kgs 7,499.30 kgs
Stair 2,517.86 kgs - 672.61 kgs
Elevator 1,762.33 kgs - 1,768.78 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (3F)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 16,185.09 kgs - 15,019.27 kgs


Slab 6,231.00 kgs - 3,118.50 kgs
Column 7,432.61 kgs 7,499.30 kgs
Stair 2,462.19 kgs - 657.74 kgs
Elevator 1,762.33 kgs - 1,768.78 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (4F)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 16,185.09 kgs - 15,019.27 kgs


Slab 6,231.00 kgs - 3,118.50 kgs
Column 7,432.61 kgs 7,499.30 kgs
Stair 2,462.19 kgs - 657.74 kgs
Elevator 1,762.33 kgs - 1,768.78 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (5F)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 16,185.09 kgs - 15,019.27 kgs


Slab 6,231.00 kgs - 3,118.50 kgs
Column 7,432.61 kgs 7,499.30 kgs
Stair 2,462.19 kgs - 657.74 kgs
Elevator 1,762.33 kgs - 1,768.78 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (6F)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 16,186.99 kgs - 15,021.04 kgs


Slab 6,676.83 kgs - 3,341.63 kgs
Column 7,602.71 kgs 7,670.93 kgs
Stair 2,462.19 kgs - 657.74 kgs
Elevator 1,849.57 kgs - 1,856.34 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (7F)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 16,186.99 kgs - 15,021.04 kgs


Slab 6,597.03 kgs - 3,301.69 kgs
Column 7,602.71 kgs 7,670.93 kgs
Stair 2,439.09 kgs - 651.57 kgs
Elevator 1,849.57 kgs - 1,856.34 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (8F)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 16,186.99 kgs - 15,021.04 kgs


Slab 6,597.03 kgs - 3,301.69 kgs
Column 7,602.71 kgs 7,670.93 kgs
Stair 2,439.09 kgs - 651.57 kgs
Elevator 2,599.87 kgs - 2,609.38 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (RD)

As per contract As per Foreman Ric


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 14,110.53 kgs - 13,094.14 kgs


Slab 6,913.30 kgs - 3,459.98 kgs
Column 2,728.34 kgs 2,752.82 kgs
Concrete ledge 397.50 kgs - 184.80 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars
PROJECT : SPLENDOR PLACE
OWNER : MIROBENI
LOCATION : 1816 J. BACOBO ST., MALATE MANILA
ARCHITECT : JONATHAN GAN

Subject : COST COMPARISON FOR PAKYAWAN (URD)

As per contract As per Foreman Richa


Items

Particular/Description Unit Cost


Qty Total Cost Qty
Labor

FORMWORKS (Installation and Stripping works)

Beam 3,309.60 kgs - 3,071.21 kgs


Slab 2,476.57 kgs - 1,239.48 kgs

Hauling kgs kgs

TOTAL = -
VARIANCE =

Prepared by: Checked by:

Manuelito Zapata Angel del Rosario


As per Foreman Richard
Unit Cost Remarks
Labor Total Cost

-
-

Confirmed by:

Richard Caderao
Foreman-Rebars

You might also like