Professional Documents
Culture Documents
intersections require only cut or only fill, then we can use the following method.
10 m
a b a
4 2 4
a c d c b a
4 3 2 3 4 5
10 m
b d d d c a
4 3 5 2 2 3
a c d c a
5 4 2 2 2
a b a
3 1 1
𝑏 = 2 + 4 + 4 + 1 = 11
𝑐 = 3 + 3 + 2 + 4 + 2 = 14
𝑑 = 2 + 3 + 5 + 2 + 2 = 14
10 × 10
𝑉𝑜𝑙𝑢𝑚𝑒 = × (31 + 2 × 11 + 3 × 14 + 4 × 14) = 3775 𝑚3
4
21
2.2.3 Average End Area
The average end area method of quantifying cut and fill is often used when dealing with long
narrow tracts, such as for roads. In this method, the site is divided into stations, as shown in the
following figure.
100’ 75’
STATION 03
STATION 01
STATION 02
The first step in determining the volume using the average end area method is to draw a profile at
the station lines. Next, the cut and fill area for each of the profiles is calculated, and finally, the cut
or fill area of two adjacent profiles is averaged and multiplied by the distance between the two
stations to determine the cut and fill quantity between the stations.
The following figure shows the profile for Station 01. Because these profiles are drawn to scale, the
area can be calculated easily by breaking up these profiles into rectangles and triangles.
22
Example: Cut between station 1 and 2 is calculated as follows:
114.3+232.4
𝐶𝑢𝑡 = × 75′ = 13,001𝑐𝑓
2
23
2.2.3 General Excavation
Included under general (mass) excavation is the removal of all types of soil that can be handled in
fairly large quantities, such as excavations required for a basement, mat footing, or a cut for a
highway or parking area.
1. Building dimensions.
3. The amount of working space required between the edge of the footing and the beginning of
excavation.
4. The elevation of the existing land, by checking the existing contour lines on the site plan.
If job conditions will not allow the sloping of soil, the estimator will have to consider using sheet
piling or some type of bracing to shore up the bank.
When sloping sides are used for mass excavations, the volume of the earth that is removed is found
by developing the average cut length in both dimensions and by multiplying them by the depth of
the cut.
C B A L A B C
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 𝐸𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 = 𝐿𝑒𝑛𝑔𝑡ℎ × 𝑊𝑖𝑑𝑡ℎ × 𝐷𝑒𝑝𝑡ℎ = 𝐿𝑥 × 𝐿𝑦 × 𝐷
24
Example:
Determine the amount of general excavation required for the basement portion of the building
shown in the following figure. Assume the workspace between the edge of the footing and the
beginning of the excavation will be 0.5 m, by checking the existing contour lines on the site plan the
expected depth of the cut is 3 m after a deduction for the topsoil that would have already been
removed, and a slope of 2:1 for soil will be used, which means for every 2 m of vertical depth an
additional 1 m of horizontal width is needed, rather than using shoring or sheet piling.
1 2 3 4 5
8.00 m
T T
AREA
F1
B B
7.50 m
7.50 m
C C
3.00 m
3.00 m
F1
D D
0.3 m
1.5 m
0.3 m
F1
0.3 m
1.5 m
C1 0.3 m
0.4 m 0.3 m
m
Section (1-1)
0.3 m
0.4 m
0.4 m
0.1 m
Cross-Sections of Footings
25
Solution:
L= 10 m in x-direction or 8 m in y-direction
A= 1.5/2 m
B= 0.5 m
D C= 1.5 m
D= 3 m
C B A L A B C
26
27
Column
Column
Column
Continuous Foot
28
2.2.3.2 Continuous Footing Excavation
Example:
Determine the amount of general excavation required for the continuous footings of the building
shown in the building plan and the cross-sections drawings. Assume that the slope of the soil will
be 1.5:1, the working area will be 0.5 m, and the depth of excavation will be 1.5 m.
Solution:
0.3 m
1.50 m
1.50 m
0.4 m
1.00 m 0.1 m 1.00 m
1.5 m
Length of Cut = A1toA2 + A3toA4 + A4toB4 + B4toB5 + B5toD5 + D5toD3 + D3toC3 + C3toC2
+ C2toD2 + D2toD1 + D1toA1 – Width of cut already calculated in the basement excavation
1.125 m
Continuous Footing m2.25 m 3m
2
1
Basement
1.5 m 0.5 m 0.75
m
= 91 m
29
2.2.3.3 Spread Footing Excavation
Example:
There are 3 spread footings shown in building figure. Given that the soil slope should be 1.5:1, the
working distance should be 0.5 m, the cut depth will be 1.5 m, and the footing is square. Calculate
the excavation volume?
0.3 m
1.50 m
1.50 m
0.4 m
1.00 m 0.1 m 1.00 m
1.5 m
30
2.2.4 Backfilling
Exterior Wall
Exterior Wall
D Building Volume
Continuous Continuous
Foot Df Foot
Db
Pf W Pf
Backfill Side-view Section
1.5−.3 1.7−.3
𝑃𝑓 = = 0.6 𝑚 , 𝑃𝑏 = = 0.7 𝑚 Pb
2 2
10.00 m
12.00 m
8.00 m
BASEMENT
AREA
14.00 m
31