Br. No 1/2 Estimate .

Bridge proper

Estimate of Bridge Proper and Protection Works

AS per APWD's SOR for Rural Roads for All Divisions .

Sl. No./
Amount In
SOR Item Unit Rate (Rs.) Quantity
Rs.
Clause

Dismantling
Labour for dismantling all members of the timber
bridge (except piles) and stacking them at suitable
1/16.10 places as directed (all members will be under Rm 577.00 24.00 13848.00
custody of the contractor till taken over by the
department)

Labour for taking out old piles of the bridge and


2/16.9 Each 682.00 60.000 40920.00
staking them at suitable places as directed.

Foundation
3/11.1
Excavation for structures : Earth work in
excavation for foundation of structures as per
drawings and technical specification clause 305.1,
including setting out, construction of shoring and
bracing, removal of stumps and other deeleterious
matter and disposal up to 50m,, dressing of sides
and bottom and back filling in trenches with
excavated suitable material.

I. Ordinary soil
A. Manual
means
(I) upto 3.0m depth m3 61.00 0.000 0.00
(ii) 3m to 6m depth m3 90.00 200.820 18073.80
4/16.56
Bored cast-in-situ M35 grade R.C.C. pile
excluding reinforcement complete as per drawing
and technical specification and removal of m 11101.00 256.000 2841856.00
excavated earth with all lifts and lead upto 1000m.
(Pile diameter-1000mm)
5/16.61 Pile load test on single vertical pile in accordance
with IS:2911 (Part-IV)

a) Initial and routine load test tonne 330.00 360.000 118800.00


6/16.62
Cement concrete for reinforced concrete in pile
cap complete as per drawing and Technical
Specification of MORTH Section
1100,1500&1700

B. RCC Grade M25 ( Using Concrete Mixer) m3 6365.00 113.520 722554.80

473196521.xlsx
Br. No 1/2 Estimate .Bridge proper

7/16.63
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap as per drawing
m3 5086.00 12.15 61794.90
and technical specification of MORTH Section
1100 & 1700

8/11.8
Supplying , fitting and placing TMT bar
reinforcement in foundation complete as per
tonne 67337.00 31.647 2131021.98
drawing and Technical Specifications clause 1000
& 1202.

9/16.41
Providing and construction of temporary island to
A(iii)
accommodate pile rig and other assessories
including casting of pile cap, all complete in depth Each 151360.00 0.000 0.00
of water up to 400cm (rate taken from item no.
16.41)
10/16.4 Providing and construction of one span service
1D road to reach island location from one pier Rm 2051.00 0.000 0.00
location to another pier location

Substructure
11/12.5 Plain/Reinforced Cement concrete, in Substructure
complete as per Drawing and Technical
Specifications as per MORTH Section
1500,1700,2200

F. RCC Grade M25(Using Concrete mixer)

I) Height up to 5.0m m3 6528.00 88.733 579246.18

II) Height 5.0m to 10.0m m3 6683.00 0.000 0.00


12/12.7
Supplying , fitting and placing TMT bar
reinforcement (Fe 415) in substructure complete
tonne 67418.00 10.422 702606.11
as per drawing and Technical Specifications
clause 1002, 1005, 1010 & 1202.

13/12.10 Backfill behind abutment, wing wall and return


wall complete as per drawings and technical
m3 1048.00 135.828 142347.74
specification clause 1204.3.8
i. Granular material.
14/12.12
Supplying, fitting and fixing in position true to
line and level elastomeric bearing conforming to
IRC:83(pt.II) section IX complete including all cm3 1.08 80640.00 87091.20
accessories as per drawing and Technical
Specification clause 1207.1.

473196521.xlsx
Br. No 1/2 Estimate .Bridge proper

Superstructure
Furnishing and placing reinforced / Prestressed
15/16.8 cement concrete in superstructure as per drawing
and Technical Specifications at clause 800,1205
and 1205 . A with crushed Stone.

B. RCC Grade M25 ( Using Concrete Mixer)

(II) For T-Beam and Slab


(p) Height up to 5.0 m m3 8010.00 95.50 764955.00
(q) Height 5.0 m to 10.0 m m3 8331.00 0.000 0.00
16/13.3 Supplying, fitting and placing un-coated TMT bar
reinforcement in super structure complete as per
tonne 70236.00 14.880 1045111.68
drawing and technical specifications clauses 1000
& 1202.
17/13.5
Providing and laying cement concrete wearing
coat M30 grade including reinforcement complete
m3 12292.00 14.243 175068.81
as per drawing and technical specifications clauses
800 and 1206.3. (B) With crushed stone.

18/13.6
Construction of RCC railing of M25Grade in cast
insitu with 20mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not
to exceed 1 in 500 centre to centre spacing m 2722.00 65.040 177038.88
between vertical post not to exceed 2000mm as
per drawing and technical specifications clauses
800,900 and 1208.3.

19/16.92
Drainage spouts complete as per approved
Each 8012.00 20 160240.00
drawings and technical specification clause 1209.

20/16.98
Burried Joint (Providing and laying a burried
expansion joint, expansion gap being 20mm,
covered with 12mm thick, 200mm wide
galvanised wieldable structural steel plate as per
IS:2062, placed symmetrical to centre line of the m 1406.00 16.90 23761.40
join, resting freely over the top surface of deck
concrete, welding of 8mm dia. 100mm long
galvanised nails spaced 300mm c/c along center
line of the plate, all as specified in clause 2604.

PCC M15 ordinary grade (1:2.5:5) in levelling


21/13.1 course below approach slab complete as per
m3 5196.00 5.425 28188.30
1A drawing and technical specifications clause 800
&1211

Providing and fixing 20mm thick compressible


22/16.9
fibre board in expansion joint complete as per m 325.00 16.900 5492.50
9 (ii)
drawing & Technical Specification clause 2605.

473196521.xlsx
Br. No 1/2 Estimate .Bridge proper

RCC approach slab with M25 grade approach slab


including reinforcent and form work complete as
23/13.1
per drawing and technical specifications clauses m 11471.00 16.275 186690.53
2
800 & 1211.
A. with crushed stone.

24
Carrying out SSI and preparation of DPR
including design and drawing of bridge including
approaches and protection complete as directed by m 0.00 43.500 0.00
the Engineer. A) For Bridge length less than 25
m ( as per accepted rate)

Construction of cold weather Bamboo bridge over


all width 3.70m and clear road way 3.0m with
26/16.1 m 9805.00 40.000 392200.00
jungle wood post 20 to 25 cm dia 5 nos in each
row and rows being 2.0m apart

Sub Total (A) = Rs. 10418907.82


PROTECTION WORKS
Providing and laying pitching on slopes laid over
prepared filter media as per drawing and Technical
19 Specification Clause 1302
Cum 126.60 1091.000 138120.79
(i) Stone/Boulder
Providing and laying filter material underneath
20 pitching in slopes complete as per drawing and Cum 63.30 1455.000 92101.63
Technical Specification Clause 1302
21 Proiding and laying boulder apron for bed protection
with stone boulder of minimum size and weight as per
table 1300.1, no fragment weighing less than 25 kg laid Cum
dry complete as per drawing and technical specification
Clause 1301 357.54 1091.00 390076.95
620299.37

Sub Total (B) = Rs. 620299.37


Total (A) + (B) =Rs. 11039207.18
Total cost of bridge project including protection works.= Rs. 11039207.00

#NAME?

473196521.xlsx
Br. No 1/2 Estimate .Bridge proper

Estimate of Bridge Proper and Protection Works

AS per APWD's SOR for Rural Roads for All Divisions .

Sl. No./
Amount In
SOR Item Unit Rate (Rs.) Quantity
Rs.
Clause

Dismantling
Labour for dismantling all members of the timber
bridge (except piles) and stacking them at suitable
1/16.10 places as directed (all members will be under Rm 577.00 24.00 13848.00
custody of the contractor till taken over by the
department)

Labour for taking out old piles of the bridge and


2/16.9 Each 682.00 60.000 40920.00
staking them at suitable places as directed.

Foundation
3/11.1
Excavation for structures : Earth work in
excavation for foundation of structures as per
drawings and technical specification clause 305.1,
including setting out, construction of shoring and
bracing, removal of stumps and other deeleterious
matter and disposal up to 50m,, dressing of sides
and bottom and back filling in trenches with
excavated suitable material.

I. Ordinary soil
A. Manual
means
(I) upto 3.0m depth m3 61.00 0.000 0.00
(ii) 3m to 6m depth m3 90.00 200.820 18073.80
4/16.56
Bored cast-in-situ M35 grade R.C.C. pile
excluding reinforcement complete as per drawing
and technical specification and removal of m 11101.00 256.000 2841856.00
excavated earth with all lifts and lead upto 1000m.
(Pile diameter-1000mm)
5/16.61 Pile load test on single vertical pile in accordance
with IS:2911 (Part-IV)

a) Initial and routine load test tonne 330.00 360.000 118800.00


6/16.62
Cement concrete for reinforced concrete in pile
cap complete as per drawing and Technical
Specification of MORTH Section
1100,1500&1700

B. RCC Grade M25 ( Using Concrete Mixer) m3 6365.00 113.520 722554.80

473196521.xlsx
Br. No 1/2 Estimate .Bridge proper

7/16.63
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap as per drawing
m3 5086.00 12.15 61794.90
and technical specification of MORTH Section
1100 & 1700

8/11.8
Supplying , fitting and placing TMT bar
reinforcement in foundation complete as per
tonne 67337.00 31.647 2131021.98
drawing and Technical Specifications clause 1000
& 1202.

9/16.41
Providing and construction of temporary island to
A(iii)
accommodate pile rig and other assessories
including casting of pile cap, all complete in depth Each 151360.00 0.000 0.00
of water up to 400cm (rate taken from item no.
16.41)
10/16.4 Providing and construction of one span service
1D road to reach island location from one pier Rm 2051.00 0.000 0.00
location to another pier location

Substructure
11/12.5 Plain/Reinforced Cement concrete, in Substructure
complete as per Drawing and Technical
Specifications as per MORTH Section
1500,1700,2200

F. RCC Grade M25(Using Concrete mixer)

I) Height up to 5.0m m3 6528.00 88.733 579246.18

II) Height 5.0m to 10.0m m3 6683.00 0.000 0.00


12/12.7
Supplying , fitting and placing TMT bar
reinforcement (Fe 415) in substructure complete
tonne 67418.00 10.422 702606.11
as per drawing and Technical Specifications
clause 1002, 1005, 1010 & 1202.

13/12.10 Backfill behind abutment, wing wall and return


wall complete as per drawings and technical
m3 1048.00 135.828 142347.74
specification clause 1204.3.8
i. Granular material.
14/12.12
Supplying, fitting and fixing in position true to
line and level elastomeric bearing conforming to
IRC:83(pt.II) section IX complete including all cm3 1.08 80640.00 87091.20
accessories as per drawing and Technical
Specification clause 1207.1.

473196521.xlsx
Br. No 1/2 Estimate .Bridge proper

Superstructure
Furnishing and placing reinforced / Prestressed
15/16.8 cement concrete in superstructure as per drawing
and Technical Specifications at clause 800,1205
and 1205 . A with crushed Stone.

B. RCC Grade M25 ( Using Concrete Mixer)

(II) For T-Beam and Slab


(p) Height up to 5.0 m m3 8010.00 95.50 764955.00
(q) Height 5.0 m to 10.0 m m3 8331.00 0.000 0.00
16/13.3 Supplying, fitting and placing un-coated TMT bar
reinforcement in super structure complete as per
tonne 70236.00 14.880 1045111.68
drawing and technical specifications clauses 1000
& 1202.
17/13.5
Providing and laying cement concrete wearing
coat M30 grade including reinforcement complete
m3 12292.00 14.243 175068.81
as per drawing and technical specifications clauses
800 and 1206.3. (B) With crushed stone.

18/13.6
Construction of RCC railing of M25Grade in cast
insitu with 20mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not
to exceed 1 in 500 centre to centre spacing m 2722.00 65.040 177038.88
between vertical post not to exceed 2000mm as
per drawing and technical specifications clauses
800,900 and 1208.3.

19/16.92
Drainage spouts complete as per approved
Each 8012.00 20 160240.00
drawings and technical specification clause 1209.

20/16.98
Burried Joint (Providing and laying a burried
expansion joint, expansion gap being 20mm,
covered with 12mm thick, 200mm wide
galvanised wieldable structural steel plate as per
IS:2062, placed symmetrical to centre line of the m 1406.00 16.90 23761.40
join, resting freely over the top surface of deck
concrete, welding of 8mm dia. 100mm long
galvanised nails spaced 300mm c/c along center
line of the plate, all as specified in clause 2604.

PCC M15 ordinary grade (1:2.5:5) in levelling


21/13.1 course below approach slab complete as per
m3 5196.00 5.425 28188.30
1A drawing and technical specifications clause 800
&1211

Providing and fixing 20mm thick compressible


22/16.9
fibre board in expansion joint complete as per m 325.00 16.900 5492.50
9 (ii)
drawing & Technical Specification clause 2605.

473196521.xlsx
Br. No 1/2 Estimate .Bridge proper

RCC approach slab with M25 grade approach slab


including reinforcent and form work complete as
23/13.1
per drawing and technical specifications clauses m 11471.00 16.275 186690.53
2
800 & 1211.
A. with crushed stone.

24
Carrying out SSI and preparation of DPR
including design and drawing of bridge including
approaches and protection complete as directed by m 0.00 43.500 0.00
the Engineer. A) For Bridge length less than 25
m ( as per accepted rate)

Construction of cold weather Bamboo bridge over


all width 3.70m and clear road way 3.0m with
26/16.1 m 9805.00 40.000 392200.00
jungle wood post 20 to 25 cm dia 5 nos in each
row and rows being 2.0m apart

Sub Total (A) = Rs. 10418907.82


PROTECTION WORKS
Providing and laying pitching on slopes laid over
prepared filter media as per drawing and Technical
19 Specification Clause 1302
Cum 126.60 1091.000 138120.79
(i) Stone/Boulder
Providing and laying filter material underneath
20 pitching in slopes complete as per drawing and Cum 63.30 1455.000 92101.63
Technical Specification Clause 1302
21 Proiding and laying boulder apron for bed protection
with stone boulder of minimum size and weight as per
table 1300.1, no fragment weighing less than 25 kg laid Cum
dry complete as per drawing and technical specification
Clause 1301 357.54 1091.00 390076.95
620299.37

Sub Total (B) = Rs. 620299.37


Total (A) + (B) =Rs. 11039207.18
Total cost of bridge project including protection works.= Rs. 11039207.00

#NAME?

473196521.xlsx
Estimate of Bridge Proper and Protection Works

AS per APWD's SOR for Rural Roads for All Divisions for 2016-17

Sl. No./ Reference to Amount In


SOR Item MORT&H Unit Rate (Rs.) Quantity
Specifications Rs.
Clause
Labour for dismantling all
Dismantling
members of the timber bridge
(except piles) and stacking them
1/16.10 at suitable places as directed (all Rm 577.00 0.00 0.00
members
Labour forwill
Excavation forbe under
structures
taking out oldcustody
:piles
Earth
of
workthe contractor till taken over
2/16.9 of thein excavation
bridge for them
and staking at Each 682.00 0.000 0.00
by the department)
foundation of structures as per
suitable places as directed.
drawings and technical
Foundation
specification clause 305.1,
3/11.1 including setting out,
construction of shoring and
I. Ordinary
bracing, soil of stumps and
removal
other deeleterious matter and
disposal up to 50m,,A.dressingManualof
means
sides and bottom and back
(I) uptoin3.0m
filling depthwith
trenches m3 61.00 0.000 0.00
excavated suitable
Bored cast-in-situ M35 material.
grade
R.C.C.
(ii) 3m pile
to 6m excluding
depth m3 90.00 223.200 20088.00
reinforcement complete as per
4/16.56 drawing and technical
m 11101.00 288.000 3197088.00
specification and removal of
5/16.61 Pile load test
excavated on with
earth singleallvertical
lifts and
pile
lead in accordance
upto 1000m.(Pilewithdiameter-
IS:2911
(Part-IV)
1000mm)
a) Initial and routine load test tonne 330.00 352.000 116160.00
Cement concrete for reinforced
6/16.62 concrete in pile cap complete as
per drawing and Technical
Specification of MORTH
B. RCC 1100,1500&1700
Section Grade M25 ( Using
Providing and laying of PCC m3 6365.00 113.520 722554.80
Concrete Mixer)
M15 levelling course 100mm
7/16.63 thick below the pile cap as per
Supplying , fitting and placing m3 5086.00 12.15 61794.90
drawing and technical
TMT bar reinforcement in
8/11.8 specification
Providing
foundationand ofconstruction
MORTH
complete as per of
Section 1100 & 1700 tonne 67337.00 27.552 1855275.61
temporary
drawing and island to
Technical
9/16.41A( accommodate
Specifications pile rig1000
clause and other
&
iii) assessories
1202. including casting of Each 151360.00 0.000 0.00
Providing
pile cap, alland construction
complete of of
in depth
10/16.41 one
waterspan service
up to 400cm road to taken
(rate reach
D Rm 2051.00 0.00
island location
from item from one pier
no. 16.41)
location to another pier location
Substructure
Plain/Reinforced Cement
concrete, in Substructure
11/12.5 complete as per Drawing and
Technical Specifications as per
MORTH Section
1500,1700,2200
F. RCC Grade M25(Using
Concrete mixer)

I) Height up to 5.0m m3 6528.00 47.163 307880.06

Supplying , fitting
II) Height 5.0m and placing
to 10.0m m3 6683.00 0.000 0.00
TMT bar reinforcement (Fe 415)
12/12.7 in substructure complete as per
Backfill behind abutment, wing tonne 67418.00 3.702 249601.36
drawing
wall and and Technical
return wall complete as
Supplying, fitting
Specifications
13/12.10 per drawings and and1002,
clause fixing in
technical
position true&to1202.
1005, 1010 line and level m3 1048.00 128.225 134379.41
specification clause 1204.3.8
elastomeric bearing conforming
14/12.12 to IRC:83(pt.II) section IX i.
Granular material. cm3 1.08 80640.00 87091.20
complete including all
Furnishing
accessories and placing
as per drawing and
Superstructure
reinforced / Prestressed cement
Technical Specification clause
concrete
1207.1. in superstructure as per
15/16.8 drawing and Technical
Specifications at clause
800,1205 and 1205 . A( Using
with
B. RCC Grade M25
crushed Stone.
Concrete Mixer)

(II) For T-Beam and Slab

(p) Height up to 5.0 m m3 8010.00 61.20 490212.00

Supplying,
(q) Height 5.0 fitting
m toand 10.0placing
m m3 8331.00 0.000 0.00
un-coated TMT bar
16/13.3 Providing
reinforcement and laying supercement
Construction ofinRCC structure
railing of tonne 70236.00 12.080 848450.88
concrete
complete wearing
as per coat
drawing M30 and
M25Grade in cast insitu with
17/13.5 grade
20mmincluding
technicalnominal reinforcement
specifications
size clauses
aggregate,
complete
1000
Burried& as
1202.
Joint
true to line per
and drawing
(Providing and
and
grade, tolerance m3 12292.00 10.913 134136.45
technical
laying specifications
a burried expansion clauses
18/13.6 of vertical RCC post not to joint,
800 and 1206.3.
expansion gap (B) With
being 20mm, m 2722.00 53.200 144810.40
exceed 1 in 500 centre to centre
crushed
covered stone.
with 12mm thick,post
spacing
Drainagebetween vertical
spouts complete as per
19/16.92 200mm wide galvanised
not to exceed 2000mm as per
approved drawings and technical Each 8012.00 8 64096.00
wieldable
drawing and structural
technical steel plate
specification clause 1209.
20/16.98 as per IS:2062,
specifications placed
clauses 800,900
symmetrical
and 1208.3. to centre line of the m 1406.00 15.00 21090.00
PCC M15 ordinary grade
join, resting freely over the top
(1:2.5:5) in levelling course
21/13.11 surface of deck concrete,
below approach slab complete as m3 5196.00 13.500 70146.00
A Providing
welding ofand 8mm fixing
dia. 20mm
100mm
per
RCC drawing
approach andslabtechnical
with M25 in
thick compressible
long galvanised fibre
nails board
spaced
22/16.99 specifications clause 800 &1211
grade
300mm approach
expansion c/cjoint
along slab including
complete
center as per
line of m 325.00 15.000 4875.00
(ii)
reinforcent
drawing
the plate, & and form
Technical
all as work
specified in
Carrying out SSI and
complete
Specificationas per drawing
2605.and
23/13.12 clause 2604.
preparation ofclause
DPR including m 11471.00 13.500 154858.50
technical specifications clauses
design and drawing of bridge
24 800 & 1211.
including approaches and
Construction of cold A. withweather
crushed m 2500.00 0.000 0.00
protection complete as directed
Bamboo
stone. bridge over all width
by the Engineer. A) For
3.70m and clear road way 3.0m
26/16.1 Bridge length less than 25 m m 9805.00 15.000 147075.00
with jungle wood post 20 to 25
( as per accepted rate)
cm dia 5 nos in each row and
rows being 2.0m apart
Sub Total (A) = Rs. 8831663.57

PROTECTION WORKS
Providing and laying pitching on
slopes laid over prepared filter
media as per drawing and
19 Technical Specification Clause
Cum 1091.000 53.216
1302
Providing and laying filter 58058.41
(i) Stone/Boulder
material underneath pitching in
20 slopes complete as per drawing Cum 1455.000 53.216
and Technical Specification 77428.96
21 Clause 1302
Proiding and laying boulder apron
for bed protection with stone
boulder of minimum size and
weight as per table 1300.1, no
fragment weighing less than 25 kg
Cum
laid dry complete as per drawing
and technical specification Clause
1301 1091.00 100.98 110166.15
Sub Total (B) = Rs. 187595.10
Total (A) + (B) =Rs. 9019258.68

Total cost of bridge project including protection works.= Rs. 9019259.00