Professional Documents
Culture Documents
Pert CPM Comment
Pert CPM Comment
Joebert Duran
Specialization 3
17 April 2020
Example # 1
component for a complex system, is shown in thefigure. Each circle on the diagram represents
a task or well-defined activity that is part of the project. The number in each circle represents the
Network diagram for the Critical Path Method problem. Encyclopedia Britannica, Inc.
Task A requires two weeks to complete and might, for example, represent the
development of general specifications for an electronic unit in question. Tasks B and E might
represent two related parts of the design of the unit’s power supply, C and F the design of the
Duran 2
main functional circuits, and D and G the design of the control circuitry. Arrows indicate
the precedence of relationships and depict which tasks must be completed before subsequent
tasks can begin. In this example, tasks B, C, and D cannot be started until A has been
completed (that is, no one can design specific component items before the general
Task H requires two weeks to complete but cannot be started until the designs of the
power supply and the functional and control circuits have been completed. This task might
represent the design of the unit’s case or cover, and the case cannot be made final until all of
The arrow diagram is an invaluable planning aid for determining how long a project
will take to complete. Adding all of the task times together in the example indicates that there
are 24 weeks of work to be completed. Note, however, that several tasks can be done
simultaneously. For example, once task A has been completed, B, C, and D can be started and
worked on concurrently. Thus, the earliest completion date can be determined by looking at all
possible “paths” through the network and choosing the longest one, or the one with tasks
requiring the most total time. In this example the longest, or “critical,” path is A–C–F–H,
The arrow diagram yields additional information to the project planner. The earliest
possible time that task H can be started is nine weeks after the start of the project (that is, after
tasks A, C, and F have been completed). When task A is completed at the end of week 2, tasks
B and E do not have to be started immediately in order to complete the project in the minimum
possible time; B and E each have three weeks of “slack.” The diagram shows that if activity B is
started three weeks later than its earliest possible start time (at week 5), it would be completed
Duran 3
at the end of week 5; E would then start at the beginning of week 6 and be completed in time for
The notion of slack in a project network is a powerful concept that allows planners to
schedule scarce resources efficiently and manage people and equipment so that critical
activities are kept on schedule and slack activities are delayed without placing the project in
jeopardy.
This simple example is based on CPM logic; it uses single-point task time estimates
and assumes that the completion time for the project is the simple sum of the task times along
the critical path. PERT logic assumes probabilistic estimates for each task time, with
pessimistic, realistic, and optimistic estimates for the completion times of each task.
In actual projects the relationships among the required tasks are often complex, and
the arrow diagram for the project might cover the entire wall of an office. Even though it is a
time-consuming job to work out arrow diagrams, precedence relationships, task time estimates,
and so on for large projects, CPM or PERT is an invaluable aid to planning and control. The
proliferation of computer programs that handle critical path and slack time calculations and the
development of computer systems capable of handling cost estimates, budget control, resource
allocation, and time scheduling promise to make CPM and PERT even more valuable than in
Example # 2
Immediate Estimated
Activity Activity Description Predecessors Duration
A Excavate — 2 weeks
B Lay the foundation A 4 weeks
C Put up the rough wall B 10 weeks
D Put up the roof C 6 weeks
E Install the exterior plumbing C 4 weeks
F Install the interior plumbing E 5 weeks
G Put up the exterior siding D 7 weeks
H Do the exterior painting E, G 9 weeks
I Do the electrical work C 7 weeks
J Put up the wallboard F, I 8 weeks
K Install the flooring J 4 weeks
L Do the interior painting J 5 weeks
M Install the exterior fixtures H 2 weeks
N Install the interior fixtures K, L 6 weeks
G 7 F 5
J 8
H 9
K 4 L 5
M 2
N 6
F IG U R E 1 0 .1
The p r o j e c t n e t w o r k for t h e
Reliable C o n s t r u c t i o n C o .
p ro je c t. FINISH 0
Duran 5
Comment: When do you relieve the personnel using the Pert and CPM?
The critical path method (CPM) is a staple of construction schedulers. Owners often
require a critical path analysis. Construction management programs have taught CPM for
decades, and courts use critical path schedules as evidence in construction disputes.
However, CPM intimidates many people because they find it complex and time
consuming. Some construction superintendents and foremen view critical path as a theoretical
abstraction that is irrelevant to their work. They believe that construction realities in the field
should drive the schedule — with this approach, however, efficiency generally suffers (Diana
Ramos).
A PERT chart makes planning large projects easier; it answers three key questions
about each activity that help managers identify relationships between tasks and task
dependencies. These questions involve how long it will take to complete an activity, and which
other activities must occur immediately before and immediately after this activity for effective
project completion. PERT is a good way of making these relationships visible in a diagram
The critical path includes all activities that cannot be delayed without affecting the
project completion date. PERT makes the critical path visible. All tasks not on the critical path
can have some slack time without affecting project completion time. When the project manager
must delay one task to allocate more time to another, the critical path makes clear which tasks
Pert and CPM is controlling projects that contain unknown and unpredictable factors.
When the projects are not complex, bar charts can be used to plan and control project activities.
These charts divide the project into discrete activities or tasks and analyze each task
Duran 6
individually to indicate weekly manpower requirements. As the work goes forward, progress is
charted and estimates are made on the effects of any delays or difficulties encountered during
Works Cited
Holstein., Distinguished Service Professor of Business, State University of New York at Albany.
others.https://www.britannica.com/topic/research-and-development/PERT-and-CPM
fbclid=IwAR307LVARPv1HNx1FuW8zdF4nmt2EyQ8KVVn3hjkqtUN5M7taU6CR6AkwXQ
pert-advantages-and-disadvantage/?
fbclid=IwAR3qWDZb0uPTTI5n7efLn4hWekE_1VQuBZGrIdA4EaPUEnjjvC4WFT6g93c