You are on page 1of 190

CHAPTER : S-4

TUBE WELL
CHAPTER : S-4
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
4.1 Construction of tube-well from ground level and upto 100 Meter
depth and above sizes in all types of soils in alluvium strata by
“bailing” method and without gravel packing as per IS: 2800
(Part - I& II) 1979 specifications (The work includes formation of
cavity well at bottom by development with appropriate air
compressor or bailer pumping and also lowering of casing pipe
but excluding cost of the casing pipe. The tube-well should have
a throughout bore as per nominal bore of casing pipe. The work
would be completed after obtaining sand free water.)

4.1.1 100 mm dia Nominal bore. R Mtr. 380.00 326.00 16.56% 358.00 9.82%

4.1.2 125mm-do-. R Mtr. 444.00 381.00 16.54% 419.00 9.97%

4.1.3 150mm-do- R Mtr. 533.00 433.00 23.09% 476.00 9.93%

4.2 Construction of Tube-well upto 100 Meter depth and above in all
type of rocks by DTH system and over burden, to accommodate
casing pipe of following sizes in all types of soils and over
burden including lowering of casing pipes, but excluding cost of
casing pipes as per IS : 2800 (Part I & II) 1979 specifications.
The work would be completed after obtaining sand free water.
The tube well should have a throughout bore as per nominal dia
of casing pipe:

4.2.1 100 mm dia Nominal bore. R.Mtr. 856.00 477.00 79.45% 524.00 9.85%

4.2.2 125mm-do-. R.Mtr. 894.00 552.00 61.96% 607.00 9.96%

4.2.3 150mm-do- R.Mtr. 1062.00 834.00 27.34% 917.00 9.95%

4.2.4 200 mm –do- R.Mtr. 1379.00 1035.00 33.24% 1,138.00 9.95%

4.3 Construction of tube-well from ground levels and upto 100


Meter depth and above to accommodate housing and assembly
pipe of following sizes in all types of alluvium strata by
percussion/ rotary drilling method and with gravel as per
IS:4097-1967 and packing as per IS:2800 (Part I -& II) 1979 as
amended upto date (the work includes the cost of gravel & its
primary packing and packing during development, lowering of
housing & strainer assembly pipes, with supply and wrapping of
coir-rope, wherever necessary, for arresting fine sand particles.
The work will not include cost of housing pipe and strainer pipe
assembly and development work, but work would be completed
after obtaining sand free water).

4.3.1 150 mm Nominal bore. R Mtr. 1278.00 1278.00 0.00% 1,278.00 0.00%

4.3.2 200mm –do-. R Mtr. 1757.00 1757.00 0.00% 1,757.00 0.00%

4.3.3 250mm –do-. R Mtr. 2236.00 2236.00 0.00% 2,236.00 0.00%

4.4 Development of tube well as per IS specification using suitable Hr. 718.00 718.00 0.00% 718.00 0.00%
compressor to give sand free water for required yield of the
gravel packed tube well.

4.5 Supply of ERW M.S. black casing pipe ISI marked


(IS:4270/1992) of grade Fe410 of following sizes at site of work.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-4
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
C. Code Nominal bore of pipe (mm) Outsid Thickness Mass of Unit Proposed
No. e dia of of Pipe plane tube Rate
Pipe (mm) (kg.\m)
(mm)

4.5.1 100 114.3 5.0 13.48 Mtr. 791.00 788.00 0.38% 791.00 0.38%

4.5.2 125 141.3 5.0 16.80 Mtr. 985.00 982.00 0.31% 985.00 0.31%

4.5.3 150 168.3 5.0 20.13 Mtr. 1179.00 1176.00 0.26% 1,179.00 0.26%

4.5.4 200 219.0 5.4 28.46 Mtr. 1665.00 1660.00 0.30% 1,665.00 0.30%

4.5.5 250 273.0 7.1 46.57 Mtr. 2721.00 2715.00 0.22% 2,721.00 0.22%

4.6 Supply of strainer pipes made of ERW M.S. black pipe ISI mark
of following sizes at the site of work including required size of
slotting as per IS:8110-1985.

4.6.1 150 mm Nominal Bore. Mtr. 1479.00 1328.00 11.37% 1,460.00 9.94%

4.6.2 200mm-do-. Mtr. 1965.00 1812.00 8.44% 1,965.00 8.44%

4.6.3 250mm-do-. Mtr. 3021.00 2866.00 5.41% 3,021.00 5.41%

4.7 Testing verticality of tube-well by plumbing system and yield test Each 9979.00 9979.00 0.00% 9,979.00 0.00%
and draw down test by pumping system as per IS: 2800 (Part II)
1979.

4.8 S & F tube well cover of M.S.sheet (6mm thick) with nuts and
bolts complete for casing size:
4.8.1 100mm dia Each 245.00 234.00 4.70% 245.00 4.70%

4.8.2 125mm dia Each 297.00 284.00 4.58% 297.00 4.58%

4.8.3 150mm dia Each 367.00 351.00 4.56% 367.00 4.56%

4.8.4 200mm dia Each 490.00 469.00 4.48% 490.00 4.48%

4.8.5 250mm dia Each 523.00 501.00 4.39% 523.00 4.39%

4.9 S & F M.S. clamp, set of 50 ×6mm flat iron with nuts and bolts Each 350.00 334.00 4.79% 350.00 4.79%
etc. for holding the riser pipe assembly of submersible pump
set.
4.10 Supply of 50mm dia G.I. medium class pipe(each length 5.8 m Each 15711.00 15028.00 4.54% 15,711.00 4.54%
to 6.0m) tripod as per drawing and design with chain pulley of.
3MT capacity
4.11 Installation of submersible motor pump set in Tube-well/open 4888.00 4675.00 4.56% 4,888.00 4.56%
well complete ( labour charges only) including transportation of Each
tripod, chain pulley block & any other material required for
lowering purpose.

4.12 P & F 60 cm. wide M.S. ladder in open well made of flat iron 297.00 284.00 4.58% 297.00 4.58%
32×5mm and 10mm dia bars @ 200mm c/c with angle iron hold Mtr.
fasts at suitable interval complete as per drawing.

4.13.1 Installation of India mark II hand pump set, complete on existing Each 1222.00 1169.00 4.53% 1,222.00 4.53%
plate form.
4.13.2 Construction of 185 cm. dia platform as per approved design Each 3841.00 3674.00 4.55% 3,841.00 4.55%
and drawing of UNICEF.

4.14 Supplying of India mark II hand pump set complete ISI marked Each 11347.00 10854.00 4.54% 11,347.00 4.54%
with cylinder and ten connecting rods etc. ISI

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-4
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

4.15 Supplying and installation of 32 mm dia G.I. pipe medium class Mtr. 307.00 294.00 4.42% 307.00 4.42%
ISI marked in 3m length including all accessories and fittings
required for installation of hand pump.

4.16 Supplying and installation of submersible pumping motor pump


sets I.S.I. Marked (IS : 8034-1989 ) of approved make like
K.S.B., KIRLOSKAR, Calama etc. or equivalent, making
connection suitable for T.W./D.C.B./Open well. The job includes
screwing and welding of flanges on G.I. riser pipes, installation
of complete fitting and accessories, with riser pipes, jointing of
electrical cables and other connections making switch board
electrical connections, all labour for testing of submersible pump
set and supply of water to water mains, complete in all respect
(Refer Electrical BSR )

4.17 For item of earthing refer to Electrical


BSR .

4.18 For item of submersible cable refer to Electrical


BSR.

4.19 Item of panel board if required shall be as per design and


specification approved by the Engineer In-charge as per the
requirement.
4.20 Providing & lowering of G.I. Pipes, flange pipe including rubber
washer and nuts of 8 mm dia complete in all respect I.S.I.
Make.
4.20.1 B Class 50 mm dia R. Mtr. 343.00 343.00 0.00% 343.00 0.00%

4.20.2 B Class 80 mm dia R. Mtr. 611.00 584.00 4.62% 611.00 4.62%

4.20.3 B Class 100 mm dia R. Mtr. 943.00 902.00 4.55% 943.00 4.55%

4.21 Un-lowering of submersible pump set with all piping from a Each 6110.00 5844.00 4.55% 6,110.00 4.55%
tube-well/ open-well complete (labour charge only ) including Job
transportation of tripod, chain, pulley-block and other materials
required and lowering of repaired/ new pump in the tube-well /
open-well complete in all respect.

4.22 Construction of Recharge Shaft in filter pit including Earth


work Excavation , lifting excavted earth with all lift and 50
m lead and centering & shuttering evenever required.

4.22.1 Diameter 900 mm Rm 242.00 242.00 0.00% 242.00 0.00%


4.22.2 Diameter 750 mm Rm 212.00 212.00 0.00% 212.00 0.00%

4.23 Supply & fixing Pre-cast RCC Rinngs at the mouth of


recharge shaft of M20 mix with 40 mm thickness
4.23.1 Diameter 900 mm Rm 696.00 696.00 0.00% 696.00 0.00%
4.23.2 Diameter 750 mm Rm 605.00 605.00 0.00% 605.00 0.00%

4.24 Supply & lowering air line of 25mm dia, G.I. pipe 'B' class
having perforation 3 to 5mm size all arrow of G.I. pipe in
Zig-Zag fashion & making air vent at top including the cost
of Tee-Nipples, Elbow, Socket etc.
Rm 273.00 273.00 0.00% 273.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-4
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
4.25 Supply and lowering vent air pipe 63mm dia rigid PVC
pipe(IS 4985) mark class II (4kg per cm2 ) with required all
necessary fittings including perforation of 3 to 5 mm size
all around the pipe at a distance of 180 to 220mm in zig
zag fashion and making air vent at top complete as per
direction of Engineer incharge.
Rm 140.00 140.00 0.00% 140.00 0.00%

4.26 Supply & lying River-gravels of following sizes in recharge


shaft, filter pit after screening & washing from kachha shift
without deduction of voids

4.26.1 Size 9 to 12 mm Cum 1815.00 1815.00 0.00% 1,815.00 0.00%


4.26.2 Size 3 to 5 mm Cum 2662.00 2662.00 0.00% 2,662.00 0.00%

4.27 Supply & laying of clean, clear sharp river sand of size 1 to
2mm coarse, without deduction of voids. Cum 3388.00 3388.00 0.00% 3,388.00 0.00%

83214.00 79157.00 5.13% 82086.00 3.70%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
DRAINAGE / DISPOSAL WORKS
CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

STONEWARE PIPES & FITTING

3.1 Providing Laying & jointing glazed S.W. pipes grade `A` (IS;651
marked) of approved make with spun yarn & stiff mixture of
cement mortar 1:1, excavation & refilling of earth in all types of
soil upto 1.2m depth, S.W. fittings, including testing of joints etc,
complete.

3.1.1 100mm dia P.Mtr. 125.00 125.00 0.00% 125.00 0.00%

3.1.2 150mm dia P.Mtr. 218.00 218.00 0.00% 218.00 0.00%

3.1.3 200mm dia P.Mtr. 363.00 363.00 0.00% 363.00 0.00%

3.1.4 230mm dia P.Mtr. 436.00 436.00 0.00% 436.00 0.00%

3.1.5 250mm dia P.Mtr. 436.00 436.00 0.00% 436.00 0.00%

3.1.6 300mm dia P.Mtr. 581.00 581.00 0.00% 581.00 0.00%

3.1.7 400mm dia P.Mtr. 827.00 827.00 0.00% 827.00 0.00%

Note:-
1 If grade `AA S.W. pipes (IS:651 mark) are used then add 5%

2 Deduct 5% if jointing is done in CM 1:3.


3.2 Providing and laying cement concrete 1:5:10 (1 cement : 5
coarse sand : 10 graded stone aggregate 40mm nominal size)
alround S.W. pipes including bed concrete as per standard
design
3.2.1 100 mm diameter S.W. pipe P.Mtr. 391.00 391.00 0.00% 391.00 0.00%
3.2.2 150 mm diameter S.W. pipe P.Mtr. 479.00 479.00 0.00% 479.00 0.00%
3.2.3 200 mm diameter S.W. pipe P.Mtr. 558.00 558.00 0.00% 558.00 0.00%
3.2.4 230 mm diameter S.W. pipe P.Mtr. 611.00 611.00 0.00% 611.00 0.00%
3.2.5 250 mm diameter S.W. pipe P.Mtr. 645.00 645.00 0.00% 645.00 0.00%
3.2.6 300 mm diameter S.W. pipe P.Mtr. 740.00 740.00 0.00% 740.00 0.00%
3.2.7 350 mm diameter S.W. pipe P.Mtr. 837.00 837.00 0.00% 837.00 0.00%
3.2.8 400 mm diameter S.W. pipe P.Mtr. 935.00 935.00 0.00% 935.00 0.00%
3.3 Providing and laying cement concrete 1:5:10 (1 cement : 5
coarse sand : 10 graded stone aggregate 40mm nominal size)
upto haunches of S.W. pipes including bed concrete as per
standard design
3.3.1 100 mm diameter S.W. pipe P.Mtr. 186.00 186.00 0.00% 186.00 0.00%
3.3.2 150 mm diameter S.W. pipe P.Mtr. 301.00 301.00 0.00% 301.00 0.00%
3.3.3 200 mm diameter S.W. pipe P.Mtr. 354.00 354.00 0.00% 354.00 0.00%
3.3.4 230 mm diameter S.W. pipe P.Mtr. 388.00 388.00 0.00% 388.00 0.00%
3.3.5 250 mm diameter S.W. pipe P.Mtr. 413.00 413.00 0.00% 413.00 0.00%
3.3.6 300 mm diameter S.W. pipe P.Mtr. 475.00 475.00 0.00% 475.00 0.00%
3.3.7 350 mm diameter S.W. pipe P.Mtr. 541.00 541.00 0.00% 541.00 0.00%
3.3.8 400 mm diameter S.W. pipe P.Mtr. 611.00 611.00 0.00% 611.00 0.00%
3.4 Providing & fixing S.W. square mouth Gully trap `A` grade (ISI
marked) of approved make & design in existing man-hole.

3.4.1 Size 100 X 100mm Each 121.00 121.00 0.00% 121.00 0.00%
3.4.2 Size 150 X 100mm Each 143.00 143.00 0.00% 143.00 0.00%
3.4.3 Size 225 X 150mm Each 191.00 191.00 0.00% 191.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
3.5 Providing and fixing square mouth S.W. gully trap grade "A"
complete with C.I. grating brick masonry chamber with bricks of
class designation 75 and water tight C.I. cover with frame of
300x300mm size (inside the weight of cover to be not less than
4.50 kg and frame to be not less than 2.70 kg. as per standard
design :

3.5.1 150 x 100 mm size P type Each 1054.00 1054.00 0.00% 1,054.00 0.00%
3.5.2 225 x 150 mm size P type Each 1359.00 1359.00 0.00% 1,359.00 0.00%
3.6 P & F S.W. Master Trap (Inter-cepting) `A` grade (I.S.: 651
marked) of approved quality/make
3.6.1 100mm dia Each 256.00 256.00 0.00% 256.00 0.00%
3.6.2 150mm dia Each 343.00 343.00 0.00% 343.00 0.00%
3.7 Labour charges for Removing S.W. pipes including breaking of
joints & bed concrete, stacking of useful material at site within 50
mtr. Lead and disposal of unserviceable material within 0.5 Km.
lead:
3.7.1 100 & 150mm dia pipe P.Mtr. 14.00 14.00 0.00% 14.00 0.00%
3.7.2 200, 230 & 250mm dia pipe P.Mtr. 15.00 15.00 0.00% 15.00 0.00%
3.7.3 300mm dia pipe P.Mtr. 17.00 17.00 0.00% 17.00 0.00%
3.7.4 350mm dia pipe P.Mtr. 17.00 17.00 0.00% 17.00 0.00%
3.7.5 400mm dia pipe P.Mtr. 28.00 28.00 0.00% 28.00 0.00%
R.C.C. NON PRESSURE PIPES
3.8 Providing, Laying & Jointing R.C.C. class NP-2 Non-Pressure
pipes (IS : 458mark) of approved make with collars, jointed with
C.M. 1:2 or having Spigot and socket ends with flexible rubber
rings joint including testing of joints etc. complete :

3.8.1 100mm dia Internal P.Mtr. 217.00 217.00 0.00% 217.00 0.00%
3.8.2 150mm dia Internal P.Mtr. 219.00 219.00 0.00% 219.00 0.00%
3.8.3 200mm dia Internal P.Mtr. 331.00 331.00 0.00% 331.00 0.00%
3.8.4 250mm dia Internal P.Mtr. 353.00 353.00 0.00% 353.00 0.00%
3.8.5 300mm dia Internal P.Mtr. 442.00 442.00 0.00% 442.00 0.00%
3.8.6 450mm dia Internal P.Mtr. 724.00 724.00 0.00% 724.00 0.00%
3.8.7 500mm dia Internal P.Mtr. 849.00 849.00 0.00% 849.00 0.00%
3.8.8 600mm dia Internal P.Mtr. 1086.00 1086.00 0.00% 1,086.00 0.00%
3.8.9 700 mm dia Internal P.Mtr. 1425.00 1425.00 0.00% 1,425.00 0.00%
3.8.10 800 mm dia Internal P.Mtr. 1652.00 1652.00 0.00% 1,652.00 0.00%
3.8.11 900 mm dia Internal P.Mtr. 2060.00 2060.00 0.00% 2,060.00 0.00%

Note : Deduct 20 % for Non ISI marked pipes of all size

SAND-CAST IRON SOIL, WATER & RAIN WATER PIPES.

3.9 P & F Sand-cast Iron (S.C.I.) Pipe (IS : 1729mark) of approved .


make in wall or in floor with M.S. holder bat clamps in 10 X 10 X
10 Cm. M-15 grade concrete blocks, joints filled with CM 1:4 with
spun yarn including cutting holes and making good the wall:

3.9.1 50mm dia P.Rmt. 441.00 441.00 0.00% 441.00 0.00%


3.9.2 75mm dia P.Rmt. 477.00 477.00 0.00% 477.00 0.00%
3.9.3 100mm dia P.Rmt. 549.00 549.00 0.00% 549.00 0.00%
3.9.4 150mm dia P.Rmt. 1037.00 1037.00 0.00% 1,037.00 0.00%

3.10 Add extra for Lead caulked joints (IS:782-1978) in sand cast iron
pipes/spun

3.10.1 75mm dia, 0.88 kg. Pig lead Each 96.00 96.00 0.00% 96.00 0.00%
3.10.2 100mm dia, 0.98 kg. Pig lead Each 109.00 109.00 0.00% 109.00 0.00%
3.10.3 150mm dia, 1.48 kg. Pig lead Each 123.00 123.00 0.00% 123.00 0.00%

3.11 P & F SCI Fittings (IS : 1729 mark) in CM 1:4 with spun yarn

3.11.1 50mm w/o door


Socket Each 100.00 100.00 0.00% 100.00 0.00%
Cowel Each 138.00 138.00 0.00% 138.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
Tee Each 211.00 211.00 0.00% 211.00 0.00%
Bend Each 160.00 160.00 0.00% 160.00 0.00%
3.11.2 75mm w/o door
Offset Each 309.00 309.00 0.00% 309.00 0.00%
Socket Each 123.00 123.00 0.00% 123.00 0.00%
D/Door Y-Tee Each 352.00 352.00 0.00% 352.00 0.00%
Cowel Each 167.00 167.00 0.00% 167.00 0.00%
Tee Each 288.00 288.00 0.00% 288.00 0.00%
Bend Each 207.00 207.00 0.00% 207.00 0.00%
Door cross Each 429.00 429.00 0.00% 429.00 0.00%
3.11.3 100mm w/o door
Offset Each 350.00 350.00 0.00% 350.00 0.00%
Socket Each 160.00 160.00 0.00% 160.00 0.00%
D/Door Y-Tee Each 515.00 515.00 0.00% 515.00 0.00%
Cowel Each 226.00 226.00 0.00% 226.00 0.00%
Tee Each 349.00 349.00 0.00% 349.00 0.00%
Bend Each 257.00 257.00 0.00% 257.00 0.00%
Door cross Each 481.00 481.00 0.00% 481.00 0.00%
3.11.4 150mm w/o door
Socket Each 314.00 314.00 0.00% 314.00 0.00%
Cowel Each 772.00 772.00 0.00% 772.00 0.00%
Bend Each 575.00 575.00 0.00% 575.00 0.00%
3.11.5 50mm with door
Tee Each 262.00 262.00 0.00% 262.00 0.00%
Bend Each 185.00 185.00 0.00% 185.00 0.00%
3.11.6 75mm with door
Tee Each 309.00 309.00 0.00% 309.00 0.00%
Bend Each 226.00 226.00 0.00% 226.00 0.00%
3.11.7 100mm with door
Tee Each 361.00 361.00 0.00% 361.00 0.00%
Bend Each 288.00 288.00 0.00% 288.00 0.00%
3.11.8 150mm with door
Tee Each 1030.00 1030.00 0.00% 1,030.00 0.00%
Bend Each 596.00 596.00 0.00% 596.00 0.00%
3.12 P & F sand cast Floor Trap (Nahni) of (IS:1729 mark) of
approved quality / make with socket down or hinged grating
including and making good the floor.
3.12.1Size 100x100mm Each 418.00 386.00 8.29% 418.00 8.29%
3.12.2Size 100x75mm Each 333.00 303.00 9.90% 333.00 9.90%
3.12.3Size 100x50mm Each 252.00 252.00 0.00% 252.00 0.00%
3.13 P & F sand cast Iron P or S Trap (IS:1729 make) of approved
make
Each 447.00 447.00 0.00% 447.00 0.00%
3.14 Labour charges for making connection of sewar line through
main hole
Each 121.00 121.00 0.00% 121.00 0.00%
3.15 Making connection with existing G.I. pipe lines of all sizes
Each 89.00 89.00 0.00% 89.00 0.00%
ASBESTOS CEMENT (A.C.) SOIL VENT & RAIN WATER PIPES
3.16 P & F on wall face A.C. pipes (IS : 1626 part-I mark) of approved
make with wooden plugs and M.S. clamps, jointing with spun
soaked in bitumen and CM 1:2 complete including making good
the wall
3.16.1 50mm dia P.Rmt 83.00 83.00 0.00% 83.00 0.00%
3.16.2 75mm dia P.Rmt 91.00 91.00 0.00% 91.00 0.00%
3.16.3 100mm dia P.Rmt 100.00 100.00 0.00% 100.00 0.00%
3.16.4 150mm dia P.Rmt 132.00 132.00 0.00% 132.00 0.00%
Note : Deduct 5%, if M.S. clamps are not used in sand cast Iron or A.C.
pipes
3.17 P & F A.C. fittings (IS : 1626 part-I mark) of approved quality /
make with spun yarn socked in bitumen & CM 1:2
3.17.1 50mm
Cowel Each 31.00 31.00 0.00% 31.00 0.00%
Socket Each 13.00 13.00 0.00% 13.00 0.00%
Offset Each 37.00 37.00 0.00% 37.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
Shoe Each 22.00 22.00 0.00% 22.00 0.00%
With door bend Each 37.00 37.00 0.00% 37.00 0.00%
With door Tee Each 47.00 47.00 0.00% 47.00 0.00%
Without door bend Each 31.00 31.00 0.00% 31.00 0.00%
Without door Tee Each 34.00 34.00 0.00% 34.00 0.00%

3.17.2 75mm
Cowel Each 37.00 37.00 0.00% 37.00 0.00%
Socket Each 14.00 14.00 0.00% 14.00 0.00%
Offset Each 44.00 44.00 0.00% 44.00 0.00%
Shoe Each 25.00 25.00 0.00% 25.00 0.00%
With door bend Each 44.00 44.00 0.00% 44.00 0.00%
With door Tee Each 52.00 52.00 0.00% 52.00 0.00%
Without door bend Each 35.00 35.00 0.00% 35.00 0.00%
Without door Tee Each 35.00 35.00 0.00% 35.00 0.00%
3.17.3 100mm
Cowel Each 44.00 44.00 0.00% 44.00 0.00%
Socket Each 15.00 15.00 0.00% 15.00 0.00%
Offset Each 61.00 61.00 0.00% 61.00 0.00%
Shoe Each 29.00 29.00 0.00% 29.00 0.00%
With door bend Each 52.00 52.00 0.00% 52.00 0.00%
With door Tee Each 58.00 58.00 0.00% 58.00 0.00%
Without door bend Each 39.00 39.00 0.00% 39.00 0.00%
Without door Tee Each 47.00 47.00 0.00% 47.00 0.00%
3.17.4 150mm
Cowel Each 58.00 58.00 0.00% 58.00 0.00%
Socket Each 22.00 22.00 0.00% 22.00 0.00%
Offset Each 62.00 62.00 0.00% 62.00 0.00%
Shoe Each 40.00 40.00 0.00% 40.00 0.00%
With door bend Each 87.00 87.00 0.00% 87.00 0.00%
Without door bend Each 58.00 58.00 0.00% 58.00 0.00%
Without door Tee Each 73.00 73.00 0.00% 73.00 0.00%

3.18 Labour charges for removing CI/AC pipes of all sizes including
accessories with care and stacking of useful material

P.Rmt. 7.00 7.00 0.00% 7.00 0.00%


RIGID PVC SOIL, WASTE & RAIN WATER (SWR) PIPES

3.19 P & F rigid pvc pipe (IS:4985 mark) class II/ (4 kg./cm2)
approved quality / make including joining the pipe with solvent
cement rubber ring and lubricant

3.19.1 63mm dia P.Rmt. 116.00 108.00 7.41% 116.00 7.41%


3.19.2 75mm dia P.Rmt. 138.00 128.00 7.81% 138.00 7.81%
3.19.3 110mm dia P.Rmt. 218.00 202.00 7.92% 218.00 7.92%
3.19.4 160mm dia P.Rmt. 275.00 255.00 7.84% 275.00 7.84%

3.20 P & F rigid pvc pipe fittings (IS : 4985 mark) of approved quality /
make including joining the pipe with solvent cement rubber ring
and lubricant :
3.20.1 Coupler (Socket)
75mm dia Each 74.00 71.00 4.23% 74.00 4.23%
110mm dia Each 90.00 86.00 4.65% 90.00 4.65%

3.20.2 Reducer 110x75mm


75mm dia Each 83.00 79.00 5.06% 83.00 5.06%
110mm dia Each 90.00 86.00 4.65% 90.00 4.65%

3.20.3 Plain Tee


75mm dia Each 98.00 94.00 4.26% 98.00 4.26%
110mm dia Each 158.00 151.00 4.64% 158.00 4.64%

3.20.4 Door Tee


75mm dia Each 150.00 144.00 4.17% 150.00 4.17%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
110mm dia Each 180.00 173.00 4.05% 180.00 4.05%

3.20.5 Door 'Y'


75mm dia Each 158.00 151.00 4.64% 158.00 4.64%
110mm dia Each 195.00 187.00 4.28% 195.00 4.28%

3.20.6 Double 'Y'


75mm dia Each 165.00 158.00 4.43% 165.00 4.43%
110mm dia Each 263.00 252.00 4.37% 263.00 4.37%

3.20.7 Double Door 'Y'


75mm dia Each 195.00 187.00 4.28% 195.00 4.28%
110mm dia Each 330.00 317.00 4.10% 330.00 4.10%
3.20.8 Bend 45
75mm dia Each 68.00 65.00 4.62% 68.00 4.62%
110mm dia Each 108.00 103.00 4.85% 108.00 4.85%

3.20.9 Bend 87.5


75mm dia Each 84.00 80.00 5.00% 84.00 5.00%
110mm dia Each 135.00 130.00 3.85% 135.00 3.85%

3.20.10 Door Bend (Top side)


75mm dia Each 113.00 108.00 4.63% 113.00 4.63%
110mm dia Each 130.00 125.00 4.00% 130.00 4.00%

3.20.11 Door Bend (Left & Right)


75mm dia Each 135.00 130.00 3.85% 135.00 3.85%
110mm dia Each 165.00 158.00 4.43% 165.00 4.43%

3.20.12 Vent Cowel


75mm dia Each 38.00 36.00 5.56% 38.00 5.56%
110mm dia Each 46.00 44.00 4.55% 46.00 4.55%

3.20.13 Socket Plug


75mm dia Each 58.00 55.00 5.45% 58.00 5.45%
110mm dia Each 68.00 65.00 4.62% 68.00 4.62%

3.20.14 Door Cap


75mm dia Each 38.00 36.00 5.56% 38.00 5.56%
110mm dia Each 53.00 50.00 6.00% 53.00 6.00%
3.20.15 Pipe Clip
75mm dia Each 23.00 22.00 4.55% 23.00 4.55%
110mm dia Each 30.00 29.00 3.45% 30.00 3.45%
3.20.16 W.C. connector with lipring
110mm dia Each 180.00 173.00 4.05% 180.00 4.05%

3.20.17 W.C. connector bent type


110mm dia Each 188.00 180.00 4.44% 188.00 4.44%

3.20.18 Plain floor trap


110mm dia Each 195.00 187.00 4.28% 195.00 4.28%

3.20.19 Multi floor trap


110mm dia Each 225.00 216.00 4.17% 225.00 4.17%

3.20.20 Height Raiser


110mm dia Each 180.00 173.00 4.05% 180.00 4.05%

3.20.21 Top Tile & straine


110mm dia Each 68.00 65.00 4.62% 68.00 4.62%

3.20.22 Top Tile only


110mm dia Each 53.00 50.00 6.00% 53.00 6.00%

3.20.23 P- Trap

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
110mm dia Each 323.00 310.00 4.19% 323.00 4.19%

3.20.24 Q- Trap
110mm dia Each 360.00 346.00 4.05% 360.00 4.05%

3.20.25 S- Trap
110mm dia Each 450.00 432.00 4.17% 450.00 4.17%

3.20.26 Ring Fitting


110mm dia Each 90.00 86.00 4.65% 90.00 4.65%

3.20.27 Gully trap


110mm dia Each 473.00 454.00 4.19% 473.00 4.19%

3.21 Construction of manhole in all type of soil inner size 90 X 60 Cm.


450 mm thick masonry in CM 1:6, 10 Cm. thick cement concrete
1:5 10 in foundation, 20 mm thick inside plaster in CM 1:6,
finished with floating neat cement, 50mm thick M-15 grade C.C.
flooring, making channels, 80mm thick stone slab covering with
40mm thick M-15 grade C.C. flooring, Cement cover with frame
of 450mm dia, earthwork etc. complete as per design including
disposal of surplus earth within 50 mtr. lead.

3.21.1 Depth up to 0.5 M Each 6261.00 6261.00 0.00% 6,261.00 0.00%

3.21.2 Add extra over item 3.21.1 for every additional 0.10m depth Each 161.00 161.00 0.00% 161.00 0.00%
above 0.5m depth
3.22 Construction of Man hole, in all types of soil, inner size 1.5 x 1.2
M, with 450mm thick masonry in CM 1:6, 10 Cm. thick cement
concrete 1:5:10 in foundation, 20mm thick inside plaster in CM
1:6, finished with floating neat cement, 50 mm thick M-15 grade
C.C. flooring making channels, 80 mm thick stone slab covering
with 40 mm thick M-15 grade C.C. flooring, Ferro Cement cover
with frame of 450mm dia, earthwork etc. complete including
disposal of surplus earth within 50 mtr. lead as per design :

3.22.1 Depth up to 1.5 M Each 9850.00 9850.00 0.00% 9,850.00 0.00%


3.22.2 Add extra over item 3.22.1 for every additional 0.10m depth Each 452.00 452.00 0.00% 452.00 0.00%
above 1.5m depth

3.23 Construction of chamber in all type of soil with 300 mm thick


masonry in CM 1:6 m 10 cm thick C.C. 1:5:10 in foundation,
20mm thick insider plaster in Cm 1:6, finished with floating neat
cement, 50mm thick M-15 grade C.C. flooring , earthwork etc.
complete as per design including disposal of surplus earth within
a lead of 50 mtr.

3.23.1 Inside size 300 X 300 mm depth upto 0.5 M Cement cover with Each 2311.00 2145.00 7.74% 2,311.00 7.74%
frame.
3.23.2 Inside size 450 X 450 mm depth upto 0.5 M Cement cover with Each 3209.00 2978.00 7.76% 3,209.00 7.76%
frame.
3.23.3 Inside size 600 X 450 mm depth upto 0.5 M Cement cover with Each 4205.00 3902.00 7.77% 4,205.00 7.77%
frame.
3.23.4 -do- depth upto 0.5 mm to 1.5 M -do- Each 4970.00 4612.00 7.76% 4,970.00 7.76%

3.24 Construction of soakage well in all type of soil with 300 mm thick
dry masonry, top and bottom 300 mm course in CM 1:6, 80mm
thick stone slab, jointing of slab in CM 1 : 3, Ralthal, Kharanja, 40
mm thick M-15 grade C.C flooring , earthwork complete as per
approved drawing including disposal of earth within a lead of 50
mtr.:

3.24.1 Size 300 cm. dia outside & 300 Cm. depth Each 21059.00 18532.00 13.64% 20,385.00 10.00%
3.24.2 -do- & 240 cm depth Each 16846.00 14825.00 13.63% 16,307.00 10.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
3.24.3 Size 240 cm. dia outside & 240 Cm. depth Each 14450.00 12716.00 13.64% 13,987.00 10.00%

3.25 Construction of soakage Trench in all types of soil with 300 mm


thick dry stone masonry, 80 mm thick stone slab covering,
jointing of slab in CM 1:3 Ralthal, Kharanja, 40 mm thick M-
15grade C.C. flooring earthwork etc. complete as per approved
drawing including disposal of earth within a lead of 50 Mtr.:

3.25.1 Top width 180Cm., bottom width 90Cm. & depth 240Cm. Each 4543.00 4165.00 9.08% 4,543.00 9.08%
3.25.2 Top width 240Cm., bottom width 150Cm. & depth 300Cm. Each 12775.00 11711.00 9.09% 12,775.00 9.09%

3.26 Construction of Soakage well in all types of soil of approved


drawing, top 90 Cm .Portion in 450mm thick masonry with CM
1:6, 80 mm thick stone slab covering, jointing of slab in CM
1:3 ,Ralthal, kharanja 40mm thick M-15 grade C.C flooring, earth
work etc . complete including disposal of surplus earth within a
lead of 50 mtr .

3.26.1 Inner dia 90 Cm & 10 to 12 Mtr deep. Each 10841.00 9937.00 9.10% 10,841.00 9.10%
3.26.2 Inner dia 60 Cm & 10 to 12 Mtr deep. Each 8292.00 7601.00 9.09% 8,292.00 9.09%

3.27 Labour charges for construction of Soakage well of 90 Cm. dia


(Earth –work & its disposal ,with in a lead of 0.5 Km .only ).

P.Rmt. 65.00 59.00 10.17% 64.00 8.47%


3.28 Add extra if Soakage Well is filled with dry stones. Each 523.00 480.00 8.96% 523.00 8.96%

3.29 Construction of septic Tank in all types of soil with 40 Cm .thick


masonry in CM 1:6, 15 Cm thick C.C bed of 1:5:10, M-15 grade
C.C flooring & over stone slab covering ,80 mm thick slab
,jointing of slab in CM 1:3. Ralthal, Kharanja, 50 mm thick stone
partition walls, 20 mm thick plaster in CM 1:6 finished with neat
floating cement, 4 Nos C.I foot rests of approved design ,two No.
450 mm dia each Ferro cement cover with frame, earth work
etc. complete as per approved drawing including disposal of
surplus earth within a lead of 50 mtr:-

3.29.1 Size 200x100x130 cm.(for 10 users) Each 24712.00 22652.00 9.09% 24,712.00 9.09%
3.29.2 Size 230x110x150 cm.(for 20 users) Each 30744.00 28182.00 9.09% 30,744.00 9.09%
3.29.3 Size 400x140x150 cm.(for 50 users) Each 42024.00 38522.00 9.09% 42,024.00 9.09%

Note :- Add or subtract proportionately for every 0.5 M increase or


decrease in Length -12.5% Breadth & Depth -18 % each

3.30 Emptying of Septic tank ,Soakage well etc. by disposing or


sludge upto 5 Km. lead & taking out sewage including cleaning of
site.

Nagar Parishad / Tanker cost Rs. 800/- per Tanker for 3.50 cum
including contractor profit
Each 330.00 303.00 8.91% 330.00 8.91%
3.31 Add extra if R.C.C slab of designed thickness & reinforcement is
provided on manhole in place of stone slab( Actual area of R.C.C
slab to be measured).
P.Sqm 187.00 172.00 8.72% 187.00 8.72%

3.32 P & F M.S. Foot Rests in with C.M.,1:3, standard design in


20mm square M.S. bar 50 mm embedded in wall & 10 cms.
projected out complete.
Each 173.00 158.00 9.49% 173.00 9.49%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
3.33 Supplying and fixing C.I. Cover with frame, C.I. gratings for
chambers & man holes.
P.Kg. 44.00 41.00 7.32% 44.00 7.32%
3.34 Supplying and fixing Ferro- cement cover with C.I. frame for
chambers & man holes of size.

3.34.1 450mm dia, 5Kg. C.I. frame to with stand 3 MT center point load
& minimum unfractured load of 1 MT. (Light duty).
Each 950.00 871.00 9.07% 950.00 9.07%
3.34.2 500mm dia 12 Kg.-do-15 MT centre point load (medium duty).

Each 1484.00 1361.00 9.04% 1,484.00 9.04%


3.34.3 500mm dia 22 Kg.-do-22 MT centre point load (Heavy duty).
Each 1986.00 1821.00 9.06% 1,986.00 9.06%
3.34.4 500mm dia 25 Kg.-do-70 MT centre point load seal type (Heavy
duty.)
Each 3041.00 2787.00 9.11% 3,041.00 9.11%
3.34.5 Rectangular shape 600 x 450 mm, to withstand 3 MT
center point load & minimum unfractured load of 1 MT. (Light
duty).
Each 1150.00 1054.00 9.11% 1,150.00 9.11%
3.35 Supplying & Fixing R.C.C. Manholes covers with frame of
approved make (Light duty).
3.35.1 Size 500mm dia (Double seal) Each 311.00 285.00 9.12% 311.00 9.12%
3.35.2 Size 450 mm Each 276.00 253.00 9.09% 276.00 9.09%
3.35.3 Size 400 mm Each 208.00 190.00 9.47% 208.00 9.47%
3.35.4 Size 600 x 600mm (Double seal) Each 475.00 436.00 8.94% 475.00 8.94%
3.35.5 Size 600 x 450 mm Each 401.00 367.00 9.26% 401.00 9.26%
3.35.6 Size 450 x 450 mm Each 302.00 277.00 9.03% 302.00 9.03%
3.35.7 Size 300 x 300 mm Each 95.00 87.00 9.20% 95.00 9.20%
3.35.8 Size 250 x 250 mm Each 78.00 72.00 8.33% 78.00 8.33%
3.35.9 Size 180 x 180 mm Each 70.00 64.00 9.38% 70.00 9.38%
3.36 Construction of Open Surface Drain with 112mm thick brick
masonry in CM 1:4,110mm thick base concrete 1:5:10, 37mm
thick M-15 grade C.C. flooring ,12mm 1:4 cement plaster on all
exposed faces of walls including top surface excavation &
disposal of earth complete as per approved design/drawing:

3.36.1 112mm drain,225mm Av. depth P.Rmt 587.00 420.00 39.76% 462.00 10.00%
3.36.2 150mm drain,225mm Av. depth P.Rmt 930.00 693.00 34.20% 762.00 9.96%
3.36.3 250mm drain,300mm Av. depth P.Rmt 1050.00 1050.00 0.00% 1,050.00 0.00%

3.37 Construction of open Drain with 112mm thick brick masonry in


CM 1:4 Semi circular S.W. glazed channel (confirming to IS
Standards) fixed with cement mortar 1:1 over a bed of 100mm
thick C.C. 1:5:10, filling of edged with M-15 grade C.C. flooring,
12mm cement plaster 1:4, over all exposed faces, excavation &
disposal of earth with in a lead of 50 mtr complete as per
approved drawings :

3.37.1 112 mm drain,225mm Av. depth width 10 Cm S.W. glazed P.Rmt. 608.00 529.00 14.93% 581.00 9.83%
channel.
3.37.2 150 mm drain,225mm Av. depth width 15 Cm S.W. glazed P.Rmt. 721.00 627.00 14.99% 689.00 9.89%
channel.
3.37.3 250 mm drain,225mm Av. depth width 250 Cm S.W. glazed P.Rmt. 1217.00 1058.00 15.03% 1,163.00 9.92%
channel.
3.38 Extra For additional 5 Cm. Average depth of drain of all sizes.

P.Rmt. 75.00 65.00 15.38% 71.00 9.23%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
3.39 P & F precast dense cement concrete (Vibro-pressed) drain
section Block of different size as per approved drawing and
design and strength as per IS code 2185 part I of grade 'D'
(5.00mm2) proper quality of additive/admixture like plasticizer etc.
added to produce high quality and durable drain section Blocks
of 'L' shape 'U' shape etc. as per approved design and drawing
complete with fixing and joining in C.M.1:4 in proper grade and
level complete in all respect including earth work and disposal of
surplus earth within 0.5 Km. lead. (cost of Steel/ welded mesh
etc. shall be paid extra).

3.39.1 40mm thick P.Sqm 912.00 793.00 15.01% 872.00 9.96%


3.39.1 Upto 60mm thick P.Sqm 1140.00 991.00 15.04% 1,090.00 9.99%
3.39.1 Upto 80mm thick P.Sqm 1369.00 1190.00 15.04% 1,309.00 10.00%

3.40 Construction of Cement Concrete Chamber 125mm dia on


depressed floor upto 45cm height from floor with :

3.40.1 C.P. Brass grating Each 227.00 197.00 15.23% 216.00 9.64%
3.40.2 C.P. Brass doom grating Each 243.00 211.00 15.17% 232.00 9.95%
3.40.3 C.I. Grating Each 197.00 171.00 15.20% 188.00 9.94%
3.40.4 Stainless Steel Sheet Grating Each 227.00 197.00 15.23% 216.00 9.64%

3.40.A Construction of Cement Concrete Chamber 125mm dia on


depressed floor upto 45cm height from floor with :

3.40.A.1 C.P. Brass grating Each 340.00 296.00 14.86% 325.00 9.80%
3.40.A.2 C.P. doom grating Each 379.00 330.00 14.85% 363.00 10.00%
3.40.A.3 C.I. Grating Each 304.00 264.00 15.15% 290.00 9.85%

3.40.A.4 Stainless Steel Sheet Grating Each 340.00 296.00 14.86% 325.00 9.80%

SPUN - CENTRIFUGALLY CAST IRON SOIL WATER & RAIN WATER PIPES :-
3.41 Providing & fixing Spun - Centrifugally cast Iron Pipes (IS : 3989
Mark) of approved make in wall or in floor with M.S. Holder bat
clamps in 10 x 10 x 10 Cm. M-15 Grade concrete blocks, joints
filled with CM 1:4 with spun yarn including cutting holes and
making good the wall :-

3.41.1 75 mm dia P.Rmt. 1187.00 1032.00 15.02% 1,135.00 9.98%


3.41.2 100 mm dia P.Rmt. 1377.00 1197.00 15.04% 1,316.00 9.94%
3.41.3 150 mm dia P.Rmt. 2479.00 2156.00 14.98% 2,371.00 9.97%
3.42 Providing & fixing Spun - Centrifugally cast Iron Pipes fitting (IS :
3989 Mark) in CM 1:4 with spun Yarn

3.42.1 75mm w/o door


Offset Each 627.00 545.00 15.05% 599.00 9.91%
Socket Each 270.00 235.00 14.89% 258.00 9.79%
D/Door Y-Tee Each 760.00 661.00 14.98% 727.00 9.98%
Bend Each 397.00 345.00 15.07% 379.00 9.86%
Door Cross Each 961.00 836.00 14.95% 919.00 9.93%
Cowel Each 379.00 330.00 14.85% 363.00 10.00%
Tee Each 692.00 602.00 14.95% 662.00 9.97%
3.42.2 100mm w/o door
Offset Each 711.00 618.00 15.05% 679.00 9.87%
Socket Each 408.00 355.00 14.93% 390.00 9.86%
D/Door Y-Tee Each 949.00 825.00 15.03% 907.00 9.94%
Bend Each 559.00 486.00 15.02% 534.00 9.88%
Door Cross Each 1259.00 1095.00 14.98% 1,204.00 9.95%
Cowel Each 636.00 553.00 15.01% 608.00 9.95%
Tee Each 858.00 746.00 15.01% 820.00 9.92%

3.42.3 150mm w/o door

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
Socket Each 726.00 631.00 15.06% 694.00 9.98%
D/Door Y-Tee Each 1709.00 1486.00 15.01% 1,634.00 9.96%
Bend Each 1274.00 1108.00 14.98% 1,218.00 9.93%
Door Cross Each 1881.00 1636.00 14.98% 1,799.00 9.96%
Cowel Each 1091.00 949.00 14.96% 1,043.00 9.91%
Tee Each 1711.00 1488.00 14.99% 1,636.00 9.95%

3.42.4 75mm with door


Bend Each 460.00 400.00 15.00% 440.00 10.00%
Door Cross Each 437.00 380.00 15.00% 418.00 10.00%
Tee Each 761.00 662.00 14.95% 728.00 9.97%

3.42.5 100mm with door


Bend Each 584.00 508.00 14.96% 558.00 9.84%
Door Cross Each 1298.00 1129.00 14.97% 1,241.00 9.92%
Tee Each 915.00 796.00 14.95% 875.00 9.92%
3.42.6 150mm with door
Bend Each 1296.00 1127.00 15.00% 1,239.00 9.94%
Door Cross Each 1899.00 1651.00 15.02% 1,816.00 9.99%
Tee Each 1883.00 1637.00 15.03% 1,800.00 9.96%
3.43 Providing and Fixing Spun - Cast Iron floor trap (Nahani) of (IS :
3989 Mark) approved quality / make with socket down or hinged
grating including cutting and making good the floor :-

3.43.1 Size 100 x 100 mm Each 856.00 744.00 15.05% 818.00 9.95%
3.43.2 Size 100 x 75 mm Each 806.00 701.00 14.98% 771.00 9.99%
3.44 Add 10% extra over item 3.41 if the pipes are laid under
suspended condition under the roof
3.45 Providing and fixing unplasticized poly vinyl chloride (UPVC)
SWR pipes Type B for sciland waste discharge system (IS:13592
: 1992 Marked) of approved quality / make)

3.45.1 75mm dia P.Rmt. 189.00 164.00 15.24% 180.00 9.76%


3.45.2 110 mm dia P.Rmt. 379.00 330.00 14.85% 363.00 10.00%

3.46 Providing and fixing unplasticized poly vinyl chloride (UPVC)


SWR pipes Type B for sciland waste discharge system (IS:13592
: 1992 Marked) of approved quality / make)

3.46.1 Coupler
75mm dia Each 76.00 66.00 15.15% 72.00 9.09%
110mm dia Each 117.00 102.00 14.71% 112.00 9.80%

3.46.2 Reducer Coupler


75mm dia Each 83.00 72.00 15.28% 79.00 9.72%
110mm dia Each 135.00 117.00 15.38% 128.00 9.40%

3.46.3 Single push Fit coupler


75mm dia Each 79.00 69.00 14.49% 75.00 8.70%
110mm dia Each 137.00 119.00 15.13% 130.00 9.24%
3.46.4 Bend 87.5 Dg.
75mm dia Each 102.00 89.00 14.61% 97.00 8.99%
110mm dia Each 168.00 146.00 15.07% 160.00 9.59%

3.46.5 Bend 45 Dg.


75mm dia Each 84.00 73.00 15.07% 80.00 9.59%
110mm dia Each 144.00 125.00 15.20% 137.00 9.60%

3.46.6 Door Bend 87.5 Dg.


75mm dia Each 135.00 117.00 15.38% 128.00 9.40%
110mm dia Each 209.00 182.00 14.84% 200.00 9.89%

3.46.7 Singh 'Y'


75mm dia Each 156.00 136.00 14.71% 149.00 9.56%
110mm dia Each 301.00 262.00 14.89% 288.00 9.92%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

3.46.8 Singh 'Y' with Door


75mm dia Each 204.00 177.00 15.25% 194.00 9.60%
110mm dia Each 377.00 328.00 14.94% 360.00 9.76%

3.46.9 Double 'Y'


75mm dia Each 214.00 186.00 15.05% 204.00 9.68%
110mm dia Each 385.00 335.00 14.93% 368.00 9.85%
#DIV/0!
3.46.10 Double 'Y' with Door
75mm dia Each 324.00 282.00 14.89% 310.00 9.93%
110mm dia Each 498.00 433.00 15.01% 476.00 9.93%
3.46.11 Socket plug
75mm dia Each 66.00 57.00 15.79% 62.00 8.77%
110mm dia Each 83.00 72.00 15.28% 79.00 9.72%
3.46.12 Pipe Clip
75mm dia Each 21.00 18.00 16.67% 19.00 5.56%
110mm dia Each 31.00 27.00 14.81% 29.00 7.41%

3.46.13 Double tee with Door


75mm dia Each 365.00 317.00 15.14% 348.00 9.78%
110mm dia Each 622.00 541.00 14.97% 595.00 9.98%

3.46.14 W.C. connector


110mm dia Each 235.00 204.00 15.20% 224.00 9.80%

3.46.15 W.C. Connector (Bend) with ring


110mm dia Each 247.00 215.00 14.88% 236.00 9.77%

3.46.16 Single Tee


75mm dia Each 128.00 111.00 15.32% 122.00 9.91%
110mm dia Each 228.00 198.00 15.15% 217.00 9.60%

3.46.17 Single Tee with Door


75mm dia Each 147.00 128.00 14.84% 140.00 9.38%
110mm dia Each 265.00 230.00 15.22% 253.00 10.00%

3.46.18 Double Tee (4 ways)


75mm dia Each 231.00 201.00 14.93% 221.00 9.95%
110mm dia Each 400.00 348.00 14.94% 382.00 9.77%

3.46.19 Multi floor trap


110mm dia Each 261.00 227.00 14.98% 249.00 9.69%
3.46.20 Offset
110mm dia Each 307.00 267.00 14.98% 293.00 9.74%
3.46.21 Extra Square Jail
110mm dia Each 41.00 36.00 13.89% 39.00 8.33%

3.46.22 Extra Round Jail


110mm dia Each 28.00 24.00 16.67% 26.00 8.33%

3.46.23 Extra 4 SWR Ringh


75mm dia Each 14.00 12.00 16.67% 13.00 8.33%
110mm dia Each 18.00 16.00 12.50% 17.00 6.25%

3.46.24 Gully Trap 160 mm


110mm dia Each 745.00 648.00 14.97% 712.00 9.88%

3.46.25 Nahni Trap with Jail 4"


110mm dia Each 186.00 162.00 14.81% 178.00 9.88%

3.46.26 Nahni Trap without Jail 4"


110mm dia Each 163.00 142.00 14.79% 156.00 9.86%

3.46.27 Nahni Trap with Jail 3"

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
110mm dia Each 164.00 143.00 14.69% 157.00 9.79%

3.46.28 Nahni Trap without Jail 3"


110mm dia Each 145.00 126.00 15.08% 138.00 9.52%

3.46.29 Vent Cowel 75mm


110mm dia Each 53.00 46.00 15.22% 50.00 8.70%
3.46.30 Vent Cowel 100mm
110mm dia Each 64.00 56.00 14.29% 61.00 8.93%
3.47 Raising manhole cover and frames slab to required level
including dismantling existing slab and making good the damage
as required (raising depth of manhole masonry to be paid
separately).

3.47.1 Rectangular manhole 90x60 cm Each 1140.00 991.00 15.04% 1,090.00 9.99%
3.47.2 Rectangular manhole 150x120 cm Each 1746.00 1518.00 15.02% 1,669.00 9.95%

3.48 Providing & fixing Spun –Centrifugally cast Iron Pipes fitting (IS :
3989 Mark ) in CM 1:4 with spun Yarn 100mm w/o door as per
direction of Engineer-in-Charge.
(a) P Trap of standard size Each 985.00 851.00 15.75% 936.00 9.99%
(b) Long P Trap (900mm) Each 2668.00 2450.00 8.90% 2,668.00 8.90%
(c) Long P Bend Each 1177.00 839.00 40.29% 922.00 9.89%
(d) Long Floor Trap (600mm) Each 1859.00 1505.00 23.52% 1,655.00 9.97%
3.49 Removing & Re fixing of S.C.I. Pipe and Spun Pipe with C.I.clip as
per direction of Engineer-in-Charge of following diameters :-

(a) 100mm dia Each 165.00 165.00 0.00% 165.00 0.00%


(b) 150mm dia Each 253.00 132.00 91.67% 145.00 9.85%

3.50 Cleaning of sewer line of various sizes as per requirement at site Rmt 88.00 88.00 88.00
of different sizes including 100mm,150mm & 225mm dia of 0.00% 0.00%
Stoneware pipe as per direction of Engineer-in-Charge.

3.51 Cleaning of C.I. Pipe Line of various sizse as per requirement at Rmt 55.00 55.00 55.00
site of different sizes including 100mm,150mm & 225mm dia of
C.I.Pipes as per direction of Engineer-in-Charge. 0.00% 0.00%

3.52 Repairing of Cement Concrete Chambers of different size as per Each 55.00 55.00 55.00
requirement at site and as per direction of Engineer-in-charge. 0.00% 0.00%

3.53 Providing & fixing Hubless Spun –Centrifugally cast Iron Pipes
(IS : 15905 Mark ) of Approved make in wall or in floor with M.S.
Holder bat clamps in 10 X 10 X10 Cm. M-15 Grade concrete
blocks, joints filled with CM 1:4 with spun yarn including cutting
holes and making good the wall:-

3.53.1 75 mm dia Rmt 1035.00 1025.00 0.98% 1,035.00 0.98%


3.53.2 100 mm dia Rmt 1259.00 1247.00 0.96% 1,259.00 0.96%
3.53.3 150 mm dia Rmt 2036.00 2036.00 0.00% 2,036.00 0.00%

3.54 Providing & fixing Hubless Spun –Centrifugally cast Iron Pipes
fitting (IS : 15905 Mark ) in CM 1:4 with spun Yarn.
3.54.1 75mm w/o door
(i) Offset (130mm) Each 511.00 511.00 0.00% 511.00 0.00%
(ii) Shielded (SS) Coupling (With EPDM Rubber) Each 418.00 418.00 0.00% 418.00 0.00%
(iii) D/Door Y-Tee Each 543.00 543.00 0.00% 543.00 0.00%
(iv) Bend Each 273.00 273.00 0.00% 273.00 0.00%
(v) Cowel Each 364.00 364.00 0.00% 364.00 0.00%
(vi) Tee Each 364.00 364.00 0.00% 364.00 0.00%

3.54.2 100mm W/o door


(i) Ofset (130mm) Each 709.00 709.00 0.00% 709.00 0.00%
(ii) Shielded (SS) Coupling (With EPDM Rubber) Each 456.00 456.00 0.00% 456.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-3
Chapter Description Variation Proposed % Above
Code No. Analysis As per BSR
Unit on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
(iii) D/Door Y-Tee Each 1000.00 1000.00 0.00% 1,000.00 0.00%
(iv) Bend Each 388.00 388.00 0.00% 388.00 0.00%
(v) Cowel Each 449.00 449.00 0.00% 449.00 0.00%
(vi) Tee Each 639.00 639.00 0.00% 639.00 0.00%

3.54.3 150mm W/o door


(i) Shielded (SS) Coupling (With EPDM Rubber) Each 639.00 639.00 0.00% 639.00 0.00%
(ii) D/Door Y-Tee Each 1861.00 1861.00 0.00% 1,861.00 0.00%
(iii) Bend Each 820.00 820.00 0.00% 820.00 0.00%
(iv) Cowel Each 953.00 953.00 0.00% 953.00 0.00%
(v) Tee Each 1840.00 1840.00 0.00% 1,840.00 0.00%

3..54.4 75mm with door, bend Each 371.00 371.00 0.00% 371.00 0.00%

3.54.5 100mm with door


(i) Bend Each 593.00 593.00 0.00% 593.00 0.00%
(ii) Tee Each 809.00 809.00 0.00% 809.00 0.00%

3.55 Mechanised Cleaning of sewer line of diameter upto 200mm with mtr
the help of trolley mounted electrical driven machine having
flexible steel springs of length 20ft. Each which are rotated with
the help of electric motor and clutch assembly. 140.00 140.00 0.00% 140.00 0.00%

3.56 Mechanised sewer line Cleaning upto diameter 100mm with the mtr
help of PU coated glass fibre rod mounted on a wheel with brush
attachment. 97.00 97.00 0.00% 97.00 0.00%

3.57 Mechanised Cleaning and desilting of manhole/sewer line


chambers With the help of mechanical bucket which gets open
and close through levers.
3.57.1 depth upto 0.5 mtr. Each 89.00 89.00 0.00% 89.00 0.00%
3.57.2 Depth upto 1.0 mtr. Each 165.00 165.00 0.00% 165.00 0.00%
3.57.3 Depth upto 2.0 mtr. Each 308.00 308.00 0.00% 308.00 0.00%
3.57.4 Depth upto 3.0 mtr. Each 446.00 446.00 0.00% 446.00 0.00%
3.57.5 Depth upto 5.0 mtr. Each 710.00 710.00 0.00% 710.00 0.00%

3.58 Suplying and Fixing Ductile iron Man Hole Covers/storm water Kg.
grating and gratingwith frame of various sizes weight and types
and load bearing capacity as per EN -124 ,superior quality or
equivalent, comlete as per Direction of Engineer In charge.
165.00 165.00 0.00% 165.00 0.00%

334804.00 307331.00 8.94% 330393.00 7.50%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-2
WATER SUPPLY INSTALLATION
CHAPTER : S-2
Chapter Code Description Unit Analysis Rate As per BSR As per % above % Proposed % Above Proposed % Above
No. 2018 A BSR 2018 on BSR above Rate for with BSR Rate for BSR with BSR
B 2018 BSR BSR 2019 2018A 2019 2018 B
2018 B A B

GALVANISED IRON PIPES


2.1 a P & F G.I. pipes (Internal work) with G.I. fittings (IS:1239
Mark) & MS clamps including cutting and making good
the walls and floors :

Exposed on wall A B
2.1.1 15mm dia nominal bore Each 181.00 193.00 134.00 147.00 35.07% 31.29% 147.00 9.70% 160.00 8.84%
2.1.2 20mm dia nominal bore Each 226.00 239.00 175.00 188.00 29.14% 27.13% 192.00 9.71% 205.00 9.04%
2.1.3 25mm dia nominal bore Each 282.00 308.00 226.00 253.00 24.78% 21.74% 247.00 9.29% 277.00 9.49%
2.1.4 32mm dia nominal bore Each 347.00 385.00 283.00 321.00 22.61% 19.94% 310.00 9.54% 351.00 9.35%
2.1.5 40mm dia nominal bore Each 437.00 458.00 356.00 376.00 22.75% 21.81% 390.00 9.55% 411.00 9.31%
2.1.6 50mm dia nominal bore Each 538.00 593.00 430.00 494.00 25.12% 20.04% 471.00 9.53% 540.00 9.31%
2.1.7 65mm dia nominal bore Each 670.00 709.00 534.00 610.00 25.47% 16.23% 585.00 9.55% 667.00 9.34%
2.1.8 80mm dia nominal bore Each 762.00 884.00 663.00 785.00 14.93% 12.61% 726.00 9.50% 859.00 9.43%
2.1.9 15mm dia nominal bore Each 185.00 198.00 139.00 152.00 33.09% 30.26% 152.00 9.35% 166.00 9.21%
2.1.10 20mm dia nominal bore Each 223.00 236.00 177.00 190.00 25.99% 24.21% 194.00 9.60% 208.00 9.47%
-
2.2 P & F GI pipes (External works) with GI fittings (IS:1239 -
Mark) including trenching & refilling earth etc.

2.2.1 15mm dia nominal bore Each 181.00 192.00 125.00 140.00 44.80% 37.14% 137.00 9.60% 153.00 9.29%
2.2.2 20mm dia nominal bore Each 191.00 202.00 153.00 164.00 24.84% 23.17% 168.00 9.80% 179.00 9.15%
2.2.3 25mm dia nominal bore Each 230.00 253.00 194.00 217.00 18.56% 16.59% 212.00 9.28% 237.00 9.22%
2.2.4 32mm dia nominal bore Each 285.00 319.00 243.00 277.00 17.28% 15.16% 266.00 9.47% 303.00 9.39%
2.2.5 40mm dia nominal bore Each 342.00 360.00 299.00 317.00 14.38% 13.56% 327.00 9.36% 347.00 9.46%
2.2.6 50mm dia nominal bore Each 408.00 456.00 363.00 411.00 12.40% 10.95% 397.00 9.37% 450.00 9.49%
2.2.7 65mm dia nominal bore Each 545.00 580.00 471.00 522.00 15.71% 11.11% 516.00 9.55% 571.00 9.39%
2.2.8 80mm dia nominal bore Each 627.00 735.00 570.00 677.00 10.00% 8.57% 624.00 9.47% 735.00 8.57%
2.2.9 100mm dia nominal bore Each 867.00 1010.00 810.00 953.00 7.04% 5.98% 867.00 7.04% 1,010.00 5.98%
2.2.10 125mm dia nominal bore Each 1362.00 1362.00 1192.00 1305.00 14.26% 4.37% 1,305.00 9.48% 1,362.00 4.37%
-
2.3 Making connection of GI distribution branch with GI -
main including all fitting
2.3.1 Upto 25mm dia Each 457.00 277.00 64.98% 303.00 9.39% -
2.3.2 Beyond 25mm & upto 100mm dia Each 650.00 486.00 33.74% 532.00 9.47% -
2.4 Fixing water meter (IS:779 mark) and stop cock in GI -
pipe line including making chamber of approved size
excluding cost of water meter & stop cock.
Each 384.00 201.00 91.04% 220.00 9.45% -
2.5 P & F water meter (IS:779 mark) of approved make. -
2.5.1 15mm dia Each 863.00 860.00 0.35% 863.00 0.35% -
2.5.2 20mm dia Each 1575.00 1569.00 0.38% 1,575.00 0.38% -
2.5.3 25mm dia Each 2160.00 2152.00 0.37% 2,160.00 0.37% -
-
COCKS, MIXERS, DIVERTORS & VALVES -
Note a The rates are for ISI marked item -
b If the items are Non ISI marked reduce the rate by 25% -

2.6 P & F pillar cocks (IS:8934 mark) of superior quality and -


approved make :
2.6.1 CP Pillar cock, 15mm dia nominal bore Each 733.00 675.00 8.59% 733.00 8.59% -
2.6.2 CP Pillar cock Elbow action, 15mm nominal bore Each 853.00 795.00 7.30% 853.00 7.30% -
2.6.3 CP Pillar cock fancy type, 15mm nominal bore Each 993.00 936.00 6.09% 993.00 6.09% -
2.6.4 CP Pillar cock, Swan neck with casted spout, 15mm Each 818.00 761.00 7.49% 818.00 7.49% -
nominal bore
2.6.5 CP Pillar cock, high neck, 15mm nominal bore Each 759.00 702.00 8.12% 759.00 8.12% -
2.6.6 Synthetic Material (PTMT) Pillar cock of approved Each 358.00 302.00 18.54% 331.00 9.60% -
quality/make-15, mm nominal bore
2.7 P & F Bib Cock (IS:8931 Mark)
Superior quality of approved make :
2.7.1 Brass 400 grm, 15mm nominal bore. Each 335.00 318.00 5.35% 335.00 5.35% -
2.7.2 PVC heavy duty, 15mm nominal bore. Each 88.00 72.00 22.22% 79.00 9.72% -
2.7.3 CP Brass bib cock, 15mm nominal bore. Each 619.00 602.00 2.82% 619.00 2.82% -
2.7.4 CP Brass swan neck, 15mm nominal bore. Each 535.00 517.00 3.48% 535.00 3.48% -
2.7.5 (-do-) long body, 15mm nominal bore weight not less Each 677.00 658.00 2.89% 677.00 2.89% -
than 690 grm
2.7.6 (-do-) long nose, 15mm nominal bore weight not less Each 852.00 833.00 2.28% 852.00 2.28% -
than 810 gm
2.7.7 (-do-) Elbow action, 15mm nominal bore Each 773.00 755.00 2.38% 773.00 2.38% -
2.7.8 Synthetic Material (PTMT) bib cock of approved quality / Each 203.00 187.00 8.56% 203.00 8.56% -
make, nominal bore, 15mm 86 mm long
2.7.9 (-do-) Fancy Type, 122mm long Each 236.00 219.00 7.76% 236.00 7.76% -
2.7.10 (-do-) long body, 175mm long Each 269.00 253.00 6.32% 269.00 6.32% -

2.8 P & F stop cock (IS:8931 Mark), superior quality of


approved make :
2.8.1 Brass 400 gm. 15mm nominal bore. Each 289.00 272.00 6.25% 289.00 6.25% -
2.8.2 Brass 750 gm. 20mm nominal bore. Each 355.00 338.00 5.03% 355.00 5.03% -
2.8.3 Brass 1350 gm. 25mm nominal bore. Each 580.00 562.00 3.20% 580.00 3.20% -
2.8.4 C.P. Brass 15mm nominal bore. Each 628.00 609.00 3.12% 628.00 3.12% -
2.8.5 (-do-) Concealed stop cock 15mm Each 784.00 765.00 2.48% 784.00 2.48% -
2.8.6 Synthetic material (PTMT) stop cock of approved quality Each 196.00 178.00 10.11% 195.00 9.55% -
/ make 15mm
2.8.7 (-do-) Concealed stop cock 15mm Each 309.00 292.00 5.82% 309.00 5.82% -

2.9 P & F Sink cocks of superior quality & approved made :

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-2
Chapter Code Description Unit Analysis Rate As per BSR As per % above % Proposed % Above Proposed % Above
No. 2018 A BSR 2018 on BSR above Rate for with BSR Rate for BSR with BSR
B 2018 BSR BSR 2019 2018A 2019 2018 B
2018 B A B
2.9.1 CP Sink cock swinging spout 15mm Each 684.00 665.00 2.86% 684.00 2.86% -
2.9.2 (-do-) Casted spout 15mm Each 758.00 739.00 2.57% 758.00 2.57% -
2.10 P & F Push cock superior quality of approved make
2.10.1 CP Brass 15mm Each 337.00 319.00 5.64% 337.00 5.64% -
2.10.2 Synthetic material (PTMT) push cock of approved Each 209.00 192.00 8.85% 209.00 8.85% -
quality / make 15mm

2.11 P & F Ball Cock (IS : 1703 Mark) with Rod & P.V.C. Ball
complete :
2.11.1 Brass wt.400 gm. 15mm Each 262.00 234.00 11.97% 256.00 9.40% -
2.11.2 Brass wt.750 gm. 20mm Each 403.00 374.00 7.75% 403.00 7.75% -
2.11.3 (-do-) wt.1000 gm. 25mm Each 436.00 407.00 7.13% 436.00 7.13% -
2.11.4 (-do-) wt.1000 gm. 32mm Each 437.00 408.00 7.11% 437.00 7.11% -
2.11.5 (-do-) wt.1200 gm. 40mm Each 716.00 686.00 4.37% 716.00 4.37% -
2.11.6 (-do-) wt.2000 gm. 50mm Each 743.00 711.00 4.50% 743.00 4.50% -
2.11.7 Synthetic material (PTMT) of approved make 15mm Each 242.00 213.00 13.62% 233.00 9.39% -
nominal size.
2.11.8 (-do-) 20mm nominal size Each 321.00 293.00 9.56% 321.00 9.56% -
2.11.9 (-do-) 25mm nominal size Each 658.00 629.00 4.61% 658.00 4.61% -
2.11.10 (-do-) 50mm nominal size Each 1713.00 1680.00 1.96% 1,713.00 1.96% -

2.12 P & F Inlet Connection (Angle Valves) Superior quality,


of approved make for Wash basin, Gyset etc.
2.12.1 C.P. Inlet connection 15mm. Brass (IS:8931 marked) Each 467.00 438.00 6.62% 467.00 6.62% -

2.12.2 ---do--- with 37cm long pipe and nut Each 642.00 612.00 4.90% 642.00 4.90% -
2.12.3 ---do--- with 37cm longthread and nut Each 700.00 670.00 4.48% 700.00 4.48% -
2.12.4 Synthetic material (PTMT) Inlet connection of approved
quality / make 15mm nominal size.
Each 281.00 253.00 11.07% 277.00 9.49% -
2.13 P & F 15mm. Dia Connection Pipe of approved
quality/make :
2.13.1 PVC pipe with C.P. Brass nuts upto length 300mm Each 56.00 44.00 27.27% 48.00 9.09% -
2.13.2 (-do-) upto length 370mm Each 64.00 52.00 23.08% 57.00 9.62% -
2.13.3 (-do-) 450mm Each 81.00 70.00 15.71% 77.00 10.00% -
2.13.4 (-do-) 600mm Each 89.00 77.00 15.58% 84.00 9.09% -
2.13.5 CP Brass pipe with CP Brass nuts upto length 300mm Each 72.00 60.00 20.00% 66.00 10.00% -

2.13.6 (-do-) 370mm Each 89.00 77.00 15.58% 84.00 9.09% -


2.13.7 (-do-) 450mm Each 105.00 94.00 11.70% 103.00 9.57% -
2.13.8 (-do-) 600mm Each 139.00 127.00 9.45% 139.00 9.45% -

2.14 P & F Flush Cock / Flush Valve (IS : 9758 Mark) For WC
of approved quality make.
2.14.1 CP brass push type 15mm nominal bore. Each 265.00 248.00 6.85% 265.00 6.85% -
2.14.2 (-do-) 20mm nominal bore. Each 499.00 480.00 3.96% 499.00 3.96% -
2.14.3 (-do-) exposed 25mm nominal bore. Each 926.00 907.00 2.09% 926.00 2.09% -
2.14.4 (-do-) 32mm nominal bore. Each 1387.00 1366.00 1.54% 1,387.00 1.54% -
2.14.5 (-do-) concealed 25mm nominal bore. Each 999.00 979.00 2.04% 999.00 2.04% -
2.14.6 (-do-) 32mm nominal bore. Each 1539.00 1516.00 1.52% 1,539.00 1.52% -
2.14.7 (-do-) Half-turn exposed 25mm nominal bore. Each 817.00 798.00 2.38% 817.00 2.38% -
2.14.8 (-do-) concealed 25mm nominal bore. Each 958.00 938.00 2.13% 958.00 2.13% -
2.14.9 Brass / Gun metal half-turn wt. 1 kg. of approved Each 504.00 486.00 3.70% 504.00 3.70% -
quality / make, 25mm nominal bore.
2.14.10 CP Brass flush valve 32mm nominal bore. Each 2223.00 2199.00 1.09% 2,223.00 1.09% -

2.15 P & F Full way valve (IS:778 Mark) or wheel valve of


approved make :
2.15.1 Gun-metal 15mm nominal bore. Each 292.00 263.00 11.03% 288.00 9.51% -
2.15.2 (-do-) 20mm nominal bore. Each 383.00 354.00 8.19% 383.00 8.19% -
2.15.3 (-do-) 25mm nominal bore. Each 562.00 533.00 5.44% 562.00 5.44% -
2.15.4 (-do-) 32mm nominal bore. Each 743.00 711.00 4.50% 743.00 4.50% -
2.15.5 (-do-) 40mm nominal bore. Each 1097.00 1066.00 2.91% 1,097.00 2.91% -
2.15.6 (-do-) 50mm nominal bore. Each 1459.00 1427.00 2.24% 1,459.00 2.24% -
2.16 P & F Gun-metal non-return Valve or Check Valve (IS:
Make) or approved make, superior quality
2.16.1 15mm nominal bore. Each 245.00 217.00 12.90% 238.00 9.68% -
2.16.2 20mm nominal bore. Each 318.00 289.00 10.03% 316.00 9.34% -
2.16.3 25mm nominal bore. Each 502.00 472.00 6.36% 502.00 6.36% -
2.16.4 32mm nominal bore. Each 683.00 654.00 4.43% 683.00 4.43% -
2.16.5 40mm nominal bore. Each 917.00 886.00 3.50% 917.00 3.50% -
2.16.6 50mm nominal bore. Each 1282.00 1250.00 2.56% 1,282.00 2.56% -

2.17 P & F Flush valve (Hydraulic) with level complete (IS :


9758 Mark) of approved make :
2.17.1 32mm nominal bore. Each 2721.00 2684.00 1.38% 2,721.00 1.38% -
2.17.2 25mm nominal bore. Each 2362.00 2326.00 1.55% 2,362.00 1.55% -

2.18 P & F Oxidised Gas Taps, Bench-type of superior


quality and approved make :
2.18.1 One way Each 409.00 369.00 10.84% 404.00 9.49% -
2.18.2 Two way Each 541.00 500.00 8.20% 541.00 8.20% -
2.18.3 Three way Each 616.00 575.00 7.13% 616.00 7.13% -
2.18.4 Four way Each 739.00 698.00 5.87% 739.00 5.87% -
2.19 P & F Chromium plated Swan-neck Laboratory Cock of
Approved quality / make :
2.19.1 One way Each 409.00 369.00 10.84% 404.00 9.49% -
2.19.2 Two way Each 541.00 500.00 8.20% 541.00 8.20% -
2.19.3 Three way Each 739.00 698.00 5.87% 739.00 5.87% -
2.19.4 Four way Each 822.00 779.00 5.52% 822.00 5.52% -

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-2
Chapter Code Description Unit Analysis Rate As per BSR As per % above % Proposed % Above Proposed % Above
No. 2018 A BSR 2018 on BSR above Rate for with BSR Rate for BSR with BSR
B 2018 BSR BSR 2019 2018A 2019 2018 B
2018 B A B
2.20 P & F Spouts of superior quality and approved make :

2.20.1 C.P. brass spout Each 697.00 668.00 4.34% 697.00 4.34% -
2.20.2 (-do-) Extra heavy with flange Each 851.00 821.00 3.65% 851.00 3.65% -
2.21 P & F Mixing Range (15mm)
2.21.1 C.P. One hole / close basin mixer with casted spout Each 1950.00 1875.00 4.00% 1,950.00 4.00% -
2.21.2 (-do-) with swinging spout casted Each 2250.00 2173.00 3.54% 2,250.00 3.54% -
2.21.3 C.P. sink mixer with swinging spout J-pipe Each 2250.00 2173.00 3.54% 2,250.00 3.54% -
2.21.4 (-do-) with casted spout Each 2250.00 2173.00 3.54% 2,250.00 3.54% -
2.21.5 C.P. valve mixer non-telephonic type Each 1950.00 1875.00 4.00% 1,950.00 4.00% -
2.21.6 C.P. wall mixer telephonic type crutch & telephonic Each 3738.00 3643.00 2.61% 3,738.00 2.61% -
shower
2.21.7 (-do-) without crutch & telephonic shower Each 2811.00 2718.00 3.42% 2,811.00 3.42% -
2.21.8 C.P. Bath - tub mixer without telephonic shower but with Each 3415.00 3335.00 2.40% 3,415.00 2.40% -
crutch
2.21.9 C.P. Surgical basin mixer elbow action Each 2903.00 2810.00 3.31% 2,903.00 3.31% -
2.21.10 (-do-) with shower (wall type) Each 4185.00 4088.00 2.37% 4,185.00 2.37% -

2.22 P & F Divertors of superior quality and approved make :

2.22.1 CP brass Tip-tone divertor bath spout with mixing valve. Each 2385.00 2323.00 2.67% 2,385.00 2.67% -

2.22.2 (-do-) Concealed Five-way divertors. Each 2570.00 2507.00 2.51% 2,570.00 2.51% -
2.22.3 (-do-) Four-way (-do-) Each 2619.00 2556.00 2.46% 2,619.00 2.46% -
2.22.4 (-do-) Three-way (-do-) Each 2438.00 2375.00 2.65% 2,438.00 2.65% -
2.22.5 (-do-) Two-way with 22cm pipe flange Each 1395.00 1336.00 4.42% 1,395.00 4.42% -

2.23 P & F Bidet (IS : 2556 Mark) of superior quality and


approved make with fittings :
2.23.1 CP brass bidet fittings without Pop up Each 3845.00 3777.00 1.80% 3,845.00 1.80% -
2.23.2 (-do-) with shower and Pop up waste Each 4529.00 4459.00 1.57% 4,529.00 1.57% -

2.24 P & F precast RCC water storage Tank with RCC cover
25mm thick and 15cm. Long GI over-flow pipe including
making connections etc. & hoisting upto 1M. Ht. From
ground level having :

2.24.1 340 litre water capacity size 90x75x60 cm Each 648.00 648.00 0.00% 648.00 0.00% -
2.24.2 270 litres water capacity size 90 x 60 x 60 cm Each 576.00 576.00 0.00% 576.00 0.00% -

2.25 Hoisting Charges of precast RCC water storage tank on


each floor

2.25.1 340 litre water capacity Each 144.00 144.00 0.00% 144.00 0.00% -
2.25.2 270 litres water capacity Each 108.00 108.00 0.00% 108.00 0.00% -
2.26 P & F PVC storage Tank (IS : 12701 marked indicating
the BIS license No.), of approved make with cover,
25mm dia 1M long G.I. over flow pipe & 25 cm. long
wash out pipe with plug & socket, including making
connection etc. complete of approved design :

2.26.1 200 litres capacity. Each 1535.00 1529.00 0.39% 1,535.00 0.39% -
2.26.2 300 (-do-) Each 2303.00 2295.00 0.35% 2,303.00 0.35% -
2.26.3 500 (-do-) Each 3837.00 3823.00 0.37% 3,837.00 0.37% -
2.26.4 750 (-do-) Each 5751.00 5731.00 0.35% 5,751.00 0.35% -
2.26.5 1000 (-do-) Each 7673.00 7647.00 0.34% 7,673.00 0.34% -
2.26.6 2000 (-do-) Each 15345.00 15293.00 0.34% 15,345.00 0.34% -
2.26.7 3000 (-do-) Each 23018.00 22941.00 0.34% 23,018.00 0.34% -
2.26.8 5000 (-do-) Each 38363.00 38235.00 0.33% 38,363.00 0.33% -

2.27 Hoisting Charges for each floor :


2.27.1 For items 2.26.1 to 2.26.4 Each 50.00 50.00 0.00% 50.00 0.00% -
2.27.2 For items 2.26.5 to 2.26.8 Each 100.00 100.00 0.00% 100.00 0.00% -
2.28 Providing and fixing Bitumen Paint Coating over G.I.
Pipes Complete as per specifications :

2.28.1 15mm dia Each 1.15 1.15 0.00% 1.00 -13.04% -


2.28.2 20mm dia Each 1.40 1.40 0.00% 1.40 0.00% -
2.28.3 25mm dia Each 2.00 2.00 0.00% 2.00 0.00% -
2.28.4 40mm dia Each 2.75 2.75 0.00% 2.75 0.00% -

2.29.1.2 1620 (20mm OD) pipe Each 245.00 212.75 15.16% 233.00 9.52%
2.29.1.3 2025 (25mm OD) pipe Each 300.00 270.25 11.01% 296.00 9.53%
2.29.1.4 2532 (32mm OD) pipe Each 396.00 366.00 8.20% 396.00 8.20%
2.29.1.5 3240 (40mm OD) pipe Each 518.00 477.00 8.60% 518.00 8.60%

2.30 Providing and fixing Polyethylene - Aluminimum -


Polyethylene (PE-AL-PE) Composite Pressure Pipes as
per 15450 : 2004 U.V. stablised with carbon black
having thermal stabillity for hot and cold water supply
with all compression type composite internal seal fittings
(e.g. elbows, tees, reducers, couplers connectors etc.)
including cutting chases on walls & making (Internal
work)

2.30.1 Concealed installation including cutting chases and


making good the walls etc. complete.

2.30.1.1 1216 (16mm OD) pipe P.Rmt. 276.00 209.30 31.87% 229.00 9.41%
2.30.1.2 1620 (20mm OD) pipe P.Rmt. 310.00 242.65 27.76% 266.00 9.62%
2.30.1.3 2025 (25mm OD) pipe P.Rmt. 364.00 295.55 23.16% 324.00 9.63%
2.30.1.4 2532 (32mm OD) pipe P.Rmt. 460.00 386.40 19.05% 423.00 9.47%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-2
Chapter Code Description Unit Analysis Rate As per BSR As per % above % Proposed % Above Proposed % Above
No. 2018 A BSR 2018 on BSR above Rate for with BSR Rate for BSR with BSR
B 2018 BSR BSR 2019 2018A 2019 2018 B
2018 B A B
2.30.1.5 3240 (40mm OD) pipe P.Rmt. 560.00 489.90 14.31% 536.00 9.41%

2.31 Providing and fixing Polyethylene - Aluminimum -


Polyethylene (PE-AL-PE) Composite Pressure Pipes as
per 15450 : 2004 U.V. stablised with carbon black
having thermal stabillity for hot and cold water supply
with all compression type composite internal seal fittings
(e.g. elbows, tees, reducers, couplers connectors etc.)
including trenching & refilling the same etc. (External
work)

2.31.1 1216 (16mm OD) pipe P.Rmt. 185.00 169.05 9.44% 185.00 9.44%
2.31.2 1620 (20mm OD) pipe P.Rmt. 210.00 197.00 6.60% 210.00 6.60%
2.31.3 2025 (25mm OD) pipe P.Rmt. 258.00 244.00 5.74% 258.00 5.74%
2.31.4 2532 (32mm OD) pipe P.Rmt. 326.00 312.00 4.49% 326.00 4.49%
2.31.5 3240 (40mm OD) pipe P.Rmt. 415.00 401.00 3.49% 415.00 3.49%

2.32 Supply & fixing G.I. Union ISI marked in G.I. pipe line as
required complete in all respect of size.

2.32.1 15mm dia nominal bore P.Rmt. 69.00 63.00 9.52% 69.00 9.52%
2.32.2 20mm dia nominal bore P.Rmt. 100.00 91.00 9.89% 100.00 9.89%
2.32.3 25mm dia nominal bore P.Rmt. 146.00 133.00 9.77% 146.00 9.77%
2.32.4 32mm dia nominal bore P.Rmt. 200.00 182.00 9.89% 199.00 9.34%
2.32.5 40mm dia nominal bore P.Rmt. 266.00 242.00 9.92% 265.00 9.50%
2.32.6 50mm dia nominal bore P.Rmt. 386.00 351.00 9.97% 384.00 9.40%
2.32.7 65mm dia nominal bore P.Rmt. 932.00 847.00 10.04% 927.00 9.45%
2.32.8 80mm dia nominal bore P.Rmt. 1265.00 1150.00 10.00% 1,259.00 9.48%

2.33 Providing and fixing Superior quality CP Brass


fittings of approved make as per direction of
Engineer-in-charge
2.33.1 Pillar Cock 15 mm nominal size Each 748.00 748.00 0.00 748.00 819.00 9.49% 748.00 0.00%
2.33.2 Swan neck pillar cock 15 mm nominal size Each 1436.00 1436.00 0.00 1436.00 1,572.00 9.47% 1436.00 0.00%
2.33.3 Bib Cock with long thread 15 mm nominal size Each 748.00 748.00 0.00 748.00 819.00 9.49% 748.00 0.00%
2.33.4 Long body Bib Cock 15 mm nominal size Each 985.00 985.00 0.00 985.00 1,079.00 9.54% 985.00 0.00%
2.33.5 Two way Bib Cock 15 mm nominal size Each 1067.00 1067.00 0.00 1067.00 1,168.00 9.47% 1067.00 0.00%
2.33.6 Angular stop cock with long thread 15 mm nominal Each 693.00 693.00 0.00 693.00 759.00 9.52% 693.00 0.00%
size
2.33.7 Stop cock long thread Each 726.00 726.00 0.00 726.00 795.00 9.50% 726.00 0.00%
2.33.8 Stop cock with reduced body Each 924.00 924.00 0.00 924.00 1,012.00 9.52% 924.00 0.00%
2.33.9 Concealed stop cock 15 mm nominal size Each 1056.00 1056.00 0.00 1056.00 1,156.00 9.47% 1056.00 0.00%
2.33.10 Sink cock with swinging casted spout (table Each 1474.00 1474.00 0.00 1474.00 1,614.00 9.50% 1474.00 0.00%
mounted ) 15 mm nominal size
2.33.11 Single lever wash basin mixer with 450 mm long Each 4235.00 4235.00 0.00 4235.00 4,637.00 9.49% 4235.00 0.00%
copper connection pipe
2.33.12 Central hole basin mixer Each 2453.00 2453.00 0.00 2453.00 2,686.00 9.50% 2453.00 0.00%
2.33.13 Wall mixer 3 in 1 system with provision of Each 3403.00 3403.00 0.00 3403.00 3,726.00 9.49% 3403.00 0.00%
tetephonic bath shower with bend pipe
2.33.14 600 mm long towel rail Each 1637.00 1637.00 0.00 1637.00 1,793.00 9.53% 1637.00 0.00%
2.33.15 Revolving type towel ring Each 1001.00 1001.00 0.00 1001.00 1,096.00 9.49% 1001.00 0.00%
2.33.16 Soap dish Each 974.00 974.00 0.00 974.00 1,067.00 9.55% 974.00 0.00%
2.33.17 Double coat hook Each 748.00 748.00 0.00 748.00 819.00 9.49% 748.00 0.00%
2.33.18 190 mm rain shower Each 5075.00 5075.00 0.00 5075.00 5,557.00 9.50% 5075.00 0.00%
2.33.19 Shower arm Each 1100.00 1100.00 0.00 1100.00 1,205.00 9.55% 1100.00 0.00%
2.33.20 Paper holder Each 1023.00 1023.00 0.00 1023.00 1,120.00 9.48% 1023.00 0.00%
2.33.21 Hand shower with 8 mm dia 1 mt long PVC tube & Each 1665.00 1665.00 0.00 1665.00 1,823.00 9.49% 1665.00 0.00%
wall hook complete

2.34 Providing and fixing 3-layer PP-R (Polypropylene


random coplymer ) pipes SDR 7.4 UV stabilized and
antimicrobial fusion welded, having thermal stability
for hot & cold water supply including all PP-R plain
& brass threaded Polypropylene random fittings and
fixing the pipe with clamps at 1.00 spacing. This
includes testing of joint complete as per direction of
Engineer - in charge.( INTERNAL WORK- EXPOSED
ON WALL)

2.34.1 PN-16 Pipe, 16 mm OD Rm 131.00 139.00 6.11 131.00 152.00 9.35% 131.00 0.00%
2.34.2 PN-16 Pipe, 20 mm OD Rm 150.00 161.00 7.33 150.00 176.00 9.32% 150.00 0.00%
2.34.3 PN-16 Pipe, 25 mm OD Rm 215.00 218.00 1.40 215.00 239.00 9.63% 215.00 0.00%
2.34.4 PN-16 Pipe, 32 mm OD Rm 301.00 305.00 1.33 301.00 334.00 9.51% 301.00 0.00%
2.34.5 PN-16 Pipe, 40 mm OD Rm 417.00 421.00 0.96 417.00 461.00 9.50% 417.00 0.00%
2.34.6 PN-16 Pipe, 50 mm OD Rm 605.00 608.00 0.50 605.00 666.00 9.54% 605.00 0.00%
0.00

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-2
Chapter Code Description Unit Analysis Rate As per BSR As per % above % Proposed % Above Proposed % Above
No. 2018 A BSR 2018 on BSR above Rate for with BSR Rate for BSR with BSR
B 2018 BSR BSR 2019 2018A 2019 2018 B
2018 B A B
2.35 Providing and fixing 3-layer PP-R (Polypropylene 0.00
random coplymer ) pipes SDR 7.4 UV stabilized and
antimicrobial fusion welded, having thermal stability
for hot & cold water supply including all PP-R plain
& brass threaded Polypropylene random fittings and
fixing the pipe with clamps at 1.00 spacing. This
includes cost of cutting chases and making good
the same including testing of joint complete as per
direction of Engineer - in charge.(CONCELED WORK
INCLUDING CUTTING CHASES AND MAKING GOOD
THE WALL ETC.)

2.35.1 PN-16 Pipe, 16 mm OD Rm 179.00 183.00 2.23 179.00 200.00 9.29% 179.00 0.00%
2.35.2 PN-16 Pipe, 20 mm OD Rm 201.00 204.00 1.49 201.00 223.00 9.31% 201.00 0.00%
2.35.3 PN-16 Pipe, 25 mm OD Rm 259.00 262.00 1.16 259.00 287.00 9.54% 259.00 0.00%
2.35.4 PN-16 Pipe, 32 mm OD Rm 345.00 349.00 1.16 345.00 382.00 9.46% 345.00 0.00%
0.00
2.36 Providing and fixing 3-layer PP-R (Polypropylene 0.00
random coplymer ) pipes SDR 7.4 UV stabilized and
antimicrobial fusion welded, having thermal stability
for hot & cold water supply including all PP-R plain
& brass threaded Polypropylene random fittings
including trenching, refilling and testing of joint
complete as per direction of Engineer - in charge.
(EXTERNAL WORKS)

2.36.1 PN-16 Pipe, 16 mm OD Rm 118.00 123.00 4.24 118.00 135.00 9.76% 118.00 0.00%
2.36.2 PN-16 Pipe, 20 mm OD Rm 140.00 145.00 3.57 140.00 159.00 9.66% 140.00 0.00%
2.36.3 PN-16 Pipe, 25 mm OD Rm 198.00 203.00 2.53 198.00 222.00 9.36% 198.00 0.00%
2.36.4 PN-16 Pipe, 32 mm OD Rm 285.00 289.00 1.40 285.00 316.00 9.34% 285.00 0.00%
2.36.5 PN-16 Pipe, 40 mm OD Rm 400.00 405.00 1.25 400.00 443.00 9.38% 400.00 0.00%
2.36.6 PN-16 Pipe, 50 mm OD Rm 516.00 593.00 14.92 516.00 649.00 9.44% 516.00 0.00%
2.36.7 PN-16 Pipe, 63 mm OD Rm 868.00 873.00 0.58 868.00 956.00 9.51% 868.00 0.00%

2.37 Providing and fixing Chlorinated Polyvinyl Chloride


(CPVC) pipes, having thermal stability for hot & cold
water supply including all CPVC plain & brass
threaded fittings i/c fixing the pipe with clamps at
1.00 m spacing. This includes jointing of pipes &
fittings with one step CPVC solvent cement and
testing of joints complete as per direction of
Engineer in Charge. (Internal work Exposed on wall)

2.37.1 15 mm nominal outer dia pipes Rm 122.00 165.00 35.25 140.00 181.00 9.70% 140.00 0.00%
2.37.2 20mm nominal outer dia pipes Rm 143.00 192.00 34.27 155.00 210.00 9.38% 155.00 0.00%
2.37.3 25 mm nominal outer dia pipes Rm 188.00 237.00 26.06 197.00 260.00 9.70% 197.00 0.00%
2.37.4 32mm nominal outer dia pipes Rm 246.00 309.00 25.61 258.00 338.00 9.39% 258.00 0.00%
2.37.5 40 mm nominal outer dia pipes Rm 346.00 455.00 31.50 363.00 498.00 9.45% 363.00 0.00%
2.37.6 50 mm nominal outer dia pipes Rm 535.00 599.00 11.96 561.00 656.00 9.52% 561.00 0.00%
0.00
2.38 Providing and fixing Chlorinated Polyvinyl Chloride 0.00
(CPVC) pipes, having thermal stability for hot & cold
water supply including all CPVC plain & brass
threaded fittings i/c fixing the pipe with clamps at
1.00 m spacing. This includes jointing of pipes &
fittings with one step CPVC solvent cement and the
cost of cutting chases and making good the same
including testing of joints complete as per direction
of Engineer in Charge. (Concealed work including
cutting chases and making good the walls etc.,)

2.38.1 15 mm nominal outer dia pipes Rm 190.00 202.00 6.32 195.00 221.00 9.41% 195.00 0.00%
2.38.2 20mm nominal outer dia pipes Rm 198.00 222.00 12.12 202.00 243.00 9.46% 202.00 0.00%
2.38.3 25 mm nominal outer dia pipes Rm 263.00 267.00 1.52 263.00 292.00 9.36% 263.00 0.00%
2.38.4 32mm nominal outer dia pipes Rm 333.00 337.00 1.20 333.00 369.00 9.50% 333.00 0.00%

2.39 Providing and fixing Chlorinated Polyvinyl Chloride


(CPVC) pipes, having thermal stability for hot & cold
water supply including all CPVC plain & brass
threaded fittings, this included jointing of pipes &
fittings with one step CPVC solvent cement ,
trenching refilling & testing of joints complete as
per direction of Engineer in Charge.
(External work).

2.39.1 15 mm nominal outer dia pipes Rm 112.00 142.00 26.79 117.00 155.00 9.15% 117.00 0.00%
2.39.2 20mm nominal outer dia pipes Rm 131.00 162.00 23.66 137.00 177.00 9.26% 137.00 0.00%
2.39.3 25 mm nominal outer dia pipes Rm 175.00 207.00 18.29 183.00 227.00 9.66% 183.00 0.00%
2.39.4 32mm nominal outer dia pipes Rm 229.00 266.00 16.16 240.00 291.00 9.40% 240.00 0.00%
2.39.5 40 mm nominal outer dia pipes Rm 314.00 385.00 22.61 329.00 422.00 9.61% 329.00 0.00%
2.39.6 50 mm nominal outer dia pipes Rm 525.00 529.00 0.76 529.00 579.00 9.45% 529.00 0.00%
0.00

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : S-2
Chapter Code Description Unit Analysis Rate As per BSR As per % above % Proposed % Above Proposed % Above
No. 2018 A BSR 2018 on BSR above Rate for with BSR Rate for BSR with BSR
B 2018 BSR BSR 2019 2018A 2019 2018 B
2018 B A B
2.40 Providing and fixing Premium quality Towel rack Each 2808.00 2808.00 2808.00 3,075.00 9.51% 2808.00 0.00%
600mm long 260mm wide with lower hangers CP
Brass fittings of approved make as per direction of
Engineer-in-charge

0.00
2.41 Labour Charges for Removing & Refixing the water Each 335.00 335.00 335.00 367.00 9.55% 335.00 0.00%
Storage Tank of all sizes and including all
Necessary fitting complete in all respect as per
approved sample and direction of engineer in
charge.

2.42 Providing and fixing premium quality Angular stop Each 1429.00 1429.00 1429.00 1,565.00 9.52% 1429.00 0.00%
cock with wall flange complete as per sample
approved by Engineer in charge

2.43 Providing and fixing premium quality Two way Bib Each 2123.00 2123.00 2123.00 2,325.00 9.51% 2123.00 0.00%
cock with wall flange complete as per sample
approved by Engineer in charge

2.44 Providing and fixing superior quality PVC Tank


Cover complete as per approved by Engineer In
Charge

2.44.1 300 Lt. capacity Rate analysis for 1 No. Each 135.00 135.00 135.00 148.00 9.63% 135.00 0.00%

2.44.2 500 Lt. capacity Rate analysis for 1 No. Each 146.00 146.00 146.00 160.00 9.59% 146.00 0.00%

2.44.3 Above 500 Lt. capacity Rate analysis for 1 No. Each 157.00 157.00 157.00 172.00 9.55% 157.00 0.00%

2.45 Providing & fixing C.I. Saddle pieces 100mm dia Each 178.00 178.00 178.00 195.00 9.55% 178.00 0.00%
with nut & bolt & washer & Rubber Gasket complete
as per direction of engineer in charge

2.46 Supply and installation of Premium quality sluice Each 4584.00 4584.00 4584.00 5,019.00 9.49% 4584.00 0.00%
valve 100mm dia including all fittings as per
approved by Engineer in charge.

2.47 Providing Laying Jointing DI Pipe (Ductile iron pipe) Mtr 989.00 989.00 989.00 1,083.00 9.50% 989.00 0.00%
of 100 mm dia ISI marked K-7 grade as per IS : 5329-
2000 with internal cement mortar lining for potable
water with rubber ring (EPDM/ SBR) Joints per IS :
5382-1985 complete including Hydraulic testing &
commissioning as per Technical Specification.

223099.30 9672.00 216488.15 8499.00 3.05% 13.80% 221668.15 2.39% 9191.00 8.14%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
SANITARY INSTALLATION WORK
NOTE: All items which are manufactured ISI marked, shall only be used. this condition shall be always
incorporated in special condition of contract.
CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

WATER CLOSETS
1.1 P. & F Squatting Pan (Indian type) white glazed vitreous china
1st quality W.C. Pan (IS : 2556 Mark) with 100 mm vitreous
china P or S trap including cutting and making good the wall and
floor (excluding the pair of foot rest.)
1.1.1 Size 450mm. Each 1412.00 1028.00 37.35% 1,079.00 4.96%
1.1.2 Size 510 mm Each 1454.00 1070.00 35.89% 1,123.00 4.95%
1.1.3 Size 580mm Each 1498.00 1114.00 34.47% 1,169.00 4.94%

1.2 P & F Indian type white glazed vitreous china 1st quality W.C.
orissa pan (IS :2556 Mark) with 100 mm vitreous china P or S
trap including cutting and making good the wall and floor:

1.2.1 Size 530x410mm. Each 2024.00 1638.00 23.57% 1,719.00 4.95%


1.2.2 Size 580x440mm. Each 2081.00 1696.00 22.70% 1,780.00 4.95%

1.3 P & F WVC Foot- rest (IS : 2556 Mark) including cutting and
making good the floor size:

1.3.1 250x125x25mm. Pair 191.00 181.00 5.52% 190.00 4.97%


1.3.2 250x130x30mm Pair 165.00 165.00 0.00% 165.00 0.00%
1.4 P & F European type white glazed vitreous china 1st quality W.C
pan (IS : 2556 Mark) with P or S trap including cutting and
making good the wall and floor
Each 1590.00 1206.00 31.84% 1,266.00 4.98%
1.5 P & F European type white glazed vitreous china 1st quality
Double syphonic W.C (IS :2556 Mark) with P or S trap including
cutting and making good the wall and floor
Each 4753.00 4358.00 9.06% 4,575.00 4.98%
1.6 P & F Universal (anglo-Indian type) white glazed vitreous china
W.C. pan 1st quality with P or Strap including cutting and making
good the wall and floor
Each 2645.00 2257.00 17.19% 2,369.00 4.96%
1.7 P & F European type white glazed vitreous china 1st quality W.C.
(IS : 2556 Mark) including cutting and making good the wall and
floor
1.7.1 Wall Mounting Each 3088.00 2699.00 14.41% 2,833.00 4.96%
1.7.2 Wall Mounting (extended) Each 3421.00 3031.00 12.87% 3,182.00 4.98%
1.7.3 Wall Mounting (syphonic) Each 4503.00 4110.00 9.56% 4,315.00 4.99%
Note-A Add extra over item No. 1.1 to 1.7, 1.14, 1.15, 1.19 and 1.39 for
using approved light coloured vitreous china ware i.e.ivory
champagne , perl , soft green , soft blue ,pink, ,light grey etc.
instead of white vitreouschinawares.
Note-B Add extra over item No. 1.1 to 1.7, 1.14, 1.15, 1.19 and 1.39 for
using approved dark colored vitreous china ware i.e.Cherry Red ,
Dark blue, Jet black, Magenta, Burgandy instead of white
vitreous chinawares.
1.8 P & F water closet Seat Covers with brass hinges
complete :
1.8.1 Solid PVC (ISI marked) grade-I Black for EWC. Each 346.00 346.00 0.00% 346.00 0.00%
1.8.2 -do- White. Each 418.00 418.00 0.00% 418.00 0.00%
1.8.3 -do- Coloured. Each 448.00 447.00 0.22% 448.00 0.22%
1.8.4 Non-breakable of other approved make Black. Each 276.00 276.00 0.00% 276.00 0.00%
1.8.5 -do- White. Each 298.00 297.00 0.34% 298.00 0.34%
1.8.6 -do- Coloured. Each 328.00 328.00 0.00% 328.00 0.00%

1.9 P & F C.P. lugs for toilet seat cover. Pair 87.00 87.00 0.00% 87.00 0.00%
1.10 Labour charges for removing W.C. pan (any type) of all sizes Each 115.00 115.00 0.00% 115.00 0.00%
with care including all necessary fittings P or S trap.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

1.11 P & F White glazed Conversion Bend for W.C. from P trap to S Each 163.00 163.00 0.00% 163.00 0.00%
trap.
1.12 P & F vitreous china P trap of approved quality Each 199.00 199.00 0.00% 199.00 0.00%
1.13 Add extra if C.I.P trap is used in place of Vitreous china P trap for Each 139.00 139.00 0.00% 139.00 0.00%
W.C.
1.14 P & F White Vitreous China Double Syphonic European W.C. Each 7638.00 7638.00 0.00% 7,638.00 0.00%
(I.S:2556Mark) with mounted W.V.C. flushing cistern of (IS :
2556 Mark) of 10 litre capacity complete with all necessary
internal fittings including cutting and making good the wall and
floor.

URINALS:
1.15 P & F lst quality WVC Urinal (IS:2556 mark) with 25mm dia G.I.
waste pipe, dome waste couplings, concealed iron brackets or
screws etc complete.

1.15.1 Flat Back (small) size 456x355x265mm. Each 1462.00 1124.00 30.07% 1,180.00 4.98%
1.15.2 Flat Back (large) or half stall size 610x400x80mm. Each 2744.00 2285.00 20.09% 2,399.00 4.99%
1.15.3 Mini stall size 455x385x350mm. Each 1491.00 1192.00 25.08% 1,251.00 4.95%

1.16 P & F W.V.C. Urinal Partition Plate of approved standard make


of size 630x315mm including making good the wall.
Each 1089.00 991.00 9.89% 1,040.00 4.94%
1.17 P&F Marble Urinal Partition slab both sides polished of approved
design cut from marble size 900x600mm.

1.17.1 Makrana II quality marble having light spots Each 1102.00 1005.00 9.65% 1,055.00 4.98%
1.17.2 Makrana `Albeta` Marble having light streaks. Each 952.00 855.00 11.35% 897.00 4.91%
1.17.3 Makrana `Adanga` or Raj Nagar 1St Quality White or Andhi Indo- Each 803.00 706.00 13.74% 741.00 4.96%
Italian marble.

1.18 P & F W.V.C. Half-Round Channel of approved make in C.M.


1:3, joints finished in white cement of:
1.18.1 Size 100mm dia. P.Rmt. 467.00 467.00 0.00% 467.00 0.00%

1.18.2 Size 150mm dia. P.Rmt. 664.00 664.00 0.00% 664.00 0.00%

1.19 P & F W.V.C. (IS: 2556 Mark) Squatting Urinal of standard make
complete. Including cutting & making good the floor:
1.19.1 Size 450x350mm Each 1275.00 1275.00 0.00% 1,275.00 0.00%

1.20 Labour charges for removing and refixing of urinals (all type &
sizes) including all necessary fittings.
Each 165.00 165.00 0.00% 165.00 0.00%
1.21 P & F High Level Flushing Cistern of 10 litres capacity of approved
make including C.I. brackets duly painted, chain & pull and 32 mm dia
G.I. concealed flush pipe with M.S. clamps, 20 mm dia G.I. overflow
pipe upto 185 cm. Long, brass ball cock (IS :1703 Mark) with PVC ball
and internal fittings and mosquito proof coupling, complete including
cutting and making good the wall.P & F High Level Flushing Cistern of
10 litres capacity of approved make including C.I. brackets duly
painted, chain & pull and 32 mm dia G.I. concealed flush pipe with M.S.
clamps, 20 mm dia G.I. overflow pipe upto 185 cm. Long, brass ball
cock (IS :1703 Mark) with PVC ball and internal fittings and mosquito
proof coupling, complete including cutting and making good the wall.

White PVC (IS: 7231 Mark). Each 1763.00 1691.00 4.26% 1,763.00 4.26%

1.22 P & F Low level Flushing Cistern of 10 litres capacity (IS :


2556mark). Of approved make with complete fittings C.I.
brackets duly painted, brass ball cock with ball, (IS: 1703 mark)
complete including cutting and making good the wall:
1.22.1 WVC with C.P. brass bend. Each 2043.00 1971.00 3.65% 2,043.00 3.65%
1.22.2 PVC with PVC bend as per IS : 7231 Each 1394.00 1323.00 5.37% 1,389.00 4.99%
1.22.3 PVC with PVC bend of make Commander champion Each 1300.00 1300.00 0.00% 1,300.00 0.00%
1.22.4 WVC for symphonic EWC. Each 2642.00 2567.00 2.92% 2,642.00 2.92%
1.22.5 PVC with CP brass long band. Each 1643.00 1573.00 4.45% 1,643.00 4.45%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

1.23 P & F Automatic Flushing Cistern of first quality (IS : 774 mark)
of approved make fitting, siphon with copper tube, C.I. brackets
complete including cutting and making good the wall. WVC (as
per IS : 2556) 10 litres
Each 1223.00 1223.00 0.00% 1,223.00 0.00%
Note :- Deduct if plastic syphon is used.

1.24 P & F Flush Pipe of approved make with complete fittings for
high level flushing cistern:
1.24.1 G.I. `B` class (Concealed) 25mm. Each 534.00 464.00 15.09% 487.00 4.96%
1.24.2 G.I. `B` class (Concealed) 32 mm. Each 650.00 580.00 12.07% 609.00 5.00%
1.24.3 PVC exposed (heavy) 32mm. Each 243.00 174.00 39.66% 182.00 4.60%
1.24.4 GI (Sheet) hot galvanized exposed (10 litres). Each 326.00 258.00 26.36% 270.00 4.65%

1.25 P & F WVC (10 litres) low-level flushing cistern with cover. Each 1064.00 1028.00 3.50% 1,064.00 3.50%
1.26 P & F WVC (10 litres) low-level flushing cistern cover only Each 427.00 407.00 4.91% 427.00 4.91%
1.27 P & F WVC syphon with plunger plate only. Each 297.00 296.00 0.34% 297.00 0.34%
1.28 P & F WVC Auto cistern with cover only. Each 723.00 688.00 5.09% 722.00 4.94%
1.29 P & F WVC Auto cistern cover only. Each 229.00 229.00 0.00% 229.00 0.00%

1.30 P & F C.P. brass Urinal Flush Pipe set complete with flanged
brackets of approved make.
1.30.1 For 4 Urinals Each 1729.00 1575.00 9.78% 1,653.00 4.95%
1.30.2 For 3 Urinals Each 1147.00 994.00 15.39% 1,043.00 4.93%
1.30.3 For 2 Urinals Each 811.00 733.00 10.64% 769.00 4.91%
1.30.4 For 1 Urinal Each 594.00 518.00 14.67% 543.00 4.83%

1.31 P & F C.P. brass Urinal Spreader for stall urinal of approved
make.
1.31.1 P & F Synthetic (PTMT) Urinal Spreader for stall urinal of Each 458.00 442.00 3.62% 458.00 3.62%
approved make.
1.32 P & F C.P. brass Doom Waste Coupling 32 mm dia. Each 319.00 303.00 5.28% 318.00 4.95%
1.32.1 P & F C.P. brass Doom Waste Coupling 40 mm dia. Each 333.00 317.00 5.05% 332.00 4.73%

1.33 P & F Plastic Syphon of approved make for automatic flush tank.

Each 236.00 220.00 7.27% 231.00 5.00%


1.34 P & F Copper tube Syphon for auto flush tank.
Each 430.00 400.00 7.50% 420.00 5.00%
1.35 Removing and re-fixing of wash hand basin including
allnecessary fittings.
Each 165.00 165.00 0.00% 165.00 0.00%
1.36 P & F C.I. brackets duly painted including cutting & making good
the wall.
Pair 135.00 135.00 0.00% 135.00 0.00%
1.37 P & F C.P. Brass flush Valve with C.P. flush bend of approved
make.

1.37.1 Lever type with Elbow 32 mm dia Each 2954.00 2944.00 0.34% 2,954.00 0.34%
1.37.2 Push type with Elbow 32 mm dia Each 3158.00 3147.00 0.35% 3,158.00 0.35%
1.37.3 Concealed type for 115 mm thick wall Each 3531.00 3519.00 0.34% 3,531.00 0.34%
1.37.4 Concealed type for 230 mm thick wall Each 3647.00 3634.00 0.36% 3,647.00 0.36%
1.37.5 Economy model 25 mm dia. Each 2145.00 2137.00 0.37% 2,145.00 0.37%
1.37.6 Economy model 32 mm dia. Each 2475.00 2466.00 0.36% 2,475.00 0.36%
WASH BASINS:
1.39 P & F WVC wash basin (1st quality, I.S. : 2556 Mark) of
approved make with C.I. brackets duly painted, 1 No. 15 mm
C.P. Pillar cock (IS : 8934 Mark) & 32 mm C.P. brass waste
coupling of approved make, 25 mm G.I. waste pipe complete
including cutting & making good the wall.:
1.39.1 Size 450 mm x 300 mm Each 1771.00 1472.00 20.31% 1,545.00 4.96%
1.39.2 Size 510 mm x 400 mm Each 1880.00 1580.00 18.99% 1,659.00 5.00%
1.39.3 Size 550 mm x 400 mm Each 1954.00 1653.00 18.21% 1,735.00 4.96%
1.39.4 Size 580 mm x 450 mm Each 2104.00 1803.00 16.69% 1,893.00 4.99%
1.39.5 Size 610 mm x 510 mm Each 2620.00 2317.00 13.08% 2,432.00 4.96%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

1.39.6 Size 400 mm x 400 mm or 450 mm x 390 mm Corner Each 1804.00 1504.00 19.95% 1,579.00 4.99%
1.39.7 460 dia for counter top Each 2230.00 1928.00 15.66% 2,024.00 4.98%
1.39.8 Size 550 mm x 400 mm dia for counter top Each 2271.00 1968.00 15.40% 2,066.00 4.98%
1.39.9 Size 630 mm x 500 mm dia for counter top Each 2970.00 2665.00 11.44% 2,798.00 4.99%
1.40 P & F Terrazzo (Mosaic) wash hand basin with supporting
brackets waste coupling and PVC waste pipe complete, including
painting of brackets making good the walls:
1.40.1 450 mm x 280 mm Each 1083.00 785.00 37.96% 824.00 4.97%
1.40.2 550 mm x 400 mm Each 1433.00 1133.00 26.48% 1,189.00 4.94%
KITCHEN & LAB. SINKS:
1.41 P & F Kitchen & Lab. Sink of approved make with C.I. brackets
duly painted, 40 mm C.P. waste coupling, C.P. Brass chain with
rubber plug, 40 mm G.I. waste pipe upto floor level complete
including cutting and making good the wall & floor :

1.41.1 Fire clay glazed kitchen sink (I.S. Marked) size 600 x 450 x Each 3460.00 3177.00 8.91% 3,335.00 4.97%
250mm.
1.41.2 Fire clay glazed kitchen sink (I.S. Marked) size 600 x 450 x 200 Each 3293.00 3011.00 9.37% 3,161.00 4.98%
mm.
1.41.3 WVC Lab sink (IS:2556 mark) size 530 x 430 x 180 mm Each 2919.00 2639.00 10.61% 2,770.00 4.96%
1.41.4 WVC Lab sink (IS:2556 mark) size 500 x 350 x 150 mm Each 2087.00 1810.00 15.30% 1,900.00 4.97%
1.41.5 WVC Lab sink (IS:2556 mark) size 450 x 300 x 150 mm Each 1961.00 1684.00 16.45% 1,768.00 4.99%
1.41.6 Mosaic fine polished kitchen sink size 600 x 450 x 200mm. Each 1295.00 1021.00 26.84% 1,072.00 5.00%
1.41.7 Mosaic fine polished kitchen sink size 450 x 450 x 200mm. Each 1129.00 854.00 32.20% 896.00 4.92%
1.41.8 Mosaic fine polished kitchen sink size 600 x 450 x 200 mm with Each 1172.00 1172.00 0.00% 1,172.00 0.00%
600 x 450mm drain board
1.41.9 1.0 mm thick Salem stainless steel AISI -304 kitchen sink of
approved make (Nirali, Neel – kanth, Jaina, Faber-Castell ) with
large waste coupling.
Overall size Bowl size
(inches) (inches)
1.41.10 18 x 16 x 6 16x14x6 Each 3550.00 3267.00 8.66% 3,430.00 4.99%
1.41.11 22 x 18 x 7 20x16x7 Each 4259.00 3974.00 7.17% 4,172.00 4.98%
1.41.12 24 x 18 x 8 20x16x8 Each 4376.00 4090.00 6.99% 4,294.00 4.99%
1.41.13 37 x 18 x 7 17x15x7 (with drain board) Each 5624.00 5334.00 5.44% 5,600.00 4.99%
1.41.14 45 x 20 x 8 20x16x8 (with drain board) Each 9787.00 9484.00 3.19% 9,787.00 3.19%
Note :- Deduct for item No 1.41.9 to 1.41.14 for using any other
make than specified above.
1.42 P & F Drain Board of approved make with C.I. brackets duly
painted compolete including cutting & making good the wall:
1.42.1 WVC (I.S.: 2556 Mark) size 530 x 450mm Each 1315.00 1200.00 9.58% 1,260.00 5.00%
1.42.2 Mosaic fine polished size 600 x 450 Each 270.00 270.00 0.00% 270.00 0.00%

1.43 P & F 1st quality WVC pedestal for wash basin. Each 832.00 832.00 0.00% 832.00 0.00%
MISCELLANEOUS
1.44 P & F Bottle Trap of approved make :
1.44.1 C.P Brass 32 mm Each 562.00 561.00 0.18% 562.00 0.18%
1.44.2 C.P Brass 40 mm Each 668.00 667.00 0.15% 668.00 0.15%
1.44.3 Synthetic Material (PTMT)32 mm Each 470.00 469.00 0.21% 470.00 0.21%
1.44.4 Synthetic Material (PTMT)42 mm Each 495.00 494.00 0.20% 495.00 0.20%
1.44.5 P.V.C Each 85.00 85.00 0.00% 85.00 0.00%
1.45 P& F waste Coulping with fittings of approved quality /make:
1.45.1 C.P Brass 32 mm dia Each 139.00 139.00 0.00% 139.00 0.00%
1.45.2 C.P Brass 40 mm dia Each 211.00 211.00 0.00% 211.00 0.00%
1.45.3 Synthetic Material(PTMT) 32 mm Each 95.00 95.00 0.00% 95.00 0.00%
1.45.4 Synthetic Material (PTMT)40 mm Each 139.00 139.00 0.00% 139.00 0.00%

1.46 P& F waste Pipe with all fitting


1.46.1 P.V.C with C.P nut 32 mm Each 119.00 119.00 0.00% 119.00 0.00%
1.46.2 P.V.C with PVC nut 32 mm Each 59.00 59.00 0.00% 59.00 0.00%
1.46.3 P.V.C. with C.P. nut 40 mm dia Each 152.00 152.00 0.00% 152.00 0.00%
1.46.4 G.I(B class) 32mm Each 139.00 139.00 0.00% 139.00 0.00%
1.46.5 G.I(B class) 40 mm Each 158.00 158.00 0.00% 158.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

1.47 P & F Bevelled edge Mirror of special glass of approved make


(Atul, Modi Guard, Saint Gobin or equivalent) complete with 6mm
thick asbestos cement sheet ground fixed to wooden screws &
washers.
1.47.1 Size 600 x 450mm x 4 mm thick Each 349.00 349.00 0.00% 349.00 0.00%
1.47.2 Other sizes P.Sqm 930.00 930.00 0.00% 930.00 0.00%

Note :- For other quality approved make mirrors deduct 30%


1.48 P & F Looking Mirrors with P.V.C. frame of approved (Atul, Modi
Guard , Saint Gobin or equivalent)
1.48.1 Size 500x400mm Each 334.00 334.00 0.00% 334.00 0.00%
1.48.2 Oval shape 450x350 mm Each 450.00 450.00 0.00% 450.00 0.00%
1.48.3 Round 500mm dia Each 487.00 487.00 0.00% 487.00 0.00%
Note :- For other quality approved make mirror deduct 30%
1.49 P & F Toilet Shelf of approved quality/make:
1.49.1 W.V.C. (I.S.: 2556 Mark) Size 300mm Each 178.00 178.00 0.00% 178.00 0.00%
1.49.2 W.V.C. (I.S.: 2556 Mark) Size 550 mm Each 264.00 264.00 0.00% 264.00 0.00%
1.49.3 Synthetic Material with tumbler of approved quality/make size Each 205.00 205.00 0.00% 205.00 0.00%
470 x 114 x 36mm
1.49.4 Hard Plastic of Commander/equivalent size 590x140mm Each 198.00 198.00 0.00% 198.00 0.00%
1.49.5 Acrylic shelf on C.P. brass casted brackets & guard rail of Each 766.00 766.00 0.00% 766.00 0.00%
Commander or equivalent make size 550x125mm
1.49.6 Glass Shelf with edges rounded off Anodised Aluminium angle Each 139.00 139.00 0.00% 139.00 0.00%
frame & C.P. brass brackets & guard rail size 600x120mm

1.50 P & F Towel Rail or Ring of approved quality/make:


1.50.1 C.P. brass Towel Rail elbow type with concealed screws size Each 356.00 356.00 0.00% 356.00 0.00%
450mm (Heavy duty).
1.50.2 C.P. brass Towel Rail elbow type with concealed screws size Each 396.00 396.00 0.00% 396.00 0.00%
600 mm (Heavy duty).
1.50.3 C.P. brass towel rail with brackets 450 x 20mm. Each 198.00 198.00 0.00% 198.00 0.00%
1.50.4 C.P. brass towel rail with brackets 600 x 20mm. Each 224.00 224.00 0.00% 224.00 0.00%
1.50.5 Synthetic Material(PTMT) of approved quality/make size 525 x90 Each 99.00 99.00 0.00% 99.00 0.00%
x 75mm
1.50.6 Synthetic Material(PTMT) of approved quality/make size 675 x90 Each 112.00 112.00 0.00% 112.00 0.00%
x 75mm
1.50.7 WVC (1stquality, ISI Marked) of approved make. Recessed towel Each 106.00 106.00 0.00% 106.00 0.00%
Hanger size 108 x 108mm.
1.50.8 C.P. Brass Towel Ring revolving type Each 132.00 132.00 0.00% 132.00 0.00%
1.50.9 Synthetic Material (PTMT) Towel Ring of approved quality/make. Each 119.00 119.00 0.00% 119.00 0.00%

1.51 P & F Grating of approved quality/make:


1.51.1 Stainless Steel Sheet size 125mm dia. Each 54.00 54.00 0.00% 54.00 0.00%
1.51.2 Stainless Steel Sheet size 125mm dia. Heavy Quality of Each 75.00 75.00 0.00% 75.00 0.00%
approved make
1.51.3 Synthetic Material(PTMT) of approved quality/make size 125mm Each 68.00 68.00 0.00% 68.00 0.00%
dia
1.51.4 (-do-) 150mm dia. Each 90.00 90.00 0.00% 90.00 0.00%
1.51.5 (-do-) Square 150 x 150 x 8mm. (Anti Cockroach) Each 235.00 235.00 0.00% 235.00 0.00%
1.51.6 C.P. brass with frame (Heavy) & superior quality size 125mm dia. Each 105.00 105.00 0.00% 105.00 0.00%

1.51.7 (-do-) Light & superior quality size 125mm dia Each 54.00 54.00 0.00% 54.00 0.00%
1.51.8 Cast Iron. Each 46.00 46.00 0.00% 46.00 0.00%

1.52 P & F Liquid Soap Container with brackets complete of approved


make:
1.52.1 C.P. brass Each 211.00 211.00 0.00% 211.00 0.00%
1.52.2 Synthetic Material of approved quality/make: Each 160.00 160.00 0.00% 160.00 0.00%

1.53 P & F Tooth Paste & Brush Holder of approved quality/make:

1.53.1 C.P. brass Each 66.00 66.00 0.00% 66.00 0.00%


1.53.2 C.P. brass (Heavy and Superior quality. Each 330.00 330.00 0.00% 330.00 0.00%
1.53.3 Stainless Steel Each 172.00 172.00 0.00% 172.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

1.54 P & F Toilet Paper Holder with rod of approved quality/make:

1.54.1 C.P. brass Each 139.00 139.00 0.00% 139.00 0.00%


1.54.2 C.P. brass heavy & Superior quality. Each 370.00 370.00 0.00% 370.00 0.00%
1.54.3 WVC (1stquality, ISI Marked) recessed size 150x150mm. Each 226.00 226.00 0.00% 226.00 0.00%
1.54.4 (-do-) exposed (-do-) Each 183.00 183.00 0.00% 183.00 0.00%

1.55 P & F Soap Dish or Tray of approved quality/make


1.55.1 C.P. brass Each 59.00 59.00 0.00% 59.00 0.00%
1.55.2 C.P. brass heavy and superior quality. Each 79.00 79.00 0.00% 79.00 0.00%
1.55.3 WVC (1st Quality, ISI Marked) recessed size 150 x 150 mm. Each 178.00 178.00 0.00% 178.00 0.00%

1.55.4 (-do-) 200 x100mm. Each 205.00 205.00 0.00% 205.00 0.00%
1.55.5 (-do-) Soap tray 170mm. Each 119.00 119.00 0.00% 119.00 0.00%
1.55.6 (-do-) Soap Dish 380mm. Each 165.00 165.00 0.00% 165.00 0.00%

1.56 P & F Twin- peg of approved quality / make


1.56.1 C.P. brass Each 101.00 101.00 0.00% 101.00 0.00%
1.56.2 C.P. brass (heavy)Superior quality Each 131.00 131.00 0.00% 131.00 0.00%
1.56.3 Acrylic Each 87.00 87.00 0.00% 87.00 0.00%

1.57 P & F Shower arm 15mm dia of approved quality/make.


1.57.1 C.P.brass heavy & superior quality 150mm Projection. Each 145.00 145.00 0.00% 145.00 0.00%
1.57.2 (-do-) size 220mm(-do-) Each 240.00 240.00 0.00% 240.00 0.00%
1.57.3 (-do-) size 300mm.(-do-) Each 270.00 270.00 0.00% 270.00 0.00%
1.57.4 (-do-) size 370mm.(-do-) Each 290.00 290.00 0.00% 290.00 0.00%

1.58 P & F Bath Shower of approved quality/make.


1.58.1 C.P. brass fixed. Each 183.00 183.00 0.00% 183.00 0.00%
1.58.2 C.P. brass of Heavy & superior quality 150mm. Each 298.00 298.00 0.00% 298.00 0.00%
1.58.3 C.P. brass of Heavy & superior quality, revolving with adjustable Each 473.00 473.00 0.00% 473.00 0.00%
key 150mm.

1.59 P & F Extension Pipe for bib cocks of approved quality/make.

1.59.1 C.P. brass of Heavy & Superior quality 50x15mm Each 145.00 145.00 0.00% 145.00 0.00%
1.59.2 (-do-) 100 X 15mm. Each 167.00 167.00 0.00% 167.00 0.00%
1.59.3 (-do-) 150 X 15mm. Each 183.00 183.00 0.00% 183.00 0.00%

1.60 P & F Acrylic Toilet accessories set consisting of Towel rail,


shelf, towel ring, soap dish, paste & brush holder & twin peg of
approved quality/make.
Each 924.00 924.00 0.00% 924.00 0.00%
1.61 Labour Charges for removing WVC pan:
1.61.1 Indian/Orissa pan Each 99.00 99.00 0.00% 99.00 0.00%
1.61.2 European W.C. Each 99.00 99.00 0.00% 99.00 0.00%
1.61.3 Flushing cistern Each 46.00 46.00 0.00% 46.00 0.00%

1.62 P & F Jet spray for water closet with C.P. Copper Tube flange of Each 290.00 290.00 0.00% 290.00 0.00%
approved make.
1.63 Providing & fixing C.P.flange for 15mm dia taps. Each 14.00 14.00 0.00% 14.00 0.00%

1.64 Providing and fixing 1st quality standard white, grey, ivory, fume red
brown, light green, light blue and other light shades glazed tiles
confirming to IS : 13753 & IS :15622 of size 200mm x 300mm in walls,
floors, steps, pillars etc. laid on a bed of neat cement slurry finished
with flush pointing in the white cement mixed with pigment to match the
shade of the tile complete (excluding the cost of cement plaster on
walls and pillar).

P.Sqm 875.00 660.00 32.58% 693.00 5.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

1.64.3 Add extra over item no. 1.64.1 and 1.64.2 for Marble printed, 15% 15% 15.0%
granite shade tiles.
1.64.4 Add extra over 1.64.1 and 1.64.2 for using coloured dark shade
tiles instead of White / Ivory / Light Grey/ Light Green/ Sky Blue/
Light Brown and other light shade coloures.
P.Sqm 99.00 81.00 22.22% 85.00 4.94%

1.65 Providing and fixing 75 mm wide Decorative Border in different


shades and in all coloures for glazed tiles
P.Rmt. 300.00 300.00 0.00% 300.00 0.00%

1.66 Providing and fixing Motive pieces all coloures for glazed tiles.

1.66.1 Size 200 x 200mm Each 132.00 132.00 0.00% 132.00 0.00%
1.66.2 Size 200 x 300mm Each 164.00 164.00 0.00% 164.00 0.00%

1.67 Providing and fixing 1st quality MAT finished ceremic tile size
300x300mm confirming to IS : 13755 and IS : 15622 colour such
as white, grey, ivory, fume red brown, light green, light blue and
other light shades in floors, steps, pillars etc. laid on a bed of
neat cement slurry finished with flush pointing in the white
cement mixed with pigment to match the shade of the tile
complete (including the cost of cement mortar bed 1:4).

P.Sqm 1120.00 753.00 48.74% 790.00 4.91%

1.67.3 Add extra over item No 1.67.1 and 1.67.2 for using 400x400mm P.Sqm 84.00 84.00 0.00% 84.00 0.00%
size MAT finished tiles in place of 300x300mm size

1.67.4 Add extra over 1.67.1 and 1.67.2 for using coloured dark shade P.Sqm 84.00 84.00 0.00% 84.00 0.00%
tiles instead of White / Ivory / Light Grey/ Light Green/ Sky Blue/
Light Brown and other light shade coloures.

1.68 Extra for using Marble printed / Granite shade or dark Sqm 10% 10% 10.00% 10%
shade tiles instead of white, grey, ivory, fume red brown,
light green, light blue and other light shades in glazed tiles
and MAT finished tiles.

1.69 Extra for using size above 200x300mm in glazed tiles and for Sqm 10% 10% 10.00% 10%
using 400mm x 400mm MAT finished tiles in place of 300mm x
300mm size.

1.70 Filling of sunk portion of roof with earthen pots of required height
including filling voids with 1:3:6 light concrete, using brick bats
complete levelling and dressing the surface by 50mm thick
cement concrete 1:2:4 as per specification. Cum 1538.00 1538.00 0.00% 1,538.00 0.00%

1.71 P & F C.P. Health Faucet with 1Mtr. Long Tube & Hook of
approved make and heavy as per direction of Enginner-in-
Charge Each 653.00 653.00 0.00% 653.00 0.00%

1.72 P & F C.P. brass Urinal Spreader for Large Urinal of heavy duty
of approved make as per direction of Enginner-in-Charge
Each 642.00 642.00 0.00% 642.00 0.00%

1.73 Removing & Re fixing of P.V.C. Cistern fittings (Syphon, Ball


cock & Handle Set) complete as per direction of Enginner-in-
Charge Each 414.00 414.00 0.00% 414.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER S-1
Chapter Description
Code No. Proposed % Above
Analysis As per BSR Variation on
Unit Rate for with BSR
Rate 2018 BSR 2018
BSR 2019 2018

1.74 Providing & Fixing Premium Quality white glazed vitreous china
Sanitary Wares (IS:2556 Mark) of approved make as per
direction of Engineer-in-charge including cutting and making
good the wall and floor.

1.74.1 W.C. orissa pan with 100 mm vitreous china P or S trap Each 2786.00 2786.00 0.00% 2,786.00 0.00%
1.74.2 Universal (anglo-Indian type) with P or S trap Each 5805.00 5805.00 0.00% 5,805.00 0.00%
1.74.3 Wall Mounting European type W.C. Each 8247.00 8247.00 0.00% 8,247.00 0.00%
1.74.4 Double Syphonic European W.C. with mounted W.V.C. flushing
cistern of 10 litre capacity complete with all necessary internal
fittings with Hydraulic seat cover. Each 16217.00 16217.00 0.00% 16,217.00 0.00%

1.75 Providing & Fixing premium qulaity WVC Urinal with PVC waste
pipe, dome couplings, concealed iron brackets or screws etc.
complete.
1.75.1 Flat Back (small) size 440x265x315 mm. Each 2381.00 2381.00 0.00% 2,381.00 0.00%
1.75.2 Flat Back (large) or half stall size 590x375x390 mm. Each 5678.00 5678.00 0.00% 5,678.00 0.00%

1.76 Providing & Fixing premium qulaity W.V.C. Urinal Partition plate
of size 630x315 mm Each 2396.00 2396.00 0.00% 2,396.00 0.00%

1.77 Providing & Fixing premium qulaity WVC Wash basin with C.I.
brackets duly painted & 32 mm C.P. brass waste coupling of
approved make with PVC waste pipe complete
1.77.1 Size 550 mm x 400 mm Each 2122.00 2122.00 0.00% 2,122.00 0.00%
1.77.2 Size 550 mm x 400 mm dia for counter top. Each 3065.00 3065.00 0.00% 3,065.00 0.00%

1.78 P & F Premiumquality water closet Seat Covers with brass


hinges complete Solid PVC (ISI marked) grade-I White for EWC.
Each 649.00 649.00 0.00% 649.00 0.00%

1.79 P & F Premium quality Low level Flushing Cistern of 10 litres


capacity (IS:2556 mark) of approved make as per Engineer-in-
charge with complete fittings C.I. brackets duly painted, brass
ball cock with ball, (IS:1703 mark) complete including cutting and
making good the wall :
Each 1657.00 1657.00 0.00% 1,657.00 0.00%

1.80 P&F Looking Mirror 5mm thick of approved make with


ornamental frame size 50x12 with 6mm Ply Board on Back Side
Complete as per approved sample Sqm 2313.00 2313.00 0.00% 2,313.00 0.00%

1.81 Supply of Hydraulic Seat Cover for Europeon WC of superior


quality approved make in white Colour Each 3688.00 3688.00 0.00% 3,688.00 0.00%

1.82 Providing & Fixing chair for wall hung W.C. Each 1458.00 1458.00 0.00% 1,458.00 0.00%

1.83 Providing & Fixing Concealed cistern with Floor mounting frame
and flush plate of superior quality and approved sample by
Engineer-in-charge. Each 7560.00 7560.00 0.00% 7,560.00 0.00%

1.84 Providing and fixing new spindle for Bib cock/pillar cock for
repairing purpose to solve leakage and proper functioning of tap.
Each 104.00 104.00 0.00% 104.00 0.00%

1.85 Providing & Fixing premium quality Toilet corner Glass Shelf size
225x225mm with C.P. brass brackets & guard rail edges
rounded of SS frame Each 1420.00 1420.00 0.00% 1,420.00 0.00%

1.86 Providing & Fixing premium quality waste coupling 32mm


half thread as per approved by Engineer in Charge. Each 472.00 472.00 0.00% 472.00 0.00%

1.87 Providing & Fixing Premium quality Bottle trap internal portion
32mm, size 250mm long wall connection pipe & wall flange as
per approved by Engineer in Charge. Each 1454.00 1454.00 0.00% 1,454.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-17
ADDITIONAL MISCELLANEOUS ITEMS
%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9

17.1 Supply and installation of Multi Rib Proofing/cladding Sheet


Manufacture out of 0.50mm TCT (Total Coated Thickness) high
tensile Zinc aluminum alloy coated galvaiumeseel (as per 150gsm
zinc aluminum coated 550Mpa tuekd strength) confirming to IS:
1397/astm A-792 sheet to have wide pens 30mm high NB at 250
centre and centre width of 1020mm shets be casted with regular
modified plyster system on a continuous with line on centre for face
and with a polyster coating respectively sheet shall have
proportionality with siphoned plate at made at to prevent leakage
sheet shall be fixed by more of sell drilling lift tapping hot dip zinc
coated hox head fasterner of size 12x14x55mm long. The sheet shall
be supplied in cost one length and foe a minimum up to 12mts with all
scaffolding. Sqm 626.00 626.00 0.00% 626.00 0.00%
17.1.1 Add extra for 0.60mm TCT (Total Coated Thickness) high tensile
Zinc aluminum alloy coated galvaiumeseel sheet in place of
0.50mm thick
17.1.2 Add extra for 0.80mm TCT (Total Coated Thickness) high tensile
Zinc aluminum alloy coated galvaiumeseel sheet in place of
0.50mm thick

17.2 Supply and Installation of ROOF – PREFABRICATED INSULATED


PPGL FACE PANEL:
Roof: Insulated sandwich panels for roof of total thickness mentioned
below exclusive of crest height of top corrugation. Panel shall be
made of 0.50mm (+/-0.04mm) thick pre coated metal sheet on both
sides of rigid polyurethane insulation. The top external facing metal
sheet shall have corrugated shape with crest. The trapezoidal shape
crowns/crest height should not be less than 30mm. The pre-coated
metal sheet shall be PPGL (Pre Painted Galvalume Sheet with AZ
coating) sheet having SDP (Super Durable Polyester) colour coat of
18 micron (min). The bottom sheet must have tongue and groove type
flange (U shape) of 8mm x 8mm on groove side and 8mm x 12mm on
tongue side. Flange must be on lengthwise sides for joining adjacent
panels. Panel's bottom side PPGL sheet must also be pre-
strengthened by full lengthwise stiffening with semi-circular beading of
12mm width & 3 to 4mm depth at 240 (+/-5) mm pitch. The top
corrugated sheet must have at-least one open crown/crest for
overlapping adjacent panel widthwise. Similarly the top corrugated
sheet must have suitable open extension of min 6” on bottom
widthwise side of panel for overlapping further panels joined
lengthwise also. The insulation core shall be self-extinguishing DIN
4102,Class B3 fire retardant class rigid PUR with thermal conductivity
of 0.025 W/mK and with initial density of 40kg/m3 (+/-2kg) suitable for
Thickness 65mm (+/- 2mm) Sqm. 2292.00 2292.00 0.00% 2,292.00 0.00%
Thickness 105mm (+/- 2mm) Sqm. 2593.00 2593.00 0.00% 2,593.00 0.00%

17.3 Supply and Installation of WALL – PREFABRICATED INSULATED


PPGL PANEL:
Walls: Insulated sandwich panels for wall of total thickness mentioned
below. Panel shall have 0.50mm (+/-0.04mm) thick pre coated metal
sheet on both sides of rigid PUR insulation. The pre-coated metal
sheet shall be PPGL (Pre Painted Galvalume Sheet with AZ coating)
sheet having SDP (Super Durable Polyester) colour coat of 18 micron
(min). The panels shall be vertically joined together with adjacent
panel by tongue and groove joints. For joining, wall panel's metal
sheet facings must have lengthwise flange (U shape) of 8mm x 8mm
on groove side and 8mmx12mm on tongue side of panel. The pre-
coated metal sheet (PPGL) must also be pre-strengthened by full
lengthwise stiffening with semi-circular beading of 12mm width & 3 to
4mm depth at 240 (+/-5) mm pitch. Panels may have optional
provision for inbuilt electrical conduit running lengthwise atvertical
center of specified panels. The insulation core shall be self-
extinguishing DIN 4102,Class B3 fire retardant class rigid PUR with
thermal conductivity of 0.025 W/mK and with density of 40kg/m3 (+/-
2kg) suitable for temperature range of -30 degree C to +80 degree C.
The panel must be made using glue-free high pressure pressing self-
bonding method. PPGL sheet on both sides of panel shall have a
min15 micron protective plastic guard film to avoid scratches during
transportation.
T.A. TO S.E. AAO Superintending Engineer
%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
Thickness 55mm (+/- 2mm) Sqm. 2109.00 2109.00 0.00% 2,109.00 0.00%
Thickness 65mm (+/- 2mm) Sqm. 2292.00 2292.00 0.00% 2,292.00 0.00%

17.4 Supply and Installation of WALL – PREFABRICATED INSULATED


CEMENT FACE PANEL:
Factory-readymade structural reinforced insulated wall panel of
thickness mentioned below. Panel shall be made of 6mm (+/-0.6mm)
thick asbestos-free fiber cement sheet/ Cement bonded particle board
as per IS:14276:1995 on both sides of rigid PUR insulation. The wall
panel shall be vertically joined together with adjacent panel by biscuit
joints lengthwise with suitable construction adhesive. Joining member
(biscuit) shall be made of approx 12mm thick cement sheet /Cement
bonded particle board as per IS:14276:1995. Panels may have
optional provision for inbuilt electrical conduit running lengthwise at
vertical center of specified panels. Both vertical lengthwise sides of
panels must have full length MS tubes of min 1.0mm thickness for
better structural strength.The final panel surface must be free from
undulations. The Insulating core shall be self-extinguishing DIN
4102,Class B3 fire retardant class rigid PUR with thermal conductivity
of 0.025 W/mK and with density of 40kg/m3 (+/-2kg) suitable for
temperature range of -30 degree C to +80 degree C. The panel must
be made using glue-free high pressure hot pressing self-bonding
method and shall be free from major surface undulations.

Thickness 65mm (+/- 2mm) Sqm. 2292.00 2292.00 0.00% 2,292.00 0.00%
Thickness 75mm (+/- 2mm) Sqm. 2410.00 2410.00 0.00% 2,410.00 0.00%

17.5 Supply and Installation of WALL – PREFABRICATED INSULATED


LAMINATED FACE PANEL:
Factory-readymade interior wall panel of thickness mentioned below.
The panels shall have suitable provision for joining adjacent panels.
Interior panels may have optional provision for inbuilt electrical conduit
running lengthwise at vertical center of specified panels. The
insulation core shall be self-extinguishing DIN 4102,Class B3 fire
retardant class rigid PUR with thermal conductivity of 0.025 W/mK and
with density of 40kg/m3 (+/-2kg) suitable for temperature range of -30
degree C to +80 degree C. The panel must be made using glue-free
high pressure hot pressing self-bonding method and shall be free from
major surface undulations. both sides of panel shall have a min15
micron protective plastic guard film to avoid scratches during
transportation.
1. Panel shall be made of min 4mm (+/- 0.5mm) thick laminated wood
based medium density fiber board sheet on both sides of rigid PUR
insulation.

Thickness 65mm (+/- 2mm) Sqm. 2410.00 2410.00 0.00% 2,410.00 0.00%
Thickness 75mm (+/- 2mm) Sqm. 2528.00 2528.00 0.00% 2,528.00 0.00%

17.6 Supply and Installation of SMALL ROOM (TOILET & GUARD ROOM)
– PREFABRICATED INSULATED PPGL FACE PANEL:
Insulated closed lip panels (for door, wall and roof) of thickness
mentioned below. Panel shall have 0.50mm (+/-0.04mm) thick pre-
coated metal sheet on both sides of rigid PUR insulation. The pre-
coated metal sheet shall be PPGL (Pre Painted Galvalume Sheet with
AZ coating) sheet having SDP (Super Durable Polyester) colour coat
of 18 micron(min). The Pre coated metal sheet on both sides must be
pre-strengthened by full lengthwise stiffening with semi-circular
beading of 12mm wide & 3mm depth at 240 (+/-5) mm pitch. Panels
shall have closed lengthwise sides made by right angle flange on both
side of Pre coated metal sheets, free from cap type covers. The top
and bottom part on widthwise sides of panels must have full width MS
Square tube insert of (min 25mm x 1.0mm) for better screw retention
and strength. The insulation core shall be self-extinguishing DIN
4102,Class B3 fire retardant class rigid PUR with thermal conductivity
of 0.025 W/mK and with density of 40kg/m3 (+/-2kg) suitable for
temperature range of -30 degree C to +80 degree C. The panel must
be made using glue-free high pressure hot pressing self-bonding
method free from major undulations. PPGL sheet on both sides of
panel shall have a min15 micron protective plastic guard film to avoid
scratches during transportation.

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
Thickness of 32mm (+/-2mm) Sqm. 2055.00 2055.00 0.00% 2,055.00 0.00%
Thickness of 50mm (+/-2mm) Sqm. 2206.00 2206.00 0.00% 2,206.00 0.00%

17.7 AccessoriesSupply and Installation of (Labour rate included in main


item)
Bottom and Top U track :
U-track for mounting panels with floor. The channel shall be made
from minimum 1.15 mm thick PPGL sheet with flange height of
minimum 35 mm and width as per thickness of panel used. RMT 200.00 200.00 0.00% 200.00 0.00%

17.7.1 Flashings (inner and outer):


Corner angle flashings of equal shape for covering various corners
and open sides of panels. Flashings shall be made from 0.5mm thick
pre-coated PPGL sheet in following sizes:
50mm x 50mm RMT 150.00 150.00 0.00% 150.00 0.00%
100mm x 100mm 200.00 200.00

17.7.2 Roof Ridge Cap:


Ridge flashing for roof panels shall be made from 0.5mm thick pre-
coated PPGL sheet of
200mm x200 mm. RMT 200.00 200.00 0.00% 200.00 0.00%

17.7.3 Roof Front Corrugated Cap:


Front side flashing for roof panels (corrugated trapazodial shape) shall
be made from 0.5mm thick pre-coated PPGL sheet. RMT 200.00 200.00 0.00% 200.00 0.00%

17.7.4 Roof End Cap:


End cap for closing ends of roof panels made from 0.5mm thick PPGL
sheet. RMT 150.00 150.00 0.00% 150.00 0.00%

17.7.5 Frame for Door/Window:


Frame shall be made out of min 1.15mm thick press steel sheet. RMT 200.00 200.00 0.00% 200.00 0.00%

17.7.6 Panel End Caps:


U or L shape caps suitable for thickness of panel used, with 30mm
flange. It should be made frem 0.5mm Pre coated PPGL sheet.
RMT 100.00 100.00 0.00% 100.00 0.00%

17.7.7 Self Drilling Screws:


5” Each 12.00 12.00 0.00% 12.00 0.00%
3.5” Each 9.00 9.00 0.00% 9.00 0.00%
1” Each 5.00 5.00 0.00% 5.00 0.00%

17.7.8 Adhesives KG. 180.00 180.00 0.00% 180.00 0.00%

17.8 Supply and fixing of Cement Bonded Particle Board (as per IS 14276)
false ceiling using 6MM thick Cement Board with galvanized and pre
painted steel T section of size 24mm x 27mm x 0.4mm for main T
duty pre punched to accept cross T section of size 24mm x
25mm x 0.4mm duly punched at both ends for insertion into main T.
The grid size will be 610mm x 610mm. The frame work (grid) is
suspended to the roof by using G.I flat of 0.60mm or 14-gauge
G.I wire with necessary fixers to the roof and frame work. Cement
Board panel is laded on the grid. The cost inclusive of necessary
hardware, labor, one coat of primer (Both side) and two coats of
smooth finish on visible side.
Sqm 594.00 594.00 0.00% 594.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
17.9 Supply and fixing of Cement Bonded Particle Board (as per 14276)
wall paneling using 10 MM thick Cement Board with frame work made
of GI stud section of size 48mm x 35mm x 0.55mm thick placed at
every 610 mm C/C intervals vertically and at 1200mm internals
horizontally fixed to the wall by means of self expansion screws and
caps. Cement Board panel is to be fixed to frame by means of self
taping screws placed at every 300 mm intervals leaving 3mm gap
between two panels. The cost inclusive of one coat of Altek primer
and two coats of Altek smooth finish and cost & conveyance of all
materials, labor charges etc. complete as per the direction of Engineer
in charge.

Sqm 1526.00 1526.00 0.00% 1,526.00 0.00%

17.10 Supply and fixing of Cement Bonded Particle Board (as per 14276)
double skin partition using with 10 MM thick Cement Board made out
of G.I. track section of size 50mmx 35mm x 0.55 mm for fixing to the
roof and floor and stud section of size 48mm x 35mm x 0.55mm
placed in track section vertically at 610mm intervals and at 1200mm
intervals horizontally fixed to the wall by means of self expansion
screws and caps to the wall and roof. Cement Board panel is to be
fixed both sides of frame work by using self taping screws fixed at
every 300mm intervals to the frame work leaving 3 mm gap between
two panels. The cost inclusive with one coat of Alltek primer and two
coats of Alltek smooth finish and cost and conveyance of all materials
to site, labor charges etc., complete as per the direction of Engineer in
charge.

Sqm 2208.00 2208.00 0.00% 2,208.00 0.00%

17.11 Supply and fixing of Factory Laminated Cement Bonded Particle


Board double skin partition using with 10MM Factory Laminated
Cement Bonded Board made out of G.I track section of size 50 mm x
35mm x 0.55mm for fixing to the roof and floor and stud section of
size 48mm x 35mm x 0.55mm placed in track section vertically at
610mm intervals and at 1200mm internals horizontally. The frame is
fixed by means of self expansion screws and caps to the wall / roof.
Laminated Cement Bonded Particle Board is to be fixed both sides of
the frame work by using 2mm thick electro plated CR flat section
leaving 3mm gap between two panels. The cost inclusive of cost and
conveyance of all materials to sites, other materials incidentals and
labor charges as per the direction of Engineer in charges.

Sqm 3092.00 3092.00 0.00% 3,092.00 0.00%

17.12 Supply and fixing of Bath room / Toilet door shutter with 16mm
Factory Laminated Cement Bonded Particle Board BISON Lam (IS
14276) door shutter with all-round ‘U’ lipping of PPS section of size
12mm X 18mmX 12mmX0.6mm thickness with a hardware of 12mm
dia X200mm long aluminum aldrop – 2 nos2 No of 125mm long
handles and also 3 no Of IS304 grade Patee Hinges
3mmX12mmX180mm long with pole receiver of 10mm dia pole
X40mm long welded on 2mm X40mm(ss304) plates works as receiver
for RT patte hinges. The price inclusive of all material at site.

Sqm 2188.00 2188.00 0.00% 2,188.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
17.13 Solid Rectangular Block (400x200x200, 400x200x100, 400x200x150,
225x200x100)

Providing and fixing up to floor five level of cement concrete solid


blocks (M-20 Grade) of different sizes (Manufactured with fully
mechanised dry cast process with forced action mixer whose arms
revolve along the main axis and rotate about its own axis also, having
humidity sensor for moisture control of w/c ratio in concrete mix.
Manufactured with steel moulds (Milled and manufactured in CSI
diamond or CSI Nitro process for accuracy) on steel base plate of min
16 mm thick; Having Vibration and pressing action both together with
the help of mutiplesynchronised vibrators. Power of hydraulic station
should be minimum 50KW for compaction and cured in controlled
chambers having humidity control and automated air circulation
system) including hoisting and setting in position with cement mortar
1:3 (1 Cement : 3 Coarse Sand), cost of required centering, shuttering
complete.

Cum 9370.00 9370.00 0.00% 9,370.00 0.00%

17.14 Hollow Rectangular Block (400x200x200, 400x200x100)


Providing and fixing up to floor five level of cement concrete Hollow
Rectangular blocks of different sizes (Manufactured with fully
mechanised dry cast process with forced action mixer whose arms
revolve along the main axis and rotate about its own axis also, having
humidity sensor for moisture control of w/c ratio in concrete mix.
Manufactured with steel moulds (Milled and manufactured in CSI
diamond or CSI Nitro process for accuracy) on steel base plate of min
16 mm thick; Having Vibration and pressing action both together with
the help of mutiplesynchronised vibrators. Power of hydraulic station
should be minimum 50KW for compaction and cured in controlled
chambers having humidity control and automated air circulation
system) including hoisting and setting in position with cement mortar
1:3 (1 Cement : 3 Coarse Sand), cost of required centering, shuttering
complete.

Cum 6675.00 6675.00 0.00% 6,675.00 0.00%

17.15 Insulated Rectangular Block (400x200x200 mm)


Providing and fixing up to floor five level of cement concrete insulated
blocks of different sizes having a layer of polysterene as insulating
material (Manufactured with fully mechanised dry cast process with
forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy) on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
including hoisting and setting in position with cement mortar 1:3 (1
Cement : 3 Coarse Sand) including cost of required centering,
shuttering complete.
Cum 9920 9920 0.00% 9,920.00 0.00%

17.16 Interlocking Paver Blocks having 80 mm thickness in M-40 grade


concrete

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
Providing and Laying 80 mm thick cement concrete blocks of M-40
Grade (Manufactured with fully mechanised dry cast process with
forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel
moulds(Milled and manufactured in CSI diamond or CSI Nitro process
for accuracy) on steel base plate of min 16 mm thick; Having
Vibration and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
spreading 25mm thick sand underneath and filling joints with sand on
existing W.B.M.base, as per IS15658:2006 and all materials shall
conform to MoRTH Specification Clause 602.
Sqm. 1100.00 1100.00 0.00% 1,100.00 0.00%

17.17 Interlocking Paver Blocks having 100 mm thickness in M-50 grade


concrete
Providing and Laying 100 mm thick cement concrete blocks of M-50
Grade(Manufactured with fully mechanised dry cast process with
forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy) on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
spreading 25mm thick sand underneath and filling joints with sand on
existing W.B.M.base, as per IS15658:2006 and all materials shall
conform to MoRTH Specification Clause 602.

Sqm. 1289.00 1289.00 0.00% 1,289.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
17.18 Interlocking Paver Blocks having 120 mm thickness in M-50 grade
concrete
Providing and Laying 120 mm thick cement concrete blocks of M-50
Grade(Manufactured with fully mechanised dry cast process with
forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy)on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
spreading 25mm thick sand underneath and filling joints with sand on
existing W.B.M.base, as per IS15658:2006 and all materials shall
conform to MoRTH Specification Clause 602.

Sqm 1424.00 1424.00 0.00% 1,424.00 0.00%

17.19 Interlocking Paver Blocks having 100 mm thickness in M-55 grade


concrete
Providing and Laying 100 mm thick cement concrete blocks of M-55
Grade (Manufactured with fully mechanised dry cast process with
forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy)on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
spreading 25mm thick sand underneath and filling joints with sand on
existing W.B.M.base, as per IS15658:2006 and all materials shall
conform to MoRTH Specification Clause 602.

Sqm 1389 1389 0.00% 1,389.00 0.00%

17.20 Interlocking Paver Blocks having 120 mm thickness in M-55 grade


concrete
Providing and Laying 120 mm thick cement concrete blocks of M-55
Grade (Manufactured with fully mechanised dry cast process with
forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy) on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
spreading 25mm thick sand underneath and filling joints with sand on
existing W.B.M.base, as per IS15658:2006 and all materials shall
conform to MoRTH Specification Clause 602.

Sqm. 1489.00 1489.00 0.00% 1,489.00 0.00%

17.21 Kerb Stones of 1200x300x150, 1000x450x150, 1000x600x150,


600x300x150 size (M-30)

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
Providing and Laying cement concrete Kerb Stones of different sizes
in M-30 grade (Manufactured with fully mechanised dry cast process
with forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy) on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system) in
position to the required line, level and curvature jointed with cement
mortar 1:3 (1 Cement : 3 Coarse sand) including making of joints,
drainage opening wherever required.

Cum 8572.00 8572.00 0.00% 8,572.00 0.00%

17.22 Kerb Stones of 1200x300x150, 1000x400x150, 1000x600x150,


600x300x150 size (M-40)
Providing and Laying cement concrete Kerb Stones of different sizes
in M-40 grade (Manufactured with fully mechanised dry cast process
with forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy) on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system) in
position to the required line, level and curvature jointed with cement
mortar 1:3 (1 Cement : 3 Coarse sand) including making of joints,
drainage opening wherever required.

Cum 9067.00 9067.00 0.00% 9,067.00 0.00%

17.23 Cellular Concrete Block for Pitching and garden paths (600x400x80)
in M-30
Providing and fixing Cellular concrete blocks (M-30 Grade),
600x400x80 mm sizes (Manufactured with fully mechanised dry cast
process with forced action mixer whose arms revolve along the main
axis and rotate about its own axis also, having humidity sensor for
moisture control of w/c ratio in concrete mix. Manufactured with steel
moulds (Milled and manufactured in CSI diamond or CSI Nitro process
for accuracy) on steel base plate of min 16 mm thick; Having
Vibration and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
including hoisting and setting in position with cement mortar 1:3 (1
Cement : 3 Coarse Sand), cost of required centering, shuttering
complete.
Sqm. 739.00 739.00 0.00% 739.00 0.00%

17.24 Pre Cast Concrete Flooring (Slab 600x600x100, 1000x650x100)


Providing and fixing Precast concrete flooring slabs (M-30 Grade) of
different sizes(Manufactured with fully mechanised dry cast process
with forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy) on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
including hoisting and setting in position with cement mortar 1:3 (1
Cement : 3 Coarse Sand), cost of required centering, shuttering
complete and spreading 25mm thick sand underneath.

Sqm. 894.00 894.00 0.00% 894.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9

17.25 Pre Cast U/Semi circular Drains (Outer size 600x400 mm, wall
thickness 80 mm)
Providing and fixing Precast concreteUdrains (M-30 Grade) of
different sizes (Manufactured with fully mechanised dry cast process
with forced action mixer whose arms revolve along the main axis and
rotate about its own axis also, having humidity sensor for moisture
control of w/c ratio in concrete mix. Manufactured with Steel moulds
(Milled and manufactured in CSI diamond or CSI Nitro process for
accuracy) on steel base plate of min 16 mm thick; Having Vibration
and pressing action both together with the help of
mutiplesynchronised vibrators. Power of hydraulic station should be
minimum 50KW for compaction and cured in controlled chambers
having humidity control and automated air circulation system)
including hoisting and setting in position with cement mortar 1:3 (1
Cement : 3 Coarse Sand), cost of required centering, shuttering
complete and spreading 25mm thick sand underneath.

R.M. 417.00 417.00 0.00% 417.00 0.00%

17.26 Dry Cleaning of sofa sets using shampooing machine with all
materials & drying it do the level using machinery at designated place
by engineer-in-charge one seat of sofa (payment for multi seater sofa
will be done as the number of seats of that sofa.)
17.26.1 Single Seater Sofa Each 140.00 140.00 0.00% 140.00 0.00%
17.26.2 Two Seater Sofa Each 211.00 211.00 0.00% 211.00 0.00%
17.26.3 Three Seater Sofa Each 302.00 302.00 0.00% 302.00 0.00%

17.27 Dry Cleaning of Woolen Carpet of any size using shampooing


machine with all material & drying it using machinery at the designated
place as told by engineer in charge. Sqm 93.00 93.00 0.00% 93.00 0.00%

17.28 Complete replacement of Tapestry cloth of Sofa set costing @ Rs.


300/- per Mtr. Approx of superior quality including stitching charges
(As approved by the Engineer in Charge) as per existing
pattern/design.
17.28.1 Single seater sofa Each 1317.00 1317.00 0.00% 1,317.00 0.00%
17.28.2 Three seater sofa Each 3583.00 3583.00 0.00% 3,583.00 0.00%

17.29 Complete replacement of damaged foam of Sofa set and using


100mm thick Joint less P.U. foam in seat of 32 density feather foam of
superior quality of approved make (as approved by the Engineer-in-
charge) pasted with Adhesive (Rubber Solution) of superior quality.

17.29.1 Single seater sofa Each 685.00 685.00 0.00% 685.00 0.00%
17.29.2 Three seater sofa Each 1921.00 1921.00 0.00% 1,921.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
17.30 Complete replacement of damaged foam of Sofa set and using 50mm
thick joint less P.U. foam of 32 density feather foam superior quality of
approved make (as approved by the Engineer-in-charge) in back duly
pasted with Adhesive (Rubber Solution) of superior quality.

17.30.1 Single seater sofa Each 412.00 412.00 0.00% 412.00 0.00%
17.30.2 Three seater sofa Each 1172.00 1172.00 0.00% 1,172.00 0.00%

17.31 Complete replacement of damaged foam of Sofa set and using 25mm
thick joint less P.U. foam of 32 density feather foam superior quality
of approved make (as approved by the Engineer-in-charge) in Hand
rest, in seat and back and design work as required of superior quality.

17.31.1 Single seater sofa Each 779.00 779.00 0.00% 779.00 0.00%
17.31.2 Three seater sofa Each 1652.00 1652.00 0.00% 1,652.00 0.00%

17.32 Repair of wooden frame of Sofa set using Tat, Nail, Screw, Bolt (if
required) and re-assembling sofa set (Cost Including all Consumble
Item) complete in all respect as per direction of the Engineer-in-charge

17.32.1 Single seater sofa Each 625.00 625.00 0.00% 625.00 0.00%
17.32.2 Three seater sofa Each 1903.00 1903.00 0.00% 1,903.00 0.00%

17.33 Repair using replacement of Jata, Dori, wooden batten & legs
everything in all respect as per approval of Engineer-in-charge.
17.33.1 Single seater sofa Each 456.00 456.00 0.00% 456.00 0.00%
17.33.2 Three seater sofa Each 686.00 686.00 0.00% 686.00 0.00%

17.34 Providing and Fixing machine made Synthetic Carpet having total
Carpet weight 850 gm Psqm. and 5mm thickness superior quality
complete in all respect as per direction of Engineer-in-charge. Each 440.00 440.00 0.00% 440.00 0.00%

17.35 Providing and Fixing Chiken wire mesh at the joint of masonry
members/ R.C.C. Members with Nails complete in all respect. Sqm 71.00 71.00 0.00% 71.00 0.00%
17.36 Covered & water proof Dome type mehfil pandal with iron frame, white
wall curtains with ply and false ceiling etc. complete in all respects
with provisions of few gates and pressboxes inside the pandal as per
requirement. Approx height 20-25 feet with new Cloth covered.
Sqm 260.00 260.00 0.00% 260.00 0.00%
17.37 Preparing VIP Room 15'×30' Water Proof Ceiling white Curtain on wall
(New). Carpet flooring. With Sofas, Center Tables etc with Chemical
Toilet complete having Europen W.C., Wash Basin,PVC water tank,
Water Connection, Towel rail, soap dish etc complete in all respect.
No 60000 60000 0.00% 60,000.00 0.00%
17.37.1 Chemical Toilet complete having Europen E.C., Wash Basin,PVC
water tank, Water Connection, Towel rail, soap dish etc complete in all
respect. No 15000 15000 0.00% 15,000.00 0.00%
17.38 Box Gate (New) 16'×14' No 7500 7500 0.00% 7,500.00 0.00%
17.39 P/F side wall (New Cloths) Sqm 40 40 0.00% 40.00 0.00%
17.40 P/F Barricading in Stadium Area Two Horizantel line with Ballies
Vertical Ballies 2.5 Mtr. c/c Complet with clothing etc. (New) Sqm 131 131 0.00% 131.00 0.00%
17.41 Hire charges for Chair Banquet No 75 75 0.00% 75.00 0.00%
17.42 Hire charges for flower decoration original & Duplicate stage, entry
gate etc. complete as directed by engineer in charge No 26132 26132 0.00% 26,132.00 0.00%
17.43 Hire charges for Jhalar (New) Rmt 27 27 0.00% 27.00 0.00%
17.44 Hire charges for Non woven synthtic carpet (Red/Green) (New) Sqm 27 27 0.00% 27.00 0.00%
17.45 Hire charges for Wooden stage height 120 to 150cm, with steps
made of 50mm dia iron pipe frame with adjustable height system and
having smooth top wooden board complete. Sqm 187 187 0.00% 187.00 0.00%
17.46 Hire charges for V.V.I.P. sofa set good quality No 2115 2115 0.00% 2,115.00 0.00%
17.47 Hire charges for folded type two seater sofa set (cum bed) with good
quality white cloth cover Each 254 254 0.00% 254.00 0.00%
17.48 Hire charges for White cotton cloth cover for padded chair including
ribbon Each 12 12 0.00% 12.00 0.00%
17.49 Hire charges for PVC Chair Each 7 7 0.00% 7.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


%
Variation
Chapter Rate as Variation Adopted from
As per
Code No. Description Unit per over Rate for proposed
BSR2018
analysis BSR2018 BSR2019 BSR 2018
& BSR
2016
1 2 3 6 5 7 9
17.50 Hire charges for Wooden Table 6'×3' (Babool) Each 30 30 0.00% 30.00 0.00%
17.51 Hire charges for White cotton chader (Sheet) (Washed) Each 15 15 0.00% 15.00 0.00%
17.52 Hire charges for Centre Table sunmica Top 2'×4' Each 22 22 0.00% 22.00 0.00%
17.53 Hire charges for Pipe Pandal ht upto 12 to 18 ft Sqm 30 30 0.00% 30.00 0.00%
17.54 Drinking water arrangement :
17.54.1 Drinking water bottle 200 ML Bislery/Aquafina No 12 12 0.00% 12.00 0.00%
17.54.2 Drinking water bottle 1 Ltr Bislery/Aquafina No 19 19 0.00% 19.00 0.00%
17.55 Buke + Guldaste No 249 249 0.00% 249.00 0.00%
17.56 Hire charges for Providing fire extinguishers No 622 622 0.00% 622.00 0.00%
17.57 Providing & fixing flax work including Lettering, printing etc. complete

17.58 With frame work Sqm 373 373 0.00% 373.00 0.00%
17.59 Without frame work only flax printing Sqm 187 187 0.00% 187.00 0.00%
17.60 Hire charges of Mirror 18"×36" with frame No 1244 1244 0.00% 1,244.00 0.00%
17.61 50mm Galvanised Iron Pipe 6 mtr Long with Flag No 100 100 0.00% 100.00 0.00%
17.62 Hire charges for A.C Tower Ton 2738 2738 0.00% 2,738.00 0.00%
17.63 Agronet on Dome Sqm 6 6 0.00% 6.00 0.00%
17.64 Qwyksa dh 3 ekykvksa dh cUnjokj dk dk;ZA ¼rktk Rmt 448 448 0.00% 448.00 0.00%
17.65 Qwy½
dV ¶ykoj cqdksa ls Msdksjs'ku dk;ZA ¼rktk Qwy½
17.65.1 10 LVhd okys No 311 311 0.00% 311.00 0.00%
17.65.2 6 LVhd okys No 124 124 0.00% 124.00 0.00%
17.65.3 4 LVhd okys No 62 62 0.00% 62.00 0.00%
17.65.4 xsV@nhokjksa ij dV ¶ykoj dh csyksa dk dk;Z ¼rktk Rmt 373 373 0.00% 373.00 0.00%
17.65.5 Qwy½
yM+h ekyk dk dk;Z ¼rktk Qwy½ Rmt 75 75 0.00% 75.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
ALLUMINIUM & PVC WORK
CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018

16.1 Providing and fixing anodized aluminum work (Anodizing to be got


done from approved Anodizer) for doors ,windows, ventilators and
partition with extruded built up standard tubular and other sections of
approved make conforming to IS :733 and IS :1285 anodised
transparent 81 dyed to required shade according to IS : 1868.
(Minimum anodic coating of grade AC 15), fixed with rawl plugs and
screws or with fixing clips ,or with expansion hold fasteners including
necessary filling up of gap. at junctions , at top ,bottom and sides with
required PVC/neoprene felt etc. Aluminium section shall be smooth
,rust free, straight ,mitered and jointed mechanically wherever
required including cleat angle Aluminium snap beading for glazing
/paneling , C.P. brass/ stainless steel screws Al. Tower bolt & Al.
handle & Al. Aldrop etc.,all complete as per architectural drawings and
the directions of Engineer- in – charge .(Glazing and paneling to be
paid for separately).

16.1.1 For fixed portion Kg. 526.00 397.00 32.49% 416.00 4.79%
16.1.2 Powder coating aluminum ( minimum thickness of powder coating 50
micron) Kg. 554.00 422.00 31.28% 443.00 4.98%
16.1.3 Polyester Powder coating aluminum ( minimum thickness of powder
coating 50 micron) Kg. 565.00 437.00 29.29% 458.00 4.81%

16.1.1.2 For shutters of openable doors ,windows & ventilators including


providing & fixing hinges / rollers etc. and making provision for fixing
of fittings wherever required (lockes shall be paid for separately).
Kg 562.00 409.00 37.41% 429.00 4.89%
16.1.1.3 Powder coating aluminum ( minimum thickness of powder
coating 50 micron) Kg. 586.00 435.00 34.71% 456.00 4.83%
16.1.1.4 Polyester Powder coating aluminum ( minimum thickness of
powder coating 50 micron) Kg. 598.00 450.00 32.89% 472.00 4.89%

16.1.3 For shutters of sliding windows and making provision for fixing of
fittings wherever required (lockes shall be paid for separately). Kg 425.00 425.00 0.00% 425.00 0.00%
Note : Add 10% extra over item No. 16.1 for work done in curved / circular
shape.

16.2 Providing and fixing 12 mm thick prelaminated three layer medium


density (exterior grade ) particle board Grade I, Type II conforming to
IS : 12823 bonded formaldehyde synthetic resin ,of approved brand
and manufacture in paneling fixed in aluminium doors ,windows
shutters and partition frames with C.P. brass / stainless steel screws
etc. complete as per architectural drawings and direction of engineer-
in-charge.

16.2.1 Pre-laminated particle board with decorative lamination on one


side and balancing lamination on other side. Sqm 1404.00 1246.00 12.68% 1,308.00 4.98%

16.2.2 Prelaminated particle board with decorative lamination on both sides.


Sqm 1400.00 1400.00 0.00% 1,400.00 0.00%

16.3 Providing and fixing glazing in aluminium door, window ,ventilator


shutters and partitions etc. with PVS / neoprene gasket etc. complete
as per the architectural drawings and the directions of engineer-in-
charge.(Cost of aluminium snap beading shall be paid in basic item.)

16.3.1 With glass panes of 4.0 mm thickness ( weight not less than 10.0
kg/sqm) as per IS : 2835. Sqm 1019.00 949.00 7.38% 996.00 4.95%

16.3.2 With glass panes of 5.0 mm thickness (weight not less than
13.75kg/sqm) as per IS : 2835. Sqm 925.00 925.00 0.00% 925.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.3.3 With tinted glass panes of 5.0mm thickness (weight not less than
13.75kg/sqm). Sqm. 1126.00 1126.00 0.00% 1,126.00 0.00%

16.4 Providing & fixing double action hydraulic floor spring of approved brand and
manufacture to aluminum door shutter including cost of cutting floors as
required, embedding in floors and cover plate etc. complete as per direction
of Engineer In-charge.

16.4.1 Confirming to IS 6315 such as Sandhu/Amar or equivalent make.


Each 3291.00 3291.00 0.00% 3,291.00 0.00%

16.4.2 Approved brand like Hardwin Euro Superior quality or equivalent for
extra heavy doors. Each 2657.00 2657.00 0.00% 2,657.00 0.00%

16.5 Providing and fixing expanded grill made of anodized aluminum as per
design and drawing having members section of size 7.5mm x 6.0mm
and opening of size 102mm x 99mm to aluminum window/vent with
required screws, Y and H aluminium sec (as per drawing) at the ends
and middle joints respectively complete in all respect as per direction
of engineer in charge.
Sqm. 2657.00 2657.00 0.00% 2,657.00 0.00%

16.5.1 S&f fixed wire gauge of stainless steel of 14 mesh x 24 gauge to the
aluminium window by Aluminium beading 20x3mm with suitable
screws at not exceeding 150mm distance at all heights with all lead
and lift with scafolding. Sqm 800.00 800.00 0.00% 800.00 0.00%

16.6 Providing and fixing brass lock without handle for Aluminium door, of
approved quality, make & design as directed by Engineer In-charge.
Each 452.00 452.00 0.00% 452.00 0.00%

16.7 Providing and fixing friction stay for aluminum windows, Ebco or Each
equivalent , complete in all respect size 10”. Pair 459.00 459.00 0.00% 459.00 0.00%

16.8 Providing and fixing sun control film, 25 micron thick of approved
colour and shade , complete in all respect , at all level , as directed by
engineer- in -charge. Sqm 434.00 434.00 0.00% 434.00 0.00%

16.9 Providing and fixing powder coated aluminium 1.5" dia drapery rod
with finials , rings end cap cording set and bracket etc. complete of
approved make (Arolux, Mac, vista or eqvi.) and approved design as
per specification and direction of engineer- in–charge

(a) For first 0.90 meter length of rod . Rmt 935.00 935.00 0.00% 935.00 0.00%

(b) For subsequent length of rod ( beyond 0.90 m length covered in item
1(a) above). Rmt 645.00 645.00 0.00% 645.00 0.00%

c) Deduct if cording set not used from Item 6.9 (a). Rmt 150.00 150.00 0.00% 150.00 0.00%

16.10 Providing and fixing vertical blinds , made out of non woven polyester
fabric 85 to 90 mm wide of approved shade & design with power
coated aluminum channel minimum 1”x1” system including cording set
etc. complete as per specification & direction of engineer- in –charge
Sqm 2415.00 2415.00 0.00% 2,415.00 0.00%

16.11 Providing and fixing Horizontal blinds made out of 25 mm wide


aluminum powder coated strips with powder coated channel etc.
complete (Aerolux, vista, Mac or equivalent) as per direction or
engineer- in –charge Sqm 2412.00 2412.00 0.00% 2,412.00 0.00%
16.12 Polyester powder coating and electro coloring in various color and
shade approved by Engineer In charge (For item No. 16.1.1)
(a) Section 101.60 x 44.45mm Rmt. 97.00 97.00 0.00% 97.00 0.00%

(b) Section 63.00 x 38.00mm Rmt. 81.00 81.00 0.00% 81.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.13 Polyester powder coating and electro coloring in various color and
shade approved by Engineer In charge. (For item No. 16.1.2 &
16.1.3) Sqm 504.00 504.00 0.00% 504.00 0.00%
PLASTIC DOOR FRAMES
16.14 Providing and fixing of P.V.C. door frame made from extruded PVC
Confirming to IS : 10151-1982 section having multi chamber cross
section with a maximum wall thickness of 2.8mm ± 0.3 mm duly
reinforced with steel tie rod at bottom, and weather seals complete :

16.14.1 P.V.C. door frame section (68 x 60mm) RMtr. 584.00 584.00 0.00% 584.00 0.00%

16.14.2 P.V.C. door frame section (53 x 60mm) RMtr. 480.00 480.00 0.00% 480.00 0.00%

16.14.3 P.V.C. door frame section (40 x 58mm) RMtr. 371.00 371.00 0.00% 371.00 0.00%

16.14.4 P.V.C. door frame section (40 x 48mm) RMtr. 201.00 201.00 0.00% 201.00 0.00%
PLASTIC DOOR SHUTTER :
16.15 Providing and fixing of Plastic door shutter infill made from multi
chamber hollow P.V.C. sections having cross section of 200 x 20 x
1mm joined with one another by a dove tail locking system and
shutter frame made from extruded P.V.C. section in overall cross
section of 59 x 24mm and door fittings such as hinges, aldrop,
handles, stopper, locking bolt, will be provided.
Sqm 2406.00 2406.00 0.00% 2,406.00 0.00%
16.16 Providing and fixing of Plastic shutter Infill made from extruded multi
chamber hollow P.V.C. section having cross section of 200 x 20 x
1mm and shutter frame made from extrude P.V.C. section in the
configuration of double walled ‘C’ section having an overall cross
section of 40 x 37 mm and door fittings such as hinges, aldrop.
Handles, stopper, locking bolt will be provided.
Sqm. 2677.00 2677.00 0.00% 2,677.00 0.00%
16.17 Providing and fixing of Plastic shutter Infill made from multi chamber
hollow P.V.C. sections having cross section of 200 x 20 x 1mm and
shutter frame made from Aluminum ‘C’ section size 23.6 x 20 x
1.8mm and door fitting such as hinges, aldrop, handles, stopper,
locking bolt will be provided :

16.17.1 Single shutter door. Sqm 2194.00 2194.00 0.00% 2,194.00 0.00%

16.17.2 Double shutter door. Sqm 2406.00 2406.00 0.00% 2,406.00 0.00%

16.18 Providing and fixing of Plastic shutter Infill made from hollow Plastic
sections in the dimension of 150 x 12 x 1mm and shutter configuration
of an ‘A’ section having an overall cross section of 47 x 26mm and
door fittings such as hinges, aldrop, handles, locking bolt will be
provided.
Sqm 1932.00 1932.00 0.00% 1,932.00 0.00%

16.19 P & F of All PVC Door shall be made from extruded PVC sections
reinforce with steel. The corners & joints shall be miter cut and
welded/Mechanical joint. The outer frame and shutter frame shall be
made from PVC section having an cross section of 53 x 60mm wall
thickness 2.8mm ± 0.3mm, suitable snap fit glazing and function
beads in as overall cross section of 30 x 23 and 15mm x 23mm shall
be used for provision of glass of panel. E.P.D.M. weather scales and
glazing scales shall be provided.

16.19.1 SHUTTER Panel infill made from PVC section 200 x 20 x 1 mm. Sqm 4448.00 4448.00 0.00% 4,448.00 0.00%

16.19.2 SHUTTER Panel fully Glazed with 5mm thick plain glass Sqm 4217.00 4217.00 0.00% 4,217.00 0.00%

16.19.3 SHUTTER Panel Partly Glazed with 5mm thick plain glass and partly
paneled with PVC sections 200 x 20 x 1mm. Sqm 4368.00 4368.00 0.00% 4,368.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.20 Providing and fixing to existing door frame 24mm thick factory made PVC
door shutter made of styles and rails of a UPVC hollow section of size
59x24mm and wall thickness 2mm ± 0.2mm with inbuilt edging on both
sides. The styles and rails mitred and jointed at the corners by means of
M.S. galvanised / plastic brackets of size 75x220mm having wall thickness
1.0mm and stainless of size screws. The styles of the shutter reinforced by
inserting galvanised M.S. tube of size 20x20mm and 1mm ± 0.1mm wall
thickness. The lock rail made up of 'H' section, a UPVC hollow section of size
100x24mm and 2mm ± 0.2mm wall thickness fixed to the shutter style by
means of plastic / galvanisd M.S. 'U' cloats. The shutter frame filled with a
UPVC multi-chambered single panel of size not less than 620mm, having
over all thickness of 20mm and 1mm ± 0.1mm wall thickness. The panels
filled vertically and tie bar at two places by inserting horizontally 6mm
galvanised M.S. rod and fastened with nuts and washers, complete as per
manufactur's specification and direction of Engineer-in-charge

including all door, fittings such as Hinges, L-drop, Handles, Locking bolts
etc. as per approval of Engineer-in-charge. Sqm. 2351.00 2351.00 0.00% 2,351.00 0.00%
16.21 Providing and fixing to existing door frame 30mm thick factory made
Polyvinyl Choloride (PVC) door shutter made of styles and rails of a UPVC
hollow section of size 60x30mm and wall thickness 2mm ± 0.2mm with inbuilt
decorative moulding edging on one sides. The styles and rails mitred and
jointed at the corners by means of M.S. galvanised / plastic brackets of size
75x220mm having wall thickness 1.0mm and stainless of size screws. The
styles of the shutter reinforced by inserting galvanised M.S. tube of size
25x20mm and 1mm ± 0.1mm wall thickness. The lock rail made up of 'H'
section, a UPVC hollow section of size 100x30mm and 2mm ± 0.2mm wall
thickness fixed to the shutter style by means of plastic / galvanisd M.S. 'U'
cleats. The shutter frame filled with a UPVC multi-chambered single panel of
size not less than 620mm, having over all thickness of 20mm and 1mm ±
0.1mm wall thickness. The panels filled vertically and tie bar at two places by
inserting horizontally 6mm galvanised M.S. rod and fastened

with nuts and washers, complete as per manufactur's specification and


direction of Engineer-in-charge including all door fittings such as Hinges, L-
drop, Handles, Locking bolts etc. as per approved of Engineer-in-charge.
Sqm. 2753.00 2753.00 0.00% 2,753.00 0.00%
PLASTIC WINDOWS :
16.22 Providing and fixing of All plastic Openable Windows shall be made
from extruded PVC section reinforced with steel. The corner & joints
shall be mitered cut and welded/Mechanically joint. The outer frame
and shutter frame shall be made from extruded PVC section, having
and overall cross section of 53 x 60mm Suitable snap fit glazing and
function beads having an overall cross section of 30 x 23mm and 15 x
23mm shall be used for provision of glass or Panel E.P.D.M. weather
scales and glazing scales and approved steel fitting with 4mm thick
plain glass complete.

Sqm 4709.00 4709.00 0.00% 4,709.00 0.00%

16.23 Providing and fixing of All Plastic fixed Windows made from PVC
section reinforced with steel. The Corners & joints shall be miter cut
and welded. The outer frame shall be made from extruded PVC
sections having on overall cross section of 53 x 60mm suitable snap
fit glazing beads having an overall cross section of 30 x 23mm shall
be used for provision of glass. E.P.D.M. weather scales and glazing
scales and approved steel fittings with 4mm thick plain glass
complete.
Sqm 2355.00 2355.00 0.00% 2,355.00 0.00%

16.24 Providing and fixing of All Plastic Two track sliding Windows shall be
made from extruded PVC sections reinforced with Steel. The corners
& joints shall be miter cut and welded. The outer frame shall be made
from extruded PVC section having an overall cross section of 53 x
60mm and the slider Panel shall be made from extruded PVC
sections having an overall cross sections of 58 x 40mm suitable snap
fit glazing beads having an overall cross section of 19mm x 19.5mm
shall be used for provision of glass. E.P.D.M. weather seal sand
glazing scales and approved steel fitting with 4mm thick plain glass
complete.
Sqm 3663.00 3663.00 0.00% 3,663.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.25 Providing and fixing of All plastic fixed louvered Ventilators shall be
made from extruded PVC section reinforce with steel. The corners
and joints shall be miter cut and welded. The outer frame shall be
made from extruded PVC section having an overall cross section of
40 x 37mm. Suitable snap fit molded louver ends louver blade of
PVC/glass and safety bar shall be provided.

Sqm 2777.00 2777.00 0.00% 2,777.00 0.00%

16.26.1 Providing and fixing of All Plastic Fly Mesh shutters shall be made
from extruded PVC section having an overall cross section of 30 x
23mm E.P.D.M. weather scales shall be provided to make it air tight.
Mosquito net of nylon/ polymer/GI mesh to be fixed on the shutter
frame. Suitable fittings shall be provided.
Sqm 1691.00 1691.00 0.00% 1,691.00 0.00%

16.26.2 P&f FRP door shutter made from special fibreglass reinforced plastic
sheet and polyurethane foam core, FRP Sheet should be made from
emulsion bonded CMS having single fibre tensile strength of
3.6x103N/mm² and co-efficient of thermal conductivity 1.04 W/Moc
and GP polyester resin having specific gravity of 1.1+0.01 sheet
should have UVstability for use inside and outside. Core of the door
shutter should be filled with polyurethane foam,. injected with the help
of hydraulic injection method and have density of minimum of
40kg/m3. Door shutter should have apple steel mesh for extra
security, and wiched in the core as per requirements of the
customers. Door shutter should have apple treated wooden border of
size 50x21mm in all the four sides for adjustable of size. The other
hardware location shall be reinforced with treated wood of suitable
size. The shutter shall have depressed mould design with special
wood vein texture on the surface including required fittings.

Sqm 3600.00 3600.00 0.00% 3,600.00 0.00%


PLASTIC PARTITION
16.27 Providing and fixing of all Plastic partition with frames made from
extruded PVC sections having on overall cross section of 53 x 60mm.
The frames shall be joined by means of concealed cleats. Suitable
snap Fit glazing beads and function beads having an overall cross
section 30 x 23 mm and 15 x 23mm shall be used for provision of
glass of panels. The horizontal and vertical members duly fixed should
be spaced 1000mm to 1200mm apart. :

16.27.1 Partition made from PVC section 200 x 20 x 1mm Sqm 3613.00 3613.00 0.00% 3,613.00 0.00%

16.27.2 Partition infill fully glazed with 5mm thick plain glass. Sqm 3269.00 3269.00 0.00% 3,269.00 0.00%

16.27.3 Partition infill partly glazed with 5mm thick plain glass and partly
paneled by PVC section 200 x 20 x 1mm. Sqm 3502.00 3502.00 0.00% 3,502.00 0.00%

PLASTIC FALSE CEILING :


(A) Plastic False Ceiling using Aluminum. Tee/Angle :
16.28 Providing and fixing of suspended false ceiling in the grid of 600 x 600
mm/600 x 600 to 900 x 900mm using aluminum tees with inter lock
system of main tee, cross tee and wall angle (size of tee and angle
approx. 25mm x 25mm x 0.5mm or equivalent) etc. complete with G.I.
Adjustable suspenders skeleton. Ceiling tiles made from multi
chamber hollow PVC section having an overall cross section of :-

16.28.1 Using 200 x 20 x 1 mm section. Sqm 1912.00 1912.00 0.00% 1,912.00 0.00%

P.V.C. PELMETS :
16.29 Providing and fixing PVC pelmets made out from multi chamber
hollow Plastic section with tongue & grooves size 12 x 150mm, Iron
brackets, 20mm dia C.P. Steel Curtain rod complete. Mtr. 291.00 291.00 0.00% 291.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.30 Providing and fixing paneled portion with Mild Steel Section ,having size of
25x38 mm with a wall thickness of 1.2 mm ± 0.1 mm the members are
jointed by M.S Cleat of 75 x75 x2 mm size having usual process variation
and with the necessary screws as per requirements .The Horizontal
members and vertical members are duly, intersecting to each other at a
space of 0.9x0.9 Mtr. apart the partition in fill is to be made out of multiple
chambered hollow PVC sections having overall dimensions of 254x6mm
corresponding to Sintex's product code no. SPUF 144 in Prelam finish with
an average wall thickness of 0.8mm ± 0.3mm, exceeding 30mm approx
variation and supporting ribs at a distance of not exceeding 30mm approx,
and jointed with one another by lap joint. The PVC section shall be fixed on
both sides of the MS frame works with self tapping screw of 19mmx8mm
size. The periphery of the partition of low height is to be covered by the PVC
multi chambered hollow sections having usefull process variation. This can
be fixed by applying cynical adhesive.

Sqm 2050.00 2050.00 0.00% 2,050.00 0.00%


16.31 Providing and fixing of false ceiling at a height decided by the engineer in-
charge on a M.S made skeleton frame work .The perimeter square M.S. Pipe
shall be fixed along with the wall ,having dimension of 25x25 mm and with a
wall thickness of 1mm +/- 0.3 mm. The main member of the grade is made
out of M.S pipe having on a overall thickness 38x25 mm and with a wall
thickness of 1mm +/- 0.3mm. The side pipe and the intermediate pipes is
fixed to the roof from the top with the help of ceiling angles /pipes.

After the grid work is completed ,it has to be covered by the multi-chamber
hollow PVC section from below , with the help of self – tapping screw of 19
mm x 8mm. These PVC hollow section are having an overall dimension of
150 mm x 10 mm or 254 mm x 6 mm , with a wall thickness of 1.0 mm ± 0.3
mm and 0.8 ± 0.2 mm respectively approved by the Engineer In charge ,are
jointed with each other by lap joint ,which will conceal the screws.
Necessary cutouts for electric connections ,lighting ,air conditioning etc.
shall be provided at required palace . The edge and cornice shall be
covered by extruded PVC corner beading sections of size 13 m x 10 mm
with a wall thickness of 1.7 mm ± 0.3 mm . The same has to be fixed by
applying cynoacrylate adhesive .
Sqm. 1510.00 1510.00 0.00% 1,510.00 0.00%
16.32 Providing and fixing of wall paneling on the frame work made out of G.I
channel of size 75x10 mm or from wooden ripper of required size with CSK
wood screws of size 50x8 mm fixed to the wall with rowel plug at a spacing
of 900 mm center to center . The paneling on the above frame work to be
done using Hollow PVC multi-chambered section of size 150x 10mm or 254
x 6m. SPOOF in Prelam finish with an average wall thickness of 1.0 each
other by lap joint and to be fixed to the G.I channel by self –tapping screw
of size 19 x 8 mm. Necessary cutouts for electrical connections to be
provided at required places. The edges and periphery , finally to be covered
by extruded PVC beading section of size 13 x 10 mm having an average
wall thickness of 1.7 m +/- 0.3 mm with an usual variation.

Sqm. 1257.00 1257.00 0.00% 1,257.00 0.00%

16.33 Providing and fixing factory made polyvinyl chloride (PVC) Door frame
of the size 50x47mm with a wall thickness of 5mm made out of
extruded 5mm, made out of extruded 5mm PVC foam sheet, mitre cut
at two corners and jointing with 2 nos. of 150mm long brackets of
15x15mm M.S. Square tube. The two vertical door profiles are to be
reinforced with 19x19mm M.S. square tube of 19gauge, EPDM rubber
gasket weather seal to be providing through out the frame shall be
fixed to the wall using 65/100mm long M.S. Screws through the frame
by using PVC fasterners. A minimum of 4 nos. of screws to be
provided for each vertical member and minimum 2 nos. for horizontal
member etc. complete as per manufacture specifications and direction
of Engineer- in-charge.

Rmt 475.00 475.00 0.00% 475.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.34 Providing and 30mm thick factory made Solid Panel PVC Door Shutter
consisting of frame made out of M.S. tubes of 19 gauge thickness and sizes
of 19mm for styles & 15mm x 15mm for top and bottom rails. M.S. frame
shall have a coat of steel primers of approved make and manufacture M.S.
frame shall be covered with 5mm thick heat moulded "Rajshri" PVC 'C'
Channel of size 30x50mm forming styles and 5mm thick, 75mm wide PVC
sheets for top rail, lock rail and bottom rail on either side & 10mm (5mmx2)
thick, 20mm wide cross sheets as gap insert for top rail & bottom rail.
Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded /
sealed to the stiles & rail with 30mm wide x 5mm thick PVC sheet beading
on either side the jointed together with solvent cement adhesive. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior
side of the 'C' Channel using PVC solvent cement adhesive etc. complete as
per direction of Engineer-in-charge, manufacture's specification & drawing
(For W.C. & Bathroom shutters).

including all door fittings such as Hinges, L-drop, Handles, Locking bolts etc.
as per approved of Engineer-in-charge Sqm. 3180.00 3180.00 0.00% 3,180.00 0.00%

16.35 Providing and fixing 30mm thick FACTORY MADE SOLID BOTH SIDE
PRELAM PANEL PVC DOOR SHUTTER consiting of frame made out of
M..S. tubes of 19 gauge thickness and size of 19mm x 19mm for stiles top &
bottom rails M.S. farme shall have a coat of sheet primers of approved make
and manufacture, M.S. farme covered with 5mm thick heat moulded "Rajshri"
prelim PVC 'C' channel of size 30mm thickness, 70mm width out of which
50mm shall be flat and 20mm shall be tapered in 45" angle on either side
forming stiles and 5mm thick 95mm wide Rajshri Prelam PVC sheet out of
75mm shall be flat and 20mm shall be tapered in 45" on the inner side to
from top and bottom rail and 115mm wide Rajshri Prelam PVC sheet out of
which 75mm shall be flat and 20mm shall be tapered on both sides to from
lock rail. Top, bottom and lock rails shall be provided either side of the panel.
10mm (5mm x 2)thick, 20mm wide cross PVC sheet shall be provided

as gap insert for top rail and bottom rail. Panelling of 5mm thick both side
Prelam PVC sheet to be fitted in the M.S. frame welded / sealed to stile and
rails with 7mm (5mm + 2mm) thick x 15mm wide PVC sheet beading on
inner side and jointed together with solvent cement adhesive. An additional
5mm thick PVC strip of 20mm width is to be struck on the interior side of the
"C' channel using PVC solvent etc. complete as per specifications & drawing.
(For internal shutters).including all door fittings such as Hinges, L-drop,
Handles, Locking bolts etc. as per approved of Engineer-in-charge.

Sqm. 4138.00 4138.00 0.00% 4,138.00 0.00%

16.36 Providing and fixing Prelaminated PVC sheet wall panelling of thickness
5mm stuck on inner frame work of 50mm vide strips of 5mm thick PVC
sheet. The strip should have in their center a groove of 6mm width and 1mm
depth for sinking the head of the screw used to fix the strips to the wall and
should be placed vertically at equal intervals of 250mm center to center. The
PVC strips shall be fixed to the wall using 65mm long M.S. screws through
the groove in the strip by using PVC fasterners. The distance between two
screw's shall not be more than 300mm. A groove of 1mm may be left at the
joint of two panel for aesthetic looks. This frame work is done for making
existing wall surface in ensured level and for sticking the wall panelling sheet
(panel) on it. The exact size of panel and correspondingly of the grid may be
varied depending on the size of the wall. However it must ensured that a
strips of 5mm thick PVC sheet of width 75mm feathered atthe edges shall be
stuck at the places where two panels are jointed, using solvent

cement including all door fittings such as Hinges, L-drop, Handles, Locking
bolts etc. as per approved of Engineer-in-charge. Sqm. 1763.00 1763.00 0.00% 1,763.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018

16.37 Providing and fixing Structural glazing work with toughened glass of 6mm thick and
reflective colour as approved in dark shade like Blue/Dark Blue etc. with frame work
of curtain section 65x60mm (Weight 1.64 kg/m min.) made of aluminium with chrome
plating. Internal frame work will also be of curtain section 65x60mm of chrome plated
aluminium section with20x20mm aluminium tube section and structural spacer made
of rubber. The aluminium frame work size as per instruction of Engineer-in-charge
and including openable panels with all necesary sections and fitting.The work include
silicon structural adhesive for complete gripping of glass with framing members and
silicon weather seal sealant to prevent moisture/water through joints. Glass will be
fixed in plumb and with uniform spacing of 10-12mm wide duly filled with silicon
weather seal sealant. The work includes all labour,scaffolding , structural aluminium
work, toughened glasses,silicon weather seal sealant, silicon structural adhesive
structrucal spacer, all accessoreis like handles, peg stays, M-15 grade cement
concrete for fixing holdfast .(Face area of glass shall be measured)

Sqm 5008.00 4892.0000 2.37% 5,008.00 2.37%

16.38 Supply and fixing of polycrete wall fencing of existing wall, fencing of 0.9 mtr. Height
above the existing wall, main member PVC profile section of size
125mmx125mmx900mm (c/c 1.67 mtr. length) with a wall thickness of
2.00mm+0.20mm and Horizontal panel PVC profile section of size 305mmx20mm (3
nos. 1.6 mtr. length) with wall thickness 1.00mm + 0.1mm and side edge covered with
PVC C-Section of size 24mm x18mm with a wall thickness of 2.00mm+0.20mm
Horizontal panel reinforced with G.I. section (C-Type) with a wall thickness of
1.20+0.10mm and horizontal panel having side in main member groove (vertical pillar
125x125mm) all complete as per design specification and as direction by Engineer in
charge.
Sqm 2407.00 2336.0000 3.04% 2,407.00 3.04%

16.39 Providing and fixing of uPVC casement fixed windows or ventilators manufactured in
ISO 9001:2000 & 14001:2004 certified company. Frame : Made from the Extruded
uPVC Window Profile Section of size 60 x 60mm having outer wall thickness of
2.25mm (+/- 0.2mm) and 3 box multi-chamber construction, White in finish, duly
reinforced with 1.2mm thick G/J/U/O TYPE GI section. All the four corners shall be
mitered cut & thermal welded so as to form window frame. Frame shall be milled with
drain and air equalizer hole in order to be water tight and for drainage of accumulated
water, if any, to outer side. Fix Mullion made of 76 x 60mm uPVC Profile Section with
steel reinforcement shall be provided in windows as per the requirement. Frame shall
have ‘O’ type EPDM gasket fitted in in-built groove of frame profile for proper air &
sound insulation of the shutter. Glazing bead of size 34 x 20mm with ‘K’ & ‘O’ type
inner and outer EPDM weather seal gaskets alongwith 5mm thick ISI make plain float
glass.All welding joints of frame and shutter shall be cleaned and milled with the CNC
mechanism to provide uniform grooved finish on all visible joints. Hardware :
Installation at Site : Complete window is to be installed on site with 10 x 100mm
fastners with white cap in existing pre-finished wall cut-out cemented to glass level
plane at all height & width and silicon glue is applied to fill up the crevices between
wall and window frame. Complete in all respect as per the drawing and specifications
and direction of engineer-in-charge.

Sqm 4912.00 4884.0000 0.57% 4,912.00 0.57%

16.40 Providing and fixing expanded grill made of aluminum as per design and drawing
having members section of size 7.5mm x 6.0mm and opening of size 75mmx72mm to
aluminum window/vent with required screws, Y and H aluminium sec (as per drawing)
at the ends and middle joints respectively complete in all respect as per direction of
engineer in charge.

16.40.1 Anodised aluminum (anodised transparent 81 dyed to required shade according to


IS : 1868. (Minimum anodic coating of grade AC 15, Anodizing to be got done from
approved Anodizer) Anodised aluminum (anodised transparent 81 dyed to required
shade according to IS : 1868. (Minimum anodic coating of grade AC 15, Anodizing to
be got done from approved Anodizer)
Sqm 1692.00 1675.0000 1.01% 1,692.00 1.01%

16.40.2 Powder coating aluminum ( minimum thickness of powder coating 50 micron)


Sqm 1753.00 1736.0000 0.98% 1,753.00 0.98%

16.40.3 Polyester Powder coating aluminum ( minimum thickness of powder coating 50


micron) Sqm 1875.00 1858.0000 0.91% 1,875.00 0.91%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.41 Providing and fixing expanded grill made of aluminum as per design and drawing
having members section of size 7.5mm x 6.0mm and opening of size 50mmx48mm to
aluminum window/vent with required screws, Y and H aluminium sec (as per drawing)
at the ends and middle joints respectively complete in all respect as per direction of
engineer in charge.

16.41.1 Anodised aluminum (anodised transparent 81 dyed to required shade according to


IS : 1868. (Minimum anodic coating of grade AC 15, Anodizing to be got done from
approved Anodizer) Sqm 1753.00 1736.0000 0.98% 1,753.00 0.98%

16.41.2 Powder coating aluminum ( minimum thickness of powder coating 50 micron)


Sqm 1814.00 1797.0000 0.95% 1,814.00 0.95%

16.41.3 Polyester Powder coating aluminum ( minimum thickness of powder coating 50


micron) Sqm 1936.00 1919.0000 0.89% 1,936.00 0.89%

16.42 Providing and fixing of uPVC Sliding windows: Frame Made from the Extruded uPVC
Window Profile Section of size 106w x 50h mm having outer wall thickness of 2.5mm
(+/- 0.2mm) and 3 box multi-chamber construction, White in finish, duly reinforced
with 1.2 mm thick GI section. Frame shall have three track configuration, two for
sliding of window shutter and one for mosquito mesh shutter. Vertical member of
frame which bears the sliding shutter load shall have aluminium rail/track for smooth
sliding of shutter rollers. All the four corners shall be mitered cut & thermal welded so
as to form window frame. Frame shall be milled with drain and air equalizer hole in
order to be water tight and for drainage of accumulated water, if any, to outer side.
Shutter : The shutter of sliding window shall be made of 39w x 69h mm Extruded 3
box multi- chamber uPVC Window Profile Section of white colour having outer wall
thickness of 2.5mm (+/- 0.2mm) provided with reinforcement of 1.5mm thick GI
section duly mitered cut & thermal welded at all corners and fitted with uPVC glazing
bead of size 22 x 20 mm with inner and outer co-extruded EPDM/TPE-E weather
seal gaskets alongwith 6mm thick ISI make plain float glass. Mesh shutter (optional)
shall be made of 39w x 69h mm Extruded 3 box multi-chamber UPVC Window profile
section of white colour having outer wall thickness of 2.5mm (+/- 0.2mm) provided
with reinforcement of 1.5 mm thick GI section duly mitered cut & thermal welded at all
corners and fitted with nylon/polymer mesh and rollers/pully. Sqm 8013.00 8443.0000 -5.09% 8,013.00 -5.09%

16.43 Providing and fixing of uPVC Sliding windows: Frame Made from the Extruded uPVC
Window Profile Section of size 106w x 50h mm having outer wall thickness of 2.5mm
(+/- 0.2mm) and 3 box multi-chamber construction, Laminated (colour) finish, duly
reinforced with 1.2 mm thick GI section. Frame shall have three track configuration,
two for sliding of window shutter and one for mosquito mesh shutter. Vertical member
of frame which bears the sliding shutter load shall have aluminium rail/track for
smooth sliding of shutter rollers. All the four corners shall be mitered cut & thermal
welded so as to form window frame. Frame shall be milled with drain and air equalizer
hole in order to be water tight and for drainage of accumulated water, if any, to outer
side. Shutter : The shutter of sliding window shall be made of 39w x 69h mm Extruded
3 box multi- chamber uPVC Window Profile Section of white colour having outer wall
thickness of 2.5mm (+/- 0.2mm) provided with reinforcement of 1.5mm thick GI
section duly mitered cut & thermal welded at all corners and fitted with uPVC glazing
bead of size 22 x 20 mm with inner and outer co-extruded EPDM/TPE-E weather
seal gaskets alongwith 6mm thick ISI make plain float glass. Mesh shutter (optional)
shall be made of 39w x 69h mm Extruded 3 box multi-chamber UPVC Window profile
section of white colour having outer wall thickness of 2.5mm (+/- 0.2mm) provided
with reinforcement of 1.5 mm thick GI section duly mitered cut & thermal welded at all
corners and fitted with nylon/polymer mesh and rollers/pully. Sqm 12503.00 12965.0000 -3.56% 12,503.00 -3.56%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.44 Providing and fixing of uPVC Sliding windows: Frame Made from the Extruded uPVC
Window Profile Section of size 106w x 50h mm having outer wall thickness of 2.5mm
(+/- 0.2mm) and 3 box multi-chamber construction, White in finish, duly reinforced
with 1.2 mm thick GI section. Frame shall have three track configuration, Vertical
member of frame which bears the sliding shutter load shall have aluminium rail/track
for smooth sliding of shutter rollers. All the four corners shall be mitered cut & thermal
welded so as to form window frame. Frame shall be milled with drain and air equalizer
hole in order to be water tight and for drainage of accumulated water, if any, to outer
side. Shutter : The shutter of sliding window shall be made of 39w x 69h mm Extruded
3 box multi- chamber uPVC Window Profile Section of white colour having outer wall
thickness of 2.5mm (+/- 0.2mm) provided with reinforcement of 1.5mm thick GI
section duly mitered cut & thermal welded at all corners and fitted with uPVC glazing
bead of size 22 x 20 mm with inner and outer co-extruded EPDM/TPE-E weather
seal gaskets alongwith 6mm thick ISI make plain float glass. Mesh shutter (optional)
shall be made of 39w x 69h mm Extruded 3 box multi-chamber UPVC Window profile
section of white colour having outer wall thickness of 2.5mm (+/- 0.2mm) provided
with reinforcement of 1.5 mm thick GI section duly mitered cut & thermal welded at all
corners and fitted with nylon/polymer mesh and rollers/pully. Sqm 5957.00 6343.0000 -6.09% 5,957.00 -6.09%

16.45 Providing and fixing of uPVC Sliding windows: Frame Made from the Extruded uPVC
Window Profile Section of size 106w x 50h mm having outer wall thickness of 2.5mm
(+/- 0.2mm) and 3 box multi-chamber construction, Laminated (colour) finish, duly
reinforced with 1.2 mm thick GI section. Frame shall have three track configuration,
Vertical member of frame which bears the sliding shutter load shall have aluminium
rail/track for smooth sliding of shutter rollers. All the four corners shall be mitered cut
& thermal welded so as to form window frame. Frame shall be milled with drain and
air equalizer hole in order to be water tight and for drainage of accumulated water, if
any, to outer side. Shutter : The shutter of sliding window shall be made of 39w x 69h
mm Extruded 3 box multi- chamber uPVC Window Profile Section of white colour
having outer wall thickness of 2.5mm (+/- 0.2mm) provided with reinforcement of
1.5mm thick GI section duly mitered cut & thermal welded at all corners and fitted with
uPVC glazing bead of size 22 x 20 mm with inner and outer co-extruded EPDM/TPE-
E weather seal gaskets alongwith 6mm thick ISI make plain float glass. Mesh shutter
(optional) shall be made of 39w x 69h mm Extruded 3 box multi-chamber UPVC
Window profile section of white colour having outer wall thickness of 2.5mm (+/-
0.2mm) provided with reinforcement of 1.5 mm thick GI section duly mitered cut &
thermal Sqm 9801.00 10187.0000 -3.79% 10,187.00 0.00%

16.46 Providing and fixing of UPVC casement fully openable windows (outward / inward):
Outer Frame made from the Extruded UPVC Windows profile section of size 60w X
60h mm having outer wall thickness of 2.5mm (+/- 0.2mm) and three chamber
constuction, White in finish, duly reinforced with 1.5mm thick GI section. All the four
corners shall be mitered cut & thermal welded so as to form window frame. Frame
shall be milled with drain and air equalizer hole in order to be water tight and for
drainage of accumulated water, if any, to outer side. Fix Mullion made of 60w X 80h
mm UPVC profile section with steel reinforcement shall be provided in windows
having 2 or more openable shutters, as per the requirement. Frame shall have co-
extruded with EPDM/TPE-E gasket fitted in in-built groove of frame profile for proper
air & sound insulation of the shutter.

Shutter: The shutter of outward openable window shall be made of size 60w
X 74h mm and shutter of inward openable window shall be made of size 60w x 77h
mm Extruded 3 box multi-chamber UPVC Window profile section of white colour
having outer wall thickness of 2.25mm (+/- 0.2mm) provided with reinforcement of
1.5mm thick GI section duly mitered cut & thermal welded at all corners and fitted with
UPVC glazing bead of size 36 X 20mm with inner and outer co-extruded EPDM/TPE-
E weather seal gasket alongwith 6mm thick ISI make plain float glass. All welding
joints of frame and shutter shall be cleaned and milled with the CNC mechainism to
provide uniform grooved finish on all visible jaints. Hardware: Window shutter are
fixed with frame on 2.5mm thick SS301 Grade friction hinge system to keep the
window opened at desird angle. Friction Hinge also enables easy cleaning of glass on
both side from the inside of building. Sqm 17177.00 9118.0000 88.39% 9,576.00 5.02%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.47 Providing and fixing of UPVC casement fully openable windows (outward / inward):
Outer Frame made from the Extruded UPVC Windows profile section of size 60w X
60h mm having outer wall thickness of 2.5mm (+/- 0.2mm) and three chamber
constuction in Laminated (colour) finish, duly reinforced with 1.5mm thick GI section.
All the four corners shall be mitered cut & thermal welded so as to form window
frame. Frame shall be milled with drain and air equalizer hole in order to be water
tight and for drainage of accumulated water, if any, to outer side. Fix Mullion made of
60w X 80h mm UPVC profile section with steel reinforcement shall be provided in
windows having 2 or more openable shutters, as per the requirement. Frame shall
have co-extruded with EPDM/TPE-E gasket fitted in in-built groove of frame profile for
proper air & sound insulation of the shutter.
Shutter: The
shutter of outward openable window shall be made of size 60w X 74h mm and shutter
of inward openable window shall be made of size 60w x 77h mm Extruded 3 box
multi-chamber UPVC Window profile section of white colour having outer wall
thickness of 2.25mm (+/- 0.2mm) provided with reinforcement of 1.5mm thick GI
section duly mitered cut & thermal welded at all corners and fitted with UPVC glazing
bead of size 36 X 20mm with inner and outer co-extruded EPDM/TPE-E weather seal
gasket alongwith 6mm thick ISI make plain float glass. All welding joints of frame and
shutter shall be cleaned and milled with the CNC mechainism to provide uniform
grooved finish on all visible jaints. Hardware: Window shutter are fixed with frame on
2.5mm thick SS301 Grade friction hinge system to keep the window opened at desird
angle. Friction Hinge also enables easy cleaning of glass on both side from the inside
of building. Sqm 12969.00 13474.0000 -3.75% 13,474.00 0.00%

16.48 Providing and fixing of UPVC casement fully open-able windows (outward / inward) :
Frame made from the Extruded UPVC Windows profile section of size 60w X 60h mm
having outer wall thickness of 2.5 mm (+/- 0.2mm) and 3 box multi-chamber
constuction, White in finish, duly reinforced with 1.5 mm thick G/J/U/O TYPE GI
section. All the four corners shall be mitered cut & thermal welded so as to form
window frame. Frame shall be milled with drain and air equalizer hole in order to be
water tight and for drainage of accumulated water, if any, to outer side. Fix Mullion
made of 60w X 80h mm UPVC profile section with steel reinforcement shall be
provided for the fix portion of the window and for the window area having 2 or more
openable shutters / fix part as per the requirement. Frame shall have co-extruded
EPDM/TPE-E gasket fitted in in-built groove of frame profile for proper air & sound
insulation of the shutter. Shutter: The shutter of outward openable window shall be
made of size 60w X 74h mm and shutter of inward openable window shall be made of
size 60w X 77h mm Extruded 3 box multi-chamber UPVC Window profile section of
white colour having outer wall thickness of 2.5 mm (+/- 0.2mm) provided with
reinforcement of 1.5 mm thick GI section duly mitered cut & thermal welded at all
corners. shutter as well as fix part of the window shall be fitted with UPVC glazing
bead of size 36 X 20 mm with inner and outer co-extruded EPDM/TPE-E Gasket. Sqm 10640.00 11027.0000 -3.51% 11,027.00 0.00%

16.49 Providing and fixing of UPVC casement fully open-able windows Laminated Profile
( Colour ) (outward / inward) : Frame made from the Extruded UPVC Windows profile
section of size 60w X 60h mm having outer wall thickness of 2.5 mm (+/- 0.2mm) and
3 box multi-chamber constuction, Laminated(colour) finish, duly reinforced with 1.5
mm thick GI section. All the four corners shall be mitered cut & thermal welded so as
to form window frame. Frame shall be milled with drain and air equalizer hole in order
to be water tight and for drainage of accumulated water, if any, to outer side. Fix
Mullion made of 60w X 80h mm UPVC profile section with steel reinforcement shall
be provided for the fix portion of the window and for the window area having 2 or
more openable shutters / fix part as per the requirement. Frame shall have co-
extruded EPDM/TPE-E gasket fitted in in-built groove of frame profile for proper air &
sound insulation of the shutter.

Shutter: The shutter of outward openable window


shall be made of size 60w X 74h mm and shutter of inward openable window shall be
made of size 60w X 77h mm Extruded 3 box multi-chamber UPVC Window profile
section of white colour having outer wall thickness of 2.5 mm (+/- 0.2mm) provided
with reinforcement of 1.5 mm thick GI section duly mitered cut & thermal welded at all
corners. shutter as well as fix part of the window shall be fitted with UPVC glazing
bead of size 36 X 20 mm with inner and outer co-extruded EPDM/TPE-E Gasket. Sqm 13886.00 14272.0000 -2.70% 14,272.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-16
Chapter Description Variatio
Code No. Proposed % Above
Analysis As per BSR n on
Unit Rate for with BSR
Rate 2018 BSR
BSR 2019 2018
2018
16.50 Providing and fixing of openable uPVC Doors with or without fix top: Frame Made of
Extruded uPVC Window Profile Section of size 60w x 70h mm having outer wall
thickness of 2.75mm (+/- 0.2mm) and 3 box multi-chamber construction, White in
finish, duly reinforced with 1.2mm thick GI section. All the corners shall be mitered cut
& thermal welded so as to form door frame. Fix Mullion made of 60w x 80h mm uPVC
Profile Section with steel reinforcement shall be provided for the top fix portion of the
doors or in case of the doors having more than two openable shutters, as per the
requirement / drawing. Frame of openable door shall have „O‟ type EPDM gasket
fitted in in-built groove of frame profile for proper air & sound insulation of the shutter.
Shutter : The shutters of openable door shall be made of 60w x 95h mm Extruded 3
box multi-chamber uPVC Window Profile Section of white colour having outer wall
thickness of 2.75mm (+/- 0.2mm) provided with reinforcement of 2.0 mm thick GI
section duly mitered cut & thermal welded at all corners, provided with center mullion
(if specified in drawing) of size 60w x 80h mm uPVC Profile Section and fitted with
uPVC glazing
bead of size 36 x 20mm with inner and outer co-extruded EPDM/TPE-E weather seal
gaskets alongwith 6mm thick ISI make plain float glass. All welding joints of frame and
shutter shall be cleaned and milled with the CNC mechanism to provide uniform
grooved finish on all visible joints. Hardware: Each openable door shutters is to be
fixed with three load beading butt hinges and locking of doors is to be provided with Sqm 9537.00 9930.0000 -3.96% 9,930.00 0.00%
multi-point door
Complete transmission gear (ESPAG)
is to be installed with10
on site with white finish fastners
X 100mm powder- with
coated lockable
white cap in
existing pre-finished wall cut-out cemented to glass level plane at all height & width
and silicon glue is applied to fill up the crevices between wall and door frame.
Complete in all respect as per the drawing and specification and direction of engineer-
in-charge.

16.51 Providing and fixing of openable uPVC Doors with or without fix top: Frame Made of
Extruded uPVC Window Profile Section of size 60w x 70h mm having outer wall
thickness of 2.75mm (+/- 0.2mm) and 3 box multi-chamber construction, Laminated
(colour) finish, duly reinforced with 1.2mm thick GI section. All the corners shall be
mitered cut & thermal welded so as to form door frame. Fix Mullion made of 60w x
80h mm uPVC Profile Section with steel reinforcement shall be provided for the top fix
portion of the doors or in case of the doors having more than two openable shutters,
as per the requirement / drawing. Frame of openable door shall have co-extruded
EPDM/TPE-E gasket fitted in in-built groove of frame profile for proper air & sound
insulation of the shutter. Shutter : The shutters of openable door shall be made of 60w
x 95h mm Extruded 3 box multi-chamber uPVC Window Profile Section of white
colour having outer wall thickness of 2.75mm (+/- 0.2mm) provided with reinforcement
of 2.0 mm thick GI section duly mitered cut & thermal welded at all corners, provided
with center mullion (if specified in drawing) of size 60w x 80h mm uPVC Profile
Section and fitted with uPVC glazing
bead of size 36 x 20mm with inner and outer co-extruded EPDM/TPE-E weather seal
gaskets alongwith 6mm thick ISI make plain float glass. All welding joints of frame and
shutter shall be cleaned and milled with the CNC mechanism to provide uniform
grooved finish on all visible joints. Hardware: Each openable door shutters is to be Sqm 13165.00 13558.0000 -2.90% 13,558.00 0.00%
Complete door is to be installed on site with 10 X 100mm fastners with white cap in
existing pre-finished wall cut-out cemented to glass level plane at all height & width
and silicon glue is applied to fill up the crevices between wall and door frame.
Complete in all respect as per the drawing and specification and direction of engineer-
in-charge.

104822.00 103753.00 1.03% 103986.00 0.22%

T.A. TO S.E. AAO Superintending Engineer


SUMMERY OF % ABOVE/BELOW WITH OLD BSR 2013
FOR PROPOSED BUILDING B.S.R. w.e.f. 2018 S.E. P.W.D. CIRCLE, BHARATPUR

Chapeter No. Description Proposed As per BSR % above % % 1.12


Rate Total 2018 rates on BSR Minimum Maximum
Total 2018
1 EARTH WORK 19364.47 17890.95 8.24% -26.20% 10.00%

2 MORTAR 99744.00 92791.00 7.49% 1.07% 10.00%

3 CEMENT CONCRETE 79438.20 75695.20 4.94% 0.00% 5.00%

4 REINFORCED CONCRETE 114617.70 110289.67 3.92% 0.00% 4.96% 0 to 5% Except Item


No4.10,4.11.4.31
5 BRICK WORK 66005.00 62997.50 4.77% 0.00% 5.00% Except Item No5.19.2

6 PART - A : GENERAL STONE WORK 683184.22 651457.22 4.87% 0.00% 5.00%

7 MARBLE, GRANITE AND TILE WORKS 177496.25 170841.25 3.90% 0.00% 5.00%

8 WOOD WORK 1001723.66 971626.00 3.10% 0.00% 5.00%

9 STEEL AND FENCING WORK 99761.49 98121.29 1.67% 0.00% 5.00%

10 ROOFING 51099.15 49729.00 2.76% 0.00% 4.98%

11 FLOORING WORK 104407.00 95261.25 9.60% -20.00% 20.00%

12 FINISHING WORK 16963.05 15041.40 12.78% 0.00% 20.00% Ecept Item 12.78,12.79

13 REPAIRS TO BUILDINGS 19409.50 17702.00 9.65% 0.00% 20.00% Except Item No5.13.13

14 DISMANTLING AND DEMOLISHING WORK 22057.00 18657.41 18.22% 0.00% 20.00% Except Item No. 14.15.2
& 14.16.2
15 MISCELLANCEOUS BUILDING ITEMS AND 44021.00 44856.08 -1.86% 0.00% 5.00%
WATER PROOFING TREATMENT
16 ALLUMINIUM & PVC WORK 103986.00 103753.00 0.22% 0.00% 4.98%

S-1 SANITARY INSTALLATION WORK 245242.35 239863.15 2.24% 0.00% 5.00%

S-2 WATER SUPPLY INSTALLATION 221668.15 216488.15 2.39% -13.04% 10.00%

B 9191.00 8499.00 8.14% 4.37% 9.49%

S-3 DRAINAGE / DISPOSAL WORKS 330393.00 307331.00 7.50% 0.00% 10.00%

S-4 TUBE WELL 82086.00 79157.00 3.70% 0.00% 9.97%

TOTAL 3591858.19 3448048.52 5.63% -2.56% 9.26%

T.A. TO S.E. AAO Superintending Engineer


1.047

1.048

1.05

1.05

1.05

1.05

1.05

1.2

1.2

1.2

1.2

1.05005

1.0503

1.05

1.095

1.1

1.1001

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
MISCELLANCEOUS BUILDING ITEMS AND WATER PROOFING TREATMENT

CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018

DAMP PROOF COURSE (DASA)

15.1 Providing and laying damp-proof course 25mm thick with cement sand
mortar 1 : 3 including two coats of hot blown bitumen (2 Kg. per Sqm)
complete as per specification. Sqm. 120.00 120.00 0.00% 120.00 0.00%

15.2 Providing and laying damp-proof course with cement concrete grade M-
150 (1 : 2 : 4) mortar prepared with 1% solution of water-proof
compound including two coats of hot blown bitumen (2Kg. per Sqm)
complete as per specification with glass strip 3mm thick at a distance of
1m. interval :

15.2.1 30mm thick Sqm. 210.00 210.00 0.00% 210.00 0.00%

15.2.2 50mm thick. Sqm. 347.00 344.00 0.87% 347.00 0.87%

15.2.3 75mm thick. Sqm. 408.00 408.00 0.00% 408.00 0.00%

15.2.4 100mm thick. Sqm. 498.00 498.00 0.00% 498.00 0.00%

15.3 Providing and laying horizontal damp proof course with Hessian base
self-finished bitumen felt, type 3 grade 2 including hot applied Blown
bitumen coating, 10cm. thick cement concrete fillet complete as per
specifications Sqm. 345.00 345.00 0.00% 345.00 0.00%

15.4 Providing and laying horizontal fiber base self-finished felt type 2 grade 3
including hot applied blown bitumen coating. 10cm. thick cement
concrete fillet complete as per specification. Sqm. 360.00 360.00 0.00% 360.00 0.00%
15.5 Providing and laying premixed tar or bitumen damp-proof course
40mm thick (excluding cost of bitumen). Sqm. 58.00 58.00 0.00% 58.00 0.00%
15.6 Providing & fixing precast cement concrete coping 1 : 2 : 4 mix
50mm thick complete as per specification :
50mm Thick Sqm. 242.00 212.00 14.15% 222.00 4.72%

15.7 Deduct in item No. 15.2 if no glass strips are used. Sqm. 21.00 21.00 0.00% 21.00 0.00%

15.8 Deduct in item No. 15.2 for not applying 2 coats of hot blown
bitumen complete as per specifications. Sqm. 30.00 30.00 0.00% 30.00 0.00%
EXPANSION JOINT :
15.9 Expansion joint raised type including cutting & finishing joint, raising
brick pardi including plaster and making gola around pardi covered with
kota stone with required slop to repel water effectively. Mtr. 272.00 272.00 0.00% 272.00 0.00%
WATER PROOFING TREATMENT
15.10 Providing and laying four course water proofing treatment with bitumen
felt over roofs consisting of first and third courses of blown or/and
residual bitumen applied hot @ 1.45Kg. per square meter of area for
each course, second course of roofing felt type 3grade –I (Hessian
based self finished bitumen felt) manufactured by Bengal Bitumen ,SPT
Ltd ,Arcus Ltd etc., and fourth and final course of stone grit 6mm and
down size of pea sized gravel spread at 6cubes diameter per square
meter including preparation of surface, but excluding grading, complete
with confirming to IS : 1322 and 1345 with:

15.10.1 Bitumen felt (Hessian base) type 3 grade - I conforming to : 1322.


Sqm. 159.00 159.00 0.00% 159.00 0.00%

15.10.2 Bitumen felt (glass fiber base) type 2 grade-I. Sqm. 252.00 252.00 0.00% 252.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.11 Providing and laying six courses water proofing treatment with bitumen
felt over roofs consisting of first, third and fifth courses of blown bitumen
or / and residual bitumen applied hot @ 1.45 ,1.20 and 1.45 Kg per
sqm. of area respectively second and fourth courses of roofing felt type
3 grade-I conforming to IS 1322 (Hessian based self finished bitumen
felt) conforming to IS 1322 manufactured by Bengal Bitumen ,SPT Ltd
,Arcus Ltd etc., and sixth and final course of stone grit 6mm and down
size of pea sized gravel spread at 6 cubic dm. per square metre
including preparation of surface but excluding grading complete .

Sqm. 373.00 373.00 0.00% 373.00 0.00%

15.12 Providing and laying six courses water proofing treatment with bitumen
felt over roofs consisting of first, third and fifth courses of blown or/and
residual bitumen applied hot at 1.45, 1.20 and 1.70 Kg. per Sqm. of area
respectively second and fourth courses of roofing felt type 2 grade-I
(fiber base self finished bitumen felt) and sixth and final course of stone
grit 6mm and down size or pea sized gravel spread at 8cu.dm per sqm
including preparation of surface excluding grading complete confirming
to IS : 1322 and 1346.
Sqm. 373.00 373.00 0.00% 373.00 0.00%

15.13 Providing and laying six courses water proofing treatment with bitumen
felt over roofs consisting of first, third and fifth courses of blown or/and
residual bitumen applied hot at 1.45, 1.20 and 1.70Kg. per Sqm of area
respectively second and fourth courses of roofing felt type 2 grade 2
(fiber base self finished bitumen felt) and sixth and final course of stone
grit 6mm and down size of pea sized gravel spread at 8cu.dm per sqm
including preparation of surface excluding grading complete confirming
to IS : 1322 and 1346.
Sqm. 367.00 367.00 0.00% 367.00 0.00%

15.14 Supplying and applying bituminous solution primer on roofs or on wall


surface at 0.24 liter per sqm. Sqm. 22.00 22.00 0.00% 22.00 0.00%

15.15 Supplying and laying under layer of bitumen saturated felt type-1. Sqm. 76.00 76.00 0.00% 76.00 0.00%

15.16 Deduct for omitting in water proofing treatment final course of spreading
stone grit 6mm. and down size of pea sized gravel :

15.16.1 At 6dm3 per Sqm. Sqm. 5.00 5.00 0.00% 5.00 0.00%

15.16.2 At 8dm3 per Sqm. Sqm. 6.00 6.00 0.00% 6.00 0.00%

15.17 Grading for roof water proofing treatment with :

15.17.1 Lime concrete with 20mm nominal size brick aggregate and 50% lime
mortar 1 : 2 (1 lime putty : 2 surkhi). Cum 1662.00 1662.00 0.00% 1,662.00 0.00%

15.17.2 Cement concrete 1 : 2 : 4 (1 cement : 2 coarse sand : 4


graded stone aggregate 20mm nominal size) with water proof
compound as per manufacture's specification. Cum 5317.00 4359.00 21.98% 4,577.00 5.00%

15.17.3 Cement mortar 1 : 3 (1 cement : 3 coarse sand). Cum 4558.00 4462.00 2.15% 4,558.00 2.15%

15.17.4 Cement mortar 1 : 4 (1 cement : 4 coarse sand). Cum 2765.00 2765.00 0.00% 2,765.00 0.00%

15.18 Providing and laying two coats of black rubberized water proof coating
after cleaning the existing surface with wire brush, surface should be
free from dust, loose particle, oil and grease etc. Apply 1st coat over
surface or RCC/Stone slab/Lime terrace/and MS Tanks etc. and apply2nd
coat after drying completely 1st coat (drying period 8 hours) complete in
all respects (as per manufacturer’s specification).

Sqm. 76.00 76.00 0.00% 76.00 0.00%

15.19 Add extra over item No. 15.18, if 3rd coat is applied for highly affected
surfaces. Sqm. 29.00 29.00 0.00% 29.00 0.00%

15.20 Add extra over item No. 15.18, if white rubberized water proofing, is
used in place of black as per manufacturer specification. Sqm. 44.00 44.00 0.00% 44.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.21 Add extra over item No. 15.20, if 3rd coat of white rubberized water
proofer is applied for highly affected surfaces. Sqm. 29.00 29.00 0.00% 29.00 0.00%

15.22 Providing and laying two coats of clear (colorless) water proofing
coating of Silicon water repellent over brick/ exposed stone masonry
facing/ Mosaic/ stone tile roofing/Interior and exterior walls surface after
cleaning with brush and apply with brush or spray gun in 2 coats
complete (Also over treatment of crack seal caulking compound).
Sqm. 76.00 76.00 0.00% 76.00 0.00%

15.23 Providing and filling block rubberized joint filler in all visible cracks of
masonry/concrete/terrace concrete blocks/ canal lining
basement/A.C./G.I./sheets roofs gutters down pipes after removing
existing treatment and cleaning with wire brush and joint should be free
frame dust, loose particle, oil and grease than filling joints with filler putty
knife spatula or brook knife and let it dry for at least 72 hours complete
(as per manufacturer specifications)
Sqm. 100.00 100.00 0.00% 100.00 0.00%

15.24 Add extra over item No. 15.23, if white crack seal caulking compound
used in place of black above over terrace/RCC Crack in vertical walls
masonry/plaster/expansion joints door frame joints around wash basin in
fixed stone slab around bath tub glazed tile joints kitchen platform, but
joints should not be more than 10mm depth and let it dry upto 48 hours
complete.
Sqm. 40.00 40.00 0.00% 40.00 0.00%

15.25 Providing and painting of Tank mastic anticorrosive paint two coats on
steel and concrete Tanks pipes fluid concrete etc. with surface duly
clean and free from moisture. Sqm. 7.00 7.00 0.00% 7.00 0.00%

15.26 Providing and painting silver shield anticorrosive (Aluminum finish) paint
over bituminous water proofing on sloppy roofs, grills, poles, rolling
shutters and protective treatment two coats complete. Sqm.. 18.00 18.00 0.00% 18.00 0.00%

15.27 Providing and laying bituminous mastic flooring as per IS-1195/1196 for
stores public corridors, ware-houses loading garages workshops
etc.,25mm thick Sqm. 360.00 360.00 0.00% 360.00 0.00%
R.C.C. FRAMES
15.28 Providing and fixing in cement sand mortar 1 : 3 single/double rebated
R..C. Door Window and ventilator frames (Chowkhats) including 1%
reinforcement as per design and concrete mix 1 : 2 : 4 cutting etc.
complete incl. horns. and hold fasts :
15.28.1 Size 75 x 50mm Mtr. 79.00 79.00 0.00% 79.00 0.00%

15.28.2 Size 75 x 75mm Mtr. 90.00 90.00 0.00% 90.00 0.00%

15.28.3 Size 100 x 75mm Mtr. 97.00 97.00 0.00% 97.00 0.00%

15.28.4 Size 125 x 75mm Mtr. 118.00 118.00 0.00% 118.00 0.00%

15.29 Add extra for RC frames (Chowkhats) Curved in plan over item No.
15.28. Mtr. 10% 10%

15.30 Add extra over item No. 15.36 for finishing the exposed face with terrazo
(Mosaic) finish. Mtr. 20% 20%

CUT STONE DOOR AND WINDOW FRAMES


NOTE : The rates include fixing curing and finishing etc. complete for ground
floor and basement structure.
15.31 Providing and fixing in cement sand mortar 1 : 4 single paitam (rebated)
stone doors windows and ventilator frames of approved quarry :

15.31.1 Size 75 x 60mm Mtr. 78.00 78.00 0.00% 78.00 0.00%

15.31.2 Size 75 x 75mm Mtr. 101.00 101.00 0.00% 101.00 0.00%

15.31.3 Size 100 x 60mm Mtr. 104.00 104.00 0.00% 104.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.31.4 Size 100x 75mm Mtr. 109.00 109.00 0.00% 109.00 0.00%

15.31.5 Size 125 x 100mm Mtr. 130.00 130.00 0.00% 130.00 0.00%

15.32 Treatment of roof leakage by paste consist of waxes and chemicals as


per manufactures as specification including of cleaning of surface
spreading the paste over the leaking surface etc. complete. Kg. 144.00 144.00 0.00% 144.00 0.00%

15.33 Providing and fixing in CM 1 : 4 double paitam (rebated) stone door


window and ventilator frames of approved quarry :

15.33.1 Size 100 x 75mm. Mtr. 156.00 156.00 0.00% 156.00 0.00%

15.33.2 Size 125 x 75mm Mtr. 167.00 167.00 0.00% 167.00 0.00%

15.33.3 Size 125 x 100mm Mtr. 184.00 184.00 0.00% 184.00 0.00%

15.34 Providing and fixing in CM 1 : 4 four paitam (rebated) stone door window
and ventilator frames of approved quarry :

15.34.1 Size 125 x 100mm Mtr. 207.00 207.00 0.00% 207.00 0.00%

15.34.2 Size 125 x 75mm Mtr. 184.00 184.00 0.00% 184.00 0.00%

15.35 Add extra over item Nos. 15.31, 15.33 & 15.34 for frames curved in plan
Mtr. 10% 10%

15.36 Labour charges for cutting on rebated (paitam) Mtr. 13.00 13.00 0.00% 13.00 0.00%

RAIN WATER SPOUT AND PIPES


NOTE : All the rain water pipe and accessories should be confirming to the
relevant IS Codes.

15.37 Providing and fixing on wall face CI rain water pipes including filling the
joint with spun yarn soaked in neat cement slurry and cement mortar
1 : 2 (1 cement : 2 fine sand) :

15.37.1 75mm diameter. Mtr. 605.00 605.00 0.00% 605.00 0.00%

15.37.2 100mm diameter. Mtr. 725.00 725.00 0.00% 725.00 0.00%

15.37.3 150mm diameter. Mtr. 925.00 925.00 0.00% 925.00 0.00%


15.38 Providing and fixing embedding sand cast iron rain water pipes in the
masonry surrounded with 12mm thick cement mortar of the same mix as
that of masonry (lead caulking will be paid separately) :

15.38.1 75mm dia pipe. Mtr. 489.00 489.00 0.00% 489.00 0.00%

15.38.2 100mm dia pipe. Mtr. 489.00 489.00 0.00% 489.00 0.00%

15.38.3 150mm dia pipe. Mtr. 1061.00 1061.00 0.00% 1,061.00 0.00%

15.39 Providing and fixing MS holder bat clamps of approved design to CI or


SCI rain water pipes embedded in and including cement concrete block
10 x 10 x 10cmof 1: 2 : 4 mix(1 cement : 2 course sand : 4 graded stone
aggregate 20mm nominal size) and cost of cutting holes and making
good the walls etc.) :

15.39.1 75mm diameter. Each 75.00 75.00 0.00% 75.00 0.00%

15.39.2 100mm diameter. Each 127.00 127.00 0.00% 127.00 0.00%

15.39.3 150mm diameter. Each 141.00 141.00 0.00% 141.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.40 Providing and fixing on walls face CI accessories for rain water pipes
including filling the joints with spun yarn soaked in neat cement slurry
and cement mortar 1 : 2 ( 1cement : 2 fine sand) :
15.40.1 CI plain bend :
(a) 75mm diameter. Each 216.00 216.00 0.00% 216.00 0.00%

(b) 100mm diameter. Each 266.00 266.00 0.00% 266.00 0.00%

(c) 150mm diameter. Each 627.00 627.00 0.00% 627.00 0.00%

15.40.2 CI head flat or corner type bend :


(a) 75mm diameter. Each 216.00 216.00 0.00% 216.00 0.00%

(b) 100mm diameter. Each 259.00 259.00 0.00% 259.00 0.00%

(c) 150mm diameter. Each 639.00 639.00 0.00% 639.00 0.00%

15.40.3 CI plain shoes :

(a) 75mm diameter. Each 216.00 216.00 0.00% 216.00 0.00%

(b) 100mm diameter. Each 259.00 259.00 0.00% 259.00 0.00%

(c) 150mm diameter. Each 639.00 639.00 0.00% 639.00 0.00%

15.40.4 CI branches (plain)

(a) 75mm dia single branch. Each 316.00 316.00 0.00% 316.00 0.00%

(b) 100mm dia single branch. Each 409.00 409.00 0.00% 409.00 0.00%

(c) 150mm dia single branch. Each 1006.00 1006.00 0.00% 1,006.00 0.00%

(d) 75mm dia double branch. Each 453.00 453.00 0.00% 453.00 0.00%

(e) 100mm dia double branch. Each 647.00 647.00 0.00% 647.00 0.00%

15.40.5 CI off-set (Plain) :

(a) 75mm dia 55mm projection. Each 200.00 200.00 0.00% 200.00 0.00%

(b) 75mm dia 75mm projection. Each 231.00 231.00 0.00% 231.00 0.00%

(c) 75mm dia 100mm projection. Each 263.00 263.00 0.00% 263.00 0.00%

(d) 75mm dia 150mm projection. Each 294.00 294.00 0.00% 294.00 0.00%

(e) 100mm dia 55mm projection. Each 289.00 289.00 0.00% 289.00 0.00%

(f) 100mm dia 75mm projection. Each 321.00 321.00 0.00% 321.00 0.00%

15.41 Add extra over item No. 15.40 for providing lead caulked joint to sand
cast iron accessories for rain water pipes and fittings :

15.41.1 75mm dia pipe. Each 101.00 101.00 0.00% 101.00 0.00%

15.41.2 100mm dia pipe. Each 115.00 115.00 0.00% 115.00 0.00%

15.41.3 150mm dia pipe. Each 130.00 130.00 0.00% 130.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.42 Providing, fixing and embedding sand cast iron accessories for rain
water pipes in the masonry surrounded with 12mm thick cement mortar
of the same mix as that of masonry (lead caulking will be paid
separately) :

15.42.1 S.C.I. plain bend :


(a) 75mm dia. Each 225.00 225.00 0.00% 225.00 0.00%

(b) 100mm dia. Each 281.00 281.00 0.00% 281.00 0.00%

(c) 150mm dia. Each 650.00 650.00 0.00% 650.00 0.00%

15.42.2 Sand cast iron plain shoes :


(a) 75mm dia. Each 230.00 230.00 0.00% 230.00 0.00%

(b) 100mm dia. Each 274.00 274.00 0.00% 274.00 0.00%

(c) 150mm dia. Each 639.00 639.00 0.00% 639.00 0.00%

15.43 Providing and fixing on wall face asbestos cement rain water pipe
including jointing with spun yarn soaked in bitumen and cement
mortar 1 : 2 (1 cement : 2 coarse sand) complete including M.S.
clamp :

15.43.1 75mm dia. Rmt 86.00 86.00 0.00% 86.00 0.00%

15.43.2 100mm dia. Rmt 93.00 93.00 0.00% 93.00 0.00%

15.43.3 150mm dia. Rmt 122.00 122.00 0.00% 122.00 0.00%

15.44 Providing and fixing for A.C. pipe on wall plug and standard holder bat
clamps comprising of two semicircular valves of flat iron and cast iron
base screwed on wooden plugs is not done :

15.44.1 75mm dia. Each 16.00 16.00 0.00% 16.00 0.00%

15.44.2 100mm dia. Each 18.00 18.00 0.00% 18.00 0.00%

15.44.3 150mm dia. Each 23.00 23.00 0.00% 23.00 0.00%

15.45 Providing and fixing on wall face asbestos cement fitting for rain water
pipes including jointing with spun yarn soaked in bitumen and cement
mortar 1 :2 (1 cement : 2 coarse sand) :

15.45.1 Bends of required degree :


(a) 75mm dia without door. Each 35.00 35.00 0.00% 35.00 0.00%

(b) 75mm dia with door. Each 44.00 44.00 0.00% 44.00 0.00%

(c) 100mm dia without door. Each 38.00 38.00 0.00% 38.00 0.00%

(d) 100mm dia without door. Each 51.00 51.00 0.00% 51.00 0.00%

(e) 150mm dia without door. Each 58.00 58.00 0.00% 58.00 0.00%

(f) 150mm dia with door. Each 86.00 86.00 0.00% 86.00 0.00%

15.45.2 OFF SETS


(a) 75mm dia meter
52.2mm Each 33.00 33.00 0.00% 33.00 0.00%

76.2mm Each 35.00 35.00 0.00% 35.00 0.00%

114.3mm Each 36.00 36.00 0.00% 36.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
152.4mm Each 38.00 38.00 0.00% 38.00 0.00%

228.6mm Each 39.00 39.00 0.00% 39.00 0.00%

303.8mm Each 40.00 40.00 0.00% 40.00 0.00%

457.2mm Each 41.00 41.00 0.00% 41.00 0.00%

(b) 100mm dia meter


52.2mm Each 49.00 49.00 0.00% 49.00 0.00%

76.2mm Each 51.00 51.00 0.00% 51.00 0.00%

114.3mm Each 52.00 52.00 0.00% 52.00 0.00%

152.4mm Each 53.00 53.00 0.00% 53.00 0.00%

228.6mm Each 55.00 55.00 0.00% 55.00 0.00%

303.8mm Each 56.00 56.00 0.00% 56.00 0.00%

457.2mm Each 58.00 58.00 0.00% 58.00 0.00%

(c) 150mm dia meter


52.2mm Each 56.00 56.00 0.00% 56.00 0.00%

76.2mm Each 58.00 58.00 0.00% 58.00 0.00%

114.3mm Each 58.00 58.00 0.00% 58.00 0.00%

152.4mm Each 59.00 59.00 0.00% 59.00 0.00%

228.6mm Each 62.00 62.00 0.00% 62.00 0.00%

303.8mm Each 63.00 63.00 0.00% 63.00 0.00%

457.2mm Each 67.00 67.00 0.00% 67.00 0.00%

15.45.3 TEES
(a) 75mm dia without door. Each 38.00 38.00 0.00% 38.00 0.00%

(b) 75mm dia with door. Each 51.00 51.00 0.00% 51.00 0.00%

(c) 100mm dia without door. Each 51.00 51.00 0.00% 51.00 0.00%

(d) 100mm dia with door. Each 55.00 55.00 0.00% 55.00 0.00%

(e) 150mm dia without door. Each 79.00 79.00 0.00% 79.00 0.00%

(f) 150mm dia with door. Each 85.00 85.00 0.00% 85.00 0.00%

15.45.4 SHOES
(a) 75mm dia. Each 24.00 24.00 0.00% 24.00 0.00%

(b) 100mm dia meter. Each 29.00 29.00 0.00% 29.00 0.00%

(c) 150mm dia meter. Each 39.00 39.00 0.00% 39.00 0.00%

15.45.5 SOCKETS
(a) 75mm dia. Each 15.00 15.00 0.00% 15.00 0.00%

(b) 100mm dia meter. Each 16.00 16.00 0.00% 16.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
(c) 150mm dia meter. Each 22.00 22.00 0.00% 22.00 0.00%

15.46 Deduct in item No. 15.43 to 15.45, for using non ISI A.C. pipes /
accessories. 20% 20%

15.47 Providing and laying integral cement based treatment for water proofing
on horizontal surface at all level as directed by Engineer- in-Charge and
consisting of :

(a) 1st layer of 20mm thick approved and specified rough stone slab over a
25mm thick base of cement mortar 1:3 (1 cement: 3 coarse sand) mixed
with water proofing compound ‘Impermo’ of Snowcem or equivalent
conforming to IS:2645 in the recommended proportion. Joints sealed
and grouted with cement slurry mixed with water proofing recommended
proportion.

(b) 2nd layer of 25mm thick cement mortar 1:3 (1 cement : 3 coarse
sand) mixed with water proofing compound in recommended
proportions.
(c) Finishing top with stone aggregate of 10mm to 12mm nominal size
spreading @ 8 cudm/sqm thoroughly embedded in the 2nd layer.

15.47.1 Using rough Kota stone Sqm. 644.00 644.00 0.00% 644.00 0.00%

15.47.2 Using rough red sand stone. Sqm. 588.00 588.00 0.00% 588.00 0.00%

15.48 Providing and laying integral cement based treatment for water proofing
on the vertical surface by fixing specified stone slab 20mm thick with
cement slurry mixed with water proofing compound ‘Impermo’ of
Snowcem or equivalent conforming to IS:2645 in recommended
proportions with a gap of 20mm (minimum) between stone slabs and the
receiving surfaces and filling the gaps with neat cement slurry mixed
with water proofing compound and finishing the exterior of stone slab
with cement mortar 1:4 (1 cement:4 coarse sand) 20mm thick with neat
cement punning mixed with water proofing compound in recommended
proportion complete at all levels and as directed by Engineer-in-charge

15.48.1 Using rough Kota stone Sqm. 765.00 765.00 0.00% 765.00 0.00%

15.48.2 Using rough red sand stone. Sqm. 708.00 708.00 0.00% 708.00 0.00%

15.49 Providing and laying water proofing treatment to vertical and horizontal
surfaces of depressed portions of W.C., kitchen and the like consisting
of
I) 1st course of applying cement slurry @ 4.4 Kg/sqm’ mixed with water
proofing compound ‘Impermo’ of Snowcem or equivalent conforming to
IS 2645 in recommended proportions.
II) IInd course of 20mm cement plaster 1:3 (1 cement: 3 coarse sand)
mixed with water. proofing compound in recommended proportion.
III) IIIrd course of applying blown or residual bitumen applied hot at 1.7 Kg
per sqm. of area.
IV IVth course of 400 micron thick PVC sheet .(Overlaps at joints of PVC
sheet should be 100 mm wide and pasted to each other with bitumen @
Kg/sqm.) Sqm. 265.00 265.00 0.00% 265.00 0.00%
15.50 Providing and fixing APP (Atactic Polypropylene Polymer) modified Pre
fabricated five layer 2mm thick water proofing membrance, black
finished reinforced with glass fiber matt manufactured by Bitumen
Company Ltd, Sopreme , Tamko,IWL India and Texsa India consisting of
a coat of bitumen primer for bitumen membrance @ 0.40 Qtl/Sqm by the
sub-membrane manufactured of density of 250 C, 0.87-0.89 KS/ Ltr and
viscosity 70-160 CPS over the primer coat the layer of membrance shall
be laid using butane torch also sealing all joints etc. and preparing the
surface complete. The vital physically and chemical parameters of the
membrance shall be as under :-

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
Joint strength in longitudinal and transverse direction at 23‘ C as
350/300 N/5cm. Tear strength in longitudinal and transverse direction as
60/80N. Softening point of membrane not less than 150°C. Cold
flexibility shall be upto -2‘ C when tested in accordance with ASTM, D
-5147. (The laying of membrane shall be got done through the
authorized applicator of the manufacture of membrane).

15.50.1 2mm ( for corrugated roof sheets) Sqm.. 288.00 288.00 0.00% 288.00 0.00%

15.51 Providing and laying APP (Atactic Polypropylene Polymer) modified


prefabricated five layer, 3mm thick water proofing membrane, black
finished reinforced with glass fiber matt manufactured by Bitumen Co.
Ltd., Sopreme, General Membranes Tamko, IWL India and Texsa India
consisting of a coat of bitumen primer for bitumen membrane @ 0.40
Ltr/sq.mt. by the same membrane manufactured of density at 25°C, 0.87
-0.89 kg/ltr and viscosity 70 -160 cps. Over the primer coat the layer of
membrane shall be laid using butane torch and sealing all joints etc.,
and preparing the surface complete. The vital physical and chemical
parameters of the membrane shall be as under :-

Joint strength in longitudinal and transverse direction at 23°C as


350/300 N/5cm. Tear strength in longitudinal and transverse direction as
60/80N. Softening point of membrane not less than 150°C. Cold
flexibility shall be upto -2°C when tested in accordance with ASTM, D
-5147. (The laying of membrane shall be got done through the
authorized applicator of the manufacturer of membrane).

15.51.1 3mm thick Sqm.. 345.00 345.00 0.00% 345.00 0.00%

15.52 Providing and laying APP (Atactic Polypropylene Polymer) modified


prefabricated five layer 3mm thick water proofing membrane, black
finished reinforced with non-woven polyester matt manufactured by
Bitumen Co. Ltd., Sopreme, General membranes , Tamko, IWL India or
Texsa India consisting of a coat of bitumen primer for bitumen
membrane @ 0.40 Itr/sq.mt. by the same membrane manufacture of
density at 25°C, 0.87-0.89 kg/ltr and viscosity 70-160 cps. Over the
primer coat the layer of membrane shall be laid using Butane Torch and
sealing all joints etc., and preparing the surface complete. The vital
physical and chemical parameters of the membrane shall be as under: -

Joint strength in longitudinal and transverse direction at 23°C as


650/450N/5cm. Tear strength in longitudinal and transverse direction as
300/250N. Softening point of membrane not less than 150°C. Cold
flexibility shall be upto -2°C when tested in accordance with ASTM, D-
5147. The laying of membrane shall be got done through the authorized
applicator of the manufacturer of membrane.

15.52.1 3mm thick Sqm.. 403.00 403.00 0.00% 403.00 0.00%

15.53 Extra for covering top of membrane with Geotextile, 120gsm non woven,
100% polyester of thickness 1 to 1.25mm bonded to the membrane with
intermittent touch by heating the membrane by Butane Torch as per
manufactures recommendation [ for Item No.15.53 to 15.55]
Sqm.. 46.00 46.00 0.00% 46.00 0.00%

15.54 Providing and laying water proofing treatment in sunken portion of


WCs ,bathroom etc., by applying Polymer modified cementous slurry
mixed with Armour cerate of M/s The Structural Water Proofing
Company Pvt. Ltd. Or Tapecrete of M/s Cico Engineer Service or Hydro
Proof of Fosroc consisting of appearing:
I) first layer of slurry of cement @ 0.488 kg/sqm mixed with Armourcrete or
Tapecrete @0.253 kg//sqm .This layer will be allowed to air cure for 4
hours
II) Second layer of slurry of cement @ .242 kg/sqm mixed with
Armourcrete or Tapecrete @ 0.126 kg/sqm This layer will be allowed to
air cure for 4 hours followed by water curing for 48 hours.
The rates includes preparation of surface treatment & sealing of all joints
,corners, junction with polymer mixed slurry. Sqm. 144.00 144.00 0.00% 144.00 0.00%
Note - Rendering /plastering as protective layer, if required will be
paid separately

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.55 Providing and laying water proofing treatment on roofs of slabs by
applying acrylic based Polymer modified cementous slurry mixed with
Armourcerete of M/s The Structural Water Proofing Company Pvt. Ltd.
Or Tapecrere of M/s Cico Engineer Service or Hydro Proof of Fosroc
consisting of appearing:
I) after surface preparation, first layer of slurry of cement @ 0.488 ‘kg/sqm
mixed with Armourcrete or Tapecrete @ 0.253 kg/sqm.
II) laying second layer of Fiber glass cloth manufactured by M/s The
Structural Water Proofing Company Pvt Ltd when the first layer is still
green . Overlaps of joints of fiber cloth should not be less than 10 cm .

III) Third layer of 1.5 mm thickness consisting of slurry of cement @ 1.289


kg/sqm mixed with Armourcrete or Tapecrete @ 0..670 kg/sqm and
coarse sand @ 1.289 kg/sqm. This will be allowed to air cure for 4
hours followed by water curing for 48 hours.
The entire treatment will be taken upto 30cm on parapet wall and tucked
into groove in parapet all around
IV) fourth and final layer of brick tiling ‘with cement mortar or any other
approved protective coarse. (which will be paid for separately) For the
purpose of measurement the entire treated surface will be measured
Sqm. 352.00 352.00 0.00% 352.00 0.00%

15.56 Providing & laying built up insulation & water proofing treatment at all
levels as per following specification and courses :
I Coarse
One coat of bituminous primer as per IS :3384 @ 0.3 liter per sqm.
II Coarse
One coat of straight run bitumen @ 1.5 kg/ sqm
III Coarse
First layer of 9mm thick expanded polyethylene sheets having density 50
kg /m3 + 5% (R-Armours or equivalent) fixed with 100 mm .wide
neoprene adhesive.
IV Coarse
One layer neoprene adhesive @ 350 ml /sqm.
V Coarse
Second layer of 9mm .thick expended polyethylene sheets having
density 50 Kg/Cum. + 5% (R-Armour or equivalent ) fixed with buttjoint
and joint further sealed with 100 mm .wide stripe of polymeric felt /EPE
fixed with neoprene adhesive .
VI Coarse
63mm. thick P.C.C 1:3:6 ( 1cement :3 sand :6 stone aggregate ) in
panels of maximum 1.2m. 1.2 m size with 24 SWG 38mm . chicken
wire mesh interposed in between ,finished smooth and sealing joints
between the panels with eleastomeric mastic as per approved
manufacturer’s specifications.
The work includes treatment of junctions of horizontal & vertical
surface ,column projections ,pedestals and all other edges, continuing
the water proofing on vertical surfaces to minimum ht. of 150 mm above
finished tiled roof surface & terminating it in groove of 50x50mm &
making good. Sqm. 816.00 816.00 0.00% 816.00 0.00%

15.57 Add extra over items of Cement Plaster / Cement Concrete flooring /
Plain or RCC work Providing and mixing admixture of synthetic Fiber
6mm / 12mm. Recron 3 S @ rate of 125gm. pack per 50 Kg. of Cement
or in the ratio of as specified by manufacture specification and direction P. Pack
of Engineer In-charges with all leads and lefts. 125gm. 52.00 52.00 0.00% 52.00 0.00%
15.58 Providing and laying a layer of acrylic polymer based single pack, cold,
brush applied liquid U.V. resistant waterproofing coating Sunroof HB of
Bitumen Co. Ltd. Tamko or Tremco in one coats over entire prepared
wall surface. A prime coat is coat is applied after diluting the Synroof HB
by 20% and second coat is applied at right angles to the prime coat and
after giving proper curing time to time prime coat.
P. Sqm. 498.00 498.00 0.00% 498.00 0.00%
Note : A Pigment of desired color can be added at site to get specific
color which shall be paid for seperately.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.59 Nano technology water proofing, thermal insulation protection
coating 12 layer process for increasing life of building and damage
control for roof.-- before coating scaling, cleaning, and preparing
surface for treatment. Opening all joint and cracks and filling them
with nano technology crack filling hydrophobic chemical with 2/3
coats. then after drying doing a PCC coat on cracks. One coat of
nano technology hydrophobic/oiliophobic primer. Nano technology
water proofing treatment in3 coats non silicon based applied with
fiber mesh sheets in medium. Nano technology thermal insulation
coating highly elasticity in nature with 3 coats with 1000 micron
width.2top coats of anti stain, anti slippery, natural transparent
high shine chemical for better life of the treatment.

Sqm 2150 1162.08 85.01% 1,220.00 4.98%

15.60 Nano technology water proofing, thermal insulation protection


coating 9 layer process for increasing life of building and damage
control protection for walls.-- before coating scaling, cleaning, and
preparing surface for treatment. Opening all joint and cracks and
filling them with nano technology crack filling hydrophobic
chemical with 2 coats. then after drying doing a PCC coat on
cracks. One coat of nano technology hydrophobic/oiliophobic
primer. Nano technology water proofing treatment in 2 coats non
silicon based thermal insulation coating highly elasticity in nature
with 2 coats with 1000 micron thickness 2 top coats of anti slippery,
natural transparent high shine chemical for better life of the
treatment.

Sqm 698 828.52 -15.75% 828.52 0.00%

15.61 Nano technology water proofing or anti stain protection coating 5-7
layer process for increasing life of all stone fascia/facades/flooring
or stone building and damage control protection, life 7-9 years,
warranty 5 years-- before coating washing of stone and degreasing
of that area is done 1 coat. (Removing of
algae/moss/blackness/stains/rust etc. is extra) then after drying
doing 1 coat of Nono technology hydrophobic prime. After this on
dry area Nano technology water proofing treatment in 3 coats wet
on wet. In case of anti stain treatment 2 top coats of anti stain, anti
slippery, natural transparent high shine or matt chemical treatment
is done.
Sqm 1157 893.08 29.55% 937.00 4.92%

15.62 Providing and Applying High Elastomeric Waterproof/High Solid


acrylic water proof chemical coating on Roof
Slabs/Terrace/Balconies/parapet wall etc. with following
method/specification Concrete must be clean and rough. All oil,
dirt, debris, paint and unsound concrete must be removed. The
final step of cleaning should be complete removal of all residues
with a vacuum cleaner or by pressure washing. In case of metal
surfaces, remove rust and contamination for better protection.
Apply primer coat of special sythetic resin based water proofing
coating 1kg with 2 -it water, by brush, roller or spray.After the
primer coat is completely dried apply two coats of special synthetic
based water proofing coating It is recommended to apply the 2nd
coat after the 1st coat is totally cured. it could be diluted up till 15-
25% for 1st coat and 10-15% for 2nd coat to make material workable
and get desired coverage. Sqm 468.00 468.00 0.00% 468.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-15
Chapter Description
Code No. Variation Proposed % Above
Analysis As per BSR on BSR Rate for with BSR
Unit Rate 2018 2018 BSR 2019 2018
15.63 Providing and Applying ACRYLIC emulsion polymer waterproofing
chemical coating, on over roof on over roof
slabs/terrace/balconies/parapet wall etc.with following
method/specification:
Paint the surface with regular paint brush so as to obtain
approximately 0.3mm thickness coating. apply the 2nd coat next
day at right angles to the 1st coat so that total thickness of the
coating should be approximately 0.6mm coverage by using above
formulation will be 40 ft2/ litre of chemical. painted surface does
not require any external water curing since chemical will hold
sufficient water for curing.After the primer coat Apply 2 coats of
modified acrylic emulsion polymer water proofing compound
having solar heat reduction properties coating @ 0.330 KG/SQM on
the surface of the interval of 3-4 hours. Undulation on the surface is
repair before the waterproofing work. Sqm 486.00 486.00 0.00% 486.00 0.00%

44781.00 44856.08 -0.17% 44021.00 -1.86%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-14
DISMANTLING AND DEMOLISHING WORK
CHAPTER : B-14
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

14.1 Demolishing lime concrete and disposal of material within 50


meter lead
P.Cum 340.00 162.00 109.88% 194.00 19.75%
14.2 Demolishing cement concrete including disposal of material
within 50 meters lead :
14.2.1 1 : 3 : 6 or richer mix P.Cum 991.00 463.00 114.04% 555.00 19.87%

14.2.2 1 : 4 : 8 or leaner mix P.Cum 607.00 285.00 112.98% 342.00 20.00%

14.3 Demolishing of RCC work including stacking of steel bars and


disposal of unserviceable material within 50 meters lead

P.Cum 1464.00 676.00 116.57% 811.00 19.97%


14.4 Denolishing of RB work including stacking of steel bars and
disposal of unserviceable material within 50 meters lead

P.Cum 1297.00 604.00 114.74% 724.00 19.87%


14.5 Extra for cutting reinforcement bars in RCC or RB work
(payment shall be made on the cross sectional area of RCC or
RB work)
P.Cum 430.00 215.00 100.00% 258.00 20.00%
14.7 Demolishing brick work including stacking of serviceable
material and disposal of unserviceable material within 50
meters lead
14.7.1 In mud mortar. P.Cum 190.00 190.00 0.00% 190.00 0.00%
14.7.2 In lime mortar. P.Cum 310.00 310.00 0.00% 310.00 0.00%
14.7.3 In cement mortar P.Cum 823.00 391.00 110.49% 469.00 19.95%
14.8 Removing mortar from bricks and cleaning bricks including
stacking within a lead of 50 meters (stacks of cleaned bricks
shall be measured)
14.8.1 From bricks work in mud mortar 1000 3201.00 1491.00 114.69% 1,789.00 19.99%
Nos.
14.8.2 From bricks work in lime mortar 1000 3721.00 1719.00 116.46% 2,062.00 19.95%
Nos.
14.8.3 From bricks work in cement mortar 1000 4685.00 2143.00 118.62% 2,571.00 19.97%
Nos.
14.9 Dismantling stone rubble masonry including stacking of
serviceable material and disposal of unserficeable material
within 50 meters leads
14.9.1 In lime mortar P.Cum 463.00 220.00 110.45% 264.00 20.00%
14.9.2 In Cement mortar P.Cum 984.00 465.00 111.61% 558.00 20.00%

14.10 Dismantling dressed stone work Ashlar face stone work, marble
work of precast concrete work including stacking of serviceable
material and disposal of unserviceable material within 50
meters leads.
14.10.1 In lime mortar P.Cum 586.00 278.00 110.79% 333.00 19.78%
14.10.2 In Cement mortar P.Cum 1153.00 545.00 111.56% 654.00 20.00%

14.11 Removing mortar from stones and cleaning stones and


concrete articles including stacking (net quantity of stacks of
cleaned materials will be measured) :
14.11.1 Lime mortar P.Cum 192.00 89.00 115.73% 106.00 19.10%
14.11.2 Cement mortar P.Cum 281.00 129.00 117.83% 154.00 19.38%

14.12 Dismantling doors, windows and clearstory windows (steel or


wood) shutters including chowkhats, architrave and holdfasts
etc. complete and stacking within 50 meters lead :

14.12.1 Of area 3 square meter and below Each 155.00 69.00 124.64% 82.00 18.84%
14.12.2 Of area beyond 3 square meter Each 212.00 94.00 125.53% 112.00 19.15%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-14
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

14.13 Taking out doors, windows and clearstory windows shutters


(steel or wood) including stacking within 50 meters lead :

14.13.1 Of area 3 square meter and below Each 61.00 27.00 125.93% 32.00 18.52%
14.13.2 Of area beyond 3 square meter Each 80.00 35.00 128.57% 42.00 20.00%

14.14 Dismantling wood work in frames, trusses, purlins and rafters


upto 10 meter span and 5m height including stacking the
material within 50m lead
14.14.1 Of sectional area 40 Sq. cm. and above P.Cum 1900.00 839.00 126.46% 1,006.00 19.90%
14.14.2 Of sectional area below 40 Sq. cm. P.Cum 8.00 3.00 166.67% 3.00 0.00%

14.15 Add extra over item No. 14.14 for dismantling trusses rafters
purlins etc. of wood work for every additional span of one meter
or part there of beyond 10 Mtr.
14.15.1 Of sectional area 40 Sq. cm. and above P.Cum 246.00 118.00 108.47% 141.00 19.49%
14.15.2 Of sectional area below 40 Sq. cm. P.Cum 0.69 0.32 115.63% 1.00 212.50%

14.16 Add extra over item No. 14.14 for dismantling trusses rafters
purlins etc. of wood work for every additional height of one
meter or part there of beyond 5 Mtr.
14.16.1 Of sectional area 40 Sq. cm. and above P.Cum 360.00 169.00 113.02% 202.00 19.53%
14.16.2 Of sectional area below 40 Sq. cm. P.Cum 1.40 0.65 115.38% 1.00 53.85%

14.17 Dismantling steel work in single sections including


dismembering and stacking within 50 meters lead in :
14.17.1 R.S. Joists P.Qtl. 143.00 64.00 123.44% 76.00 18.75%
14.17.2 Channels, angles, tees & flats P.Qtl. 96.00 44.00 118.18% 52.00 18.18%

14.18 Dismantling steel work in built-up sections in angles, tees, flats


and channels etc. including all gusset plates, bolts, nuts,
cutting, rivets, weiding etc. including dismembering and
stacking within 50 meters lead.
P.Qtl. 236.00 108.00 118.52% 129.00 19.44%
14.19 Dismantling steel work in built-up sections without
dismembering and stacking within 50 meters lead.
P.Qtl. 164.00 73.00 124.66% 87.00 19.18%
14.20 Extra for dismantling trusses, rafters, purlins etc. of steel work
for every additional span of one meter or part there of beyond
10 meters.
P.Qtl. 37.00 17.19 115.24% 20.00 16.35%
14.21 Add extra item No. 14.18 and 14.19 for dismantling trusses
rafters purlins etc. of steel work for every additional hieght of
one meter or part three of beyond 5 Mtr.
P.Qtl. 37.00 17.19 115.24% 20.00 16.35%
14.22 Extra for making of structural steel work required to be re-
erected.
P.Qtl. 201.00 88.00 128.41% 105.00 19.32%
14.23 Dismantling tile work in floors and roofs laid in cement mortar
including stacking of serviceable material and disposal of
unserviceable material within 50 meter lead :
14.23.1 For thickness of tiles 10mm to 25mm P.Sqm 30.00 13.22 126.93% 15.00 13.46%
14.23.2 For thickness of tiles, above 25mm and upto 40mm P.Sqm 47.00 21.16 122.12% 25.00 18.15%

14.24 Dismantling dry brick pitching in floors drains etc. including


stacking of serviceable material and disposal of unserviceable
material within 50 meters lead.
P.Cum 503.00 250.00 101.20% 300.00 20.00%
14.25 Dismantling brick tiles covering in terracing including stacking of
serviceable material and disposal of unserviceable material
within 50 meters lead.
P.Sqm 44.00 19.00 131.58% 22.00 15.79%
14.26 Demolishing mud phuska in terracing and disposal of
unserviceable material within 50 meters lead.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-14
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018
P.Cum 353.00 172.00 105.23% 206.00 19.77%
14.27 Dismantling stone slab flooring laid in cement mortar including
stacking of serviceable material and disposal of unserviceable
material within 50 meters lead.
P.Sqm 109.00 50.00 118.00% 60.00 20.00%
14.28 Dismantling roofing including ridges, hips, valleys and gutters
etc. and stacking the material within 50 meter lead of :

14.28.1 G.I. Sheet P.Sqm 70.00 31.00 125.81% 37.00 19.35%


14.28.2 Asbestos Sheet P.Sqm 33.00 14.54 126.96% 17.00 16.92%

14.29 Dismantling stone slab roofing over wooden karries or RCC


battens (dismantling karries and battens to be paid for
separately) including stacking of serviceable material and
disposal of unserviceable material within 50 meter lead :

P.Cum 1085.00 508.00 113.58% 609.00 19.88%


14.30 Dismantling Jack arch roofing and floors including stacking of
serviceable material and disposal of unserviceable material
within 50 meter lead.
P.Sqm 101.00 48.00 110.42% 57.00 18.75%
14.31 Dismantling tiled roofing with battens boarding etc. complete
including stacking of serviceable material and disposal of
unserviceable material within 50 meter lead.
P.Sqm 87.00 39.00 123.08% 46.00 17.95%
14.32 Dismantling thatch roofing including mats bamboos, jafries etc.
complete including stacking of serviceable material and
disposal of unserviceable material within 50 meter lead.

P.Sqm 24.00 10.00 140.00% 12.00 20.00%


14.33 Dismantling wooden ballies in posts and struts including
stacking within 50 meters lead.
P.Rmt. 8.00 3.96 102.02% 4.00 1.01%
14.34 Dismantling and stacking within 50 meters lead fencing post,
structs, including earth work dismantling of concrete etc. in
base of :
14.34.1 T or Angle Iron posts Each 37.00 37.00 0.00% 37.00 0.00%
14.34.2 R.C.C. posts. Each 70.00 70.00 0.00% 70.00 0.00%

14.35 Cutting ballies or wooden posts of fencing at the point of


projection above the concrete at ground and stacking the same
within 50 meter lead
Each 7.00 7.00 0.00% 7.00 0.00%
14.36 Dismantling barbed wire or flexible wire rope in fencing
including making rolls and stacking within 50 meter lead.
P.Qtl. 1559.00 700.00 122.71% 840.00 20.00%
14.37 Dismantling wooden trellis work excluding frames but including
stacking the serviceable material within 50 meter lead.

P.Sqm 26.00 11.00 136.36% 13.00 18.18%


14.38 Dismantling expanded metal or IRC fabric with necessary
battens and beading including stacking the serviceable material
within 50 meter lead.
P.Sqm 31.00 13.00 138.46% 15.00 15.38%
14.39 Dismantling wooden boarding in lining of walls and partitions,
excluding supporting members but including stacking the
serviceable material within 50 meter lead.
14.39.1 Upto 10mm thick P.Sqm 25.00 11.00 127.27% 13.00 18.18%
14.39.2 Thickness above 10mm upto 25mm P.Sqm 31.00 13.00 138.46% 15.00 15.38%
14.39.3 Thickness above 25mm upto 40mm P.Sqm 36.00 18.00 100.00% 21.00 16.67%

14.40 Dismantling precast concrete or stone slabs in wall partitions


walls etc. including stacking within 50 meter lead.

14.40.1 Thickness upto 40mm P.Sqm 53.00 28.00 89.29% 33.00 17.86%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-14
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018
14.40.2 Thickness above 40mm upto 75mm P.Sqm 74.30 44.00 68.86% 52.00 18.18%

14.41 Disamantling cement asbestos Celotax or other hard board


ceiling or partition walls incluidng stacking the serviceable
material and disposal of unserviceable material within 50 meter
lead.
P.Sqm 23.80 10.78 120.78% 12.00 11.32%
14.42 Dismantling CI or asbestos rain water pipe with fitting and
clamps including stacking the material within 50 meter lead :

14.42.1 75 mm to 80mm dia pipe P.Rmt. 15.10 7.70 96.10% 9.00 16.88%
14.42.2 100mm dia pipe P.Rmt. 16.80 8.62 94.90% 10.00 16.01%
14.42.3 150mm dia pipe P.Rmt. 17.70 9.08 94.93% 10.00 10.13%

14.43 Dismantling GI pipes (external work) including excavation and


refilling trenches after taking out the pipes and including
stacking of pipes within 50 meter lead :
14.43.1 15mm to 40mm nominal bore P.Rmt. 27.50 14.00 96.43% 16.00 14.29%
14.43.2 Above 40mm nominal bore P.Rmt. 32.60 19.00 71.58% 22.00 15.79%

14.44 Dismantling CI pipes including excavation and refilling trenches


after taking out the pipes, breaking lead caulked joints, melting
of lead and making into block, including stacking of pipes lead
at site within 50 meter, of dia.
14.44.1 Upto 150mm diameter P.Rmt. 126.20 62.00 103.55% 74.00 19.35%
14.44.2 Above 150mm dia. Upto 300mm dia. P.Rmt. 191.00 94.00 103.19% 112.00 19.15%
14.44.3 Above 300mm dia. P.Rmt. 283.00 142.00 99.30% 170.00 19.72%

14.45 Dismantling steel cylinder, RC pipes etc. including excavation


and refilling trenches after taking out the pipes, breaking lead
caulked joints, melting of lead and making into block including
stacking of pipes, within a lead of 50 meter

14.45.1 Upto 60mm dia P.Rmt. 283.00 142.00 99.30% 170.00 19.72%
14.45.2 Above 600mm dia P.Rmt. 710.00 353.00 101.13% 423.00 19.83%

14.46 Dismantling asbestos cement pressure pipes including


excavation and refilling trenches after taking out the pipes, and
stacking the pipe within a lead of 50 meter.
14.46.1 Upto 150mm diametre P.Rmt. 131.00 63.00 107.94% 75.00 19.05%
14.46.2 Above 150mm P.Rmt. 158.00 75.00 110.67% 90.00 20.00%

14.47 Taking out CI cover with frame from stone slab of man holes of
various sizes including dismantling of stone slab roofing and
stacking of useful materials near the site and disposal of
unserviceable materials within 50 meter lead.
Each 284.00 136.00 108.82% 163.00 19.85%
14.48 Taking out CI cover with frame from stone slab of man holes of
various sizes including dismantling of stone slab roofing and
stacking of useful materials near the site and disposal of
unserviceable materials within 50 meter lead.
Each 165.00 80.00 106.25% 96.00 20.00%
14.49 Dismantling of RCC spun vent shaft including excavating the cement
concrete pit completely, taking out the shaft, refilling the excavated
gap stacking the useful material near the site and disposal of
unserviceable materials within 50 meter lead.
Each 1919.00 900.00 113.22% 1,080.00 20.00%
14.50 Dismantling of gully chamber of various sizes incluidng CI
grating with frame including stacking of useful materials near
the site and disposal of unserviceable material within 50 meter
lead including refilling the gap.
Each 381.00 185.00 105.95% 222.00 20.00%
14.51 Dismantling of fushing cistern of any size including stacking of
useful materials near the site and disposal of unserviceable
material within 50 meter lead.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-14
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018
Each 378.00 178.00 112.36% 213.00 19.66%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-14
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018
14.52 Dismantling of CI sluice value including stacking of usefull
material within a lead of 50 meter :
14.52.1 Upto 150mm dia Each 133.00 64.00 107.81% 76.00 18.75%
14.52.2 Above 150mm dia. Each 270.00 270.00 0.00% 270.00 0.00%
14.53 Dismantling of spindle fire hydrant including stacking of useful
material within 50 meter lead.
Each 160.00 160.00 0.00% 160.00 0.00%
14.54 Dismantling old plaster or skirting, raking out joints and cleaning
the surface for plaster including disposal of rubbish to the
dumping ground within 50 meter lead.
P.Sqm 12.00 12.00 0.00% 12.00 0.00%
14.55 Dismantling of stone masonry with care including stacking of
serviceable material and disposal of unserviceable material with
in 50 mtr. Lead for :
14.55.1 Dry stone masonry P.Cum 232.00 110.00 110.91% 132.00 20.00%
14.55.2 Stone masonry in mud mortar P.Cum 253.00 119.00 112.61% 142.00 19.33%

14.56 Dismantling of flooring with care including stacking of


serviceable material and disposal of unserviceable material with
in 50 mtr. Lead for :
14.56.1 Lime concrete flooring upto 15cm thick P.Sqm 67.00 31.00 116.13% 37.00 19.35%

14.56.2 Lime concrete upto 15cm thick(foundation) P.Cum 225.00 225.00 0.00% 225.00 0.00%
14.56.3 Cement concrete flooring P.Sqm 109.00 50.00 118.00% 60.00 20.00%

14.57 Dismantling roofs with care incluidng stacking of serviceable


material and disposal of unserviceable material with in 50 mtr.
Lead for :
14.57.1 Lime terrace P.Sqm 72.00 33.00 118.18% 39.00 18.18%
14.57.2 Stone slab roofing complete with lime dhar and kharanja P.Sqm 771.00 354.00 117.80% 424.00 19.77%

14.58 Dismantling chajja and shelves with care including making


jhiries and making good :
14.58.1 Katla Chajja P.Sqm 72.00 29.00 148.28% 34.00 17.24%
14.58.2 Marble shelves P.Sqm 201.00 86.00 133.72% 103.00 19.77%
14.58.3 RCC shelves P.Sqm 176.00 75.00 134.67% 90.00 20.00%
14.58.4 Stone shelves P.Sqm 176.00 75.00 134.67% 90.00 20.00%
14.58.5 RCC Chajja P.Sqm 55.00 55.00 0.00% 55.00 0.00%
14.59 Dismnantling CC jali including cost of making grooves in plaster
and making good.
P.Sqm 70.00 67.00 4.48% 70.00 4.48%
14.60 Dismantling marble dado, sides of pillars etc. with care.
P.Sqm 75.00 75.00 0.00% 75.00 0.00%
14.61 Dismantling aluminium / Gypsum partitions, doors, windows,
fixed glazing and false ceiling including disposal for
unserviceable material and stacking of serviceable material with
in 50 meters lead as directed by Engineer in charge

P.Sqm 14.00 14.00 0.00% 14.00 0.00%


14.62 Add extra for all type of dismantling work for each subsequent
storey or height more than 4.5m:

14.62.1 Rate in each. Each 20% 20.00% 20.00%

14.62.2 Rate in Sqm. P.Sqm 20% 20.00% 20.00%

14.62.3 Rate in Cum. P.Cum 20% 20.00% 20.00%

14.62.4 Rate in Mtr. P.Rmt. 20% 20.00% 20.00%

14.62.5 Rate in Qtl. P. Qtl. 20% 20.00% 20.00%


38386.09 18657.41 105.74% 22057.00 18.22%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-13

REPAIRS TO BUILDINGS
CHAPTER : B-13
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018
13.1 Repair to stone masonry in cement sand mortar 1 : 6 with old Sqm 347.00 207.00 67.63% 248.00 19.81%
and new stone
13.2 Taking out decayed bricks from wall and replacing with new
ones set in :
13.2.1 Lime surkhi / sand mortar 1:2 Sqm 424.00 266.00 59.40% 319.00 19.92%
13.2.2 Cement sand mortar 1 : 6 Sqm 455.00 282.00 61.35% 338.00 19.86%
13.3 Repair to lime plaster in patches including removal of old Sqm 223.00 133.00 67.67% 159.00 19.55%
plaster in regular shape and white or colour washing
13.4 Repair to cement plaster in cement mortar 1 : 6 (1 cement : 6 Sqm 266.00 146.00 82.19% 175.00 19.86%
fine sand) including removal of old plaster in regular shape and
white or colour washing
13.5 Filling expansion joint with bitumen filler in plain or Reinforced Mtr. 34.00 31.00 9.68% 34.00 9.68%
cement concrete 25mm width & 25mm deep
13.6 Crack filling in masaladar lime cement with water proofing Mtr. 16.00 6.00 166.67% 7.00 16.67%
compound including jhiri
13.7 Cutting jhiri (recess) below 75mmx75mm in wall etc. and Mtr. 67.00 31.00 116.13% 37.00 19.35%
making good
13.8 Cutting jhiri above 75mm x 75mm and below 150x150mm etc. Mtr. 105.00 49.00 114.29% 58.00 18.37%
and making good
13.9 Scraping old surface and redoing lime loi or sandla Sqm 54.00 32.00 68.75% 38.00 18.75%
13.10 Lime plaster 1 : 2 under old stone slab with ad-mixture of gugal
gur. Etc.in three coats including dressing cutting of joints of
slab complete :
13.10.1 Proofing upto 25mm thickness Sqm 208.00 133.00 56.39% 159.00 19.55%
13.10.2 Proofing above 25mm & upto 60mm thickness Sqm 364.00 241.00 51.04% 289.00 19.92%
13.11 Cement plaster 1 : 3 under old stone slabs with ad-mixture
(gur, nails, binding wire to mesh and scraping scales &
dressing joints of slabs complete.
13.11.1 Proofing upto 25mm thickness Sqm 289.00 212.00 36.32% 254.00 19.81%
13.11.2 Proofing above 25mm & upto 60mm thickness Sqm 466.00 368.00 26.63% 441.00 19.84%
13.12 Patch repair to cement concrete floor including digging out old Sqm 317.00 238.00 33.19% 285.00 19.75%
floor in regular shape and removal of rubbish curing etc.
complete in all respects.
13.13 Washing floor with soda soap or other cleaning material Sqm 2.40 1.00 140.00% 2.00 100.00%
13.14 Removal and refixing stone chhajja 50 to 75mm thick including Sqm 217.00 108.00 100.93% 129.00 19.44%
finishing, complete in all respects
13.15 Making opening in masonary wall including dismantling, fixing Sqm 498.00 262.00 90.08% 314.00 19.85%
lintel / beam and making good the damages to wall and floor
complete to match the existing surface including proping the
existing structue above the opening excluding cost of lintel /
beam etc.

13.16 Add extra item no. 13.15 for fixing of door / window frames Sqm 181.00 100.00 81.00% 120.00 20.00%
(Chowkhats or steel windows) in the opening including fixing
hold fast in cement concrete 1:3:6 (1 cement : 3 coarse sand :
6 stone grit 20mm nominal grade) excluding the cost of frame
or steel windows.
13.17 Renewing glass panes, with putty and nails wherever
necessary :
13.17.1 4mm thick plain glass panes Sqm 651.00 589.00 10.53% 651.00 10.53%
13.17.2 5.5mm thick plain glass panes Sqm 857.00 791.00 8.34% 857.00 8.34%
13.18 Renewing glass panes with wooden fillets wherever necessary

13.18.1 4mm thick plain glass panes Sqm 918.00 736.00 24.73% 883.00 19.97%
13.18.2 5.5mm thick plain glass panes Sqm 627.00 627.00 0.00% 627.00 0.00%
13.19 Renewing glass planes and refixing existing wooden fillets :

13.19.1 4mm thick plain glass panes Sqm 550.00 550.00 0.00% 550.00 0.00%
13.19.2 5.5mm thick plain glass panes Sqm 650.00 650.00 0.00% 650.00 0.00%
13.20 Refixingold glass panes with putty and nails Sqm 177.00 98.00 80.61% 117.00 19.39%
13.21 Fixing old glass panes with wooden fillets (Excluding cost of Sqm 155.00 71.00 118.31% 85.00 19.72%
fillets)

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-13
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018
13.22 Providing and fixing 16mm MS Fan clamps of standard shape
and size in RCC slab / stone slab roofing including cutting
chase and making good and painting exposed portion of the
clamps complete :
13.22.1 In existing roof Each 172.00 101.00 70.30% 121.00 19.80%
13.22.2 In new roof Each 125.00 102.00 22.55% 122.00 19.61%
13.23 Replacing broken roofing slab in patches incluidng lime terrace, Sqm 1927.00 1537.00 25.37% 1,844.00 19.97%
ceiling plaster etc. including removal of broken slabs.

13.24 Cutting jhiri for fixing slab and making good. Mtr. 128.00 65.00 96.92% 78.00 20.00%
13.25 Providing & fixing 25mm x 25mm angle iron upto 450mm long Each 92.00 80.00 15.00% 92.00 15.00%
fixed in CM 1 : 3 including cutting holes in walls and ceiling
making good the same complete as per design.
13.26 Making holes in stone masonry wall upto 450mm x 450mm size Each 196.00 112.00 75.00% 134.00 19.64%
and making good in CM 1:6
13.27 Punching holes in flat bars in :
13.27.1 Below 15mm size Each 6.00 2.00 200.00% 2.00 0.00%
13.27.2 Above 15mm size Each 11.00 4.00 175.00% 4.00 0.00%
13.28 Guniting damaged RCC slab beams and columns for Sqm 2066.00 1764.00 17.12% 2,066.00 17.12%
strengthening with cement sand mortar 1 : 2 (1 cement : 2
sand) including preparing the surface, making "V" shaped
joints, cleaning the reinforcement bars with jet of potable water
and drying with compressed air, including cost of centering and
shuttering and finishing to match the existing surface etc.
complete including provided MS welded mesh to gauge 25mm
x 25mm framing with average thickness of 25mm

13.29 Chopping loose and cracked concrete to required depth,


cleaning the exposed surface of steel and concrete with wire
brush and sand blasting, cleaning with a jet of water / air as
necessary and getting it dried with compressed air including all
scaffolding :

13.29.1 Depth upto 25mm Sqm 110.00 72.00 52.78% 86.00 19.44%
13.29.2 Depth 25mm to 50mm Sqm 221.00 144.00 53.47% 172.00 19.44%
13.29.3 Depth 50mm to 75mm Sqm 331.00 217.00 52.53% 260.00 19.82%
13.29.4 Depth 75mm to 100mm Sqm 449.00 293.00 53.24% 351.00 19.80%
13.30 Grinding by (60/80/120/360) including cost of polishing
complete :
13.30.1 1 Course (60 No. Carborundum stone) Sqm 66.00 66.00 0.00% 66.00 0.00%
13.30.2 1 Course (80 No. Carborundum stone) Sqm 26.00 26.00 0.00% 26.00 0.00%
13.30.3 1 Course (120 No. Carborundum stone) Sqm 13.00 13.00 0.00% 13.00 0.00%
13.30.4 1 Course (360 No. Carborundum stone) and polishing complete Sqm 18.00 18.00 0.00% 18.00 0.00%

13.31 Add extra for mirror polishing on marble work / stone work Sqm 65.00 65.00 0.00% 65.00 0.00%
where ever required to give high gloss finish complete.

13.32 Add extra over item if external scaffolding to be used for repair
works
50% 50%
13.33 Providing and fixing of Aluminium at extruded corners of walls
of size 50x50x5mm including drilling, holes in tiles/ stone and
putting wooden/ PVC rawl plug of required size and counter
sunk steel screw at @300mm etc. on both baces of angles,
including grinding and smoothening of cut edges with all lead
and lift complete in all respect asper direction of Engineer-in-
charge.

P.Rmt. 670.00 670.00 0.00% 670.00 0.00%


13.34 Labour charges for removing and refixing aluminium
partitions/door including minor repair and alteration in the
same.
P.Sqm 518.00 518.00 0.00% 518.00 0.00%
13.34 Labour charges for removing and refixing aluminium
partitions/door including minor repair and alteration in the
same.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER : B-13
Chapter Description Variation Proposed % Above
Code No. Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018
P.Sqm 518.00 518.00 0.00% 518.00 0.00%
13.35 Repair of door, window shutters including cost of material
and labour for change of damaged :
(a) Style / rail of teak wood 30mm thick/ Aluminium Section

(i) 4"wide P.Rmt. 335.00 335.00 0.00% 335.00 0.00%

(ii) 6" wide P.Rmt. 457.00 457.00 0.00% 457.00 0.00%

(b) Panel by

(i) Shuttering Ply - 9mm thick (Commercial) P.Sqm 782.00 782.00 0.00% 782.00 0.00%

(ii) Wire Gauge 14 mesh x 24 gauge P.Sqm 670.00 670.00 0.00% 670.00 0.00%

(iii) Plain Glass Panes 4mm thick P.Sqm 558.00 558.00 0.00% 558.00 0.00%

(c) Aldrop of mild Steel

(i) 12" long x12mm dia Each 193.00 193.00 0.00% 193.00 0.00%

(ii) 8" long x 10mm dia Each 137.00 137.00 0.00% 137.00 0.00%

(d) Stopper of Aluminium with

(i) Single Rubber Gutka Each 43.00 43.00 0.00% 43.00 0.00%

(ii) Double Rubber Gutka Each 61.00 61.00 0.00% 61.00 0.00%

(e) Door Springs of mild Steel Each 203.00 203.00 0.00% 203.00 0.00%

(f) Steel Hinges

(i) For Wooden Chowkhat 3" size. Each 30.00 30.00 0.00% 30.00 0.00%

(ii) For Wooden Chowkhat 4" size Each 45.00 45.00 0.00% 45.00 0.00%

(iii) For Stone Chowkhat ,4"size Each 38.00 38.00 0.00% 38.00 0.00%

(g) Mild Steel Tower Bolt 6" long Each 51.00 51.00 0.00% 51.00 0.00%

(h) Steel Locking Bolt Each 67.00 67.00 0.00% 67.00 0.00%

(i) Steel Handle 6" size Each 30.00 30.00 0.00% 30.00 0.00%

13.36 Labour charges for repair to door / window without using any
material such as applying randha (finishing) tightening of bolts
& screw etc.
P.Sqm 175.00 175.00 0.00% 175.00 0.00%
13.37 Repairing/ replacement of defective parts for door/ windows
with material, dry cleaning and refixing of vanishing blinds as
per direction of Engineer In Charge
P.Sqm 482.00 482.00 0.00% 482.00 0.00%
13.38 Making of hole in R.C.C. slab/wall/beams and masonary wall
(width up to 450 mm) by core cutting machine complete as per
direction of EI

13.38.1 From diameter 100mm to 150mm Nos 1051.00 1027.00 2.34% 1,051.00 2.34%

13.38.2 Diameter above 150mm Nos 1581.00 1544.00 2.40% 1,581.00 2.40%

21203.90 17702.00 19.78% 19409.50 9.65%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
FINISHING WORK
NOTE:
1- The rates are for complete work including racking of joints, curing, grinding, mixing
2- and finishing
The rates coverT &protection
P and scaffolding material
of all places and cost
and things, of material
requiring with alland
protection leadcleaning
and lift
upto floor
such three
places andlevels.
thing of all droppings and splashes of mortar etc.

3- Deduct 10% of the cost of lime mortar if gharat or mortar mill is not used for grinding.

4- Cement mortar is to be made by mechnical mixer only.

CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.1 Lime plaster on New surface on walls with lime surkhi mortar 1:2
(1 lime putty : 2 surkhi) including raking of joints, curing etc.
complete :
12.1.1 25 mm thick in 3 coats P.Sqm 213.00 134.00 58.96% 160.00 19.40%
12.1.2 20mm thick in 2 coats P.Sqm 176.00 109.00 61.47% 130.00 19.27%
12.1.3 12 mm thick in one coat P.Sqm 142.00 88.00 61.36% 105.00 19.32%
12.1.4 Add extra over item no. 12.1 for using admixture like Gur, Methi
& Gugal @ 1.0 Kg./each for every 10 Sqm of area including
racking of joints curing etc. complete
P.Sqm 90.00 90.00 0.00% 90.00 0.00%
12.2 Lime plaster on New surface on walls with lime sand mortar 1:2
(1 lime putty : 2 sand) including raking of joints, curing etc.
complete :

12.2.1 25 mm thick in 3 coats P.Sqm 240.00 144.00 66.67% 172.00 19.44%


12.2.2 20mm thick in 2 coats P.Sqm 176.00 109.00 61.47% 130.00 19.27%
12.2.3 12 mm thick in one coat P.Sqm 142.00 88.00 61.36% 105.00 19.32%

12.3 Lime plaster on New surface on walls with lime sand, surkhi
mortar 1:1:1 (1 lime putty : 1 sand : 1surkhi) including raking of
joints, curing etc. complete :
12.3.1 25 mm thick in 2.5 coats P.Sqm 229.00 142.00 61.27% 170.00 19.72%
12.3.2 20mm thick in 2 coats P.Sqm 185.00 112.00 65.18% 134.00 19.64%
12.3.3 12 mm thick in one coat P.Sqm 142.00 88.00 61.36% 105.00 19.32%
12.4 Araish plaster (1 lime puttly : 2 jhingra) over lime plaster back
ground
12.4.1 Add extra if colour is used P.Sqm 360.00 169.00 113.02% 202.00 19.53%
12.5 Applying Birla / JK white cement based putty over cement
plaster surface for making even surface.
P.Sqm 120.00 120.00 0.00% 120.00 0.00%
12.6 Applying plaster of Paris over cement plasper surface for
making even surface
P.Sqm 200.00 110.00 81.82% 132.00 20.00%
12.6 (A) Providing & laying POP moulding & beading in celling including
nalling & scaffolding etc. complete of size
(a) 25mm x 12 mm P.Rmt. 55.00 55.00 0.00% 55.00 0.00%
(b) 25mm x 25mm P.Rmt. 65.00 63.00 3.17% 65.00 3.17%
12.6 (B) Providing & laying POP Cornice of required design & pattern in
ceiling including nailing & scaffolding etc. complete with fine
finishing of size :
(a) 50mm x 50mm P.Rmt. 55.00 55.00 0.00% 55.00 0.00%
(b) 65mm x 65mm P.Rmt. 65.00 65.00 0.00% 65.00 0.00%
( c) 75mm x 75mm P.Rmt. 75.00 75.00 0.00% 75.00 0.00%
Cement Plaster
12.7 Plaster on new surface on wall in cement sand mortar 1:3
including raking of joints etc. complete fine finish :
12.7.1 25mm thick P.Sqm 274.00 216.00 26.85% 259.00 19.91%
12.7.2 20mm thick P.Sqm 212.00 169.00 25.44% 202.00 19.53%
12.7.3 12 mm thick P.Sqm 178.00 144.00 23.61% 172.00 19.44%
12.8 Plaster on new surface on walls in cement sand mortar 1:4
including raking of joints etc. complete fine finish
12.8.1 25mm thick P.Sqm 269.00 212.00 26.89% 254.00 19.81%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.8.2 20 mm thick P.Sqm 234.00 187.00 25.13% 224.00 19.79%


12.8.3 12 mm thick P.Sqm 166.00 133.00 24.81% 159.00 19.55%

12.9 Plaster on new surface on walls in cement sand mortar 1:6


including raking of joints etc. complete fine finished :-
12.9.1 25mm thick P.Sqm 247.00 192.00 28.65% 230.00 19.79%
12.9.2 20 mm thick P.Sqm 190.00 151.00 25.83% 181.00 19.87%
12.9.3 12 mm thick P.Sqm 153.00 121.00 26.45% 145.00 19.83%

12.10 Plaster on new surface on walls in cement sand mortar 1:8


including raking of joints etc. complete fine finished :-
12.10.1 25mm thick P.Sqm 235.00 181.00 29.83% 217.00 19.89%
12.10.2 20mm thick P.Sqm 191.00 143.00 33.57% 171.00 19.58%
12.10.3 12mm thick P.Sqm 162.00 116.00 39.66% 139.00 19.83%

12.11 Cement lime plaster on new surface on walls in cement : Lime


putty : sand mortar 1:1:6 including raking of joints etc. complete
fine finished :-
12.11.1 25mm thick P.Sqm 338.00 200.00 69.00% 240.00 20.00%
12.11.2 20mm thick P.Sqm 268.00 159.00 68.55% 190.00 19.50%
12.11.3 12 mm thick P.Sqm 153.00 92.00 66.30% 110.00 19.57%

12.12 Cement lime plaster on new surface on walls in cement : Lime


putty : sand mortar 1:2:9 including raking of joints etc. complete
fine finished :-
12.12.1 25mm thick P.Sqm 290.00 177.00 63.84% 212.00 19.77%
12.12.2 20mm thick P.Sqm 263.00 151.00 74.17% 181.00 19.87%
12.12.3 12 mm thick P.Sqm 153.00 92.00 66.30% 110.00 19.57%
12.13 Add extra over item No. 12.7 to 12.10 for water proofing
compound if used @ 2% of the cement by weight.
P.Sqm 149.00 79.00 88.61% 94.00 18.99%
12.14 Add extra over item no. 12.1 to 12.12 for repairs to plaster
including cutting the patch in a uniform shape, racking preparing
surface of wall, complete in all respect.
P.Sqm 22.00 10.00 120.00% 12.00 20.00%
12.15 Finishing with neat cement (punning)
P.Sqm 33.00 20.00 65.00% 24.00 20.00%
12.16 Fine finishing cost of cement plaster sandla with cement, marble
powder (passing through IS sieve 10) and lime mix 1:1:6 per
specification upto 4mm thick
P.Sqm 49.00 28.00 75.00% 33.00 17.86%
12.17 Deduct over item No. 12.8 to 12.12 if sandla is to be done on
top surface.
P.Sqm 5.00 5.00 0.00% 5.00 0.00%
12.18 Add extra item no. 12.1 to 12.12 for plaster done over ceiling

P.Sqm 20% 20%


12.19 Add extra over item no. 12.1 to 12.12 for plaster over spherical
or groin ceiling.
P.Sqm 25% 25%
12.20 Making grooves as per design in plaster 10mm to 20mm wide

12.20.2 Making of drip course (Tapka) in cement sand mortar 1:6 width
upto 40 mm and 10 mm thick as per approved design

P.Rmt. 8.50 4.00 112.50% 4.00 0.00%


12.21 Making lining out on plaster to imitate stone or concrete block
walling
P.Sqm 45.00 21.00 114.29% 25.00 19.05%
12.22 6 mm thick cement plaster to ceiling of mix 1:3 (1cement : 3-
fine sand)
P.Sqm 167.00 130.00 28.46% 156.00 20.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.23 6mm thick cement plaster 1:3 ( 1cement : 3fine sand) finished
with a floating coat of neat cement and thick coat of Lime wash
on top of walls when dry for bearing of R.C.C slabs and beams.

P.Sqm 95.00 95.00 0.00% 95.00 0.00%


MISCELLANEOUS
12.24 Ornamental lime plaster in lime surkhi mortar 1:2 making
Kangooras etc. as per Jaipur practice.
P.Sqm 516.00 426.00 21.13% 511.00 19.95%

12.25 Ornamental cement plaster in cement sand mortar 1:4,


making Kangooras etc. as per Jaipur practice.
P.Sqm 575.00 575.00 0.00% 575.00 0.00%
12.26 Making gola below Kangooras in cement sand mortar 1:3 as per
approved design .
P.Sqm 175.00 175.00 0.00% 175.00 0.00%
12.27 Mud plaster with cow dung finishing on old surface
P.Sqm 35.00 18.00 94.44% 21.00 16.67%
12.28 20mm to 25mm thick non-crodable and water proof mud plaster
using 1.8kg of wheat straw (Bhusa) and 1.8kg of cut back per
Cubic feet of mud over thatched roof including scaling of Cracks
etc. complete in all respect.
P.Sqm 124.00 102.00 21.57% 122.00 19.61%
12.29 Add extra over item no. 12.1 to 12.12 for plaster work on
exterior wall of height more than 4.5m from plinth level of every
additional height of 4.5 Mtr. Or part thereof.
P.Sqm 10% 10.00%
12.30 Add extra for plastering on circular work not exceeding 6 mtr. In
radius
P.Sqm 10% 10.00%

12.31 Add extra for plaster work for providing 12mm thick bend upto
30cm wide in cement sand mortar 1:4
12.31.1 Flush band P.Sqm 124.00 57.00 117.54% 68.00 19.30%

12.31.2 Sunk band P.Sqm 151.00 71.00 112.68% 85.00 19.72%

12.31.3 Moulded band P.Sqm 186.00 121.00 53.72% 145.00 19.83%

ROUGH CAST PLASTER


12.32 Rough cast plaster with a mixture of sand and gravel or crushed
stone 2.36mm to 12.5mm nominal size dashed over and
including the fresh plaster in two layer, under layers of 12mm
thick cement plaster and top layer 10mm thick of CM 1:4
(1cement :4 sand) mixed with 10% finally grounded hydrated
lime by volume of cement :

12.32.1 Under layer of 12mm thick cement plaster done in cement sand
mortar 1:4 (1 cement : 4 sand)
(a) Ordinary cement finish using ordinary cement P.Sqm 358.00 240.00 49.17% 288.00 20.00%
(b) Dark coloured finish using ordinary cement and required P.Sqm 415.00 300.00 38.33% 360.00 20.00%
pigments
(c) Light coloured finish using white cement and required pigments P.Sqm 463.00 363.00 27.55% 435.00 19.83%

12.32.2 Under layer of 12mm thick cement plaster done in cement sand
mortar 1:3 (1 cement : 3 sand)
(a) Ordinary cement finish using ordinary cement P.Sqm 368.00 249.00 47.79% 298.00 19.68%
(b) Dark coloured finish using ordinary cement and required P.Sqm 419.00 304.00 37.83% 364.00 19.74%
pigments
(c ) Light coloured finish using white cement and required pigments P.Sqm 467.00 368.00 26.90% 441.00 19.84%

SUPERIOR PLASTER

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.33 Add extra over item No. 12.32 for plaster with a mixture of
washed pebbles of crushed stone 5mm to 12.5mm nominal size
instead of gravel or crushed stone etc.
P.Sqm 23.00 23.00 0.00% 23.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.34 Decorative plaster work with spectrum textured coating as per


approved colour and shade complete as per manufacturers
specifications.

12.34.1 Roller Finish.


P.Sqm 125.00 125.00 0.00% 125.00 0.00%

12.34.2 Trowel Finish (1 to 1.5mm thick). P.Sqm 210.00 210.00 0.00% 210.00 0.00%

12.34.3 Granular Finishing P.Sqm 185.00 185.00 0.00% 185.00 0.00%

12.34.4 Grit Textured @ 2.5 to 3.0mm thick. P.Sqm 330.00 330.00 0.00% 330.00 0.00%

12.34.5 PERKY-TEXTURED - (Brush Finish) av. thickness 152 to 200 P.Sqm 95.00 95.00 0.00% 95.00 0.00%
microns.

12.34.6 PERKY-FINE TEXTURED- (Roller Finish) av. thickness 400 to P.Sqm 138.00 138.00 0.00% 138.00 0.00%
500 microns.

12.34.7 AMBROSIA TEXTURED- (Spray Finish) av. thickness 200 to P.Sqm 240.00 240.00 0.00% 240.00 0.00%
1000 microns.
12.34.8 ORNATA TEXTURED- (Trowel Finish) av. thickness 1200 to P.Sqm 275.00 275.00 0.00% 275.00 0.00%
1500 microns.

12.34.9 WALJWELS TEXTURED- (Trowel Finish) av. thickness 1000 to P.Sqm 240.00 240.00 0.00% 240.00 0.00%
1500 microns.

12.34.10 PADRON TEXTURED- (Trowel Finish) av. thickness 1500 to P.Sqm 300.00 300.00 0.00% 300.00 0.00%
2000 microns.

12.34.11 PLACTION TEXTURED- (Trowel Finish) av. thickness 1500 to P.Sqm 325.00 325.00 0.00% 325.00 0.00%
2000 microns.

12.34.12 FLAKES TEXTURED- (Trowel Finish) av. thickness 800 to 1000 P.Sqm 400.00 400.00 0.00% 400.00 0.00%
microns.

POINTING
12.35 Pointing on stone masonry in lime sand mortar 1:2 (Lime putty :
2 sand)

12.35.1 Flush or ruled pointing P.Sqm 48.00 24.00 100.00% 28.00 16.67%
12.35.2 Sunk or weather struck pointing P.Sqm 58.00 28.00 107.14% 33.00 17.86%
12.35.3 Raised and cut pointing P.Sqm 57.00 31.00 83.87% 37.00 19.35%
12.35.4 Deep grooved pointing. P.Sqm 42.00 42.00 0.00% 42.00 0.00%
12.35.5 Add extra for using Kara mortar instead of lime sand mortar 1:2 P.Sqm 12.00 9.00 33.33% 10.00 11.11%

12.36 Pointing on stone masonry in cement sand mortar 1:3 (1 cement


: 3 sand)
12.36.1 Flush or ruled pointing P.Sqm 81.00 44.00 84.09% 52.00 18.18%
12.36.2 Sunk or weather struck pointing. P.Sqm 90.00 90.00 0.00% 90.00 0.00%
12.36.3 Raised and cut pointing P.Sqm 158.00 83.00 90.36% 99.00 19.28%
12.36.4 Deep grooved pointing. P.Sqm 100.00 100.00 0.00% 100.00 0.00%
12.37 Pointing on brick or tile masonry in lime sand mortar 1:2 (1 lime
putty : 2 sand)

12.37.1 Flush or ruled pointing P.Sqm 83.00 46.00 80.43% 55.00 19.57%
12.37.2 Sunk or weather struck pointing P.Sqm 85.00 47.00 80.85% 56.00 19.15%
12.37.3 Raised and cut pointing. P.Sqm 70.00 70.00 0.00% 70.00 0.00%

12.38 Pointing on brick or title masonry in cement sand mortar 1:3 (1


cement : 3 sand)
12.38.1 Flush or ruled pointing P.Sqm 56.00 33.00 69.70% 39.00 18.18%

12.38.2 Sunk or weather struck pointing P.Sqm 69.00 39.00 76.92% 46.00 17.95%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.38.3 Raised and cut pointing. P.Sqm 80.00 80.00 0.00% 80.00 0.00%
12.39 Pointing on stone slab ceiling with cement mortar 1:3 (1 cement
: 3 sand)

12.39.1 Flush pointing P.Sqm 71.00 41.00 73.17% 49.00 19.51%


12.39.2 Raised pointing. P.Sqm 80.00 80.00 0.00% 80.00 0.00%

12.40 Add extra item no. 12.35 to 12.39 on exterior walls of height
more than 4.5m from plinth level for every additional height of
4.5m or part thereof
P.Sqm 10% 10%

12.41 Add extra for colour/pigment of approved shade added in mortar


for all type of pointing with lime/cement on all type of masonry.

P.Sqm 16.00 16.00 0.00% 16.00 0.00%

12.42 Deduct if curing not to be done by contractor and the same is to


be done by department for plaster / pointing.
10% 10.00%

12.43 Deduct if plaster is not done in required number of coats.


20% 20.00%

WHITE WASHING COLOUR WASHING


12.44 White washing with lime to give an even shade including all
scaffolding :

12.44.1 New work (three or more coats) P.Sqm 16.30 9.00 81.11% 10.00 11.11%
12.44.2 Old work (two or more coats) including scrapping old surface P.Sqm 9.50 6.00 58.33% 7.00 16.67%
and repairing with whiting where ever necessary
12.44.3 Old work (one or more coats) including scrapping old surface P.Sqm 5.70 3.00 90.00% 3.00 0.00%
and repairing with whiting where ever necessary
12.45 Satna lime wash on wall one coat (or more coats) including
scrapping old surface and repairing with whiting where ever
necessary
P.Sqm 8.30 6.00 38.33% 7.00 16.67%
12.46 White washing with whiting to give an even shade including all
scaffolding :
12.46.1 New work (three or more coats) P.Sqm 15.60 8.00 95.00% 9.00 12.50%
12.46.2 Old work (two or more coats) including scrapping old surface P.Sqm 9.10 5.00 82.00% 6.00 20.00%
and repairing where ever necessary
12.46.3 Old work One or more coats) including scrapping old surface P.Sqm 5.50 3.00 83.33% 3.00 0.00%
and repairing where ever necessary
12.47 Colour washing of all shades to give an even shade including all
scaffolding :
12.47.1 New work (two or more coats) with a base coat to white washing P.Sqm 21.00 11.00 90.91% 13.00 18.18%
with lime.
12.47.2 New work (two or more coats) with a base coat of whiting. P.Sqm 21.60 12.00 80.00% 14.00 16.67%
12.47.3 Old work (one or more coats) with whiting with a base coat of P.Sqm 12.70 7.00 81.43% 8.00 14.29%
white washing including scrapping old surface.
12.47.4 Old work (two or more coats) with whiting with a base coat of P.Sqm 12.20 6.00 103.33% 7.00 16.67%
white washing including scrapping surface.

12.47.5 Old work (one or more coats) with lime including scrapping P.Sqm 7.20 4.00 80.00% 4.00 0.00%
surface.
12.47.6 Old work (one or more coats) with whiting including scrapping P.Sqm 7.30 4.00 82.50% 4.00 0.00%
surface.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.48 Removing white or colour wash by scrapping and sand papering


and preparing the surface smooth including necessary repairs to
scratches by sandla/loi. (only for colour changing only).

P.Sqm 7.60 4.00 90.00% 4.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

DISTEMPER
12.49 Distempering with dry distemper of approved brand and shade
(two or more coats) and of required shade on new work, over
and including, priming coat of whiting to given and even shade
including all scaffolding.
P.Sqm 58.00 29.00 100.00% 34.00 17.24%

12.50 Distempering with dry distemper of approved brand and


manufacture shade on old work to give an even shade including
all scaffolding and scrapping and necessary repairs complete.

12.50.1 Colour change P.Sqm 19.00 19.00 0.00% 19.00 0.00%


12.50.2 Same Colour P.Sqm 12.50 12.00 4.17% 12.00 0.00%

12.51 Distempering with oil bound washable distemper of approved


brand and manufacture to give an even shade including all
scaffolding :

12.51.1 New work (two or more coats) over and including scrapping and P.Sqm 100.00 56.00 78.57% 67.00 19.64%
priming coat with cement primer
12.51.2 old work (one or more coats) including scrapping surface and
necessary repairs.
(a) Colour Change P.Sqm 28.00 18.00 55.56% 21.00 16.67%
(b) Same Colour P.Sqm 14.00 14.00 0.00% 14.00 0.00%

12.52 Applying one coat of primer of approved brand and manufacture


on wall surface including all scaffolding. (new surface) :

12.52.1 Cement primer (on new surface) P.Sqm 32.00 19.00 68.42% 22.00 15.79%

CEMENT PAINT
12.53 Finishing wall with water proofing cement paint of approved
brand and manufacture and or required shade to give an even
shade including all scaffolding :

12.53.1 New work (Three or more coats) P.Sqm 99.00 62.00 59.68% 74.00 19.35%
12.53.2 old work (one or more coats) P.Sqm 50.00 28.00 78.57% 33.00 17.86%

12.54 Removing dry or oil bound distemper by scrapping sand


papering and preparing surface smooth including necessary
repairs to scratches by sandla/loi and all scaffolding (for colour
changing only)

P.Sqm 9.56 5.00 91.20% 6.00 20.00%

PAINTING AND VARNISHING


NOTE : The rates are for approved quality make paints confirming to I.S.
127-106, 341 and 340
12.55 Applying priming coat :

12.55.1 With ready mix pink or gray primer of approved brand and P.Sqm 31.00 25.00 24.00% 30.00 20.00%
manufacture on wood work hard and soft wood.
12.55.2 With ready mix Aluminium primer of approved brand and P.Sqm 30.00 24.00 25.00% 28.00 16.67%
manufacture on resinous wood and plywood
12.55.3 With ready mix Zink Chromate yellow primer of approved brand P.Sqm 38.00 21.00 80.95% 25.00 19.05%
and manufacture on steel galvanized iron/steel wire.

12.56 Painting with ready paint of approved brand and manufacture in


all shades to given an even shade :

12.56.1 New steel work (two or more coats) P.Sqm 33.00 33.00 0.00% 33.00 0.00%
12.56.2 New wood work (two or more coats) P.Sqm 45.00 45.00 0.00% 45.00 0.00%
12.56.3 old steel work (one or more coats) P.Sqm 48.00 30.00 60.00% 36.00 20.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.56.4 old wood work (one or more coats) P.Sqm 48.00 30.00 60.00% 36.00 20.00%

12.57 Painting one thin coat with lead of approved brand and
manufacture on wet or patchy portion of plastered surfaces
P.Sqm 117.00 89.00 31.46% 106.00 19.10%
12.58 Painting on GI sheet with ready mixed paint of approved brand
and manufacture to give an even shade :
12.58.1 New work (Two or more coats) P.Sqm 66.00 40.00 65.00% 48.00 20.00%
12.58.2 Old work (one or more coats) white grey and green shade. P.Sqm 43.00 26.00 65.38% 31.00 19.23%

12.59 Painting (two or more coats) on rain water soil, waste and vent
pipes and fitting with black anticorrosive bitumastic paint of
approved brand and manufacture over and including a priming
coat of ready mixed zinc chromate yellow on new work :

12.59.1 50mm dia. Pipes P.Rmt. 23.00 13.00 76.92% 15.00 15.38%
12.59.2 75mm dia. Pipes P.Rmt. 29.00 17.00 70.59% 20.00 17.65%
12.59.3 100mm dia. Pipes P.Rmt. 38.00 22.00 72.73% 26.00 18.18%
12.59.4 150mm dia. Pipes P.Rmt. 55.00 31.00 77.42% 37.00 19.35%

12.60 Painting (one or more coats) on rain water soil, waste and vent
pipes and fitting with black anticorrosive bitumastic paint of
approved brand and manufacture on old work :
12.60.1 50mm dia. Pipes P.Rmt. 10.00 6.50 53.85% 7.00 7.69%
12.60.2 75mm dia. Pipes P.Rmt. 14.00 7.50 86.67% 9.00 20.00%
12.60.3 100mm dia. Pipes P.Rmt. 19.00 10.50 80.95% 12.00 14.29%
12.60.4 150mm dia. Pipes P.Rmt. 28.00 15.50 80.65% 18.00 16.13%

12.61 Painting (two or more coats) on rain water soil, waste and vent
pipes and fitting with Aluminium paint of approved brand and
manufacture over a priming coat of ready mixed zinc chromate
yellow primer on new work :
12.61.1 50mm dia. Pipes P.Rmt. 21.00 12.00 75.00% 14.00 16.67%
12.61.2 75mm dia. Pipes P.Rmt. 29.00 18.00 61.11% 21.00 16.67%
12.61.3 100mm dia. Pipes P.Rmt. 42.00 27.00 55.56% 32.00 18.52%
12.61.4 150mm dia. Pipes P.Rmt. 62.00 40.00 55.00% 48.00 20.00%

12.62 Painting (one or more coats) on rain water soil, waste and vent
pipes and fitting with Aluminium of approved brand and
manufacture on old work :
12.62.1 50mm dia. Pipes P.Rmt. 11.00 7.00 57.14% 8.00 14.29%
12.62.2 75mm dia. Pipes P.Rmt. 15.00 10.00 50.00% 12.00 20.00%
12.62.3 100mm dia. Pipes P.Rmt. 20.00 14.00 42.86% 16.00 14.29%
12.62.4 150mm dia. Pipes P.Rmt. 24.00 18.00 33.33% 21.00 16.67%

12.63 Painting with oil type wood preservative of approved brand and
manufacture :
12.63.1 New work (Two or more coats) P.Sqm 23.00 18.00 27.78% 21.00 16.67%
12.63.2 Old work (one or more coats) P.Sqm 18.00 14.00 28.57% 16.00 14.29%

12.64 Coat-tarring coats on new work using 0.16 and 0.12 litre of coal
tar per Sqm in the first and second coat respectively
P.Sqm 43.00 32.00 34.38% 38.00 18.75%
12.65 Coat-tarring one coat on old work using 0.12 litre of coal tar per
Sqm.
P.Sqm 23.00 16.00 43.75% 19.00 18.75%
12.66 Spray painting with flat wall paint of approved brand and
manufacture to give an even shade :
12.66.1 Two or more coats on new work including priming coat of P.Sqm 114.00 72.00 58.33% 86.00 19.44%
distemper primer of approved brand and manufacture.
12.66.2 Two or more coats on new work including priming coat of P.Sqm 112.00 69.00 62.32% 82.00 18.84%
cement primer of approved brand and manufacture.
12.66.3 On lod work (One or more coats) P.Sqm 46.00 29.00 58.62% 34.00 17.24%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.67 Wall painting with plastic emulsion paint of approved brand and
manufacture to give an even shade :
12.67.1 Two or more coats on new work including preparation of base P.Sqm 80.00 68.00 17.65% 80.00 17.65%
with primer, putty, lippy complete in all respect.
12.67.2 One or more coats on old work P.Sqm 52.00 43.00 20.93% 51.00 18.60%
12.68 Painting with enamel paint of approved brand and manufacture
to give an even shade :
12.68.1 Two or more coats on new work P.Sqm 86.00 59.00 45.76% 70.00 18.64%
12.68.2 one or more coats on lod work P.Sqm 56.00 41.00 36.59% 49.00 19.51%
12.69 Painting with Aluminium paint of approved brand and
manufacture to give an even shade :
12.69.1 Two or more coats on new work P.Sqm 89.00 60.00 48.33% 72.00 20.00%
12.69.2 One or more coats on old work P.Sqm 56.00 38.00 47.37% 45.00 18.42%

12.70 Painting with acid proof paint of approved brand and


manufacture to required colour to give an even shade :
12.70.1 (a) Two or more coats on new work P.Sqm 72.00 48.00 50.00% 57.00 18.75%

12.70.2 (a) One or more coats on old work P.Sqm 47.00 32.00 46.88% 38.00 18.75%

12.71 Painting with black anti/corrosive bitumastic paint of approved


brand and manufacture to give an even shade :
12.71.1 Two or more coats on new work P.Sqm 68.00 46.00 47.83% 55.00 19.57%
12.71.2 One or more coats on old work P.Sqm 45.00 30.00 50.00% 36.00 20.00%

12.72 Painting small articles of painted surface and not in conjunction


with similar painted work paint of approved brand and
manufacture and or required quality and shade to give an even
shade :
12.72.1 Area not exceeding 0.1 Sqm P.Sqm 11.50 9.00 27.78% 10.00 11.11%
12.72.2 Upto 15 cm in width or in girth P.Sqm 12.00 7.00 71.43% 8.00 14.29%
12.73 Varnishing with varnish of approved brand and manufacture :

12.73.1 Two or more coats glue sizing with copal varnish over an under P.Sqm 33.00 33.00 0.00% 33.00 0.00%
coat of flatting varnish.
12.73.2 Two or more coats transparent wood filler copal varnish over an P.Sqm 32.00 32.00 0.00% 32.00 0.00%
under coat of flatting varnish.
12.73.3 One or more coats with copal varnish P.Sqm 42.00 25.00 68.00% 30.00 20.00%
12.73.4 Two or more coats transparent wood filler with sprey varnish P.Sqm 127.00 49.00 159.18% 58.00 18.37%
over an under coat of flatting varnish.
12.73.5 One or more coats with spray varnish P.Sqm 65.00 26.00 150.00% 31.00 19.23%

12.74 French sprit polishing


12.74.1 Two or more coats on new work including a coat of wood filler. P.Sqm 247.00 143.00 72.73% 171.00 19.58%

12.74.2 One or more coats on old work P.Sqm 128.00 75.00 70.67% 90.00 20.00%

12.75 Oiling with linseed oil


12.75.1 Two or more coats on new work P.Sqm 37.00 21.00 76.19% 25.00 19.05%
12.75.2 One or more coats on old work P.Sqm 27.00 15.50 74.19% 18.00 16.13%
12.75.3 One or more coats on picture or curtain rail P.Sqm 26.00 15.50 67.74% 18.00 16.13%

12.76 Bees waxing on wood work with local made wax polish :
12.76.1 New work in proportion 2 :15 : 1 : 0.50 (2-bees wax : 1.5-linseed P.Sqm 115.00 58.00 98.28% 69.00 18.97%
oil : 1-turpentine oil : 0.50-varnish by weight).
12.76.2 Old work in proportion 4 : 3 : 2 : 1 (4-bees wax : 3- P.Sqm 35.00 35.00 0.00% 35.00 0.00%
linseed oil : 2- Turpentine oil : 1-varnish by weight).

12.77 Polished on wood work with ready made wax polish of approved
brand and manufacture :

12.77.1 New Work P.Sqm 55.00 55.00 0.00% 55.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.77.2 Old work P.Sqm 53.00 36.00 47.22% 43.00 19.44%

12.78 Lettering with black Japan paint of approved brand and


manufacture
P.Sqm 3.10 1.25 148.00% 2.00 60.00%
12.79 Re-lettering with black Japan paint of approved brand and
manufacture.
P.Sqm 2.00 1.15 73.91% 2.00 73.91%
12.80 Painting (One or more coats) with black Japan paint of approved
brand and manufacture to give and even shades.
P.Sqm 39.00 21.00 85.71% 25.00 19.05%
12.81 Painting fire places and iron grating with paint of approved
brand and manufacture upto area 5 sqm
P.Sqm 255.00 124.00 105.65% 148.00 19.35%
12.82 Pink colour wash with khameera mixed with pigment including
making gota, gardana, Kangooras and ornamental lining work
as per approved Jaipur style and pattern, complete in all
respects :
12.82.1 One new surface (3 coats) P.Sqm 60.00 60.00 0.00% 60.00 0.00%
12.82.2 One old surface (2 coats) P.Sqm 91.00 48.00 89.58% 57.00 18.75%

12.83 Painting two coats of anti-termite paint on wooden surface by


using chemical emulsion manufactured as per is : 10013 (Part-
III) - 1989 and to be applied as per manufacture's spedifications.

P.Sqm 107.00 81.00 32.10% 97.00 19.75%


12.84 Finishing wall with vinyl satin finish coating paints of approved
shade with two or more coats including sand papering, priming
coat, making surface with putty or plaster of Paris etc. complete
in all respects :

12.84.1 One New Surface P.Sqm 140.00 101.00 38.61% 121.00 19.80%
12.84.2 On old surface. P.Sqm 70.00 70.00 0.00% 70.00 0.00%

DUCO PAINTING
12.85 Painting on new surface with duco paint (IC or equivalent) to
give an even shade (minimum 4 coats) with preparation of
surface by rubbing, primer coats, duco filler putty including
polishing etc. complete :
12.85.1 On wood work P.Sqm 384.00 Deleted
12.85.2 On steel work P.Sqm 195.00 Deleted

12.86 Painting on old surface with paint (ICI or equivalent) to give an


even shade (minimum 4 coats) with preparation of surface by
rubbing, primer coats, duco filler putty including polishing etc.
complete :

12.86.1 On wood work P.Sqm 186.00 Deleted


12.86.2 On steel work P.Sqm 85.00 Deleted

12.87 Providing and applying superior quality wall painting with Velvet
touch emulsion paint of approved brand and manufacture to give
an even shade with putty and preparation of surface applying
with the help of paint roller the work complete in all respect as
per direction of Engineer-in-charge.

12.87.1 New Work Three or More coat Sqm 192.00 224.42 -14.45% 192.00 -14.45%

12.87.2 Old Work Analysis Sqm 123.00 147.43 -16.57% 123.00 -16.57%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-12
Chapter Description
Code No. Variation Proposed % Above
Analysis As per
Unit on BSR Rate for with BSR
Rate BSR 2018
2018 BSR 2019 2018

12.88 Providing and applying superior quality Duco paint on wood work
like doors, windows etc. of approved brand and manufacture to
given an even shade including preparation of surface with primer
and putty complete in all respect with spray machine as per
direction of Engineer-in-charge. New work three or more coat.
Sqm 2935.00 1690.00 73.67% 2,028.00 20.00%

2935.00 15041.40 -80.49% 16963.05 12.78%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
FLOORING WORK
CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018
FLOORING WORK
BRICK FLOORING
11.1 Brick on edge flooring with bricks of class designation 75 including
pointing in CM (1 : 3) complete laid on 12mm thick bed of :

11.1.1 Cement Sand Mortar 1 : 6 P.Sqm 659.00 477.00 38.16% 572.00 19.92%
11.1.2 Cement Sand Mortar 1 : 4 P.Sqm 697.00 509.00 36.94% 610.00 19.84%

11.2 Extra for brick flooring laid in diagonal herring bone bond or other
pattern as specified.
P.Sqm 29.40 13.00 126.15% 15.00 15.38%
CEMENT CONCRETE FLOORING

11.3 Cement concrete flooring grade 1:2:4 (1-cement : 2-coarse sand : 4-


graded stone aggregate) rounding off edges etc. but excluding the
cost of nosing of steps etc. complete :

11.3.1 25mm thick with 12.5mm thick nominal size aggregate. P.Sqm 248.00 182.00 36.26% 218.00 19.78%
11.3.2 40mm thick with 20mm thick nominal size aggregate. P.Sqm 326.00 247.00 31.98% 296.00 19.84%
11.3.3 50mm thick with 20mm thick nominal size aggregate. P.Sqm 345.00 264.00 30.68% 316.00 19.70%
11.3.4 75mm thick with 20mm thick nominal size aggregate. P.Sqm 459.00 358.00 28.21% 429.00 19.83%

11.3.5 Add extra if finished with a floating coat of neat cement including
cement slurry, making of lines or grooves etc complete.

P.Sqm 38.80 26.00 49.23% 31.00 19.23%


11.4 Cement concrete flooring 1 : 3 : 6 finished in all respects including
rounding off edges etc. but excluding the cost of nosing of steps etc.
complete :

11.4.1 25mm thick with 12.5mm thick nominal size aggregate. P.Sqm 190.00 119.00 59.66% 142.00 19.33%
11.4.2 40mm thick with 20mm thick nominal size aggregate. P.Sqm 254.00 167.00 52.10% 200.00 19.76%
11.4.3 50mm thick with 20mm thick nominal size aggregate. P.Sqm 281.00 194.00 44.85% 232.00 19.59%
11.4.4 75mm thick with 20mm thick nominal size aggregate. P.Sqm 414.00 288.00 43.75% 345.00 19.79%

11.5 50mm thick cement concrete flooring with Metallic concrete


hardener topping, under layer of 38mm thick cement concrete 1:2:4
(1-cement : 2-coarse sand : 4-graded stone aggregate 20mm thick
nominal size) and top layer of 12mm thick metallic concrete
hardener consisting of mix 1:2 (1 cement : 2 stone aggregate, 6mm
nominal size) by volume & mixed with metallic hardening compound
of approved quality @ 2Kg./Sqm including cement slurry, rounding
off edges etc. but excluding the cost of nosing of step etc. complete.

P.Sqm 533.00 453.00 17.66% 533.00 17.66%


11.6 60mm thick cement concrete flooring with Metallic concrete
hardener topping, under layer of 42mm thick cement concrete 1:2:4
(1 cement : 2 course sand : 4 graded stone aggregate 20mm
nominal size) and top layer of 18mm thick metallic concrete
hardener consisting of mix 1:2 (1 cement : 2 stone aggregate, 6mm
nominal size) by volume & mixed with metallic hardening compound
of approved quality @ 3Kg./Sqm including cement slurry, rounding
off edges etc. but excluding the cost of nosing of step etc. complete.

P.Sqm 576.00 487.00 18.28% 576.00 18.28%


11.7 Cement plaster in skirting and/dado with cement mortar 1:3 (1
cement : 3 course sand) finished with a floating coat of neat cement
including rounding of junctions with floor :

11.7.1 15mm thick. P.Sqm 259.00 155.00 67.10% 186.00 20.00%


11.7.2 20mm thick. P.Sqm 287.00 181.00 58.56% 217.00 19.89%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018
11.8 40mm thick flooring with red oxide under layer 30mm thick cement
concrete 1:2:4 (1 cement : 2 course sand : 4 graded stone
aggregate 12mm nominal size) and top layer 10mm thick plaster of
cement red oxide mix using 3.5 Kg. of red oxide of iron per 50Kg. of
cement 1:3 (1 cement : 3 course sand) finished with a floating coat
of neat cement red oxide mix of same proportion including cement
slurry, rounding of edges and strips but excluding the cost of nosing
of steps etc. complete.

P.Sqm 888.00 585.00 51.79% 702.00 20.00%


11.9 Add or deduct over item No. 11.8 for using more or less than 3.5
Kg. of red oxide of iron per 50 Kg. of cement in 40mm thick red
oxide flooring.
P.Sqm 30.00 30.00 0.00% 30.00 0.00%
11.10 Red oxide plaster/dado with top layer 6mm thick plaster of cement
red oxide of mix using 3.5Kg. of red oxide of iron per 50 Kg. of
cement 1:3 (1 cement : 3 course sand) finished with a floating coat
of neat cement red oxide mix of same proportion :
11.10.1 18mm thick with under layer 12mm thick cement plaster 1:3 (1 P.Sqm 419.00 296.00 41.55% 355.00 19.93%
cement : 3 coarse sand).
11.10.2 21mm thick with under layer 15mm thick cement plaster 1:3 (1 P.Sqm 434.00 309.00 40.45% 370.00 19.74%
cement : 3 coarse sand).
11.11 Add or deduct over item No. 11.10 for using more or less than
3.5Kg. of red oxide of iron per 50Kg. of cement in 18mm or 21mm
thick red oxide plaster skirting/dado.
P.Sqm 21.00 21.00 0.00% 21.00 0.00%
11.12 Cement concrete pavement of required thickness with.
(a) 1:2:4 (1-Cement:2-course sand : 4-graded stone aggregate 20 mm
nominal size) including finishing complete.
P.Cum 5093.00 4207.00 21.06% 5,048.00 19.99%
(b) 1:1.5:3 (1-Cement:1.5-course sand : 3-graded stone aggregate 20 mm
nominal size) including finishing complete.
P.Cum 5517.00 5009.00 10.14% 5,517.00 10.14%
11.13 Extra for making chequers of approved pattern on cement concrete
floors, steps landing, pavement etc.
P.Sqm 35.00 16.00 118.75% 19.00 18.75%
11.14 Filling of sunk portion of roof with earthen pots of required height
including filling voids with 1:2:4 light concrete, using brick bats
complete levelling and dressing the surface by 50mm thick cement
concrete 1:2:4 as per specification.
P.Sqm 1640.00 1483.00 10.59% 1,640.00 10.59%
TERRAZZO FLOORING
11.15 40mm thick marble chips flooring rubbed and polished to granolithic
finish under layer 34mm thick cement concrete 1:2:4 (1 cement : 2
course sand : 4 graded stone aggregate 12.5mm nominal size)
including fixing of dividing strip (excluding the cost of strips) and top
layer 6mm thick with marble chips of approved colour & 1mm to
4mm nominal size laid in cement marble chips mix of 4 : 7 (4
cement : 7 marble chips) by volume including cement slurry etc.
complete :

11.15.1 Ordinary cement without any pigment. P.Sqm 561.00 427.00 31.38% 512.00 19.91%
11.15.2 Light shade pigment with ordinary cement. P.Sqm 590.00 435.00 35.63% 522.00 20.00%
11.15.3 Medium shade pigment with approximately 50% white cement and P.Sqm 563.00 411.00 36.98% 493.00 19.95%
50% ordinary cement.
11.15.4 White cement without any pigment. P.Sqm 622.00 460.00 35.22% 552.00 20.00%
11.15.5 Light shade pigment with white cement. P.Sqm 563.00 411.00 36.98% 493.00 19.95%
11.15.6 Dark shade pigment with ordinary cement. P.Sqm 596.00 443.00 34.54% 531.00 19.86%

11.16 40mm thick marble chips flooring rubbed and polished to granolithic
finish under layer 31mm thick cement concrete 1:2:4 (1 cement : 2
course sand : 4 graded stone aggregate 12.5mm nominal size)
including fixing of dividing strip (excluding the cost of strips) and top
layer 9mm thick with marble chips of approved colour & 4mm to
7mm nominal size laid in cement marble chips 2 : 3 (2 cement : 3
marble chips) by volume including cement slurry etc. complete

11.16.1 Ordinary cement without any pigment. P.Sqm 594.00 445.00 33.48% 534.00 20.00%
11.16.2 Light shade pigment with ordinary cement. P.Sqm 643.00 499.00 28.86% 598.00 19.84%
11.16.3 Medium shade pigment with approximately 50% white cement and P.Sqm 647.00 502.00 28.88% 602.00 19.92%
50% ordinary cement.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018
11.16.4 White cement without any pigment. P.Sqm 671.00 514.00 30.54% 616.00 19.84%
11.16.5 Light shade pigment with white cement. P.Sqm 728.00 577.00 26.17% 692.00 19.93%
11.16.6 Dark shade pigment with ordinary cement. P.Sqm 642.00 497.00 29.18% 596.00 19.92%
11.17 40mm thick marble chips flooring rubbed and polished to granolithic
finish under layer 28mm thick cement concrete 1:2:4 (1 cement : 2
course sand : 4 graded stone aggregate 12.5mm nominal size)
including fixing of dividing strip (excluding the cost of strips) and top
layer 12mm thick with marble chips of approved colour 7mm to
10mm nominal size laid in cement marble chips mix by weight in
proportion of 2 : 3 (2 cement : 3 marble chips) by volume including
cement slurry etc. complete :

11.17.1 Ordinary cement without any pigment. P.Sqm 618.00 473.00 30.66% 567.00 19.87%
11.17.2 Light shade pigment with ordinary cement. P.Sqm 690.00 553.00 24.77% 663.00 19.89%
11.17.3 Medium shade pigment with approximately 50% white cement and P.Sqm 744.00 601.00 23.79% 721.00 19.97%
50% ordinary cement.
11.17.4 White cement without any pigment. P.Sqm 726.00 569.00 27.59% 682.00 19.86%
11.17.5 Light shade pigment with white cement. P.Sqm 798.00 648.00 23.15% 777.00 19.91%
11.17.6 Dark shade pigment with ordinary cement. P.Sqm 677.00 538.00 25.84% 645.00 19.89%

11.18 40mm thick marble chips flooring rubbed and polished to granolithic
finish under layer 35mm thick cement concrete 1:2:4 (1 cement : 2
course sand : 4 graded stone aggregate 12.5mm nominal size)
including fixing of dividing strip (excluding the cost of strips) and top
layer 15mm thick with marble chips of approved colour & 10mm to
13mm nominal size laid in cement marble chips mix in proportion of
2 : 3 (2 cement : 3 marble chips) by volume including cement slurry
etc. complete :

11.18.1 Ordinary cement without any pigment. P.Sqm 602.00 462.00 30.30% 554.00 19.91%
11.18.2 Light shade pigment with ordinary cement. P.Sqm 575.00 575.00 0.00% 575.00 0.00%
11.18.3 Medium shade pigment with approximately 50% white cement and P.Sqm 600.00 600.00 0.00% 600.00 0.00%
50% ordinary cement.
11.18.4 White cement without any pigment. P.Sqm 760.00 760.00 0.00% 760.00 0.00%
11.18.5 Light shade pigment with white cement. P.Sqm 800.00 800.00 0.00% 800.00 0.00%
11.18.6 Dark shade pigment with ordinary cement. P.Sqm 575.00 575.00 0.00% 575.00 0.00%
11.19 Marble chips skirting/dado rubbed and polished to granolithic finish
6mm thick with white marble chips of approved colour and size from
smallest to 4mm nominal size laid in cement marble chips mix in
proportion of 4:7(4 cement : 7 marble chips) by volume including
fixing of dividing strips (excluding the cost of strips) complete in all
respects :

11.19.1 18mm thick with under layer of 12mm thick cement plaster 1:3 (1
cement : 3 coarse sand) :
(a) Ordinary cement without any pigment. P.Sqm 757.00 379.00 99.74% 454.00 19.79%
(b) Light shade pigment with ordinary cement. P.Sqm 795.00 403.00 97.27% 483.00 19.85%
(c) Medium shade pigment with approximately 50% white cement P.Sqm 819.00 425.00 92.71% 510.00 20.00%
and 50% ordinary cement.
(d) White cement without any pigment. P.Sqm 816.00 430.00 89.77% 516.00 20.00%
(e) Light shade pigment with white cement. P.Sqm 846.00 449.00 88.42% 538.00 19.82%
(f) Dark shade pigment with ordinary cement. P.Sqm 786.00 393.00 100.00% 471.00 19.85%
11.19.2 21mm thick with under layer of 15mm thick in cement plaster 1:3 (1
cement : 3 coarse sand) :

(a) Ordinary cement without any pigment. P.Sqm 772.00 391.00 97.44% 469.00 19.95%
(b) Light shade pigment with ordinary cement. P.Sqm 737.00 389.00 89.46% 466.00 19.79%
(c) Medium shade pigment with approximately 50% white cement P.Sqm 761.00 409.00 86.06% 490.00 19.80%
and 50% ordinary cement.
(d) White cement without any pigment. P.Sqm 913.00 517.00 76.60% 620.00 19.92%
(e) Light shade pigment with white cement. P.Sqm 856.00 453.00 88.96% 543.00 19.87%
(f) Dark shade pigment with ordinary cement. P.Sqm 802.00 405.00 98.02% 486.00 20.00%

11.19.3 25mm thick with under layer of 19mm thick in cement plaster 1:3 (1
cement : 3 coarse sand) :

(a) Ordinary cement without any pigment. P.Sqm 400.00 400.00 0.00% 400.00 0.00%
(b) Light shade pigment with ordinary cement. P.Sqm 450.00 450.00 0.00% 450.00 0.00%
(c) Medium shade pigment with approximately 50% white cement P.Sqm 834.00 437.00 90.85% 524.00 19.91%
and 50% ordinary cement.
(d) White cement without any pigment. P.Sqm 560.00 560.00 0.00% 560.00 0.00%
(e) Light shade pigment with white cement. P.Sqm 575.00 575.00 0.00% 575.00 0.00%
(f) Dark shade pigment with ordinary cement. P.Sqm 530.00 530.00 0.00% 530.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018
11.20 Providing Aluminium strips 40mm wide and 2mm thick in joints of
terrazzo floors.
P.Sqm 128.00 86.00 48.84% 103.00 19.77%
11.21 Providing glass strips in joints of terrazzo/cement concrete floor :

11.21.1 40mm wide and 4mm thick P.Sqm 34.00 23.00 47.83% 27.00 17.39%
11.21.2 40mm wide and 5.5mm thick P.Sqm 46.80 31.00 50.97% 37.00 19.35%
11.21.3 20mm wide and 3mm thick for skirting. P.Sqm 17.60 12.00 46.67% 14.00 16.67%

11.22 Providing PVC strips in joint of terrazzo/ cement concrete floor PVC
strips 40 mm wide and 2 to 3mm thick.
P.Sqm 17.00 17.00 0.00% 17.00 0.00%
11.23 Add extra over item No. 11.15 to 11.18 for terrazzo flooring laid as
floor border margins and similar bands exceeding 7.5cm but not
exceeding 30cm in width.
P.Sqm 27.00 11.00 145.45% 13.00 18.18%
11.24 Add extra over item No. 11.15 to 11.18 for terrazzo flooring on stair
case treads not exceeding 30 cm in width including cost of forming
of nosing etc.
P.Sqm 40.00 18.00 122.22% 21.00 16.67%
11.25 Add extra over item No. 11.15 to 11.18 for terrazzo flooring in
narrow band bands not exceeding 7.5cm in width.
P.Rmt. 1.25 1.25 0.00% 1.00 -20.00%
11.26 Add extra for making moulded nosing in terrazzo including returned
moulded ends and angles to mouldings.
P.Rmt. 60.00 60.00 0.00% 60.00 0.00%
11.27 Special surface finishing to treads risers at the end of concrete
steps and the like including form work.
P.Sqm 43.00 29.00 48.28% 34.00 17.24%
11.28 Crazy marble stone flooring 20mm thick marble stone with black or
of specified colour topping including filling the gaps with cement
marble chips mix in proportion of 4 : 7 (4cement : 7 white black or
white or black marble chips) size from 1mm to 4mm by volume and
under layer of 25mm thick cement concrete [1:2:4, graded stone
aggregate 12.5mm nominal size] rubbing and polishing and cement
slurry etc. complete :

11.28.1 In ordinary cement. P.Sqm 425.00 425.00 0.00% 425.00 0.00%


11.28.2 White cement without pigment. P.Sqm 721.00 535.00 34.77% 642.00 20.00%
11.28.3 Add extra if fine edge cut regular shape crazy is done. P.Sqm 30.00 30.00 0.00% 30.00 0.00%
11.28.4 Deduct if crazy of Kota, Madras or other similar stone topping is P.Sqm 30.00 30.00 0.00% 30.00 0.00%
done.
11.29 Providing and laying 6mm thick marble chippings (No. 0, 2 and 2B
graded) set in cement marble powder mix 3:1 (3 cement : 1 marble
powder) by weight in proportion of 4:7 (4cement marble powder
mix : 7 marble chips) by volume, rubbed and polished complete in
all respects.
P.Sqm 210.00 210.00 0.00% 210.00 0.00%
TILE FLOORING
11.30 Precast terrazo tiles of approved make, 20mm thick with marble
chips of size upto 6mm laid in floors, and landing, jointed with neat
cement slurry mixed with pigment to match the shade of the tiles,
including rubbing and polishing complete on 30mm thick bed of
cement sand mortar 1 : 4.
11.30.1 Dark shade using ordinary cement. P.Sqm 758.00 680.00 11.47% 758.00 11.47%
11.30.2 Medium shade using approximately 50% white cement and 50% P.Sqm 746.00 667.00 11.84% 746.00 11.84%
ordinary cement.
11.30.3 Light shade using white cement. P.Sqm 814.00 729.00 11.66% 814.00 11.66%
11.30.4 Deduct if fixing is done in lime sand mortar 1:3 (1ime putty : 3 P.Sqm 75.00 75.00 0.00% 75.00 0.00%
coarse sand).
11.30.5 Deduct if fixing is done in lime surkhi mortar 1:3 (lime putty : 3 P.Sqm 75.00 75.00 0.00% 75.00 0.00%
surkhi).

11.30.6 Add extra over item No. 11.30.1 to 11.30.3 for using 24mm thick
terrazo tiles with marble chips of size upto 10mm instead of 20mm
thick terrazzo tiles with marble chips of size upto 6mm
P.Sqm 52.00 52.00 0.00% 52.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018
11.31 Precast terrazzo tiles of approved make 20mm thick with marble
chips of size upto 6mm in skirting & risers, treads of steps and
dados 12mm thick cement plaster 1:3 (1 cement : 3 coarse sand)
jointed with neat cement slurry mixed with pigment to match the
shade of the tiles, including rubbing and polishing complete with
tiles of :

11.31.1 Dark shade using ordinary cement. P.Sqm 736.00 657.00 12.02% 736.00 12.02%
11.31.2 Medium shade using approximately 50% white cement and 50% P.Sqm 790.00 702.00 12.54% 790.00 12.54%
ordinary cement.
11.31.3 Light shade using white cement. P.Sqm 814.00 722.00 12.74% 814.00 12.74%

11.32 Providing & laying Chequered terrazzo tiles of approved make


22mm thick with marble chips of size upto 6mm, in floors, jointed
with neat cement slurry mixed wit pigment to match the shade of
tiles including rubbing and polishing complete in all respect as per
specification, on 28mm thick bed of C.M. 1:4 :

11.32.1 Dark shade using ordinary cement. P.Sqm 758.00 680.00 11.47% 758.00 11.47%
11.32.2 Medium shade using approximately 50% white cement and 50% P.Sqm 792.00 711.00 11.39% 792.00 11.39%
ordinary cement.
11.32.3 Light shade using white cement. P.Sqm 814.00 729.00 11.66% 814.00 11.66%

11.32.4 Add extra for using 30mm thick chequereed terrazzo tiles instead of
22mm thick terrazo tiles.
P.Sqm 52.00 52.00 0.00% 52.00 0.00%
11.33 Providing & laying Chequered plain cement concrete embossed o
specially manufactured non-slipping tiles of approved make 20mm
thick laid on 20mm thick bed of cement mortar 1:6 jointed with neat
cement slurry complete.
P.Sqm 534.00 453.00 17.88% 534.00 17.88%
11.34 Add extra for chequered coloured plain cement concrete or specially
manufactured non-slipping 9-12 mm ironite topping tiles of approved
make 20 mm thick.
P.Sqm 40.00 40.00 0.00% 40.00 0.00%
KOTA STONE FLOORING

11.35 Polished Blue Kota Stone flooring skirting, laid over 20mm thick
base of C.M. 1:4 and jointed with grey cement slurry to match the
shade of the slab including rubbing and polishing complete :

11.35.1 For area of each slab upto 900 Sq. Cm :


(a) 25mm thick slab. P.Sqm 888.00 628.00 41.40% 753.00 19.90%
(b) 30 mm thick slab. P.Sqm 835.00 732.00 14.07% 835.00 14.07%
(c) 40mm thick slab. P.Sqm 900.00 789.00 14.07% 900.00 14.07%

11.35.2 For area of each slab from 901 to 2000 Sq.Cm :

(a) 25mm thick slab. P.Sqm 900.00 789.00 14.07% 900.00 14.07%
(b) 30 mm thick slab. P.Sqm 1015.00 890.00 14.04% 1,015.00 14.04%
(c) 40mm thick slab. P.Sqm 1050.00 921.00 14.01% 1,050.00 14.01%

11.35.3 For area of each slab from 2001 to 5000 Sq.Cm

(a) 25mm thick slab. P.Sqm 1030.00 904.00 13.94% 1,030.00 13.94%
(b) 30 mm thick slab. P.Sqm 1090.00 956.00 14.02% 1,090.00 14.02%
(c) 40mm thick slab. P.Sqm 1125.00 987.00 13.98% 1,125.00 13.98%

11.36 Extra for making hole in Kota Stone/Marble stone flooring diameter
upto 150mm.
P.Sqm 76.00 50.00 52.00% 60.00 20.00%
11.37 Polished Blue Kota Stone slab in steps, walls, pillars having fine
machine cut edges laid on 12mm (Av.) thick cement mortar 1:3 and
jointed with grey cement slurry mixed with pigment to match the
shade of the slab, including rubbing and polishing complete :

11.37.1 20mm thick slab area upto 900 Sq.Cm. P.Sqm 800.00 702.00 13.96% 800.00 13.96%
11.37.2 25mm thick slab area 901 to 2000 Sq.Cm. P.Sqm 880.00 772.00 13.99% 880.00 13.99%
11.37.3 30mm thick slab area 2001 to 5000 Sq.Cm. P.Sqm 1019.00 852.00 19.60% 1,019.00 19.60%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018

11.37.4 Deduct from item No. 11.35 to 11.37 for using Kota stone other than
blue in colour.
P.Sqm 110.00 110.00 0.00% 110.00 0.00%
11.38 20 to 25mm thick polished stone flooring over 20mm thick base of
Cm. 1:4 (1 cement : 4 coarse sand) and jointed with grey cement
slurry including rubbing complete in all respects:

11.38.1 Madras Stone P.Sqm 855.00 855.00 0.00% 855.00 0.00%


11.38.2 Chittor Stone P.Sqm 824.00 793.00 3.91% 824.00 3.91%
11.38.3 Nimbhahera Stone P.Sqm 725.00 725.00 0.00% 725.00 0.00%

11.39 20mm thick polished stone for steps risers, skirting, dados, wall &
pillars laid on 12mm thick base of CM. 1:3 & jointed with grey
cement including rubbing & polishing :

11.39.1 Madras Stone P.Sqm 880.00 880.00 0.00% 880.00 0.00%


11.39.2 Chittor Stone P.Sqm 825.00 825.00 0.00% 825.00 0.00%
11.39.3 Nimbhahera Stone P.Sqm 770.00 770.00 0.00% 770.00 0.00%
11.40 35mm thick Rough Chisel dressed stone flooring of approved shade
set in pattern over 20mm thick base of cement mortar 1:6 (1 cement
: 6 coarse sand) and jointed with cement sand mortar 1:3 complete
in all respects :
11.40.1 Nimbhahera Stone P.Sqm 440.00 440.00 0.00% 440.00 0.00%
11.40.2 Chittor Stone P.Sqm 490.00 490.00 0.00% 490.00 0.00%
11.40.3 Kota Stone P.Sqm 509.00 487.00 4.52% 509.00 4.52%

11.41 Grinding & polishing on mosaic / polished stone flooring :


P.Sqm 235.00 217.00 8.29% 235.00 8.29%
11.42 Add extra for mirror polishing on terrazzo / stone flooring :
P.Sqm 118.00 109.00 8.26% 118.00 8.26%
11.43 Pointing with cement sand mortar 1:3 to stone flooring.
P.Sqm 108.00 50.00 116.00% 60.00 20.00%
11.44 Random rubble dry stone Kharanja under floor.
P.Cum 850.00 672.00 26.49% 806.00 19.94%
11.45 Providing and laying R.R. stone kharanja in cement mortar 1:6 in
one course :

11.45.1 23 Cm. thick. P.Sqm 450.00 450.00 0.00% 450.00 0.00%


11.45.2 15 Cm. thick P.Sqm 421.00 279.00 50.90% 334.00 19.71%
SAND STONE FLOORING

11.46 Rough chisel dressed stone flooring over 20mm (Av.) thick base in
CM 1:6 including pointing with cement mortar 1:2 (1 cement : 2
stone dust) with and admixture of pigment to match the shade of
stone with joint thickness upto 15mm:
11.46.1 35mm thick red sand stone. P.Sqm 530.00 530.00 0.00% 530.00 0.00%
11.46.2 45mm thick red sand stone. P.Sqm 575.00 575.00 0.00% 575.00 0.00%
11.46.3 35mm thick white sand stone. P.Sqm 560.00 560.00 0.00% 560.00 0.00%
11.46.4 45mm thick white sand stone. P.Sqm 726.00 708.00 2.54% 726.00 2.54%

11.47 25mm thick fine dressed and machine grinded surface stone
flooring over 20mm (Av.) thick base in cement in CM 1:6 with joints
finished flush with:

11.47.1 Red sand stone. P.Sqm 660.00 660.00 0.00% 660.00 0.00%
11.47.2 White sand stone. P.Sqm 690.00 690.00 0.00% 690.00 0.00%

11.48 Coursed Stone paving set in CM 1:6 laid over a bed of 20mm thick
cement sand mortar 1:6 with cement pointing 1:3 :

11.48.1 125 to 150mm thick. P.Sqm 500.00 500.00 0.00% 500.00 0.00%
11.48.2 200 to 225mm thick. P.Sqm 610.00 610.00 0.00% 610.00 0.00%

11.49 Extra in course stone paving when bitumen sand pointing using
68Kg. bitumen 80/100 with 0.6 Cum. Sand is used in place of
cement sand pointing.
P.Sqm 30.00 30.00 0.00% 30.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018
FLOORING

11.50 Providing and fixing Polyvinyl Chloride sheet/ P.V.C. tile (with
backing of Hessian cloth or other woven fabric flooring using rubber
base adhesives including rolling with light wooden roller complete :

11.50.1 1.5mm thick sheet. P.Sqm 405.00 405.00 0.00% 405.00 0.00%
11.50.2 2.0mm thick sheet. P.Sqm 448.00 448.00 0.00% 448.00 0.00%
11.50.3 3.0mm thick sheet. P.Sqm 552.00 552.00 0.00% 552.00 0.00%
11.50.4 20mm thick PVC tile. Fully flexible Vinyl flooring. P.Sqm 338.00 338.00 0.00% 338.00 0.00%

11.51 Providing and Fixing Cushion Vinyl/Fully flexible Vinyl Flooring


confirming to I.S.-3462 Flooring of approved make with fibre base
using rubber base adhesives including rolling with light wooden
roller complete :
11.51.1 1.0 mm thick. P.Sqm 505.00 505.00 0.00% 505.00 0.00%
11.51.2 1.5 mm thick. P.Sqm 590.00 590.00 0.00% 590.00 0.00%
11.51.3 2.0 mm thick. P.Sqm 735.00 735.00 0.00% 735.00 0.00%

11.51.4 Add extra over item No. 11.51.3 for antistatic flooring:
P.Sqm 10.00 10.00 0.00% 10.00 0.00%
11.52 Add extra over item No. 11.35 and 11.38 for combination flooring of
Blue Kota and Marble stones :
11.52.1 Using upto 10% marble stone. P.Sqm 40.00 40.00 0.00% 40.00 0.00%
11.52.2 Using above 10% and upto 15% marble stone. P.Sqm 62.00 62.00 0.00% 62.00 0.00%
11.52.3 Using above 15% and upto 20% marble stone. P.Sqm 85.00 85.00 0.00% 85.00 0.00%

WOODEN FLOORING

11.53 25mm thick wooden planking, tongued and grooved in flooring


including fixing with iron screws complete (Lower frame to be paid
extra) with :
11.53.1 First class Teak wood. P.Sqm 2163.00 2145.00 0.84% 2,163.00 0.84%
11.53.2 First class Chir wood. P.Sqm 2168.00 2150.00 0.84% 2,168.00 0.84%
11.53.3 First class Assam Teak or Sheesham wood. P.Sqm 2304.00 2225.00 3.55% 2,304.00 3.55%

NOTE : For 2nd class wood deduct. 20%


11.54 38mm thick parquet (Wood block) flooring of first class teak wood
laid over 25mm thick levelling layer of cement concrete 1:2 :4 (to be
paid separately) coated with in a thin layer of hot bitumen (blown
type) @ 2.45Kg. per Sqm including fixing blocks in position after
dipping in hot bitumen (blown type) upto half depth, planned,
levelled smooth and finished complete.

P.Sqm 6869.00 6131.00 12.04% 6,869.00 12.04%


11.55 Providing and fixing metal strips of 1.6mm thickness at the junction
with other floors :

11.55.1 25mm wide Aluminium strips. P.Rmt. 76.00 70.00 8.57% 76.00 8.57%
11.55.2 38mm wide Aluminium strips. P.Rmt. 103.00 97.00 6.19% 103.00 6.19%

11.56 Providing and laying with a direct laminated surface treated with
aluminium oxide on top of a high density fibre board with a density
of 910 Kg./per Mtr. having a click system tongue and groove joint to
secure a long lasting joint. The planks are or termite resistant and
water protected with both side lamination :

11.56.1 Wooden flooring Planks of size 1290x190x7mm (7mm thick


laminated floor class of use 23/32 having a wear resistance level of
AC-3 as per EN-13329, ASTMC-1028,DIN-52612, DIN-54345, EN-
717-2, DIN-51953).
P.Sqm 2900.00 2900.00 0.00% 2,900.00 0.00%
11.56.2 Wooden flooring Planks of size 1290x190x8mm (8mm thick
laminated floor class of use 23/33 having a wear resistance level of
AC-4 as per EN-13329, ASTMC-1028, DIN-52612, DIN-54345, EN-
717-2, DIN-51953).
P.Sqm 3100.00 3100.00 0.00% 3,100.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-11
Chapter Description Variation Proposed % Above
Code No. As per BSR
Unit Analysis Rate on BSR Rate for with BSR
2018
2018 BSR 2019 2018
11.56.3 Wooden flooring Planks of size 1290x396x8mm (8mm thick
laminated floor class of use 23/33 having a wear resistance level of
AC-4 as per EN-13329, ASTMC-1028, DIN-52612, DIN-54345, EN-
717-2, DIN-51953).
P.Sqm 3300.00 3300.00 0.00% 3,300.00 0.00%
11.57.1 Providing and fixing of precast concrete interlocking blocks of M 30
grade 60mm thick manufactured from fully computerised automatic
stationery hydraullic vibropressed machine and fully computerised
automatic batching plant of class A1/A2 as per BS 6717:2001. The
CC interlocking paving blocks be laid on average 50mm. thick bed
of coarse sand and the joint is to be filled with fine sand. Laying
procedure on compacted sub-base as defined. Complete job is to
be executed as per the instruction of Engineer incharge. The rates
to be inclusive of all lead, Lifts and taxes. General specification of
blocks:

1) Shape as defined by Engineer incharge


2) Tensile splitting strength and braking load as per BS 6717:2001

3) Color: Grey cement natural colour


4) Variation in dimension: Less than 1.6mm.
5) Variation in thickness: Less than 3.2mm
6) Abrasion: As per BS: 6717:2001 P.Sqm 585.00 577.00 1.39% 585.00 1.39%

11.57.2 Add extra over item no. 11.57.1 for 80 mm thick blocks
P.Sqm 150.00 150.00 0.00% 150.00 0.00%
11.57.3 Add extra over item no. 11.57.1 for 100 mm thick blocks
P.Sqm 271.00 271.00 0.00% 271.00 0.00%
110806.05 95261.25 16.32% 104407.00 9.60%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
ROOFING
NOTE:
1- Rates are for complete item of work and are inclusive of all centering, shuttering,
curing and finishing including all leads and delivery of material at site of work
with all lead and lift.

2- The rates for A.C. and G.I. sheet roofing are inclusive of all necessary, overlaps
and wastage in cutting and all standard screws nuts washers bolts and nuts ‘J’ or
‘L’ hooks etc. required as per specifications.

3- All precautions shall be taken to ensure that the finished roof is water tight and
without any leakage under all weather conditions. Particular care shall be taken in
providing good workmanship specially at vulnerable points.

CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
ROOFING
STONE SLAB ROOFING
10.1 Stone slab roofing on ground floor with fine grained stone
slab from approved quarry including filling of joints of parapet
and slab on both sides in cement sand mortar 1:4, ralthal,
stone kharanja, lime terracing 90mm average thickness [as
per JAIPUR PRACTICE] with ceiling pointing in cement sand
mortar 1 : 3 complete as per specification for span :

10.1.1 Upto 2.00 metre. P.Sqm 2537.00 1713.00 48.10% 1,798.00 4.96%
10.1.2 Above 2.00 metre and upto 2.50 metre. P.Sqm 2537.00 1713.00 48.10% 1,798.00 4.96%
10.1.3 Above 2.50 metre and upto 3.00 metre. P.Sqm 2548.00 1750.00 45.60% 1,837.00 4.97%
10.1.4 Above 3.00 metre and upto 3.30 metre. P.Sqm 2548.00 1750.00 45.60% 1,837.00 4.97%

10.2 Add extra over 10.1 for subsequent :


10.2.1 1 First Floor. P.Sqm 80.00 80.00 0.00% 80.00 0.00%
10.2.2 Second Floor. P.Sqm 115.00 115.00 0.00% 115.00 0.00%
10.2.3 Third Floor. P.Sqm 160.00 160.00 0.00% 160.00 0.00%
10.3 Deduct from item No. 10.1 for Kharanja not required to be
done.
P.Sqm 181.00 126.00 43.65% 132.00 4.76%
10.4 Providing and laying lime Dhar only 90mm thick average on
roofs on ground floor with 1:2:2:2 (1 lime putty : 2 surkhi or
sand : 2 old lime mortar powder : 2 stone grit 12 to 20 mm )
mix by volume with required quantities of Gur, Gugal, Methi,
Hemp etc. Properly compacted and smoothly finished in all
respect (JAIPUR PRACTICE) as per specifications.

P.Sqm 300.00 300.00 0.00% 300.00 0.00%


10.5 Add extra over item No. 10.4 for additional thickness above
90mm average for each 10mm extra thickness.
P.Sqm 21.00 21.00 0.00% 21.00 0.00%
10.6 Add extra over item No 10.4 or 10.5 for each subsequent
storey for thickness.

10.6.1 Upto 90mm P.Sqm 10.00 10.00 0.00% 10.00 0.00%


10.6.2 Above 90 mm upto100 mm P.Sqm 12.00 12.00 0.00% 12.00 0.00%
10.6.3 Above 100 mm P.Sqm 14.00 14.00 0.00% 14.00 0.00%
10.7 Providing gola (batta) in lime concrete using 50% lime
surkhi/sand mortar 1 : 2 with grit along joint of walls and
terrace finished with lime mortar 1 : 2 plaster with Gur,
Gugal, Methi etc. in concave shape of size :
10.7.1 75mm x 75mm P.Sqm 28.00 28.00 0.00% 28.00 0.00%
10.7.2 100mm x 100mm P.Sqm 35.00 35.00 0.00% 35.00 0.00%
10.7.3 150mm x 150mm P.Sqm 50.00 50.00 0.00% 50.00 0.00%
10.8 Providing batta (gola) 75mm x 75mm in cement concrete (1 :
2 : 4) including finishing with cement mortar 1 : 3 as per
standard design.
P.Sqm 73.00 73.00 0.00% 73.00 0.00%
10.9 Spreading of hot blown bitumen (IS grade 25/85, 25/90
industrial grade) applied at 175 to 180 degree C @ rate of
1.70 Kg. per Sqm complete.
P.Sqm 75.00 75.00 0.00% 75.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.10 Providing and laying brick tiles of class designation 100 over
mumty, roofs, grouted with cement mortar 1 : 3 mix with 2%
of integrated water proofing compound by wt. Of cement
over 12mm thick layer of cement mortar 1 : 3 and finished
neat.
P.Sqm 225.00 225.00 0.00% 225.00 0.00%
10.11 Providing brick kharanja in lime sand mortar 1 : 2 in square
pattern over roof of ground floor :

10.11.1 75mm to 100mm thick average P.Sqm 381.00 285.00 33.68% 299.00 4.91%

10.11.2 55mm to 60mm thick average P.Sqm 240.00 240.00 0.00% 240.00 0.00%

10.11.3 Add for if cement mortar 1 : 4 is used instead of lime sand


mortar 1 : 2.
P.Sqm 53.00 53.00 0.00% 53.00 0.00%
10.12 Providing 100mm thick average mud phuska damped brick
earth on roofs laid to slope consolidated and plastered with
25mm thick mud mortar mixed with phuska at 35 Kg/cum of
earth, gobri leaping with mix 1 : 1 (1clay : 1 cow dung) and
covered with flat tiles of bricks class designation 100 grouted
with cement mortar 1 : 3 (1 cement : 3 fine sand) mixed with
2% of integrated water proofing compound by wt. of cement
and finished neat.

Each 275.00 275.00 0.00% 275.00 0.00%


10.13 Add extra over item No. 10.12 for every additional 1 Cm
thickness of mud phuska.
Sqm 5.00 5.00 0.00% 5.00 0.00%

10.14 Lime concrete terracing on roofs average thickness 100mm


laid to slope with 25mm nominal size brick aggregate and
50% lime mortar 1 : 2 (1-lime putty : 2- surkhi/sand) rammed
and finished with Gur and Belgiri treatment including
rounding of junction with parapet wall complete.

Sqm 240.00 240.00 0.00% 240.00 0.00%


10.15 Encasing of R.S. joist with cement concrete (1 : 3 : 6)
including expended metal of B.B. lathing finished with
cement rendering.
P.Sqm 220.00 220.00 0.00% 220.00 0.00%
10.16 Encasing of R.S. Joist with khanda/bricks in cement mortar
1:4 with neat finishing
P.Sqm 250.00 250.00 0.00% 250.00 0.00%
10.17 Providing stone slab covering over drains including filling of
joints in cement sand mortar 1 : 3 with 35mm thick cement
concrete flooring 1 : 2 : 4 mix complete with good finish with :

10.17.1 Stone slab 100 to 150mm thick average P.Sqm 1050.00 1050.00 0.00% 1,050.00 0.00%
10.17.2 Stone slab 60 to 75mm thick average P.Sqm 999.00 968.00 3.20% 999.00 3.20%
10.17.3 Stone slab 40 to 50mm thick average P.Sqm 815.00 815.00 0.00% 815.00 0.00%

10.18 Labour charges for hoisting and placing in position stone


slab for roof on ground floor :

10.18.1 Upto 2.00 Mtr. P.Sqm 85.00 85.00 0.00% 85.00 0.00%
10.18.2 Above 2.00 Mtr. and upto 2.50 Mtr. P.Sqm 100.00 100.00 0.00% 100.00 0.00%
10.18.3 Above 2.50 Mtr. and upto 3.00 Mtr. P.Sqm 115.00 115.00 0.00% 115.00 0.00%
10.18.4 Above 3.00 Mtr. and upto 3.30 Mtr. P.Sqm 125.00 125.00 0.00% 125.00 0.00%

10.19 P/F tiles over roof fixed in 25 mm thick cement mortar 1 : 4


bed complete

10.19.1 20mm thick plain cement concrete roofing tiles


P.Sqm 577.00 526.00 9.70% 552.00 4.94%
10.19.2 20mm thick terrazo tile over roofing including cutting,
grinding with mechine complete
P.Sqm 738.00 627.00 17.70% 658.00 4.94%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018

10.20 Crazy marble stone flooring 20mm thick marble stone over
roof in ordinary cement with black or of specified color
topping including filling the gaps with cement marble chips
mix in proportion of 4 : 7 (4cement : 7 white black or white or
black marble chips) size from 1mm to 4mm by volume and
under layer of 25mm thick cement concrete [1 : 2 : 4, graded
stone aggregate 12.5mm nominal size] rubbing and polishing
and cement slurry etc. complete :

10.20.1 Providing marble strips in joint of crazy flooring strips 40 mm


wide and 12 mm thick.
P.Sqm 475.00 475.00 0.00% 475.00 0.00%
10.21 Finishing with 25mm thick cement plaster on roofs in cement
sand mortar 1 : 4 mix including water proofing compound @
2% of cement used, with neat cement, finishing, curing etc.
complete in all respect including making of 300 mm x 300
mm square.
P.Sqm 261.00 174.00 50.00% 182.00 4.60%
10.22 Providing Cement based water proofing treatment to RCC
Roof with brick bats 25 mm to 100 mm in CM 1:4 (1-
Cement : 4-Sand) the under layer being 20mm thick bed
plaster of cement sand mortar 1:6 with neat cement punning
@ 3 Kg/sqm including cleaning of RCC surface and adding
of water proofing compound at all stages at 2% of weight of
cement including curing etc. complete in all respect finishing
with 20mm thick cement sand mortar of mix 1:4 mixed with
water proofing compound.

P.Sqm 425.00 425.00 0.00% 425.00 0.00%


10.23 Providing props & rafters (Ballies & fantas at lower roof at the
time of execution of work in upper floors in multi storey
building. The spacing of grid shall not exceed 1 Mtr. x 1 Mtr.
(Rates are for one Month)
P.Sqm 41.00 41.00 0.00% 41.00 0.00%
10.24 Making khurras 450 x 450mm with average minimum
thickness 50mm cement concrete 1 : 2:4 over P.V.C. Sheet 1
Mtr. x 1 Mtr. x 40micron finished with 12mm cement plaster 1
: 3 and one coat of neat cement, rounding edges and making
and finishing the out let complete.

Each 130.00 130.00 0.00% 130.00 0.00%

GALVANISED IRON SHEET ROOFING

10.25 Providing corrugated G.I. Sheet roofing fixed with G.I.J. or L


hooks bolts and nuts 8mm diameter with bitumen and G.I.
limpet washers or with G.I. limpet washers filled with white
lead and including a coat of approved steel primer and two
coat of approved paint on over lapping of sheet complete
(upto a pitch of 60o) & excluding the cost of purlins rafters
and truses, for class of sheets :

10.25.1 1.60mm thick P.Sqm 1585.00 1522.00 4.14% 1,585.00 4.14%


10.25.2 1.25mm thick P.Sqm 1302.00 1237.00 5.25% 1,298.00 4.93%
10.25.3 1.00mm thick P.Sqm 1095.00 1029.00 6.41% 1,080.00 4.96%
10.25.4 0.80mm thick P.Sqm 929.00 864.00 7.52% 907.00 4.98%
10.25.5 0.63mm thick P.Sqm 788.00 723.00 8.99% 759.00 4.98%

10.26 Add extra over item No. 10.25 for providing and fixing CGI
sheets vertically or to a pitch exceeding 60o
P.Sqm 12.00 4.00 200.00% 4.00 0.00%

10.27 Add extra over item No. 10.25 for providing and fixing CGI
sheets in curved roofing
P.Sqm 13.00 4.00 225.00% 4.00 0.00%

10.28 Extra for Straight cutting in CGI sheet roofing for making
opening of area exceeding 40 dm2 for chimney stack, sky
light etc.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
P.Rmt. 80.00 33.00 142.42% 34.00 3.03%
10.29

10.30 Providing ridges or hips of width 600mm overall with plain GI


sheet fixed with GI, J or L-hooks, bolts and nuts 8mm dia GI
limpet and bitumen washers complete :

10.30.1 0.80mm thick P.Rmt. 655.00 596.00 9.90% 625.00 4.87%


10.30.2 0.63mm thick P.Rmt. 578.00 509.00 13.56% 534.00 4.91%

10.31 Providing valleys of 900mm width overall in plain GI Sheet


1.60mm thick fixed with GI,or L-hooks, bolts and nuts 8mm
dia GI limpet and bitumen washers complete.
P.Rmt. 1224.00 1185.00 3.29% 1,224.00 3.29%
10.32 Providing flashing of 40mm overall width plain GI sheet fixed
with GI, J or L-hooks, bolts and nuts 8mm dia GI limpet and
bitumen washers complete bent to shape and fixed in wall
with cement mortar 1 : 3 (1 cement : 3 coarse sand):

10.32.1 1.25mm thick sheet P.Rmt. 552.00 469.00 17.70% 492.00 4.90%
10.32.2 1.00mm thick sheet P.Rmt. 495.00 403.00 22.83% 423.00 4.96%

10.33 Providing and fixing 150mm wide 450mm overall semicircular


plain GI sheet gutter with iron brackets 40mm x 3mm size,
bolts, nuts, and washers etc. including making necessary
connection with rain water pipes complete.

10.33.1 1.25mm thick P.Rmt. 593.00 488.00 21.52% 512.00 4.92%


10.33.2 1.00mm thick P.Rmt. 583.00 477.00 22.22% 500.00 4.82%
10.33.3 0.80mm thick P.Rmt. 570.00 462.00 23.38% 485.00 4.98%
10.33.4 0.63mm thick P.Rmt. 557.00 447.00 24.61% 469.00 4.92%

A.C. SHEET ROOFING

10.34 Providing corrugated asbestos cement 6mm thick sheet


roofing and fixing with GI, J or L-hooks, bolts and nuts 8mm
dia GI plain and bitumen washers complete excluding the
cost of purlines, rafters and trusses :

10.34.1 Upto 60o pitch P.Rmt. 417.00 412.00 1.21% 417.00 1.21%
10.34.2 Above 60o pitch P.Rmt. 429.00 421.00 1.90% 429.00 1.90%

10.35 Extra for Straight cutting in AC corrugated, semi corrugated


6mm thick sheet roofing for making opening of area
exceeding 40 dm2 for chimney stacks, sky light etc.
P.Rmt. 28.00 12.00 133.33% 12.00 0.00%
10.36 Extra for Circular cutting in AC corrugated, semi corrugated
6mm thick sheet roofing for making opening of area
exceeding 40 dm2
P.Rmt. 33.00 13.00 153.85% 13.00 0.00%
10.37 Providing and fixing wind ties of required flat iron section
including making holes as required duly painted with red
oxide paint complete.
P.Kg. 80.00 80.00 0.00% 80.00 0.00%
10.38 Providing and fixing ridges and hips in asbestos cement
sheet roofing :

10.38.1 One piece plain angular ridges. P.Rmt. 250.00 250.00 0.00% 250.00 0.00%
10.38.2 Serrated or plain wing adjustable ridges P.Rmt. 295.00 282.00 4.61% 295.00 4.61%
10.38.3 Close fitting adjustable ridges P.Rmt. 350.00 350.00 0.00% 350.00 0.00%
10.38.4 North light adjustable ridges P.Rmt. 295.00 282.00 4.61% 295.00 4.61%
10.38.5 Unserrated adjustable hips. P.Rmt. 295.00 282.00 4.61% 295.00 4.61%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.39 Providing and fixing asbestos cement roofing accessories
with galvanized iron J & L-hooks, bolts & nuts and or G.I.
seem bolts and nuts GI plain and bitumen washers etc.
complete :

10.39.1 Apron flashing pieces. P.Rmt. 217.00 211.00 2.84% 217.00 2.84%
10.39.2 Eaves filler pieces. P.Rmt. 154.00 147.00 4.76% 154.00 4.76%
10.39.3 North-light & ventilator curves. P.Rmt. 301.00 294.00 2.38% 301.00 2.38%
10.39.4 Barge boards. P.Rmt. 244.00 237.00 2.95% 244.00 2.95%
10.39.5 Ridge finials P.Rmt. 133.00 133.00 0.00% 133.00 0.00%
10.39.6 Curved barge boards for North light curve. P.Rmt. 230.00 230.00 0.00% 230.00 0.00%
10.39.7 Roof lights. P.Rmt. 1116.00 1116.00 0.00% 1,116.00 0.00%
10.39.8 Expansion joints for ridges. P.Rmt. 385.00 385.00 0.00% 385.00 0.00%
10.39.9 Expansion joints for North light curves. P.Rmt. 300.00 300.00 0.00% 300.00 0.00%
10.39.10 ‘S’-type louvers. P.Rmt. 213.00 151.00 41.06% 158.00 4.64%

FALSE CEILING
10.40 Providing and fixing chir wood frame work for false ceiling of
net work of 600mm x 600mm approximately of batten size
60mm x 60mm as main rafters and 50 x 25mm as secondary
rafters with 10mm dia M.S. hangers at suitable intervals,
including coating of anti-termite treatment and fixing in wall
etc. complete in all respect :

P.Sqm 553.00 550.00 0.55% 553.00 0.55%


10.41 Providing and fixing 15 to 18 mm thick false ceiling tiles of
plaster of Paris as per approved design over wooden frame
with Brass screws complete in all respects including fixing of
exposed surface smooth with plaster of paris (excluding the
cost of wooden frame) :
10.41.1 Plain tiles . P.Sqm 1064.00 916.00 16.16% 961.00 4.91%
10.41.2 Ornamental tiles. P.Sqm 1089.00 945.00 15.24% 992.00 4.97%
10.42 Providing and fixing ceiling tiles with teak wood beading of
size 60mm x 12mm on existing & wooden frame as per
approved drawing and specification using :
10.42.1 12mm thick insulation board, like celotex tiles. P.Sqm 1092.00 1070.00 2.06% 1,092.00 2.06%
10.42.2 6mm thick insulation board. P.Sqm 826.00 804.00 2.74% 826.00 2.74%
10.42.3 3mm thick hard board. P.Sqm 747.00 721.00 3.61% 747.00 3.61%
10.42.4 12mm thick flat pressed half random perforated phenol board
tiles.
P.Sqm 826.00 804.00 2.74% 826.00 2.74%
10.42.5 3mm thick plain A.C. Sheet. P.Sqm 400.00 400.00 0.00% 400.00 0.00%

10.43 Providing and Fixing at all height all false ceiling of 12.5mm thick
tapered edge Gypsum board conforming to IS : 2095 including
providing and fixing of frame work made of special section power
pressed from M.S sheet and galvanized in accordance with zinc
coating 600 as per IS : 277 and consisting of angle cleats of 25 mm
wide x 16mm thick with flanges of 22 mm and 37 mm at 1200mm
center to center one flange fixed to the ceiling with dash fastner
12.5mm dia x 40mm long with 6mm dia bolts to the hangers of
25x25x0.5mm of required length, and other end of angle hanger
being fixed with nut and bolts to G.I. channels 45mm x 15mm x
0.9mm runnimg at the rate of

1200mm center to center to which the ceiling section 0.5mm thick


bottom wedge of 80mm with tapered flanges of 26mm each having
clips of 10.5mm at 450mm center to center shall be fixed in a
direction perpendicular to G.I. channel with connecting clips made
out of 2.64mm dia x 230mm long G.I. wire at every junction
including fixing the gypsum board with ceiling section and perimeter
channels 0.5mm thick 27mm high having flanges of 20mm and
30mm long, the perimeter of ceiling fixed to wall / partition with the
help of rawl plugs at 450mm center to center with 25mm long drive-
all screws.also including the cost of making openings for right
fittings, grills, diffusers, cutouts made with frame of perimeter
channels suitably fixed all complete as per drawing and
specifications and direction of the Engineerin-charge but the
excluding the cost of painting.

P.Sqm 1370.00 1324.00 3.47% 1,370.00 3.47%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.44 Thatch roofing 100 to 150mm thick in two layers with
bamboos rafters and sleepers in both directions and laying
complete.
P.Sqm 541.00 345.00 56.81% 362.00 4.93%
10.45 Single country tiles roofing including hips & ridges complete
over wooden batten or bamboos.
P.Sqm 367.00 238.00 54.20% 249.00 4.62%
10.46 Add extra over item No. 10.45 if Mangalore tiles are used in
place of country tiles.
P.Sqm 110.00 110.00 0.00% 110.00 0.00%
10.47 Add over item Nos. 10.45 and 10.46 if aluminium tees are
provided.
P.Sqm 66.00 66.00 0.00% 66.00 0.00%
10.48 P & F of plastic ceiling tiles with adhesive complete of
dimension of 600 x 300 as per approved design including
cleaning of surface by wire brush and filling of uneven
surface by putties etc. complete including scaffolding
complete.
P.Sqm 691.00 669.00 3.29% 691.00 3.29%
10.49 P & F of wall paper with adhesive as per approved design
and make including cleaning the surface by wire brush of
filling uneven surface by putties etc. complete including
scaffolding complete (for estimate purposes).
P.Sqm 1088.00 472.00 130.51% 495.00 4.87%
10.50 P & F Plain Fiber glass sheet ( FRP sheet fiber
Reinforcement product sheet confirming to IS:12866-1989
having minimum thickness as below Including fixing with nuts
,bolts hooks and bitumen washer etc complete.

10.50.1 1.5mm thick (Wt. 2.5 Kg./Mtr. Sq.) P.Sqm 1212.00 1204.00 0.66% 1,212.00 0.66%
10.50.2 2.0mm thick (Wt. 3.3 Kg./Mtr. Sq.) P.Sqm 1570.00 1561.00 0.58% 1,570.00 0.58%
10.50.3 3.0mm thick (Wt. 5.0 Kg./Mtr. Sq.) P.Sqm 2285.00 2276.00 0.40% 2,285.00 0.40%
10.50.4 5.0mm thick (Wt. 8.4 Kg./Mtr. Sq.) P.Sqm 3749.00 3740.00 0.24% 3,749.00 0.24%

10.51 Add extra for corrugated Fiber glass sheet as per Asbestos
cement profile/ steel profile over item No 10.50
15% 15.00%

10.52 Providing and fixing stainless steel ( Grade 304) railing made of Hollow
tubes, channels, plates etc., including welding, grinding, buffing,
polishing and making curvature (wherever required) and fitting the
same with necessary stainless steel nuts and bolts complete, i/c fixing
the railing with necessary accessories & stainless steel dash
fasteners , stainless steel bolts etc., of required size, on the top of the
floor or the side of waist slab with suitable arrangement as per
approval of Engineer-in-charge, (for payment purpose only weight of
stainless steel members shall be considered excluding fixing
accessories such as nuts, bolts, fasteners etc.).

Kg. 457.00 457.00 0.00% 457.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.53 Providing and fixing tiled false ceiling of approved materials of size
595X595 mm in true horizontal level suspended on inter locking metal
grid of hot dipped galvanized steel sections ( galvanized @ 120 grams
per sqm both side inclusive ) consisting of maIn “T” runner with
suitably spaced joints to get required length and of size 24X38 mm
made from 0.30 mm thick (minimum) sheet spaced at 1200 mm center
to center and cross “T” of size 24X25 mm made of 0.30 mm thick
(minimum) sheet, 1200 mm long spaced between main “T” at 600 mm
center to center to form a grid of 1200X600 mm and secondary cross
“T” of length 600 mm and size 24X25 mm made of 0.30 mm thick
(minimum) sheet to be interlocked at middle of the 1200X600 mm panel
to form grids of 600X600 mm and wall angle of size 24X24X0.3 mm and
laying false ceiling tiles of approved texture in the grid including,
required cutting/ making, opening for services like diffusers, grills, light
fittings, fixtures, smoke detectors etc. Main “T” runners to be
suspended from ceiling using GI slotted cleats of size 27 X 37 X 25 X
1.6 mm fixed to ceiling with 12.5 mm dia and 50 mm long dash
fasteners, 4 mm GI adjustable rods with galvanized butterfly level clips
of size 85 X 30 X 0.8 mm spaced at 1200 mm center to center along
main T, bottom exposed width of 24 mm of all T-sections shall be pre-
painted with polyester paint, all complete for all heights as per
specifications, drawings and as directed by Engineer-in-charge.

10.53.1 GI Metal Ceiling Lay in Plain Tegular edge Global white colour tiles of
size 595X595 mm, and 0.5 mm thick with 8 mm drop, made of G I Sheet
having galvanizing of 100 gms/sqm (boths ides inclusive) and electro
statically polyester powder coated of thickness 60 microns (minimum),
including factory painted after bending.

Sqm 1420.00 1420.00 0.00% 1,420.00 0.00%

10.53.2 GI Metal Ceiling Lay in perforated Tegular edge global white colour tiles
of size 595x595mm and 0.5 mm thick with 8 mm drop made of GI Sheet
having galvanizing of 100 gms/ sqm (both sides inclusive) and 20%
perforation area with 1.8 mm dia holes and having NRC (Noise
Reduction Coefficient ) of 0.5, electro statically polyester powder
coated of thickness 60 microns (minimum), including factory painted
after bending and perforation and backed with a black Glass fiber
acoustical fleece.

Sqm 1536.00 1536.00 0.00% 1,536.00 0.00%

10.54 Providing & Fixing of Mineral Fibre Anti Bacterial Suspended Ceiling System with
Bioguard (Bevelled Tegular) EDGE TILES WITH 15 mm Exposed GRID. The tiles
should have Humidity Resistance (RH) of 95% Light Reflectance 90%, Thermal
Conductivity K =0.052-0.057 w/m K, Colour White, Fire Performance UK Class
0/Class 1 (BS 476 Part 6 & 7), in module size of 600 x 600 x 15 mm with Anti
Microbial coating on the face of the tile, suitable for Green Building application,
with Recycled content of 34 % The tile shall be laid on Silhouette profile grid
system with 15 mm white/black flanges incorporating a 6 mm central reveal in
white/black colour and with a web height of 45mm and a load carrying capacity of
minimum 15.68 Kgs/M2 & minimum pull out strength of 100 kgs. Silhouette, Main
Runners & Cross Tees to have mitred ends & "birdsmouth" notches to provide
mitred cruciform junctions. The T Sections have a Galvanizing of 90 grams per
M2 and need to be installed with suspension system of make. The Tile & Grid
system used together should carry a 10 year warranty. INSTALLATION :- To
comprise main runner spaced at 1200 mm centres securely fixed to the structural
soffit using suspension system (Specifications below) at 1200mm maximum
centre. The First/Last suspension system at the end of each main runner should
not be greater than 450 mm from the adjacent wall. Flush fitting 1200 mm long
cross tees to be interlocked between main runners at 600 mm centre to form 1200
x 600 mm module. Cut cross tees longer than 600mm require independent
support. 600 x 600 mm module to be formed by fitting 600 mm long flush fitting
cross tees centrally between the 1200 mm cross tees. Perimeter trim to be wall
angles of size 3000 x 19 x 19mm, secured to walls at 450 mm maximum centres.
SUSPENSION SYSTEM accessories consisting of M6 Anchor Fasteners with
Vertical Hangers made of Galvanised steel of size 26 x 26x 25x1.2 mm with a
Galvanised Thickness of 80 gsm, A pre Straightened Hanger wire of dia-2.5 mm of
1.8 m length., thickness of 80 gsm and a tensile strength of 344-413 MPa, along
with Adjustable hook clips of 0.8 mm thick, galvanised spring steel for 2.68 mm
with a minimum pull strength of 110 kg. The adjustable clip also consists of a 3.5
mm aquiline wire to be used with the main runner.

Mtr 1561.00 1561.00 0.00% 1,561.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.55 Providing & Fixing of Mineral Fibre Acoustical Suspended Ceiling System with
(Bevelled Tegular) EDGE TILES WITH 15 mm Exposed GRID. The tiles should
have Humidity Resistance (RH) of 99% NRC 0.5, Light Reflectance _>85%,
Thermal Conductivity K =0.052-0.057 w/m K, Colour White, Fire Performance UK
Class 0/Class 1 (BS 476 Part 6 & 7), in module size of 600 x 600 x 16 mm, suitable
for Green Building application, with Recycled content of 32 %. The tile shall be
laid on Silhouette profile grid system with 15 mm white/black flanges
incorporating a 6 mm central reveal in white/black colour and with a web height of
45mm and a load carrying capacity of minimum 15.68 Kgs/Sqm minimum pull out
strength of 100 kgs. Silhouette, Main Runners & Cross Tees to have mitred ends
& "birdsmouth" notches to provide mitred cruciform junctions. The T Sections
have a Galvanizing of 90 grams per sqm and need to be installed with suspension
system of make. The Tile & Grid system used together should carry a 30 year
warranty. ISTALLATION :- To comprise main runner spaced at 1200 mm centres
securely fixed to the structural soffit using suspension system (Specifications
below) at 1200mm maximum centre. The First/Last suspension system at the end
of each main runner should not be greater than 450 mm from the adjacent wall.
Flush fitting 1200 mm long cross tees to be interlocked between main runners at
600 mm centre to form 1200 x 600 mm module. Cut cross tees longer than 600mm
require independent support. 600 x 600 mm module to be formed by fitting 600
mm long flush fitting cross tees centrally between the 1200 mm cross tees.
Perimeter trim to be wall angles of size 3000 x 19 x 19mm, secured to walls at 450
mm maximum centers. SUSPENSION SYSTEM consisting of M6 Anchor
Fasteners with Vertical Hangers made of Galvanised steel of size 26 x 26x 25x1.2
mm with a Galvanised Thickness of 80 gsm, A pre Straightened Hanger wire of
dia-2.5 mm of 1.8 m length., thickness of 80 gsm and a tensile strength of 344-413
MPa, along with Adjustable hook clips of 0.8 mm thick, galvanised spring steel for
2.68 mm with a minimum pull strength of 110 kg. The adjustable clip also consists
of a 3.5 mm aquiline wire to be used with the main runner.

Mtr 1479.00 1479.00 1,479.00

10.56
Providing and fixing 300C Aluminium Panel with perforation of 2mm
diameter and 5mm centre to centre to give 15% open area with Non
woven textile False Ceiling system of approved colour consisting of
Panel 300 mm wide X 30 mm deep X 0.7 mm thick with bevelled edges
having panel length upto 6 mtrs, Coil Coated on a Continuous Paint
Line, Double baked and roll formed for higher strength and good roll
forming characteristics. The panel ends will be raised upto 29mm.
Panel shall be clipped to a baked enamelled aluminium panel carrier of
41.5mm wide x 62mm deep x 0.95 mm thick in standard length of 5
mtrs. made of double baked stove enamelled aluminium magnesium
alloy AA3005 black with cut outs to hold the panels. The Carrier shall
be suspended by means of G.I. threaded rod of 6-mm diameter directly
fixed to the Carrier. The Carrier tabs to be bent down to secure the
panels at all Panel Carrier intersections. The panels will be installed in
a module of 300MM. (Tensile strength of suspension-344/413 mpa and
fastner strength-110kg) All Ceiling Panels shall adhere to GreenPro
Certifications.
Sqm 4314.00 4314.00 0.00% 4,314.00 0.00%

10.57 Providing and fixing of perforated Metal Tile Ceiling System comprising of Tile
of 600mm wide and 600mm long manufactured out of 0.7mm thick aluminium
alloy 3105 with beveled edge of 4.15mm width height of 32mm. The tiles shall be
perforated to 1.5mm dia with open area of 23%. The Tile will be manufactured on
advanced includes several leveling stages in the manufacturing process by
approved manufacturers. Tile ends will be raised with pips and slops to ensure
positive engagement into the spring to enable for de-mounting of individual
panels. The Tile sides will be sufficiently high to ensure a minimum deflection
across the length of Tile. All Tiles will be bevel edged. The Tile shall be epoxy
polyester powder coating in white colour. The Tile shall be cllpped into clip in
rail of 0.5mm thick GI. in form of a grid system using a cross connector. The clip
in rail shall be supported from slab by means of rigid Suspension of 4mm G .I
rod, Hold on Clamp with Clip. POWDER COATING SPECIFICATION: Aluminium
PANELS, cleaned through eco friendly cleaning ,process and powder applied
thru electrostatic charged Automatic Carona technology spray guns and cured in
combination of Infrared & hot air oven in a certified plant as Akzo International
approved applicator . Sqm 3432.00 3432.00 0.00% 3,432.00 0.00%
The powder is conforming with the performance requirements of the
AAMA2603.02 & Qualicoat Claa 1 specifications. The coating thickness
will be minimum 60 microns with properties of Salt Spray of 1500 hrs in
exposure in SST Cabinet with Minimum blister rating 8. (Tensile
strength of suspension-344/413 mpa and fastner strength-110kg) All
Ceiling Panels shall adhere to GreenPro Certifications.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.58 Providing and fixing of Un-perforated Metal Tile Ceiling System comprising of
Tile of 600mm wide and 600mm long manufactured out of 0.7mm thick
aluminium alloy 3105 with beveled edge of 4.15mm width height of 32mm. The
Tile will be manufactured on advanced equipment that includes several leveling
stages in the manufacturing process by approved manufacturers . Tile ends will
be raised with pips and slops to ensure positive engagement into the spring to
enable for de-mounting of individual panels. The Tile sides will be sufficiently
high to ensure a minimum deflection across the length of Tile. All Tiles will be
bevel edged. The Tile shall be epoxy polyester powder coating with in white
colour. The Tile shall be cllpped into clip in rail of 0.5mm thick GI. in form of a
grid system using a cross connector. The clip in rail shall be supported from
slab by means of rigid Suspension of 4mm G .I rod, Hold on Clamp with Clip.
POWDER COATING SPECIFICATION: Aluminium PANELS, cleaned through eco
friendly cleaning ,process and powder applied thru electrostatic charged
Automatic Carona technology spray guns and cured in combination of Infrared &
hot air oven in a certified plant as Akzo International approved applicator . Sqm 2896.00 2896.00 0.00% 2,896.00 0.00%
The powder is conforming with the performance requirements of the
AAMA2603.02 & Qualicoat Claa 1 specifications. The coating thickness
will be minimum 60 microns with properties of Salt Spray of 1500 hrs in
exposure in SST Cabinet with Minimum blister rating 8. (Tensile
strength of suspension-344/413 mpa and fastner strength-110kg) All
Ceiling Panels shall adhere to GreenPro Certifications.

10.59 Providing and fixing of Un perforated Antibacterial Metal Tile Ceiling


System comprising of Tile of 600mm wide and 600mm long
manufactured out of 0.7mm thick aluminium alloy 3105 with beveled
edge of 4.15mm width height of 32mm. The Tile will be manufactured
on advanced equipment that includes several leveling stages in the
manufacturing process by approved manufacturers. Tile ends will be
raised with pips and slops to ensure positive engagement into the
spring to enable for de-mounting of individual panels. The Tile sides
will be sufficiently high to ensure a minimum deflection across the
length of Tile. All Tiles will be bevel edged. The Tile shall be epoxy
polyester powder coating with ANTIBAC in white colour which is in
compliant to ROHS directive. The Tile shall be cllpped into clip in rail
of 0.5mm thick GI. in form of a grid system using a cross connector.
The clip in rail shall be supported from slab by means of rigid
Suspension of 4mm G .I rod, Hold on Clamp with Clip. POWDER
COATING SPECIFICATION: Aluminium PANELS, cleaned through eco
friendly cleaning ,process and powder applied thru electrostatic
charged Automatic Carona technology spray guns and cured in
combination of Infrared & hot air oven in a certified plant as Akzo
International approved applicator . Sqm 3743.00 3743.00 0.00% 3,743.00 0.00%
The powder is conforming with the performance requirements of the
AAMA2603.02 & Qualicoat Claa 1 specifications. The coating thickness
will be minimum 60 microns with properties of Salt Spray of 1500 hrs in
exposure in SST Cabinet with Minimum blister rating 8.
(Tensile strength of suspension-344/413 mpa and fastner strength-
110kg) All Ceiling Panels shall adhere to GreenPro Certifications.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.60 Providing and fixing of Unperforated Metal Tile Ceiling System
comprising of Tile of 600mm wide and 600mm long manufactured out
of 0.5mm thick Galvanised Iron with beveled edge of 4.15mm width
height of 32mm. The tiles shall be perforated to 1.5mm dia with open
area of 23%. The Tile will be manufactured on advanced equipment
that includes several leveling stages in the manufacturing process by
approved manufacturers. Tile ends will be raised with pips and slops
to ensure positive engagement into the spring to enable for de-
mounting of individual panels. The Tile sides will be sufficiently high
to ensure a minimum deflection across the length of Tile. All Tiles will
be bevel edged. The Tile shall be epoxy polyester powder coating in
white colour. The Tile shall be cllpped into clip in rail of 0.5mm thick
GI. in form of a grid system using a cross connector. The clip in rail
shall be supported from slab by means of rigid Suspension of 4mm
G .I rod, Hold on Clamp with Clip. POWDER COATING SPECIFICATION:
Aluminium PANELS, cleaned through eco friendly cleaning ,process
and powder applied thru electrostatic charged Automatic Carona
technology spray guns and cured in combination of Infrared & hot air
oven in a certified plant as Akzo International approved applicator . Sqm 3068.00 3068.00 0.00% 3,068.00 0.00%
The powder is conforming with the performance requirements of the
AAMA2603.02 & Qualicoat Claa 1 specifications. The coating thickness
will be minimum 60 microns with properties of Salt Spray of 1500 hrs in
exposure in SST Cabinet with Minimum blister rating 8.
(Tensile strength of suspension-344/413 mpa and fastner strength-
110kg)
All Ceiling Panels shall adhere to GreenPro Certifications.

10.61 Providing and fixing of Unperforated Metal Tile Ceiling System


comprising of Tile of 600mm wide and 600mm long manufactured out
of 0.5mm thick Galvanised Iron with beveled edge of 4.15mm width
height of 32mm. The tiles shall be plain. The Tile will be manufactured
on advanced equipment that
includes several leveling stages in the manufacturing process by
approved manufacturers. Tile ends will be raised with pips and slops
to ensure positive engagement into the spring to enable for de-
mounting of individual panels. The Tile sides will be sufficiently high
to ensure a minimum deflection across the length of Tile. All Tiles will
be bevel edged. The Tile shall be epoxy polyester powder coating in
white colour. The Tile shall be cllpped into clip in rail of 0.5mm thick
GI. in form of a grid system using a cross connector. The clip in rail
shall be supported from slab by means of rigid Suspension of 4mm
G .I rod, Hold on Clamp with Clip. POWDER COATING SPECIFICATION:
Aluminium PANELS, cleaned through eco friendly cleaning ,process
and powder applied thru electrostatic charged Automatic Carona
technology spray guns and cured in combination of Infrared & hot air
oven in a certified plant as Akzo International approved applicator .
Sqm 2313.00 2313.00 0.00% 2,313.00 0.00%
The powder is conforming with the performance requirements of the
AAMA2603.02 & Qualicoat Claa 1 specifications. The coating thickness
will be minimum 60 microns with properties of Salt Spray of 1500 hrs in
exposure in SST Cabinet with Minimum blister rating 8.
(Tensile strength of suspension-344/413 mpa and fastner strength-
110kg)
All Ceiling Panels shall adhere to GreenPro Certifications.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
10.62 Supply & Fixing of torsion spring Plank Ceiling System, comprising of
Plank of 600mm wide and 600mm long manufactured out of 0.7mm
thick Aluminium Alloy 3105 perforated 1.5mm dia With 22% open area.
The metal ceiling panels shall be downward accessible with a minimum
of four (4) torsion springs per panel . The Plank will be manufactured
on advanced CAD/CAM equipment that includes several levelling
stages in the manufacturing process. Torsion Spring panel with two
side legs die formed and two end legs die formed and punched to
receive torsion springs (min two springs each end or side) for secure
engagement into Tee Grid main runners which are factory punched to
receive torsion springs. Planks will be square edged. The metal
ceiling panels shall be downward accessible with a minimum of four (4)
torsion springs per panel. The Plank shall be Polyester powder coated
in desired colour. Main Runners: 24mm deep, inverted “Tee” sections,
3.6m long, with factory punched flanges to receive torsion spring
assembly. Main Tee on center spacing to match panel length. Cross
Runners: 24 mm deep, inverted “Tee” sections designed to interlock in
to web of main tee section on designated spacing. Cross tee length to
match panel length. Cross tees are spaced spacing 1200mm on center
maximum. Suspension System: Sqm 4775.00 4775.00 0.00% 4,775.00 0.00%
As per manufacturer standard considering type of plenum and its
height. Paint finish –
POWDER COATING SPECIFICATION: Aluminium PANELS, cleaned
through eco friendly cleaning ,process and powder applied thru
electrostatic charged Automatic Carona technology spray guns and
cured in combination of Infrared & hot air oven in a certified plant as
Akzo International approved applicator . The powder is conforming
with the performance requirements of the AAMA2603.02 & Qualicoat
Claa 1 specifications. The coating thickness will be minimum 60
microns with properties of Salt Spray of 1500 hrs in exposure in SST
Cabinet with Minimum blister rating 8 Acoustic Felt (Optional): Non-
woven felt made of glass-reinforced fibre glued over the perforation for
sound absorption. NRC- 0.7.
(Tensile strength of suspension-344/413 mpa and fastner strength-
110kg)
All Ceiling Panels shall adhere to GreenPro Certifications.

10.63 Supply & Fixing of torsion spring Plank Ceiling System, comprising of
Plank of 600mm wide and 600mm long manufactured out of 0.7mm
thick Aluminium Alloy 3105 perforated 1.5mm dia With 22% open area.
The metal ceiling panels shall be downward accessible with a minimum
of four (4) torsion springs per panel . The Plank will be manufactured
on advanced CAD/CAM equipment that includes several levelling
stages in the manufacturing process. Torsion Spring panel with two
side legs die formed and two end legs die formed and punched to
receive torsion springs (min two springs each end or side) for secure
engagement into Tee Grid main runners which are factory punched to
receive torsion springs. Planks will be square edged. The metal
ceiling panels shall be downward accessible with a minimum of four (4)
torsion springs per panel. The Plank shall be Polyester powder coated
in desired colour. Main Runners: 24mm deep, inverted “Tee” sections,
3.6m long, with factory punched flanges to receive torsion spring
assembly. Main Tee on center spacing to match panel length. Cross
Runners: 24 mm deep, inverted “Tee” sections designed to interlock in
to web of main tee section on designated spacing. Cross tee length to
match panel length. Cross tees are spaced spacing 1200mm on center
maximum. Sqm 4697.00 4697.00 0.00% 4,697.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-10
Chapter Description Proposed % Above
Code No. As per BSR Variation on
Unit Analysis Rate Rate for with BSR
2018 BSR 2018
BSR 2019 2018
Suspension System: As per manufacturer standard considering type of
plenum and its height. Paint finish –
POWDER COATING SPECIFICATION: Aluminium PANELS, cleaned
through eco friendly cleaning ,process and powder applied thru
electrostatic charged Automatic Carona technology spray guns and
cured in combination of Infrared & hot air oven in a certified plant as
Akzo International approved applicator . The powder is conforming
with the performance requirements of the AAMA2603.02 & Qualicoat
Claa 1 specifications. The coating thickness will be minimum 60
microns with properties of Salt Spray of 1500 hrs in exposure in SST
Cabinet with Minimum blister rating 8. Acoustic Felt (Optional): Non-
woven felt made of glass-reinforced fibre glued over the perforation for
sound absorption. NRC- 0.7. (Tensile strength of suspension-344/413
mpa and fastner strength-110kg)
All Ceiling Panels shall adhere to GreenPro Certifications.

10.64 Supply & Fixing of torsion spring Plank Ceiling System, comprising of
Plank of 600mm wide and 1200mm long manufactured out of 0.6mm
thick GALVANISED IRON perforated 1.5mm dia With 22% open area.
The metal ceiling panels shall be downward accessible with a minimum
of four (4) torsion springs per panel . The Plank will be manufactured
on advanced CAD/CAM equipment that includes several levelling
stages in the manufacturing process. Torsion Spring panel with two
side legs die formed and two end legs die formed and punched to
receive torsion springs (min two springs each end or side) for secure
engagement into Tee Grid main runners which are factory punched to
receive torsion springs. Planks will be square edged. The metal
ceiling panels shall be downward accessible with a minimum of four (4)
torsion springs per panel. The Plank shall be Polyester powder coated
in desired colour. Main Runners: 24mm deep, inverted “Tee” sections,
3.6m long, with factory punched flanges to receive torsion spring
assembly. Main Tee on center spacing to match panel length. Cross
Runners: 24 mm deep, inverted “Tee” sections designed to interlock in
to web of main tee section on designated spacing. Cross tee length to
match panel length. Cross tees are spaced spacing 1200mm on center
maximum. Sqm 4047.00 4047.00 0.00% 4,047.00 0.00%
Suspension System: As per manufacturer standard considering type of
plenum and its height. Paint finish –
POWDER COATING SPECIFICATION: Aluminium PANELS, cleaned
through eco friendly cleaning ,process and powder applied thru
electrostatic charged Automatic Carona technology spray guns and
cured in combination of Infrared & hot air oven in a certified plant as
Akzo International approved applicator . The powder is conforming
with the performance requirements of the AAMA2603.02 & Qualicoat
Claa 1 specifications. The coating thickness will be minimum 60
microns with properties of Salt Spray of 1500 hrs in exposure in SST
Cabinet with Minimum blister rating 8. Acoustic Felt (Optional): Non-
woven felt made of glass-reinforced fibre glued over the perforation for
sound absorption. NRC- 0.7. (Tensile strength of suspension-344/413
mpa and fastner strength-110kg)
All Ceiling Panels shall adhere to GreenPro Certifications.

56171.15 49729.00 12.95% 51099.15 2.76%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
STEEL AND FENCING WORK
CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
STEEL AND FENCING WORK

9.1 Structural steel work in single section fixed without connecting plate
including cutting, hoisting, fixing in position and applying a priming coat
of approved steel primer all complete above plinth level upto 4.5 mtr
height.

9.1.1 In flats, tees, angles and channels. P.Kg. 70.00 66.00 6.06% 69.00 4.55%
9.1.2 In R.S Joist P.Kg. 72.00 68.00 5.88% 71.00 4.41%

9.2 Structural steel work in single section fixed with connecting plate
including cutting, hoisting, fixing in position and applying a priming coat
of approved steel primer all complete above plinth level upto 4.5 mtr
height.

9.2.1 In flats, tees, angles and channels. P.Kg. 68.00 65.00 4.62% 68.00 4.62%
9.2.2 In R.S Joist P.Kg. 66.00 66.00 0.00% 66.00 0.00%
9.3 Structural steel work riveted or bolted in built up sections, trusses and
framed work, including cutting, hoisting, fixing in position and applying a
priming coat of approved steel primer all complete above plinth level upto
4.5 mtr height.

9.3.1 In flats, tees, angles and channels. P.Kg. 75.00 70.00 7.14% 73.00 4.29%
9.3.2 In R.S Joist P.Kg. 71.00 71.00 0.00% 71.00 0.00%

9.4 Structural steel work welded in built up sections, trusses and framed
work including cutting, hoisting, fixing in position and applying a priming
coat of approved steel primer all complete above plinth level upto 4.5 mtr
height.

9.4.1 In flats, tees, angles and channels. P.Kg. 71.00 68.00 4.41% 71.00 4.41%
9.4.2 In R.S Joist P.Kg. 71.00 71.00 0.00% 71.00 0.00%

9.5 Steel work in built up tubular trusses including cutting, hoisting, fixing in
position and applying a priming coat of approved steel primer, welded
and bolted including special shaped washers etc. complete above plinth
level upto 4.5 mtr height.

9.5.1 Hot finished welded type tubes. P.Kg. 105.00 87.00 20.69% 91.00 4.60%
9.5.2 Hot finished seamless type tubes. P.Kg. 100.00 100.00 0.00% 100.00 0.00%
9.5.3 Electric resistance or induction butt welded tubes. P.Kg. 105.00 105.00 0.00% 105.00 0.00%

9.6 Add extra over item No. 9.1 to 9.5 for hoisting and fixing for every P.Kg. 0.65 0.65 0.00%
0.65
0.00%
additional one metre or part thereof beyond 4.5 mtr height.

9.7 Cutting R.S. joist and rail Each 34.00 13.00 161.54% 0.00%
13.00
Hole

9.8 Drilling holes in rails, joist or M.S. plate. Each 29.00 13.00 123.08% 0.00%
13.00
Hole

9.9 Cutting bolts and rivets. Each 8.75 3.64 140.38% 0.00%
3.64
Hole

9.10 Providing and fixing M.S. rivets of all sizes in position.


P.Kg. 236.00 111.00 112.61% 116.00 4.50%
9.11 Welding by Gas plant.
P.Kg. 7.00 7.00 0.00% 7.00 0.00%
9.12 Welding by electric plant.
P.Kg. 6.00 6.00 0.00% 6.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
9.13 Providing and fixing T -iron frames for doors, windows and ventilators of
mild steel Tee-sections, joints mitred and welded with 15x3 mm lugs
10cm long embedded in cement concrete blocks 15x10x10 cm of 1 :3:6
(1 cement: 3 coarse sand: 6 graded stone aggregate 20 mm nominal
size) or with wooden plugs and screws or rawl plugs and screws or with
fixing clips or with bolts and nuts as require including fixing of necessary
butt hinges and screws and applying a priming coat of approved steel
primer.

P.Kg. 88.00 84.00 4.76% 88.00 4.76%


9.14 Providing and fixing pressed steel mitred door frames manufactured from
commercial mild steel sheet of 1.25mm (16 gauge) thickness including
hinges jamb, lock jamb, head and if required angle threshold of mild steel
angle of section 50x25mm, or base ties of 1.25mm pressed mild steel
welded or rigidly fixed together by mechanical means, adjustable lugs
with split end tail to each jamb including steel butt hinges 2.5mm thick
with mortar guards, lock strike-plate and shock absorbers as specified
and applying a coat of approved steel primer after pre-treatment of the
surface including filling with C.C 1:2:4( M-15 Grade)complete in all
respect as directed by Engineerin-charge:

9.14.1 Profile E P.Rmt. 520.00 514.00 520.00


9.14.2 Profile B P.Rmt. 453.00 421.00 7.60% 442.00 4.99%
9.14.3 Profile C P.Rmt. 508.00 459.00 10.68% 481.00 4.79%
9.15 Providing and fixing frame for doors and windows of EZ-7 ISI marks
section welded at corners and dully painted with red oxide paint, frame to
be fixed by MS flat 230 x 16 x 3mm size holdfast embedded in cement
concrete M 100 (1 : 3 : 6) block size 230 x 115 x 75mm with oxidized iron
100 mm round hinges screwed and welded complete in all respect as per
design with priming coat of red oxide.

P.Kg. 118.00 109.00 8.26% 114.00 4.59%


9.16 Supply and fixing in cement mortar welded hand railing made out of MS
round or square bars, flats etc. for staircase or verandah as per design
complete in all respect (wooden or PVC hand railing to be paid extra)
with priming coat of red oxide.
P.Kg. 90.00 85.00 5.88% 89.00 4.71%
9.17 Add extra over item No. 9.16 for fixing hand railing in lead (weight of lead
to be paid).
P.Kg. 132.00 132.00 0.00% 132.00 0.00%
9.18 Providing and fixing cow catcher made of R.S. joist angles channels MS
rounds including cutting welding and fabrication with priming coat of red
oxide (as per design).
P.Kg. 80.00 76.00 5.26% 79.00 3.95%
9.19 Providing and fixing steel gate, grating and grills made of angles, tees, square
bars, flats,or black pipe with holdfast and fittings complete as per design and
drawing including cutting welding and fabrication with priming coat of red oxide

P.Kg. 88.00 86.00 2.33% 88.00 2.33%


9.19.1 Add extra if square,rectangular hollow tubelar sections are used
P.Kg. 13.50 13.00 3.85% 13.00 0.00%

9.20 Providing and fixing in position collapsible steel shutters with vertical M.S.
Channels 20 x 10 x 2mm and bracket with flat iron diagonals 20 x 5mm. size with
top and bottom rail of T-iron 40 x 40 x 6mm. with 40mm dia steel pulleys/ball
bearing complete with bolts, nuts locking arrangements inside and outside
stoppers, handles etc. as per specification including applying a priming coat of
approved steel primer. (To be measured and paid as per outer dimension).

9.20.1 With 75mm opening when closed P.Sqm 5380.00 4140.00 29.95% 4,347.00 5.00%
9.20.2 With 100mm opening when closed P.Sqm 4600.00 4100.00 12.20% 4,305.00 5.00%

9.21 Providing and fixing 1mm thick M.S. sheet slidingshutters with frame &
diagonals braces of 40 x 40 x6mm. angle iron 3mm M.S. gusset plates at
the junction and corners, 25mm dia pulley 40x40x6mm angle and T-iron
guide at the top and bottom respectively including applying a priming
coat of approved steel primer.
P.Sqm 3036.00 2834.00 7.13% 2,975.00 4.98%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
9.22 Providing and fixing 1mm thick M.S. sheet garrage door shutters with
frame of 40 x 40 x 6mm. angle iron 3mm M.S. gusset plates at the
junction and corners including all fittings and applying a coat of approved
steel primer : (Excluding cost of frames)

9.22.1 Using M.S. angles 40 x 40 x 6mm for diagonal braces.


P.Sqm 3136.00 2955.00 6.13% 3,102.00 4.97%
9.22.2 Using M.S. Angle 35 x 35 x 5mm frame & diagonal braces.
P.Sqm 2800.00 2800.00 0.00% 2,800.00 0.00%
9.22.3 Using flats 30 x 6mm for diagonal braces and central cross piece.
P.Sqm 2750.00 2750.00 0.00% 2,750.00 0.00%
9.23 Supplying and fixing rolling shutters of approved make, made of 80 x
1.25mm. M.S. laths interlocked together through their entire length and
jointed together at the end by end locks mounted on specially designed
pipe shaft with brackets, side guides and arrangements for inside and
outside locking with push and pull operation complete including cost of
spring hooks, providing and fixing necessary 25.3cm. long wire springs
grade No. 2 and M.S. top cover 1.25mm thick for rolling shutters as per
design. (Clear openable area to be measured for payment).

P.Sqm 2050.00 2050.00 0.00% 2,050.00 0.00%


9.24 Providing & fixing ball bearing for rolling shutters
Each 330.00 330.00 0.00% 330.00 0.00%
9.25 Add extra over item No. 9.23 for providing mechanical device chain and
crank operation for operating rolling shutters.

9.25.1 Exceeding 10.00 Sqm and upto 16.80 Sqm in the area.
P.Sqm 550.00 550.00 0.00% 550.00 0.00%
9.25.2 Exceeding 16.80 Sqm in the area.
P.Sqm 600.00 600.00 0.00% 600.00 0.00%
9.26 Providing and fixing M.S. sheet single leaf door shutter in angle iron
frame 35x35x5mm suitabilly diagonally braced with 25x3mm flat iron
above and below lock rail of size 50x5mm beading extra including all
fittings, as per direction of Engg. incharge but excluding cost of
chowkhats: including two coats of anit-corrosive red oxide primer paint

9.26.1 M.S. Sheet 18 S. W.G. P.Sqm 2155.00 2155.00 0.00% 2,155.00 0.00%

9.26.2 M.S. Sheet 20 S.W.G P.Sqm 2010.00 2010.00 0.00% 2,010.00 0.00%

9.26.3 M.S. Sheet 22 S.W.G P.Sqm 1955.00 1955.00 0.00% 1,955.00 0.00%

9.26.4 M.S. Sheet 24 S.W.G P.Sqm 1840.00 1840.00 0.00% 1,840.00 0.00%

9.26.5 Add extra for double leaf shutters. 20% 20.00%

Note:- Add extra over item No. 9.21,9.22, 9.23, 9.26 for using G.I. P.Sqm 105.00 105.00 0.00% 0.00%
105.00
Sheets instead of M.S. Sheets

9.27 Providing and fixing Standard steel door fabricated out of standard rolled
section conforming to IS 1038 (revised) with glazing bars tennoned &
riveted to the frame, the bottom of shutter shall be provided with 18
gauge M.S. Sheet kicking panel, providing and fixing 4mm thick plain
float glass, aluminium handles, glazing chips etc., complete including two
coats of anti-corrosive red oxide primer paint.

9.27.1 With heavy-duly Mortice lock P.Sqm 2251.00 2168.00 3.83% 2,251.00 3.83%

9.27.2 With heavy-duty aluminum aldrops P.Sqm 2100.00 2100.00 0.00% 2,100.00 0.00%

9.27.3 Deduct from item No. 9.27.1 & 9.27.2 for providing 14 mesh x 24 guage P.Sqm 90.00 90.00 0.00%
90.00
0.00%
wire gauge instead of 4mm thick plain float glass.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
9.28 Providing and fixing steel glazed doors windows and ventilator shutters
of standard rolled steel section joints mitred and welded with steel lugs
13x3mm, 10cm. long embedded in cement concrete block 15x10x10cm.
of 1:3:6 (1cement : 3 coarse sand : 6 graded stone aggregate 20mm
nominal size) or with wooden plugs and screws or rawl plugs and screws
with fixing clips or with bolts and nuts as required including providing and
fixing of plain glass panes 4mm thick with cooper glazing clips and
special metal sash putty of approved make or metal beading with screws
complete including priming coat of approval steel primer, excluding the
cost of metal beading and other fitting except necessary hinges of pivots
steel handles peg stay etc. as required :

9.28.1 Doors P.Sqm 2400.00 2400.00 0.00% 2,400.00 0.00%


9.28.2 Windows fixed P.Sqm 2150.00 2150.00 0.00% 2,150.00 0.00%
9.28.3 Windows side hung (openable) P.Sqm 2350.00 2350.00 0.00% 2,350.00 0.00%
9.28.4 Ventilators top hung P.Sqm 2360.00 2360.00 0.00% 2,360.00 0.00%
9.28.5 Ventilators centre hung P.Sqm 2360.00 2360.00 0.00% 2,360.00 0.00%
9.28.6 In composite units of doors, windows and Ventilators. P.Sqm 2360.00 2360.00 0.00% 2,360.00 0.00%

9.28.7 For overall portion treated as fixed P.Sqm 2150.00 2127.00 1.08% 2,150.00 1.08%
9.28.8 Partly fixed and partly openable [ fixed area not to exceed 33% P.Sqm 2300.00 2300.00 0.00% 2,300.00 0.00%

9.29 Add extra over item No. 9.28 for :

9.29.1 Providing brass handles/peg stays and fittings in place of oxidized fitting P.Sqm 70.00 70.00 0.00%
70.00
0.00%

9.29.2 Aluminium handles/peg stays fitting instead of oxidized fitting. P.Sqm 65.00 65.00 0.00% 65.00 0.00%

9.29.3 5mm thick plain glass instead of 4mm thick plain glass P.Sqm 100.00 100.00 0.00% 100.00 0.00%

9.30 Deduct over item No. 9.28 for :

9.30.1 Not providing glass panels P.Sqm 350.00 350.00 0.00% 350.00 0.00%

9.30.2 Pin headed 4mm thick glass panels is used instead of 4mm thick plain P.Sqm 40.00 40.00 0.00%
40.00
0.00%
glass

9.30.3 Not provided oxidised fittings. P.Sqm 85.00 85.00 0.00% 85.00 0.00%
9.31 Supplying and fixing fixed wire gauge of 14 mesh x 24 gauge to the
metal frame of rolled section by metal beading 20x3mm with suitable
screw at not exceeding 150mm distance.
P.Sqm 787.00 698.00 12.75% 732.00 4.87%
9.32 Providing and fixing Square bars or other flat welded to window,
ventilatiors etc.
P.Sqm 73.00 68.00 7.35% 71.00 4.41%
9.33 Fixing standard steel glazed doors, windows and ventilators in walls with
15x3mm lugs 10cm long embedded in cement concrete blocks 15x10
x10 cm of 1:3:6 (1 cement: 3 coarse sand: 6 graded stone aggregate 20
mm nominal size) or with wooden plugs and screws or rawl plugs and
screws or with fixing clips or with bolts and nuts as required, including
fixing of glass panes with glazing clips and special metal-sash putty of
approved make, or metal beading with screws (only steel windows with
lugs, glass pane cut to size and glazing clips or metal beading with
screws, shall be supplied by department free of cost.)

P.Sqm 438.00 208.00 110.58% 218.00 4.81%


9.34 Providing and fixing bright finished brass casement window handles /
fasteners of minimum weight 200 grams to side hung steel windows with
necessary welding and machine screws etc. complete.
Each 68.00 68.00 0.00% 68.00 0.00%
9.35 Providing and fixing bright finished brass peg stays 300 mm long of
minimum weight 330 grams. to side hung steel windows with necessary
welding and machine screws etc. complete.
Each 101.00 101.00 0.00% 101.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
9.36 Providing and fixing bright finished brass peg stays to steel ventilators
with necessary welding and machines screws etc. complete :

9.36.1 250mm long of minimum weight of 280 grams Each 101.00 101.00 0.00% 101.00 0.00%

9.36.2 200mm long of minimum weight of 240 grams Each 62.00 62.00 0.00% 62.00 0.00%

9.37 Providing and fixing 14 mm bright finished brass spring catch to steel
centre hung ventilators with necessary welding and machine screws etc.
complete.
Each 51.00 51.00 0.00% 51.00 0.00%
9.38 Providing and fixing steel windows or ventilators with openable wire
gauge shutters of standard rolled sections shutters of standard rolled
sections confirming to I.S. 1038 (revised) joints welded i.e. Providing &
fixing fly screen of 14 mesh x 24 gauge with suitable screws to the body
by metal beading 20 x 3mm complete with projecting hinges, bars,
handles, lugs with a priming coat of red oxide paint.

P.Sqm 2159.00 2068.00 4.40% 2,159.00 4.40%


9.39 Deduct from item Nos. 9.28 & 9.38 if section used is not as per I.S. 1038
(revised)
30%
9.40 Providing and fixing welded mesh/expanded metal mesh in frame work,
flat iron beading 20x3mm including top cross laps inside and out sides
welding, iron bolts, crews, clips etc. complete (excluding frame work) of
size.

9.40.1 Welded mesh 50 x 50mm x 16 gauge. P.Sqm 803.00 749.00 7.21% 786.00 4.94%
9.40.2 Welded mesh 50 x 25mm x 16 gauge P.Sqm 581.00 526.00 10.46% 552.00 4.94%
9.40.3 Welded mesh 25 x 25mm x 16 gauge P.Sqm 803.00 749.00 7.21% 786.00 4.94%
9.40.4 Expended metal size 20 to 25 mm size 18 SWG. P.Sqm 862.00 808.00 6.68% 848.00 4.95%

9.41 Providing and fixing angle iron frame 25x25x3mm for ventilators with
fixed wire gauge 16 mesh 24 gauge incl. 100mm square bars at interval
of 100mm welded screwed to frame with mental beading 20 x 3m
complete in all respect as per design.
P.Sqm 1750.00 1750.00 0.00% 1,750.00 0.00%
9.42 Providing and fixing 20 x 6mm mild steel 15cm long clamps for securing
chick tops.
P.Sqm 41.00 41.00 0.00% 41.00 0.00%
9.43 Providing and fixing mild steel rings of 6mm round bar and 40mm
internal dia with nail for fasten in ropes of chicks.
P.Sqm 15.00 15.00 0.00% 15.00 0.00%
9.44 Providing and fixing M.S. round holding bolts with nuts and washers
complete.
P.Kg. 64.00 62.00 3.23% 64.00 3.23%
9.45 Supplying of M.S. holdfast (40mmx3mm) over all length 45 cm with
splitted (end) for doors and windows as per design.
Each 42.00 42.00 0.00% 42.00 0.00%

9.46 P & F bolts including nuts and bolts complete.


P.Kg. 60.00 60.00 0.00% 60.00 0.00%
9.47 Providing and fixing 50mm dia G.I. medium ‘B’ class railing with two
horizontal pipes and 1.5 Mtr. Long vertical pipe 1.5 Mtr. Centre to centre
with all accessories, like elbows, tees etc., including welding, thereading
and embedding in cement concrete 1:2:4 block of size 30x30x40cm. with
2 Nos. angle iron 25x25x5mm size holdfast complete as per drawings
and drawings.

P.Rmt. 1550.00 1550.00 0.00% 1,550.00 0.00%


9.48 Cast iron moulding fixing work in gate covers for fencing post etc.
P.Kg. 60.00 60.00 0.00% 60.00 0.00%
(METAL PRESSED DOORS/WINDOWS)

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
9.49 Supplying and fixing of steel doors, with frame of hollow metal pressed
section 105 x 60mm as per I.S.I. 1.25mm thick with double sheet shutter
1.00mm thick M.S. sheet to spot welded and embossed with rib type
design on both sides, front side vertical and back side horizontal and
spot welded including hold fasts of (15x3mm), M.S. oxidized fittings such
as butt hinges sliding doors bolts, handles, tower bolts etc. complete in
all respects as per drawing and specifications including applying priming
coat of approved steel primer.

P.Sqm 3213.00 3193.00 0.63% 3,213.00 0.63%


9.50 Supplying and fixing of steel doors with frame of hollow metal pressed
section (80 x 50mm) of 1.25mm thick with single sheet shutter having
thickness 0.80mm M.S. sheet to be spoet welded and embossed with rib
type design front vertical including hold fast of (15x3mm), M.S. oxidized
fittings such as hinges, sliding bolts, handles, tower bolts etc. complete in
all respects as per drawing and specifications including applying priming
coat of approved steel primer.

P.Sqm 2807.00 2786.00 0.75% 2,807.00 0.75%


9.51 Supplying and fixing of Steel windows made out (65 x 40mm), hollow
metal pressed section of 1.25mm thick sheet F4 & F7 standard rolled
section conforming to IS 1038 with wholly openable shutter of 0.80 mm
thick (out side & inside) opening C.R. sheet embossed panels, joints
matted and flush welded with suitable hinges, steel lugs & screws with
approved oxidised steel handles, fittings, peg stays (casement stays) etc.
complete in all respect including providing 10mm square M.S. bars
10cm. C/C and applying priming coat of red oxide paint.

P.Sqm 3523.00 3472.00 1.47% 3,523.00 1.47%


9.52 Supplying & fixing of M.S. louvered ventilators made out of 65 x 40mm
hollow metal pressed section 1.25mm thick sheet and louver 60mm
wide, 1.25mm thick at angle of joints mitred and flush welded with
suitable steel lugs etc. complete including applying priming coat of red
oxide paint.
P.Sqm 2400.00 2400.00 0.00% 2,400.00 0.00%
9.53 Prepainted (steel with base metal as per IS-513 with 120 GSM of Zinc
phosphating and 20 mic, of prime and polisher base paint of appvd.
shade and colour) galvanised rolled frame section mechanically
assembled glazed door with hinged or any other appvd, arrangements
for opening, approved type of stayed, P/F 5 mm thick plain glass sheets
with prepainted neosprin beading as the case may be, weather strapping
with EPDM air tight gasket lining fixed around glass and around panel
frame incl. fixing standard appvd. standard hinges, handles, locks etc.
Where ever required . as per detailed drawings of Raj. Vidhan Sabha
Bhawan Project Jaipur, including protecting the windows frame during
execution. The windows/ventilators shall be made out of CRCA material.

9.53.1 For wholly fixed windows/ventilators P.Sqm 2700.00 2700.00 0.00% 2,700.00 0.00%
9.53.2 Add extra over item 9.52.1 for openable shutter made out of
specifications and details as laid out in 9.52 (only openable panel to be
measured)
P.Sqm 660.00 660.00 0.00% 660.00 0.00%
9.54 Providing and fixing steel glazed window frame made out of 80x40 mm
hollow sheet section of 16 gauge thickness, joint mitred welded and
grinded including hold fast of steel lugs 13mm x 3mm and 15 Cm long
embedded in C C block 15 x 10 x 10 Cm of 1:3:6 nominal concrete and
including fixing of pivoted hinges of superior quality, window shutters
made out of 50 x 25.0 mm hollow steel section 15 mm paitam of 18
gauge thickness, joint mitred and grinded including 10mm x 10mm
square bars welded to frame for paitam fixing float glass 4mm thick
panes with glazing clips and metal sash putty and fixing of shutters
frames peg stay, U shape handle 100 mm long, tower bolts 100 mm long
of steel powder coated superior quality including fixing and jointing with
frame hinges priming coat with steel primer complete in all respect as per
direction of Engineer-in –charge.

9.54.1 Window fixed. P.Sqm 1450.00 1450.00 0.00% 1,450.00 0.00%

9.54.2 Window openable. P.Sqm 1875.00 1875.00 0.00% 1,875.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
FENCING WORK
9.55 180cm high fencing with angle iron post 55x55x6mm. placed at every
3Mtr. apart 45cm. in ground embedded in cement concrete 1:3:6
(30x30x60cm) corner and every tenth post to be strutted with
55x55x6mm. angle iron provided with 6 horizontal lines and two
diagonals of black barbed wire between two posts fitted and fixed with
G.I. staples including earth work in excavation etc. complete.

P.Rmt. 513.00 482.00 6.43% 506.00 4.98%

9.56 150cm high fencing with angle iron 50x50x6mm. placed at every 3Mtr.
apart 30cm. in ground embedded in cement concrete 1:3:6
(30x30x45cm) corner and every tenth post to be strutted with
50x50x6mm. angle iron provided with 6 horizontal lines and two
diagonals of black barbed wire between two posts fitted and fixed with
G.I. staples including earth work in excavation etc. complete.

P.Rmt. 460.00 460.00 0.00% 460.00 0.00%

9.57 120cm. high fencing with angle iron posts 50x50x6mm. placed at every 3
Mtr. apart 30cm. in ground embedded in cement concrete 1:3:6
(30x30x45cm) corner & every tenth posts to be strutted with 50x50x6mm
angle iron provided with three horizontal lines and two diagonals of black
barbed wire between two posts fitted and fixed with G.I. staple including
earth work in excavation etc.complete.

P.Rmt. 420.00 420.00 0.00% 420.00 0.00%

9.58 150 cm high fencing of precast R.C. posts of 15cmx15cm tapered to


10x10cm at top placed at every 3m apart 30cm in ground embedded in
cement concrete 1:3:6 (30x30x45cm) corner and every tenth posts to be
strutted with same R.C. posts provided with 6 horizontal lines and two
diagonals of black barbed wire between the two posts fitted and fixed
with G.I. staples including earth work in excavation etc. complete

P.Rmt. 320.00 301.00 6.31% 316.00 4.98%


9.59 Add or deduct for each wire line on item No. 9.55 to 9.58.
P.Rmt. 13.00 12.00 8.33% 12.00 0.00%
9.60 Add or deduct for additional or less hight per 10cm, on item No. 9.55 to
9.58.
P.Rmt. 22.00 22.00 0.00% 22.00 0.00%
9.61 Add for using galvanized barbed wire instead of black barbed wire
P.Rmt. 3.00 3.00 0.00% 0.00%
Each 3.00
wire
9.62 Supplying and fixing of chain link fencing with angle iron posts
50x50x6mm placed at every 3 Mtr. apart 30cm in ground embedded in
cement concrete 1:3:6 (30x30x45cm) corner and every tenth post to be
strutted with (50 x 50 x 6cm) angle iron provided and fixed and fitted with
posts including earth work in excavation etc. complete with chain link
size.

9.62.1 50mm x 50mm x 3.15mm P.Rmt. 715.00 690.00 3.62% 715.00 3.62%
9.62.2 75mm x 15mm x 3.15mm P.Rmt. 575.00 575.00 0.00% 575.00 0.00%
9.62.3 100mm x 100mm x 3.15mm P.Rmt. 500.00 500.00 0.00% 500.00 0.00%
9.62.4 150mm x 150mm x 3.15mm P.Rmt. 415.00 415.00 0.00% 415.00 0.00%

9.63 Supply & fixing of steel window made out 75x40 mm hollow metal
pressed section of 16 gauge thick sheet partly openable and partly fixed
panel shutter with 5 mm thick plain glass panes outside openable and
wire gauge 14x24 gauge inside openable shutter with M.S. square bar
10 mm side, fixed, portion of window should be glazed by 5 mm thick
plain glass of TG welded to M.S. frame and approved make putty with
glazing clips inching joints mitred and plug welded with suitable hinges
hold fast steel lug and screws with approved oxidized steel handles
fittings peg stays etc. complete in all respect including providing 10 mm
square MS bars 15 cm. center to cernter and applying priming coat of
red oxide paints as per approved drawing by Engineer's incharge ground
floor/ first floor.

P.Sqm 3829.00 3570.00 7.25% 3,748.00 4.99%


9.64 Providing & fixing stainless steel railing with 75cm height from floor with
75mm OD main post where necessary with 40mm OD post with 90cm
distance at stair with 50mm OD top railing pipe with fitting in all respect.
As per direction of engineer in charge.
P.Rmt. 2860.00 2731.00 4.72% 2,860.00 4.72%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-9
Chapter Description Proposed % Above
Code No. Analysis As per Variation on
Unit Rate for with BSR
Rate BSR 2018 BSR 2018
BSR 2019 2018
9.65 Supply & fixing steel shutter (Almirah type) with 18 gauge steel border &
steel shutter including locking arrangement and painting etc. complete
fixed on wall with joint fast (iron clip)
P.Sqm 1948.00 1948.00 0.00% 1,948.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


8.6 Providing and fixing fully paneled double leaf shutter for doors as per approved design and drawing Note :- Thickness of wooden panels Grade-I of respective Wood (col. No.4) shall be as under.
with approved ordinary C.P./oxidized steel fittings as per Annexure – A’ and width of styles & top rails Thickness of Doors (mm) 25 30 35 40 45 50
of 100mm and lock rails width of 150mm and bottom rails of 200mm width including teak wood Thickness of Panel (mm) 10 12 12 16 16 20
beading of size 19mmx12mm on both faces complete :
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
8.6.1 25 mm thick
(A) Nigeria teak wood grade - I Sqm. 1837.00 1837.00 1837.00 1837.00 1837.00 1837.00 1837.00
Panels 501.00 972.00 1128.00 1128.00 436.00 411.00 972.00
Fittings 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- As per Analysis 2667.00 3138.00 3294.00 3294.00 2602.00 2577.00 3138.00
2018 2496.00 2912.00 2626.00 2555.00 2360.00 2320.00 2751.00
7% 8% 25% 29% 10% 11% 14%
Proposed Rate BSR 2019 2,667.00 3,138.00 3,019.00 2,938.00 2,602.00 2,577.00 3,138.00
% Above with BSR 2018 6.85% 7.76% 14.97% 14.99% 10.25% 11.08% 14.07%

(B) Ghana teak wood grade - I Sqm. 1723.00 1723.00 1723.00 1723.00 1723.00 1723.00 1723.00
refer 1.1(A), 2.1(A) 464.00 972.00 1128.00 1128.00 436.00 411.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2516.00 3024.00 3180.00 3180.00 2488.00 2463.00 3024.00
2323.00 2781.00 2495.00 2424.00 2229.00 2189.00 2620.00
8% 9% 27% 31% 12% 13% 15%
Proposed Rate BSR 2019 2,516.00 3,024.00 2,869.00 2,787.00 2,488.00 2,463.00 3,013.00
% Above with BSR 2018 8.31% 8.74% 14.99% 14.98% 11.62% 12.52% 15.00%

(C) Sheesham wood grade - I Sqm. 1894.00 1894.00 1894.00 1894.00 1894.00 1894.00 1894.00
520.00 972.00 1128.00 1128.00 436.00 411.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2743.00 3195.00 3351.00 3351.00 2659.00 2634.00 3195.00
2351.00 2803.00 2517.00 2446.00 2251.00 2211.00 2642.00
17% 14% 33% 37% 18% 19% 21%
Proposed Rate BSR 2019 2,703.00 3,195.00 2,894.00 2,812.00 2,588.00 2,542.00 3,038.00
% Above with BSR 2018 14.97% 13.99% 14.98% 14.96% 14.97% 14.97% 14.99%

(D) Hollock wood grade - I Sqm. 1647.00 1647.00 1647.00 1647.00 1647.00 1647.00 1647.00
439.00 972.00 1128.00 1128.00 436.00 411.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2415.00 2948.00 3104.00 3104.00 2412.00 2387.00 2948.00
2206.00 2694.00 2408.00 2336.00 2142.00 2102.00 2533.00
9% 9% 29% 33% 13% 14% 16%
Proposed Rate BSR 2019 2,415.00 2,948.00 2,769.00 2,686.00 2,412.00 2,387.00 2,912.00
% Above with BSR 2018 9.47% 9.43% 14.99% 14.98% 12.61% 13.56% 14.96%
8.6.2 30 mm thick

T.A. TO S.E. AAO Superintending Engineer


Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2043.00 2043.00 2043.00 2043.00 2043.00 2043.00 2043.00 2043.00 2043.00 2043.00 2043.00 2043.00
589.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2961.00 3655.00 3344.00 3095.00 3145.00 3500.00 3018.00 3500.00 2808.00 2783.00 3406.00 3344.00
2834.00 3024.00 3149.00 2827.00 2992.00 2863.00 2846.00 2792.00 2597.00 2557.00 2917.00 2988.00
4% 21% 6% 9% 5% 22% 6% 25% 8% 9% 17% 12%
Proposed Rate BSR 2019 2,961.00 3,477.00 3,344.00 3,095.00 3,145.00 3,292.00 3,018.00 3,210.00 2,808.00 2,783.00 3,354.00 3,344.00
% Above with BSR 2018 4.48% 14.98% 6.19% 9.48% 5.11% 14.98% 6.04% 14.97% 8.12% 8.84% 14.98% 11.91%

(B) Ghana teak wood grade - I Sqm. 1907.00 1907.00 1907.00 1907.00 1907.00 1907.00 1907.00 1907.00 1907.00 1907.00 1907.00 1907.00
543.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2779.00 3519.00 3208.00 2959.00 3009.00 3364.00 2882.00 3364.00 2672.00 2647.00 3270.00 3208.00
2625.00 2868.00 2993.00 2671.00 2835.00 2707.00 2689.00 2635.00 2441.00 2401.00 2761.00 2832.00
6% 23% 7% 11% 6% 24% 7% 28% 9% 10% 18% 13%
Proposed Rate BSR 2019 2,779.00 3,298.00 3,208.00 2,959.00 3,009.00 3,113.00 2,882.00 3,030.00 2,672.00 2,647.00 3,175.00 3,208.00
% Above with BSR 2018 5.87% 14.99% 7.18% 10.78% 6.14% 15.00% 7.18% 14.99% 9.46% 10.25% 14.99% 13.28%

(C) Sheesham wood grade - I Sqm. 2110.00 2110.00 2110.00 2110.00 2110.00 2110.00 2110.00 2110.00 2110.00 2110.00 2110.00 2110.00
612.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3051.00 3722.00 3411.00 3162.00 3212.00 3567.00 3085.00 3567.00 2875.00 2850.00 3473.00 3411.00
2661.00 2894.00 3019.00 2697.00 2862.00 2733.00 2716.00 2662.00 2467.00 2427.00 2787.00 2858.00
15% 29% 13% 17% 12% 31% 14% 34% 227% 17% 25% 19%
Proposed Rate BSR 2019 3,051.00 3,328.00 3,411.00 3,101.00 3,212.00 3,142.00 3,085.00 3,061.00 2,837.00 2,791.00 3,205.00 3,286.00
% Above with BSR 2018 14.66% 15.00% 12.98% 14.98% 12.23% 14.97% 13.59% 14.99% 15.00% 15.00% 15.00% 14.98%

(D) Hollock wood grade - I Sqm. 1816.00 1816.00 1816.00 1816.00 1816.00 1816.00 1816.00 1816.00 1816.00 1816.00 1816.00 1816.00
512.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2657.00 3428.00 3117.00 2868.00 2918.00 3273.00 2791.00 3273.00 2581.00 2556.00 3179.00 3117.00
2486.00 2764.00 2889.00 2567.00 2732.00 2603.00 2586.00 2532.00 2337.00 2297.00 2657.00 2728.00
7% 24% 8% 12% 7% 26% 8% 29% 10% 11% 20% 14%
Proposed Rate BSR 2019 2,657.00 3,178.00 3,117.00 2,868.00 2,918.00 2,993.00 2,791.00 2,911.00 2,581.00 2,556.00 3,055.00 3,117.00
% Above with BSR 2018 6.88% 14.98% 7.89% 11.73% 6.81% 14.98% 7.93% 14.97% 10.44% 11.28% 14.98% 14.26%

T.A. TO S.E. AAO Superintending Engineer


8.6.3 35 mm thick
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2248.00 2248.00 2248.00 2248.00 2248.00 2248.00 2248.00 2248.00 2248.00 2248.00 2248.00 2248.00
589.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3166.00 3860.00 3549.00 3300.00 3350.00 3705.00 3223.00 3705.00 3013.00 2988.00 3611.00 3549.00
3070.00 3260.00 3385.00 3063.00 3228.00 3099.00 3082.00 3027.00 2833.00 2793.00 3153.00 3224.00
3% 18% 5% 8% 4% 20% 5% 22% 6% 7% 15% 10%
Proposed Rate BSR 2019 3,166.00 3,749.00 3,549.00 3,300.00 3,350.00 3,563.00 3,223.00 3,481.00 3,013.00 2,988.00 3,611.00 3,549.00
% Above with BSR 2018 3.13% 15.00% 4.84% 7.74% 3.78% 14.97% 4.57% 15.00% 6.35% 6.98% 14.53% 10.08%
2.28
(B) Ghana teak wood grade - I Sqm. 2091.00 2091.00 2091.00 2091.00 2091.00 2091.00 2091.00 2091.00 2091.00 2091.00 2091.00 2091.00
543.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2963.00 3703.00 3392.00 3143.00 3193.00 3548.00 3066.00 3548.00 2856.00 2831.00 3454.00 3392.00
2837.00 3079.00 3205.00 2883.00 3047.00 2918.00 2901.00 2847.00 2653.00 2612.00 2972.00 3044.00
4% 20% 6% 9% 5% 22% 6% 25% 8% 8% 16% 11%
Proposed Rate BSR 2019 2,963.00 3,540.00 3,392.00 3,143.00 3,193.00 3,355.00 3,066.00 3,274.00 2,856.00 2,831.00 3,417.00 3,392.00
% Above with BSR 2018 4.44% 14.97% 5.83% 9.02% 4.79% 14.98% 5.69% 15.00% 7.65% 8.38% 14.97% 11.43%

(C) Sheesham wood grade - I Sqm. 2327.00 2327.00 2327.00 2327.00 2327.00 2327.00 2327.00 2327.00 2327.00 2327.00 2327.00 2327.00
612.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3268.00 3939.00 3628.00 3379.00 3429.00 3784.00 3302.00 3784.00 3092.00 3067.00 3690.00 3628.00
2876.00 3109.00 3234.00 2912.00 3077.00 2948.00 2931.00 2877.00 2682.00 2642.00 3002.00 3073.00
14% 27% 12% 16% 11% 28% 13% 32% 15% 16% 23% 18%
Proposed Rate BSR 2019 3,268.00 3,575.00 3,628.00 3,348.00 3,429.00 3,390.00 3,302.00 3,308.00 3,084.00 3,038.00 3,452.00 3,533.00
% Above with BSR 2018 13.63% 14.99% 12.18% 14.97% 11.44% 14.99% 12.66% 14.98% 14.99% 14.99% 14.99% 14.97%

(D) Hollock wood grade - I Sqm. 1986.00 1986.00 1986.00 1986.00 1986.00 1986.00 1986.00 1986.00 1986.00 1986.00 1986.00 1986.00
512.00 1283.00 972.00 723.00 773.00 1128.00 646.00 1128.00 436.00 411.00 1034.00 972.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 2827.00 3598.00 3287.00 3038.00 3088.00 3443.00 2961.00 3443.00 2751.00 2726.00 3349.00 3287.00
2680.00 2958.00 3084.00 2762.00 2926.00 2797.00 2780.00 2726.00 2532.00 2492.00 2852.00 2923.00
5% 22% 7% 10% 6% 23% 7% 26% 9% 9% 17% 12%
Proposed Rate BSR 2019 2,827.00 3,401.00 3,287.00 3,038.00 3,088.00 3,216.00 2,961.00 3,134.00 2,751.00 2,726.00 3,279.00 3,287.00
% Above with BSR 2018 5.49% 14.98% 6.58% 9.99% 5.54% 14.98% 6.51% 14.97% 8.65% 9.39% 14.97% 12.45%

T.A. TO S.E. AAO Superintending Engineer


8.6.4 40 mm thick
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2453.00 2453.00 2453.00 2453.00 2453.00 2453.00 2453.00 2453.00
803.00 1283.00 723.00 773.00 646.00 436.00 411.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3585.00 4065.00 3505.00 3555.00 3428.00 3218.00 3193.00 3816.00
3484.00 3497.00 3300.00 3464.00 3318.00 3070.00 3030.00 3390.00
3% 16% 6% 3% 3% 5% 5% 13%
Proposed Rate BSR 2019 3,585.00 4,021.00 3,505.00 3,555.00 3,428.00 3,218.00 3,193.00 3,816.00
% Above with BSR 2018 2.90% 14.98% 6.21% 2.63% 3.32% 4.82% 5.38% 12.57%

(B) Ghana teak wood grade - I Sqm. 2275.00 2275.00 2275.00 2275.00 2275.00 2275.00 2275.00 2275.00
745.00 1283.00 723.00 773.00 646.00 436.00 411.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3349.00 3887.00 3327.00 3377.00 3250.00 3040.00 3015.00 3638.00
3211.00 3291.00 3094.00 3259.00 3113.00 2864.00 2824.00 3184.00
4% 18% 8% 4% 4% 6% 7% 14%
Proposed Rate BSR 2019 3,349.00 3,784.00 3,327.00 3,377.00 3,250.00 3,040.00 3,015.00 3,638.00
% Above with BSR 2018 4.30% 14.98% 7.53% 3.62% 4.40% 6.15% 6.76% 14.26%

(C) Sheesham wood grade - I Sqm. 2543.00 2543.00 2543.00 2543.00 2543.00 2543.00 2543.00 2543.00
833.00 1283.00 723.00 773.00 646.00 436.00 411.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3705.00 4155.00 3595.00 3645.00 3518.00 3308.00 3283.00 3906.00
3257.00 3325.00 3129.00 3293.00 3147.00 2899.00 2858.00 3218.00
14% 25% 15% 11% 12% 14% 15% 21%
Proposed Rate BSR 2019 3,705.00 3,823.00 3,595.00 3,645.00 3,518.00 3,308.00 3,283.00 3,700.00
% Above with BSR 2018 13.75% 14.98% 14.89% 10.69% 11.79% 14.11% 14.87% 14.98%

(D) Hollock wood grade - I Sqm. 2155.00 2155.00 2155.00 2155.00 2155.00 2155.00 2155.00 2155.00
705.00 1283.00 723.00 773.00 646.00 436.00 411.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3189.00 3767.00 3207.00 3257.00 3130.00 2920.00 2895.00 3518.00
3150.00 3627.00 3168.00 3218.00 3091.00 2881.00 2856.00 3479.00
1% 4% 1% 1% 1% 1% 1% 1%
Proposed Rate BSR 2019 3,189.00 3,767.00 3,207.00 3,257.00 3,130.00 2,920.00 2,895.00 3,518.00
% Above with BSR 2018 1.24% 3.86% 1.23% 1.21% 1.26% 1.35% 1.37% 1.12%

T.A. TO S.E. AAO Superintending Engineer


8.6.5 45 mm thick
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2659.00 2659.00 2659.00 2659.00 2659.00 2659.00
803.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3791.00 4271.00 3761.00 3634.00 3424.00 4022.00
3720.00 3732.00 3700.00 3554.00 3306.00 3625.00
2% 14% 2% 2% 4% 11%
Proposed Rate BSR 2019 3,791.00 4,271.00 3,761.00 3,634.00 3,424.00 4,022.00
% Above with BSR 2018 1.91% 14.44% 1.65% 2.25% 3.57% 10.95%

(B) Ghana teak wood grade - I Sqm. 2459.00 2459.00 2459.00 2459.00 2459.00 2459.00
745.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3533.00 4071.00 3561.00 3434.00 3224.00 3822.00
3423.00 3502.00 3470.00 3324.00 3076.00 3395.00
3% 16% 3% 3% 5% 13%
Proposed Rate BSR 2019 3,533.00 4,027.00 3,561.00 3,434.00 3,224.00 3,822.00
% Above with BSR 2018 3.21% 14.99% 2.62% 3.31% 4.81% 12.58%
2.3
(C) Sheesham wood grade - I Sqm. 2759.00 2759.00 2759.00 2759.00 2759.00 2759.00
833.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3921.00 4371.00 3861.00 3734.00 3524.00 4122.00
3473.00 3540.00 3508.00 3362.00 3114.00 3433.00
13% 23% 10% 11% 13% 20%
Proposed Rate BSR 2019 3,921.00 4,071.00 3,861.00 3,734.00 3,524.00 3,947.00
% Above with BSR 2018 12.90% 15.00% 10.06% 11.06% 13.17% 14.97%

(D) Hollock wood grade - I Sqm. 2325.00 2325.00 2325.00 2325.00 2325.00 2325.00
705.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3359.00 3937.00 3427.00 3300.00 3090.00 3688.00
3224.00 3348.00 3316.00 3170.00 2922.00 3241.00
4% 18% 3% 4% 6% 14%
Proposed Rate BSR 2019 3,359.00 3,850.00 3,427.00 3,300.00 3,090.00 3,688.00
% Above with BSR 2018 4.19% 14.99% 3.35% 4.10% 5.75% 13.79%

T.A. TO S.E. AAO Superintending Engineer


8.6.6 50 mm thick
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2864.00 1583.00 1583.00 1583.00 1583.00 1583.00
950.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 4143.00 3195.00 2685.00 2558.00 2348.00 2946.00
4104.00 2940.00 2685.00 2558.00 2348.00 2833.00
1% 9% 0% 0% 0% 4%
Proposed Rate BSR 2019 4,143.00 3,195.00 2,685.00 2,558.00 2,348.00 2,946.00
% Above with BSR 2018 0.95% 8.67% 0.00% 0.00% 0.00% 3.99%

(B) Ghana teak wood grade - I Sqm. 2642.00 2642.00 2642.00 2642.00 2642.00 2642.00
876.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3847.00 4254.00 3744.00 3617.00 3407.00 4005.00
3785.00 3714.00 3682.00 3536.00 3287.00 3607.00
2% 15% 2% 2% 4% 11%
Proposed Rate BSR 2019 3,847.00 4,254.00 3,744.00 3,617.00 3,407.00 4,005.00
% Above with BSR 2018 1.64% 14.54% 1.68% 2.29% 3.65% 11.03%

(C) Sheesham wood grade - I Sqm. 2975.00 2975.00 2975.00 2975.00 2975.00 2975.00
987.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 4291.00 4587.00 4077.00 3950.00 3740.00 4338.00
3843.00 3757.00 3724.00 3578.00 3330.00 3650.00
12% 22% 9% 10% 12% 19%
Proposed Rate BSR 2019 4,291.00 4,320.00 4,077.00 3,950.00 3,740.00 4,197.00
% Above with BSR 2018 11.66% 14.99% 9.48% 10.40% 12.31% 14.99%

(D) Hollock wood grade - I Sqm. 2494.00 2494.00 2494.00 2494.00 2494.00 2494.00
827.00 1283.00 773.00 646.00 436.00 1034.00
329.00 329.00 329.00 329.00 329.00 329.00
Total :- 3650.00 4106.00 3596.00 3469.00 3259.00 3857.00
3559.00 3544.00 3512.00 3366.00 3117.00 3437.00
3% 16% 2% 3% 5% 12%
Proposed Rate BSR 2019 3,650.00 4,075.00 3,596.00 3,469.00 3,259.00 3,857.00
% Above with BSR 2018 2.56% 14.98% 2.39% 3.06% 4.56% 12.22%

T.A. TO S.E. AAO Superintending Engineer


8.9 Providing and fixing partly paneled and partly glazed with 4 mm thick plane glass double leaf shutter Note :- Thickness of wooden panels Grade-I of respective Wood (col. No.4) shall be as under.
for doors as per approved design and drawings with approved ordinary C.P./ oxidized steel fittings as Thickness of Doors (mm) 25 30 35 40 45 50
per Annexure - ‘A’ and width of style and top rails of 100 mm and lock rail width of 150mm and Thickness of Panel (mm) 10 12 12 16 16 20
bottom rails of 200 mm width including teak wood beading of size 19 mm x 12 mm on both faces
complete :

8.9.1 25 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(A) Nigeria teak wood grade - I Sqm. 1778.00 2092.00 2196.00 2196.00 2092.00
867.33 867.33 867.33 867.33 867.33
Total :- 2645.00 2959.00 3063.00 3063.00 2959.00
2451.00 2728.00 2538.00 2490.00 2622.00
8% 8% 21% 23% 13%
Proposed Rate BSR 2019 2,645.00 2,959.00 2,918.00 2,863.00 2,959.00
% Above with BSR 2018 7.92% 8.47% 14.97% 14.98% 12.85%

(B) Ghana teak wood grade - I Sqm. 1677.33 2016.00 2120.00 2120.00 2016.00
829.33 829.33 829.33 829.33 829.33
Total :- 2507.00 2845.00 2949.00 2949.00 2845.00
2468.00 2806.00 2766.00 2712.00 2806.00
2% 1% 7% 9% 1%
Proposed Rate BSR 2019 2,507.00 2,845.00 2,949.00 2,949.00 2,845.00
% Above with BSR 2018 1.58% 1.39% 6.62% 8.74% 1.39%

(C) Sheesham wood grade - I Sqm. 1828.67 2130.00 2234.00 2234.00 2130.00
886.33 886.33 886.33 886.33 886.33
Total :- 2715.00 3016.00 3120.00 3120.00 3016.00
2318.00 2619.00 2428.00 2381.00 2512.00
17% 15% 29% 31% 20%
Proposed Rate BSR 2019 2,665.00 3,011.00 2,792.00 2,738.00 2,888.00
% Above with BSR 2018 14.97% 14.97% 14.99% 14.99% 14.97%

(D) Hollock wood grade - I Sqm. 1610.00 1965.33 2069.33 2069.33 1965.33
804.00 804.00 804.00 804.00 804.00
Total :- 2414.00 2769.00 2873.00 2873.00 2769.00
2185.00 2510.00 2319.00 2272.00 2403.00
10% 10% 24% 26% 15%
Proposed Rate BSR 2019 2,414.00 2,769.00 2,666.00 2,612.00 2,763.00
% Above with BSR 2018 10.48% 10.32% 14.96% 14.96% 14.98%

T.A. TO S.E. AAO Superintending Engineer


8.9.2 30 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(A) Nigeria teak wood grade - I Sqm. 1974.00 2436.67 2229.33 2063.33 2096.67 2333.33 2012.00 2333.33 2270.67 2229.33
936.00 936.00 936.00 936.00 936.00 936.00 936.00 936.00 936.00 936.00
Total :- 2910.00 3373.00 3165.00 2999.00 3033.00 3269.00 2948.00 3269.00 3207.00 3165.00
2755.00 2881.00 2965.00 2750.00 2861.00 2774.00 2763.00 2727.00 2810.00 2858.00
6% 17% 7% 9% 6% 18% 7% 20% 14% 11%
Proposed Rate BSR 2019 2,910.00 3,313.00 3,165.00 2,999.00 3,033.00 3,190.00 2,948.00 3,136.00 3,207.00 3,165.00
% Above with BSR 2018 5.63% 14.99% 6.75% 9.05% 6.01% 15.00% 6.70% 15.00% 14.13% 10.74%

(B) Ghana teak wood grade - I Sqm. 1852.67 2346.00 2138.67 1972.67 2006.00 2242.67 1921.33 2242.67 2180.00 2138.67
890.67 890.67 890.67 890.67 890.67 890.67 890.67 890.67 890.67 890.67
Total :- 2743.00 3237.00 3029.00 2863.00 2897.00 3133.00 2812.00 3133.00 3071.00 3029.00
2564.00 2725.00 2809.00 2594.00 2704.00 2618.00 2607.00 2571.00 2654.00 2702.00
7% 19% 8% 10% 7% 20% 8% 22% 16% 12%
Proposed Rate BSR 2019 2,743.00 3,133.00 3,029.00 2,863.00 2,897.00 3,010.00 2,812.00 2,956.00 3,052.00 3,029.00
% Above with BSR 2018 6.98% 14.97% 7.83% 10.37% 7.14% 14.97% 7.86% 14.97% 15.00% 12.10%

(C) Sheesham wood grade - I Sqm. 2034.00 2481.33 2274.00 2108.00 2141.33 2378.00 2056.67 2378.00 2315.33 2274.00
958.33 958.33 958.33 958.33 958.33 958.33 958.33 958.33 958.33 958.33
Total :- 2992.00 3440.00 3232.00 3066.00 3100.00 3336.00 3015.00 3336.00 3274.00 3232.00
2596.00 2751.00 2835.00 2620.00 2731.00 2645.00 2633.00 2597.00 2680.00 2728.00
15% 25% 14% 17% 14% 26% 15% 28% 22% 18%
Proposed Rate BSR 2019 2,985.00 3,163.00 3,232.00 3,013.00 3,100.00 3,041.00 3,015.00 2,986.00 3,082.00 3,137.00
% Above with BSR 2018 14.98% 14.98% 14.00% 15.00% 13.51% 14.97% 14.51% 14.98% 15.00% 14.99%

(D) Hollock wood grade - I Sqm. 1771.33 2285.33 2078.00 1912.00 1945.33 2182.00 1860.67 2182.00 2119.33 2078.00
860.33 860.33 860.33 860.33 860.33 860.33 860.33 860.33 860.33 860.33
Total :- 2632.00 3146.00 2938.00 2772.00 2806.00 3042.00 2721.00 3042.00 2980.00 2938.00
2436.00 2622.00 2705.00 2490.00 2601.00 2515.00 2503.00 2467.00 2550.00 2599.00
8% 20% 9% 11% 8% 21% 9% 23% 17% 13%
Proposed Rate BSR 2019 2,632.00 3,015.00 2,938.00 2,772.00 2,806.00 2,892.00 2,721.00 2,837.00 2,932.00 2,938.00
% Above with BSR 2018 8.05% 14.99% 8.61% 11.33% 7.88% 14.99% 8.71% 15.00% 14.98% 13.04%

T.A. TO S.E. AAO Superintending Engineer


8.9.3 35mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2110.67 2573.33 2366.00 2200.00 2233.33 2470.00 2148.67 2470.00 2407.33 2366.00
1004.33 1004.33 1004.33 1004.33 1004.33 1004.33 1004.33 1004.33 1004.33 1004.33
Total :- 3115.00 3578.00 3370.00 3204.00 3238.00 3474.00 3153.00 3474.00 3412.00 3370.00
2991.00 3117.00 3201.00 2986.00 3096.00 3010.00 2999.00 2963.00 3046.00 3094.00
4% 15% 5% 7% 5% 15% 5% 17% 12% 9%
Proposed Rate BSR 2019 3,115.00 3,578.00 3,370.00 3,204.00 3,238.00 3,461.00 3,153.00 3,407.00 3,412.00 3,370.00
% Above with BSR 2018 4.15% 14.79% 5.28% 7.30% 4.59% 14.98% 5.14% 14.98% 12.02% 8.92%

(B) Ghana teak wood grade - I Sqm. 1975.33 2468.67 2261.33 2095.33 2128.67 2365.33 2044.00 2365.33 2302.67 2261.33
952.00 952.00 952.00 952.00 952.00 952.00 952.00 952.00 952.00 952.00
Total :- 2927.00 3421.00 3213.00 3047.00 3081.00 3317.00 2996.00 3317.00 3255.00 3213.00
2776.00 2937.00 3021.00 2806.00 2916.00 2830.00 2818.00 2783.00 2865.00 2914.00
5% 16% 6% 9% 6% 17% 6% 19% 14% 10%
Proposed Rate BSR 2019 2,927.00 3,377.00 3,213.00 3,047.00 3,081.00 3,254.00 2,996.00 3,200.00 3,255.00 3,213.00
% Above with BSR 2018 5.44% 14.98% 6.36% 8.59% 5.66% 14.98% 6.32% 14.98% 13.61% 10.26%

(C) Sheesham wood grade - I Sqm. 2178.67 2626.00 2418.67 2252.67 2286.00 2522.67 2201.33 2522.67 2460.00 2418.67
1030.67 1030.67 1030.67 1030.67 1030.67 1030.67 1030.67 1030.67 1030.67 1030.67
Total :- 3209.00 3657.00 3449.00 3283.00 3317.00 3553.00 3232.00 3553.00 3491.00 3449.00
2811.00 2967.00 3050.00 2835.00 2946.00 2860.00 2848.00 2812.00 2895.00 2944.00
14% 23% 13% 16% 13% 24% 13% 26% 21% 17%
Proposed Rate BSR 2019 3,209.00 3,412.00 3,449.00 3,260.00 3,317.00 3,289.00 3,232.00 3,233.00 3,329.00 3,385.00
% Above with BSR 2018 14.16% 15.00% 13.08% 14.99% 12.59% 15.00% 13.48% 14.97% 14.99% 14.98%

(D) Hollock wood grade - I Sqm. 1884.67 2398.67 2191.33 2025.33 2058.67 2295.33 1974.00 2295.33 2232.67 2191.33
917.00 917.00 917.00 917.00 917.00 917.00 917.00 917.00 917.00 917.00
Total :- 2802.00 3316.00 3108.00 2942.00 2976.00 3212.00 2891.00 3212.00 3150.00 3108.00
2631.00 2816.00 2900.00 2685.00 2795.00 2709.00 2697.00 2662.00 2745.00 2793.00
6% 18% 7% 10% 6% 19% 7% 21% 15% 11%
Proposed Rate BSR 2019 2,802.00 3,238.00 3,108.00 2,942.00 2,976.00 3,115.00 2,891.00 3,061.00 3,150.00 3,108.00
% Above with BSR 2018 6.50% 14.99% 7.17% 9.57% 6.48% 14.99% 7.19% 14.99% 14.75% 11.28%

T.A. TO S.E. AAO Superintending Engineer


8.9.4 40 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2390.00 2710.00 2336.67 2370.00 2285.33 2544.00
1072.67 1072.67 1072.67 1072.67 1072.67 1072.67
Total :- 3463.00 3783.00 3409.00 3443.00 3358.00 3617.00
3346.00 3354.00 3223.00 3333.00 3236.00 3283.00
3% 13% 6% 3% 4% 10%
Proposed Rate BSR 2019 3,463.00 3,783.00 3,409.00 3,443.00 3,358.00 3,617.00
% Above with BSR 2018 3.50% 12.79% 5.77% 3.30% 3.77% 10.17%

(B) Ghana teak wood grade - I Sqm. 2232.67 2591.33 2218.00 2251.33 2166.67 2425.33
1013.33 1013.33 1013.33 1013.33 1013.33 1013.33
Total :- 3246.00 3605.00 3231.00 3265.00 3180.00 3439.00
3095.00 3148.00 3017.00 3128.00 3030.00 3077.00
5% 15% 7% 4% 5% 12%
Proposed Rate BSR 2019 3,246.00 3,605.00 3,231.00 3,265.00 3,180.00 3,439.00
% Above with BSR 2018 4.88% 14.52% 7.09% 4.38% 4.95% 11.76%

(C) Sheesham wood grade - I Sqm. 2470.00 2770.00 2396.67 2430.00 2345.33 2604.00
1102.67 1102.67 1102.67 1102.67 1102.67 1102.67
Total :- 3573.00 3873.00 3499.00 3533.00 3448.00 3707.00
3138.00 3183.00 3052.00 3162.00 3064.00 3111.00
14% 22% 15% 12% 13% 19%
Proposed Rate BSR 2019 3,573.00 3,660.00 3,499.00 3,533.00 3,448.00 3,577.00
% Above with BSR 2018 13.86% 14.99% 14.65% 11.73% 12.53% 14.98%

(D) Hollock wood grade - I Sqm. 2126.00 2511.33 2138.00 2171.33 2086.67 2345.33
973.33 973.33 973.33 973.33 973.33 973.33
Total :- 3099.00 3485.00 3111.00 3145.00 3060.00 3319.00
2929.00 3011.00 2880.00 2991.00 2893.00 2940.00
6% 16% 8% 5% 6% 13%
Proposed Rate BSR 2019 3,099.00 3,462.00 3,111.00 3,145.00 3,060.00 3,319.00
% Above with BSR 2018 5.80% 14.98% 8.02% 5.15% 5.77% 12.89%

T.A. TO S.E. AAO Superintending Engineer


8.9.5 45 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2527.33 2847.33 2507.33 2422.67 2681.33
1141.33 1141.33 1141.33 1141.33 1141.33
Total :- 3669.00 3989.00 3649.00 3564.00 3823.00
3582.00 3590.00 3569.00 3471.00 3519.00
2% 11% 2% 3% 9%
Proposed Rate BSR 2019 3,669.00 3,989.00 3,649.00 3,564.00 3,823.00
% Above with BSR 2018 2.43% 11.11% 2.24% 2.68% 8.64%

(B) Ghana teak wood grade - I Sqm. 2355.33 2714.00 2374.00 2289.33 2548.00
1074.67 1074.67 1074.67 1074.67 1074.67
Total :- 3430.00 3789.00 3449.00 3364.00 3623.00
3307.00 3360.00 3339.00 3241.00 3289.00
4% 13% 3% 4% 10%
Proposed Rate BSR 2019 3,430.00 3,789.00 3,449.00 3,364.00 3,623.00
% Above with BSR 2018 3.72% 12.77% 3.29% 3.80% 10.16%

(C) Sheesham wood grade - I Sqm. 2614.00 2914.00 2574.00 2489.33 2748.00
1174.67 1174.67 1174.67 1174.67 1174.67
Total :- 3789.00 4089.00 3749.00 3664.00 3923.00
3353.00 3398.00 3377.00 3279.00 3326.00
13% 20% 11% 12% 18%
Proposed Rate BSR 2019 3,789.00 3,907.00 3,749.00 3,664.00 3,824.00
% Above with BSR 2018 13.00% 14.98% 11.02% 11.74% 14.97%

(D) Hollock wood grade - I Sqm. 2239.33 2624.67 2284.67 2200.00 2458.67
1030.00 1030.00 1030.00 1030.00 1030.00
Total :- 3269.00 3655.00 3315.00 3230.00 3489.00
3123.00 3206.00 3185.00 3087.00 3134.00
5% 14% 4% 5% 11%
Proposed Rate BSR 2019 3,269.00 3,655.00 3,315.00 3,230.00 3,489.00
% Above with BSR 2018 4.67% 14.00% 4.08% 4.63% 11.33%

T.A. TO S.E. AAO Superintending Engineer


8.9.6 50 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2762.00 2130.00 1790.00 1705.33 1964.00
782.67 782.67 782.67 782.67 782.67
Total :- 3545.00 2913.00 2573.00 2488.00 2747.00
3519.00 2797.00 2573.00 2488.00 2726.00
1% 4% 0% 0% 1%
Proposed Rate BSR 2019 3,545.00 2,913.00 2,573.00 2,488.00 2,747.00
% Above with BSR 2018 0.74% 4.15% 0.00% 0.00% 0.77%

(B) Ghana teak wood grade - I Sqm. 2564.67 2836.00 2496.00 2411.33 2670.00
1135.67 1135.67 1135.67 1135.67 1135.67
Total :- 3700.00 3972.00 3632.00 3547.00 3806.00
3620.00 3571.00 3551.00 3453.00 3500.00
2% 11% 2% 3% 9%
Proposed Rate BSR 2019 3,700.00 3,972.00 3,632.00 3,547.00 3,806.00
% Above with BSR 2018 2.21% 11.23% 2.28% 2.72% 8.74%

(C) Sheesham wood grade - I Sqm. 2860.67 3058.00 2718.00 2633.33 2892.00
1246.67 1246.67 1246.67 1246.67 1246.67
Total :- 4107.00 4305.00 3965.00 3880.00 4139.00
3671.00 3614.00 3593.00 3496.00 3543.00
12% 19% 10% 11% 17%
Proposed Rate BSR 2019 4,107.00 4,156.00 3,965.00 3,880.00 4,074.00
% Above with BSR 2018 11.88% 15.00% 10.35% 10.98% 14.99%

(D) Hollock wood grade - I Sqm. 2433.33 2737.33 2397.33 2312.67 2571.33
1086.33 1086.33 1086.33 1086.33 1086.33
Total :- 3520.00 3824.00 3484.00 3399.00 3658.00
3412.00 3401.00 3381.00 3283.00 3330.00
3% 12% 3% 4% 10%
Proposed Rate BSR 2019 3,520.00 3,824.00 3,484.00 3,399.00 3,658.00
% Above with BSR 2018 3.17% 12.44% 3.05% 3.53% 9.85%

T.A. TO S.E. AAO Superintending Engineer


8.12 Providing and fixing fully paneled double leaf shutters for windows and ventilators as per approved Note :- Thickness of wooden panels Grade-I of respective Wood (col. No.4) shall be as under.
design and drawings with approved steel fittings as per Annexure ‘A’ and width of styles, bottom and Thick ness of Doors (mm) 25 30 35 40 45 50
top rails 75 mm including beading of 25mm x 15mm size on both faces. Thickness of Panel (mm) 10 12 12 16 16 20

8.12.1 25 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(A) Nigeria teak wood grade - I Sqm. 1770.00 1770.00 1770.00 1770.00 1770.00 1770.00 1770.00
679.00 1158.00 1344.00 1344.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 2893.00 3372.00 3558.00 3558.00 2734.00 3446.00 3372.00
2710.00 3145.00 2803.00 2718.00 2487.00 2866.00 2953.00
7% 7% 27% 31% 10% 20% 14%
Proposed Rate BSR 2019 2,893.00 3,372.00 3,223.00 3,125.00 2,734.00 3,295.00 3,372.00
% Above with BSR 2018 6.75% 7.22% 14.98% 14.97% 9.93% 14.97% 14.19%

(B) Ghana teak wood grade - I Sqm. 1887.00 1887.00 1887.00 1887.00 1887.00 1887.00 1887.00
631.00 1158.00 1344.00 1344.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 2962.00 3489.00 3675.00 3675.00 2851.00 3563.00 3489.00
2789.00 3279.00 2938.00 2853.00 2622.00 3001.00 3087.00
6% 6% 25% 29% 9% 19% 13%
Proposed Rate BSR 2019 2,962.00 3,489.00 3,378.00 3,280.00 2,851.00 3,451.00 3,489.00
% Above with BSR 2018 6.20% 6.40% 14.98% 14.97% 8.73% 15.00% 13.02%

(C) Sheesham wood grade - I Sqm. 1946.00 1946.00 1946.00 1946.00 1946.00 1946.00 1946.00
703.00 1158.00 1344.00 1344.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3093.00 3548.00 3734.00 3734.00 2910.00 3622.00 3548.00
2686.00 3167.00 2825.00 2740.00 2509.00 2888.00 2975.00
15% 12% 32% 36% 16% 25% 19%
Proposed Rate BSR 2019 3,088.00 3,548.00 3,248.00 3,151.00 2,885.00 3,321.00 3,421.00
% Above with BSR 2018 14.97% 12.03% 14.97% 15.00% 14.99% 14.99% 14.99%

(D) Hollock wood grade - I Sqm. 1692.00 1692.00 1692.00 1692.00 1692.00 1692.00 1692.00
599.00 1158.00 1344.00 1344.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 2735.00 3294.00 3480.00 3480.00 2656.00 3368.00 3294.00
2527.00 3054.00 2712.00 2627.00 2396.00 2776.00 2862.00
8% 8% 28% 32% 11% 21% 15%
Proposed Rate BSR 2019 2,735.00 3,294.00 3,118.00 3,021.00 2,656.00 3,192.00 3,291.00
% Above with BSR 2018 8.23% 7.86% 14.97% 15.00% 10.85% 14.99% 14.99%

T.A. TO S.E. AAO Superintending Engineer


8.12.2 30 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(A) Nigeria teak wood grade - I Sqm. 1966.00 1966.00 1966.00 1966.00 1966.00 1966.00 1966.00 1966.00 1966.00 1966.00 1966.00 1966.00
769.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3179.00 3939.00 3568.00 3272.00 3331.00 3754.00 3179.00 3754.00 2930.00 2901.00 3642.00 3568.00
3039.00 3221.00 3370.00 2986.00 3182.00 3029.00 3007.00 2944.00 2712.00 2666.00 3092.00 3178.00
5% 22% 6% 10% 5% 24% 6% 28% 8% 9% 18% 12%
Proposed Rate BSR 2019 3,179.00 3,704.00 3,568.00 3,272.00 3,331.00 3,483.00 3,179.00 3,385.00 2,930.00 2,901.00 3,555.00 3,568.00
% Above with BSR 2018 4.61% 15.00% 5.88% 9.58% 4.68% 14.99% 5.72% 14.98% 8.04% 8.81% 14.97% 12.27%

(B) Ghana teak wood grade - I Sqm. 2106.00 2106.00 2106.00 2106.00 2106.00 2106.00 2106.00 2106.00 2106.00 2106.00 2106.00 2106.00
711.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3261.00 4079.00 3708.00 3412.00 3471.00 3894.00 3319.00 3894.00 3070.00 3041.00 3782.00 3708.00
3133.00 3382.00 3531.00 3147.00 3343.00 3190.00 3168.00 3105.00 2873.00 2827.00 3253.00 3339.00
4% 21% 5% 8% 4% 22% 5% 25% 7% 8% 16% 11%
Proposed Rate BSR 2019 3,261.00 3,889.00 3,708.00 3,412.00 3,471.00 3,668.00 3,319.00 3,570.00 3,070.00 3,041.00 3,740.00 3,708.00
% Above with BSR 2018 4.09% 14.99% 5.01% 8.42% 3.83% 14.98% 4.77% 14.98% 6.86% 7.57% 14.97% 11.05%

(C) Sheesham wood grade - I Sqm. 2177.00 2177.00 2177.00 2177.00 2177.00 2177.00 2177.00 2177.00 2177.00 2177.00 2177.00 2177.00
798.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3419.00 4150.00 3779.00 3483.00 3542.00 3965.00 3390.00 3965.00 3141.00 3112.00 3853.00 3779.00
3010.00 3247.00 3397.00 3013.00 3208.00 3055.00 3033.00 2970.00 2739.00 2693.00 3118.00 3205.00
14% 28% 11% 16% 10% 30% 12% 34% 15% 16% 24% 18%
Proposed Rate BSR 2019 3,419.00 3,734.00 3,779.00 3,464.00 3,542.00 3,513.00 3,390.00 3,415.00 3,141.00 3,096.00 3,585.00 3,685.00
% Above with BSR 2018 13.59% 15.00% 11.25% 14.97% 10.41% 14.99% 11.77% 14.98% 14.68% 14.96% 14.98% 14.98%

(D) Hollock wood grade - I Sqm. 1873.00 1873.00 1873.00 1873.00 1873.00 1873.00 1873.00 1873.00 1873.00 1873.00 1873.00 1873.00
673.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 2990.00 3846.00 3475.00 3179.00 3238.00 3661.00 3086.00 3661.00 2837.00 2808.00 3549.00 3475.00
2820.00 3113.00 3262.00 2878.00 3073.00 2921.00 2899.00 2835.00 2604.00 2558.00 2984.00 3070.00
6% 24% 7% 10% 5% 25% 6% 29% 9% 10% 19% 13%
Proposed Rate BSR 2019 2,990.00 3,579.00 3,475.00 3,179.00 3,238.00 3,359.00 3,086.00 3,260.00 2,837.00 2,808.00 3,431.00 3,475.00
% Above with BSR 2018 6.03% 14.97% 6.53% 10.46% 5.37% 14.99% 6.45% 14.99% 8.95% 9.77% 14.98% 13.19%

T.A. TO S.E. AAO Superintending Engineer


8.12.3 35 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(A) Nigeria teak wood grade - I Sqm. 2162.00 2162.00 2162.00 2162.00 2162.00 2162.00 2162.00 2162.00 2162.00 2162.00 2162.00 2162.00
769.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3375.00 4135.00 3764.00 3468.00 3527.00 3950.00 3375.00 3950.00 3126.00 3097.00 3838.00 3764.00
3264.00 3446.00 3596.00 3211.00 3407.00 3254.00 3232.00 3169.00 2938.00 2892.00 3317.00 3404.00
3% 20% 5% 8% 4% 21% 4% 25% 6% 7% 16% 11%
Proposed Rate BSR 2019 3,375.00 3,962.00 3,764.00 3,468.00 3,527.00 3,742.00 3,375.00 3,644.00 3,126.00 3,097.00 3,814.00 3,764.00
% Above with BSR 2018 3.40% 14.97% 4.67% 8.00% 3.52% 15.00% 4.42% 14.99% 6.40% 7.09% 14.98% 10.58%

(B) Ghana teak wood grade - I Sqm. 2326.00 2326.00 2326.00 2326.00 2326.00 2326.00 2326.00 2326.00 2326.00 2326.00 2326.00 2326.00
711.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3481.00 4299.00 3928.00 3632.00 3691.00 4114.00 3539.00 4114.00 3290.00 3261.00 4002.00 3928.00
3385.00 3634.00 3783.00 3399.00 3594.00 3441.00 3420.00 3356.00 3125.00 3079.00 3505.00 3591.00
3% 18% 4% 7% 3% 20% 3% 23% 5% 6% 14% 9%
Proposed Rate BSR 2019 3,481.00 4,179.00 3,928.00 3,632.00 3,691.00 3,957.00 3,539.00 3,859.00 3,290.00 3,261.00 4,002.00 3,928.00
% Above with BSR 2018 2.84% 15.00% 3.83% 6.85% 2.70% 15.00% 3.48% 14.99% 5.28% 5.91% 14.18% 9.38%

(C) Sheesham wood grade - I Sqm. 2407.00 2407.00 2407.00 2407.00 2407.00 2407.00 2407.00 2407.00 2407.00 2407.00 2407.00 2407.00
798.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3649.00 4380.00 4009.00 3713.00 3772.00 4195.00 3620.00 4195.00 3371.00 3342.00 4083.00 4009.00
3240.00 3477.00 3627.00 3243.00 3438.00 3285.00 3263.00 3200.00 2969.00 2923.00 3348.00 3435.00
13% 26% 11% 14% 10% 28% 11% 31% 14% 14% 22% 17%
Proposed Rate BSR 2019 3,649.00 3,998.00 4,009.00 3,713.00 3,772.00 3,777.00 3,620.00 3,680.00 3,371.00 3,342.00 3,850.00 3,950.00
% Above with BSR 2018 12.62% 14.98% 10.53% 14.49% 9.71% 14.98% 10.94% 15.00% 13.54% 14.33% 14.99% 14.99%

(D) Hollock wood grade - I Sqm. 2053.00 2053.00 2053.00 2053.00 2053.00 2053.00 2053.00 2053.00 2053.00 2053.00 2053.00 2053.00
673.00 1529.00 1158.00 862.00 921.00 1344.00 769.00 1344.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3170.00 4026.00 3655.00 3359.00 3418.00 3841.00 3266.00 3841.00 3017.00 2988.00 3729.00 3655.00
3029.00 3321.00 3470.00 3086.00 3282.00 3129.00 3107.00 3044.00 2812.00 2766.00 3192.00 3278.00
5% 21% 5% 9% 4% 23% 5% 26% 7% 8% 17% 12%
Proposed Rate BSR 2019 3,170.00 3,819.00 3,655.00 3,359.00 3,418.00 3,598.00 3,266.00 3,500.00 3,017.00 2,988.00 3,670.00 3,655.00
% Above with BSR 2018 4.66% 15.00% 5.33% 8.85% 4.14% 14.99% 5.12% 14.98% 7.29% 8.03% 14.97% 11.50%

T.A. TO S.E. AAO Superintending Engineer


8.12.4 40 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(A) Nigeria teak wood grade - I Sqm. 2358.00 2358.00 2358.00 2358.00 2358.00 2358.00 2358.00 2358.00 2358.00
1095.00 1529.00 862.00 921.00 769.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3897.00 4331.00 3664.00 3723.00 3571.00 3322.00 3293.00 4034.00 3960.00
3762.00 3671.00 3437.00 3632.00 3458.00 3163.00 3117.00 3543.00 3629.00
4% 18% 7% 3% 3% 5% 6% 14% 9%
Proposed Rate BSR 2019 3,897.00 4,221.00 3,664.00 3,723.00 3,571.00 3,322.00 3,293.00 4,034.00 3,960.00
% Above with BSR 2018 3.59% 14.98% 6.60% 2.51% 3.27% 5.03% 5.65% 13.86% 9.12%

(B) Ghana teak wood grade - I Sqm. 2545.00 2545.00 2545.00 2545.00 2545.00 2545.00 2545.00 2545.00 2545.00
1019.00 1529.00 862.00 921.00 769.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4008.00 4518.00 3851.00 3910.00 3758.00 3509.00 3480.00 4221.00 4147.00
3888.00 3885.00 3651.00 3846.00 3671.00 3377.00 3331.00 3757.00 3843.00
3% 16% 5% 2% 2% 4% 4% 12% 8%
Proposed Rate BSR 2019 4,008.00 4,467.00 3,851.00 3,910.00 3,758.00 3,509.00 3,480.00 4,221.00 4,147.00
% Above with BSR 2018 3.09% 14.98% 5.48% 1.66% 2.37% 3.91% 4.47% 12.35% 7.91%

(C) Sheesham wood grade - I Sqm. 2638.00 2638.00 2638.00 2638.00 2638.00 2638.00 2638.00 2638.00 2638.00
1134.00 1529.00 862.00 921.00 769.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4216.00 4611.00 3944.00 4003.00 3851.00 3602.00 3573.00 4314.00 4240.00
3724.00 3707.00 3473.00 3668.00 3493.00 3199.00 3153.00 3578.00 3665.00
13% 24% 14% 9% 10% 13% 13% 21% 16%
Proposed Rate BSR 2019 4,216.00 4,263.00 3,944.00 4,003.00 3,851.00 3,602.00 3,573.00 4,114.00 4,214.00
% Above with BSR 2018 13.21% 15.00% 13.56% 9.13% 10.25% 12.60% 13.32% 14.98% 14.98%

(D) Hollock wood grade - I Sqm. 2234.00 2234.00 2234.00 2234.00 2234.00 2234.00 2234.00 2234.00 2234.00
968.00 1529.00 862.00 921.00 769.00 520.00 491.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3646.00 4207.00 3540.00 3599.00 3447.00 3198.00 3169.00 3910.00 3836.00
3473.00 3529.00 3294.00 3490.00 3315.00 3021.00 2975.00 3400.00 3486.00
5% 19% 7% 3% 4% 6% 7% 15% 10%
Proposed Rate BSR 2019 3,646.00 4,058.00 3,540.00 3,599.00 3,447.00 3,198.00 3,169.00 3,910.00 3,836.00
% Above with BSR 2018 4.98% 14.99% 7.47% 3.12% 3.98% 5.86% 6.52% 15.00% 10.04%

T.A. TO S.E. AAO Superintending Engineer


8.12.5 45 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

(A) Nigeria teak wood grade - I Sqm. 2555.00 2555.00 2555.00 2555.00 2555.00 2555.00 2555.00 2555.00
1095.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4094.00 4528.00 3861.00 3920.00 3768.00 3519.00 4231.00 4157.00
3988.00 3897.00 3662.00 3858.00 3683.00 3389.00 3768.00 3854.00
3% 16% 5% 2% 2% 4% 12% 8%
Proposed Rate BSR 2019 4,094.00 4,481.00 3,861.00 3,920.00 3,768.00 3,519.00 4,231.00 4,157.00
% Above with BSR 2018 2.66% 14.99% 5.43% 1.61% 2.31% 3.84% 12.29% 7.86%

(B) Ghana teak wood grade - I Sqm. 2764.00 2764.00 2764.00 2764.00 2764.00 2764.00 2764.00 2764.00
1019.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4227.00 4737.00 4070.00 4129.00 3977.00 3728.00 4440.00 4366.00
4141.00 4138.00 3904.00 4099.00 3924.00 3630.00 4010.00 4096.00
2% 14% 4% 1% 1% 3% 11% 7%
Proposed Rate BSR 2019 4,227.00 4,737.00 4,070.00 4,129.00 3,977.00 3,728.00 4,440.00 4,366.00
% Above with BSR 2018 2.08% 14.48% 4.25% 0.73% 1.35% 2.70% 10.72% 6.59%

(C) Sheesham wood grade - I Sqm. 2869.00 2869.00 2869.00 2869.00 2869.00 2869.00 2869.00 2869.00
1134.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4447.00 4842.00 4175.00 4234.00 4082.00 3833.00 4545.00 4471.00
3954.00 3937.00 3703.00 3898.00 3723.00 3429.00 3808.00 3895.00
12% 23% 13% 9% 10% 12% 19% 15%
Proposed Rate BSR 2019 4,447.00 4,527.00 4,175.00 4,234.00 4,082.00 3,833.00 4,379.00 4,471.00
% Above with BSR 2018 12.47% 14.99% 12.75% 8.62% 9.64% 11.78% 14.99% 14.79%

(D) Hollock wood grade - I Sqm. 2415.00 2415.00 2415.00 2415.00 2415.00 2415.00 2415.00 2415.00
968.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 3827.00 4388.00 3721.00 3780.00 3628.00 3379.00 4091.00 4017.00
3680.00 3736.00 3501.00 3697.00 3522.00 3228.00 3607.00 3693.00
4% 17% 6% 2% 3% 5% 13% 9%
Proposed Rate BSR 2019 3,827.00 4,296.00 3,721.00 3,780.00 3,628.00 3,379.00 4,091.00 4,017.00
% Above with BSR 2018 3.99% 14.99% 6.28% 2.25% 3.01% 4.68% 13.42% 8.77%

T.A. TO S.E. AAO Superintending Engineer


8.12.6 50 mm thick.
Ch. Description Unit Wood 12 mm thick 9 mm thick 12 mm thick 12 mm thick 9 mm thick 12 mm thick 9 mm thick 4 mm thick Wire gauge 24 12 mm thick 9 mm thick
Code grade-I teak ply teak ply particle shuttering shuttering commercial commercial plain glass gauge 14 teak ply teak teak
No. panels (both faces (both faces board panels ply ply ply ply panels mesh of IS (one face ply
panels) panels) (Urea boned) (both faces (both faces (both faces (both faces designation panels) (one face
panels) panels) panels) panels) 85 gauge wires panels)
(Urea (Urea of dia 0.56 mm
bonded) bonded) panels

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(A) Nigeria teak wood grade - I Sqm. 2741.00 2741.00 2741.00 2741.00 2741.00 2741.00 2741.00 2741.00
1277.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4462.00 4714.00 4047.00 4106.00 3954.00 3705.00 4417.00 4343.00
4412.00 4112.00 3877.00 4073.00 3898.00 3604.00 3983.00 4069.00
1% 15% 4% 1% 1% 3% 11% 7%
Proposed Rate BSR 2019 4,462.00 4,714.00 4,047.00 4,106.00 3,954.00 3,705.00 4,417.00 4,343.00
% Above with BSR 2018 1.13% 14.64% 4.38% 0.81% 1.44% 2.80% 10.90% 6.73%

(B) Ghana teak wood grade - I Sqm. 2983.00 2983.00 2983.00 2983.00 2983.00 2983.00 2983.00 2983.00
1182.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4609.00 4956.00 4289.00 4348.00 4196.00 3947.00 4659.00 4585.00
4580.00 4390.00 4156.00 4328.00 4176.00 3882.00 4261.00 4348.00
1% 13% 3% 0% 0% 2% 9% 5%
Proposed Rate BSR 2019 4,609.00 4,956.00 4,289.00 4,348.00 4,196.00 3,947.00 4,659.00 4,585.00
% Above with BSR 2018 0.63% 12.89% 3.20% 0.46% 0.48% 1.67% 9.34% 5.45%

(C) Sheesham wood grade - I Sqm. 3100.00 3100.00 3100.00 3100.00 3100.00 3100.00 3100.00 3100.00
1325.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4869.00 5073.00 4406.00 4465.00 4313.00 4064.00 4776.00 4702.00
4375.00 4167.00 3933.00 4128.00 3953.00 3659.00 4038.00 4125.00
11% 22% 12% 8% 9% 11% 18% 14%
Proposed Rate BSR 2019 4,869.00 4,792.00 4,406.00 4,465.00 4,313.00 4,064.00 4,643.00 4,702.00
% Above with BSR 2018 11.29% 15.00% 12.03% 8.16% 9.11% 11.07% 14.98% 13.99%

(D) Hollock wood grade - I Sqm. 2596.00 2596.00 2596.00 2596.00 2596.00 2596.00 2596.00 2596.00
1118.00 1529.00 862.00 921.00 769.00 520.00 1232.00 1158.00
444.00 444.00 444.00 444.00 444.00 444.00 444.00 444.00
Total :- 4158.00 4569.00 3902.00 3961.00 3809.00 3560.00 4272.00 4198.00
4060.00 3944.00 3709.00 3905.00 3730.00 3436.00 3815.00 3901.00
2% 16% 5% 1% 2% 4% 12% 8%
Proposed Rate BSR 2019 4,158.00 4,535.00 3,902.00 3,961.00 3,809.00 3,560.00 4,272.00 4,198.00
% Above with BSR 2018 2.41% 14.98% 5.20% 1.43% 2.12% 3.61% 11.98% 7.61%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
WOOD WORK
CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
WOOD WORK
8.1 Supplying & fixing door, window, chowkhats and other
frames, including antitermite treatment, M.S. flat, hold fasts
of size 250 x 40 x 3mm fixed with M.S. bolt 5mm dia 50mm
long duly embedded in cement concrete M-15 grade :

8.1.1 Nigeria teak wood Grade - I.


P.Cum 82234.00 75211.00 9.34% 78,971.00 5.00%
8.1.2 Ghana teak wood Grade - I.
P.Cum 75533.00 68510.00 10.25% 71,935.00 5.00%
8.1.3 Sal wood Grade - I.
P.Cum 80001.00 71860.00 11.33% 75,453.00 5.00%
8.1.4 Sheesham wood Grade - I.
P.Cum 85585.00 69627.00 22.92% 73,108.00 5.00%
8.1.5 Chir wood Grade - I.
P.Cum 77767.00 68510.00 13.51% 71,935.00 5.00%
8.1.6 Hollock wood Grade - I.
P.Cum 71066.00 64042.00 10.97% 67,244.00 5.00%

8.2 Supplying and fixing wood work in frames of wall panelling,


false ceiling partition wall etc. as per approved design and
drawing including antitermite treatment.

8.2.1 Nigeria teak wood Grade - I.


P.Cum 69501.00 69167.00 0.48% 69,501.00 0.48%
8.2.2 Ghana teak wood Grade - I.
P.Cum 62831.00 62497.00 0.53% 62,831.00 0.53%
8.2.3 Hollock wood Grade - I.
P.Cum 58385.00 58050.00 0.58% 58,385.00 0.58%
8.2.4 Chir wood Grade - I.
P.Cum 65055.00 64720.00 0.52% 65,055.00 0.52%

8.3 Deduct from item Nos. 8.1 and 8.2 if inferior than Grade - I
wood is used.
20% 20%
8.4 Add extra over item no. 8.1 for wood work for stair case
railing.
10% 10%
8.5 Add extra in frames for circular members such as in fan
lights, staircase railing etc.
10% 10%
8.6 Table 8A
8.7 Add extra over item No. 8.6 for :
8.7.1 Using phenol bonded exterior grade particle board instead of
Urea bonded, in column No. 7.
P.Sqm 25.00 25.00 0.00% 25.00 0.00%
8.7.2 One side teak face particle board, in column No.7
P.Sqm 166.00 166.00 0.00% 166.00 0.00%
8.7.3 Both sides teak face particle board, in column No. 7
P.Sqm 249.00 249.00 0.00% 249.00 0.00%

8.7.4 One sides laminated face particle board, in column No. 7

P.Sqm 168.00 168.00 0.00% 168.00 0.00%


8.7.5 Both sides laminated face particle board, in column No. 7

P.Sqm 380.00 328.00 15.85% 344.00 4.88%


8.7.6 Using medium density fibre board instead of particle board,
in column No. 7
(a) Interior grade
P.Sqm 134.00 134.00 0.00% 134.00 0.00%
(b) Exterior grade
P.Sqm 205.00 205.00 0.00% 205.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

8.7.7 Using medium density fibre board one side laminated face
instead of particle board, in column No. 7
(a) Interior grade
P.Sqm 172.00 172.00 0.00% 172.00 0.00%
(b) Exterior grade
P.Sqm 215.00 215.00 0.00% 215.00 0.00%
7.7.8 Using medium density fibre board both side laminated face
instead of particle board, in column No. 7
(a) Interior grade
P.Sqm 249.00 249.00 0.00% 249.00 0.00%
(b) Exterior grade
P.Sqm 374.00 374.00 0.00% 374.00 0.00%
8.7.9 Using thicker panels than 12mm, in column No. 7, for doors
of thickness 40mm and above.

(a) 15mm thick MDF board Interior grade.


P.Sqm 249.00 248.00 0.40% 249.00 0.40%
(b) 15mm thick MDF board Exterior grade.
P.Sqm 251.00 251.00 0.00% 251.00 0.00%
(c) 18mm thick MDF board Interior grade.
P.Sqm 249.00 249.00 0.00% 249.00 0.00%
(d) 18mm thick MDF board Exterior grade.
P.Sqm 374.00 324.00 15.43% 340.00 4.94%
(e) 18mm thick particle board Interior grade.
P.Sqm 249.00 247.00 0.81% 249.00 0.81%
(f) 18mm thick particle board Exterior grade.
P.Sqm 374.00 322.00 16.15% 338.00 4.97%
8.7.10 Providing other type of fittings : (as persample approved by
engineerIncharge)
(a) Brass fittings.
P.Sqm 500.00 500.00 0.00% 500.00 0.00%
(b) Anodised aluminium fittings.
P.Sqm 323.00 323.00 0.00% 323.00 0.00%
8.7.11 Add extra for providing fixed Nigeria / Ghana Teak wood
grade - I louvers instead of wooden panels in column No. 4
for Nigeria / Ghana wood door shutters.
P.Sqm 130.00 130.00 0.00% 130.00 0.00%
8.7.12 Add extra for providing movable Nigeria / Ghana Teak wood
grade - I louvers instead of wooden panels in column No.4
for Nigeria / Ghana Teak wood door shutters.

P.Sqm 155.00 155.00 0.00% 155.00 0.00%


8.7.13 Extra for providing heavy sheet glass panes instead of
ordinary glass in glazed doors, windows and clerestory
window shutters. (Area of opening for glass panes excluding
portion inside rebate shall be measured) :
8.7.13.1 5 mm thick instead of 4 mm thick.
P.Sqm 150.00 150.00 0.00% 150.00 0.00%
8.7.13.2 8 mm thick instead of 4 mm thick
P.Sqm 844.00 844.00 0.00% 844.00 0.00%
8.7.14 Extra for providing frosted glass panes instead of ordinary
glass panes in doors, windows and clerestory window
shutters. (Area of opening for glass panes excluding portion
inside rebate shall be measured)
(a) 4 mm thick
P.Sqm 344.00 344.00 0.00% 344.00 0.00%
(b) 5 mm thick
P.Sqm 639.00 639.00 0.00% 639.00 0.00%
8.7.15 Add extra for etching work in glass work as per direction of
engineer incharge (Area of opening for glass panes
excluding portion inside rebate shall be measured)
P.Sqm 963.00 963.00 0.00% 963.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
8.7.16 Add extra for providing reflective/antelo glass in bright
brown. Yellow and blue colour (Area of opening for glass
panes excluding portion inside rebate shall be measured)

(a) 4 mm thick
P.Sqm 1511.00 1511.00 0.00% 1,511.00 0.00%
(b) 5 mm thick
P.Sqm 1678.00 1678.00 0.00% 1,678.00 0.00%
8.8 Deduct from item No. 8.6. for :

8.8.1 Using A.C. sheet/ Flexo board 6mm thick for doors of
thickness 25mm and 30mm, in column No. 11.
P.Sqm 33.00 33.00 0.00% 33.00 0.00%
8.8.2 Using pin-head glass instead of 4mm thick plains glass, in
column No. 12 :
P.Sqm 40.00 40.00 0.00% 40.00 0.00%
8.8.3 Providing Single leaf shutter instead of double leaf.
20%
8.9 Table 8A
8.10 Add extra over item No. 8.9 for :

8.10.1 Using Phenol bonded exterior grade particle board instead of


urea bonded in column No. 7.
P.Sqm 17.00 17.00 0.00% 17.00 0.00%
8.10.2 One side teak face particle board in column No. 7.
P.Sqm 110.00 110.00 0.00% 110.00 0.00%
8.10.3 Both side teak face particle board in column No. 7
P.Sqm 167.00 167.00 0.00% 167.00 0.00%
8.10.4 One side laminated face particle board in column No.7.
P.Sqm 134.00 134.00 0.00% 134.00 0.00%

8.10.5 Both side laminated face particle board in column No. 7.


P.Sqm 251.00 216.00 16.20% 226.00 4.63%
8.10.6 Using medium density fibre board instead of particle board in
column No. 7 :
(a) Interior grade.
P.Sqm 89.00 89.00 0.00% 89.00 0.00%
(b) Exterior grade.
P.Sqm 138.00 138.00 0.00% 138.00 0.00%
8.10.7 Using medium density fibre board one side laminated face
instead of particle board in column No. 7 :
(a) Interior grade.
P.Sqm 114.00 114.00 0.00% 114.00 0.00%
(b) Exterior grade.
P.Sqm 142.00 142.00 0.00% 142.00 0.00%
8.10.8 Using medium density fibre board both side laminated face
instead of particle board in column No.7 :
(a) Interior grade.
P.Sqm 167.00 167.00 0.00% 167.00 0.00%
(b) Exterior grade.
P.Sqm 251.00 251.00 0.00% 251.00 0.00%

8.10.9 Using thicker panels than 12mm in column No. 7. for door
thickness 40mm & above.
(a) 15mm thick M.D.F. Board Interior grade.
P.Sqm 167.00 164.00 1.83% 167.00 1.83%
(b) 15mm thick M.D.F. Board Exterior grade.
P.Sqm 167.00 167.00 0.00% 167.00 0.00%
(c) 18mm thick M.D.F. Particle Board Interior grade
P.Sqm 167.00 167.00 0.00% 167.00 0.00%
(d) 18mm thick M.D.F. Particle Board Exterior grade
P.Sqm 251.00 216.00 16.20% 226.00 4.63%
(e) 18mm thick Particle Board Interior grade.
P.Sqm 167.00 164.00 1.83% 167.00 1.83%
(f) 18mm thick Particle Board Exterior grade.
P.Sqm 251.00 216.00 16.20% 226.00 4.63%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

8.10.10 Add extra for providing Nigeria / Ghana Teak wood grade - I
fixed louvers instead of glazing in column No. 4 for Nigeria /
Ghana teak wood door shutter.
P.Sqm 80.00 80.00 0.00% 80.00 0.00%

8.10.11 Add extra for providing Nigeria / Ghana Teak wood grade - I
movable louvers instead of glazing in column No. 4 for
Nigeria / Ghana teak wood shutter.
P.Sqm 100.00 100.00 0.00% 100.00 0.00%
8.11 Deduct from item No. 8.9 for :

8.11.1 Using (A.C. Sheet/ Flexo board) 6mm thick for doors of
thickness 25mm and 30mm thick in column No. 11.
P.Sqm 20.00 20.00 0.00% 20.00 0.00%
8.11.2 Using Pin head glass instead of 4mm thick plain glass for all
type of doors.
P.Sqm 19.00 19.00 0.00% 19.00 0.00%
8.11.3 Providing Single leaf shutter instead of double leaf.
P.Sqm 20% #DIV/0! 20.00%
8.12 Table 8A
8.13 Delete
8.14 Add extra over item No. 8.12 and 8.13 for
8.14.1 Using Phenol bonded exterior grade particle board instead of
urea bonded in column No. 7 :Fully Panelled Item 8.12
P.Sqm 28.00 28.00 0.00% 28.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 20.00 20.00 0.00% 20.00 0.00%
8.14.2 One side teak face particle board in column No. 7. Fully
Panelled Item 8.12
P.Sqm 184.00 184.00 0.00% 184.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 92.00 92.00 0.00% 92.00 0.00%
8.14.3 Both side teak face particle board in column No.7 :Fully
Panelled Item 8.12
P.Sqm 260.00 260.00 0.00% 260.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 130.00 130.00 0.00% 130.00 0.00%
8.14.4 One side laminated face particle board in column No. 7 :Fully
Panelled Item 8.12
P.Sqm 187.00 187.00 0.00% 187.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 93.00 93.00 0.00% 93.00 0.00%
8.14.5 Both side laminated face particle board in column No. 7:Fully
Panelled Item 8.12
P.Sqm 285.00 285.00 0.00% 285.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 131.00 131.00 0.00% 131.00 0.00%
8.14.6 Using medium density fibre board instead of particle board in
column No. 7:
(a) Interior grade.
Fully Panelled Item 8.12
P.Sqm 148.00 148.00 0.00% 148.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 74.00 74.00 0.00% 74.00 0.00%
(b) Exterior grade.
Fully Panelled Item 8.12
P.Sqm 231.00 231.00 0.00% 231.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 116.00 116.00 0.00% 116.00 0.00%
8.14.7 Using medium density fibre board one side laminated face
instead of particle board in column No. 7 :
(a) Interior grade.
Fully Panelled Item 8.12
P.Sqm 190.00 190.00 0.00% 190.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 95.00 95.00 0.00% 95.00 0.00%
(b) Exterior grade.
Fully Panelled Item 8.12
P.Sqm 238.00 238.00 0.00% 238.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 119.00 119.00 0.00% 119.00 0.00%

8.14.8 Using medium density fibre board both side laminated face
instead of particle board in column No. 7 :
(a) Interior grade.
Fully Panelled Item 8.12
P.Sqm 226.00 226.00 0.00% 226.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 113.00 113.00 0.00% 113.00 0.00%
(b) Exterior grade.
Fully Panelled Item 8.12
P.Sqm 278.00 278.00 0.00% 278.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 139.00 139.00 0.00% 139.00 0.00%

8.14.9 Using thicker panels than 12mm in column No. 7 for window
of thickness 40mm & above. (a) 15mm thick M.D.F. Board

(i) Interior grade.


Fully Panelled Item 8.12
P.Sqm 208.00 208.00 0.00% 208.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 104.00 104.00 0.00% 104.00 0.00%
(ii) Exterior grade.
Fully Panelled Item 8.12
P.Sqm 276.00 276.00 0.00% 276.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 138.00 138.00 0.00% 138.00 0.00%
(b) 18mm thick M.D.F. Board
(i) Interior grade.
Fully Panelled Item 8.12
P.Sqm 294.00 294.00 0.00% 294.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 125.00 125.00 0.00% 125.00 0.00%
(ii) Exterior grade.
Fully Panelled Item 8.12
P.Sqm 311.00 311.00 0.00% 311.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 156.00 156.00 0.00% 156.00 0.00%
(c) 18mm thick Partial Board
(i) Interior grade.
Fully Panelled Item 8.12
P.Sqm 160.00 158.00 1.27% 160.00 1.27%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 53.00 53.00 0.00% 53.00 0.00%
(ii) Exterior grade.
Fully Panelled Item 8.12
P.Sqm 240.00 207.00 15.94% 217.00 4.83%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 86.00 86.00 0.00% 86.00 0.00%

8.14.10 Providing other type of fittings :


(a) Brass fittings (Bush or equi.)
Fully Panelled Item 8.12
P.Sqm 650.00 623.00 4.33% 650.00 4.33%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 650.00 623.00 4.33% 650.00 4.33%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
(b) Anodised Aluminium fittings.
Fully Panelled Item 8.12
P.Sqm 178.00 136.00 30.88% 142.00 4.41%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 178.00 136.00 30.88% 142.00 4.41%
8.14.11 Add extra for providing Nigeria / Ghana Teak wood grade - I
fixed louvers instead of glazing in column No. 4 for Nigeria /
Ghana teak wood window shutter.
Fully Panelled Item 8.12
P.Sqm 130.00 130.00 0.00% 130.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 111.00 111.00 0.00% 111.00 0.00%
8.14.12 Add extra for providing Nigeria / Ghana Teak wood grade - I
movable louvers instead of glazing in column No. 4 for
Nigeria / Ghana teak wood Shutter.
Fully Panelled Item 8.12
P.Sqm 170.00 170.00 0.00% 170.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 153.00 153.00 0.00% 153.00 0.00%
8.15 Deduct from item No. 8-12 and 8-13 for :
8.15.1 Using A.C Sheet /Flexo board 6mm thick for window of
thickness 25mm and 30mm thick in column No.11 :
Fully Panelled Item 8.12
P.Sqm 22.00 22.00 0.00% 22.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 10.00 10.00 0.00% 10.00 0.00%

8.15.2 Using pin head glass instead of 4mm thick plain glass in
column No.12
Fully Panelled Item 8.12
P.Sqm 45.00 45.00 0.00% 45.00 0.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 23.00 23.00 0.00% 23.00 0.00%
8.15.3 Providing single leaf shutters instead of double leaf.
Fully Panelled Item 8.12
P.Sqm 3.00% 3.00%
Partly Panelled & Partly Glazed Item No. 8.13
P.Sqm 3.00% 3.00%

8.16 OTHER FITTINGS

8.16.1 Providing and Fixing Bearing Base door closure


Each 1100.00 1100.00 0.00% 1,100.00 0.00%
8.16.2 Providing and Fixing hydraulic door closure ISI marked
Each 550.00 550.00 0.00% 550.00 0.00%
8.16.3 Providing and Fixing superior quality like Hardvyn or
equivalent hydraulic door closure
Each 990.00 990.00 0.00% 990.00 0.00%
8.16.3.1 Providing and Fixing mortice lock of :
(a) Harrison make with CP steel handles Each 330.00 330.00 0.00% 330.00 0.00%

(b) Godrej make with CP steel handles. Each 480.00 480.00 0.00% 480.00 0.00%

(c) Godrej make with brass handles. Each 480.00 480.00 0.00% 480.00 0.00%

8.16.4 Providing and Fixing Almirah lock of approved make :


(a) 50 mm size
Each 66.00 66.00 0.00% 66.00 0.00%
(b) 62 mm size
Each 72.00 72.00 0.00% 72.00 0.00%
(c) 70 mm size
Each 78.00 78.00 0.00% 78.00 0.00%
8.16.5 Providing and Fixing lock in glass sheet :
Each 84.00 84.00 0.00% 84.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
8.17 Providing and fixing Chir/Babool Country wood framing,
ledged and braced door and window shutter made out of 10
cm. Wide thick tennon and grooved joints complete with top
bottom middle and diagonal at 10 cm wide bracing :

8.17.1 30 mm thick .
Chir Wood Sqm
P.Sqm 3261.00 3238.00 0.71% 3,261.00 0.71%
Babool Wood
P.Sqm 1778.00 1669.00 6.53% 1,752.00 4.97%
8.17.2 35 mm thick .
Chir Wood Sqm
P.Sqm 3569.00 3550.00 0.54% 3,569.00 0.54%
Babool Wood
P.Sqm 1930.00 1861.00 3.71% 1,930.00 3.71%
8.17.3 40 mm thick .
Chir Wood Sqm
P.Sqm 3998.00 3979.00 0.48% 3,998.00 0.48%
Babool Wood
P.Sqm 2064.00 2032.00 1.57% 2,064.00 1.57%
8.18 Providing and fixing external grade board solid core single
leaf flush door shutters ISI 2202-67 marked using Phenol
formal dehyderesin in glue both sides with approved steel
fittings complete as per annexure 'A' :
8.18.1 25 mm thick .
Commercial Veneer both side P.Sqm 1490.00 1477.00 0.88% 1,490.00 0.88%
Decorative teak veneer One side P.Sqm 1768.00 1755.00 0.74% 1,768.00 0.74%
Decorative teak veneer both side P.Sqm 2223.00 2211.00 0.54% 2,223.00 0.54%

8.18.2 30 mm thick .
Commercial Veneer both side P.Sqm 1601.00 1589.00 0.76% 1,601.00 0.76%
Decorative teak veneer One side P.Sqm 2001.00 1988.00 0.65% 2,001.00 0.65%
Decorative teak veneer both side P.Sqm 2401.00 2388.00 0.54% 2,401.00 0.54%

8.18.3 35 mm thick .
Commercial Veneer both side P.Sqm 1712.00 1700.00 0.71% 1,712.00 0.71%
Decorative teak veneer One side P.Sqm 2146.00 2133.00 0.61% 2,146.00 0.61%
Decorative teak veneer both side P.Sqm 2579.00 2566.00 0.51% 2,579.00 0.51%

8.18.4 40 mm thick .
Commercial Veneer both side P.Sqm 1768.00 1755.00 0.74% 1,768.00 0.74%
Decorative teak veneer One side P.Sqm 2218.00 2205.00 0.59% 2,218.00 0.59%
Decorative teak veneer both side P.Sqm 2668.00 2655.00 0.49% 2,668.00 0.49%

8.18.5 19 mm thick (for almirah shutter) .


Commercial Veneer both side P.Sqm 1000.00 1000.00 0.00% 1,000.00 0.00%
Decorative teak veneer One side P.Sqm 1250.00 1250.00 0.00% 1,250.00 0.00%
Decorative teak veneer both side P.Sqm 1450.00 1450.00 0.00% 1,450.00 0.00%

8.19 Add extra in Flush doors :


8.19.1 For Double leaf P.Sqm 109.00 81.00 34.57% 85.00 4.94%
8.19.2 For vision panel. P.Sqm 124.00 90.00 37.78% 94.00 4.44%

8.19.3 For external teak wood lipping on flush door.


25mm x 6 mm P.Rmt. 44.00 44.00 0.00% 44.00 0.00%
30mm x 6 mm P.Rmt. 47.00 47.00 0.00% 47.00 0.00%
35mm x 6 mm P.Rmt. 50.00 50.00 0.00% 50.00 0.00%
40mm x 6 mm P.Rmt. 52.00 52.00 0.00% 52.00 0.00%

8.19.4 For Internal teak wood lipping in 25mm depth P.Sqm 215.00 210.00 2.38% 215.00 2.38%

8.19.5 Extra in flush doors for providing vision panel of size 15x15
cm square of 15cm dia
Each 181.00 125.00 44.80% 131.00 4.80%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
8.19.6 Extra if louvers (not exceeding 0.2 sqm) are provided in flush
door shutters (overall area of door shutters to be measured)
Decorative type door.
P.Sqm 306.00 306.00 0.00% 306.00 0.00%
8.19.7 Extra for cutting rebate in flush door shutters (Total area of
the shutter to be measured)
P.Sqm 92.00 92.00 0.00% 92.00 0.00%
8.19.8 Add extra for Sunmica 0.8mm thick.
P.Sqm 410.00 410.00 0.00% 410.00 0.00%
8.20 type (hollow core construction ) with internal frame of 1st grade
wood having styles and top rails of 100 mm width & bottom and
lock rails of 150 mm width with 3 Nos. cross battens of 50mm thick
and 1 nos. 50 mm vertical middle member thoughtout length using
4 mm thick commercial ply on both faces of shutters & 6 mm thick
beading of respective wood using with approved steel fitting as per
Annexure 'A' :-

8.20.1 Nigeria teak wood grade - I


25mm thick P.Sqm 3091.00 2481.00 24.59% 2,605.00 5.00%
30mm thick P.Sqm 3269.00 2753.00 18.74% 2,890.00 4.98%
35mm thick P.Sqm 3462.00 2976.00 16.33% 3,124.00 4.97%
40mm thick P.Sqm 3621.00 3159.00 14.62% 3,316.00 4.97%

8.20.2 Ghana teak wood grade - I


25mm thick P.Sqm 3043.00 2426.00 25.43% 2,547.00 4.99%
30mm thick P.Sqm 3194.00 2668.00 19.72% 2,801.00 4.99%
35mm thick P.Sqm 3370.00 2869.00 17.46% 3,012.00 4.98%
40mm thick P.Sqm 3514.00 3034.00 15.82% 3,185.00 4.98%

8.20.3 Sheesham teak wood grade - I


25mm thick P.Sqm 3115.00 2435.00 27.93% 2,556.00 4.97%
30mm thick P.Sqm 3306.00 2681.00 23.31% 2,815.00 5.00%
35mm thick P.Sqm 3509.00 2887.00 21.54% 3,031.00 4.99%
40mm thick P.Sqm 3632.00 3006.00 20.83% 3,156.00 4.99%

8.20.4 Hollock wood grade - I


25mm thick P.Sqm 2918.00 2349.00 24.22% 2,466.00 4.98%
30mm thick P.Sqm 3145.00 2611.00 20.45% 2,741.00 4.98%
35mm thick P.Sqm 3308.00 2799.00 18.19% 2,938.00 4.97%
40mm thick P.Sqm 3413.00 2919.00 16.92% 3,064.00 4.97%
8.20.5 Providing and fixing factory made solid core single leaf Door
shutters made out of composite ECO friendly wood
laminated with 0.8 mm thick polymer termite and water
resistant five retendent technology, gluing by vacuum
lamination technology various pre-moulded design on both
face as per IS-2202 (part-1) 1991 (Door fitting shall be
supplied by the department.

(a) 35 mm thick(2100mm x900mm size) Each 5566.00 5566.00 0.00% 5,566.00 0.00%
(b) 30 mm thick(2100mm x900mm size) Each 5313.00 5313.00 0.00% 5,313.00 0.00%

8.21 Add extra over item No. 8.20 for Double leaf shutters. P.Sqm 25%

8.22 Add extra for providing 4 mm thick teak veneer ply instead of
4mm thick commercial ply over item No. 8.20.

P.Sqm 317.00 317.00 0.00% 317.00 0.00%


8.23 Add extra for providing vision panel not exceeding 1 Sqm
rectangular or circular.
Each 57.00 57.00 0.00% 57.00 0.00%
PELMETS
8.24 Providing and fixing 12 mm thick pelmets with 20mm dia
C.P. steel curtain rod and brackets 100x25x3mm M.S. flat
etc. complete :
8.24.1 Sheesham wood Grade -I
100mm wide P.Rmt. 251.00 224.00 12.05% 235.00 4.91%
150mm wide P.Rmt. 299.00 270.00 10.74% 283.00 4.81%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
8.24.2 particle or fibre board (Phenol Bonded).
100mm wide P.Rmt 266.00 230.00 15.65% 241.00 4.78%
150mm wide P.Rmt 315.00 274.00 14.96% 287.00 4.74%
8.24.3 particle or fibre board (Phenol Bonded). with lamination or
teak veneer one face .
100mm wide P.Rmt. 266.00 236.00 12.71% 247.00 4.66%
150mm wide P.Rmt. 315.00 285.00 10.53% 299.00 4.91%

8.24.4 Hollock wood


100mm wide P.Rmt. 210.00 189.00 11.11% 198.00 4.76%
150mm wide P.Rmt. 229.00 209.00 9.57% 219.00 4.78%

8.24.5 Nigeria wood


100mm wide P.Rmt. 246.00 231.00 6.49% 242.00 4.76%
150mm wide P.Rmt. 289.00 278.00 3.96% 289.00 3.96%

8.24.6 Ghana wood


100mm wide P.Rmt. 246.00 231.00 6.49% 242.00 4.76%
150mm wide P.Rmt. 289.00 278.00 3.96% 289.00 3.96%

8.25 Add extra over item No. 8.24 providing 12 mm thick top
horizontal cover of respective wood on pelmets :

8.25.1 Sheesham wood Grade -I P.Rmt 137.00 128.00 7.03% 134.00 4.69%
8.25.2 Particle of Fibre board (Phenol Bonded). P.Rmt 151.00 134.00 12.69% 140.00 4.48%

8.25.3 Particle of Fibre board (Phenol Bonded). with lamination or


teak veneer.
P.Rmt 151.00 143.00 5.59% 150.00 4.90%
8.25.4 Hollock wood P.Rmt 111.00 111.00 0.00% 111.00 0.00%
8.25.5 Nigeria wood P.Rmt 131.00 131.00 0.00% 131.00 0.00%
8.25.6 Ghana wood P.Rmt 119.00 119.00 0.00% 119.00 0.00%
8.25.7 Teak wood beading 25mm x 6mm P.Rmt 11.00 11.00 0.00% 11.00 0.00%

CURTAIN RODS
8.26 Providing and fixing Anodised Aluminium Curtain rod with
Aluminium brackets complete :

8.26.1 12 mm dia P.Rmt 32.00 32.00 0.00% 32.00 0.00%


8.26.2 20 mm dia Mtr P.Rmt 44.00 44.00 0.00% 44.00 0.00%
8.26.3 25 mm dia P.Rmt 57.00 57.00 0.00% 57.00 0.00%

8.27 Providing and fixing Aluminium curtian rails with rollers stop
ends rails and brackets in pelmets.
P.Rmt 177.00 177.00 0.00% 177.00 0.00%
8.28 Providing and fixing 20 mm dia Conduit pipe curtain rods
with steel brackets etc. complete.
P.Rmt 25.00 25.00 0.00% 25.00 0.00%
8.29 Providing and Fixing 38 mm thick wood panelled wall having
75 mm wide wood frame having door opening provision
maximum pan el. area 0.4 Sqm with steel fitting & antitermite
treatment complete as per drawing with panels of :

8.29.1 6mm thick fibre cement flexo board (A.C. Sheet)


with Chir wood frame P.Sqm 1980.00 1811.00 9.33% 1,901.00 4.97%
with Nigeria teak wood frame P.Sqm 2031.00 1899.00 6.95% 1,993.00 4.95%

8.29.2 9 mm thick commercial ply grade-1 (Phenol bonded)


with Chir wood frame P.Sqm 3404.00 2254.00 51.02% 2,366.00 4.97%
with Nigeria teak wood frame P.Sqm 3455.00 2342.00 47.52% 2,459.00 5.00%

8.29.3 12mm thick particle board(Phenol bonded)


with Chir wood frame P.Sqm 2609.00 2394.00 8.98% 2,513.00 4.97%
with Nigeria teak wood frame P.Sqm 2661.00 2482.00 7.21% 2,606.00 5.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
8.29.4 9 mm thick both side teak ply (Phenol bonded)
with Chir wood frame P.Sqm 3098.00 2956.00 4.80% 3,098.00 4.80%
with Nigeria teak wood frame P.Sqm 3150.00 3045.00 3.45% 3,150.00 3.45%

8.29.5 12 mm thick both face laminated particle board (Phenol


bonded)
with Chir wood frame P.Sqm 3343.00 2956.00 13.09% 3,103.00 4.97%
with Nigeria teak wood frame P.Sqm 3394.00 3045.00 11.46% 3,197.00 4.99%

8.29.6 12 mm thick fibre board (Phenol bonded)


With chir wood frame P.Sqm 3098.00 2956.00 4.80% 3,098.00 4.80%
with Nigeria teak wood frame P.Sqm 3150.00 3045.00 3.45% 3,150.00 3.45%
8.29.7 12 mm thick fibre board both side laminated (Phenol bonded)

With chir wood frame P.Sqm 2662.00 2344.00 13.57% 2,461.00 4.99%
with Nigeria teak wood frame P.Sqm 3394.00 3185.00 6.56% 3,344.00 4.99%

8.29.8 4 mm thick plain glass.


With chir wood frame P.Sqm 2047.00 1874.00 9.23% 1,967.00 4.96%
with Nigeria teak wood frame P.Sqm 2099.00 1963.00 6.93% 2,061.00 4.99%
8.30 Providing and fixing Hollow core partition wall using 50x30
mm Chir wood frame 600 mm c/c on both directions,door
opening as per drawing with steel fittings antitermite
treatment complete as per specifications using:

8.30.1 4 mm thick commercial ply grade-I (phenol Bonded) on both


sides.
P.Sqm 2597.00 2279.00 13.95% 2,392.00 4.96%
8.30.2 4 mm thick teak ply on both sides.
P.Sqm 2659.00 2561.00 3.83% 2,659.00 3.83%
8.30.3 4 mm thick fibre cement flexo board (A.C. sheet ) on both
sides.
P.Sqm 1887.00 1814.00 4.02% 1,887.00 4.02%
8.30.4 6 mm thick fibre Board on both sides.
P.Sqm 2957.00 2328.00 27.02% 2,444.00 4.98%
8.30.5 0.8 mm mica of approved make on ply with addesive
complete.
P.Sqm 887.00 755.00 17.48% 792.00 4.90%

SHELVES
8.31 Providing and fixing flat pressed 3 layer particle board in
shelves with screws and wooden brackets:
8.31.1 12 mm thick P.Sqm 410.00 410.00 0.00% 410.00 0.00%
8.31.2 19 mm thick P.Sqm 550.00 550.00 0.00% 550.00 0.00%
8.31.3 25 mm thick P.Sqm 610.00 610.00 0.00% 610.00 0.00%

8.32 Providing and fixing wooden shelves support on 40x40x6


mm T or L iron brackets fixed at suitable distance but not
exceeding 750mm apart embedded in 75mm x 150mm block
of cement concrete nominal mix 1:3:6 :

8.32.1 Chir wood grade- I


25mm thick P.Sqm 2743.00 2729.00 0.51% 2,743.00 0.51%
35mm thick P.Sqm 1300.00 1300.00 0.00% 1,300.00 0.00%
8.32.2 Sal wood grade-I
25mm thick P.Sqm 2806.00 2792.00 0.50% 2,806.00 0.50%
35mm thick P.Sqm 1800.00 1800.00 0.00% 1,800.00 0.00%

8.32.3 Sheesham wood grade -I


25mm thick P.Sqm 2963.00 2770.00 6.97% 2,908.00 4.98%
35mm thick P.Sqm 1800.00 1800.00 0.00% 1,800.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
WALL PANELLING

8.33 Providing and fixing wall panelling using soft wood frame of
size 50x25mm @600 mm c/c in both directions duly treated
with anti-termite treatment making grooves painting of
grooves specification and drawing using :

8.33.1 6 mm thick teak ply grade -I (phenol bonded)


P.Sqm 1921.00 1760.00 9.15% 1,848.00 5.00%
8.33.2 12 mm thick Acoustical Board with 25 mm thick Glass wool.

P.Sqm 1790.00 1610.00 11.18% 1,690.00 4.97%


8.33.3 9 mm thick teak ply grade -I (phenol bonded)
P.Sqm 2287.00 2147.00 6.52% 2,254.00 4.98%
8.33.4 8 mm thick teak one side laminated fibre board (Phenol
bonded)
P.Sqm 2141.00 1991.00 7.53% 2,090.00 4.97%
8.33.5 12 mm thick one side laminated board Practical board
(Phenol bonded)
P.Sqm 2532.00 2147.00 17.93% 2,254.00 4.98%
8.33.6 12mm thick Acoustical Board with 50mm thick glass wood
and glass fibremat.
P.Sqm 1912.00 1750.00 9.26% 1,837.00 4.97%
8.33.7 Providing and fixing 50 mm thick resin bounded glass whool
32 kg/cum density wrapped in julities cloth bag (box type)
and held in position using chicken mesh.
P.Sqm 360.00 360.00 0.00% 360.00 0.00%
8.33.8 Providing and fixing Hassian cloth of approved colour and
texture over soft wood frame glass wool & fibre glass tissuse
paper.
P.Sqm 175.00 175.00 0.00% 175.00 0.00%
MISCELLANEOUS WOOD WORK

8.34 Providing and fixing Nigeria / Ghana Teak wood grade-I


mouldings and beadings in droos and windows size :-

8.34.1 50x12 mm P.Rmt. 60.00 60.00 0.00% 60.00 0.00%


8.34.2 50x20 mm P.Rmt. 75.00 75.00 0.00% 75.00 0.00%
8.34.3 25x12 mm P.Rmt. 40.00 40.00 0.00% 40.00 0.00%
8.34.4 20x12 mm P.Rmt. 40.00 40.00 0.00% 40.00 0.00%

8.35 Groove cutting in Glasses handles and fixing other


accessories complete with care
Each 15.00 15.00 0.00% 15.00 0.00%
8.36 Making peep hole 125 mm dia or 225x100 mm with
aluminium beading on both faces including fixing of 4mm
thick plain glass complete
Each 85.00 85.00 0.00% 85.00 0.00%
8.37 Providing and fixing wooden stoppers with lugs of teak wood.

Each 15.00 15.00 0.00% 15.00 0.00%


8.38 Providing and fixing of Sal ballies in trusses, posts purlines
and rafters etc. with nails and spikes :

8.38.1 75 Cm Dia P.Rmt. 200.00 200.00 0.00% 200.00 0.00%


8.38.2 100 Cm Dia P.Rmt. 284.00 284.00 0.00% 284.00 0.00%
8.38.3 120 Cm Dia P.Rmt. 284.00 284.00 0.00% 284.00 0.00%
8.38.4 150 Cm Dia P.Rmt. 395.00 395.00 0.00% 395.00 0.00%

8.39 Providing and fixing channel pipe and rollers for making
arrangement of sliding of doors complete in all respects.
P.Rmt. 650.00 650.00 0.00% 650.00 0.00%
8.40 Providing brackets fixed in 7 .5x7 .5x15 cm blocks of cement
concrete 1 :3:6 (1 cement: 3 coarse sand :6 graded stone
aggregate 20 mm nominal size) to support 20 cm wide
shelves.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

8.40.1 T or L iron 30 cm long of section 40x40x6 mm each Each 112.00 104.00 7.69% 109.00 4.81%

8.40.2 Aluminium T or L 30 cm long of section 40x40x4 mm each. Each 162.00 108.00 50.00% 113.00 4.63%

8.41 Providing 50x50x50mm 2nd class teak wood plugs including


cutting brick work and fixing in cement mortar 1 : 3 (1
cement: 3 fine sand) and making good the walls etc.

Each 20.00 13.00 53.85% 13.00 0.00%


8.42 Providing and fixing expandable fastners of specified size
with necessary plastic sleeves and galvanised M.S. screws
including drilling holes in masonry work /CC/R.C.C. and
making good etc. complete

8.42.1 25 mm long Each 18.00 13.00 38.46% 13.00 0.00%


8.42.2 32 mm long Each 18.00 16.00 12.50% 16.00 0.00%
8.42.3 40 mm long Each 11.00 Each 18.00 18.00 0.00% 18.00 0.00%
8.42.4 50 mm long Each 21.00 21.00 0.00% 21.00 0.00%

8.43 Providing and fixing ghana teak wood plain lining tongued
and grooved on and including wooden plugs complete with
necessary screws and priming coat on unexposed surface.

8.43.1 40 mm thick P.Sqm 3333.00 3309.00 0.73% 3,333.00 0.73%


8.43.2 25mm thick P.Sqm 2209.00 2185.00 1.10% 2,209.00 1.10%
8.44 Providing and fixing 20 mm thick plain lining tongued and
grooved on and including wooden plugs complete with
necessary screws .and priming coat on unexposed surface
with.
8.44.1 NIgeriaTeak Wood P.Sqm 1836.00 1811.00 1.38% 1,836.00 1.38%
8.44.2 Ghana Teak Wood P.Sqm 1836.00 1811.00 1.38% 1,836.00 1.38%
8.45 Providing and fixing 12 mm thick plain lining tongued and
grooved on and including wooden plugs complete with
necessary screws and priming coat on unexposed surface
with: ghana teak Wood.
P.Sqm 1237.00 1213.00 1.98% 1,237.00 1.98%
8.46 Providing and fixing 4 mm thick plywood plain lining with
necessary screws, priming coat on unexposed surface etc.
complete with teak ply facing of approved manufacture.

P.Sqm 1397.00 1153.00 21.16% 1,210.00 4.94%


8.47 Providing and fixing 40mm thick ghana teak wood plain
panelling with skirting chair rails, and cornice with
necessary , screws, priming coat on unexposed surface etc.
complete.
P.Sqm 4675.00 3868.00 20.86% 4,061.00 4.99%
8.48 Providing and fixing skirting of prelaminated with (one side
decorative and other side balancing lamination) flat pressed,
3 layer (like Novapan, Ecoboard, etc.,) or graded particle
board (like Bhutan Board) (medium density) Grade I, Type II,
IS :12823 marked, with necessary fixing arrangements and
screws including drilling necessary holes for rawl plugs etc.
and priming coat on unexposed surface complete.

8.48.1 18 mm thick P.Sqm 1704.00 1576.00 8.12% 1,654.00 4.95%


8.48.2 25 mm thick P.Sqm 2291.00 2139.00 7.11% 2,245.00 4.96%
8.49 Providing and fixing teak wood lipping of size 25x3 mm in
pelmet
P.Rmt. 52.00 40.00 30.00% 42.00 5.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-8
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
8.50 Providing and fixing curtain rods of 1.25 mm thick chromium
plated brass plate, with two chromium plated brass brackets
fixed with C.P. brass screws and wooden plugs, etc.,
wherever necessary complete:

8.50.1 12 mm P.Rmt. 375.00 375.00 0.00% 375.00 0.00%


8.50.2 20 mm P.Rmt. 483.00 483.00 0.00% 483.00 0.00%
8.50.3 25 mm P.Rmt. 519.00 519.00 0.00% 519.00 0.00%

8.51 Providing and fixing nickel plated M.S. pipe curtain rods with
nickel plated brackets

8.51.1 25 mm dia (heavy type) P.Rmt. 146.00 146.00 0.00% 146.00 0.00%
8.51.2 20 mm dia (heavy type) P.Rmt. 142.00 142.00 0.00% 142.00 0.00%

8.52 Providing beams including hoisting, fixing in position and


applying wood preservative for the unexposed surfaces, etc.
complete with Sal Wood.
P.Cum 69214.00 67927.00 1.89% 69,214.00 1.89%

8.53 Providing & Fixing of ward robe shutters made out of 19mm thick
BWP block board ISI of superior quality make. Front side finishing
with 4mm thick teak veneer approved make and 0.8mm thick
approved shade mica in the inner side. Covering with teak wood
beading 25x12mm all the sides of shutter & 35x12mm on outer
frame for making good the wall joint including heavy brass S.S.
fittings (Handle 200mm 2 Nos., Tower Bolt 150mm 2 Nos., Brass
Lock 1 Nos., Magnetic Catcher 2 Nos., Brass Hinges 75x40x2.5
mm 6 Nos., SS Hanger Rod 20mm dia) complete with melamine
polishing as per drawing and design approved by Engineer in
Charge.
Sqm 7221.00 7221.00 0.00% 7,221.00 0.00%

8.54 Providing and Fixing Bamboo Zafari/Fencing consisting of superior


quality 25mm dia Solid Bamboo placed vertically & fixed together
with 3 Nos Horizontal running members of wood in scantling of
section size 50x40mm and fixed with nut and bolt to existing
surface/angle post as per direction given by Engineer-in-charge
Sqm 2615.00 2615.00 0.00% 2,615.00 0.00%

8.55 Providing & Fixing mica of approved make for inner/outer side of
shutters with fevicol & nails complete as per approved by
engineer in charge.

8.55.1 0.6mm thick mica Sqm 570.00 570.00 0.00% 570.00 0.00%

8.55.2 0.8mm thick mica Sqm 692.00 692.00 0.00% 692.00 0.00%

8.56 Providing & Fixing decorative veneer of approved make for


inner/outer side of shutters with fevicol & nails complete as per
approved by engineer in charge.

8.56.1 4.0mm thick veneer Sqm 1303.00 1303.00 0.00% 1,303.00 0.00%

8.56.2 6.0mm thick veneer Sqm 1425.00 1425.00 0.00% 1,425.00 0.00%

8.57 Providing and fixing S.S. Rod 30mm dia (304 grade ,16SWG)
including brackets fixed with C.P. brass screws and rawl plugs,
etc., wherever necessary complete two side central all fittings.
Rmt 1034.00 1034.00 0.00% 1,034.00 0.00%

1048057.11 971626.00 7.87% 1001723.66 3.10%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-7
MARBLE, GRANITE AND TILE WORKS
CHAPTER B-7
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
MARBLE, GRANITE AND TILE WORKS
7.1 Marble stone flooring table rubbed, 18 mm thick over 20mm
(Av.) thick base of CM 1:4 (1 cement : 4 coarse sand)
jointing with white cement mortar 1:2 (1 white cement : 2
marble dust) with pigment to match the shade of the marble
slab including grinding, rubbing and polishing complete.

OR
Providing and fixing stone slabs table rubbed, 18 mm thick in
Walls, Steps, Pillars, Counters, Jambs, Shelves, Sills etc. laid on
12mm (Av.) thick base of CM 1:3 (1 cement : 3 coarse sand)
jointing with white cement mortar 1:2 (1white cement : 2 marble
dust) with pigment to match the shade of the marble slab complete
including grinding, rubbing and polishing.

WHITE MARBLE
7.1.1 Makrana second quality plain.
Upto 800 Cm2 Tiles
P.Sqm 1453.00 1416.00 2.61% 1,453.00 2.61%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1701.00 1664.00 2.22% 1,701.00 2.22%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 2135.00 2098.00 1.76% 2,135.00 1.76%
Above 3601 Cm2 Slabs
P.Sqm 3127.00 3090.00 1.20% 3,127.00 1.20%
7.1.2 Makrana Superior quality having light spots.

Upto 800 Cm2 Tiles


P.Sqm 1577.00 1251.00 26.06% 1,313.00 4.96%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1825.00 1572.00 16.09% 1,650.00 4.96%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 2383.00 1928.00 23.60% 2,024.00 4.98%
Above 3601 Cm2 Slabs
P.Sqm 3375.00 2213.00 52.51% 2,323.00 4.97%

7.1.3 Makrana 'Adanga'.


Upto 800 Cm2 Tiles
P.Sqm 1174.00 1059.00 10.86% 1,111.00 4.91%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1391.00 1271.00 9.44% 1,334.00 4.96%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1515.00 1429.00 6.02% 1,500.00 4.97%
Above 3601 Cm2 Slabs
P.Sqm 1763.00 1679.00 5.00% 1,762.00 4.94%
7.1.4 Rajnagar 1st quality with light spots.
Upto 800 Cm2 Tiles
P.Sqm 1174.00 1008.00 16.47% 1,058.00 4.96%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1267.00 1179.00 7.46% 1,237.00 4.92%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1391.00 1286.00 8.16% 1,350.00 4.98%
Above 3601 Cm2 Slabs
P.Sqm 1639.00 1536.00 6.71% 1,612.00 4.95%
7.1.5 Rajnagar 2nd quality with light spots and streaks.
Upto 800 Cm2 Tiles
P.Sqm 1143.00 1059.00 7.93% 1,111.00 4.91%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1236.00 1140.00 8.42% 1,197.00 5.00%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1279.00 1059.00 20.77% 1,111.00 4.91%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-7
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
Above 3601 Cm2 Slabs
P.Sqm 1453.00 1358.00 7.00% 1,425.00 4.93%

7.1.6 Ambaji (Abu) with green shadow.


Upto 800 Cm2 Tiles
P.Sqm 1515.00 1429.00 6.02% 1,500.00 4.97%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1577.00 1515.00 4.09% 1,577.00 4.09%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 2135.00 1928.00 10.74% 2,024.00 4.98%
Above 3601 Cm2 Slabs
P.Sqm 2631.00 2570.00 2.37% 2,631.00 2.37%

7.1.7 Ambaji (Abu) Panther.


Upto 800 Cm2 Tiles
P.Sqm 1267.00 1140.00 11.14% 1,197.00 5.00%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1391.00 1286.00 8.16% 1,350.00 4.98%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1453.00 1358.00 7.00% 1,425.00 4.93%
Above 3601 Cm2 Slabs
P.Sqm 2011.00 1785.00 12.66% 1,874.00 4.99%

7.1.8 Andhi Pista and Jhiri.


Upto 800 Cm2 Tiles
P.Sqm 1155.00 1059.00 9.07% 1,111.00 4.91%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1236.00 1140.00 8.42% 1,197.00 5.00%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1453.00 1358.00 7.00% 1,425.00 4.93%
Above 3601 Cm2 Slabs
P.Sqm 1577.00 1536.00 2.67% 1,577.00 2.67%

7.1.9 Andhi Indo - Italian and baldevgarh.


Upto 800 Cm2 Tiles
P.Sqm 1267.00 1140.00 11.14% 1,197.00 5.00%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1422.00 1322.00 7.56% 1,388.00 4.99%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1515.00 1465.00 3.41% 1,515.00 3.41%
Above 3601 Cm2 Slabs
P.Sqm 2135.00 1928.00 10.74% 2,024.00 4.98%
7.1.10 Banswara.
Upto 800 Cm2 Tiles
P.Sqm 1081.00 959.00 12.72% 1,006.00 4.90%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1267.00 1140.00 11.14% 1,197.00 5.00%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1453.00 1358.00 7.00% 1,425.00 4.93%
Above 3601 Cm2 Slabs
P.Sqm 1887.00 1850.00 2.00% 1,887.00 2.00%
7.1.11 PINK MARBLE
Udaipur (Babarmal).
Upto 800 Cm2 Tiles
P.Sqm 1267.00 1140.00 11.14% 1,197.00 5.00%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1391.00 1286.00 8.16% 1,350.00 4.98%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1453.00 1286.00 12.99% 1,350.00 4.98%
Above 3601 Cm2 Slabs
P.Sqm 1608.00 1536.00 4.69% 1,608.00 4.69%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-7
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

7.1.12 Makrana Adanga.


Upto 800 Cm2 Tiles
P.Sqm 1205.00 1059.00 13.79% 1,111.00 4.91%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1453.00 1271.00 14.32% 1,334.00 4.96%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1577.00 1429.00 10.36% 1,500.00 4.97%
Above 3601 Cm2 Slabs
P.Sqm 1887.00 1679.00 12.39% 1,762.00 4.94%

7.1.13 Bundi.
Upto 800 Cm2 Tiles
P.Sqm 1087.00 976.00 11.37% 1,024.00 4.92%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1217.00 1140.00 6.75% 1,197.00 5.00%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1329.00 1215.00 9.38% 1,275.00 4.94%
Above 3601 Cm2 Slabs
P.Sqm 1608.00 1536.00 4.69% 1,608.00 4.69%

GREEN MARBLE
7.1.14 Kesriaji (Rikhabdeo).
Upto 800 Cm2 Tiles
P.Sqm 1267.00 1179.00 7.46% 1,237.00 4.92%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1391.00 1286.00 8.16% 1,350.00 4.98%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1577.00 1536.00 2.67% 1,577.00 2.67%
Above 3601 Cm2 Slabs
P.Sqm 2011.00 1928.00 4.30% 2,011.00 4.30%

7.1.15 Abu.
Upto 800 Cm2 Tiles
P.Sqm 1267.00 1140.00 11.14% 1,197.00 5.00%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1484.00 1386.00 7.07% 1,455.00 4.98%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1608.00 1536.00 4.69% 1,608.00 4.69%
Above 3601 Cm2 Slabs
P.Sqm 2135.00 1999.00 6.80% 2,098.00 4.95%
7.1.16 Bhaislana,Abu,Kishangarh Zebra.

Upto 800 Cm2 Tiles


P.Sqm 1205.00 1059.00 13.79% 1,111.00 4.91%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1267.00 1179.00 7.46% 1,237.00 4.92%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1391.00 1286.00 8.16% 1,350.00 4.98%
Above 3601 Cm2 Slabs
P.Sqm 1608.00 1536.00 4.69% 1,608.00 4.69%

GREY MARBLE
7.1.17 Bundi.
Upto 800 Cm2 Tiles
P.Sqm 1205.00 1059.00 13.79% 1,111.00 4.91%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 1267.00 1140.00 11.14% 1,197.00 5.00%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 1391.00 1286.00 8.16% 1,350.00 4.98%
Above 3601 Cm2 Slabs
P.Sqm 1608.00 1536.00 4.69% 1,608.00 4.69%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-7
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

NOTE:
1- Add extra for doing mirror polishing.

2- Add extra for marble cladding work in plain arches and


domes including all scaffolding etc. complete.

3- Add extra in Marble flooring work for upto 50mm wide


strip of Green/ White/ Jaisalmer Stone in flooring work as per
direction of Engineer Incharge.

7.2 Providing and fixing Granite stone slab mirror polished and
machine edge cut in walls, pillars, steps, Shelves, Sills
Counters, Floors etc. laid on 12mm (Av.) thick base of
cement mortar 1:3 (1 cement : 3 coarse sand) jointing with
white cement mortar 1:2 (1 white cement : 2 marble dust)
with pigment to match the shade of the granite slab complete
including rubbing and polishing of :

7.2.1 Jhunjhunu / Jalore (Red / Choclate Colour)


Upto 800 Cm2 Tiles
P.Sqm 2051.00 1814.00 13.07% 1,904.00 4.96%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 2286.00 2087.00 9.54% 2,191.00 4.98%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 2930.00 2829.00 3.57% 2,930.00 3.57%
Above 3601 Cm2 Slabs
P.Sqm 3575.00 3492.00 2.38% 3,575.00 2.38%

7.2.2 Jhanshi (Red / Choclate Colour)


Upto 800 Cm2 Tiles
P.Sqm 2286.00 2087.00 9.54% 2,191.00 4.98%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 2608.00 2457.00 6.15% 2,579.00 4.97%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 3165.00 3082.00 2.69% 3,165.00 2.69%
Above 3601 Cm2 Slabs
P.Sqm 4513.00 4430.00 1.87% 4,513.00 1.87%

7.2.3 South (Red / Choclate Colour)


Upto 800 Cm2 Tiles
P.Sqm 2286.00 2087.00 9.54% 2,191.00 4.98%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 2579.00 2424.00 6.39% 2,545.00 4.99%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 3575.00 3492.00 2.38% 3,575.00 2.38%
Above 3601 Cm2 Slabs
P.Sqm 4865.00 4781.00 1.76% 4,865.00 1.76%

7.2.4 Green / Black / Other granite


Upto 800 Cm2 Tiles
P.Sqm 2286.00 2087.00 9.54% 2,191.00 4.98%
801 Cm2 to 1500 Cm2 Tiles
P.Sqm 2579.00 2424.00 6.39% 2,545.00 4.99%
1501 Cm2 to 3600 Cm2 Tiles
P.Sqm 3223.00 3140.00 2.64% 3,223.00 2.64%
Above 3601 Cm2 Slabs
P.Sqm 4220.00 4137.00 2.01% 4,220.00 2.01%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-7
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
7.2.5 South Zed Black
Up to 1500 Cm2 Tiles Sqm. 2428.00 2205.00 10.11% 2,315.00 4.99%
1501 Cm2 to 3600 Cm2 Tiles Sqm. 3361.00 3054.00 10.05% 3,206.00 4.98%
Above 3601 Cm Slabs2
Sqm. 3897.00 3711.00 5.01% 3,896.00 4.99%

7.2.6 Good quality South Black


Up to 1500 Cm2 Tiles Sqm. 2195.00 2193.00 0.09% 2,195.00 0.09%
1501 Cm to 3600 Cm Tiles
2 2
Sqm. 2778.00 2776.00 0.07% 2,778.00 0.07%
Above 3601 Cm2 Slabs Sqm. 3595.00 3593.00 0.06% 3,595.00 0.06%

7.3 Providing and fixing 1st quality standard white, grey, ivory,
fume red brown, light green, light blue and other light shades
glazed tiles confirming to IS : 13753 & IS :15622 of size
200mm x 300mm in walls, floors, steps, pillars etc. laid on a
bed of neat cement slurry finished with flush pointing in the
white cement mixed with pigment to match the shade of the
tile complete (excluding the cost of cement plaster on walls
and pillar).

P.Sqm 875.00 660.00 32.58% 693.00 5.00%

7.3.3 Add extra over item no. 7.3.1 and 7.3.2 for Marble printed,
granite shade tiles.
15% 15% 15.00% 15%
7.3.4 Add extra over 7.3.1 and 7.3.2 for using coloured dark shade
tiles instead of White / Ivory / Light Grey/ Light Green/ Sky
Blue/ Light Brown and other light shade coloures.

P.Sqm 99.00 81.00 22.22% 85.00 4.94%


7.4 Providing and fixing 75 mm widen Decorative Border in
different shades and in all coloures for glazed tiles
P.Rmt. 300.00 300.00 0.00% 300.00 0.00%
7.5 Providing and fixing Motive pieces all coloures for glazed
tiles.

7.5.1 Size 200 x 200mm


Each 116.00 116.00 0.00% 116.00 0.00%
7.5.2 Size 200 x 300mm
Each 147.00 147.00 0.00% 147.00 0.00%
7.6 Providing and fixing 1st quality MAT finished ceremic tile size
300x300mm confirming to IS : 13755 and IS : 15622 colour
such as white, grey, ivory, fume red brown, light green, light
blue and other light shades in floors, steps, pillars etc. laid on
a bed of neat cement slurry finished with flush pointing in the
white cement mixed with pigment to match the shade of the
tile complete (including the cost of cement mortar bed 1:4).

P.Sqm 1120.00 753.00 48.74% 790.00 4.91%

7.6.3 Add extra over item No 7.6.1 and 7.6.2 for using
400x400mm size MAT finished tiles in place of 300x300mm
size.
P.Sqm 84.00 84.00 0.00% 84.00 0.00%
7.6.4 Add extra over 7.6.1 and 7.6.2 for using coloured dark shade
tiles instead of White / Ivory / Light Grey/ Light Green/ Sky
Blue/ Light Brown and other light shade coloures.

P.Sqm 84.00 84.00 0.00% 84.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-7
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018
7.7 P & F Vitrified Porcelain Polished tiles ( Naveen/ Euro make ,
size 600 mm x 600 mm and thickness 10mm) on floor,
skirting and steps etc. laid with tile admixture (Roff Pidilite or
equivalent) including filling of joints by water proofing tile
grout (Fevimate, Roofie, Untile or equivalent) specially for
adhesive with graded granuals, polymer and stable pigment
fine finished including cleaning of joints etc. complete as per
direction of Engineer Incharge. Conforming to IS 15622 of
approved make in all colour and shade,

P.Sqm 1149.00 1149.00 0.00% 1,149.00 0.00%


Note :
Deduct over item no. 7.7 for using any other make 10% 10% 10%
7.8 Providing and fixing marble mirror polished 7mm thick tiles of
approved make and size in walls, floors, steps, pillars etc.
laid on a bed of neat cement slurry including nicely finished
joints using water proof joint filler powder and finished with
flush pointing in white cement mixed with pigment to match
the shade of tile complete (excluding cost of cement
plaster) :

7.8.1 Banswara white tiles.


P.Sqm 1468.00 953.00 54.04% 1,000.00 4.93%
7.8.2 Andhi white tiles.
P.Sqm 1497.00 1020.00 46.76% 1,071.00 5.00%
7.8.3 Rajnagar white tiles.
P.Sqm 1702.00 1256.00 35.51% 1,318.00 4.94%
7.8.4 Ambaji white tiles.
P.Sqm 1702.00 1256.00 35.51% 1,318.00 4.94%
7.8.5 Kesriaji green & Bhaislana black tiles
P.Sqm 1204.00 717.00 67.92% 752.00 4.88%
7.9 Providing and fixing gun metal clamps as per design in
cement sand mortar 1:3 (1 cement : 3 fine sand) including of
making necessary chases.

7.9.1 25 x 6 mm x 30 cm long.
Each 165.00 164.00 0.61% 165.00 0.61%
7.9.2 15 x 6 mm x 16.5 cm long.
Each 63.00 63.00 0.00% 63.00 0.00%
7.10 Providing and fixing copper pipe 7.5cm long of 6mm external
diameter in cement sand 1:3 (1 cement :3 fine sand)
including making necessary chases.
Each 32.00 32.00 0.00% 32.00 0.00%

7.11 Providing and fixing stone dowel 10x5x2.5cm cut to double


wedge shape as per design in cement sand mortar 1:3 (1
cement : 3 fine sand) including making necessary chases.

Each 11.00 10.00 10.00% 10.00 0.00%

7.12 Extra for providing edge moulding to 18mm thick marble


stone counters, vantities etc. over item No. 7.1 & 7.2
including machine polishing to edge to give high gloss finish
etc. complete as per design approved by Engineer - in -
Charge.
7.12.1 Marble work
P.Sqm 248.00 146.00 69.86% 153.00 4.79%
7.12.2 Granite Work
P.Sqm 381.00 224.00 70.09% 235.00 4.91%
7.13 Extra for providing opening of required size & shape for
wash basin / kitchen sink in kitchen platform, vanit counters
and similar location in marble / stone work including
necessary holes for pillars taps etc. including rubbing and
polishing of cut edge etc. complete.

Each
63.00 59.00 6.78% 61.00 3.39%
Opening

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-7
Chapter Description Unit Variation Proposed % Above
Code No. Analysis As per BSR
on BSR Rate for with BSR
Rate 2018
2018 BSR 2019 2018

7.14 Providing non slip grooves to granite/ kota stone flooring, counters,
vanities etc. using groove cutter V type including machine
polishing to groove to give high gloss finish etc. complete as per 95.00 95.00 0.00% 95.00 0.00%
design approved by engineer in charge Mtr.

7.15 P & F 1st qualityHeavy Duty Vitrified Polished Digital tiles on floor,
skirting and steps etc.in different sizes (thickness minimum 10mm)
with water absortion less than or equal 0.08% and conforming to
IS 15622 of approved make in all colour and shade, laid with 20
mm thick CM 1: 4 including grounting the joints with white cement
and matching pigment etc complete.

7.15.1 size 600 mm X 600 mm Sqm 869.00 869.00 0.00% 869.00 0.00%
7.15.2 size 600 mm X 1200 mm Sqm 1410.00 1410.00 0.00% 1,410.00 0.00%

7.16 P & F 1st quality Heavy Duty Vitrified glazed MAT tiles on floor,
skirting and steps etc.in different sizes (thickness minimum 10mm)
with water absortion less than or equal 0.08% and conforming to
IS 15622 of approved make in all colour and shade, laid with 20
mm thick CM 1: 4 including grounting the joints with white cement
and matching pigment etc complete.

7.16.1 size 600 mm X 600 mm Sqm 1178.00 1178.00 0.00% 1,178.00 0.00%
7.16.2 size 600 mm X 1200mm Sqm 1178.00 1178.00 0.00% 1,178.00 0.00%

7.17 P & F 1st quality Heavy Duty Vitrified Double Charged tiles on
floor, skirting and steps etc.in different sizes (thickness minimum
10mm) with water absortion less than or equal 0.08% and
conforming to IS 15622 of approved make in all colour and shade,
laid with 20 mm thick CM 1: 4 including grounting the joints with
white cement and matching pigment etc complete.

7.17.1 size 600 mm X 600mm Sqm 1640.00 1640.00 0.00% 1,640.00 0.00%
7.17.2 size 800 mm X 800mm Sqm 947.00 947.00 0.00% 947.00 0.00%
7.17.3 size 1000 mm X 1000mm Sqm 1178.00 1178.00 0.00% 1,178.00 0.00%

185984.25 170841.25 8.86% 177496.25 3.90%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
PART - A : GENERAL STONE WORK
NOTE:
1- Rates provided are for the complete finished items inclusive of cost of water and
2- materials
In case of with all leads labour,
non-availability allheader
of stone type of
of taxes,
proper royalty, scaffolding,
size cement concretecuring,
header laying,
of mix
fixing
1:3 : 6finishing etc.,25mm
(M-100) with hire charges
graded for tools
stone and plants,
aggregate withtemplates and other
smooth finish may beappliances,
provided
required
by for the purpose
the contractor of execution
at no extra cost. of the items work as per specification.

3- The Concrete for all grade shall be produced in conformation to the laid down
procedures and all relevant clauses of IS 456 : 2000
CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
STONE MASONRY
6.1 Random Rubble stone masonry for foundation and plinth in
Cement Sand mortar above 30CM thick wall in:
6.1.1 Mud Mortar.
P.Cum 2583.00 1584.00 63.07% 1,663.00 4.99%
6.1.2 Dry Masonry.
P.Cum 1884.00 1209.00 55.83% 1,269.00 4.96%
6.1.3 Lime Sand Mortar 1:3 ( 1-Lime Putty : 3-Sand).
P.Cum 2845.00 1940.00 46.65% 2,037.00 5.00%
6.1.4 Cement Mortar 1:3 ( 1-Cement : 3-Sand).
P.Cum 4207.00 2886.00 45.77% 3,030.00 4.99%
6.1.6 Cement Mortar 1:5 ( 1-Cement : 5-Sand).
P.Cum 3778.00 2570.00 47.00% 2,698.00 4.98%
6.1.7 Cement Mortar 1:6 ( 1-Cement : 6-Sand).
P.Cum 3646.00 2455.00 48.51% 2,577.00 4.97%
6.2 Random Rubble stone masonry for superstructure above plinth
level one storey height above 30cm. thick walls in :
6.2.1 Mud Mortar.
P.Cum 3447.00 2022.00 70.47% 2,123.00 5.00%
6.2.2 Dry Masonry.
P.Cum 3278.00 1889.00 73.53% 1,983.00 4.98%
6.2.3 Lime Sand Mortar 1:3 ( 1-Lime Putty : 3-Sand).
P.Cum 4239.00 2619.00 61.86% 2,749.00 4.96%
6.2.4 Cement Mortar 1:3 ( 1-Cement : 3-Sand).
P.Cum 4997.00 3303.00 51.29% 3,468.00 5.00%
6.2.5 Cement Mortar 1:4 ( 1-Cement : 4-Sand).
P.Cum 4721.00 3122.00 51.22% 3,278.00 5.00%
6.2.6 Cement Mortar 1:5 ( 1-Cement : 5-Sand).
P.Cum 4567.00 2988.00 52.84% 3,137.00 4.99%
6.2.7 Cement Mortar 1:6 ( 1-Cement : 6-Sand).
P.Cum 4435.00 2875.00 54.26% 3,018.00 4.97%
6.2.8 Cement Mortar 1:8 ( 1-Cement : 8-Sand).
P.Cum 4278.00 2750.00 55.56% 2,887.00 4.98%
6.3 Extra over item No.6.1 & 6.2 for :

6.3.1 Wall curved in plan to mean radius not exceeding 6 Mtr.


P.Cum 456.00 240.00 90.00% 252.00 5.00%
6.3.2 Wall upto 30cm. and less thickness.
P.Cum 275.00 117.00 135.04% 122.00 4.27%
6.3.3 Pillar masonry including bed plates as per specifications.
(Bed plates to be paid separately).
P.Cum 426.00 185.00 130.27% 194.00 4.86%
6.3.3.1 Upto 45 cm length and all sides are free
P.Cum 200.00 197.00 1.52% 200.00 1.52%
6.3.3.2 Upto 45 cm length and two corners are free
P.Cum 115.00 111.00 3.60% 115.00 3.60%
6.3.3.3 Upto 90 cm length and all sides are free
P.Cum 155.00 151.00 2.65% 155.00 2.65%
6.4 Add extra for facing as per design and detailed specifications
including additional cost of stones over item No.6.1 & 6.2
for :
6.4.1 Course rubble facing First sort.
P.Cum 441.00 297.00 48.48% 311.00 4.71%
6.4.2 Course rubble facing Second sort.
P.Cum 341.00 258.00 32.17% 270.00 4.65%
6.4.3 Ashlar fine tooled facing.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
P.Sqm 620.00 290.00 113.79% 304.00 4.83%
6.4.4 Ashlar rough tooled facing.
P.Sqm 310.00 152.00 103.95% 159.00 4.61%
6.4.5 Ashlar pitched facing.
P.Sqm 295.00 143.00 106.29% 150.00 4.90%
6.4.6 R.R. stone decorative facing.
P.Sqm 150.00 77.00 94.81% 80.00 3.90%
6.4.7 Workshop pattern masonry.
P.Sqm 148.00 80.00 85.00% 84.00 5.00%
VENEERING WORK
6.5 Providing stone veneer facing in cement mortar 1:4 including
cement pointing 1:3 in white cement with admixture of
pigment matching the stone shade, upto one storey height
above plinth level, in:

6.5.1 Red Karauli sand stone rough dressed 25 to 35mm thick. P.Cum 1718.00 1087.00 58.05% 4.97%
1,141.00

6.5.2 Extra over item No. 6.5.1 for fine grinded stone used instead
of rough drssed.

P.Sqm 85.00 85.00 0.00% 85.00 0.00%

6.5.3 White Dholpur sand stone rough dressed 25 to 35mm thick.

P.Cum 2167.00 1605.00 35.02% 1,685.00 4.98%


6.5.4 Extra item No. 6.5.3 for fine grinded stone used instead of
rough dressed.
P.Sqm 85.00 85.00 0.00% 85.00 0.00%
6.5.5 Modak or similar stone rough dressed 30 to 40mm thick.

P.Sqm 1580.00 1276.00 23.82% 1,339.00 4.94%


6.5.6 Extra for fine grinded stone used instead of rough dressed.

P.Sqm 85.00 85.00 0.00% 85.00 0.00%


6.5.7 Marble facing abardari (white and pink) polished, 18 to
25mm thick.
P.Cum 1747.00 1468.00 19.01% 1,541.00 4.97%
6.5.8 Chittor/Nimbahera or similar stone facing polished 18 to
25mm thick.
P.Cum 2156.00 1597.00 35.00% 1,676.00 4.95%
6.6 Providing stone veneer facing in strips upto 125mm width
and upto 20mm thick in cement mortar 1:4 including ement
pointing 1:2 with and admixture of pigment matching the
stone shade upto 4.5Mtr. Height above plinth level, in :

6.6.1 White/Red/other stone rough dressed.


P.Cum 1709.00 1083.00 57.80% 1,137.00 4.99%
6.6.2 Extra over item No. 6.6.1 for fine grinded stone used
instead of rough dressed.
P.Sqm 85.00 85.00 0.00% 85.00 0.00%
ARCH MASONRY
6.7 Stone masonry for arches in cement sand mortar 1:3
including centering shuttering and pointing etc. upto 4.5 Mtr.
height from plinth level :

6.7.1 With hammer dressed stone (to be plastered)


P.Cum 7250.00 4049.00 79.06% 4,251.00 4.99%
6.7.2 With coursed rubble stone (to be pointed)
P.Cum 7743.00 4176.00 85.42% 4,384.00 4.98%
6.7.3 Block-in-Course chisel dressed, arch span upto 1.5
Mtr.
P.Cum 9943.00 5137.00 93.56% 5,393.00 4.98%
6.7.4 Block-in-Course chisel dressed, arch span above 1.5
Mtr.
P.Cum 10441.00 5362.00 94.72% 5,630.00 5.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
6.7.5 Cut stone fine dressed with fine joints, arch span upto 1.5
Mtr.
P.Cum 12005.00 6009.00 99.78% 6,309.00 4.99%
6.7.6 Cut stone fine dressed with fine joints, arch span above 1.5
Mtr.
P.Cum 12468.00 6215.00 100.61% 6,525.00 4.99%
6.7.8 Relieving arch stone masonry.

P.Cum 7463.00 5805.00 28.56% 6,095.00 5.00%


6.8 Extra over item No. 6.7 for dome masonry. Shuttering and
Form work if required to be paid seprately.
P.Cum 1513.00 619.00 144.43% 649.00 4.85%
6.9 Deduct if arch masonry is done in lime sand mortar 1:2 over
item No. 6.7.
P.Cum 627.00 416.00 50.72% 436.00 4.81%
6.10 Pardi wall in Katla stone in cement mortar 1:6, 75mm to
150mm thick excluding plaster.

P.Sqm 875.00 518.00 68.92% 543.00 4.83%


6.11 Dry stone pitching including preparing the surface etc.
complete :

6.11.1 Random Rubble


P.Cum 1133.00 865.00 30.98% 908.00 4.97%
6.11.2 Coursed rubble.
P.Cum 1260.00 916.00 37.55% 961.00 4.91%
MISCELLANEOUS
6.12 Providing and fixing clamps of required size shape for
anchoring stone wall lining (veneer) to the backing or
securing adjacent stone in stone wall lining (veneer) in
cement mortar 1:2 including making the necessary chases
made of :
6.12.1 Copper
Kg. 985.00 897.00 9.81% 941.00 4.91%
6.12.2 Gun metal (casted).
Kg. 985.00 897.00 9.81% 941.00 4.91%
DASA, SILLS, COPING, LINTELS, CHAJJA ETC.
6.13 Supplying and fixing in cement sand mortar 1:4 sand or
other approved stone dasa or coping of thickness 75 to
100mm (fine dressed) :

6.13.1 Plain or Bull nosed.


P.Sqm 3625.00 3405.00 6.46% 3,575.00 4.99%
6.13.2 Goladar.
P.Sqm 4004.00 3567.00 12.25% 3,745.00 4.99%
6.13.3 Plain Tikaridar.
P.Sqm 5957.00 4403.00 35.29% 4,623.00 5.00%
6.13.4 Plain ornamental.
P.Sqm 7560.00 5088.00 48.58% 5,342.00 4.99%
6.14 Supplying and fixing rough dressed stone sills, dasa, coping,
cornices sriwan, string courses etc. in cement mortar 1:4
including pointing with admixture of pigment matching with
the stone shade :
6.14.1 50 mm thick.
P.Sqm 1762.00 1640.00 7.44% 1,722.00 5.00%
6.14.2 75 mm thick.
P.Sqm 2418.00 2308.00 4.77% 2,418.00 4.77%
6.14.3 100 mm thick.
P.Sqm 2418.00 2308.00 4.77% 2,418.00 4.77%
6.15 Supplying and fixing dressed sand or other approved stone
shelves, tands in cement mortar 1:3 with fine dressed
edges :
6.15.1 25mm thick.
P.Sqm 1059.00 1022.00 3.62% 1,059.00 3.62%
6.15.2 35mm thick.
P.Sqm 1124.00 1109.00 1.35% 1,124.00 1.35%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
6.15.3 50mm thick.
P.Sqm 1300.00 1263.00 2.93% 1,300.00 2.93%
6.15.4 75mm thick.
P.Sqm 1617.00 1572.00 2.86% 1,617.00 2.86%
6.16 Supplying and fixing in walls machine cut and polished stone
shelves, tands and sills in CM 1:3 with machine cut edges :

6.16.1 Sand or other approved stone 25mm thick.


P.Sqm 1357.00 1323.00 2.57% 1,357.00 2.57%
6.16.2 Sand or other approved stone 35mm thick.
P.Sqm 1357.00 1323.00 2.57% 1,357.00 2.57%
6.16.3 Sand or other approved stone 50mm thick.
P.Sqm 1357.00 1323.00 2.57% 1,357.00 2.57%
6.16.4 Kota stone 25 to 30mm thick.
P.Sqm 591.00 557.00 6.10% 584.00 4.85%
6.16.5 Madras Stone 25 to 30 mm thick.
P.Sqm 709.00 675.00 5.04% 708.00 4.89%
6.16.6 Chittor/Nimbahera 25 to 30mm thick.
P.Sqm 650.00 616.00 5.52% 646.00 4.87%
6.16.7 Extra over item 6.16.1 to 6.16.6 for machine cut both side
polished stone is used
P.Sqm 70.00 70.00 0.00% 70.00 0.00%
6.17 Supplying and fixing stone lintels/bed plates of approved
quarry rough dressed in cement mortar 1:4 :

6.17.1 Upto 15 cm. thick.


P.Cum 11671.00 8030.00 45.34% 8,431.00 4.99%
6.17.2 Above 15 cm. thick.
P.Cum 10169.00 7430.00 36.86% 7,801.00 4.99%
6.18 Providing and fixing 30 to 40 mm thick stone chajjas in
cement sand mortar 1:4 including making gola at junction
with wall in cement concrete M-15 grade (1:2 : 4 nominal
mix), drip course :

6.18.1 Pointing both faces in CM 1:3 with an admixture of pigment


matching the stone shade.
P.Sqm 544.00 465.00 16.99% 488.00 4.95%
6.18.2 20mm thick plastering in CM 1:6 on both faces.
P.Sqm 678.00 563.00 20.43% 591.00 4.97%

6.19 Deduct from item No. 6.18.1 for fixing done in lime sand
mortar 1:2 instead of CM 1:3.
P.Sqm 60.00 60.00 0.00% 60.00 0.00%
6.20 Providing dab stone over Chajjas duly fixed in cement sand
mortar 1:6 complete :

6.20.1 80mm thick.


P.Sqm 1186.00 934.00 26.98% 980.00 4.93%
6.20.2 50mm thick.
P.Sqm 1158.00 936.00 23.72% 982.00 4.91%
6.21 Providing and fixing fine dressed machine cut approved sand
stone steps (risers and treads) in CM 1:4 including pointing
the joints with white cement mortar 1: 2 with admixture of
matching the stone shade with width of steps 1200 mm :

6.21.1 35 to 40mm thick.


P.Sqm 992.00 840.00 18.10% 882.00 5.00%
6.21.2 50mm thick.
P.Sqm 1027.00 880.00 16.70% 924.00 5.00%
6.22 Providing and fixing stone jali 40mm thick through out
(without sinking or moulding in jali slab) in CM 1:3 including
pointing in white cement marble mortar 1:2 (1 cement : 2
marble dust) with an admixture of pigment matching the
stone shade, jali patterns to be cut square to jali slab without
any chamfers etc. :

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
6.22.1 Red Sand stone.
P.Sqm 4732.00 3139.00 50.75% 3,295.00 4.97%
6.22.2 White Sand stone.
P.Sqm 4732.00 3392.00 39.50% 3,561.00 4.98%
6.23 Add extra for doing masonry work in or under water and or
liquid mud including cost of pumping or bailing out water and
removing and slush etc. complete.
Cum P. 125.00 59.00 111.86% 3.39%
Mtr. 61.00
Depth
6.24 Extra for subsequent storey or height of 4.5 Mtr. or part
thereof for all masonry work :
6.24.1 Quantity in Sqm.
P.Sqm 16.00 16.00 0.00% 16.00 0.00%
6.24.2 Quantity in Cum
P.Sqm 202.00 89.00 126.97% 93.00 4.49%
6.25 Making groove of approved design upto 20 x 20mm size in
the joints of stone veneering work for walls, columns, offsets
etc. including finishing in white cement marble mortar 1:2 (1
cement : 2 marble dust) with an admixture of pigment
matching the stone shade, complete
P. Rmt. 25.00 13.22 89.11% 13.22 0.00%
Note :- Recover cost of useful stone @ 2/3rd of masonry
work dismantalled quantity.
P.Cum 600.00 600.00 0.00% 600.00 0.00%
PART - B : ASHLAR WORK
ASHLAR STONE WORK
6.26 Supplying and fixing ashlar sills, jambs, skirting, steps etc.
rough dressed :
Supplying and fixing Soorsagar Bhura or equivalent ashlar
sills, lintels and dassa, bearing, bed & top surface made
perfectly even, jambs, skirting steps etc. rough dressed:

6.26.1 Upto 15 cm. thick


Red Ashler P.Cum 14618.00 8415.00 73.71% 8,835.00 4.99%
Soorsagar or eqvt. White Ashler P.Cum 16012.00 11031.00 31.11% 11,582.00 5.00%
6.26.2 Above 15 cm. and upto 20cm. thick
Red Ashler P.Cum 14718.00 8458.00 74.01% 8,880.00 4.99%
Soorsagar or eqvt. White Ashler P.Cum 16112.00 11074.00 31.27% 11,627.00 4.99%
6.26.3 Above 20 cm. thick and upto 2.15 m length (Pats.).
Red Ashler P.Cum 14818.00 8500.00 74.33% 8,925.00 5.00%
Soorsagar or eqvt. White Ashler P.Cum 16212.00 11117.00 31.43% 11,672.00 4.99%
6.26.4 Above 20 cm. thick & above 2.15 m length
Red Ashler P.Cum 14843.00 8512.00 74.38% 8,937.00 4.99%
Soorsagar or eqvt. White Ashler P.Cum 16237.00 11128.00 31.47% 11,684.00 5.00%
6.27

6.27.1 Upto 15 cm. thick.


Soorsagar or eqvt. White Ashler P.Cum 5005.00 Deleted
6.27.2 Above 15 cm & upto 20 cm. thick
Soorsagar or eqvt. White Ashler P.Cum 5105.00 Deleted

6.27.3 Above 20cm. thick (Pats) and upto 2.15m length.


Soorsagar or eqvt. White Ashler P.Cum 5230.00 Deleted
6.27.4 Above 20cm thick (pats) and above 2.15m. length.
Soorsagar or eqvt. White Ashler P.Cum 5380.00 Deleted
6.28 Supply and fixing ashlar lintels and Dassa exposed
horizontal and vertical faces 3 – lines fine dressed (bearing
bed & top surface made perfectly even) :

6.28.1 Upto 15 cm. thick.


Red Ashler P.Cum 17316.00 9610.00 80.19% 10,090.00 4.99%
Soorsagar or eqvt. White Ashler 18092.00 12016.00 33.58% 12,616.00 4.99%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
6.28.2 Above 15 cm & upto 20 cm. thick
Red Ashler P.Cum 17596.00 9743.00 80.60% 10,230.00 5.00%
Soorsagar or eqvt. White Ashler 18452.00 12187.00 33.95% 12,796.00 5.00%
6.28.3 Above 20cm. thick and upto 2.15m length.
Red Ashler P.Cum 17666.00 9824.00 79.82% 10,315.00 5.00%
Soorsagar or eqvt. White Ashler 18522.00 12268.00 33.77% 12,881.00 5.00%
6.28.4 Above 20cm thick & above 2.15m. length.
Red Ashler P.Cum 17946.00 9957.00 80.24% 10,454.00 4.99%
Soorsagar or eqvt. White Ashler 18802.00 12401.00 34.04% 13,021.00 5.00%
6.29 Supplying and fixing ashlar solid block pillars fully fine (3
lines) dressed.
Red Ashler P.Cum 24022.00 12311.00 95.13% 12,926.00 5.00%
Soorsagar or eqvt. White Ashler 26255.00 15634.00 40.45% 16,415.00 5.00%
6.30 Supplying and fixing ashlar stone arches fully fine (3 lines)
dressed for 1.5 to 5m. span (Net content payable).

Red Ashler P.Cum 20036.00 10609.00 88.86% 11,139.00 5.00%


Soorsagar or eqvt. White Ashler 22111.00 13905.00 37.11% 14,600.00 5.00%
6.31 Supplying and fixing ashlar face stone 10 cm. thick fine (3
lines) dressed.
Red Ashler P.Sqm 4223.00 2478.00 70.42% 2,601.00 4.96%
Soorsagar or eqvt. White Ashler 4579.00 3593.00 21.53% 3,772.00 4.98%
6.32 Supplying and fixing ashlar coping ordinary 7 to 10cm. thick
2 – line dressed (normal length of single piece not less than
0.90m).

Red Ashler P.Sqm 4002.00 2421.00 65.30% 2,542.00 5.00%


Soorsagar or eqvt. White Ashler 3398.00 3397.00 0.03% 3,398.00 0.03%
6.33 Supplying and fixing ashlar coping moulded and counter
slopped 7 to 10cm. thick (2-line dressed) (-do-)
Red Ashler P.Sqm 4522.00 2658.00 70.13% 2,790.00 4.97%
Soorsagar or eqvt. White Ashler 3918.00 3644.00 6.99% 3,826.00 4.99%
6.34 Supplying and fixing ashlar shrivan (Kharpa grooved) rough
dressed (-do-)
Red Ashler P.Cum 13642.00 7714.00 76.85% 8,099.00 4.99%
Soorsagar or eqvt. White Ashler
6.35 Fine dressing of ashlar stone work (payable on Executive
Engineer’s test checking) :

6.35.1 Three line dressed.


Red Ashler P.Sqm 756.00 357.00 111.76% 374.00 4.76%
Soorsagar or eqvt. White Ashler 1570.00 726.00 53.76% 762.00 4.96%
6.35.2 Two line dressed.

Red Ashler P.Sqm 596.00 278.00 114.39% 291.00 4.68%


Soorsagar or eqvt. White Ashler 976.00 451.00 53.79% 473.00 4.88%
6.35.3 One line dressed.
Red Ashler P.Sqm 353.00 159.00 122.01% 166.00 4.40%
Soorsagar or eqvt. White Ashler 788.00 350.00 55.58% 367.00 4.86%
6.36 Rough dressing ashlar stone work (payable only for
departmental work).
Red Ashler P.Sqm 132.00 67.00 97.01% 70.00 4.48%
Soorsagar or eqvt. White Ashler 187.00 90.00 51.87% 94.00 4.44%
6.37 Supplying and fixing ashlar cantilever steps fine (3 lines)
dressed (triangular exposed surface is to be measured).

Red Ashler P.Cum 50074.00 40373.00 24.03% 42,391.00 5.00%


Soorsagar or eqvt. White Ashler 60874.00 40787.00 33.00% 42,826.00 5.00%
6.38 (-do-) (2 lines) (triangular exposed surface is to be
measured).
Red Ashler P.Cum 48074.00 38073.00 26.27% 39,976.00 5.00%
Soorsagar or eqvt. White Ashler 58874.00 38487.00 34.63% 40,411.00 5.00%
6.39 Deduct if the shape of cantilever and landing steps is
rectangular :

6.39.1 From item No. 6.37

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
Red Ashler P.Cum 25037.00 20187.00 24.03% 21,196.00 5.00%
Soorsagar or eqvt. White Ashler 30437.00 20394.00 33.00% 21,413.00 5.00%
6.39.2 From item No. 6.38
Red Ashler P.Cum 24037.00 19037.00 26.26% 19,988.00 5.00%
Soorsagar or eqvt. White Ashler 29437.00 19244.00 34.63% 20,206.00 5.00%
6.40 Supplying and fixing ashlar rain water spouts fine (3 lines)
dressed as per approved design of size :

6.40.1 60 x 26 x 18 cm.
Red Ashler Each 492.00 297.00 65.66% 311.00 4.71%
Soorsagar or eqvt. White Ashler 717.00 462.00 35.56% 485.00 4.98%
6.40.2 60 x 30 x 25 cm.
Red Ashler Each 630.00 426.00 47.89% 447.00 4.93%
Soorsagar or eqvt. White Ashler 625.00 625.00 0.00% 625.00 0.00%
6.41 Supplying and fixing ashlar stone chhajja 5 to 7 cm. thick all
exposed surface fully fine dressed, weather dripped
including 75x75mm. cement botta (1:2 : 4) between chhajja
& wall (single piece upto 1:2m length) :
6.41.1 Three line dressed.
Red Ashler P.Sqm 1219.00 1087.00 12.14% 1,141.00 4.97%
Soorsagar or eqvt. White Ashler 1628.00 1535.00 5.71% 1,611.00 4.95%
6.41.2 Two line dressed
Red Ashler P.Sqm 1059.00 966.00 9.63% 1,014.00 4.97%
Soorsagar or eqvt. White Ashler 1035.00 1035.00 0.00% 1,035.00 0.00%
6.41.3 One line dressed.
Red Ashler P.Sqm 816.00 777.00 5.02% 815.00 4.89%
Soorsagar or eqvt. White Ashler 902.00 902.00 0.00% 902.00 0.00%

6.42 Supplying and fixing Red ashlar railing ordinary with takia
and thambli complete fine dressed :
6.42.1 Three line dressed.
Red Ashler P.Sqm 1073.00 1010.00 6.24% 1,060.00 4.95%
6.42.2 Two line dressed
Red Ashler P.Sqm 913.00 913.00 0.00% 913.00 0.00%
6.42.3 One line dressed.
Red Ashler P.Sqm 744.00 744.00 0.00% 744.00 0.00%

6.43 Supplying and fixing Red ashlar stone jali 5 to 7 cm. thick
curved :
6.43.1 Upto half depth.
Red Ashler P.Sqm 1740.00 1685.00 3.26% 1,740.00 3.26%
6.43.2 Upto full depth.
Red Ashler P.Sqm 2214.00 2159.00 2.55% 2,214.00 2.55%
6.44 Re-fixing old ashlar stone w/o dressing.
Red Ashler P.Cum 338.00 338.00 0.00% 338.00 0.00%
Soorsagar or eqvt. White Ashler 383.00 361.00 5.74% 379.00 4.99%
6.45 (-do-) stone slab.
Red Ashler P.Sqm 72.00 72.00 0.00% 72.00 0.00%
Soorsagar or eqvt. White Ashler 121.00 88.00 27.27% 92.00 4.55%
6.46 Supplying and fixing Red ashlar shelves 5 to 7cm. thick
exposed surface rough dressed.
Red Ashler P.Sqm 273.00 267.00 2.25% 273.00 2.25%
6.47 (-do-) exposed surface fine (3 lines) dressed.
Red Ashler P.Sqm 678.00 466.00 45.49% 489.00 4.94%
6.48 Red ashlar todies for verandah (pillar and pat) fine (3 lines)
dressed.
Red Ashler P.Sqm 1119.00 476.00 135.08% 499.00 4.83%
6.49 Supplying and fixing ashlar todies for chhajjas and shelves
fine (3 lines) dressed 30 x 30 x 10 cm.
Red Ashler Each 735.00 468.00 57.05% 491.00 4.91%
6.50 Supplying and fixing chittar or equivalent stone slab perchits
with making edges and top surface level in cement mortar
1:3 complete finished :
6.50.1 Upto 2.15m. span.
Soorsagar or eqvt. White Ashler P.Sqm 896.00 640.00 28.57% 672.00 5.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-6
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
6.50.2 Add extra for span more than 2.15m
Soorsagar or eqvt. White Ashler P.Sqm 100.00 100.00 0.00% 100.00 0.00%
6.51 Supplying and fixing 7 to 10 cm. Soorsagar or equivalent
stone chaps in lime mortar or gypsum rough dressed more
than 0.60 m. length.
Soorsagar or eqvt. White Ashler P.Sqm 298.00 198.00 33.56% 207.00 4.55%
6.52 Supplying and fixing 2.5 to 5 cm. thick Darba Darbi wall of
red (Ros) stone rough dressed fixed in lime mortar or
gypsum.
Red Ashler P.Sqm 385.00 302.00 27.48% 317.00 4.97%
6.53 Supplying and fixing soorsagar or equivalent white stone
slab steps 75 to 100 mm thick fine (3 lines) dressed for tread
& riser upto 2m. length, simply supported or centrally fixed
with both ends free (projection to be paid only).

Soorsagar or eqvt. White Ashler P.Sqm 2853.00 1505.00 47.25% 1,580.00 4.98%
6.54 Deduct if Soorsagar or equivalent Bhura Ashlar stone is
used in place of white ashlar.
Soorsagar or eqvt. White Ashler P.Sqm 23.00 23.00 0.00% 23.00 0.00%

6.55 Providing & fixing "ornamental stone cladding" of approved sand stone
with dressing complete as per existing design/pattern/approved
design,fixing with 30mm thickgrinded cement mortar 1:2 & pointing with
white cement with araldite and pigment to match shade the stone
complete in all respect as per direction of Engineer incharge.(75mm
thick)
P.Sqm 3424.00 3368.00 1.64% 3,424.00 1.66%

6.56 Providing and fixing fine dressed sand stone "Dasa/coping" as per
existing matching , fixing in grinded lime surkhi mortar 1:2 including
pointing in cream and stone powder 1:1 with an admixture of pigment to
match the shade of stone complete in all respect. (d) above 100mm to
150mm thick with pan patti design. P.Sqm 2988.00 2941.00 1.57% 2,988.00 1.60%

6.57 Providing and fixing stone "Pillars" (Stambha) on pillers of Sabha


Mandap/ Antral/ Praeshmandapa etc.fine dressed as per existing matching
stone/ approved quarry with plain moulding work as per temple
architecture complete with all scaffolding and shuttering work, all lead
and lift in proper order and sequence etc.as per direction of Engineer
Incharge.
P.Cum 34785.00 34624.00 0.46% 34,785.00 0.46%

6.58 Providing and fixing of fine dressed "Valted decorative ceiling" of Sabha
mandapa/ Antral/ Praeshmandapa etc. having simple carving work /
moulding work of matching/ approved stone fixing carefully by
machenical/manual system carefully with proper order and sequence as
per temple architecture including all scaffolding and shuttering work, all
lead and lift as per direction of Engineer incharge. (a) Thickness of
slab150mm to 200mm
P.Sqm 32773.00 32493.00 0.85% 32,773.00 0.86%

6.59 Providing and fixing "Stone Kalasha" as per existing matching on doms
od chattries/jharokhas as per existing design & dimensions as per
traditional practices, fixing of kalash carefully without damaging the
doms complete in all respect. Sand stone/approved stone Kalasha
height.(exposed part) 45cm. to 60cm. Each 2724.00 2644.00 2.94% 2,724.00 3.03%

6.60 Providing and fixing stone " Lintels " of Sabha Mandap/ Antral/
Praeshmandapaas etc.fine dressed as per existing matching stone/
approved quarry with plain moulding work as per temple architecture
complete with all scaffolding and shuttering work, lead and lift in proper
order and sequence etc.as per direction of Engineer Incharge.
P.Cum 30038.00 29982.00 0.19% 30,038.00 0.19%
995470.00 651457.22 52.81% 683184.22 4.87%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-5

BRICK WORK

NOTE:
1- Rates are for three storey from plinth level and include cost of water, scaffolding,
centering and shuttering, curing and raking of joints etc. complete
CHAPTER - B-5 in all respect.
Chapter Description Unit Analysis Rate As per BSR Variation Proposed % Above
Code No. 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
BRICK WORK
5.1 Brick masonry in foundation and plinth with bricks of class
designation 75 in :

5.1.1 Cement lime mortar 1 : 1 : 6 (1 cement : 1 lime putty : 6


coarse sand)
P.Cum 5083.00 3709.00 37.05% 3,887.00 4.80%
5.1.2 Cement lime mortar 1 : 2 : 9 (1 cement : 2 lime putty : 9
coarse sand)
P.Cum 4862.00 3558.00 36.65% 3,729.00 4.81%
5.1.3 Cement lime mortar 1:3 :12 (1 cement : 3 lime putty : 12
coarse sand)
P.Cum 4860.00 3540.00 37.29% 3,710.00 4.80%
5.1.4 Cement mortar 1:3 (1 cement : 3 coarse sand)
P.Cum 5377.00 3881.00 38.55% 4,067.00 4.79%
5.1.5 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
P.Cum 5168.00 3742.00 38.11% 3,922.00 4.81%
5.1.6 Cement mortar 1 : 5 (1 cement : 5 coarse sand)
P.Cum 5052.00 3642.00 38.71% 3,817.00 4.81%
5.1.7 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
P.Cum 4952.00 3554.00 39.34% 3,725.00 4.81%
5.1.8 Cement mortar 1 : 8 (1 cement : 8 coarse sand)
P.Cum 4832.00 3460.00 39.65% 3,626.00 4.80%
5.1.9 Mud mortar
P.Cum 3882.00 2780.00 39.64% 2,913.00 4.78%
5.2 Add extra over item No.5.1 for brick work in super structure
upto third storey.
P.Cum 745 232.00 221.12% 243.00 4.74%
5.3 Add extra over item No. 5.1 for brick work in :-

5.3.1 Square or Rectangular Pillars.


P.Cum 390.00 171.00 128.07% 179.00 4.68%
5.3.1.1 Masonry curved in plan not exceeding mean radius upto 6
Mtrs.
P.Cum 390.00 250.00 56.00% 262.00 4.80%
5.3.1.2 Upto 45 cm length and two corners are free
P.Cum 116 105.00 10.48% 110.00 4.76%
5.3.1.3 Upto 90 cm length and all sides are free
P.Cum 165 150.00 10.00% 157.00 4.67%
5.3.2 Circular Pillars.
P.Cum 165 150.00 10.00% 157.00 4.67%
5.3.3 Circular masonry in plan upto a mean radius not exceeding
6 Mtr.
P.Cum 150 150.00 0.00% 150.00 0.00%

5.4 Extra for cutting or chamfering of bricks upto one brick depth
to required shape in masonry work.
P.Cum 325.00 9.00 3511.11% 9.00 0.00%
5.5 Brick work in plain arches in super structure upto third
storey in cement mortar 1 : 3 including centering and
shuttering complete span upto 6 Mtr. with Brick of class
designation 75.
P.Cum 7206.00 4660.00 54.64% 4,884.00 4.81%
5.6 Brick work in gauged arches in super structure upto third
storey in cement mortar 1 : 3 including centering and
shuttering complete span upto 6 meter with Brick of class
designation 75.
P.Cum 6769.00 4621.00 46.48% 4,843.00 4.80%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-5
Chapter Description Unit Analysis Rate As per BSR Variation Proposed % Above
Code No. 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
5.7 Add extra over item No. 5.5 & 5.6 for arches exceeding 6m
span including all shuttering and centering, bolting wedging
and removal.
P.Cum 120.00 120.00 0.00% 120.00 0.00%
5.8 Half brick masonry in foundation & plinth using bricks of
designation 75

5.8.1 Cement lime mortar 1:1:6 (1 cement : 1 lime : 6 coarse P.Sqm 636.00 480.00 32.50% 4.79%
send) 503.00
5.8.2 Cement mortar 1 : 3 (1 cement : 3 coarse sand)
P.Sqm 669.00 499.00 34.07% 523.00 4.81%
5.8.3 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
P.Sqm 645.00 483.00 33.54% 506.00 4.76%
5.8.4 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
P.Sqm 621.00 463.00 34.13% 485.00 4.75%
5.9 Add extra over item No. 5.8 for half brick masonry in super
structure upto third story including cost of norminal hoop
reinforcement (2 Nos. ,6mm Ø M.S. bar at every fourth
course) .
P.Sqm 95.00 27.00 251.85% 28.00 3.70%
5.10 Brick work in partition in super structure upto third storey
7cm. thick (brick on edges) using bricks of class designation
75 in :
5.10.1 Cement mortar 1 : 3 (1 cement : 3 coarse sand)
P.Sqm 523.00 376.00 39.10% 394.00 4.79%
5.10.2 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
P.Sqm 508.00 366.00 38.80% 384.00 4.92%
5.10.3 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
P.Sqm 492.00 353.00 39.38% 370.00 4.82%
5.11 Honey comb brick work half brick thick with bricks of class
designation 75 upto third storey in:

5.11.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand)


P.Sqm 404.00 286.00 41.26% 300.00 4.90%
5.11.2 Cement mortar1 : 6(1 cement : 6 coarse sand
P.Sqm 388.00 271.00 43.17% 284.00 4.80%
5.12 Providing brick in half brick or brick on edge 5 to 7 cm.
projected from wall face in bricks of class designation 75 in
cement mortar 1 : 4 (1cement : 4 coarse sand) for cornices
corbelling and coping etc upto third storey .
P.Rmt. 12.00 12.00 0.00% 12.00 0.00%
5.13 Extra over item no. 5.1 for laying brick work in or under
water and or liquid mud including cost of pumping of or
bailing out water and removal of slush etc. complete.

Cum. Per
190.00 102.00 86.27% 4.90%
1m depth
107.00
5.14 Add extra over item No.5.1 for laying bricks work in or under
foul condition.
P.Cum 191.00 88.00 117.05% 92.00 4.55%
5.15 Brick work in super structure upto third storey with selected bricks
of class designation 75 in exposed brick work including making
horizontal and vertical grooves 10mm. wide 12mm. deep
complete in cement mortar 1:6.
P.Cum 5053.00 3609.00 40.01% 3,782.00 4.79%
5.16 Honey comb brick work 23cm thick with bricks of class
designation 75 upto third storey in:

5.16.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand)


P.Sqm 812.00 600.00 35.33% 628.00 4.67%
5.16.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand)

P.Sqm 774.00 564.00 37.23% 591.00 4.79%


5.17 Dry brick pitching in proper bond with bricks of class
designation 75.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-5
Chapter Description Unit Analysis Rate As per BSR Variation Proposed % Above
Code No. 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
P.Cum 3814.00 2801.00 36.17% 2,935.00 4.78%
5.18 Add extra over respective items all type of bricks for using
clay fly ash bricks.

5.19 Add extra for doing brick work for each subsequent storey
for respective items beyond third story.

5.19.1 Quantity in Cum.


P.Cum 149.00 77.00 93.51% 80.00 3.90%
5.19.2 Quantity in R. Mtr.
R.Mtr 3.00 2.50 20.00% 3.00 20.00%
5.19.3 Quantity in Sqm.
P.Sqm 19.00 9.00 111.11% 9.00 0.00%
5.20 Brick work with machine moulded perforated bricks of class
designation 125 confirming to IS : 2222- 1991 in
superstructure above plinth level upto three floor level in
cement mortar 1:6 (1-Cement : 6- Coarse Sand) :

5.20.1 with F.P.S. bricks. P.Cum 5200.00 4650.00 11.83% 4,873.00 4.80%

5.20.2 with Modular bricks. P.Cum 4600.00 4200.00 9.52% 4,402.00 4.81%

5.21 Add extra over item of brick work with class designation 100
in substitution of class designation 75 :

5.21.1 Quantity in Cum. P.Cum 190.00 175.00 8.57% 183.00 4.57%

5.21.2 Quantity in Sqm. P.Sqm 22.00 20.00 10.00% 21.00 5.00%

NEW ITMES
5.22 Brick work with clay flyash F.P.S. brick (IS 13757-
1993 ) of class designation 75 in superstructure above
plinth level upto floor five level in :
5.22.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand) Cum 4874.00 4621.00 5.48% 4,843.00 4.80%
5.22.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand) Cum 4657.00 4415.00 5.48% 4,627.00 4.80%

5.23 Brick work with mechanised autoclaved flyash lime


bricks conforming to IS: 12894 :2002 of class
designation 100 in superstructure above plinth level
upto floor V level in.
5.23.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand) Cum 4895.00 4641.00 5.47% 4,864.00 4.80%
5.23.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand) Cum 4679.00 4435.00 5.50% 4,648.00 4.80%

5.24 Add extra for brick work in superstructure above floor


five level, for each four floors or part thereof.
5.24.1 Quantity in Cum. Cum. 236.00 236.00 0.00% 236.00 0.00%
5.24.2 Quantity in Sqm. Sqm. 21.00 21.00 0.00% 21.00 0.00%

5.25 Add extra over item of brick work with class


designation 100 in substitution of class designation
75 :
5.25.1 Quantity in Cum. Cum. 148.00 148.00 0.00% 148.00 0.00%
5.25.2 Quantity in Sqm. Sqm. 17.00 17.00 0.00% 17.00 0.00%

5.26 Half Brick work with mechanised autoclaved flyash lime


bricks conforming to IS: 12894 :2002 of class
designation 100 in superstructure above plinth level
upto floor V level in.
5.26.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand) Sqm 606.00 564.00 7.45% 591.00 4.79%
5.26.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand) Sqm 582.00 541.00 7.58% 567.00 4.81%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-5
Chapter Description Unit Analysis Rate As per BSR Variation Proposed % Above
Code No. 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
5.27 Half Brick work with mechanised autoclaved flyash lime
bricks conforming to IS: 12894 :2002 of class
designation 75 in superstructure above plinth level upto
floor V level in.
5.27.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand) Sqm 587.00 547.00 7.31% 573.00 4.75%
5.27.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand) Sqm 563.00 524.00 7.44% 549.00 4.77%

5.28.1 Providing & Laying autoclave aerated blocks masonry with


100mm thick AAC Blocks of Grade-I Conforming to IS:2185
Part:III in superstructure above plinth level with cement
mortar 1:4 (1 cement: 4 coarse sand) .The rates includes
providing and placing in position 2 Nos. 6 mm dia M.S. bars
at evry third course of masonary.
Cum. 5057.00 4913.00 2.93% 5,057.00 2.93%

5.28.2 Providing & Laying autoclave aerated blocks masonry with


150mm/230mm/300mm thick AAC Blocks of Grade-I
Conforming to IS:2185 Part:III in superstructure above plinth
level with polymer modified adhesive mortar as per direction
of Engineer in Charge. Cum. 4396.00 4216.00 4.27% 4,396.00 4.27%

86619.00 62997.50 37.50% 66005.00 4.77%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-4

REINFORCED CONCRETE

NOTE:
1- Rates for complete work laying, compaction, vibration, curing and all types of T & P,
including P.O.L. etc and grinding and mixing of mortar.

2- The rates for centering and shuttering are for steel plates shuttering for complete
work including centering, shuttering nails and other such items required. The
shuttering shall be removed after required time as per instruction by Engineer-
incharge & IS 456:2000.

3- The Concrete for all grade shall be produced in conformation to the laid down
procedures and all relevant clauses of IS 456 : 2000

4- If any machinery like mechanical mixture machine, vibrator or mechanical mortar


miller etc. is supplied by the Department, the hire charges as per department rate will
be charged and transportation cost will be borne by the contractor.

5- No R.C.C. work shall be permitted without the use of mechanical mixer by hopper and
vibrator.

6- Contractor at site shall arrange a stand by mechanical mixer and extra vibrator if
more than 20 cum of RCC is to be done in a single day.

7- The rate for R.C.C. work is inclusive of cost of providing cement mortar covers
Blocks. The rates for centering includes placement of cover blocks.

8- The producer / manufacturer / contractor shall obtain mix proportions of each grade
of concrete from a recognized laboratory and submit detail to the Engineer-in-charge
for approval. Concrete of any particular design mix and grade shall be produced /
manufactured by weight batched hopper mechnical mixer with assigned capacity of
mixing drum as directed by Engineer-in-charge.

9- If any change required in the approved Job Mix design ingredient, Fresh Job Mix
design shall be obtain by the contractor from approved lab and shall be got approved
from Engineer-in-charge

CHAPTER - B-4
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
CAST-IN-SITU CONCRETE:
4.1 Providing and laying in position specified grade of cement
concrete for all RCC structural elements upto plinth level including
curing, compaction, finishing with rendering in cement sand
mortar 1:3 (1 cement: 3 coarse sand) and making good the joints
excluding the cost of centering, shuttering and reinforcement.

M20 grade Nominal Mix/ Design Mix


P.Cum 5438.00 4186.00 29.91% 4,383.00 4.71%

4.2 Providing and laying in position specified grade of cement


concrete for RCC structural elements upto floor three level
including curing, compaction, finishing with rendering in cement
sand mortar 1:3 (1 cement: 3 coarse sand) and making good the
joints excluding the cost of centering, shuttering and
reinforcement for :-

4.2.1 Walls (any thickness) including attached pilasters,


buttresses, plinth and string courses, fillets, columns, pillars,
piers, abutments, posts and struts etc.
4.2.1.1 M20 grade Nominal Mix
P.Cum 5689.00 4562.00 24.70% 4,776.00 4.69%
4.2.1.2 M20 grade Design Mix
P.Cum 5871.00 4562.00 28.69% 4,776.00 4.69%
4.2.2 Beams, suspended floors, roofs, griders having slopes up to
15º, landings, balconies, shelves, chajjas, lintels, bands,
plain windows sills, staircases and spiral staircases.

4.2.2.1 M20 grade Nominal Mix


P.Cum 6042.00 4660.00 29.66% 4,879.00 4.70%
4.2.2.1 M20 grade Design Mix
P.Cum 6361.00 4660.00 36.50% 4,879.00 4.70%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-4
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
4.2.3 Arches, arch ribs, domes, vaults, shells, folded plate,
chimneys, shafts , roofs having slope more than 15º ,vertical
and horizontal fins individually or forming box louvers, facias
and eaves boards.
4.2.3.1 M20 grade Nominal Mix

P.Cum 6326.00 4709.00 34.34% 4,930.00 4.69%


4.2.3.2 M20 grade Design Mix
P.Cum 6326.00 4709.00 34.34% 4,930.00 4.69%
4.3 Add extra over item no. 4.1.2 , 4.2.1.2 , 4.2.2.2 and 4.2.3.2

4.3.1 Providing M-25 grade R.C.C. instead of M-20 grade R.C.C.

P.Cum 1628.00 892.00 82.51% 934.00 4.71%


4.3.2 Providing M-30 grade R.C.C. instead of M-20 grade R.C.C.

P.Cum 1695.00 1322.00 28.21% 1,384.00 4.69%


4.3.3 Providing M-35 grade R.C.C. instead of M-20 grade R.C.C.

P.Cum 1748.00 1598.00 9.39% 1,673.00 4.69%


4.4 Add extra for RCC work in superstructure above floor three
level for each subsequent floor level or part thereof for item
no.4.2
P.Cum 75.00 75.00 0.00% 75.00 0.00%
4.5 Add extra over item no. 4.1 and 4.2 of concrete work for
using integrals water proofing compound as approved by
Engineer In Charge in specified standard / recommended
dosages.

5% 5% 5%
SHUTTERING
4.6 Centering and Shuttering with plywood or steel sheets
including strutting, propping bracing both ways and removal
of formwork for foundation in basements rafts, footings,
straps beams, bases of columns etc. up to plinth level.

P.Sqm 162.00 137.00 18.25% 143.00 4.38%

4.7 Centering & shuttering with plywood or steel sheets


including strutting, propping bracing both ways with wooden
members and removal of formwork for upto floor three level
for :
4.7.1 Walls (any thickness) including attached pilasters,
buttresses plinth and string course.
P.Sqm 326.00 250.00 30.40% 262.00 4.80%
4.7.2 Suspended floors, roofs landings staircases, balconies,
girders, cantilevers, bands, coping bed plates, anchor
blocks, sills, chhajjas, lintel, beam etc.
P.Sqm 370.00 280.00 32.14% 293.00 4.64%
4.7.3 Columns, pillars, posts and struts etc.
P.Sqm 392.00 300.00 30.67% 314.00 4.67%
4.7.4 Spiral staircases, chimneys shafts etc.
P.Sqm 395.00 320.00 23.44% 335.00 4.69%
4.7.5 Arches, domes, vaults etc. up to 6 Mtr span.
P.Sqm 891.00 700.00 27.29% 733.00 4.71%
4.7.6 Arches, domes, vaults etc exceeding 6 Mtr span
P.Sqm 1467.00 1025.00 43.12% 1,073.00 4.68%
4.7.7 Fins, Facia, louvers, etc.
P.Sqm 611.00 500.00 22.20% 524.00 4.80%
4.7.8 Singly - curved shells.
P.Sqm 500.00 500.00 0.00% 500.00 0.00%
4.7.9 Doubly - curved shells.
P.Sqm 600.00 600.00 0.00% 600.00 0.00%
4.7.10 Grid roofing with panel area less than 2.5 Sqm (contact area
to be measured).

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-4
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
P.Sqm 329.00 298.00 10.40% 312.00 4.70%
4.7.11 Grid roofing with panel area more than 2.5 Sqm. (contact
area to be measured)
P.Sqm 285.00 258.00 10.47% 270.00 4.65%
4.7.12 Add extra for shuttering in circular work in plan up to dia
10m over item Nos. 4.7.1 to 4.7.2
P.Sqm 36.00 36.00 0.00% 36.00 0.00%
4.7.13 Add extra for shuttering in circular work in plan, above 10
mtr. and up to 30 Mtr. Dia over item no. 4.7.1 and 4.7.2

P.Sqm 24.00 24.00 0.00% 24.00 0.00%


4.8 Add extra over item no 4.7.1 to 4.7.11for using steel
telescopic prop instead of wooden member
P.Sqm 25% 20% 25.00% 21% 4.70%

4.9 Add extra over item no 4.7.1 to 4.7.11for using steel cup
lock system instead of wooden member
P.Sqm 53.00 52.00 1.92% 53.00 1.92%
4.10 Add extra over item Nos. 4.7.1 to 4.7.11 for doing centering
and shuttering work for each subsequent storey above three
floor.
P.Sqm 29.00 22.00 31.82% 25.00 13.64%
4.11 Add extra over item no. 4.7.1 to 4.7.11 for every additional 1
m ht or part there off beyond 4.5mtr single story height of
shuttering.
P.Sqm 61.00 30.00 103.33% 34.00 13.33%

STEEL REINFORCEMENT:
4.12 Providing and fabricating reinforcement for R.C.C. work
including straightening, cutting, bending, placing in position
and binding (including cost of binding wire) all complete up
to floor three level.
4.12.1 Mild steel and medium tensile bars (IS : 432).
Kg. 66.00 63.00 4.76% 66.00 4.76%
4.12.2 Cold twisted deformed bars (IS : 1786).
Kg. 67.00 65.00 3.08% 67.00 3.08%
4.12.3 Hot rolled deformed bars (IS : 1139).
Kg. 67.00 65.00 3.08% 67.00 3.08%
4.12.4 Thermo-mechanically Treated bars (Conforming of relevent
IS code)
Kg. 67.00 66.00 1.52% 67.00 1.52%
4.13 Labour charges for cutting, bending for fabrication and binding
reinforcement (plain or tor/ribbed steel) as per drawing and design
for R.C.C. and R.B. work including cost of binding wire with all
lead and lift up to floor three level complete.
Kg. 8.00 6.50 23.08% 6.50 0.00%
4.14 Add extra over item No. 4.12 and 4.13 in superstructure
above floor three level for subsequent floor level or part
there of.
Kg. 0.88 0.50 76.00% 0.52 4.70%
PRECAST CEMENT CONCRETE
4.15 Providing, hoisting and fixing up to floor three level precast
reinforced concrete work in Nominal M20 grade mix including cost
of required centering, shuttering, finishing, smooth with 6 mm thick
cement plaster 1:3 (1 cement: 3 fine sand) on exposed surface
complete excluding cost of reinforcement.
4.15.1 String courses, copings, bed plates, anchor blocks, plain
window sills etc
P.Cum 6608.00 5821.00 13.52% 6,095.00 4.71%
4.15.2 Mouldings as in cornices, windows sills etc.
P.Cum 7553.00 6200.00 21.82% 6,491.00 4.69%
4.15.3 Small lintels not exceeding 1.5 m clear span
P.Cum 7259.00 5869.00 23.68% 6,145.00 4.70%
4.15.4 Lintels beams and bressumers including setting in cement
mortar 1:3 (1 cement: 3 coarse sand) aggregate 20mm
nominal size).

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-4
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
P.Cum 6908.00 5691.00 21.38% 5,958.00 4.69%
4.15.5 Shelves, Vertical & horizontal fins individually or forming box
louvers setting in cement mortar 1:2 (1 cement: 2 sand)

P.Cum 12419.00 10375.00 19.70% 10,863.00 4.70%


4.15.6 Cement concrete jali reinforced with 1.6 mm dia Mild steel
wire complete as per approved design excluding plastering
of jambs, sills and soffits
4.15.6.1 75mm thick
P.Sqm 868.00 614.00 41.37% 643.00 4.72%
4.15.6.2 50mm thick
P.Sqm 805.00 561.00 43.49% 587.00 4.63%
4.15.6.3 40 mm thick
P.Sqm 707.00 478.00 47.91% 500.00 4.60%
4.15.6.4 30mm thick
P.Sqm 644.00 441.00 46.03% 462.00 4.76%
4.16 Add extra over item no.4.15.6 for both side jali
P.Sqm 40% 40.00% 0.00% 40.00% 0.00%
4.17 Supplying and fixing Precast R.C.C. door and window
frames up to floor three level nicely finished in M-20 Nominal
Mix with 1% steel, single or double rebated as required, of
size:
4.17.1 100 mm x 75 mm
P.Mtr. 159.00 121.00 31.40% 127.00 4.96%
4.17.2 125mm x 75mm
P.Mtr. 187.00 146.00 28.08% 153.00 4.79%

4.18 Add extra over item Nos. 4.15 to 4.17 in superstructure


above floor three level for subsequent floor level or part
there of.
1.50% 1.50% 1.50% 0.00%
4.19 Providing and fixing precast R.C.C. slab in M15 Nominal Mix
as per design up to 30 mm thick for shelves etc. including
cost of reinforcement consisting of wire mesh
100x100x4mm with fine finish.
P.Sqm 417.00 398.00 4.77% 417.00 4.77%
4.20 Add extra over item No. 4.19 for mosaic finish on one to
three edges and top surface of shelves with marble chipping
(1 mm to 4mm nominal size) in grey cement duly finished
and polished.
P.Sqm 95.00 95.00 0.00% 95.00 0.00%
ENCASING ROLLED STEEL STECTION
4.21 Encasing rolled steel section in beams and columns, with
M20 Nominal Mix cement concrete including centering and
shuttering complete but excluding cost of reinforcement.

P.Cum 8782.00 6427.00 36.64% 6,729.00 4.70%


4.22 Encasing rolled steel section in grillages with M20 Nominal
Mix including centering and shuttering complete but
excluding cost of expanded metal and hangers.

P.Cum 6067.00 4847.00 25.17% 5,075.00 4.70%


4.23 Providing and fixing expanded metal mesh of size 20x 60
mm and strands 3.5 mm vide 1.6 mm thick weighing 3.64
Kg per sqm. for encasing of rolled steel sections in beams,
columns and grillages excluding cost of hangers.

P.Sqm 261.00 258.00 1.16% 261.00 1.16%


MISCELLANEOUS
4.24 Providing and fixing in position copper plate as per design
for expansion joints.
Kg. 905.00 905.00 0.00% 905.00 0.00%
4.25 Providing and fixing in position Aluminum plate as per
design for expansion joints.
Kg. 498.00 498.00 0.00% 498.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-4
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
4.26 Providing and filling in position bitumen sealing compound
grade A (IS 1834 ) in expansion joints.
P. Cm. 711.00 623.00 14.13% 652.00 4.65%
depth
P. Cm.
width for
100 mtr.
Length

4.27 Providing and filling in position bitumen mix filler of


proportion 80 Kg. of hot bitumen, 1 Kg. of cement and 0.25
cubic meter of coarse sand for expansion joints.
P. Cm. 168.00 157.00 7.01% 164.00 4.46%
depth
P. Cm.
width for
100 mtr.
Length

4.28 Providing and fixing in position bitumen impregnated


fiberboard confirming to IS: 1838-1961 in expansion joints
including the cost of primer sealing compound.
4.28.1 12 mm. thick
P.Sqm 766.00 760.00 0.79% 766.00 0.79%

4.28.2 18 mm. thick


P.Sqm 988.00 982.00 0.61% 988.00 0.61%
4.28.3 25 mm. thick
P.Sqm 1321.00 1315.00 0.46% 1,321.00 0.46%
4.29 Providing and fixing Asbestos sheet 6mm thick and 150mm.
Wide over expansion joint with fixing rowl plug and screws
as per designs to match the colour shade of the distemper
or wall treatment.
P.Rmt 844.00 681.00 23.94% 713.00 4.70%

4.30 Providing and fixing Aluminum sheet 2.0 mm thick and


150mm. Wide over expansion joint with fixing rowl plug and
aluminum screws as per designs to match the colour shade
of the distemper or wall treatment.
P.Rmt 2476.00 1779.00 39.18% 1,863.00 4.72%
4.31 Add extra for laying R.C.C. in or under water and or liquid
mud including the cost of pumping or bailing out water and
removing slush etc. complete.
P.Cum 0.07 39.00 -99.82% 44.00 12.82%
Per Mtr.
Depth.
4.32 Providing and fixing expansion joint board for building RCC
column beams, walls, slab of Polyethylene foam of density
30 to 35 Kg/m3 of Armour Board.

4.32.1 12 mm Thick
P.Sqm 468.00 467.00 0.21% 468.00 0.21%
432.2 20mm Thick
P.Sqm 523.00 522.00 0.19% 523.00 0.19%
4.32.3 25 mm Thick
P.Sqm 633.00 632.00 0.16% 633.00 0.16%
4.32.4 30 mm Thick
P.Sqm 704.00 704.00 0.00% 704.00 0.00%
4.32.5 40 mm Thick
P.Sqm 880.00 880.00 0.00% 880.00 0.00%

4.33 Providing and placing in position suitable PVC water Stops


confirming to IS: 12200 for construction/ expansion joints
between two RCC members and fixed to the reinforcement
with binding wire before pouring concrete etc. complete.

4.33.1 Serrated with central bulb (225 mm wide, 8 to11 mm thick)

P. Mtr. 525.00 525.00 0.00% 525.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-4
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
4.33.2 Dumb bell with central bulb (180 mm wide, 10mm thick)

P. Mtr. 410.00 410.00 0.00% 410.00 0.00%


4.33.3 Kickers (320 mm wide, 5 mm thick)
P. Mtr. 490.00 490.00 0.00% 490.00 0.00%
4.34 Supplying and providing of two components poly sulphide sealant
containing solid contents, confirming to standard specification and
approved compatible primer, for priming vertical faces prior to
application of poly sulphide sealant including all labour charges for
sealing of expansion joints after drill mixing of two components
sealing compound. Cleaning and preparation of expansion joint
using wire brush sand papering with emery paper and filing with
suitable mechanical means. The work includes racking and
cleaning of joints, sticking, debonding tape on bottom of joint,
applying primer on edges, using masking tape on edges,
providing of sealant and removal of masking tape immediately
after providing sealant in joint.

4.34.1 To vertical joint between RCC columns, bricks & stone masonry in
size 40 mm width and 12 mm depth, including providing back up
material (Thermocoal foam) if required.
P. Mtr. 600.00 600.00 0.00% 600.00 0.00%
4.34.2 To joints in flooring, as per drawing with first layer of poly sulphide
sealant in size 20 mm width and 10 mm depth over PE Foam and
then providing polyethylene foam back up rod 25 mm dia size and
finally providing another layer of poly sulphide sealant in size 20
mm width and 10 mm depth over P.E. back up rod as per
application procedure and direction of Engineer-in-charge.

P. Mtr. 500.00 500.00 0.00% 500.00 0.00%


4.34.3 To horizontal joints between beams masonry in size 40 mm
width and 20 mm depth on top faces with pouring grade
providing required back-up material (Thermocoal foam/ PE
foam) complete.
P. Mtr. 825.00 825.00 0.00% 825.00 0.00%

4.35 Welding of M.S. rounds plain/TOR for R.C.C. work, joints


are to be butt or V-shaped, confirming to I.S. standards,
complete in all respect at work site:

4.35.1 For 25mm. dia bars


Each 75.00 75.00 0.00% 75.00 0.00%
4.35.2 For 32 mm. dia bars
Each 105.00 105.00 0.00% 105.00 0.00%
4.35.3 For 36mm. dia bars
Each 150.00 150.00 0.00% 150.00 0.00%
4.35.4 For 40mm. dia bars
Each 175.00 175.00 0.00% 175.00 0.00%
4.36 Providing and laying controlled cement concrete for cement
concrete pavements including mixing and vibrations concrete with
necessary needle vibrators and surface with screed board
vibrating complete in all respect with 20/25 mm stone aggregate
(crusher broken) including anti-skid textured finish to required
camber/ super lavation and grade including curing etc. as per
specification with cement concrete M-30 grade including cost of
Steel frame work for sides of C.C. pavement consisting of M. S.
channels flats and angles with required steel pegs ( some of them
may left embedded in concrete/ including providing frame work.

P.Cum 5500.00 5500.00 0.00% 5,500.00 0.00%


4.37 Add extra over item no. 4.36 for vacuum processed
concrete including cost of equipments labour etc.
P.Sqm 50.00 50.00 0.00% 50.00 0.00%
4.38 Cutting of construction joint/ longitudinal joint 4 to 6 mm.
wide & 75 to 100 mm deep using mechanical concrete cutter
including cost of diamond bit cutting wheel and filling of
bitumen sealing compound in groove including cost of
sealing compound.
P. Mtr. 65.00 65.00 0.00% 65.00 0.00%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-4
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018

4.39 Providing and laying in position Ready mix concrete manufactured Cum 6273.00 5362.00 16.99% 5,614.00 4.70%
in fully automatic Batching Plant and transported to site in transit
mixer for having continous agitated mixer, manufactured as per
approved mix design of specified grade of RCC work including
pumping of R.M.C. from transit mixer to site of laying , exculding
the cost of centering, shuttering and reinforcement with all lead
and lift including cost of admixtures in recommended portion as
per IS 9103 to accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as per
direction of Engineer in charge . All works upto floor V floor M20
grade Design Mix by using min 400 Kg of cement per cum of
concrete.

4.40 Add extra for providing richer mixes respectively at all floor levels

4.40.1 Providing M-25 grade concrete by using min 410 kg of cement per Cum 69.00 60.00 15.00% 63.00 5.00%
cum instead of M-20 grade design mix.
4.40.2 Providing M-30 grade concrete by using min 420 kg of cement per Cum 138.00 120.00 15.00% 126.00 5.00%
cum instead of M-20 grade design mix.
4.40.3 Providing M-35 grade concrete by using min. 428 kg of cement Cum 193.00 168.00 14.88% 176.00 4.76%
per cum instead of M-20 grade design mix.
4.40.4 Providing M- 40 grade concrete by using min. 435 kg of cement Cum 241.00 210.00 14.76% 220.00 4.76%
per cum instead of M-20 grade design mix.

4.40.5 Add extra for RCC work in superstructure above floor five level for Cum 98.00 98.00 0.00% 98.00 0.00%
each four floor or part thereof .

4.40.6 Deduct for using less cement quantity than the quantity as Kg 7.00 6.00 16.67% 6.00 0.00%
provided in the item of design mix concrete/RMC as arrived as
per mix design.(on cement quantity)

135100.60 110289.67 22.50% 114617.70 3.92%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-3
CEMENT CONCRETE
NOTE:
1- The rates are for all lead of cement, lime, ballast, sand, surkhi and grit etc. at site
2- of
Forwork and are inclusive
all concrete work onlyof layingsand
coarse and mixing,
shall beall T & P, mixer, vibrator with P.O.L,
used.
3- scaffolding
Concrete mixetc. including
prepared bycost of curing.mechanical mixer shall be used.
power-driven
4- Under exceptional conditions, where mechanical mixer and vibrator are not used
(with the approval of Engineer-in-Charge) rates to be reduce by 15%, for
mechanical mixer and 10 % for vibrator.
CHAPTER - B-3
Chapter Description Unit Analysis As per BSR Variation on Proposed % Above
Code No. Rate 2018 BSR 2018 Rate for with BSR
BSR 2019 2018
LIME CONCRETE:
3.1 Providing and laying lime concrete in foundation and plinth,
using 40% lime mortar and 40 mm nominal size graded
aggregate (crusher broken) including ramming and watering
complete in all respect comprising of:

3.1.1 1 Lime Putty : 2 Surkhi Mortar


P.Cum 2842.00 2162.00 31.45% 2,270.00 5.00%
3.1.2 1 Lime Putty : 2 Sand mortar
P.Cum 3121.00 2240.00 39.33% 2,352.00 5.00%
3.1.3 1 Lime Putty : 2 Cinder mortar
P.Cum 2438.00 1837.00 32.72% 1,928.00 4.95%
3.1.4 1 Lime Putty : 3 Sand Mortar
P.Cum 2886.00 2014.00 43.30% 2,114.00 4.97%
3.1.5 Deduct if brick ballast 40 mm nominal size used in item No.
3.1 in place of stone ballast.
P.Cum 20% 20.00% 20% 0.00%
3.1.6 Deduct if hand broken aggregate is used in place of crusher
broken.
P.Cum 250.00 250.00 0.00% 250.00 0.00%

CEMENT CONCRETE (CAST-IN-SITU):


3.2 Providing and laying in position cement concrete including
curing, compaction etc. complete in specified grade
excluding the cost of centering and shuttering - All work up
to plinth level.
3.2.1 M25 grade Design Mix
P.Cum 5627.00 5120.00 9.90% 5,376.00 5.00%
3.2.2 M20 grade Nominal Mix (with graded stone aggregate
20mm nominal size).
P.Cum 4946.00 4337.00 14.04% 4,553.00 4.98%

3.2.3 M15 grade Nominal Mix (with graded stone aggregate


20mm nominal size).
P.Cum 4523.00 3845.00 17.63% 4,037.00 4.99%

3.2.4 M10 grade Nominal Mix (with graded stone aggregate


20mm nominal size).
P.Cum 4008.00 3245.00 23.51% 3,407.00 4.99%

3.2.5 M15 grade Nominal Mix (with graded stone aggregate 40


mm nominal size).
P.Cum 4455.00 3772.00 18.11% 3,960.00 4.98%

3.2.6 M10 grade Nominal Mix (with graded stone aggregate 40


mm nominal size).
P.Cum 3929.00 3157.00 24.45% 3,314.00 4.97%
3.2.7 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate
40 mm nominal size).
P.Cum 3713.00 2898.00 28.12% 3,042.00 4.97%

3.2.8 1:5:10 (1 cement : 5 coarse sand : 10 graded stone


aggregate 40mm nominal size).
P.Cum 3485.00 2647.00 31.66% 2,779.00 4.99%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-3
Chapter Description Unit Analysis As per BSR Variation on Proposed % Above
Code No. Rate 2018 BSR 2018 Rate for with BSR
BSR 2019 2018
3.2.9 Deduct for hand broken aggregates used in substitution of
crusher broken on item No. 3.2.5 to 3.2.8 and 3.3.5 to 3.3.6.

P.Cum 250.00 250.00 0.00% 250.00 0.00%


3.3 Providing and laying cement concrete including curing,
compaction etc. complete in retaining walls, return walls,
walls (any thickness) including attached pilasters, columns,
piers, abutments, pillars, posts, struts, buttresses, string or
lacing courses, parapets, coping, bed blocks, anchor blocks,
plain window sills, fillets etc up to floor three level excluding
the cost of centering and shuttering.

3.3.1 M25 grade Design Mix


5899.00 5336.00 10.55% 5,602.00 4.99%
3.3.2 M20 grade Nominal Mix (with graded stone aggregate
20mm nominal size).
5218.00 4550.00 14.68% 4,777.00 4.99%
3.3.3 1:2:4 ( 1Cement : 2 coarse snad : 4 graded stone aggregate
20mm nominal size.)
P.Cum 4795.00 4058.00 18.16% 4,260.00 4.98%
3.3.4 1:3:6 ( 1Cement : 3 coarse snad : 6 graded stone aggregate
20mm nominal size.)
P.Cum 4280.00 3459.00 23.74% 3,631.00 4.97%
3.3.5 1:2:4 ( 1Cement : 2 coarse snad : 4 graded stone aggregate
40mm nominal size.)
P.Cum 4728.00 3987.00 18.59% 4,186.00 4.99%
3.3.6 1:3:6 ( 1Cement : 3 coarse snad : 6 graded stone aggregate
40mm nominal size.)
P.Cum 4201.00 3371.00 24.62% 3,539.00 4.98%
3.4.1 Add Extra for laying concrete in superstructure upto floor
three level in item no. 3.2
P.Cum 219.00 110.00 99.09% 115.00 4.55%
3.5 Deduct if brick aggregate is used in substitution stone
aggregate in item No. 3.2.5 to 3.2.8 & 3.3.5 to 3.3.6.
P.Cum 250.00 92.00 171.74% 96.00 4.35%
3.6 Extra for laying in floor consolidation extra labour required
for slow per gress.
P.Cum 190.00 88.00 115.91% 92.00 4.55%
3.8 Providing and fixing up to floor three level pre cast cement
concrete string or lacing courses, copings, bed plates,
anchor blocks, windows sills, shelves, louvers steps,
staircases, etc. including carriage, hoisting and setting in
position with cement mortar 1:3 (1 cement : 3 coarse sand)
cost of required centering, shuttering and finishing smooth
with 6 mm thick cement plaster 1:3 (1 cement : 3 fine sand)
on exposed surface, including all T & P, curing etc.
complete:

3.8.1 Nominal M15 grade Mix (with graded stone aggregate 40


mm nominal size).
Cement Concrete 1:2:4
P.Cum 6417.00 5736.00 11.87% 6,022.00 4.99%
3.8.2 Nominal M10 grade Mix (with graded stone aggregate 40
mm nominal size).
Cement Concrete 1:3:6
P.Cum 7385.00 6868.00 7.53% 7,211.00 4.99%
3.9 Add extra over item No. 3.8 above floor three level for each
floor or part there of.
P.Cum 167.00 73.00 128.77% 76.00 4.11%
3.10 Applying one coat industrial grade bitumen of penetration
25/85 of approved quality using 1.70 kg. per Sqm on Damp
Proof Coarse after cleaning the surface with brushes and
finally with a piece of cloth slightly soaked in kerosene oil.

P.Sqm 105.00 102.00 2.94% 105.00 2.94%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-3
Chapter Description Unit Analysis As per BSR Variation on Proposed % Above
Code No. Rate 2018 BSR 2018 Rate for with BSR
BSR 2019 2018
3.11 Applying a coat of residual petroleum bitumen of penetration
80/100 of approved quality using 1.7 Kg per sqm on damp
proof coarse after cleaning the surface with brushes and
finally with a piece of cloth slightly soaked in kerosene oil.

P.Sqm 94.00 91.00 3.30% 94.00 3.30%


3.12 Providing and mixing admixure in Concrete flooring/ cement
plaster/ Cement Concret Road, Plain or RCC work & water
retaining works providing and mixing Additive of Synthetic
polypropylene Fibrillated mesh fibers free form any
reprocess Olefins &comfirming to ASTM C 1116 Type III 4.1.3
Having grade 6mm/12mm /18mm melting point of 165 deg.C.,
strength>600 mpa Sp. Gravity:0.92g/cc, diameter 10-70
microns. It is required in specified ratio @ 0.25% (125 Gm.
Fibers in 50 Kg. cement) for use. Mix it directly with contents
in rotating site mixer direction of Engineer in charge with all per
leads and lifts. As per IS 16481-2016 125
gram
pack 58.00 58.00 0.00% 58.00 0.00%
3.13 Providing and mixing admixure in Concrete Flooring/Cement
Plaster/Cement Comcrete Road, Plain or RCC work & water
retaining works providing and mixing admixture of Synthetic
Nylon-6 Fibres or polycaprolactam free from any reprocess
Olefins & confirming to ASTM C 1116 Type III 4.1.3 Having
grade 6mm / 12 mm /18 mm melting point 220 deg. C, Sp.
Gravity:1.14 g/cc, diameter 10-40 microns. It is required in
specific ratio @ 0.20% (100 gm Fibres in 50 Kg Cement) for
use as specified by manufacture specification and direction
of Engineer In-charges with all leads and lifts. As per IS per
16481-2016 100
gram
pack 55.00 55.00 0.00% 55.00 0.00%

90421.20 75695.20 19.45% 79438.20 4.94%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-2

MORTAR
CHAPTER - B-2
Chapter Description Unit Analysis As per BSR Variation on Proposed % Above
Code No. Rate 2018 BSR 2018 Rate for with BSR
BSR 2019 2018
LIME MORTAR :
2.1 Lime sand mortar 1 : 2 (1 Lime putty : 2 sand)
P.Cum 3148.00 2498.00 26.02% 2,747.00 9.97%
2.2 Lime sand mortar 1 : 3 (1Lime putty : 3 sand)
P.Cum 2620.00 1990.00 31.66% 2,189.00 10.00%

2.3 Lime surkhi mortar 1:2 (1 Lime putty : 2 surkhi)


P.Cum 2633.00 2385.00 10.40% 2,623.00 9.98%

2.4 Lime surkhi mortar 1:3 (1Lime putty : 3 surkhi)


P.Cum 2278.00 2076.00 9.73% 2,278.00 9.73%
2.5 Lime Cinder mortar 1:2 (1 Lime putty : 2Cinder)
P.Cum 1610.00 1593.00 1.07% 1,610.00 1.07%

2.6 Lime Cinder sand mortar 1 : 1 : 1 (1 Lime putty : 1Cinder : 1


sand)
P.Cum 2038.00 1861.00 9.51% 2,038.00 9.51%
2.7 Lime surkhi sand mortar 1 : 1: 1 ( 1 Lime putty : 1 surkhi : 1
sand )
P.Cum 2913.00 2465.00 18.17% 2,711.00 9.98%

2.8 Lime Kara mortar 1 : 2 (1 Lime putty : 2 Marble powder)


P.Cum 2833.00 2478.00 14.33% 2,725.00 9.97%
2.9 Cement sand Mortar 1 : 2 (1 cement : 2 sand)
P.Cum 5784.00 4481.00 29.08% 4,929.00 10.00%
2.10 Cement sand Mortar 1 : 3 (1 cement : 3 sand)
P.Cum 4890.00 3912.00 25.00% 4,303.00 9.99%
2.11 Cement sand Mortar 1 : 4 (1cement : 4 sand)
P.Cum 4138.00 3415.00 21.17% 3,756.00 9.99%
2.12 Cement sand Mortar 1 : 5 (1 cement : 5 sand)
P.Cum 3718.00 3052.00 21.82% 3,357.00 9.99%
2.13 Cement sand Mortor 1 : 6 (1 cement : 6 sand)
P.Cum 3358.00 2738.00 22.64% 3,011.00 9.97%
2.14 Cement sand Mortor 1 : 8 (1 cement : 8 sand)
P.Cum 2929.00 2401.00 21.99% 2,641.00 10.00%
2.15 Cement sand Mortar 1:10 (1 cement :10 sand)
P.Cum 2788.00 1328.00 109.94% 1,460.00 9.94%

CEMENT MARBLE POWDER MORTAR :


2.16 Cement marble powder mortar 1 : 2 (1-cement : 2- marble
powder)
P.Cum 5105.00 5026.00 1.57% 5,105.00 1.57%
2.17 Cement marble powder mortar 1 : 3 (1-cement : 3- marble
powder)
P.Cum 3597.00 3518.00 2.25% 3,597.00 2.25%
2.18 Cement marble powder mortar 1 : 4 (1cement : 4- marble
powder)
P.Cum 3146.00 3067.00 2.58% 3,146.00 2.58%
2.19 White cement marble powder mortar 1 :2 (1 white cement :
2 marble powder)
P.Cum 13265.00 12575.00 5.49% 13,265.00 5.49%
2.20 White cement marble powder mortar 1:3 (1 white cement : 3
marble powder)
P.Cum 10289.00 9739.00 5.65% 10,289.00 5.65%

2.21 Cement lime marble powder morter 1 : 1 : 6 (1 cement : 1


Lime putty : 6 marble powder) (for Sandla)
P.Cum 3061.00 2896.00 5.70% 3,061.00 5.70%

2.22 Cement lime Mortar 1:1:3 (1-cement : 1-lime putty : 3-


coarse sand).

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-2
Chapter Description Unit Analysis As per BSR Variation on Proposed % Above
Code No. Rate 2018 BSR 2018 Rate for with BSR
BSR 2019 2018
P.Cum 5146.00 4743.00 8.50% 5,146.00 8.50%

COMPOSITE MORTAR :
2.23 Cement lime sand mortar 1 : 1 : 4 ( 1 cement : 1 lime putty :
4 sand).
P.Cum 3743.00 3450.00 8.49% 3,743.00 8.49%

2.24 Cement Lime sand mortar 1 : 1 : 6 (1 cement : 1 Lime


putty : 6 sand).
P.Cum 3830.00 3300.00 16.06% 3,630.00 10.00%
2.25 Cement Lime sand mortar 1 : 2 : 9 (1 cement : 2 lime putty :
9 sand).
P.Cum 3035.00 2750.00 10.36% 3,025.00 10.00%
2.26 Cement lime sand mortar 1 : 3 : 12 (1 cement : 3 Lime
putty : 12 sand).
P.Cum 3028.00 2691.00 12.52% 2,960.00 10.00%
MUD MORTAR :
2.27 Mud Mortar including specified ingredients.
P.Cum 460.00 363.00 26.72% 399.00 9.92%
105383.00 92791.00 13.57% 99744.00 7.49%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER - B-1

EARTH WORK
CHAPTER B-1
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
1.1 Earth work in surface excavation not exceeding 30cm. in depth
but exceeding 1.5 meter in width as well as10 Sqm on plan
including disposal of excavated earth up to 50 Mtr. and lift up to
1.5 Mtr. isposed soil to be levelled and neatly dressed: All kinds
of soil
P.Sqm 55.00 26.00 111.54% 28.00 7.69%
1.2 Earth work in rough excavation, banking excavated earth in layers
not exceeding 20cm in depth, breaking clods watering, rolling
each layer with 1/2 tonne roller, or stone or steel rammers and
rolling every 3rd and top- most layer with power roller of minimum
8-10 tonne capacity and dressing up in embankment for roads,
flood banks marginal banks and guide banks or filling up ground
depressions, lead up to 50 Mtr. and lift up to 1.5 Mtr.: All kind of
soil

P. Cum 427.00 198.00 115.66% 217.00 9.60%

1.3 Banking excavated earth in layers not exceeding 20cm. in depth


breaking clods watering, rolling each layer with 1/2 tonne roller, or
stone or steel rammers, and rolling every 3rd and top- most layer
with power roller of 8-10 tonne capacity and dressing up in
embankments for roads, flood banks marginal banks, and guide
banks etc. lead up to 50 Mtr. and lift up to 1.5 Mtr. All kinds of soil

P. Cum 262.00 126.00 107.94% 138.00 9.52%


1.4 Deduct in item No. 1.2 & 1.3 for not rolling with power roller of 8 to
10 tonne capacity for banking excavated earth in layers not
exceeding 20 cm in depth.
P. Cum 2.86 2.71 5.54% 2.00 -26.20%
1.5 Deduct in item No. 1.2 & 1.3 for not watering the excavated earth
for banking.
P. Cum 45.00 21.00 114.29% 23.00 9.52%
1.6 Earth work in excavation over areas (exceeding 30cm in depth,
1.5 Mtr. in width as well as 10 Sqm on plan) including disposal of
excavated earth lead up to 50m and with all lift disposed earth to
be levelled and neatly dressed: All kinds of soil

P. Cum 393.00 174.00 125.86% 191.00 9.77%


1.7 Earth work in excavation over areas (exceeding 30cm in depth,
1.5 Mtr. in width as well as 10 Sqm on plan) including disposal of
excavated earth lead up to 50m and lift up to 1.5 Mtr. disposed
earth to be levelled and neatly dressed including stacking of
useful material if available :

1.7.1 Ordinary rock


P. Cum 573.00 280.00 104.64% 308.00 10.00%

1.7.2 Hard rock (requiring blasting) useful material 30%


P. Cum 781.00 386.00 102.33% 424.00 9.84%

1.7.3 Hard Rock (Blasting Prohibited)


P. Cum 1295.00 623.00 107.87% 685.00 9.95%
1.8 Earth work in excavation in foundation trenches or drains
including dressing of sides and ramming of bottoms, lift up to 1.5
Mtr. including taking out the excavated soil and depositing and
refilling of jhiri with watering & ramming and disposal of surplus
excavated soil as directed with in a lead of 50 meter. All kinds of
soil.

P. Cum 402.00 179.00 124.58% 196.00 9.50%


1.9 Earth work in excavation in foundation trenches or drains
including dressing of sides and ramming of bottoms, lift up to 1.5
Mtr. including taking out the excavated soil and depositing and
refilling of jhiri with watering & ramming and disposal of surplus
excavated soil as directed with a lead in a 50 meter including
stacking of useful material if available :

1.9.1 Ordinary rock

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-1
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
P. Cum 635.00 311.00 104.18% 342.00 9.97%
1.9.2 Hard rock (requiring blasting) useful material 30%
P. Cum 858.00 438.00 95.89% 481.00 9.82%

1.9.3 Hard rock(blasting prohibited) useful material 30%


P. Cum 1336.00 644.00 107.45% 708.00 9.94%
1.10 Add extra over item No. 1.8 and 1.9 for every additional lift of 1.5
m or part thereof:

1.10.1 In all kind of soils.


P. Cum 40.00 18.00 122.22% 19.00 5.56%
1.10.2 In ordinary rock and hard rock.
P. Cum 63.50 31.00 104.84% 34.00 9.68%
1.11 Add extra over item No. 1.8 and 1.9 for excavation in saturated
soil where pumping or bailing out of water is required, including
shoring strutting where required and dewatering.
20.00% 20.00%
1.12 Deducted for earth work in excavation in foundation trenches or
drains where excavated soil is not required to be refilled in jhiri
etc.
P. Cum 9.00 9.00 0.00% 9.00 0.00%
1.13 Excavating trenches of required width for pipe cables, etc.
including excavation for sockets, and dressing of sides, ramming
of bottoms, depth up to 1.5 Mtr. including taking out the excavated
soil, and then returning the soil as required in layers not
exceeding 20cm in depth including consolidating each deposited
layer by ramming, watering etc. and disposal of surplus excavated
soil as directed within a lead of 50 Mtr.:

1.13.1 All kind of soil


1.13.1.1 Pipe cables etc. not exceeding 80mm dia. P.Mtr. 244.00 111.00 119.82% 122.00 9.91%

1.13.1.2 Pipes cables, etc. exceeding 80mm dia but not exceeding 300mm
dia.
P.Mtr. 398.00 182.00 118.68% 200.00 9.89%
1.13.1.3 Pipes, cables etc. exceeding 300mm dia but not exceeding
600mm dia.
P.Mtr. 622.00 286.00 117.48% 314.00 9.79%
1.14 Add extra in item No. 1.13 for excavating trench for pipes, cables
etc. in all kinds of soil for depth exceeding 1.5 Mtr. but not
exceeding 3 Mtr.
131% 130% 130%
1.15 Add extra in item No. 1.13 for excavating trench for pipes, cables
etc. in all kinds of soil for depth exceeding 3 Mtr. But not
exceeding 4.5 Mtr.
335% 172% 172%
1.16 Excavating trenches of required width for pipes cables etc.
including excavation for sockets, depth up to 1.5 Mtr. including
taking out the excavated materials, refilling the soil as required in
layers not exceeding 20cm in depth including consolidating each
deposited layers by ramming, watering etc., stacking serviceable
material for measurements and disposal of unserviceable material
as directed, with in a lead of 50 Mtr.

1.16.1 ORDINARY ROCK: -


1.16.1.1 Pipes cables etc. not exceeding 80mm dia
P.Mtr. 365.00 179.00 103.91% 196.00 9.50%
1.16.1.2 Pipes cables, etc. exceeding 80mm dia but not exceeding 300mm
dia.
P.Mtr. 889.00 438.00 102.97% 481.00 9.82%
1.16.1.3 Pipes, cables etc. exceeding 300mm dia but not exceeding
600mm dia.
P.Mtr. 1023.00 504.00 102.98% 554.00 9.92%
1.16.2 HARD ROCK (REQUIRING BLASTING) USEFUL MATERIAL
30% OF VOLUME EXCAVATED

1.16.2.1 Pipes cables etc. not exceeding 80mm dia


P.Mtr. 465.00 238.00 95.38% 261.00 9.66%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-1
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
1.16.2.2 Pipes cables, etc. exceeding 80mm dia but not exceeding 300mm
dia.
P.Mtr. 1153.00 587.00 96.42% 645.00 9.88%
1.16.2.3 Pipes, cables etc. exceeding 300mm dia but not exceeding
600mm dia.
P.Mtr. 1326.00 676.00 96.15% 743.00 9.91%
1.16.3 HARD ROCK (BLASTING PROHIBITED) USEFUL MATERIAL
30% OF VOLUME EXCAVATED
1.16.3.1 Pipes cables etc. not exceeding 80mm dia
P.Mtr. 691.00 322.00 114.60% 354.00 9.94%
1.16.3.2 Pipes cables, etc. exceeding 80mm dia but not exceeding 300mm
dia.
P.Mtr. 1712.00 798.00 114.54% 877.00 9.90%
1.16.3.3 Pipes, cables etc. exceeding 300mm dia but not exceeding
600mm dia.
P.Mtr. 1970.00 918.00 114.60% 1,009.00 9.91%
1.17 Add extra over item No. 1.16 for excavating trenches for pipes
cables etc. in ordinary/hard rock exceeding 1.5 Mtr. In depth but
not exceeding 3 Mtr.
P.Mtr. 102% 102% 102% 0.00%
1.18 Add extra over item No. 1.16 for excavating trenches for pipes
cables etc. in ordinary/hard rock exceeding 3 Mtr. In depth but not
exceeding 4.5 Mtr.
P.Mtr. 255% 253% 253% 0.00%
1.19 P & F Close timbering in trenches including strutting, shoring and
packing cavities (wherever required) etc. Complete (Measurement
to be taken of the face area timbered):
1.19.1 Depth not exceeding 1.5 Mtr.
P.Sqm 120.00 118.00 1.69% 120.00 1.69%
1.19.2 Depth exceeding 1.5 Mtr. but not exceeding 3 Mtr
P.Sqm 126.00 123.00 2.44% 126.00 2.44%
1.19.3 Depth exceeding 3 Mtr. but not exceeding 4.5 Mtr
P.Sqm 141.00 134.00 5.22% 141.00 5.22%
1.20 P & F Close timbering in case of shafts, wells, soak pits, man-
holes and the like including strutting, shoring and packing cavities
(wherever required) etc complete (Measurement to be taken of
the face area timbered):
1.20.1 Depth not exceeding 1.5 Mtr.
P.Sqm 127.00 124.00 2.42% 127.00 2.42%
1.20.2 Depth exceeding 1.5 Mtr. but not exceeding 3 Mtr
P.Sqm 141.00 134.00 5.22% 141.00 5.22%
1.20.3 Depth exceeding 3 Mtr. but not exceeding 4.5 Mtr
P.Sqm 155.00 144.00 7.64% 155.00 7.64%
1.21 Close timbering over area including strutting, shoring and packing
cavities (wherever required) etc. complete (Measurement to be
taken of the face area timbered):
1.21.1 Depth not exceeding 1.5 Mtr.
P.Sqm 107.00 105.00 1.90% 107.00 1.90%
1.21.2 Depth exceeding 1.5 Mtr. but not exceeding 3 Mtr
P.Sqm 115.00 111.00 3.60% 115.00 3.60%
1.21.3 Depth exceeding 3 Mtr. but not exceeding 4.5 Mtr
P.Sqm 123.00 117.00 5.13% 123.00 5.13%
1.22 Add extra over item No. 1.19 & 1.20 for planking, strutting and
packing material for cavities (in close timbering) if required to be
left permanently in position (face area of timber permanently left to
be measured)
P.Sqm 224.00 224.00 0.00% 224.00 0.00%
1.23 P & F of Open timbering in trenches including strutting, shoring
complete (measurements to be taken of the face area timbered)

1.23.1 Depth not exceeding 1.5 Mtr.


P.Sqm 62.00 61.00 1.64% 62.00 1.64%
1.23.2 Depth exceeding 1.5 Mtr. but not exceeding 3 Mtr
P.Sqm 66.00 64.00 3.13% 66.00 3.13%
1.23.3 Depth exceeding 3 Mtr. but not exceeding 4.5 Mtr
P.Sqm 73.00 69.00 5.80% 73.00 5.80%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-1
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
1.24 P & F of Open timbering in case of shafts, wells, soak pits,
manholes and the like including strutting, shoring complete
(Measurement to be taken of the face are timbered):
1.24.1 Depth not exceeding 1.5 Mtr.
P.Sqm 57.00 55.00 3.64% 57.00 3.64%
1.24.2 Depth exceeding 1.5 Mtr. but not exceeding 3 Mtr
P.Sqm 63.00 60.00 5.00% 63.00 5.00%
1.24.3 Depth exceeding 3 Mtr. but not exceeding 4.5 Mtr
P.Sqm 72.00 66.00 9.09% 72.00 9.09%
1.25 P & F Open timbering over area including strutting, shoring etc
complete (Measurement to be taken of the face are timbered):
1.25.1 Depth not exceeding 1.5 Mtr.
P.Sqm 42.00 41.00 2.44% 42.00 2.44%
1.25.2 Depth exceeding 1.5 Mtr. but not exceeding 3 Mtr
P.Sqm 47.00 45.00 4.44% 47.00 4.44%
1.25.3 Depth exceeding 3 Mtr. but not exceeding 4.5 Mtr
P.Sqm 53.00 50.00 6.00% 53.00 6.00%
1.26 Add extra over item No. 1.23, 1.24 & 1.25 for planking and
strutting in open timbering if required to be left permanently in
position (face area of timber permanently left to be measured)
P.Sqm 116.00 116.00 0.00% 116.00 0.00%
1.27 Add extra over depth of 4.5 Mtr. over item of close/open timbering
for each 1.5Mtr depth.
P.Sqm 5.00 4.97 0.60% 5.00 0.60%

1.28 Add extra rate for quantities of works executed (respective


applicable rates):

1.28.1 In or under water and or liquid Mud/Marshy soil


20% 20% 20%
1.28.2 In or under foul conditions.
25.0% 25% 25%
1.29 Pumping out water caused by springs, tidal or river seepage,
broken water mains or drains and the like with pumping set of
following H.P. including P.O.L./Power consumption etc. complete.

1.29.1 5 to 9 H.P.
P.Hr. 228.00 200.00 14.00% 220.00 10.00%
1.29.2 10 to 19 H.P.
P.Hr. 333.00 270.00 23.33% 297.00 10.00%
1.29.3 20 to 30 H.P.
372.00 304.00 22.37% 334.00 9.87%

1.30 Filling available excavated earth (excluding rock) in trenches,


plinth side of foundation etc. in layers not exceeding 20 cm. in
depth, consolidating each deposited layer by ramming and
watering including lead up to 50 meter and with all lift.

P.Cum 114.00 57.00 100.00% 62.00 8.77%


1.31 Add extra for foundation/trenches/drains for every additional lift of
1.5 Mtr. or part thereof upto 4.5mtr. depth :
1.31.1 Al kinds of soil
P.Cum 54.00 23.00 134.78% 25.00 8.70%
1.31.2 Ordinary or hard rock.
P.Cum 96.00 41.00 134.15% 45.00 9.76%
1.32 Filling in plinth with river sand under floors including watering
ramming consolidating and dressing complete including cost of
sand.
P.Cum 1649.00 1175.00 40.34% 1,292.00 9.96%
1.33 Filling in plinth with locally available river shingle/good earth
under floors including watering ramming consolidating and
dressing complete including cost of.
(a) Locally available river shingle
P.Cum 539.00 521.00 3.45% 539.00 3.45%
(b) Locally available good earth
P.Cum 283.00 266.00 283.00 New

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-1
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
1.34 Surface dressing of the ground including removing vegetation and
inequalities not exceeding 15cm deep and disposal of rubbish
lead up to 50 Mtr. and lift up to 1.5 Mtr.:
1.34.1 All Kinds of soil.
P. 100 1509.00 673.00 124.22% 740.00 9.96%
Sqm
1.35 Ploughing the existing ground to a depth of 15 cm to 25 cm and
watering the same:
1.35.1 All Kinds of soil.
P. 100 1528.00 684.00 123.39% 752.00 9.94%
Sqm
1.36 Excavating holes up to 0.5cum including getting out the excavated
soil then returning the soil as required in layers not exceeding 20
cm in depth including consolidating each deposited layer by
ramming watering etc. and disposing of surplus excavated soil as
directed within a lead of 50 Mtr. and lift up to 1.5 Mtr.

1.36.1 All kinds of soil


Per Hole 225.00 102.00 120.59% 112.00 9.80%
1.36.2 Ordinary rock.
Per Hole 354.00 173.00 104.62% 190.00 9.83%
1.36.3 Hard rock (requiring blasting).
Per Hole 489.00 259.00 88.80% 284.00 9.65%
1.36.4 Hard rock (blasting prohibited).
Per Hole 755.00 370.00 104.05% 407.00 10.00%
1.37 Construction of Earthen Dola up to 1.5 Mtr. height in: All kinds of
soil.
194.00 85.00 128.24% 93.00 9.41%
1.38 Silt clearance of drains, channels and canals with lift 1.5 Mtr. and
lead up to 50 Mtr.
128.00 56.00 128.57% 61.00 8.93%
1.39 ANTI TERMITE TREATMENT: -
Providing and injection Chloropyrifos Emulsifiable concentrate
20% with 1% concentration for PRECONSTRUCTIONAL Anti
termite treatment as per IS 6313 part III as amended from time to
time and creating a continuous chemical barrier under and around
the column pits, wall trenches, basement excavation, top surface
of plinth filling, junction of wall and floor along the external
perimeter of building expansion joints, over the top surface of
consolidated earth of which aproch is to be laid surrounding of
pipes and conduits etc. complete as per specification (Plinth floor
area only shall be measured for payment).

P.Sqm 605.00 586.00 3.24% 605.00 3.24%


1.40 Providing and injecting by hand operated pressure pumps
chemical Emulsion timber ground treatment [TCGT] in ratio 1: 2
as per manufacturers specification for POST CONSTRUCTIONAL
Anti-termite treatment (as per IS 6313) part - III 1971 as amended
from time to time)
1.40.1 Along external wall where apron is not provided using Chemical
emulsion@ 7.5 litre / Sqm of the vertical surface of the sub
structure to a depth of 300 mm including excavation of channel
along the wall & rodding etc complete. With Chloropyrifos
/Lindane E.C 20 % with 1%
concentration.

P.Mtr. 47.00 44.00 6.82% 47.00 6.82%


1.40.2 Along the external wall below concrete or masonry apron using
chemical emulsion @ 2.25Liters per linear meter including drilling
and plugging holes etc With Chloropyrifos /Lindane E.C 20 % with
1% concentration.
P.Mtr. 52.00 48.00 8.33% 52.00 8.33%
1.40.3 Treatment of soil under existing floors using chemical emulsion @
one liter per hole, 300mm apart including drilling 12 mm diameter
holes and plugging with cement mortar 1: 2 (1 cement: 2 coarse
sand) to match the existing
floor.
1.40.3.1 With Chlorpyriphos/Lindane E.C 20% with 1 %
concentration.
P.Sqm 284.00 241.00 17.84% 265.00 9.96%

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-1
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
1.40.4 Treatment of existing masonry using chemical emulsion @ one
liter per hole at 300 mm interval including drilling holes at 45
degree and plugging them cement mortar 1:2(1cement: 2 coarse
sand) to the full depth of the hole.
1.40.4.1 With Chlorpyriphos/Lindane E.C 20% with 1 %
concentration.
P.Mtr. 65.00 61.00 6.56% 65.00 6.56%
1.40.5 Treatment at points of contact of wood work by chemical emulsion
Chlorpyriphos/Lindane (in oil kerosene based solution) @ 0.5
liters per hole by drilling 6 mm dia holes at downward of 45
degree at 150 mm center to center and sealing the same.

P.Mtr. 209.00 186.00 12.37% 204.00 9.68%


1.41 Ceiling / Shamyana with Iron holow poles of standard size as per
design including all accessories used in 15'x15' with height upto
12' complete for one day period including removal & cleaning the
site complete in all respect as per instruction given by Engineer
Incharge (on rent)
Each 110.00 110.00 0.00% 110.00 0.00%

1.41.1 Add extra for above item for water proofing Shamyana 25% 25% 25.00% 0.00%
1.42 Wooden stage with wooden bergas supports horizontal and
vertical by coconut strings complete in all respect height 120m to
1.50m above ground level for one day period including removal &
cleaning the site complete in all respect as per instruction given by
Engineer Incharge (on rent)
P.Sqm 375.00 375.00 0.00% 375.00 0.00%

1.43 Kanat with bamboo as per design and height upto 1.50m with all
accessories for one day period including removal & cleaning the
site complete in all respect as per instruction given by Engineer
Incharge (on rent)
P.Rmt 8.00 8.00 0.00% 8.00 0.00%

1.44 Chairs of Standard size on rent for one day


(a) Plastic Chair general Each 5.00 5.00 0.00% 5.00 0.00%
(b) VIP Chair Each 10.00 10.00 0.00% 10.00 0.00%
1.45 Spreading of matting of prescribed cloth/ material with all
accessories in Shamiyana and at stage for one day period
including removal & cleaning the site complete in all respect as
per instruction given by Engineer Incharge (on rent)
P.Sqm 1.00 1.00 0.00% 1.00 0.00%
1.46 Anti-termite treatment of existing floor and wall using
Imidacloprid 30.5% EC non repellent, odorless, low dose,
environimentally safe Termiticide with rapid action non
corrosive stain free manufactured by Bayer or equivalent
company by injecting the emulsion as specified by the
manufacturer and plugging with cement mortar 1:2 ( 1 cement
: 2 coarse sand) in the whole floor area. The pesticide Sqm 82.00 82.00 0.00% 82.00 0.00%
emulsion of imidacloprid 30.5% EC mixed with water in the
ration of 1:474 will be pumped by a motorized spray pump
specified manner. The net floor and wall area treated will be
measured for payment.

T.A. TO S.E. AAO Superintending Engineer


CHAPTER B-1
Chapter Description Unit Analysis As per BSR Variation Proposed % Above
Code No. Rate 2018 on BSR Rate for with BSR
2018 BSR 2019 2018
1.47 Anti termite treatment of floor using Imidacloprid 30.5% EC
non repellent, odorless, low dose, environmentally safe
terniticide with rapid action non corrosive stain free
manufactured by Bayer or equivalent company by drilling
12mm diameter holes 300mm apart injecting the emulsion as
specified by the manufacturer and plugging with cement
mortar 1:2 ( 1 cement : 2 coarse sand) in the whole floor area
DPE 12mm dia termitube system with required number of
junction boxes are to be installed. The termitube will run all
along the perimeter wall both inside and outside. In the
middle area the termitube to be installed at an interval of 1.00 Sqm 196.00 196.00 0.00% 196.00 0.00%
Mtr. or less both ways as required with sufficient number of
junction boxes to pump the emulsion. After successful
testing of termitube, pesticide emulsion of imidacloprid
30.5% EC mixed with water in the ration of 1:474 will be
pumped by a motorized spray pump from the junction box in
specified manner. The plinth area of the area treated will be
measured for payment.

30978.49 17890.95 73.15% 19364.47 8.24%

T.A. TO S.E. AAO Superintending Engineer


COMPARISION OF RATES WITH
BSR 2013 FROM CHAPTER 1 T 17
AND S1 TO S4

T.A. TO S.E. AAO Superintending Engineer


T.A. TO S.E. AAO Superintending Engineer
ANALYSIS OF RATES
FROM CHAPTER 1 TO 17 &
S1 TO S4

T.A. TO S.E. AAO Superintending Engineer


GOVERNMENT OF RAJASTHAN

PUBLIC WORKS DEPARTMENT


CIRCLE- BHARATPUR

BASIC SCHEDULE OF RATES


Effective from ----

* COMPARISION OF RATES
PROPOSED RATES & OLD
RATES CHAPTER-1 TO 17 &
SANITARY S-1 TO S-4

T.A. TO S.E. AAO Superintending Engineer

You might also like