DOCUMENT TITLE
FIRE FIGHTING SYSTEM
DCPL
NALCO
D T I 0
FIRE FIGHTING SYSTEM
Rev.: 0
Alumina Unloading and Transportation System
Nalco Angul Orisa.
Fire Fighting System Design, fabrication & operation of the plant shall be based on the following:
Fire protection manual of fire sectional committee, Insurance association of India.
NFPA code of practice
1. Fire Fighting System connection with the existing firefighting network. (Refer attached Layout for Fire Fighting System).
Water Tapping to be done from existing 8” Fire Hydrant (U/G Line) tapping (E=2343.605M,N=939.874M) shall
be available from weigh bridge area of rolling plant.)
Fire Hydrant Ring Main to be done covering as per Plant layout
a) Unloading Hopper Shed.(68mx18m,1 No. Floor)
b) Along Pipe Conveyor Gallery PC-100(Approx. length=350m)
c) Pent-House.(6m x 6m, 1 No. Floor)
d) Transfer Tower TP-01.(12.250mx10.200m,4 Nos. of Floor)
e) Along Pipe Conveyor Gallery PC-200(Approx. length=665m)
f) Transfer Tower TP-02. (11mx10.200m,3 Nos. of Floor)
g) Along Pipe Conveyor Gallery PC-300(Approx. length=485m)
h) Transfer Tower TP-03. (11mx10.200m,3 Nos. of Floor)
i) MCC Room(22mx 12.2m,Floors-G+2Nos)
j) Blower & PLC Room. (10mx10m,Floors-G+1No.)
k) Watch Tower with Operating Cabin (5mx5m, 1 No. Floor)
a) Ring Main
b) Fire Hydrant Valve.
c) Hose Reel with Hose Reeling Drum.
d) M.S Double door Hose Box.
e) Water Monitor.
f) Fire Fighting Piping along with Fittings.
g) Manual Isolation Valves where ever required.
h) Additional accessories in order to complete the System.
Exclusions:
Firefighting water up to the battery limits.