Table 2. SUMMARY STATUS OF ENVIRONMENTAL IMPACT MANAGEMENT AND MONITORING PLAN IMPLEMENTATION
To anticipate the Environmental hazard Reliability Pumping No No > Negative . Adequate plans for
impact and implement Natural due to accidents, stations reported reported Impact environmental
contingency action Disasters man-made natural accidents accidents > Unlikely to rehabilitation and
plans disasters eg: fires, occur restoration of site
accidental spills, > Reversible and removal of
earthquake temporary structures
> Short term and facilities installed
> Insignificant during construction
( Magnitude) phase
.Safety precautions
such as lighting and
warning signs
around the construction
site
Monitor the volume Solid waste generated Volume of Waste Pumping . Solid waste generated
of solid waste within the facility Stations within the pumping
and by the facility stations will be minimal
but provision will be
made for garbage
collection