You are on page 1of 264

PUNJAB INFRASTRUCTURE DEVELOPMENT BOARD

ANALYSIS OF RATE FOR BULK / PACKED BITUMEN SUPPLY VARIOUS TYPE COLLECTION OF BITUMEN FROM PANIPAT REFINERY
Bitumen rates Ex. Panipat w.e.f. 01/01/2014

Sl. Product Rates for supply

Rs.1.50per.Metric tonne per


Add @ 6.05% Punjab
Add @ 14.42 % Excise
Basic Rate from Panipat

Add 1 % Labur cess


Add @ 2 % Central
Nr.

Refinery to middle of the


Cartage by Road Panipat
( Amount in Rs.)

Duty ( inclusive of

Grand Total
Sub Total
Education cess )

Sale Tax
Sale Tax

reach 321 Kms.@


Total
Refinery

Kms.
1 2 3 4 5 6 7 8 9 10 11
Viscosity Grade -10 Bulk 44205 6374.36 50579.36 1011.59 3060.05 54651.00 481.50 55132.50 0.00 55132 PMT BM
I
( 80/100 grade) Packed 47305 6821.38 54126.38 1082.53 3274.65 58483.55 481.50 58965.05 0.00 58965 PMT

Bulk 45005 6489.72 51494.72 1029.89 3115.43 55640.05 481.50 56121.55 0.00 56122 PMT DBM& BC
Viscosity Grade-30
II
( 60/70 grade) Packed 48105 6936.74 55041.74 1100.83 3330.03 59472.60 481.50 59954.10 0.00 59954 PMT

Crumb Rubber Modified Bulk 44125 6362.83 50487.83 1009.76 3054.51 54552.09 481.50 55033.59 0.00 55034 PMT
III Bitumen - 50
Packed 47475 6845.90 54320.90 1086.42 3286.41 58693.73 481.50 59175.23 0.00 59175 PMT

Crumb Rubber Modified Bulk 44215 6375.80 50590.80 1011.82 3060.74 54663.36 481.50 55144.86 0.00 55145 PMT
IV Bitumen - 55
Packed 41854 6035.35 47889.35 957.79 2897.31 51744.44 481.50 52225.94 0.00 52226 PMT

Crumb Rubber Modified Bulk 44005 6345.52 50350.52 1007.01 3046.21 54403.74 481.50 54885.24 0.00 54885 PMT
V Bitumen - 60
Packed 42044 6062.74 48106.74 962.13 2910.46 51979.34 481.50 52460.84 0.00 52461 PMT

Bitumen Emulsion - Bulk 36035 5196.25 41231.25 824.62 2494.49 44550.36 481.50 45031.86 0.00 45032 PMT
VI Rapid Setting
Packed 39985 5765.84 45750.84 915.02 2767.93 49433.78 481.50 49915.28 0.00 49915 PMT TC
Bitumen Emulsion- Bulk 36245 5226.53 41471.53 829.43 2509.03 44809.99 481.50 45291.49 0.00 45291 PMT
VII Medium Setting
Packed 40195 5796.12 45991.12 919.82 2782.46 49693.40 481.50 50174.90 0.00 50175 PMT

Bitumen Emulsion- Bulk 34435 4965.53 39400.53 788.01 2383.73 42572.27 481.50 43053.77 0.00 43054 PMT
VIII Slow Setting
Packed 38385 5535.12 43920.12 878.40 2657.17 47455.69 481.50 47937.19 0.00 47937 PMT PRIMER

Lead Chart from Panipat to Plant & site of work


Panipat Ropar Bye pass RD 0.0 Site of work
!_____388___ ! _____!_______________________5.60/2

Total =388+2x2.80 394.00 Say 394 Kms Certified that the lead provided in the analysis of rate is the shortest lead and rate of bitumen
provided in the analysis of rate is the latest rate.

Sub Divisional Engineer , Executive Enginereer,


Provincial Sub Division Const. Division PWD B&R
PWD B&R,
Roopnagar. Roopnagar.
CONVERSION FROM HOUR RATE TO TONNE-KM RATE
1 Transit Mixer (4.0/4.5 cum)
Rate of transit mixer per hour 909
Wt of concrete in one load 10.8 Tonne (2.4 tonne / cum)
Analysis of time
Positioning of transit mixer at batching plant 1 Min
Loading from batching plant 2 Min
Maneuvering, reversing, turning for return 2 Min
Waiting time, unforseen contingencies etc. 2 Min
Total 7 Min
Speed with load 25 Km/hour
Speed while returning empty 35 Km/hour
Hence distance travelled in one hour 30 Km
Distance travelled in 53 minutes 26.5 Km
Hence cost of (10.8 x 26.5) tonne-Km is 909
Cost per tonne-Km = 3.176101
Say 3.2

2 Transit Mixer (3.0 cum)


Rate of transit mixer per hour 833
Wt of concrete in one load 7.2 Tonne (2.4 tonne / cum)
Analysis of time
Positioning of transit mixer at batching plant 1 Min
Loading from batching plant 2 Min
Maneuvering, reversing, turning for return 2 Min
Waiting time, unforseen contingencies etc. 2 Min
Total 7 Min
Speed with load 25 Km/hour
Speed while returning empty 35 Km/hour
Hence distance travelled in one hour 30 Km
Distance travelled in 53 minutes 26.5 Km
Hence cost of (7.2 x 26.5) tonne-Km is 833
Cost per tonne-Km = 4.365828
Say 4.4
3 Truck 5.5 cum per 10 tonnes
Rate per tonne-Km 3.00
Rate of one load per km= 22
Analysis of time
Positioning of tipper at loading point 1 Min
Loading by front end loader 1 cum bucket capacity @
25 cum per hour 13 Min
Maneuvering, reversing, dumping and turning for return 2 Min
Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
Speed with load 25 Km/hour
Speed while returning empty 35 Km/hour
Hence distance travelled in one hour 30 Km
Distance travelled effectively in 1 hour (in 40 minutes) 20 Km
Hence rate per hour 440
Say 440

3 Tipper 5 cum per 10 tonnes


Rate per tonne-Km 3.00
Rate of one load per km= 24
Analysis of time
Positioning of tipper at loading point 1 Min
Loading by front end loader 1 cum bucket capacity @
25 cum per hour 13 Min
Maneuvering, reversing, dumping and turning for return 2 Min
Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
Speed with load 25 Km/hour
Speed while returning empty 35 Km/hour
Hence distance travelled in one hour 30 Km
Distance travelled effectively in 1 hour (in 40 minutes) 20 Km
Hence rate per hour 480
Say 480
Water Tanker Wet Mix Plant
Description
70- hp 75 TPH
(A )OWNERSHIP CHARGES
i Factory cost including packing 800,000 2,000,000
ii deduct solvage value 15%( I) 120,000 300,000
iii Total investment to be depriciated (I)-(ii) 680,000 1,700,000
iv Economic life of machine in Hours 10,000 9,000
v Depreciation per hour iii/iv 68 189
vi storage charges per hour (1% of v) 1 2
vii Total ownership charges 69 191

(B) OPERATIONAL CHARGES


i Repair chrges per hour including maintenance
and replacement of tyres (150% of v) 102 283

(C) RUNNING CHARGES


i Operators (per month wage) 4,500 5,000
ii Cleaner/ Helper (per month wage) 3,000 3,000
vii Wages per hour 50 53

(D) CONSUMPTION CHARGES/HOUR


i Diesel consumption/electrical consumption Rs 42/ 37.41 224 748
ii Lubricating oil 10% of fuel cunsumption 22 75
iii Oil,grease,& cotton waste 10% of fuel consumption 22 75
269 898

(E) INTEREST & INSURANCE 10% 8 22

(F) OVERHEADS 8% on (A+B+C+D)


(Included in item rate analysis)
Rate/Hour 498 1,448
Generator Generator Generator Joint cutting Generator
250 KVA 125 KVA 100 KVA machine 33 KVA

1050000 700000 575000 180000


157,500 105,000 86,250 27,000
892,500 595,000 488,750 153,000
10000 10000 10000 10000
89 60 49 15
1 1 0 0
90 60 49 15

134 89 73 23
Market rate

4,000 4,000 4,000 4,000


3,000 3,000 3,000 3,000
47 47 47 47

935 374 374 150


94 37 37 15
94 37 37 15
1,122 449 449 180

11 7 6 2

1,403 652 624 5000 266


(A) Usage Rates of Plant and Machinery
(based on 2010 Common Schedule of Rates, Public Works Department, Govt. of Punjab and
Premium @13% as on December 2011 as per notification dated 05 December 2011)
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 319

P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 2232

Batching and Mixing Plant (b) 15 - 20 cum


P&M-003 Concrete Mixing cum/hour 13 hour 1860
capacity
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 1073

P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 198

P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 2868

P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 256

P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 16

P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 233

P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 233

P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1279

P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 853

P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 357

P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 3720

P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 2206

P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 800
Soil loading / Aggregate
P&M-017 Front End loader 1 cum bucket capacity cum/hour 60 /25 hour 806
loading
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 652

P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 535

P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1039

P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 23405

P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 17309

P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 13842

P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 11083

P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2635
Soil Ordinary/Soil Marshy /
P&M-026 Hydraulic Excavator of 1 cum bucket cum/hour 60 /60 /60 hour 1302
Soil Unsuitable
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 8665

P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 18228

P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 310

P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 62

P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 357
Clearing /Spreading /GSB
P&M-032 Motor Grader 3.35 mtr blade cum/hour 200/200/50/50 hour 2395
/WBM
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 1008
Paver Finisher Hydrostatic with sensor control Paving of DBM/ BM/SDC/
P&M-034 cum/hour 40 hour 2674
100 TPH Premix
Paving of WMM /Paving of
P&M-035 Paver Finisher Mechanical 100 TPH cum/hour 40/30 hour 975
DLC
0.75 m dia to 1.2 m dia Boring
P&M-036 Piling Rig with Bantonite Pump Rm/hour 2 to 3 hour 5464
attachment
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1243

P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 4170

P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 907

P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 129

P&M-041 Ripper Scarifying cum/hour 60 hour 28

P&M-042 Rotavator Scarifying cum/hour 25 hour 17

P&M-043 Road marking machine Road marking Sqm/hour 100 hour 93


Soil Compaction /BM
P&M-044 Smooth Wheeled Roller 8 tonne cum/hour 70/25 hour 460
Compaction
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1144
Transportation of soil, GSB,
P&M-046 Tipper - 5 cum Capacity in cum 5.5 km 6.78
WMM, Hotmix etc.
Transportation of soil, GSB,
P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 0.678
WMM, Hotmix etc.
Transportation of soil, GSB,
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 339
WMM, Hotmix etc.

Page 1 of 264
Transportation of Concrete Mix
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 1017
to site
Transportation of Concrete Mix
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 tonne.km 2.034
to site
Transportation of Concrete Mix
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 932.25
to site
Transportation of Concrete Mix
P&M-052 Transit Mixer 3.0 cum cum/hour 3 tonne.km 1.8645
to site
P&M-053 Tractor Pulling capacity in HP 50 hour 282.5

P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 282.5

P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 282.5

P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 24.5775

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 315.27

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 2.45775

P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1541

P&M-060 Water Tanker Water Transport capacity in KL 6 hour 200

P&M-061 Water Tanker Water Transport capacity in KL 6 km 7.0625

P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1317.015

Sl. No. Description of Machine Unit Rate


P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 740.15

P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 25594.5

P&M-065 Belt conveyor system hour 100

P&M-066 Boat to carry atleast 20 persons hour 100

P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 14644.8

P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 9153

P&M-069 Cold milling machine @ 20 cum per hour hour 300

P&M-070 Crane 5 tonne capacity hour 116.53125

P&M-071 Crane 10 tonne capacity hour 233.0625

P&M-072 Crane 15 tonne capacity hour 349.59375

P&M-073 Crane 20 tonne capacity hour 466.125

P&M-074 Crane 40 T capacity hour 932.25

P&M-075 Crane with grab 0.75 cum capacity hour 1073.5

P&M-076 Compressor with guniting equipment along with accessories hour 349.17

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 3661.2

P&M-078 Epoxy Injection gun hour 100

P&M-079 Generator 33 KVA hour 406.8

P&M-080 Generator 100 KVA hour 762.75

P&M-081 Generator 250 KVA hour 1906.875


Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method
P&M-082 hour 1000
of well sinking.
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 200

P&M-084 Jack for Lifting 40 tonne lifting capacity. day 500

P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 5974.875

P&M-086 Plate compactor hour 101.7

P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 1000

P&M-088 Texturing machine (for rigid pavement) hour 500

P&M-089 Truck Trailor 30 tonne capacity hour 847.50

P&M-090 Truck Trailor 30 tonne capacity t.km 0.678

P&M-091 Tunnel Boring machine hour 5000

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 1000

P&M-093 Wet Mix Plant 100 TPH hour 2195.025

P&M-094 Wet Mix Plant 75 TPH 2195.025

Page 2 of 264
(B) Labour
(based on PUNJAB GOVT. GAZ. (EXTRA), NOVEMBER 15,2012, DEPARTMENT OF LABOUR, (LABOUR BRANCH), No.
S.O. 94/C.A. 1111948/Ss.3and5/2012.-dated 15th November, 2012)

Sl. No. Description of Labour Unit Rate

L-01 Blacksmith (IInd class) day 230.00

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 264.50

L-03 Blaster (Stone cutter) day 264.50

L-04 Carpenter I Class day 264.50

L-05 Chiseller (Head Mazdoor) day 264.50

L-06 Driller (Jumper) day 264.50

L-07 Diver day 264.50

L-08 Fitter day 230.00

L-09 Mali day 264.50

L-10 Mason (IInd class) day 230.00

L-11 Mason (Ist class) day 223.36

L-12 Mate / Supervisor day 151.44

L-13 Mazdoor day 136.69

L-14 Mazdoor/Dresser (Semi Skilled) day 230.00

L-15 Mazdoor/Dresser/Sinker (Skilled) day 164.69

L-16 Medical Officer day 304.20

L-17 Operator(grouting) day 264.50

L-18 Painter I class day 223.36

L-19 Para medical personnel day 264.50

(C) Materials

Sl. No. Description Unit Rate

M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 919

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 494.68

M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 494.68

M-004 Coarse sand at Mixing Plant cum 828

M-005 Coarse sand at Site cum 710.46

M-006 Fine sand at Site cum 476.8

M-007 Moorum at Site cum 461.9

M-008 Gravel/Quarry spall at Site Cum 921

M-009 Granular Material or hard murrum for GSB works at Site Cum 727.79

M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 461.9

Page 3 of 264
M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 8.94

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 894

Rate at Plant
Description Unit
(HMP/Batching)
Rate at Site

M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 867 836.17

M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 867 867

M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 867 867

M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 867 867

M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 867 836.17

M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 867 867

M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm 867 867

M-020 Close graded Granular sub-base Material 2.36 mm cum 867 836.17

M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 476.8 476.8

M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 992.3 867

M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm 867 867

M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 867 867

M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 867 867

M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 867 867

M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 867 867

M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 867 867

M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 867 867

M-030 Aggregates below 5.6 mm cum 992.3 1066.89

M-031 Aggregates 22.4 mm to 2.36 mm cum 1012 1001

M-032 Aggregates 22.4 mm to 5.6 mm cum 1001 1001

M-033 Aggregates 45 mm to 2.8 mm cum 968.6 968.6

M-034 Aggregates 45 mm to 22.4 mm cum 1007.77 920.5

M-035 Aggregates 53 mm to 2.8 mm 990.25 990.25

M-036 Aggregates 53 mm to 22.4 mm cum 959 959

M-037 Aggregates 63 mm to 2.8 mm cum 982 982

M-038 Aggregates 63 mm to 45 mm cum 949 949

M-039 Aggregates 90 mm to 45 mm cum 938 938

M-040 Aggregates 10 mm to 5 mm cum 1078.94 987

M-041 Aggregates 11.2 mm to 0.09 mm cum 987 987

M-042 Aggregates 13.2 mm to 0.09 mm cum 1001 1001

M-043 Aggregates 13.2 mm to 5.6 mm cum 998.5 998.5

M-044 Aggregates 13.2 mm to 10 mm cum 1103.6 1016.5

M-045 Aggregates 20 mm to 10 mm cum 1103.6 1016.5

M-046 Aggregates 25 mm to 10 mm cum 1103.6 986

M-047 Aggregates 19 mm to 6 mm cum 1001 1001

M-048 Aggregates 37.5 mm to 19 mm cum 956 956

M-049 Aggregates 37.5 mm to 25 mm cum 1011.94 920.5

M-050 Aggregates 6 mm nominal size cum 969 969

M-051 Aggregates 10 mm nominal size cum 1005 1005

M-052 Aggregates 13.2/12.5 mm nominal size cum 1028 1028

M-053 Aggregates 20 mm nominal size cum 1028 1028

M-054 Aggregates 25 mm nominal size cum 925 925

M-055 Aggregates 40 mm nominal size cum 916 916

Sl. No. Description Unit Rate


M-056 AC pipe 100 mm dia metre 65

M-057 Acrylic polymer bonding coat litre 485

M-058 Alluminium Paint litre 132.61

Page 4 of 264
M-059 Aluminium alloy plate 2mm Thick sqm 425

M-060 Aluminium alloy/galvanised steel tonne 54574


Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron,
M-061 sqm 6064
cost of drilling holes, nuts, bolts etc.and signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 546

M-063 Barbed wire kg 65.56

M-064 Bearing (Cost of parts) nos 1213

M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 50000
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel
M-066 nos 15000
laminates by the process of vulcanisation,)
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 41309
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces
M-068 against stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all nos 41309
components
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 16378

M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 16378

M-071 Bentonite kg 4.1

M-072 Binding wire kg 100

M-073 Bitumen ( CRMB 55) tonne 55145

M-074 Bitumen (60-70 grade) VG -30 tonne 55132

M-075 Bitumen (80-100 grade ) VG-10 tonne 56122

M-076 Bitumen (Cutback ) tonne 47937

M-077 Bitumen (emulsion) tonne 49915

M-078 Bitumen (modified graded) tonne 38740

M-079 Brick each 4.41818

M-080 C.I.shoes for the pile kg 59.6

M-081 Cement tonne 5000

M-082 Cold twisted bars (HYSD Bars) tonne 45000

M-083 Coller for joints 300 mm dia nos 146

M-084 Compressible Fibre Board(20mm thick) sqm 486

M-085 Connectors/ Staples each 61

M-086 Copper Plate(12m long x 250mmwide) kg 290.55

M-087 Corrosion resistant Structural steel tonne 46526

M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 49

M-089 Credit for excavated rock found suitable for use cum 37

M-090 Curing compound liter 607

M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 834.4

M-092 Earth Cost or compensation for earth taken from private land cum 28
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit
M-093 metre 6064
conforming to clause 915.1 of IRC: 83 (part II),
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 1456

M-095 Epoxy compound with accessories for preparing epoxy mortar kg 486

M-096 Epoxy mortar kg 425

M-097 Epoxy primer kg 417.2

M-098 Epoxy resin-hardner mix for prime coat kg 486

M-099 Flag of red color cloth 600 x 600 mm each 91

M-100 Flowering Plants each 61

M-101 Galvanised MS flat clamp nos 25

M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 122

M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 61

M-104 Gelatin 80% kg 146

M-105 Geo grids sqm 607

M-106 Geomembrane sqm 607

M-107 Geonets sqm 607

M-108 Geotextile sqm 37.25

M-109 Geotextile filter fabric sqm 37.25

M-110 GI bolt 10 mm Dia nos 13

M-111 Grouting pump with agitator hour 304

Page 5 of 264
M-112 Grass (Doob) kg 7

M-113 Grass (Fine) kg 13

M-114 HDPE pipes 75mm dia metre 607

M-115 HDPE pipes 90mm dia metre 607

M-116 Hedge plants each 61

M-117 Helical pipes 600mm diameter metre 2426

M-118 Hot applied thermoplastic compound litre 150

M-119 HTS strand tonne 57453

M-120 Joint Sealant Compound kg 607

M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 61

M-122 LDO for steam curing litre 43

M-123 M.S. Clamps nos 13

M-124 M.S. Clamps kg 52.15

M-125 M.S.shoes @ 35 Kg per pile of 15 m kg 37

M-126 Mild Steel bars tonne 47307.5


Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto
140mm assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and
M-127 metre 1820
control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised
representative
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal
joint assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage
M-128 metre 1820
elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his
authorised representative
M-129 Nipples 12mm nos 243

M-130 Nuts and bolts kg 64.07

M-131 Paint litre 192.81

M-132 Pavement Marking Paint litre 117.16

M-133 Paving Fabric sqm 225

M-134 Perforated geosynthetic pipe 150 mm dia metre 182

M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 243

M-136 Pesticide kg 1820

M-137 Pipes 200 mm dia, 2.5 m long for drainage metre 243

M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 61

M-139 Plastic tubes 50 cm dia, 1.2 m high nos 3639

M-140 Polymer braids metre 364

M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 965

M-142 Pre-coated stone chips of 13.2 mm nominal size cum 1213


Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a
M-143 metre 668
single operation for the full length of a joint to ensure water tightness.
M-144 Pre-moulded asphalt filler board sqm 425

M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 49

M-146 Primer kg 102.94

M-147 Quick setting compound kg 364

M-148 Random Rubble Stone cum 2604.51

M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 5000

M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 4452

M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 1149

M-152 Reflectorising glass beads kg 75

M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 364

M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 364
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced
M-155 metre 364
polymer/polymeric strips)
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 364

M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 364

M-158 Rivets each 101.32

M-159 Sand bags (Cost of sand and Empty cement bag) nos 7

M-160 Sapling 2 m high 25 mm dia each 25

M-161 Scrap tyres of size 900 x 20 nos 364

M-162 Seeds kg 243

M-163 Selected earth cum 43

Page 6 of 264
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 61

M-165 Sheathing duct metre 304

M-166 Shrubs each 7

M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 364

M-168 Sodium vapour lamp each 1213

M-169 Square Rubble Coursed Stone cum 2705.04

M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 1213

M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 1820

M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 79

M-173 Steel helmet and cushion block on top of pile head during driving. kg 61

M-174 Steel pipe 25 mm external dia as per IS:1239 metre 182

M-175 Steel pipe 50 mm external dia as per IS:1239 metre 364

M-176 Steel wire rope 20 mm kg 61

M-177 Steel wire rope 40 mm kg 61

M-178 Strip seal expansion join metre 7500

M-179 Structural Steel tonne 45000

M-180 Super plastisizer admixture IS marked as per 9103-1999 kg 44.7

M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 607

M-182 Through and bond stone each 14.453

M-183 Tie rods 20mm diameter nos 49

M-184 Tiles size 300 x 300 mm and 25 mm thick each 15

M-185 Timber cum 24255

M-186 Traffic cones with 150 mm reflective sleeve nos 243

M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 6064

M-188 Unstaked lime tonne 4500

M-189 Water KL 10

M-190 Water based cement paint litre 31

M-191 Welded steel wire fabric kg 61

M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 61

M-193 Wooden ballies 2" Dia for bracing each 61

M-194 Wooden ballies 8" Dia and 9 m long each 91

M-195 Wooden packing cum 12000

M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 122

Page 7 of 264
Overheads for Road Works 10%

Contractors profit for Road Works 10%

for input of Overheads or Contractors profit please type in collum C as like


Overheads for Bridge Works 20%
below
Type symble of apostrope(') then input value then one space then symble
Overheads for Bridge Works (Rehabilitation) 25%
of percentage (%) for example '08 %

Contractors profit for Bridge Works 10%

Lead from Mixing Plant to working site 1 km

Lead for E/W borow area to site 20 km

Lead for fly ash from source to site 53 km

Page 8 of 264
Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate
per cm height
Item 8.3 Printing new letter and figures of any shade (ii) English Roman 0.30
per letter
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 40.00
Item 8.9 Painting angle iron post two coats sqm 46.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 4,152.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 3,425.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 2,422.00
Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 6,211.00
Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 5,610.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 4,228.00
PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (A) cum 3,080.00
Mixer
PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (B) PCC cum 3,390.00
Mixer
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (C) cum 3,443.00
Mixer
Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 4,650.00
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (C) cum 3,388.00
Batching Plant
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (D) cum 3,667.00
Mixer
Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 4,949.00
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (D) cum 3,614.00
Batching Plant
RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (E) cum 3,723.00
Mixer
RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (E) cum 3,740.00
Batching Plant
PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (F) cum 3,697.00
Mixer
PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (F) cum 3,641.00
Batching Plant
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (G) cum 3,740.00
Mixer
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (G) cum 3,686.00
Batching Plant
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (H) cum 3,816.00
Mixer
Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 3,952.00
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 5,217.00
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (H) cum 3,838.00
Batching Plant
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) i cum 3,719.00
Mechinery by Mixer
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) i cum 3,558.00
Mechinery by Batching Plant
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) ii cum 3,874.00
Mechinery by Mixer
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) ii cum 3,712.00
Mechinery by Batching Plant
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) iii cum 3,904.00
Mechinery by Mixer
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) iii cum 3,743.00
Mechinery by Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) iv cum 3,974.00
Mechinery by Mixer
Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 5,260.00
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) iv cum 3,812.00
Mechinery by Batching Plant
Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 5,114.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 138.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 36.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5,317.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5,783.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 6,171.83
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 4,428.00
Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 3,690.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 50,004.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 65,101.00
Item 5.17 Fog Seal sqm 53.00
Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 57.00
Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9
Item 5.21 Case-II sqm 67.00
mm
Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm
Item 5.21 Case-IV sqm 88.00
and cracked area above 50 %
Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 124.00
Item 5.15 Case-I Slurry Seal Case-I 5 mm thickness sqm 82.00
Item 5.15 Case-II Slurry Seal Case-II 3 mm thickness sqm 57.00
Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 35.00
Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 104.00

Page 9 of 264
Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 85.00

Page 10 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including cutting of trunks, branches
2.1 and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in
the depression/pit.)

(i) Girth from 300 mm to 600 mm each 137.00


(ii) Girth from 600 mm to 900 mm each 259.00
(iii) Girth from 900 mm to 1800 mm each 482.00
(iv) Girth above 1800 mm each 896.00
2.2 Clearing Grass and Removal of Rubbish hectare 8636.00
Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes,
shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
2.3 materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and
disposal of top organic soil not exceeding 150 mm in thickness.)

(ii) By Mechanical Means


A In area of light jungle hectare 49142.00
Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary,
2.4 sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and
lead of 1000 metres)

(i) Lime /Cement Concrete


I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below cum 212.00
B Cement Concrete Grade M-15 & M-20 cum 247.00
C Prestressed / Reinforced cement concrete grade M-20 & above cum 623.00
II By Mechanical Means for items No. 202( b) & ( c)
A Cement Concrete Grade M-15 & M-20 cum 372.00
B Prestressed / Reinforced cement concrete grade M-20 & above cum 634.00
(ii) Dismantling Brick / Tile work
A In lime mortar cum 143.00
B In cement mortar cum 177.00
C In mud mortar cum 129.00
D Dry brick pitching or brick soling cum 122.00
(iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar cum 157.00
B Rubble stone masonry in cement mortar. cum 177.00
C Rubble Stone Masonry in mud mortar. cum 143.00
D Dry rubble masonry cum 136.00
E Dismantling stone pitching/ dry stone spalls. cum 129.00
F Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials. cum 143.00
(iv) Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level cum 343.00
(v) Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet.
A Including dismembering tonne 836.00
B Excluding dismembering. tonne 603.00
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 6.00
(vi) Scraping of bricks dismantled from brick work including stacking.
In lime/Cement mortar 1000
A 605.00
numbers
In mud mortar 1000
B 216.00
numbers
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 243.00
B In Mud mortar cum 51.00
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 8.00
Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and dismantling of masonry
(ix) works.
A Up to 600 mm dia metre 90.00
B Above 600 mm to 900 mm dia metre 121.00
C Above 900 mm metre 208.00

Page 11 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead of
2.5 1000 metres, stacking serviceable and unserviceable materials separately)
I By Manual Means
A Bituminous courses cum 389.00
B Granular courses cum 286.00
II By Mechanical Means
A Bituminous course cum 187.00
Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by mechanical means using
pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal
2.6 of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately) cum 992.00

Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up
2.7 to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.) metre 43.00

Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to
2.8 a lead of 1000 metre) metre 10.00

Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled material
2.9 with all lifts and up to a lead of 1000 metre) metre 14.00

Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal of
2.10 dismantled material with all lifts and lead upto 1000 m and back filling of pit.)
A 5th KM stone each 199.00
B Ordinary KM Stone each 121.00
C Hectometre Stone each 24.00
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back
2.11 filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking metre 27.00
serviceable material and unserviceable material separately. )

Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead
2.12 upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of metre 74.00
concerned department)

Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm dia under
the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of
2.13 serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.) metre 86.00

Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation and
2.14 dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to each 101.00
a lead of 1000 metres and stacking the serviceable and unserviceable material separately)

Page 12 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in truck for
3.1 carrying of cut earth to embankment site with all lifts and lead upto1000 metres.) cum 97.00

Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including loading in a truck
3.2 and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres ) cum 133.00

Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by mechanical means including
3.3 cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including cum 152.00
trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.)

Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average
3.4 lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.) cum 255.00

Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements
3.5 of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres ) cum 292.00

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres. (Excavation for roadwork
in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side
3.6 slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location cum 45.00
within all lifts and lead upto 1000m)

Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres. (Excavation for
roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers,
3.7 transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with cum 60.00
requirements of lines, grades and cross sections.)

Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting prohibited) with rock breakers
3.8 including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side
slopes in accordance with requirements of lines, grades and cross sections.)

A Mechanised cum 362.00


B Manual Method cum 736.00
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock with
controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of
3.9 lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres ) cum 379.00

Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity
3.10 including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side cum 51.00
slopes in accordance with requirements of lines, grades and cross sections.)

Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation, loading
3.11 and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause cum 46.00
305.)

Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the rock face
by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the
3.12 excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead sqm 143.00
upto 1000 m, all as specified in clause No. 303)

Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides
3.13 and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.)

(i) Ordinary soil


A Manual Means (Depth upto 3 m) cum 138.00
B Mechanical Means (Depth upto 3 m) cum 36.00
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 173.00
B Mechanical Means cum 49.00
(iii) Hard rock ( requiring blasting )
A Manual Means cum 360.00
(iv) Hard rock ( blasting prohibited )
A Mechanical Means cum 472.00
(v) Marshy soil
A Manual means ( upto 3 m depth) cum 290.00

Page 13 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
B Mechanical Means cum 106.00
Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road surface to
3.14 a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. ) sqm 14.00

Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing bituminous road
3.15 surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.) sqm 4.00

Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved material
3.16 obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to cum 249.00
meet requirement of table 300-2)

Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with approved
3.17 materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and cum 84.00
compacted to meet requirement of table 300-2)

Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved material
3.18 obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to cum 293.00
meet requirement of table No. 300-2)

3.19 Compacting Original Ground


Compacting original ground supporting subgrade (Loosening of the ground upto a level of500 mm below the subgrade
Case-I level, watered, graded and compacted in layers to meet requirement of table 300-2 for subgrade construction.) cum 60.00

Case-II :Compacting original ground supporting embankment cum 29.00


Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and re-application on embankment
3.20 slopes, cut slopes and other areas in localities where the available embankment material is not conducive to plant growth) cum 131.00

Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top soil from borrow areas
3.21 located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to maintain cum 91.00
fertility of the agricultural field, finishing it to the required levels and satisfaction of the farmer.)

Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or
3.22 other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of rods and sqm 16.00
watering)

Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer,
3.23 mulching material, applying bituminous emulsion at the rate of0.23 litres per sqm and laying and fixing jute netting, including sqm 129.00
watering for 3 months all as per clause 308)

Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified
3.24 lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of50 metres (average lead 25 metres))

A Mechanical means metre 56.00


B Manual Means metre 35.00
Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm in ordinary
3.25 rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301 to 309.
Excavated material to be used in embankment at site.)

A Mechanical Means metre 114.00


B Manual Means metre 52.00
3.26 Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock as per design.) metre
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe of 100 mm internal diameter
of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon
size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross
3.27 section of excavation 450 x 550 mm. Excavated material to be utilised in roadway at site ) 587.00

Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates
3.28 conforming to table 300-4, excavated material to be utilised in roadway ) metre 171.00

Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions) lined with
3.29 RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads) metre 2356.00

Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing mud and
3.30 slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile sqm 1.00
and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.)

Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard rock fragments of size not
3.31 exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top cum 50.00
layer with granular material, rolled with vibratory road roller, all complete as per clause 313)

Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting
3.32 and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres) cum 149.00

Page 14 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary
3.33 rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with cum 224.00
all lift and lead upto 1000 metres )

Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring blasting, by
3.34 mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.) cum 293.00

Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to following
3.35 reasons:)
Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste material.
(Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
3.36 thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as specified cum 314.00
in IRC: SP: 58-2001 and as per approved plans.)

Page 15 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant
A at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )

(i) for grading- I Material cum 1606.00


Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the subgrade on a prepared surface,
pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime having minimum content of 70% of CaO,
4.3 grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of improved sub
grade)

A By Mechanical Means cum 400.00


B By Manual Means cum 376.00
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the
spread soil in place with rotavator with 3 % slaked lime with minimum content of 70% of CaO, grading with motor grader and
4.4 compacting with the road roller at OMC to achieve at least 98%of the max dry density to form a layer of sub base.) cum 561.00

Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, adding the
designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting
4.5 with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base.) cum 698.00

Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base (Providing, laying and
spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place
4.6 with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.)

(i) For Sub-Base course cum 1953.00


(ii) For Base course cum 1953.00
Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450 to the center line of the road and at
4.7 one metre interval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated material sqm 404.00
within 1000 metres lead)

Inverted Choke (Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse
4.8 sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power roller etc) cum 1266.00

Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound
macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in
4.9 stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the
interstices of coarse aggregate, watering and compacting to the required density.)

A By Manual Means
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1714.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1927.03
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1727.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1806.00
(c) Using Screening Type-B (11.2mm Agg.) cum 1899.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1741.00
(b) Using Screening Type-B (11.2mm Agg.) cum 1914.00
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1659.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1872.24
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1672.00
(b) Using Screening Type-A (13.2mm Agg.) cum 1752.00
(c) Using Screening Type-B (11.2mm Agg.) cum 1844.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1686.00
(b) Using Screening Type-B (11.2mm Agg.) cum 1859.00

Page 16 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by breaking damaged cement
concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from
4.10 breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course, cum 163.00
constructed as WBM to clause 404 except the use of screening or binding Material.)

Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry surface of
crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key
4.11 aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause 506.3.8) sqm 24.00

Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site,
4.12 laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller cum 1861.26
to achieve the desired density.)

Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of Median and Island above road
4.13 level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other cum 99.00
structures, spread, graded and compacted as per clause 407)

Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island above road level
4.14 with approved material brought from borrow pits, spread, sloped and compacted as per clause 407) cum 284.00

4.15 Construction of Shoulders (A. Earthen Shoulders)


Footpaths and Separators (Construction of footpath/separator by providing a 150 mm compacted granular sub base as per
4.16 clause 401 and 25 mm thick cement concrete grade M15, over laid with precast concrete tiles in cement mortar 1:3 sqm 586.00
including provision of all drainage arrangements but excluding kerb channel..)

Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles,
4.17 spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of
sub-base/Base)

A By Mix in Place Method


(i) For 53 mm maximum size cum 1710.00
(ii) For 45 mm maximum size cum 1741.00
B By Mixing Plant :
(i) For 53 mm maximum size cum 1868.00
(ii) For 45 mm maximum size cum 1188.00
Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture with granular soil, free from
organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less
than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than 50%, fly ash to conform to
4.18 gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to 30%, the minimum un-confined cum 580.00
compressive strength and CBR value after 28 days curing and 4 days soaking to be 7.5kg/sq, cm and 25% respectively, all
as specified in IRC: 88-1984. )

Page 17 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including
5.1 clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.) sqm 51.40

5.2 Tack coat


Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per
sqm on the prepared bituminous/granular surface cleaned with mechanical broom. sqm 16.76

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average
output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to
5.3 site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction)

(i) for Grading I ( 40 mm nominal size ) cum 7863.79


(ii) for GradingII(19 mm nominal size) cum 7871.54
Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by providing a layer of
compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key
5.4 aggregates and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of compaction)

A 50 mm thick sqm 432.00


B 75 mm thick sqm 590.00
Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared base consisting of a two layer
composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips
spreader may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the
5.5 second layer to serve as a Base conforming to the line, grades and cross-section specified, the compacted layer thickness sqm 351.00
being 75 mm)

Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type HMP
producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a
5.6 hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all
respects.)

(i) for Grading I ( 40 mm nominal size ) cum 10006.88


Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with 100-120 TPH batch type
HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 to 5 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher
5.7 with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects)

(i) for Grading I ( 13 mm nominal size ) cum 9943.00


(ii) for GradingII(10 mm nominal size) cum 10693.00
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an
average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @
5.4 to 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control
5.8 to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in all respects)

(i) for Grading-I ( 13 mm nominal size ) cum 11688.42


Surface Dressing (Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates
5.9 of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel
roller)

Case -1 :-19 mm nominal chipping size sqm 104.00


Case - II 13 mm nominal size chipping sqm 85.00
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness
composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required
5.10 line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying
and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.)

Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75
(i) tonnes/hour . sqm 152.00

(ii) Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm 186.00

Page 18 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity not less than
75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of
11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the
5.11 required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, sqm 200.00
laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to required level and grade. )

Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and
5.12 cross fall using Type A and B seal coats)
(i) Case - I : Type A sqm 80.00
Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75
(ii) tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.) sqm 60.00

Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources confirming to the
physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection, transportation,
stacking and testing and measured in cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively,
5.13 rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of aggregates at site are cum
not available, nearest crusher site may be ascertained. Loading and un-loading charges and cost of carriage may be added
to these rates to arrive at the cost at site.)

Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal
5.14 size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, sqm 592.00
pressed into surface when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.)

Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous
5.15 emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying
and compacting to provide even riding surface)

(i) 5 mm thickness sqm 85.45


(ii) 3 mm thickness sqm 58.00
(iii) 1.5 mm thickness sqm 35.00
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold milling of exiting bituminous
layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 % of the required quantity,
hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks and
5.16 evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at site cum 7908.00
and compacting to the required grade, level and thickness, all as specified in clause 517.)

5.17 Fog Spray sqm 47.00


added 1.In case it is decided by the engineer to blind the fog spray, the following may be added sqm 6.00
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous cold mix on prepared base
5.18 consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of
suitable type and capacity, transporting, laying, compacting and finishing to specified grades and levels.)

(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate cum 12877.00
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 12772.00
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 8695.00
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 8585.00
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and
5.19 bituminous binder on a prepared sub-grade or sub-base to the lines, levels, grades and cross sections as per the drawings cum 9750.00
including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing.)

Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb
rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC: SP:
53 blending of modifier with bitumen to be done either at the refinery or at the site plant capable of producing the modified
5.20 binder to be delivered in drums which shall be agitated in melted condition using suitable device before use to ensure tonne
uniform dispersion.)

5.21 Crack Prevention Courses


Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying of a stress absorbing membrane
over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone aggregates @
(i) 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates and surface sqm 57.00
finished to conform to clause 902.)

Page 19 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed
(ii) stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished sqm 67.00
to conform to clause 902.)

Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and laying a
single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area
above 50 % after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the
(iii) rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the sqm 88.00
surface for uniform spread of aggregates and surface finished to conform to clause 902.)

Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen impregnated geotextile layer after cleaning
(iv) the road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of sqm 124.00
paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause 704.4.5)

Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type
5.22 cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with
a smooth steel wheel roller, all as per clause 519.3)

(i) 75 mm thickness cum 8688.00


(ii) 40 mm thickness cum 12138.00
(iii) 25 mm thickness cum 13930.00

Page 20 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection
8.1 beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
408)

A Using Concrete Mixer metre 226.00


B Using Concrete Batching and Mixing Plant metre 231.00
Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb with channel with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb
8.2 channel 300 mm wide, 50 mm thick in PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb
laying machine, foundation concrete laid manually, all complete as per clause 408)

B Using Concrete Batching and Mixing Plant metre 439.00


Printing new letter and figures of any shade (Printing new letter and figures of any shade with synthetic enamel paint black
8.3 or any other approved colour to give an even shade)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half ) cm height per
(i) 0.60
letter
English and Roman cm height per
(ii) 0.30
letter
Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as
per IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm
thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
8.4 designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing)

(i) 90 cm equilateral triangle each 4206.00


( ii ) 60 cm equilateral triangle each 2783.00
( iii ) 60 cm circular each 3715.00
( iv ) 80 mm x 60 mm rectangular each 5160.00
(v) 60 cm x 45 cm rectangular each 3619.00
(vi ) 60 cm x 60 cm square each 4280.00
( vii ) 90 cm high octagon each 6569.00
Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting direction and place identification
retro-reflectorised sign asper IRC:67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x
8.5 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 sqm 9152.00
cm, 60 cm below ground level as per approved drawing)

Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction and place
identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3,
fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x
8.6 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement sqm 15825.00
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)

Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2
8.7 and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles
and trusses of sections and type as per structural design requirements and approved plans)

A Truss and Vertical Support tonne 83366.00


B Aluminium alloy plate for over head sign tonne 575.00
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel paint in all
8.8 shades on new plastered concrete surfaces) sqm 42.00

Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel surface after
8.9 through cleaning of surface to give an even shade) sqm 49.00

Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood surface after
8.10 through cleaning of surface to give an even shade) sqm 55.00

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on roads in
8.11 two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including cleaning
the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )

(i) Over 10 cm in width sqm 63.00


(ii) Up to 10 cm in width sqm 54.00

Page 21 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on roads in two
8.12 coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )

(i) Over 10 cm in width sqm 43.00


(ii) Up to 10 cm in width sqm 46.00
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface (Providing
and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm
8.13 area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, sqm 607.78
uniform and free from streaks and holes.)

Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in
8.14 position including painting and printing etc)
(i) 5th kilometre stone (precast) each 2632.00
(ii) Ordinary Kilometer stone (Precast) each 1610.00
(iii) Hectometer stone (Precast) each 460.00
Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100
cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm
8.15 dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.) each 1116.00

Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in
8.16 position including finishing and lettering but excluding painting) each 535.00

G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle iron
posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on
8.17 one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, metre 251.00
turn buckles etc complete as per clause 807 )

G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m angle iron
posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on
8.18 one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, metre 415.00
turn buckles etc complete as per clause 807 )

Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high fencing with angle iron posts
50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete, corner, end
8.19 and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm mesh metre 647.00
and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)

Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and erecting 50
8.20 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metre 2270.00
metres high above ground, 2 m centre to centre, complete as per approved drawings)

Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia
8.21 painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes metre 1820.00
50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)

Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler
8.22 board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the
Engineer, all as specified)

(i) M 20 grade concrete metre 3469.00


8.23 Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x
75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be
A galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical metre 2721.00
post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 810)

Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier comprising of 3
mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post,
150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be
B galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical metre 3525.00
post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)

Page 22 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by specialised
8.24 firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in this field and
ISI certified for the approved design and drawing.)

Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical posts of
medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below
ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m
center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post
to be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist
8.25 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation metre 2055.00
concrete as per approved design and drawing, rate excluding excavation and cement concrete.)

8.26 Anti - Glare Devices in Median


Plantation (Plantation of shrubs and plants of approved species in the median. apart from cutting off glare from vehicle
A coming from opposite direction, these plants provide a pleasant envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture. )

Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans (Providing and erecting an
anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre length and
1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of
B steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation concrete, metre 4323.00
applying 2 coats of paint on all exposed surfaces, all as per approved design and drawings.)

Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare screen with rectangular
vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450
to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post
C firmly embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, metre 807.00
all complete as per approved design and drawings)

Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for
8.27 street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.)

(i) For Fixing in Median each 4286.00


(ii) For fixing in Footpath each 4235.00
Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard
8.28 specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp) each 3226.00

Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the road
(new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls at
both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a
0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to
8.29 minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher
than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.)

(i) Single Row for one utility service metre 2474.00


(ii) Double Row for two utility services metre 4566.00
(iii) Triple Row for three utility services metre 6666.00
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60 km of the highway. )
8.30

Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items involved for underpass/ subway/
overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign etc. The
8.31 rates for these items are available in respective chapters which can be adopted for the quantities derived from the approved
designs and drawings)

Traffic Control System and Communication system (Providing a traffic control centre and communication system including
telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer system
These are specialised item of telecommunication system and are the commercial products. The designer is required to
8.32 contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these installations,
pricing may be done as per rates in relevant chapters for quantities derived approved design and drawing.)

Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign board
8.33 electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or
galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3)

(i) Gantry Support System tonne 81484.00


Message Display (Message display board 6 sqm electronically operated with complete electronic fitments for flashing the
(ii) pre-determined messages.)

Page 23 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
8.34 Traffic Impact Attenuators at Abutments and Piers
With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres
A of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as sqm 2389.00
per approved design and drawings.)

Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at abutment/pier of
B flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20 sqm 760.00
mm steel wire rope as per approved design and drawings)

With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from plastic
C tubes on impact over a pre-determined time, thus absorbing the energy)) sqm 18533.00

Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling
8.35 hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part each 730.00
4:1973)

Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE)
8.36 material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as each 296.00
per BS 873)

8.37 Roadside Amenities


Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system
A Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual site conditions)

Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for the
B quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates
for items may be from respective chapters.)

C Lawn (Providing a lawn planted with grass and its maintenance )


Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm
8.38 wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.) sqm

Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where
8.39 necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia each
steel pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of paint)

High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole lighting with 30 m high hot
dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per
IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern carriage,
suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power tools for raising
and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and fixing 2 nos
8.40 aviation obstruction lights on top of the mast, all complete as per approved design and drawings This is a specialised work
and is generally done by firms who specialise in such jobs. The detailed designs and estimates are submitted by the firms
alongwith their tender for checks by the Department. The cost of this work is required to be worked out based on approved
design, drawings and estimate of the lowest tender. A separate contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.)

Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under
8.41 based on the approved design and drawings:-)
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable locations in
construction zone comprising of warning zone, approach transition zone, working zone and terminal transition zone with a
minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the
carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road
8.42 level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings,
removed and disposed of after completion of construction work, all as per IRC:SP:55-2001)

Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in
length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats)
8.43 with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete each 2598.00
as per IRC:SP:55-2001 )

8.44 Permanent Type Barricade in Construction Zone


With Steel Components (Construction of a permanent type barricade made of steel components, 1.5 m high from road
level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with
A yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 ) each 4160.00

Page 24 of 264
Summary of Rate Analysis
Item No. Descriptions Unit Rate
With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m high from
road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted
B with yellow and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 ) each 5749.00

With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long,
C 600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips) each 11476.00

Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter, 800
8.45 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted with each 325.00
reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)

Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely fastened
8.46 to a staff 1 m in length for guiding the traffic) each 430.00

CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
12.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 66.00
(ii) 3 m to 6 m depth cum 85.00
(iii) Above 6 m depth cum 113.00
B Mechanical Means
(i) Depth upto 3 m cum 49.00
(ii) Depth 3 m to 6 m cum 56.00
(iii) Depth above 6m cum 68.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 94.00
B Mechanical Means cum 64.00
III Hard rock ( requiring blasting )
A Manual Means cum 314.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 347.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 288.00
B Mechanical Means cum 67.00
VI Back Filling in Marshy Foundation Pits cum 219.00
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per items
12.2 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 811.00
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm
12.4 nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum 3626.00

Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per drawing and
12.5 technical specifications cum 4545.00

12.6 A Cement mortar1:3 (1cement :3 sand) cum 3425.00


B Cement mortar1:2 (1cement :2 sand) cum 4150.00
C Cement mortar1:4 (1cement :4 sand) cum 2941.00
D Cement mortar1:6 (1cement :6 sand) cum 2519.00
12.7 Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum 6211.00
(b) Random Rubble Masonry cum 6020.00
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications
12.8

A PCC Grade M15 cum 4228.00


B PCC Grade M20 cum 4653.00
C RCC Grade M20
Case I Using concrete mixer cum 4726.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4650.00
D PCC Grade M25
Case I Using concrete Mixer cum 5021.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4949.00
Page 25 of 264
E RCC Grade M25
Case I Using concrete Mixer cum 5098.00
CHAPTER-1
CARRIAGE OF MATERIALS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1.1 Loading and Unloading of Stone Boulder/Stone cum
aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket 13 Min
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 339.00 111.87 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 806.00 265.98 P&M-017
cum/hour
b) Overhead charges @ 0.1 on (a) 37.79
c) Contractor's profit @ 0.1 on (a+b) 41.56
Cost for 5.5 cum = a+b+c 457.20
Rate per cum = (a+b+c)/ 5.5 83.13
Note Unloading will be by tipping. say 83.00
1.2 Loading and Unloading of Boulders by Manual Means

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 151.44 16.66 L-12
Mazdoor for loading and unloading day 0.750 136.69 102.52 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 339.00 254.25 P&M-048
c) Overhead charges @ 0.1 on (a+b) 37.34
d) Contractor's profit @ 0.1 on (a+b+c) 41.08
Cost for5.5 cum = a+b+c+d 451.85
Rate per cum = (a+b+c+d)/5.5 82.15
Note Unloading will be by tipping. say 82.00
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor for loading and unloading day 2.000 136.69 273.38 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 315.27 630.54 P&M-057
c) Overhead charges @ 0.1 on (a+b) 91.60
d) Contractor's profit @ 0.1 on (a+b+c) 100.76
Cost for10 tonnes = a+b+c+d 1108.40
Rate per tonnes = (a+b+c+d)/10 110.84
say 111.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km

(i) Surfaced Road


Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 339.00 135.60 P&M-048
Time taken for empty return trip. hour 0.290 339.00 98.31 P&M-048
b) Overhead charges @ 0.1 on (a) 23.39
c) Contractor's profit @ 0.1 on (a+b) 25.73

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
cost for 100 t km = a+b+c 283.03
Rate per t.km = (a+b+c)/100 2.83
say 2.80
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.500 339.00 169.50 P&M-048
Time taken for empty return trip hour 0.330 339.00 111.87 P&M-048
b) Overhead charges @ 0.1 on (a) 28.14
c) Contractor's profit @ 0.1 on (a+b) 30.95
Cost for 100 t .km = a+b+c 340.46
Rate per t.Km = (a+b+c)/100 3.40
say 3.40
1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and Choe
Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 339.00 339.00 P&M-048
Time taken for empty return trip hour 0.670 339.00 227.13 P&M-048
b) Overhead charges @ 0.1 on (a) 56.61
c) Contractor's profit @ 0.1 on (a+b) 62.27
Cost for 100 t .km = a+b+c 685.02
Rate per t.Km = (a+b+c)/100 6.85
say 6.90
1.5 Hand Broken Stone Aggregates 63 mm Nominal Size

Supply of quarried stone, hand breaking into coarse


aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.060 151.44 9.09 L-12
Mazdoor day 1.500 136.69 205.04 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 494.68 544.15 M-002
c) Overhead charges @ 0.1 on (a+b) 75.83
d) Contractor's profit @ 0.1 on (a+b+c) 83.41
Rate per cum = a+b+c+d 917.51
say 918.00
1.6 Crushing of Stone Aggregates 13.2 mm Nominal Size.

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13.2 mm nominal size.
Unit = cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 151.44 115.09 L-12
Mazdoor Skilled day 2.000 230.00 460.00 L-14
Mazdoor including breaking of any oversize boulder. day 17.000 136.69 2323.73 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 919.00 735200.00 M-001

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 18228.00 109368.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 806.00 16120.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 339.00 6780.00 P&M-048
d) Overhead charges @ 0.1 on (a+b+c) 87036.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 95740.35
Cost for 600 cum = a+b+c+d+e 1053143.86
Rate per cum = (a+b+c+d+e)*0.95/600 1667.48
say 1667.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the
production of 600 cum of stone chips of 13.2 mm size and
balance 5 per cent to the production of stone dust which
comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
1.7 Crushing of Stone Aggregates 20 mm Nominal Size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 151.44 115.09 L-12
Mazdoor Skilled day 2.000 230.00 460.00 L-14
Mazdoor including breaking of any size boulder. day 17.000 136.69 2323.73 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 919.00 735200.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 18228.00 109368.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 806.00 16120.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 339.00 6780.00 P&M-048
d) Overhead charges @ 0.1 on (a+b+c) 87036.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 95740.35
Cost for 670 cum = a+b+c+d+e 1053143.86
Rate per cum = (a+b+c+d+e)*0.90/670 1414.67
say 1415.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the
production of 670 cum of stone aggregates of 20mm size
and balance 10 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and


secondary crushing units.
1.8 Crushing of Stone Aggregates 40 mm Nominal Size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit = cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 151.44 115.09 L-12
Mazdoor Skilled day 2.000 230.00 460.00 L-14

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 17.000 136.69 2323.73 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 919.00 735200.00 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 18228.00 109368.00 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 806.00 16120.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 339.00 6780.00 P&M-048
d) Overhead charges @ 0.1 on (a+b+c) 87036.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 95740.35
Cost for 750 cum = (a+b+c+d+e)x0.85 895172.28
Rate per cum = (a+b+c+d+e)x0.85/750 1193.56
say 1194.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the
production of 750 cum of stone aggregates of 40mm size
and balance 15 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and


secondary crushing units.

Page 4 of 264
CHAPTER-2
SITE CLEARANCE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.1 201 Cutting of Trees, including cutting of Trunks, Branches and
Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling
in the depression/pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoors for cutting trees including cutting, refilling, day 0.600 136.69 82.01 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 282.50 28.25 P&M-053
c) Overhead charges @ 0.1 on (a+b) 11.33
d) Contractor's profit @ 0.1 on (a+b+c) 12.46
Rate for each tree = a+b+c+d 137.08
say 137.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoors for cutting trees including cutting, refilling, day 0.900 136.69 123.02 L-13
compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means
b) Machinery
Tractor-trolley hour 0.300 282.50 84.75 P&M-053
c) Overhead charges @ 0.1 on (a+b) 21.38
d) Contractor's profit @ 0.1 on (a+b+c) 23.52
Rate for each tree = a+b+c+d 258.73
say 259.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoors for cutting trees including cutting, refilling, day 2.000 136.69 273.38 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 282.50 113.00 P&M-053
c) Overhead charges @ 0.1 on (a+b) 39.85
d) Contractor's profit @ 0.1 on (a+b+c) 43.83
Rate for each tree = a+b+c+d 482.18
say 482.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoors for cutting trees including cutting, refilling, day 4.000 136.69 546.76 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 282.50 169.50 P&M-053
c) Overhead charges @ 0.1 on (a+b) 74.05
d) Contractor's profit @ 0.1 on (a+b+c) 81.45
Rate for each tree = a+b+c+d 895.99
say 896.00
2.2 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance of 50
metres outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 2.000 151.44 302.88 L-12
Mazdoor day 50.000 136.69 6834.50 L-13
b) Overhead charges @ 0.1 on (a) 713.74
c) Contractor's profit @ 0.1 on (a+b) 785.11
Rate per Hectare = a+b+c 8636.23
say 8636.00
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.

Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 151.44 908.64 L-12
Mazdoor day 150.000 136.69 20503.50 L-13
b) Machinery
Tractor-trolley hour 1.000 282.50 282.50 P&M-053
c) Overhead charges @ 0.1 on (a+b) 2169.46
d) Contractor's profit @ 0.1 on (a+b+c) 2386.41
Rate per Hectare = a+b+c+d 26250.51
say 34411.00
2.3 (i) B In area of thorny jungle
a) Labour
Mate day 8.000 151.44 1211.52 L-12
Mazdoor day 200.000 136.69 27338.00 L-13
b) Machinery
Tractor-trolley hour 2.000 282.50 565.00 P&M-053
c) Overhead charges @ 0.1 on (a+b) 2911.45
d) Contractor's profit @ 0.1 on (a+b+c) 3202.60
Rate per Hectare = a+b+c+d 35228.57
say 35229.00
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoor day 4.000 136.69 546.76 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 10.000 3720.00 37200.00 P&M-014
stumps
Tractor-trolley hour 1.000 282.50 282.50 P&M-053
c) Overhead charges @ 0.1 on (a+b) 3805.35
d) Contractor's profit @ 0.1 on (a+b+c) 4185.88
Rate per Hectare = a+b+c+d 46044.72
Add 12% Premium 5525.37
Total = 51570.09
say 49142.00
2.3 (ii) B In area of thorny jungle
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 12.000 3720.00 44640.00 P&M-014
stumps

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Tractor-trolley hour 1.500 282.50 423.75 P&M-053
c) Overhead charges @ 0.1 on (a+b) 4592.02
d) Contractor's profit @ 0.1 on (a+b+c) 5051.23
Rate per Hectare = a+b+c+d 55563.49
say 55563.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres

Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below

a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor for dismantling and loading day 1.000 136.69 136.69 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 21.90
d) Contractor's profit @ 0.1 on (a+b+c) 24.09
Cost for 1.25 cum = a+b+c+d 265.02
Rate per cum = (a+b+c+d)/ 1.25 212.01
say 212.00
2.4 (i) B Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor for dismantling and loading day 1.250 136.69 170.86 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 25.47
d) Contractor's profit @ 0.1 on (a+b+c) 28.02
Cost for 1.25 cum = a+b+c+d 308.20
Rate per cum = (a+b+c+d)/ 1.25 246.56
say 247.00
2.4 (i) C Prestressed / Reinforced cement concrete grade M-20 &
above
a) Labour
Mate day 0.150 151.44 22.72 L-12
Blacksmith day 0.250 264.50 66.13 L-02
Mazdoor for dismantling, loading and unloading day 3.500 136.69 478.42 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 64.35
d) Contractor's profit @ 0.1 on (a+b+c) 70.79
Cost for 1.25 cum = a+b+c+d 778.67
Rate per cum = (a+b+c+d)/ 1.25 622.94
say 623.00
2.4 II By Mechanical Means for items No. 202( b)& ( c)
A Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor for loading and unloading day 0.250 136.69 34.17 L-13

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor with Pneumatic breaker day 0.250 230.00 57.50 L-14
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 0.670 319.00 213.73 P&M-001
breaker @ 1.5 cum per hour
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 38.47
d) Contractor's profit @ 0.1 on (a+b+c) 42.32
Cost for 1.25 cum = a+b+c+d 465.49
Rate per cum = (a+b+c+d)/ 1.25 372.40
say 372.00
2.4 II B Prestressed / reinforced cement concrete grade M-20 &
above
a) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor with Pneumatic breaker day 0.660 230.00 151.80 L-14
Blacksmith day 0.250 264.50 66.13 L-02
Mazdoor for loading and unloading day 0.250 136.69 34.17 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 1.000 319.00 319.00 P&M-001
breaker @ 1.00 cum per hour
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 65.49
d) Contractor's profit @ 0.1 on (a+b+c) 72.04
Cost for 1.25 cum = a+b+c+d 792.48
Rate per cum = (a+b+c+d)/ 1.25 633.99
say 634.00
2.4 (ii) Dismantling Brick / Tile work
A In lime mortar
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor for dismantling, loading and unloading day 0.500 136.69 68.35 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 14.76
d) Contractor's profit @ 0.1 on (a+b+c) 16.24
Cost for 1.25 cum = a+b+c+d 178.66
Rate per cum = (a+b+c+d)/ 1.25 142.92
say 143.00
2.4 (ii) B In cement mortar
a) Labour
Mate day 0.030 151.44 4.54 L-12
Mazdoor for dismantling, loading and unloading day 0.750 136.69 102.52 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 18.33
d) Contractor's profit @ 0.1 on (a+b+c) 20.17
Cost for 1.25 cum = a+b+c+d 221.84
Rate per cum = (a+b+c+d)/ 1.25 177.47
say 177.00
2.4 (ii) C In mud mortar
a) Labour
Mate day 0.016 151.44 2.42 L-12
Mazdoor for dismantling and loading day 0.400 136.69 54.68 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 13.34
d) Contractor's profit @ 0.1 on (a+b+c) 14.67

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 1.25 cum = a+b+c+d 161.38
Rate per cum = (a+b+c+d)/ 1.25 129.11
say 129.00
2.4 (ii) D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 151.44 2.12 L-12
Mazdoor for Dismantling, loading and unloading day 0.350 136.69 47.84 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 12.62
d) Contractor's profit @ 0.1 on (a+b+c) 13.89
Cost for 1.25 cum = a+b+c+d 152.75
Rate per cum = (a+b+c+d)/ 1.25 122.20
say 122.00
2.4 (iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 151.44 3.63 L-12
Mazdoor for dismantling, loading and unloading. day 0.600 136.69 82.01 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 16.19
d) Contractor's profit @ 0.1 on (a+b+c) 17.81
Cost for 1.25 cum = a+b+c+d 195.93
Rate per cum = (a+b+c+d)/ 1.25 156.74
say 157.00
2.4 (iii) B Rubble stone masonry in cement mortar.
a) Labour
Mate day 0.030 151.44 4.54 L-12
Mazdoor for dismantling, loading and unloading. day 0.750 136.69 102.52 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 18.33
d) Contractor's profit @ 0.1 on (a+b+c) 20.17
Cost for 1.25 cum = a+b+c+d 221.84
Rate per cum = (a+b+c+d)/ 1.25 177.47
say 177.00
2.4 (iii) C Rubble Stone Masonry in mud mortar.
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor for dismantling, loading and unloading. day 0.500 136.69 68.35 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 14.76
d) Contractor's profit @ 0.1 on (a+b+c) 16.24
Cost for 1.25 cum = a+b+c+d 178.66
Rate per cum = (a+b+c+d)/ 1.25 142.92
say 143.00
2.4 (iii) D Dry rubble masonry
a) Labour
Mate day 0.018 151.44 2.73 L-12
Mazdoor for dismantling, loading and unloading. day 0.450 136.69 61.51 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 14.05
d) Contractor's profit @ 0.1 on (a+b+c) 15.46

Page 5 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 1.25 cum = a+b+c+d 170.02
Rate per cum = (a+b+c+d)/ 1.25 136.02
say 136.00
2.4 (iii) E Dismantling stone pitching/ dry stone spalls.
a) Labour
Mate day 0.016 151.44 2.42 L-12
Mazdoor for dismantling, loading and unloading. day 0.400 136.69 54.68 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 13.34
d) Contractor's profit @ 0.1 on (a+b+c) 14.67
Cost for 1.25 cum = a+b+c+d 161.38
Rate per cum = (a+b+c+d)/ 1.25 129.11
say 129.00
2.4 (iii) F Dismantling boulders laid in wire crates including opening of
crates and stacking dismantled materials.

a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor for dismantling, loading and unloading day 0.500 136.69 68.35 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 14.76
d) Contractor's profit @ 0.1 on (a+b+c) 16.24
Cost for 1.25 cum = a+b+c+d 178.66
Rate per cum = (a+b+c+d)/ 1.25 142.92
say 143.00
2.4 (iv) Wood Work wrought framed and fixed in frames of trusses
upto a height of 5 m above plinth level
a) Labour
Mate day 0.060 151.44 9.09 L-12
Carpenter day 0.500 264.50 132.25 L-04
Mazdoor for dismantling, loading and unloading. day 1.000 136.69 136.69 L-13
b) Machinery
Tractor-trolley hour 0.270 282.50 76.28 P&M-053
c) Overhead charges @ 0.1 on (a+b) 35.43
d) Contractor's profit @ 0.1 on (a+b+c) 38.97
Cost for 1.25 cum = a+b+c+d 428.70
Rate per cum = (a+b+c+d)/ 1.25 342.96
say 343.00
2.4 (v) Steel Work in all types of sections upto a height of 5 m
above plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 151.44 21.20 L-12
Blacksmith day 1.000 264.50 264.50 L-02
Mazdoor for dismantling, loading and unloading day 2.500 136.69 341.73 L-13
Add 2.5 per cent of cost of labour for gas cutting, ropes, 15.69
pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 282.50 48.03 P&M-053
c) Overhead charges @ 0.1 on (a+b) 69.11
d) Contractor's profit @ 0.1 on (a+b+c) 76.03
Rate per tonne = a+b+c+d 836.28
say 836.00
2.4 (v) B Excluding dismembering.

Page 6 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.220 151.44 33.32 L-12
Mazdoor for dismantling, loading and unloading day 2.000 136.69 273.38 L-13
Blacksmith day 0.500 264.50 132.25 L-02
Add 2.5 per cent of cost of labour for gas cutting, ropes, 10.97
pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 282.50 48.03 P&M-053
c) Overhead charges @ 0.1 on (a+b) 49.79
d) Contractor's profit @ 0.1 on (a+b+c) 54.77
Rate per tonne = a+b+c+d 602.51
say 603.00
2.4 (v) C Extra over item No( v ) A and( v ) B for cutting rivets.

Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 151.44 1.51 L-12
Blacksmith day 0.130 264.50 34.39 L-02
Mazdoor day 0.130 136.69 17.77 L-13
b) Overhead charges @ 0.1 on (a) 5.37
c) Contractor's profit @ 0.1 on (a+b) 5.90
Cost for 10 rivets = a+b+c 64.94
Rate for each rivet = ( a+b+c)/10 6.49
say 6.00
2.4 (vi) Scraping of Bricks Dismantled from Brick Work including
Stacking.
Unit = numbers
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 151.44 21.20 L-12
Mazdoor day 3.500 136.69 478.42 L-13
b) Overhead charges @ 0.1 on (a) 49.96
c) Contractor's profit @ 0.1 on (a+b) 54.96
Rate per1000 Nos = a+b+c 604.54
say 605.00
2.4 (iv) B In mud mortar
a) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor day 1.250 136.69 170.86 L-13
b) Overhead charges @ 0.1 on (a) 17.84
c) Contractor's profit @ 0.1 on (a+b) 19.63
Rate per1000 Nos = a+b+c 215.91
say 216.00
2.4 (vii) Scraping of Stone from Dismantled Stone Masonry
Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.060 151.44 9.09 L-12
Mazdoor day 1.400 136.69 191.37 L-13
b) Overhead charges @ 0.1 on (a) 20.05
c) Contractor's profit @ 0.1 on (a+b) 22.05
Rate per cum = a+b+c 242.55
say 243.00
2.4 (vii) B In Mud mortar

Page 7 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.010 151.44 1.51 L-12
Mazdoor day 0.300 136.69 41.01 L-13
b) Overhead charges @ 0.1 on (a) 4.25
c) Contractor's profit @ 0.1 on (a+b) 4.68
Rate per cum = a+b+c 51.45
say 51.00
2.4 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone
Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoor for scarping and loading day 4.000 136.69 546.76 L-13
b) Machinery
Tractor-trolley hour 0.320 282.50 90.40 P&M-053
c) Overhead charges @ 0.1 on (a+b) 66.14
d) Contractor's profit @ 0.1 on (a+b+c) 72.75
Cost for 100 sqm = a+b+c+d 800.28
Rate per sqm = (a+b+c+d)/100 8.00
say 8.00
2.4 (ix) Removing all type of Hume Pipes and Stacking within a lead
of 1000 metres including Earthwork and Dismantling of
Masonry Works.
Unit = metre
Taking output = 1 metre
A Up to 600 mm dia
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor day 0.520 136.69 71.08 L-13
b) Overhead charges @ 0.1 on (a) 7.41
c) Contractor's profit @ 0.1 on (a+b) 8.15
Rate per metre = a+b+c 89.67
say 90.00
2.4 (ix) B Above 600 mm to 900 mm dia
a) Labour
Mate day 0.030 151.44 4.54 L-12
Mazdoor day 0.700 136.69 95.68 L-13
b) Overhead charges @ 0.1 on (a) 10.02
c) Contractor's profit @ 0.1 on (a+b) 11.02
Rate per metre = a+b+c 121.27
say 121.00
2.4 (ix) C Above 900 mm
a) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor day 1.200 136.69 164.03 L-13
b) Overhead charges @ 0.1 on (a) 17.16
c) Contractor's profit @ 0.1 on (a+b) 18.88
Rate per metre = a+b+c 207.64
say 208.00
Note 1. The excavation of earth, dismantling of stone masonry
work in head walls and protection works is not included
which is to be measured and paid separately.
2. Credit for retrieved stone from masonry work may be
taken as per actual availability.
2.5 202 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately

Page 8 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 151.44 9.09 L-12
Mazdoor for dismantling, loading and unloading day 1.500 136.69 205.04 L-13
b) Machinery
Tractor-trolley hour 0.380 282.50 107.35 P&M-053
c) Overhead charges @ 0.1 on (a+b) 32.15
d) Contractor's profit @ 0.1 on (a+b+c) 35.36
Rate per cum = a+b+c+d 388.98
say 389.00
2.5 I B Granular courses
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor for dismantling, loading and unloading. day 1.000 136.69 136.69 L-13
b) Machinery
Tractor-trolley hour 0.330 282.50 93.23 P&M-053
c) Overhead charges @ 0.1 on (a+b) 23.60
d) Contractor's profit @ 0.1 on (a+b+c) 25.96
Rate per cum = a+b+c+d 285.53
say 286.00
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 151.44 1.51 L-12
Mazdoor day 0.300 136.69 41.01 L-13
b) Machinery
Tractor-trolley hour 0.380 282.50 107.35 P&M-053
Farm tractor with ripper @ 60 cum per hour hour 0.017 282.50 4.80 P&M-055
c) Overhead charges @ 0.1 on (a+b) 15.47
d) Contractor's profit @ 0.1 on (a+b+c) 17.01
Rate per cum = a+b+c+d 187.16
say 187.00
2.6 202 Dismantling of Cement Concrete Pavement
Dismantling of cement concrete pavement by mechanical
means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at
designated locations and disposal of dismantled materials
up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 151.44 4.54 L-12
Semi skilled mazdoor for operating pneumatic tools day 0.500 230.00 115.00 L-14
Mazdoors as helpers including loading and unloading day 0.500 136.69 68.35 L-13

b) Machinery
Air compressor 250 cfm with two leads for pneumatic hour 1.000 319.00 319.00 P&M-001
cutters/ hammers @ 1 cum per hour
Tractor-trolley hour 0.400 282.50 113.00 P&M-053
Joint Cutting Machine with 2-3 blades hour 1.000 200.00 200.00 P&M-083
c) Overhead charges @ 0.1 on (a+b) 81.99
d) Contractor's profit @ 0.1 on (a+b+c) 90.19
Rate per cum = a+b+c+d 992.06
say 992.00

Page 9 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note The above analysis is for removal of complete pavement. In
case full depth repair work is required to be done after
dismantling, provision of a concrete cutting and sawing
machine may be added for 0.25 hours.
2.7 202 Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable materials and unserviceable
materials separately.
Unit = running metre
Taking output = 1 metre
a) Labour
Mate day 0.006 151.44 0.91 L-12
Mazdoor including loading and unloading day 0.150 136.69 20.50 L-13
b) Machinery
Tractor-trolley hour 0.050 282.50 14.13 P&M-053
c) Overhead charges @ 0.1 on (a+b) 3.55
d) Contractor's profit @ 0.1 on (a+b+c) 3.91
Rate per metre = a+b+c+d 43.00
say 43.00
2.8 202 Dismantling of Kerb Stone
Dismantling kerb stone by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.010 151.44 1.51 L-12
Mazdoor including loading and unloading day 0.150 136.69 20.50 L-13
b) Machinery
Tractor-trolley hour 0.200 282.50 56.50 P&M-053
c) Overhead charges @ 0.1 on (a+b) 7.85
d) Contractor's profit @ 0.1 on (a+b+c) 8.64
Cost for 10 m = a+b+c+d 95.01
Rate per metre = (a+b+c+d)/10 9.50
say 10.00
2.9 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a lead
of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.015 151.44 2.27 L-12
Mazdoor including loading and unloading day 0.225 136.69 30.76 L-13
b) Machinery
Tractor-trolley hour 0.300 282.50 84.75 P&M-053
c) Overhead charges @ 0.1 on (a+b) 11.78
d) Contractor's profit @ 0.1 on (a+b+c) 12.96
Cost for 10 m = a+b+c+d 142.51
Rate per metre = (a+b+c+d)/10 14.25
say 14.00
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone
A 5th KM stone

Page 10 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 151.44 19.69 L-12
Mazdoor day 0.750 136.69 102.52 L-13
b) Machinery
Tractor-trolley hour 0.150 282.50 42.38 P&M-053
c) Overhead charges @ 0.1 on (a+b) 16.46
d) Contractor's profit @ 0.1 on (a+b+c) 18.10
Rate for one 5th KM stone = a+b+c+d 199.14
say 199.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor day 0.500 136.69 68.35 L-13
b) Machinery
Tractor-trolley hour 0.100 282.50 28.25 P&M-053
c) Overhead charges @ 0.1 on (a+b) 9.96
d) Contractor's profit @ 0.1 on (a+b+c) 10.96
Rate for one ordinary KM stone = a+b+c+d 120.54
say 121.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 151.44 0.61 L-12
Mazdoor day 0.100 136.69 13.67 L-13
b) Machinery
Tractor-trolley hour 0.020 282.50 5.65 P&M-053
c) Overhead charges @ 0.1 on (a+b) 1.99
d) Contractor's profit @ 0.1 on (a+b+c) 2.19
Rate for one Hectometre stone = a+b+c+d 24.11
say 24.00
2.11 202 Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing
including posts, foundation concrete, back filling of pit by
manual means including disposal of dismantled material with
all lifts and up to a lead of 1000 metres, stacking serviceable
material and unserviceable material separately.

Unit = running metre


Taking output = 30 metres
a) Labour
Mate day 0.150 151.44 22.72 L-12
Mazdoor including loading and unloading day 3.000 136.69 410.07 L-13
Blacksmith day 0.750 264.50 198.38 L-02
b) Machinery
Tractor-trolley hour 0.150 282.50 42.38 P&M-053
c) Overhead charges @ 0.1 on (a+b) 67.35
d) Contractor's profit @ 0.1 on (a+b+c) 74.09
Cost for 30 metres = a+b+c+d 814.98
Rate per metre = (a+b+c+d)/30 27.17
say 27.00
2.12 202 Dismantling of CI Water Pipe Line
Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and stacking
of serviceable material and unserviceable material
separately under supervision of concerned department

Page 11 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.090 151.44 13.63 L-12
Mazdoor day 2.000 136.69 273.38 L-13
Plumber day 0.250 264.50 66.13 L-02
b) Machinery
Truck 10 tonne capacity hour 0.250 315.27 78.82 P&M-057
Light Crane 3 tonne capacity hour 0.500 357.00 178.50 P&M-013
c) Overhead charges @ 0.1 on (a+b) 61.05
d) Contractor's profit @ 0.1 on (a+b+c) 67.15
Cost for 10 metres = a+b+c+d 738.65
Rate per metre = (a+b+c+d)/10 73.86
say 74.00
Note The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.
2.13 202 Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm
dia under the supervision of concerned department including
disposal with all lifts and up to a lead of 1000 metres and
stacking of serviceable and unserviceable material
separately but excluding earth excavation and dismantling of
masonry works.
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.100 151.44 15.14 L-12
Mazdoor day 2.500 136.69 341.73 L-13
b) Machinery
Crane 5 tonne capacity hour 0.300 116.53 34.96 P&M-070
Truck flat body 10 tonne hour 1.000 315.27 315.27 P&M-057
c) Overhead charges @ 0.1 on (a+b) 70.71
d) Contractor's profit @ 0.1 on (a+b+c) 77.78
Cost for 10 metres = a+b+c+d 855.59
Rate per metre = (a+b+c+d)/10 85.56
say 86.00
Note The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.
2.14 202 Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation
and dismantling of foundation concrete and lines under the
supervision of concerned department, disposal with all lifts
and up to a lead of 1000 metres and stacking the
serviceable and unserviceable material separately
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 151.44 72.69 L-12
Mazdoor day 10.000 136.69 1366.90 L-13
Electrician/Lineman day 2.000 264.50 529.00 L-02
b) Machinery
Tractor-trolley hour 1.500 282.50 423.75 P&M-053
c) Overhead charges @ 0.1 on (a+b) 239.23
d) Contractor's profit @ 0.1 on (a+b+c) 263.16
Cost for 30 poles = a+b+c+d 2894.73
Rate per pole = (a+b+c+d)/30 96.49
Add 5% Premium 4.82

Page 12 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Total = 101.32
say 101.00

Page 13 of 264
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.1 301 Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 151.44 272.59 L-12
Mazdoor day 45.000 136.69 6151.05 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 315.27 3152.70 P&M-057
c) Overhead charges @ 0.1 on (a+b) 957.63
d) Contractor's profit @ 0.1 on (a+b+c) 1053.40
Cost of 120 cum = a+b+c+d 11587.37
Rate per cum = (a+b+c+d)/120 96.56
say 97.00
Note In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
3.2 301 Excavation in Ordinary Rock by Manual Means
Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 151.44 424.03 L-12
Mazdoor day 70.000 136.69 9568.30 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 315.27 3152.70 P&M-057
c) Overhead charges @ 0.1 on (a+b) 1314.50
d) Contractor's profit @ 0.1 on (a+b+c) 1445.95
Cost for 120 cum = a+b+c+d 15905.49
Rate per cum = (a+b+c+d)/120 132.55
say 133.00
Note In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
3.3 301 Excavation in Soil with Dozer with lead upto 100 metres

Excavation for road way in soil by mechanical means


including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50
metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3720.00 22320.00 P&M-014
c) Overhead charges @ 0.1 on (a+b) 2260.55
d) Contractor's profit @ 0.1 on (a+b+c) 2486.60
Cost for 180 cum = a+b+c+d 27352.65
Rate per cum = (a+b+c+d)/180 151.96
say 152.00

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.4 301 Excavation in Ordinary Rock with Dozer with lead upto 100
metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mazdoor day 3.000 136.69 410.07 L-13
b) Machinery
Dozer, 80 HP @ 20 cum per hour hour 6.000 3720.00 22320.00 P&M-014
c) Overhead charges @ 0.1 on (a+b) 2274.82
d) Contractor's profit @ 0.1 on (a+b+c) 2502.31
Cost for 108 cum = a+b+c+d 27525.37
Rate per cum = (a+b+c+d)/108 254.86
say 255.00
3.5 301 Excavation in Hard Rock (requiring blasting) with disposal
upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking 0utput = 180 cum
a) Labour
Mate day 0.220 151.44 33.32 L-12
Mazdoor day 3.000 136.69 410.07 L-13
Driller day 2.000 264.50 529.00 L-06
Blaster day 0.250 264.50 66.13 L-03
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3720.00 22320.00 P&M-014
Air compressor, 250 cfm with 2 jack hammer hour 6.000 319.00 1914.00 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper10 tonne capacity hour 11.250 339.00 3813.75 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 146.00 9198.00 M-104
Electric Detonators @ 1 detonator for 2 gelatin sticks of each 252.000 14.56 3669.12 M-094 /100
125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 (37.00) (3330.00) M-089
per cent quantity blasted
d) Overhead charges @ 0.1 on (a+b+c) 4345.94
e) Contractor's profit @ 0.1 on (a+b+c+d) 4780.53
Cost for 180 cum = a+b+c+d+e 52585.85
Rate per cum = (a+b+c+d+e)/180 292.14
say 292.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.6 301 Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 hour 6.000 1302.00 7812.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 339.00 5424.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 1352.15
d) Contractor's profit @ 0.1 on (a+b+c) 1487.36
Cost for 360 cum = a+b+c+d 16361.01
Rate per cum = (a+b+c+d)/360 45.45
say 45.00
3.7 301 Excavation in Ordinary Rock using Hydraulic Excavator CK-
90 and Tippers with Disposal upto 1000 metres.

Excavation for roadway in ordinary rock with hydraulic


excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36 hour 6.000 1302.00 7812.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 339.00 3729.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 1182.65
d) Contractor's profit @ 0.1 on (a+b+c) 1300.91
Cost for 240 cum = a+b+c+d 14310.06
Rate per cum = (a+b+c+d)/240 59.63
say 60.00
3.8 301 Excavation in Hard Rock (blasting prohibited)
Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A Mechanised
Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.400 151.44 60.58 L-12
Mazdoor for trimming slopes including mannul loading day 10.000 136.69 1366.90 L-13
in truck
b) Machinery
Hydraulic excavator with rock breaker attachment @ 6 hour 6.000 1302.00 7812.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 339.00 2203.50 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 18.000 (37.00) (666.00) M-089
per cent of excavated quantity
c) Overhead charges @ 0.1 on (a+b) 1077.70
d) Contractor's profit @ 0.1 on (a+b+c) 1185.47
Cost for 36 cum = a+b+c+d 13040.14
Rate per cum = (a+b+c+d)/36 362.23
say 362.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.8 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 151.44 248.36 L-12
Mazdoor including loading in truck day 16.000 136.69 2187.04 L-13
Chiseller day 24.000 264.50 6348.00 L-05
Blacksmith day 1.000 264.50 264.50 L-02
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 339.00 983.10 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 8.000 (37.00) (296.00) M-089
per cent of excavated
c) Overhead charges @ 0.1 on (a+b) 973.50
d) Contractor's profit @ 0.1 on (a+b+c) 1070.85
Cost for 16 cum = a+b+c+d 11779.35
Rate per cum = (a+b+c+d)/16 736.21
say 736.00
Note 1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.
3.9 301 Excavation in Hard Rock (controlled blasting) with disposal
upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.220 151.44 33.32 L-12
Mazdoor day 3.000 136.69 410.07 L-13
Driller day 2.000 264.50 529.00 L-06
Blaster day 0.500 264.50 132.25 L-03
b) Machinery
Dozer 80 HP @ 30 cum per hour hour 6.000 3720.00 22320.00 P&M-014
Air compressor, 250 cfm with 2 jack hammers hour 6.000 319.00 1914.00 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 5.5 cum capacity, 4 trips per hour. hour 8.200 339.00 2779.80 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 146.00 9198.00 M-104
Electric Detonators @ 1 detonator for1/2 gelatin stick each 1008.000 14.56 14676.48 M-094 /100
of 125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 (37.00) (3330.00) M-089
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling 2841.45
arrangements to guard against any rock fly off during
blasting
d) Overhead charges @ 0.1 on (a+b+c) 5634.04
e) Contractor's profit @ 0.1 on (a+b+c+d) 6197.44
Cost for 180 cum = a+b+c+d+e 68171.84
Rate per cum = (a+b+c+d+e)/180 378.73
say 379.00
Note 1. Credit is considered for 50 per cent of quantity of
blastered rock, if found suitable for construction..
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
3.10 301 Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 hour 6.000 1302.00 7812.00 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 339.00 4623.96 P&M-048
c) Overhead charges @ 0.1 on (a+b) 1272.15
d) Contractor's profit @ 0.1 on (a+b+c) 1399.36
Cost for 300 cum = a+b+c+d 15392.96
Rate per cum = (a+b+c+d)/300 51.31
say 51.00

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.11 301 Removal of Unserviceable Soil with Disposal upto 1000
metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour hour 6.000 1302.00 7812.00 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 339.00 5546.04 P&M-048
c) Overhead charges @ 0.1 on (a+b) 1364.35
d) Contractor's profit @ 0.1 on (a+b+c) 1500.79
Cost for 360 cum = a+b+c+d 16508.68
Rate per cum = (a+b+c+d)/360 45.86
say 46.00
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.12 303 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)

a) Labour
Mate day 0.600 151.44 90.86 L-12
Mazdoor day 15.000 136.69 2050.35 L-13
b) Machinery
Air compressor 250 cfm with 2 leads @ 20 cum per hour 6.000 319.00 1914.00 P&M-001
hour
Dozer, 80 HP hour 6.000 3720.00 22320.00 P&M-014
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
c) Materials
Gelatin 80 per cent kg 42.000 146.00 6132.00 M-104
Electric Detonators @ 1 detonator for 1/2 gelatin stick each 672.000 14.56 9784.32 M-094 /100
of 125 gms each
d) Overhead charges @ 0.1 on (a+b+c) 4712.75
e) Contractor's profit @ 0.1 on (a+b+c+d) 5184.03
Cost for 400 sqm = a+b+c+d+e 57024.32
Rate per sqm = (a+b+c+d+e)/400 142.56
say 143.00
Note In case blasted rock is used to the contractor against
payment for constructed work, the cost of carriage shall be
reduced to that extent.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
(i) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
a) Labour
Mate day 0.320 151.44 48.46 L-12
Mazdoor day 8.000 136.69 1093.52 L-13
b) Overhead charges @ 0.1 on (a) 114.20
c) Contractor's profit @ 0.1 on (a+b) 125.62
Cost for 10 cum = a+b+c 1381.80
Rate per cum = (a+b+c)/10 138.18
say 138.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
3.13 (i) B Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 151.44 48.46 L-12

Page 5 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 8.000 136.69 1093.52 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1302.00 7812.00 P&M-026
c) Overhead charges @ 0.1 on (a+b) 895.40
d) Contractor's profit @ 0.1 on (a+b+c) 984.94
Cost for 300 cum = a+b+c+d 10834.32
Rate per cum = (a+b+c+d)/300 36.11
say 36.00
Note Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 151.44 60.58 L-12
Mazdoor day 10.000 136.69 1366.90 L-13
b) Overhead charges @ 0.1 on (a) 142.75
c) Contractor's profit @ 0.1 on (a+b) 157.02
Cost for 10 cum = a+b+c 1727.25
Rate per cum = (a+b+c)/10 172.72
say 173.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) B Mechanical Means

Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1302.00 7812.00 P&M-026
c) Overhead charges @ 0.1 on (a+b) 866.85
d) Contractor's profit @ 0.1 on (a+b+c) 953.53
Cost for 216 cum = a+b+c+d 10488.87
Rate per cum = (a+b+c+d)/216 48.56
say 49.00
Note 1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 151.44 80.26 L-12
ii) Driller day 0.840 264.50 222.18 L-06
iii) Blaster day 0.400 264.50 105.80 L-03
iv) Mazdoor day 12.000 136.69 1640.28 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 319.00 212.67 P&M-001
per hour
c) Material
Blasting Material kg 3.500 146.00 511.00 M-104
Detonator electric each 14.000 14.56 203.84 M-094 /100

d) Overhead charges @ 0.1 on (a+b+c) 297.60


e) Contractor's profit @ 0.1 on (a+b+c+d) 327.36
Cost for 10 cum = a+b+c+d+e 3601.00
Rate per cum = (a+b+c+d+e)/10 360.10
say 360.00
Note Cost of dewatering @ 10 per cent of labour cost may be
added, where required Assessment for dewatering shall be
made as per site conditions.
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.200 151.44 30.29 L-12
Mazdoor day 5.000 136.69 683.45 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 319.00 3190.00 P&M-001
breaker @ 1 cum per hour

Page 6 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.1 on (a+b) 390.37
d) Contractor's profit @ 0.1 on (a+b+c) 429.41
Cost for 10 cum = a+b+c+d 4723.52
Rate per cum = (a+b+c+d)/10 472.35
say 472.00
Note 1. Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 151.44 60.58 L-12
Mazdoor day 10.000 136.69 1366.90 L-13
b) Machinery
Tractor-trolley hour 2.670 282.50 754.28 P&M-053
c) Material
Selected earth for refilling cum 5.000 43.00 215.00 M-163
d) Overhead charges @ 0.1 on (a+b+c) 239.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 263.64
Cost for 10 cum = a+b+c+d+e 2900.07
Rate per cum = ( a+b+c+d+e)/ 10 290.01
say 290.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.13 (v) B Mechanical Means

a) Labour
i) Mate day 0.080 151.44 12.12 L-12
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 136.69 273.38 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 1302.00 221.34 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 339.00 152.55 P&M-048
c) Material
Selected earth for refilling cum 5.000 43.00 215.00 M-163
d) Overhead charges @ 0.1 on (a+b+c) 87.44
e) Contractor's profit @ 0.1 on (a+b+c+d) 96.18
Cost for 10 cum = a+b+c+d+e 1058.01
Rate per cum = (a+b+c+d+e)/10 105.80
say 106.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.14 305.4.3 Scarifying Existing Granular Surface to a Depth of 50 mm by
Manual Means
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 151.44 30.29 L-12
Mazdoor including loading and unloading day 5.000 136.69 683.45 L-13
b) Machinery
Tractor-trolley hour 1.670 282.50 471.78 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 118.55
e) Contractor's profit @ 0.1 on (a+b+c+d) 130.41
Cost for 100 sqm = a+b+c+d 1434.47
Rate per sqm = (a+b+c+d)/100 14.34
say 14.00
Note In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of 50 mm
by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm

Page 7 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 100 sqm
a) Labour
Mate day 0.010 151.44 1.51 L-12
Mazdoor day 0.250 136.69 34.17 L-13
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 282.50 22.60 P&M-055
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 806.00 161.20 P&M-017
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 339.00 77.97 P&M-048
c) Overhead charges @ 0.1 on (a+b) 29.75
d) Contractor's profit @ 0.1 on (a+b+c) 32.72
Cost for 100 sqm = a+b+c+d 359.92
Rate per sqm = (a+b+c+d)/100 3.60
say 4.00
3.16 305 Construction of Embankment with Material obtained from
Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor day 1.000 136.69 136.69 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 1302.00 2174.34 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 2.46 7864.80 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 786.48
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2395.00 2395.00 P&M-032
Water tanker6 KL capacity hour 4.000 200.00 800.00 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1541.00 1541.00 P&M-059
c) Material
Cost of water KL 24.000 10.00 240.00 M-189
Compensation for earth taken from private land cum 100.000 28.00 2800.00 M-092
d) Overhead charges @ 0.1 on (a+b+c) 2060.44
e) Contractor's profit @ 0.1 on (a+b+c+d) 2266.48
Cost for 100 cum = a+b+c+d+e 24931.28
Rate per cum = (a+b+c+d+e)/100 249.31
say 249.00
Note Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
3.17 305 Construction of Embankment with Material Deposited from
Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor day 0.500 136.69 68.35 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2395.00 2395.00 P&M-032
Water tanker6 KL capacity hour 4.000 200.00 800.00 P&M-060
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 1541.00 1541.00 P&M-059
c) Material
Cost of water KL 24.000 10.00 240.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 690.74
e) Contractor's profit @ 0.1 on (a+b+c+d) 759.81
Rate for 100 cum = a+b+c+d+e 8357.92
Rate per cum = (a+b+c+d+e)/100 83.58
say 84.00
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
3.18 305 Construction of Subgrade and Earthen Shoulders

Page 8 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-
2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor day 1.000 136.69 136.69 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 1302.00 2174.34 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 175xL 2.46 8602.13 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 860.21
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 2395.00 4790.00 P&M-032
Water tanker with 6 km lead hour 4.000 200.00 800.00 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1541.00 1926.25 P&M-059
c) Material
Cost of water KL 24.000 10.00 240.00 M-189
Compensation for earth taken from private land cum 100.000 28.00 2800.00 M-092
d) Overhead charges @ 0.1 on (a+b+c) 2419.57
e) Contractor's profit @ 0.1 on (a+b+c+d) 2661.52
Cost for 100 cum = a+b+c+d+e 29276.77
Rate per cum = (a+b+c+d+e)/100 292.77
say 293.00
3.19 305.3.4 Compacting Original Ground
Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mazdoor day 3.000 136.69 410.07 L-13
b) Machinery
Tractor with ripper attachment hour 9.000 282.50 2542.50 P&M-055
Motor grader for grading hour 6.000 2395.00 14370.00 P&M-032
Water tanker 6 KL capacity hour 4.000 200.00 800.00 P&M-060
Vibratory roller 8-10 tonne @ 80 cum/hour hour 7.500 1541.00 11557.50 P&M-059
c) Material
Cost of water KL 24.000 10.00 240.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2993.82
e) Contractor's profit @ 0.1 on (a+b+c+d) 3293.21
Cost for 600 cum = a+b+c+d+e 36225.27
Rate per cum = (a+b+c+d+e)/600 60.38
say 60.00
3.19 Case-II :Compacting original ground supporting embankment

Loosening, leveling and Compacting original ground


supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Table 300-2 for
embankment construction.
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Tractor with ripper attachment hour 6.000 282.50 1695.00 P&M-055
Vibratory road roller 8-10 tonne capacity hour 7.500 1541.00 11557.50 P&M-059
Water tanker6 KL capacity hour 4.000 200.00 800.00 P&M-060
c) Material
Cost of water KL 24.000 10.00 240.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 1457.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 1603.58
Cost for 600 cum = (a+b+c+d+e) 17639.37
Rate per sqm = (a+b+c+d+e)/600 29.40
say 29.00
3.20 305 Stripping and Storing Top Soil

Page 9 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 151.44 30.29 L-12
Mazdoor day 5.000 136.69 683.45 L-13
b) Machinery
Dozer 80 HP @ 100 cum per hour hour 0.100 3720.00 372.00 P&M-014
c) Overhead charges @ 0.1 on (a+b) 108.57
d) Contractor's profit @ 0.1 on (a+b+c) 119.43
Cost for 10 cum = (a+b+c+d) 1313.74
Rate per cum = (a+b+c+d)/10 131.37
say 131.00
3.21 Stripping, Storing and Re-laying Top Soil from Borrow Areas
in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Dozer, 80 HP hour 6.000 3720.00 22320.00 P&M-014
c) Overhead charges @ 0.1 on (a+b) 2260.55
d) Contractor's profit @ 0.1 on (a+b+c) 2486.60
Cost for 300 cum = (a+b+c+d) 27352.65
Rate per cum = (a+b+c+d)/300 91.18
say 91.00
3.22 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mazdoor for preparation of ground and fetching of sods day 3.000 136.69 410.07 L-13

b) Machinery
Water tanker including watering for 3 months hour 2.000 200.00 400.00 P&M-060
Tractor-trolley hour 1.000 282.50 282.50 P&M-053
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 364.00 65.52 M-167
work
Cost of water KL 12.000 10.00 120.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 129.63
e) Contractor's profit @ 0.1 on (a+b+c+d) 142.59
Cost for 100 sqm = a+b+c+d+e 1568.48
Rate per 100 sqm = (a+b+c+d+e)/100 15.68
say 16.00
3.23 308 Seeding and Mulching
Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 151.44 60.58 L-12
Mazdoor day 10.000 136.69 1366.90 L-13
b) Machinery
Water tanker 6 KL capacity including watering for 3 hour 14.000 200.00 2800.00 P&M-060
months
Tractor-trolley hour 2.400 282.50 678.00 P&M-053
c) Material
Seeds kg 3.600 243.00 874.80 M-162
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 364.00 156.52 M-167
Bitumen Emulsion litre 55.200 49.92 2755.31 M-077
Jute netting, open weave, 2.5 cm square opening sqm 264.000 61.00 16104.00 M-121
Cost of water for 3 months KL 84.000 10.00 840.00 M-189

Page 10 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overhead charges @ 0.1 on (a+b+c) 2563.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 2819.97
Cost for 240 sqm = a+b+c+d+e 31019.69
Rate per sqm = (a+b+c+d+e)/240 129.25
say 129.00
3.24 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.010 151.44 1.51 L-12
Mazdoor for dressing of bed and side of drain day 0.250 136.69 34.17 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30 hour 0.330 1302.00 429.66 P&M-026
metres per hour
c) Overhead charges @ 0.1 on (a+b) 46.53
d) Contractor's profit @ 0.1 on (a+b+c) 51.19
Cost for 10 metres = a+b+c+d 563.07
Rate per metre = (a+b+c+d)/10 56.31
say 56.00
3.24 B Manual Means
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Overhead charges @ 0.1 on (a) 28.55
c) Contractor's profit @ 0.1 on (a+b) 31.40
Cost for 10 metres = a+b+c 345.45
Rate per metre = (a+b+c)/10 34.54
say 35.00
Note Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
3.25 309 Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankment at site.
Unit = metre
Taking output = 10 metres
A Mechanical Means
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor for dressing of bed and side of drain day 0.500 136.69 68.35 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 15 hour 0.670 1302.00 872.34 P&M-026
metres per hour
c) Overhead charges @ 0.1 on (a+b) 94.37
d) Contractor's profit @ 0.1 on (a+b+c) 103.81
Cost for 10 metres = a+b+c+d 1141.89
Rate per metre = (a+b+c+d)/10 114.19
say 114.00
3.25 B Manual Means
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mazdoor day 3.000 136.69 410.07 L-13
b) Overhead charges @ 0.1 on (a) 42.82
c) Contractor's profit @ 0.1 on (a+b) 47.11
Cost for 10 metres = a+b+c 518.17
Rate per metre = (a+b+c)/10 51.82
say 52.00
3.26 309 Surface Drains in Hard Rock
Rate per metre may be worked out based on quantity of
hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
3.27 309 Sub-Surface Drains with Perforated Pipe

Page 11 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of subsurface drain with perforated pipe of 100
mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.

Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor for excavation and back filling day 2.000 136.69 273.38 L-13
c) Material
Perforated pipe of cement concrete, internal dia 100 metre 10.000 243.00 2430.00 M-135
mm
Crushed stone as per table 300-3 cum 2.400 894.00 2145.60 M-012
d) Overhead charges @ 0.1 on (a+b+c) 485.50
e) Contractor's profit @ 0.1 on (a+b+c+d) 534.05
Cost for 10 metres = a+b+c+d+e 5874.60
Rate per metre = (a+b+c+d+e)/10 587.46
say 587.00
Note Type of pipe may be modified depending upon provision in
design.
3.28 309 Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor for excavation and back filling with aggregates day 1.500 136.69 205.04 L-13

b) Material
Crushed stone as per table 300-3 cum 1.350 894.00 1206.90 M-012
c) Overhead charges @ 0.1 on (a+b) 141.50
d) Contractor's profit @ 0.1 on (a+b+c) 155.65
Cost for 10 metres = a+b+c+d 1712.11
Rate per metre = (a+b+c+d)/10 171.21
say 171.00
3.29 309 Underground Drain at Edge of Pavement
Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil cum 1.500 36.00 54.00 Item No.
3.13
b) RCC work M-20 cum 0.495 4650.00 2301.75 Item 12.8
(C) RCC
Rate per metre = (a+b) 2355.75
Rates for these items may be taken from chapters on earth say 2356.00
work and substructures respectively.
3.30 310 Preparation and Surface Treatment of Formation.
Preparation and surface treatment of formation by removing
mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a) Labour
Mate day 0.280 151.44 42.40 L-12
Mazdoor day 6.000 136.69 820.14 L-13
Mazdoor skilled day 1.000 164.69 164.69 L-15
b) Machinery
Smooth 3 wheeled steel roller 8-10 tonnes hour 3.000 460.00 1380.00 P&M-044
Water tanker 6 KL, one trip per hour hour 3.000 200.00 600.00 P&M-060
c) Material
Cost of water KL 18.000 10.00 180.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 318.72
e) Contractor's profit @ 0.1 on (a+b+c+d) 350.60
Cost for 3500 sqm = a+b+c+d+e 3856.55
Rate per sqm = (a+b+c+d+e)/3500 1.10
say 1.00
3.31 313 Construction of Rock fill Embankment

Page 12 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor day 1.500 136.69 205.04 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3720.00 1860.00 P&M-014
Vibratory road roller 8-10 tonnes @ 100 cum per hour hour 1.000 1541.00 1541.00 P&M-059

Water tanker 6 KL, one trip per hour hour 2.000 200.00 400.00 P&M-060
c) Material
Cost of water KL 12.000 10.00 120.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 413.21
e) Contractor's profit @ 0.1 on (a+b+c+d) 454.53
Cost for 100 cum = a+b+c+d+e 4999.83
Rate per cum = (a+b+c+d+e)/100 50.00
say 50.00
Note It is assumed that rock is available locally at site from
roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD
3.32 301 Excavation in Hill Area in Soil by Mechanical Means
Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor for trimming slopes and helping in excavation day 6.000 136.69 820.14 L-13
etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour hour 6.000 3720.00 22320.00 P&M-014
Front end loader hour 6.000 806.00 4836.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 12.000 339.00 4068.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 3208.05
d) Contractor's profit @ 0.1 on (a+b+c) 3528.85
Cost for 260 cum = a+b+c+d 38817.39
Rate per cum = (a+b+c+d)/260 149.30
say 149.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.

3.33 301 Excavation in Hilly Area in Ordinary Rock by Mechanical


Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 151.44 48.46 L-12
Mazdoor day 8.000 136.69 1093.52 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3720.00 22320.00 P&M-014
Front end loader hour 7.000 806.00 5642.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 339.00 2373.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 3147.70
d) Contractor's profit @ 0.1 on (a+b+c) 3462.47
Cost for 170 cum = a+b+c+d 38087.15
Rate per cum = (a+b+c+d)/170 224.04
say 224.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

3.34 301 Excavation in Hilly Areas in Hard Rock Requiring Blasting

Page 13 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.

Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 151.44 74.21 L-12
Mazdoor day 10.000 136.69 1366.90 L-13
Driller day 2.000 264.50 529.00 L-06
Blaster day 0.250 264.50 66.13 L-03
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3720.00 22320.00 P&M-014
Air compressor 250 cfm with two jack hammer @ 20 hour 5.000 319.00 1595.00 P&M-001
cum per hour
Front end loader hour 7.000 806.00 5642.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 339.00 2373.00 P&M-048
c) Materials
Gelatine 80 per cent kg 35.000 146.00 5110.00 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 140.000 14.56 2038.40 M-094 /100
of 125 gms each
d) Overhead charges @ 0.1 on (a+b+c) 4111.46
e) Contractor's profit @ 0.1 on (a+b+c+d) 4522.61
Cost for 170 cum = a+b+c+d+e 49748.70
Rate per cum = (a+b+c+d+e)/170 292.64
say 293.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.
3.35 Work in Urban Roads
The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:
a) There is mixed traffic on urban roads like slow moving
hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be
in the range of 10 -15 per cent
b) There is considerable disruption of traffic adversely
affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.

c) Cost of living in urban areas is comparatively more


resulting into higher wages.
d) At times, work is executed during night time due to
heavy traffic during day time. This involves extra expenditure
by way of making arrangement for lighting and special
transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing
the cost estimates may exercise their judgment and cater for
the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting
details for the extra cost based on the actual conditions in
specific cases will have to give in justification.
3.36 Suggesti Embankment Construction with Flyash/Pond ash available
ve from coal or lignite burning Thermal Plants as waste
material.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoor day 4.000 136.69 546.76 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 1302.00 7812.00 P&M-026
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 2.46 56272.64 Lead =53
km & P&M-
058
Add 10 per cent of cost of carriagefor loading and 5627.26
unloading

Page 14 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 3720.00 6696.00 P&M-014
Motor Grader for grading @ 100 cum/hour hour 3.600 2395.00 8622.00 P&M-032
Water tanker6 KL capacity hour 12.000 200.00 2400.00 P&M-060
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 1541.00 5547.60 P&M-059
c) Overhead charges @ 0.1 on (a+b) 9354.85
d) Contractor's profit @ 0.1 on (a+b+c) 10290.33
Cost for 360 cum = a+b+c+d 113193.68
Rate per cum = (a+b+c+d)/360 314.43
say 314.00
Note 1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

Page 15 of 264
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:- 400-1)

A Plant Mix Method


Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 151.44 60.58 L-12
Mazdoor skilled day 2.000 164.69 329.38 L-15
Mazdoor day 8.000 136.69 1093.52 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 2195.03 13170.15 P&M-093
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Water tanker 6 KL capacity 5 km lead with one trip per hour 4.500 200.00 900.00 P&M-060
hour
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover loading and 110.60
unloading
Motor Grader 110 HP hour 6.000 2395.00 14370.00 P&M-032
Vibratory roller 8-10 t hour 6.000 1541.00 9246.00 P&M-059
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 144.000 867.00 124848.00 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 57.000 867.00 49419.00 M-017
2.36 mm below @ 30 per cent cum 86.400 867.00 74908.80 M-020
Cost of water KL 27.000 10.00 270.00 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 867.00 87393.60 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 72.000 867.00 62424.00 M-017
2.36 mm below @ 40 per cent cum 115.200 867.00 99878.40 M-020
Cost of water KL 27.000 10.00 270.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 100.800 867.00 87393.60 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 36.000 867.00 31212.00 M-018
2.36 mm below @ 52.5 per cent cum 151.200 867.00 131090.40 M-020
Cost of water KL 27.000 10.00 270.00 M-189
4.1A (i) Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c) 29858.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 32843.80
Cost for 225 cum = a+b+c+d+e 361281.81
Rate per cum = (a+b+c+d+e)/225 1605.70
say 1606.00
4.1A (ii) Rate per cum for grading-II Material
d) Overhead charges @ 0.1 on (a+b+c) 29910.02
e) Contractor's profit @ 0.1 on (a+b+c+d) 32901.02
Cost for 225 cum = a+b+c+d+e 361911.26
Rate per cum = (a+b+c+d+e)/225 1608.49
say 1608.00
4.1A (iii) Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c) 29910.02
e) Contractor's profit @ 0.1 on (a+b+c+d) 32901.02
Cost for 225 cum = a+b+c+d+e 361911.26
Rate per cum = (a+b+c+d+e)/225 1608.49
say 1608.00

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note Any one of the grading for material may be adopted as per
design

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 151.44 72.69 L-12
Mazdoor skilled day 2.000 164.69 329.38 L-15
Mazdoor unskilled day 10.000 136.69 1366.90 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 2395.00 14370.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1541.00 9246.00 P&M-059
Tractor - Rotavator hour 12.000 0.00 0.00 P&M-054
Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 384.000 836.17 321089.28 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 0.000 836.17 0.00 M-017
2.36 mm below @ 30 per cent cum 0.000 836.17 0.00 M-020
Cost of water KL 18.000 10.00 180.00 M-189
OR
4.1B (i) Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c) 34725.43
e) Contractor's profit @ 0.1 on (a+b+c+d) 38197.97
Cost for 300 cum = a+b+c+d+e 420177.64
Rate per cum = (a+b+c+d+e)/300 1400.59
Add 1 % labour Cess 14.01
1414.60
say 1414.60
4.1B (ii) Rate per cum for grading-II Material
d) Overhead charges @ 0.1 on (a+b+c) 35139.78
e) Contractor's profit @ 0.1 on (a+b+c+d) 38653.76
Cost for 300 cum = a+b+c+d+e 425191.34
Rate per cum = (a+b+c+d+e)/300 1417.30
Add 1 % labour Cess 14.17
1431.48
say 1431.48
4.1B (iii) Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c) 35287.76
e) Contractor's profit @ 0.1 on (a+b+c+d) 38816.54
Cost for 300 cum = a+b+c+d+e 426981.95
Rate per cum = (a+b+c+d+e)/300 1423.27
Add 1 % labour Cess 14.23
1437.51
say 1437.51
Note Any one of the grading for material may be adopted as per
design

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.2 401 Granular Sub-Base with Coarse Graded Material (Table:- 400-
2)
Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 151.44 60.58 L-12
Mazdoor skilled day 2.000 164.69 329.38 L-15
Mazdoor day 8.000 136.69 1093.52 L-13
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 2395.00 14370.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1541.00 9246.00 P&M-059
Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060
c) Material
For coarse graded Granular sub-base Materials per table 400-
2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 134.400 867.00 116524.80 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 867.00 149817.60 M-026
2.36 mm below @ 20 per cent (Coarse Sand) cum 76.800 992.30 76208.64 M-022
Cost of water KL 18.000 10.00 180.00 M-189
OR
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 867.00 249696.00 M-026
2.36 mm below @ 25 per cent cum 96.000 992.30 95260.80 M-022
Cost of water KL 18.000 10.00 180.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 66 per cent cum 255.000 867.00 221085.00 M-025
2.36 mm below @ 34 per cent cum 129.000 992.30 128006.70 M-022
Cost of water KL 18.000 10.00 180.00 M-189
4.2 (i) Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c) 36843.05
e) Contractor's profit @ 0.1 on (a+b+c+d) 40527.36
Cost for 300 cum = a+b+c+d+e 445800.92
Rate per cum = (a+b+c+d+e)/300 1486.00
say 1486.00
4.2 (ii) Rate per cum for grading-II Material
d) Overhead charges @ 0.1 on (a+b+c) 37083.63
e) Contractor's profit @ 0.1 on (a+b+c+d) 40791.99
Cost for 300 cum = a+b+c+d+e 448711.89
Rate per cum = (a+b+c+d+e)/300 1495.71
say 1496.00
4.2 (iii) Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c) 37497.12
e) Contractor's profit @ 0.1 on (a+b+c+d) 41246.83
Cost for 300 cum = a+b+c+d+e 453715.12
Rate per cum = (a+b+c+d+e)/300 1512.38
say 1512.00
Note Any one of the grading for material may be adopted as per
design

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.12 406 Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.

Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 151.44 72.69 L-12
Mazdoor skilled day 2.000 164.69 329.38 L-15
Mazdoor day 10.000 136.69 1366.90 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 9.000 2195.03 19755.23 P&M-094
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017
Paver finisher hour 6.000 975.00 5850.00 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 1541.00 6009.90 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060
Tipper tonne.km 495 x L 2.46 1216.59 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 121.66
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 1007.77 89792.31 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 1011.94 120218.47 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 992.30 88413.93 M-022
Cost of water KL 18.000 10.00 180.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 34267.51
e) Contractor's profit @ 0.1 on (a+b+c+d) 37694.26
Cost for 225 cum = a+b+c+d+e 414636.81
Rate per cum = (a+b+c+d+e)/225 1842.83
Add 1 % labour Cess 18.43
1861.26
say 1861.26
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..
4.13 407 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 200.00 200.00 P&M-060

Page 5 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Plate compactor @ 3.5 cum per hour hour 6.000 101.70 610.20 P&M-086
c) Material
Cost of water KL 6.000 10.00 60.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 172.67
e) Contractor's profit @ 0.1 on (a+b+c+d) 189.94
Cost for 21 cum = a+b+c+d+e 2089.29
Rate per cum = (a+b+c+d+e)/21 99.49
say 99.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.

4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoor day 4.000 136.69 546.76 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 200.00 200.00 P&M-060
Plate Compactor @ 3.5 cum per hour hour 6.000 101.70 610.20 P&M-086
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 1302.00 651.00 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 2.46 2580.64 Lead =20
km & P&M-
058
Add 10 per cent of cost of transportation to cover cost 258.06
of loading and unloading
c) Material
Cost of water KL 6.000 10.00 60.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 493.09
e) Contractor's profit @ 0.1 on (a+b+c+d) 542.40
Cost for 21 cum = a+b+c+d+e 5966.38
Rate per cum = (a+b+c+d+e)/ 21 284.11
say 284.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
4.15 Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.
4.16 409 Footpaths and Separators

Page 6 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 151.44 205.96 L-12
Mason day 4.000 223.36 893.44 L-11
Mazdoor day 30.000 136.69 4100.70 L-13
b) Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 1541.00 1155.75 P&M-059
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 200.00 400.00 P&M-060
Concrete mixer 0.4/0.28 cum per hour hour 6.000 233.00 1398.00 P&M-009
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 867.00 18024.93 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 867.00 23174.91 M-026
2.36 mm below @ 20 per cent cum 11.880 867.00 10299.96 M-022
ii) For cement concrete grade M157.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 1028.00 6939.00 M-052
Sand @ 0.45 cum/cum of concrete cum 3.380 710.46 2401.35 M-005
Cement tonne 1.880 5000.00 9400.00 M-081
iii) For cement plaster 1:3
Sand cum 3.840 710.46 2728.17 M-005
Cement tonne 1.830 5000.00 9150.00 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 15.00 49500.00 M-184
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 243.00 5467.50 M-137
vi) Cost of water KL 12.000 10.00 120.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 14535.97
e) Contractor's profit @ 0.1 on (a+b+c+d) 15989.56
Cost for 300 sqm = a+b+c+d+e 175885.20
Rate per sqm = (a+b+c+d+e)/300 586.28
say 586.00
4.17 410 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base

Unit = cum
Taking output = 360 cum
A By Mix in Place Method
a) Labour
Mate day 0.480 151.44 72.69 L-12
Mazdoor skilled day 2.000 164.69 329.38 L-15
Mazdoor day 10.000 136.69 1366.90 L-13
b) Machinery
Tractor attached with rotavator @ 25 cum per hour hour 12.000 282.50 3390.00 P&M-054
Motor grader 110 HP hour 6.000 2395.00 14370.00 P&M-032
Vibratory roller 8 -10 tonnes @ 60 cum per hour hour 6.000 1541.00 9246.00 P&M-059
Water tanker 6 KL capacity hour 6.000 200.00 1200.00 P&M-060
c) Material
Aggregate at site
i) For 53 mm maximum size

Page 7 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
63 mm to 45 mm @ 33 per cent cum 157.460 949.00 149429.54 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 151.060 1000.67 151160.71 M-032
Below 5.6 mm @ 35 per cent cum 166.680 1066.89 177829.23 M-030
Cost of water KL 36.000 10.00 360.00 M-189
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 24.120 920.50 22202.46 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 237.600 1000.67 237758.40 M-032
Below 5.6 mm@ 45 per cent cum 213.480 1066.89 227759.68 M-030
Cost of water KL 36.000 10.00 360.00 M-189
4.17A (i) For 53 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 50875.44
e) Contractor's profit @ 0.1 on (a+b+c+d) 55962.99
Cost for 360.0cum = a+b+c+d+e 615592.88
Rate per cum = (a+b+c+d+e)/360 1709.98
or say 1710.00
4.17A (ii) For 45 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 51805.55
e) Contractor's profit @ 0.1 on (a+b+c+d) 56986.11
Cost for 360.0cum = a+b+c+d+e 626847.17
Rate per cum = (a+b+c+d+e)/360 1741.24
say 1741.00
Note Any one of the aggregate grading may be adopted
4.17 B By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a) Labour
Mate day 0.280 151.44 42.40 L-12
Mazdoor skilled day 1.000 164.69 164.69 L-15
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Wet mix plant @ 75 tonne per hour hour 6.000 2195.03 13170.15 P&M-093
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Motor grader 110 HP hour 6.000 2395.00 14370.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1541.00 9246.00 P&M-059
Water tanker 6 KL capacity hour 3.000 200.00 600.00 P&M-060
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 110.60
loading and unloading
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 98.400 949.00 93381.60 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 94.410 1000.67 94472.94 M-032
Below 5.6 mm @ 35 per cent cum 104.180 1066.89 111148.60 M-030
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 15.060 920.50 13862.73 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 148.500 1000.67 148599.00 M-032
Below 5.6 mm@ 45 per cent cum 133.430 1066.89 142355.13 M-030
Cost of water KL 18.000 10.00 180.00 M-189
4.17 B (i) For 53 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 34738.11
e) Contractor's profit @ 0.1 on (a+b+c+d) 38211.92

Page 8 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 225cum = a+b+c+d+e 420331.14
Rate per cum = (a+b+c+d+e)/225 1868.14
say 1868.00
4.17 B (ii) For 45 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 35337.48
e) Contractor's profit @ 0.1 on (a+b+c+d) 38871.23
Cost for 360.0cum = a+b+c+d+e 427583.55
Rate per cum = (a+b+c+d+e)/360 1187.73
say 1188.00
4.18 Suggesti Lime, Flyash Stabilised Soil Sub-Base
ve
Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as per clause 4.3 of
IRC: 88-1984, lime + Flyash content ranging between 10 to 30
per cent, the minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25 per cent respectively, all as specified in
IRC: 88-1984.

Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50 t/cum)

Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
Mazdoor (Skilled) day 1.000 164.69 164.69 L-15
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ hour 6.000 1302.00 7812.00 P&M-026
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes tonne.km 576 x L 2.46 28411.59 Lead =20
km & P&M-
058
Tipper 10T capacity for carriage of 115 tonnes Flyash tonne.km 115 x L 2.46 14979.99 Lead =53
km & P&M-
058
Tipper 10T capacity for carriage of 29 tonnes of lime hour 3.000 339.00 1017.00 P&M-048
from store to work site
Add 10 per cent of cost of carriage to cover cost of 101.70
loading and unloading
Tractor with disc harrows for pulverisation hour 6.000 282.50 1695.00 P&M-053
Motor Grader 110 HP @ 50 cum per hour for mixing in- hour 9.600 2395.00 22992.00 P&M-032
place and grading
Vibratory roller 8 - 10 tonne hour 6.000 1541.00 9246.00 P&M-059
Water tanker 6 KL capacity hour 12.000 200.00 2400.00 P&M-060
c) Material
Slaked Lime tonne 29.000 4500.00 130500.00 M-188
Compensation for earth taken from private source cum 360.000 28.00 10080.00 M-092
d) Overhead charges @ 0.1 on (a+b+c) 23025.65
e) Contractor's profit @ 0.1 on (a+b+c+d) 25328.21
Cost for 480 cum = a+b+c+d+e 278610.31

Page 9 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum= (a+b+c+d+e)/480 580.44
say 580.00
Note 1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
3.Lime + Flyash has been taken as 20 per cent of total mass
and ratio of lime and Flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

Page 10 of 264
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.1 502 Prime Coat
Providing and applying primer coat with bitumen emulsion
on prepared surface of granular Base including clearing of
road surface and spraying primer at the rate of 0.85 kg/sqm
using mechanical means.

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 357.00 999.60 P&M-031
Air compressor 250 cfm hour 2.800 319.00 893.20 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 1073.00 2146.00 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 200.00 200.00 P&M-060
c) Material
Bitumen emulsion @ 0.85 kg per sqm tonne 2.975 47937.00 142612.58 M-077
Cost of water KL 6.000 10.00 60.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 14719.69
e) Contractor's profit @ 0.1 on (a+b+c+d) 16191.66
Cost for 3500 sqm = a+b+c+d+e 178108.21
Rate per sqm = (a+b+c+d+e)/3500 50.89
Add 1 % labour Cess 0.51
51.40
say 51.40
Note Bitumen primer has been provided @ 0.850 kg per sqm as
per clause 502.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.2 503 Tack Coat
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.20 kg per
sqm on the prepared bituminous/granular surface cleaned
with mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 357.00 999.60 P&M-031
Air compressor 250 cfm hour 2.800 319.00 893.20 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 1073.00 2146.00 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 49915.00 43675.63 M-077
d) Overhead charges @ 0.1 on (a+b+c) 4799.99
e) Contractor's profit @ 0.1 on (a+b+c+d) 5279.99
Cost for 3500 sqm = a+b+c+d+e 58079.90
Rate per sqm = (a+b+c+d+e)/3500 16.59
Add 1 % labour Cess 0.17
16.76
say 16.76
Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.3 504 Bituminous Macadam
Providing and laying bituminous macadam with 100-120
TPH hot mix plant producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading
premixed with bituminous binder, transported to site, laid
over a previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction

Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 136.69 2187.04 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 23405.00 140430.00 P&M-021
actual output
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 357.00 785.40 P&M-031
Air compressor 250 cfm hour 2.200 319.00 701.80 P&M-001
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2674.00 16044.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 460.00 1794.00 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1144.00 4461.60 P&M-045
roller.
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.850 55132.00 818710.20 M-074
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 1011.94 44029.51 M-049
25 - 10 mm 45 per cent cum 130.550 1103.60 144074.98 M-046
10 - 5 mm 25 per cent cum 72.530 1078.94 78255.52 M-040
5 mm and below15 per cent cum 43.510 992.30 43174.97 M-030
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 1103.60 128061.74 M-046
10 - 5 mm 40 per cent cum 116.040 1078.94 125200.20 M-040
5 mm and below 20 per cent cum 58.020 992.30 57573.25 M-030
* Any one of the alternative may be adopted as per
approved design
(i) for Grading I ( 40 mm nominal size )
d) Overhead charges @ 0.1 on (a+b+c) 131910.34
e) Contractor's profit @ 0.1 on (a+b+c+d) 145101.38
Cost for 205 cum = a+b+c+d+e 1596115.13
Rate per cum = (a+b+c+d+e)/205 (For Grading I) 7785.93
Add 1 % labour Cess 77.86
7863.79
say 7863.79
(ii) for GradingII(19 mm nominal size)
d) Overhead charges @ 0.1 on (a+b+c) 132040.36
e) Contractor's profit @ 0.1 on (a+b+c+d) 145244.40
Cost for 205 cum = a+b+c+d+e 1597688.38

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e)/205 (For Grading-II) 7793.60
Add 1 % labour Cess 77.94
7871.54
say 7871.54

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of
Mechanical broom and 2 mazdoors for the same shall be
deleted as the same has been included in the cost of tack
coat.
5.4 505 Bituminous Penetration Macadam
Construction of penetration macadam over prepared Base
by providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of
bituminous binder and key aggregates and rolling with a
smooth wheeled steel roller 8-10 tonne capacity to achieve
the desired degree of compaction
A 50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour
Mate day 0.320 151.44 48.46 L-12
Mazdoor including for brooming of key aggregates day 6.000 136.69 820.14 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2635.00 15810.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm = 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour hour 2.570 1073.00 2757.61 P&M-004

Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 339.00 3390.00 P&M-048
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1541.00 9246.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
c) Material
Bitumen@ 5 kg per sqm tonne 22.500 55132.00 1240470.00 M-074
Crushed stone coarse aggregate passing 45 mm and cum 270.000 968.60 261522.00 M-033
retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8 cum 67.500 1000.67 67545.00 M-031
mm sieve @ 0.015 cum per sqm
d) Overhead charges @ 0.1 on (a+b+c) 160677.46

Page 5 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 176745.20
Cost for 4500 sqm = a+b+c+d+e 1944197.25
Rate per sqm = (a+b+c+d+e)/4500 432.04
say 432.00
Note 2 tippers will be needed to match the capacity of chip
spreader and front end loader.
5.4 B 75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour
Mate day 0.400 151.44 60.58 L-12
Mazdoor including for brooming of key aggregates day 8.000 136.69 1093.52 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2635.00 15810.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm
Bitumen pressure distributor for@ 1750 sqm per hour hour 2.570 1073.00 2757.61 P&M-004

Tipper 5.5 cum capacity for carriage of aggregates hour 10.000 339.00 3390.00 P&M-048
from stockpile to chip spreader
Vibratory roller 8 tonnes hour 6.000 1541.00 9246.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
c) Material
Bitumen@ 6.8 kg per sqm tonne 30.600 55132.00 1687039.20 M-074
Crushed stone coarse aggregate (loose passing 63 cum 405.000 982.00 397710.00 M-037
mm and retained on 2.8 mm sieve @ 0.09 cum per
sqm
Key aggregates passing 26.5 mm and retained on 2.8 cum 81.000 867.00 70227.00 M-026
mm sieve @ 0.018 cum per sqm
d) Overhead charges @ 0.1 on (a+b+c) 219249.93
e) Contractor's profit @ 0.1 on (a+b+c+d) 241174.92
Cost for 4500 sqm = a+b+c+d+e 2652924.14
Rate per sqm = (a+b+c+d+e)/4500 589.54
say 590.00
Note 2 tippers and 2 rollers will be needed to match the capacity
of chip spreader and front end loader.
5.5 506 Built-up-Spray Grout
Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may
be used with application of bituminous binder after each
layer, and with key aggregates placed on top of the second
layer to serve as a Base conforming to the line, grades and
cross-section specified, the compacted layer thickness being
75 mm

Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate day 0.400 151.44 60.58 L-12
Mazdoor including for brooming of key aggregates day 8.000 136.69 1093.52 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Hydraulic self propelled chip spreader both for hour 6.000 2635.00 15810.00 P&M-025
aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm
Bitumen pressure distributor for 3000 x 2 sqm @ 1750 hour 3.430 1073.00 3680.39 P&M-004
sqm per hour
Tipper 5.5 cum capacity hour 10.000 339.00 3390.00 P&M-048
Vibratory roller 8 tonnes hour 6.000 1541.00 9246.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
c) Material
Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for tonne 9.000 55132.00 496188.00 M-074
each layer
Crushed stone coarse aggregate passing 53 mm and cum 300.000 990.25 297075.00 M-035
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer
Key aggregates passing 22.4 mm and retained on 2.8 cum 39.000 1000.67 39026.00 M-031
mm sieve @ 0.13 cum per 10 sqm
d) Overhead charges @ 0.1 on (a+b+c) 87073.49
Page 6 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 95780.84
Cost for 3000 sqm = a+b+c+d+e 1053589.19
Rate per sqm = (a+b+c+d+e)/3000 351.20
say 351.00
Note 2 tippers will be needed to match the capacity of hydraulic
chip spreader and front end loader.

Page 7 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.6 505 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam
with 100-120 TPH batch type HMP producing an average
output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 4.5
per cent by weight of total mix and filler, transporting the hot
mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification
clause No. 505 complete in all respects.

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 136.69 2187.04 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 13842.00 83052.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2674.00 16044.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 460.00 1794.00 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1144.00 4461.60 P&M-045
roller.
c) Materials
Bitumen @ 4.50 per cent of weight of mix tonne 20.250 56122.00 1136470.50 M-074
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450 -20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.50 cum
Grading - 2 26.5 mm (Nominal Size) 50-75 mm
25 - 10 mm 30 per cent cum 85.950 1103.60 94854.42 M-046
10 - 5 mm 28 per cent cum 80.220 1078.94 86552.57 M-040
5 mm and below 40 per cent cum 114.600 992.30 113717.58 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.595 4500.00 38677.50 M-188
* Any one of the alternative may be adopted as per
approved design
(i) For Grading 1 ( 37.5 mm nominal size ) 75-100 mm
d) Overhead charges @ 0.1 on (a+b+c) 159671.18
e) Contractor's profit @ 0.1 on (a+b+c+d) 175638.30
Cost for 205 cum = a+b+c+d+e 1932021.27
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 9907.80
Add 1 % labour Cess 99.08
10006.88
say 10006.88
(ii) For Grading 2 ( 26.5 mm nominal size) 50-75 mm
d) Overhead charges @ 0.1 on (a+b+c) 160226.56
e) Contractor's profit @ 0.1 on (a+b+c+d) 176249.22
Cost for 205 cum = a+b+c+d+e 1938741.38
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 9942.26
Add 1 % labour Cess 99.42
10041.69
say 10041.69

Page 8 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note *1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.

5. The individual density for each size of aggregates to be


used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.

6. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
5.7 508 Semi-Dense Bituminous Concrete
Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output
of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.5 to 5 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 508
complete in all respects

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 136.69 2187.04 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 17309.00 103854.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2674.00 16044.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 110.60
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 460.00 1794.00 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1144.00 4461.60 P&M-045
roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 55132.00 1116423.00 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1103.60 63236.28 M-044
10 - 5 mm 38 per cent cum 108.870 1078.94 117464.20 M-040

Page 9 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5 mm and below 40 per cent cum 114.600 992.30 113717.58 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 4500.00 38790.00 M-188
or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix tonne 22.500 55132.00 1240470.00 M-074
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1078.94 175273.80 M-040
4.75 and below@ 41 per cent cum 116.850 992.30 115950.26 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 4500.00 38790.00 M-188
*Any one of the alternative may be adopted as per
approved design
(i) for Grading I ( 13 mm nominal size )
d) Overhead charges @ 0.1 on (a+b+c) 160242.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 176266.87
Cost for 205 cum = a+b+c+d+e 1938935.57
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 9943.26
say 9943.00
5.7 (ii) for GradingII(10 mm nominal size)
d) Overhead charges @ 0.1 on (a+b+c) 172327.91
e) Contractor's profit @ 0.1 on (a+b+c+d) 189560.70
Cost for 205 cum = a+b+c+d+e 2085167.70
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 10693.17
say 10693.00
Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack coat, provision
of broom and 2 mazdoor shall be deleted as the same has
been included in the cost of tack coat.
5. The quantity of Bitumen to be adjusted as per job mix
formula.

Page 10 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.8 509 / 507 Bituminous Concrete

Providing and laying bituminous concrete with 100-120 TPH


batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 507
complete in all respects

Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 136.69 2187.04 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 13842.00 83052.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2674.00 16044.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 1906.88 11441.25 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 460.00 1794.00 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1541.00 6009.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1144.00 4461.60 P&M-045
roller.
c) Material
i) Bitumen@ 5.4 per cent of weight of mix tonne 24.300 56122.00 1363764.60 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 24.30 tonnes
Weight of aggregate = 450 -24.30 = 425.70 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 283.80 cum
* Grading - 1-19 mm (Nominal Size) 50 mm
20 - 10 mm 35 per cent cum 99.330 1103.60 109620.59 M-045
10 - 5 mm 23 per cent cum 65.274 1078.94 70426.73 M-040
5 mm and below 40 per cent cum 113.520 992.30 112645.90 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.514 4500.00 38313.00 M-188
or
Grading - 2-13.2 mm (Nominal Size) 30-40 mm
13.2 - 10 mm30 per cent cum 85.500 1103.60 94357.80 M-044
10 - 5 mm 25 per cent cum 71.250 1078.94 76874.48 M-040
5 mm and below43 per cent cum 122.550 992.30 121606.37 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 4500.00 38790.00 M-188
*Any one of the alternative may be adopted as per
approved design
(i) for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 0.1 on (a+b+c) 182676.38
e) Contractor's profit @ 0.1 on (a+b+c+d) 200944.02
Cost for 205 cum = a+b+c+d+e 2210384.26
Rate per cum = (a+b+c+d+e)/191 11572.69
Add 1 % labour Cess 115.73
11688.42
say 11688.42
5.8 (ii) for Grading-II(10 mm nominal size)
d) Overhead charges @ 0.1 on (a+b+c) 182738.63
e) Contractor's profit @ 0.1 on (a+b+c+d) 201012.49
Cost for 205 cum = a+b+c+d+e 2211137.39

Page 11 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 11576.64
Add 1 % labour Cess 115.77
11692.40
say 11692.40
Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers,
their usage rates have been multiplied by a factor of 0.65

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.

6. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
5.9 510 Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller

Unit = sqm
Taking output = 9000 sqm
Case -1 :-19 mm nominal chipping size
a) Labour
Mate day 0.440 151.44 66.63 L-12
Mazdoor day 9.000 136.69 1230.21 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 357.00 2570.40 P&M-031
Air compressor 250 cfm hour 7.200 319.00 2296.80 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2635.00 15810.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 339.00 2034.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Bitumen pressure distributor hour 6.000 1073.00 6438.00 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 460.00 2760.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 55132.00 595425.60 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 1028.00 138780.00 M-053
cum per sqm
d) Overhead charges @ 0.1 on (a+b+c) 77257.70
e) Contractor's profit @ 0.1 on (a+b+c+d) 84983.47
Cost for 9000 sqm = a+b+c+d+e 934818.20
Rate per sqm = (a+b+c+d+e)/9000 103.87
say 104.00
5.9 Case - II 13 mm nominal size chipping

a) Labour
Mate day 0.440 151.44 66.63 L-12
Mazdoor day 9.000 136.69 1230.21 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 357.00 2570.40 P&M-031
Air compressor 250 cfm hour 7.200 319.00 2296.80 P&M-001

Page 12 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2635.00 15810.00 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 339.00 2034.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1541.00 9246.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 55132.00 496188.00 M-074
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 1028.00 92520.00 M-052
cum per sqm
d) Overhead charges @ 0.1 on (a+b+c) 63356.54
e) Contractor's profit @ 0.1 on (a+b+c+d) 69692.20
Cost for 9000 sqm = a+b+c+d+e 766614.16
Rate per sqm = (a+b+c+d+e)/9000 85.18
say 85.00
Note 1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the same
as per the Ist coat mentioned above
5.10 511 Open - Graded Premix Surfacing
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or
cut-back or emulsion to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a
smooth wheeled roller 8-10 tonne capacity, finished to
required level and grades.

Unit = sqm
Taking output = 10250 sqm (205 cum)
(i) Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less than 75
tonnes/hour .
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 136.69 2187.04 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15
b) Machinery
i) Batch type HMP 75 tonne per hour hour 6.000 23405.00 140430.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 1906.88 11441.25 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2674.00 16044.00 P&M-034
iv) Smooth wheeled/tandom roller 8-10 tonnes weight hour 6.000 1144.00 6864.00 P&M-045

c) Material
Bitumen@ 14.60 kg per 10 sqm tonne 14.970 55132.00 825326.04 M-074
Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum 276.750 998.50 276334.88 M-043
cum per 10 sqm
d) Overhead charges @ 0.1 on (a+b+c) 128563.05
e) Contractor's profit @ 0.1 on (a+b+c+d) 141419.35
Cost for 10250 sqm = a+b+c+d+e 1555612.85
Rate per sqm = (a+b+c+d+e)/10250 151.77
say 152.00

Page 13 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note If a premix sand seal coat of 'B' type is proposed, the same
is required to be provided over the open graded premix
carpet immediately on the same day. As the same HMP and
other machines will be used for laying of premix sand seal
coat, out of 6 effective working hours, 4.00 hours may be
utilised for laying of premix carpet and balance 2.00 hours
for the seal coat. The rate for the premix sand seal coat
under clause 513 (case II) has been worked out accordingly
by utilising the HMP for 2.00 hours for the purpose of seal
coat. In case type 'A' seal coat is proposed, HMP can be
worked for six hours for the premix carpet as type 'A' seal
coat does not require the use of HMP.

5.10 (ii) Case - II: Open-Graded Premix Surfacing using cationic


Bitumen Emulsion
Unit = sqm
Taking output = 900 sqm (24.3 cum)
a) Labour
Mate day 0.800 151.44 121.15 L-12
Mazdoor day 18.000 136.69 2460.42 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6.000 233.00 1398.00 P&M-009
Smooth wheeled steel roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044
c) Material
Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm tonne 1.940 55145.00 106981.30 M-073
Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27 cum 24.300 998.50 24263.55 M-043
cum per 10 sqm
d) Overhead charges @ 0.1 on (a+b+c) 13831.38
e) Contractor's profit @ 0.1 on (a+b+c+d) 15214.52
Cost for 900 sqm = a+b+c+d+e 167359.70
Rate per sqm = (a+b+c+d+e)/900 185.96
say 186.00
5.11 512 Close Graded Premix Surfacing/Mixed Seal Surfacing

Case I Mechanical means using HMP of appropriate capacity not


less than 75 tonnes/hour.
Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of 11.2
mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b)
aggregates using penetration grade bitumen to the
required line, grade and level to serve as wearing course on
a previously prepared base, including mixing in a suitable
plant, laying and rolling with a Smooth wheeled roller 8-10
tonne capacity, and finishing to required level and grade.

Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor working with HMP, road sweeper, paver and day 16.000 136.69 2187.04 L-13
roller
Skilled mazdoor for checking line & levels day 5.000 164.69 823.45 L-15
b) Machinery
i) HMP of appropicate capacity. hour 6.000 23405.00 140430.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 1906.88 11441.25 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
v) Paver finisher hydrostatic with sensor attachment hour 6.000 2674.00 16044.00 P&M-034
iv) Smooth wheeled8-10 tonnes weight hour 6.000 460.00 2760.00 P&M-044
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm tonne 22.500 55132.00 1240470.00 M-074
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum 276.750 987.00 273152.25 M-041
cum per 10 sqm
or
Type - B

Page 14 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Bitumen @ 19 kg per 10 sqm tonne 19.480 55132.00 1073971.36 M-074
Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 276.750 1000.67 276934.50 M-042
0.27 cum per 10 sqm
d) Overhead charges @ 0.1 on (a+b+c) 169348.78
e) Contractor's profit @ 0.1 on (a+b+c+d) 186283.66
Cost for 10250 sqm = a+b+c+d+e 2049120.22
Rate per sqm = (a+b+c+d+e)/10250 199.91
say 200.00
* Any one of the alternative may be adopted
5.12 513 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
(i) Case - I : Type A
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 2635.00 15810.00 P&M-025
Tipper 5.5 cum capacity hour 6.000 339.00 2034.00 P&M-048
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004
Smooth wheeled roller 8 -10 tonne weight hour 6.000 460.00 2760.00 P&M-044
c) Material
Bitumen@ 9.80 kg per 10 sqm tonne 10.050 55132.00 554076.60 M-074
Crushed stone chipping of 6.7 mm size defined as 100 cum 92.250 969.00 89390.25 M-050
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ 0.1 on (a+b+c) 67620.13
e) Contractor's profit @ 0.1 on (a+b+c+d) 74382.15
Cost for 10250 sqm = a+b+c+d+e 818203.62
Rate per sqm = (a+b+c+d+e)/10250 79.82
say 80.00
Note Since seal coat is provided immediately over the bituminous
layers, mechanical broom for clearing has not been catered.

5.12 (ii) Case - II : Type B


Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using
crushed stone chipping 6.7 mm size and penetration
bitumen of suitable grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoor day 4.000 136.69 546.76 L-13
b) Machinery
HMP of 75 tonnes/hour. hour 2.000 17309.00 34618.00 P&M-022
Electric Generator Set 250 KVA hour 2.000 1906.88 3813.75 P&M-081
Front end loader 1 cum bucket capacity hour 2.000 806.00 1612.00 P&M-017
Tipper 10 tonne capacity tonne.km 104 x 'L' 2.46 255.61 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 25.56
and unloading
Paver finisher hydrostatic with sensor attachment hour 2.000 2674.00 5348.00 P&M-034
Smooth wheeled 8-10 tonnes capacity hour 2.000 460.00 920.00 P&M-044
c) Material
Bitumen@ 6.80 kg per 10 sqm tonne 5.340 55132.00 294404.88 M-074
Crushed stone chipping of 6.7 mm size defined as cum 47.160 969.00 45698.04 M-050
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.06 cum per 10 sqm
d) Overhead charges @ 0.1 on (a+b+c) 38726.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 42599.35
Cost for 7858 sqm = a+b+c+d+e 468592.86
Rate per sqm = (a+b+c+d+e)/7858 59.63

Page 15 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 60.00
Note Since seal coat is required to be provided over the premix
carpet on the same day, out of the 6 working hours of the
HMP, 4.00 hours are proposed to be utilised for the premix
carpet and the balance 2.00 hours for the seal coat. Hence
2.00 hours have been considered for this case. This may be
linked to rate analysis worked out under clause 511.

5.13 514 Supply of Stone Aggregates for Pavement Courses


Supply of stone aggregates from approved sources
conforming to the physical requirement, specified in the
respective specified clauses, including royalties, fees rents,
collection, transportation, stacking and testing and measured
in cum as per clause 514.5
Competitive market rates to be as certained. Alternatively,
rates for stone crushing given in chapter 1may be adopted, if
found economical. In case for supply of aggregates at site
are not available, nearest crusher site may be as certained.
Loading and un-loading charges and cost of carriage may
be added to these rates to arrive at the cost at site.

5.14 515 Mastic Asphalt


Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated
finegrained hard stone chipping of 13.2 mm nominal size at
the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed
into surface when the temperature of surfaces is not less
than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.

Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a density
of 2.3 tonnes/cum.-2 tonnes
a) Labour
Mate day 0.440 151.44 66.63 L-12
Mazdoor day 10.000 136.69 1366.90 L-13
Mazdoor skilled day 1.000 164.69 164.69 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 357.00 21.42 P&M-031
Air compressor 250 cfm hour 0.060 319.00 19.14 P&M-001
Mastic cooker 1 tonne capacity hour 6.000 62.00 372.00 P&M-030
Bitumen boiler 1500 litres capacity hour 6.000 198.00 1188.00 P&M-005
Tractor for towing and positioning of mastic cooker and hour 1.000 282.50 282.50 P&M-053
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with
coarse aggregates (based on mix design done by CRRI for a
specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight tonne 0.204 55132.00 11246.93 M-074
of mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on cum 0.390 476.80 185.95 M-021
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less tonne 0.360 4500.00 1620.00 M-188
than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cum 0.550 998.50 549.18 M-043
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for cum 0.018 1213.00 21.83 M-142
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight kg 0.500 55.00 27.50 M-074
= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg

d) Overhead charges @ 0.1 on (a+b+c) 1713.27


e) Contractor's profit @ 0.1 on (a+b+c+d) 1884.59
Cost for 35.00 sqm = a+b+c+d+e 20730.53
Rate per sqm = (a+b+c+d+e)/35 592.30

Page 16 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 592.00
Note 1.The rates for 50 mm & 40 mm thick layers may be worked
out on pro-rata basis.
2.Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.

Page 17 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.15 516 Slurry Seal
512 Providing and laying slurry seal consisting of a mixture of
fine aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
(i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Mechanical broom hour 6.000 357.00 2142.00 P&M-031
Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001
Mobile slurry seal equipment hour 6.000 1008.00 6048.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 339.00 2034.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1243.00 7458.00 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060
c) Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 tonne 19.360 49915.00 966354.40 M-077

Fine aggregate 4.75 mm and below 87 per cent of cum 102.080 1066.89 108908.13 M-030
total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5, = 153.12/1.5 = 102.08 cum
Filler (ordinary Portland Cement) @ 2 per cent of total tonne 3.520 5000.00 17600.00 M-188
mix = 80 x 2.2 x 0.02
Cost of water KL 12.000 10.00 120.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 111867.10
e) Contractor's profit @ 0.1 on (a+b+c+d) 123053.81
Cost for 16000 sqm = a+b+c+d+e 1353591.93
Rate per sqm = (a+b+c+d+e)/16000 84.60
Add 1 % labour Cess 0.85
85.45
say 85.45

Page 18 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.15 (ii) 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 151.44 30.29 L-12
Mazdoor day 5.000 136.69 683.45 L-13
b) Machinery
Mechanical broom hour 6.000 357.00 2142.00 P&M-031
Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001
Mobile slurry seal equipment hour 6.000 1008.00 6048.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 339.00 2034.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060
c) Material
Residual Binder @ 13 per cent of mix = 60 x 2.2 x tonne 17.160 49915.00 856541.40 M-077
0.13
Fine aggregate 3 mm and below 85 per cent of total cum 74.800 867.00 64851.60 M-022
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

Filler @ 2 per cent of total mix = 60x 2.2 x 0.02 tonne 2.640 4500.00 11880.00 M-188
Cost of water KL 12.000 10.00 120.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 95148.07
e) Contractor's profit @ 0.1 on (a+b+c+d) 104662.88
Cost for 30000 sqm = a+b+c+d+e 1151291.69
Rate per sqm = (a+b+c+d+e)/20000 57.56
say 58.00
5.15 (iii) 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 151.44 30.29 L-12
Mazdoor day 5.000 136.69 683.45 L-13
b) Machinery
Mechanical broom hour 6.000 357.00 2142.00 P&M-031
Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001
Mobile slurry seal equipment hour 6.000 1008.00 6048.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 339.00 2034.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060
c) Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 tonne 12.670 49915.00 632423.05 M-077

Fine aggregate 2.36 mm and below,82 per cent of cum 43.300 867.00 37541.10 M-022
total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density
1.5
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02 tonne 1.580 4500.00 7110.00 M-188
Cost of water KL 12.000 10.00 120.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 69528.19
e) Contractor's profit @ 0.1 on (a+b+c+d) 76481.01
Cost for 24000 sqm = a+b+c+d+e 841291.08
Rate per sqm = (a+b+c+d+e)/24000 35.05
say 35.00
Note 1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately

Page 19 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.16 517 Recycling of Bituminous Pavement with Central Recycling
Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the
required grade, level and thickness, all as specified in clause
517.

Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day 0.480 151.44 72.69 L-12
Mazdoor day 10.000 136.69 1366.90 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000 300.00 1800.00 P&M-069
Mechanical broom @ 1250 sqm per hour hour 1.280 357.00 456.96 P&M-031
Air compressor 250 cfm hour 1.280 319.00 408.32 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 0.910 1073.00 976.43 P&M-004
Hot mix plant 100-120 TPH producing an average of hour 3.000 23405.00 70215.00 P&M-021
75 tonnes per hour
Electric generator set 250 KVA hour 3.000 1906.88 5720.63 P&M-081
Front end loader 1.00 cum bucket capacity hour 3.000 806.00 2418.00 P&M-017
Tipper 5.5 cum capacity hour 18.000 339.00 6102.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 460.00 897.00 P&M-044
Vibratory roller 8 tonnes hour 3.00x0.65* 1541.00 3004.95 P&M-059
Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 1144.00 2230.80 P&M-045
c) Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 tonne 1.987 55132.00 109558.31 M-074
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 tonne 7.728 55132.00 426060.10 M-074
x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent

Weight of fresh mix = 276 x 0.70 = 193.2 tonne


Weight of fresh aggregate in the mix = 193.2 x 0.96 =
185.47 tonne
Taking average density of 1.5 tonnes/cum, total volume of
aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent cum 28.440 1011.94 28779.57 M-049
25 - 10 mm @ 15 per cent cum 18.550 1103.60 20471.78 M-046
10- 5 mm @ 20 per cent cum 24.730 1078.94 26682.19 M-040
Below 5 mm @40 per cent cum 49.460 992.30 49079.16 M-030
Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne tonne 5.520 5000.00 27600.00 M-081

d) Overhead charges @ 0.1 on (a+b+c) 78423.02


e) Contractor's profit @ 0.1 on (a+b+c+d) 86265.32
Cost for 120 cum of DBM = a+b+c+d+e 948918.49
Rate per cum = (a+b+c+d+e)/120 7907.65
say 7908.00
Note Although the total rolling time is only 4 hours as per norms,
all the three rollers have to be available at site for 3 hours
each to match with the output of re-cycling plant. To cater for
their idling time, these have been multiplied with a factor of
0.65.
5.17 518 Fog Spray
Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.

Page 20 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mazdoor day 3.000 136.69 410.07 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031
Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001
Bitumen emulsion pressure distributor @ 1750 sqm per tonne 6.000 1073.00 6438.00 P&M-004
hour
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 49915.00 393330.20 M-077
d) Overhead charges @ 0.1 on (a+b+c) 40425.24
e) Contractor's profit @ 0.1 on (a+b+c+d) 44467.77
Cost for 10500 sqm = a+b+c+d+e 489145.46
Rate per sqm = (a+b+c+d+e)/10500 46.59
say 47.00
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoor for precoating of grit day 4.000 136.69 546.76 L-13
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 867.00 22758.75 M-024
Bitumen emulsion for precoating grit @ 2 per cent of tonne 0.790 49915.00 39432.85 M-077
grit,39.38 x 0.02
62762.59
5.98
say 6.00
5.18 519 Bituminous Cold Mix ( Including Gravel Emulsion)
Providing, laying and rolling of bituminous cold mix on
prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including
mixing in a plant of suitable type and capacity, transporting,
laying, compacting and finishing to specified grades and
levels.
Unit = cum
Taking output = 205 cum (450 tonne)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as under:-

Bitumen Emulsion 8 per cent By weight


of total mix
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor day 16.000 136.69 2187.04 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Drum mix plant for cold mixes of appropriate capacity hour 6.000 3661.20 21967.20 P&M-077
but not less than 75 tonnes/hour.
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Paver finisher hour 6.000 2674.00 16044.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1243.00 4847.70 P&M-037
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 49915.00 1796940.00 M-077
Page 21 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188
Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5 cum 75.000 1103.60 82770.00 M-045
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000 1078.94 93867.78 M-040
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 992.30 107168.40 M-030
d) Overhead charges @ 0.1 on (a+b+c) 218166.90
e) Contractor's profit @ 0.1 on (a+b+c+d) 239983.59
Cost for 205 cum = a+b+c+d+e 2639819.45
Rate per cum = (a+b+c+d+e)/205 12877.17
say 12877.00
(Applicable to cases I to IV)
Note 1.Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
5.18 (ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal
size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor day 16.000 136.69 2187.04 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 3661.20 21967.20 P&M-077
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Paver finisher hour 6.000 2674.00 16044.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1243.00 4847.70 P&M-037
Smooth wheeled steel tandom roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 49915.00 1796940.00 M-077
Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 956.33 71725.00 M-048
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 1000.67 90060.00 M-047
Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5 cum 105.000 992.30 104191.50 M-030
d) Overhead charges @ 0.1 on (a+b+c) 216383.93
e) Contractor's profit @ 0.1 on (a+b+c+d) 238022.32
Cost for 205 cum = a+b+c+d+e 2618245.54
Rate per cum = (a+b+c+d+e)/205 12771.93
say 12772.00
Note 1.Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
5.18 (iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size
aggregate

Page 22 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Composition of mix (450 tonne) is assumed to be as
under:-
Cutback bitumen 5 per cent
Filler (lime) 2 per cent
Total aggregates 93 per cent
Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor day 16.000 136.69 2187.04 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 3661.20 21967.20 P&M-077
producing average output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Paver finisher hour 6.000 2674.00 16044.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour 6.00x0.65* 1243.00 4847.70 P&M-037
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045
c) Material
Cutback bitumen @ 5 per cent tonne 22.500 47937.00 1078582.50 M-076
Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188
Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5 cum 78.000 1103.60 86080.80 M-045
Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5 cum 93.000 1078.94 100341.42 M-040
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 cum 108.000 992.30 107168.40 M-030
d) Overhead charges @ 0.1 on (a+b+c) 147309.59
e) Contractor's profit @ 0.1 on (a+b+c+d) 162040.55
Cost for 205 cum = a+b+c+d+e 1782446.05
Rate per cum = (a+b+c+d+e)/205 8694.86
say 8695.00
Note 1.Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
5.18 (iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size
aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Cutback bitumen 5 per cent
Filler2 per cent
Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor day 16.000 136.69 2187.04 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour 6.000 3661.20 21967.20 P&M-077
producing output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Page 23 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Paver finisher hour 6.000 2674.00 16044.00 P&M-034
Pneumatic tyred roller 12-15 tonnes. hour 6.00x0.65* 1243.00 4847.70 P&M-037
Smooth wheeled steel tandem roller 6-8 tonnes hour 6.00x0.65* 1144.00 4461.60 P&M-045
c) Material
Cutback bitumen on @ 5 per cent tonne 22.500 47937.00 1078582.50 M-076
Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 cum 75.000 956.33 71725.00 M-048
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 1000.67 90060.00 M-047
Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5 cum 114.000 992.30 113122.20 M-030
d) Overhead charges @ 0.1 on (a+b+c) 145441.25
e) Contractor's profit @ 0.1 on (a+b+c+d) 159985.37
Cost for 205 cum = a+b+c+d+e 1759839.11
Rate per cum = (a+b+c+d+e)/205 8584.58
say 8585.00
Note 1.Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
5.19 520 Sand Asphalt Base Course
Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder on a
prepared sub-grade or sub-base to the lines, levels, grades
and cross sections as per the drawings including mixing in a
plant of suitable type and capacity, transporting, laying,
compacting and finishing.
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate day 0.840 151.44 127.21 L-12
Mazdoor day 16.000 136.69 2187.04 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Hot Mix Plant of appropriate capacity but not less than hour 6.000 13842.00 83052.00 P&M-023
75 tonnes/hour
Electric generator set 250 KVA hour 6.000 1906.88 11441.25 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 806.00 4836.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Paver finisher hour 6.000 2674.00 16044.00 P&M-034
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65 460.00 1794.00 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65 1541.00 6009.90 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandom hour 6.00x0.65 1144.00 4461.60 P&M-045
rollers.
c) Material
Composition of mix (450 tonne) is assumed to be as
under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
Bitumen@ 5 per cent tonne 22.500 55132.00 1240470.00 M-074
Filler (lime)@ 2 per cent tonne 9.000 4500.00 40500.00 M-188
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5 cum 288.620 828.00 238977.36 M-004
d) Overhead charges @ 0.1 on (a+b+c) 165194.04
e) Contractor's profit @ 0.1 on (a+b+c+d) 181713.44
Cost for 205 cum = a+b+c+d+e 1998847.88
Rate per cum = (a+b+c+d+e)/205 9750.48

Page 24 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 9750.00
Note 1. Tack coat will be measured and paid separately
2. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of this roller, their
usage rates has been multiplied by a factor of 0.65

5.20 521 Modified Binder


Supply of modified binder produced by mixing bitumen with
modifier such as natural rubber or crumb rubber or any other
polymer found compatible with bitumen and which allows
properties given in clause 521.3 and IRC:SP: 53 blending of
modifier with bitumen to be done either at the refinery or at
central unit with all facilities by proper industrial process, is
essential.

Unit = tonne
The use of modified binder is expected to result in an
extended service life of bituminous pavements subject to
heavy traffic loads in extreme climatic conditions, thus
justifying the entire cost of adding modifiers/fibres. Other
advantages include lower temperature susceptibility, higher
resistance to aging, higher fatigue life, higher resistance to
cracking and better adhesion between aggregates and
binder.

Detailed information and inductive dose level on the use of


polymer modified binder is available in IRC : SP-53 / 2002. A
number of proprietary products are now available in the
market. For such proprietary products, test reports and cost
effectiveness should be the basis for their selection in road
works.
The modifier, in the required quantity shall be blended at the
refinery or at central unit with all facilities by proper industrial
process, is essential. If supplied in drums it shall be agitated
in melted condition with suitable device for achieving
homogeneity
Proposals to use glass fibre, polypropylene fibres or any
other similar material in a bituminous mixture should be
substantiated, complete with all details including test results,
manufacturer's recommendations for addition or means of
incorporating the fibres, homogeneously, without
segregation, into the mixture.
Before agreeing to the use of a fibre, it should have been
proved to be satisfactory in use under circumstances, similar
to the work, elsewhere or it would have under gone
appropriate performance trials. Documented evidence of use
and trials of the fibre, in any country having conditions
similar to Indian will be acceptable.
where information on use of trials is inadequate or lacking,
trials may be required to be under taken before agreeing to
the use of the fibre.
Note 1. The modified binder is usually manufactured by `
specialised firms as a proprietary product. The rate for this
product is required to be as certained from the market.
2.The specifications for various item of road works using
polymer/rubber modified bitumens are same as those for
penetration grade bitumen except those for any special
conditions which the manufacturer may indicate
3.The other controls during mixing, laying shall be same as
specified in IRC - 14, 29, 94 and 95 for open graded premix
carpet, bituminous concrete, DBM and SDBC respectively

4.The temperature of mixing and rolling will be slightly higher


than conventional bituminous mixes as indicated in Table 8
of IRC: SP: 53 - 2002
5.21 522 Crack Prevention Courses
(i) Stress absorbing membrane (SAM) crack width less than 6
mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader, sweeping
the surface for uniform spread of aggregates and surface
finished to conform to clause 902.

Page 25 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031
Air compressor 250 cfm hour 6.000 319.00 1914.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004
Hydraulic Chip spreader hour 6.000 2635.00 15810.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044
c) Material
Modified binder tonne 9.450 38740.00 366093.00 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 969.00 101745.00 M-050
d) Overhead charges @ 0.1 on (a+b+c) 49775.85
e) Contractor's profit @ 0.1 on (a+b+c+d) 54753.43
Cost for 10500 sqm = a+b+c+d+e 602287.77
Rate per sqm = (a+b+c+d+e)/10500 57.36
say 57.00
5.21 (ii) Stress absorbing membrane (SAM) with crack width 6 mm to
9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031
Air compressor 250 cfm capacity hour 6.000 319.00 1914.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004
Hydraulic Chip spreader hour 6.000 2635.00 15810.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044
c) Material
Modified binder tonne 11.550 38740.00 447447.00 M-078
Crushed stone chipping 11.2 mm size cum 105.000 1005.00 105525.00 M-051
d) Overhead charges @ 0.1 on (a+b+c) 58289.25
e) Contractor's profit @ 0.1 on (a+b+c+d) 64118.17
Cost for 10500 sqm = a+b+c+d+e 705299.91
Rate per sqm = (a+b+c+d+e)/10500 67.17
say 67.00
5.21 (iii) Stress absorbing membrane (SAM) crack width above 9 mm
and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 6.000 136.69 820.14 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 357.00 2142.00 P&M-031
Air compressor 250 cfm capacity hour 6.000 319.00 1914.00 P&M-001
Page 26 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1073.00 6438.00 P&M-004
Hydraulic Chip spreader hour 6.000 2635.00 15810.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 460.00 2760.00 P&M-044
c) Material
Modified binder tonne 15.750 38740.00 610155.00 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 1005.00 126630.00 M-051
d) Overhead charges @ 0.1 on (a+b+c) 76703.49
e) Contractor's profit @ 0.1 on (a+b+c+d) 84373.84
Cost for 10500 sqm = a+b+c+d+e 928112.19
Rate per sqm = (a+b+c+d+e)/10500 88.39
say 88.00
Note In case 2nd coat is also required to be provided, material
provided for the 2nd coat shall be as per table 500-47.
5.21 (iv) Case - IV : Bitumen impregnated geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 703.4.5

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 151.44 84.81 L-12
Mazdoor day 12.000 136.69 1640.28 L-13
Mazdoor skilled day 2.000 164.69 329.38 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 357.00 999.60 P&M-031
Air compressor 250 cfm capacity hour 2.800 319.00 893.20 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 1073.00 2146.00 P&M-004
Pneumatic roller hour 2.000 1243.00 2486.00 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 56122.00 206528.96 M-075
kg per sqm
Geotextile including 10 per cent for overlaps sqm 3850.000 37.25 143412.50 M-108
d) Overhead charges @ 0.1 on (a+b+c) 35852.07
e) Contractor's profit @ 0.1 on (a+b+c+d) 39437.28
Cost for 10500 sqm = a+b+c+d+e 433810.08
Rate per sqm = (a+b+c+d+e)/3500 123.95
say 124.00
NOTE As bitumen overlay construction shall follow closely the
fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will cover a
length of 500 m, of 7 m wide carriagway. This can be
conveniently overlaid by a bitumenious course in a day

5.22 519.3 Recipe Cold Mix


Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing
plant, laid over prepared surface, by paver finisher, rolled
with a pneumatic tyred roller initially and finished with a
smooth steel wheel roller, all as per clause 519.3

Unit = cum
Taking output = 205 cum (450 tonnes)
(i) 75 mm thickness
a) Labour
Mate day 1.000 151.44 151.44 L-12
Mazdoor day 12.000 136.69 1640.28 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity hour 6.000 25594.50 153567.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2674.00 16044.00 P&M-034
cum per hour

Page 27 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Pneumatic tyred roller12-15 tonnes. hour 6.00x0.65* 1243.00 4847.70 P&M-037
Smooth wheeled steel roller6-8 tonnes. hour 6.00x0.65* 460.00 1794.00 P&M-044
Water tanker6 KL capacity hour 1.000 200.00 200.00 P&M-060
c) Material
Bitumen emulsion @ 45 litres per tonne tonne 20.250 49915.00 1010778.75 M-077
Crushed stone aggregates 40 mm nominal size cum 297.000 916.00 272052.00 M-055
Cost of water KL 6.000 10.00 60.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 147192.32
e) Contractor's profit @ 0.1 on (a+b+c+d) 161911.55
Cost for 10500 sqm = a+b+c+d+e 1781027.08
Rate per sqm = (a+b+c+d+e)/205 8687.94
say 8688.00
Note (Case I to III)
1. These mixes are considered suitable for minor repair work
and temporary road surface improvement.
2. In case concrete mixtures are required to be used for
mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
*4.Both the rollers have to be available at site to match with
the output of batch mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted to cater for the
idling period of road rollers.
5.22 (ii) 40 mm thickness
a) Labour
Mate day 1.000 151.44 151.44 L-12
Mazdoor day 12.000 136.69 1640.28 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Batch type cold mixing plant100-120 TPH capacity hour 6.000 25594.50 153567.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2674.00 16044.00 P&M-034
cum per hour
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Pneumatic tyred roller 12-15 tonnes. hour 6.00x0.65* 1243.00 4847.70 P&M-037
Smooth wheeled steel roller 6-8 tonnes. hour 6.00x0.65* 460.00 1794.00 P&M-044
Water tanker6 KL capacity hour 1.000 200.00 200.00 P&M-060
c) Material
Bitumen emulsion @ 70 litres per tonne tonne 31.500 49915.00 1572322.50 M-077
Crushed stone aggregates 14 mm nominal size cum 287.000 1028.00 295036.00 M-052
Cost of water KL 6.000 10.00 60.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 205645.10
e) Contractor's profit @ 0.1 on (a+b+c+d) 226209.61
Cost for 10500 sqm = a+b+c+d+e 2488305.66
Rate per sqm = (a+b+c+d+e)/205 12138.08
say 12138.00
5.22 (iii) 25 mm thickness
a) Labour
Mate day 1.000 151.44 151.44 L-12
Mazdoor day 12.000 136.69 1640.28 L-13
Mazdoor skilled day 5.000 164.69 823.45 L-15
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity hour 6.000 25594.50 153567.00 P&M-064
producing an average output of 75 tonne per hour
Electric generator 125 KVA hour 6.000 652.00 3912.00 P&M-018
Front end loader 1 cum capacity hour 6.000 806.00 4836.00 P&M-017

Page 28 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2674.00 16044.00 P&M-034
cum per hour
Tipper 10 tonne capacity tonne.km 450 x L 2.46 1105.99 Lead =1
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 110.60
and unloading
Pneumatic tyred roller hour 6.00x0.65* 1243.00 4847.70 P&M-037
Smooth wheeled steel roller hour 6.00x0.65* 460.00 1794.00 P&M-044
Water tanker6 KL capacity hour 1.000 200.00 200.00 P&M-060
c) Material
Bitumen emulsion @ 85 litres per tonne tonne 38.250 49915.00 1909248.75 M-077
Crushed stone aggregates 6 mm nominal size cum 270.000 969.00 261630.00 M-050
Cost of water KL 6.000 10.00 60.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 235997.12
e) Contractor's profit @ 0.1 on (a+b+c+d) 259596.83
Cost for 10500 sqm = a+b+c+d+e 2855565.16
Rate per sqm = (a+b+c+d+e)/205 13929.59
say 13930.00

Page 29 of 264
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
7.1 702 Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties
as given in clause 702.2.3 formed in to a stable network and
a planar geocomposite structure, joints wrapped with
geotextile to prevent ingress of soil, all as per clause 702
and approved drawings including excavation and backfilling

Unit = Running metre


Taking output = one metre
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor skilled day 0.250 164.69 41.17 L-15
Mazdoor day 0.500 136.69 68.35 L-13
b) Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .

Geonets sqm 1.000 607.00 607.00 M-107


Geomembrane sqm 1.000 607.00 607.00 M-106
Geotextile sqm 2.000 37.25 74.50 M-108
Add 2 per cent cost of material for miscellaneous items like 25.77
synthetic cord
c) Overhead charges @ 0.1 on (a+b) 142.98
d) Contractor's profit @ 0.1 on (a+b+c) 157.28
Rate per metre = a+b+c+d 1730.11
say 1730.00
Note Surplus excavated material to be used at site. Hence
seprate cost for disposal not added.
7.2 702.4 Narrow Filter Sub-Surface Drain
Construction of a narrow filter sub- surface drain consisting
of porous or perforated pipe laid in narrow trench
surrounded by a geotextile filter fabric, with a minimum of
450 mm overlap of fabric and installed as per clause 702.3
and 309.3.5 including excavation and backfilling

Unit = Running metre length


Taking output = one metre
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor skilled day 0.250 164.69 41.17 L-15
Mazdoor day 0.500 136.69 68.35 L-13
b) Material
Perforated geosynthetic pipe 150 mm dia metre 1.000 182.00 182.00 M-134
Geotextile filter fabric sqm 1.250 37.25 46.56 M-109
Add 2 per cent cost of material for miscellaneous item like 4.57
synthetic cord
c) Overhead charges @ 0.1 on (a+b) 34.87
d) Contractor's profit @ 0.1 on (a+b+c) 38.36
Rate per metre = a+b+c+d 421.94
say 422.00
Note Surplus excavated material to be used at site. Hence
Separate cost for disposal not added.

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
7.3 703 Laying Paving Fabric Beneath a Pavement Overlay
Providing and laying paving fabric with physical
requirements as per table 704-2 over a tack coat of paving
grade Bitumen 80-100 penetration, laid at the rate of 1 kg
per sqm over thoroughly cleaned and repaired surface to
provide a water resistant membrane and crack retarding
layer. Paving fabric to be free of wrinkling and folding and to
be laid before cooling of tack coat, brooming and rolling of
surface with pneumatic roller to maximise paving fabric
contact with pavement surface

Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate day 0.800 151.44 121.15 L-12
Mazdoor day 20.000 136.69 2733.80 L-13
b) Machinery
Road sweeper 1250 sqm per hour hour 2.240 357.00 799.68 P&M-031
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1243.00 1740.20 P&M-037
Bitumen pressure distributor 1750 sqm per hour hour 1.680 1073.00 1802.64 P&M-004
c) Material
Paving Fabric sqm 2940.000 225.00 661500.00 M-133
Paving Bitumen 80-100 tonne 2.800 56122.00 157141.60 M-075
c) Overhead charges @ 0.1 on (a+b) 82583.91
d) Contractor's profit @ 0.1 on (a+b+c) 90842.30
Cost for 2800 sqm = a+b+c+d+e 999265.28
Rate per sqm =(a+b+c+d+e)/2800 356.88
say 356.88
7.4 704 Laying Boulder Apron in Crates of Synthetic Geogrids

Providing, preparing and laying of geogrid crated apron 1 m


x 5 m, 600 mm thick including excavation and backfilling with
baffles at 1 metre interval, made with geogrids having
characteristics as per clause 704.2, joining sides with
connectors/ring staples, top corners to be tie tensioned,
placing of suitable cross interval ties in layers of 300 mm
connecting opposite side with lateral braces and tied with
polymer braids to avoid bulging, constructed as per clause
704.3. filled with stone with minimum size of 200 mm and
specific gravity not less than 2.65, packed with stone spalls,
keyed to the foundation recess in case of sloping ground
and laid over a layer of geotextile to prevent migration of
fines, all as per clause 704 and laid as per clause 2503.3
and approved design.

Unit = cum
Taking output = 3.00 cum
a) Labour
Mate day 0.060 151.44 9.09 L-12
Mazdoor skilled day 0.500 164.69 82.35 L-15
Mazdoor day 1.500 136.69 205.04 L-13
b) Material
Geo grids sqm 21.000 607.00 12747.00 M-105
Connectors/ Staples each 50.000 61.00 3050.00 M-085
Polymer braids metre 20.000 364.00 7280.00 M-140
Stones with minimum size of 200 mm cum 3.450 494.68 1706.65 M-003
Stones spall for filling voids cum 0.450 921.00 414.45 M-008
c) Overhead charges @ 0.1 on (a+b) 2549.46
d) Contractor's profit @ 0.1 on (a+b+c) 2804.40
Cost for 3 cum = a+b+c+d 30848.42
Rate per cum = (a+b+c+d)/ 3 2372.96
say 2373.00
7.5 3100 Reinforced Earth Structures
Reinforced earth Structures have four main components as
under:
a) Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing
elements (facia material).

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Facia material and its placement.
c) Assembling, joining with facing elements and laying of
the reinforcing elements.
d) Earth fill with granular material which is to be retained
by the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
7.5 3102 (i) Assembling, joining and laying of reinforcing elements.

A With reinforcing element of steel / Aluminium strips /


polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 151.44 54.52 L-12
Mazdoor day 6.000 136.69 820.14 L-13
Mazdoor skilled day 3.000 164.69 494.07 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as per
clause 3102.
1.Galvanised carbon steel strips metre 450*1.1 364.00 180180.00 M-154
or
2.Copper Strips metre 450*1.1 364.00 180180.00 M-153
or
3.Aluminium Strips metre 450*1.1 364.00 180180.00 M-157
or
4.Stainless steel strips metre 450*1.1 364.00 180180.00 M-156
or
5.Glass reinforced polymer/fibre reinforced metre 450*1.1 364.00 180180.00 M-155
polymer/polymeric strips
@ Any one of the above alternative may be adopted as per
approved design.
Add 10 per cent of the cost of reinforcing strip towards
accessories like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia pannels, overlaps,
heat bonding or extension.
Type 1 1.Galvanised carbon steel strips
c) Overhead charges @ 0.1 on (a+b) 18154.87
d) Contractor's profit @ 0.1 on (a+b+c) 18154.87
Cost of 450 m = a+b+c+d 217858.47
Rate per metre =(a+b+c+d)/450 484.13
say 484.00
Type 2 2.Copper Strips
c) Overhead charges @ 0.1 on (a+b) 18154.87
d) Contractor's profit @ 0.1 on (a+b+c) 18154.87
Cost of 450 m = a+b+c+d 217858.47
Rate per metre =(a+b+c+d)/450 484.13
say 484.00
Type 3 3.Aluminium Strips
c) Overhead charges @ 0.1 on (a+b) 18154.87
d) Contractor's profit @ 0.1 on (a+b+c) 18154.87
Cost of 450 m = a+b+c+d 217858.47
Rate per metre =(a+b+c+d)/450 484.13
say 484.00
Type 4 4.Stainless steel strips
c) Overhead charges @ 0.1 on (a+b) 18154.87
d) Contractor's profit @ 0.1 on (a+b+c) 18154.87
Cost of 450 m = a+b+c+d 217858.47
Rate per metre =(a+b+c+d)/450 484.13
say 484.00

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Type 5 5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips
c) Overhead charges @ 0.1 on (a+b) 18154.87
d) Contractor's profit @ 0.1 on (a+b+c) 18154.87
Cost of 450 m = a+b+c+d 217858.47
Rate per metre =(a+b+c+d)/450 484.13
say 484.00
7.5(i) B With reinforcing elements of synthetic geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 151.44 54.52 L-12
Mazdoor day 6.000 136.69 820.14 L-13
Mazdoor skilled day 3.000 164.69 494.07 L-15
b) Material
Synthetic Geogrids as per clause 3102.8 and approved sqm 300.000 607.00 182100.00 M-181
design and specifications.
Add 10 per cent of the cost of reinforcing elements 18210.00
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps and other
protective elements for synthetic geogrids.
c) Overhead charges @ 0.1 on (a+b) 20167.87
d) Contractor's profit @ 0.1 on (a+b+c) 22184.66
Cost of 300 sqm of Synthetic geogrids = a+b+c+d 244031.26
Rate per sqm = (a+b+c+d)/ 300 813.44
say 813.00
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 151.44 27.26 L-12
Mazdoor day 3.000 136.69 410.07 L-13
Mazdoor skilled day 1.500 164.69 247.04 L-15
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 357.00 2142.00 P&M-013
c) Material
Pre-cast RCC M-35 facing elements of size as per cu.m 13.500 3952.00 53352.00 Item 12.8
design and 18 cm thick for 75 sqm. (Refer Item 12.8 (H)
(H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 65101.00 24738.38 Item 13.6
Add 2 per cent of cost of facia pannels, for all necessary 1561.81
temporary form work, scaffolding and provision of loops/lugs
for lifting of pannels and joining the reinforcing elements.

d) Overhead charges @ 0.1 on (a+b) 282.64


e) Contractor's profit @ 0.1 on (a+b+d) 310.90
Cost for 75 sqm = a+b+c+d+e 83072.09
Rate per sqm = (a+b+c+d+e)/ 75 1107.63
say 1108.00
Note 1.The specification and construction details to be adopted
shall be as per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved
design and drawings.
3.The quantity of filler media shall be calculated as per
approved design and specifications and shall be priced
separately.The rate for same to be adopted from chapter 15.

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.Excavation for foundation including foundation concrete
and groove in the foundation for seating of bottom most
facia panel and capping beam to be calculated as per
design and priced separately. The rates for excavation and
foundation concrete shall be taken from the chapter 12 & 13
in bridge section.
5.The earth fill to be retained is not included in this analysis.
The same is to be worked out and provided separately
complete as per clause 305.
, 6.For compaction of Earthwork, attention is invited to clause
3105.5 of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall
and will be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as
per approved design and specifications.
9.The market rate for supply of reinforcing elements and
their accessories are to be ascertained from reputed firms in
the field of earth reinforcement.
10.The earth fill material shall be clean, free draining,
granular with high friction and low cohesion, non-corrosive,
coarse grained with not 10 per cent of particles passing 75
micron sieve, free of any deleterious matter, chlorides, salts,
acids, alkalies, mineral oil, fungus and microbes and shall be
of specified PH value.
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include
following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and
joining with the facial pannels.
(v) Drainage arrangement including filter media as per
approved design and drawings.
13. The compacted earth filling to be retained shall form part
of embankment.

Page 5 of 264
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
A. Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 151.44 109.04 L-12
Mason day 2.000 223.36 446.72 L-11
Mazdoor day 16.000 136.69 2187.04 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 310.00 1860.00 P&M-029
Concrete mixer 0.48/0.28 cum capacity hour 12.000 233.00 2796.00 P&M-009
Water tanker6 KL capacity hour 5.000 200.00 1000.00 P&M-060
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1028.00 22400.12 M-053
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 710.46 7744.01 M-005
Cement 11 per cent tonne 5.700 5000.00 28500.00 M-081
Cost of water KL 30.000 10.00 300.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 6734.29
e) Contractor's profit @ 0.1 on (a+b+c+d) 7407.72
Cost for 360 meter = a+b+c+d+e 81484.95
Rate per metre = (a+b+c+d+e)/360 226.35
say 226.00
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mason day 1.000 223.36 223.36 L-11
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 310.00 1860.00 P&M-029
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1860.00 2976.00 P&M-003
Water tanker6 KL capacity hour 5.000 200.00 1000.00 P&M-060
Tipper 5.5 cum capacity hour 6.000 339.00 2034.00 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1028.00 22400.12 M-053
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 828.00 9025.20 M-004
Cement 11 per cent tonne 5.700 5000.00 28500.00 M-081
Cost of water KL 30.000 10.00 300.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 6861.02
e) Contractor's profit @ 0.1 on (a+b+c+d) 7547.13
Cost for 360 meter = a+b+c+d+e 83018.38
Rate per metre = (a+b+c+d+e)/360 230.61
say 231.00
8.2 408 Cast in Situ Cement Concrete M 20 Kerb with Channel

Construction of cement concrete kerb with channel with top


and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408
A Using Concrete Mixer
Unit = Running metre
Taking output = 300 metre length
Cement Concrete

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.720 151.44 109.04 L-12
Mason day 2.000 223.36 446.72 L-11
Mazdoor day 16.000 136.69 2187.04 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 310.00 1860.00 P&M-029
hour 6.000
and channel
Concrete mixer 0.48/0.28 hour 16.000 233.00 3728.00 P&M-009
Water tanker6 KL capacity hour 6.000 200.00 1200.00 P&M-060
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1028.00 37614.52 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 710.46 13001.42 M-005
Cement 10 per cent tonne 9.010 5000.00 45050.00 M-081
Cost of water KL 36.000 10.00 360.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 10555.67
e) Contractor's profit @ 0.1 on (a+b+c+d) 11611.24
Cost for 360 meter = a+b+c+d+e 127723.65
Rate per metre = (a+b+c+d+e)/300 425.75
Add 1 % labour Cess 4.26
430.00
say 430.00
8.2 B Using Concrete Batching and Mixing Plant
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mason day 1.000 223.36 223.36 L-11
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 310.00 1860.00 P&M-029
hour 6.000
and channel
Concrete batching and mixing plant @ 15 cum/hr. hour 2.700 1860.00 5022.00 P&M-003
Water tanker6 KL capacity hour 6.000 200.00 1200.00 P&M-060
Tipper of 5.5 cum capacity hour 6.000 339.00 2034.00 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 1028.00 37614.52 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 828.00 15152.40 M-004
Cement 10 per cent tonne 9.010 5000.00 45050.00 M-081
Cost of water KL 36.000 10.00 360.00 M-189
d) Overhead charges @ 0.1 on (a+b+c) 10880.78
e) Contractor's profit @ 0.1 on (a+b+c+d) 11968.86
Cost for 300 meter = a+b+c+d+e 131657.48
Rate per metre = (a+b+c+d+e)/300 438.86
say 439.00
8.3 801 Printing New Letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade

(i)
Hindi ( Matras commas and the like not to be measured and
paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a) Labour

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.120 151.44 18.17 L-12
Painter day 2.000 223.36 446.72 L-18
Mazdoor day 1.000 136.69 136.69 L-13
b) Material
Paint Litre 0.700 192.81 134.97 M-131
c) Overhead charges @ 0.1 on (a+b) 73.65
d) Contractor's profit @ 0.1 on (a+b+c) 81.02
Cost for 1600 cm = a+b+c+d 891.23
Rate per cm height per letter = (a+b+c+ d)/1600 0.56
say 0.60
8.3 (ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.070 151.44 10.60 L-12
Painter Ist class day 1.250 223.36 279.20 L-18
Mazdoor day 0.500 136.69 68.35 L-13
b) Material
Paint Litre 0.500 192.81 96.41 M-131
c) Overhead charges @ 0.1 on (a+b) 45.46
d) Contractor's profit @ 0.1 on (a+b+c) 50.00
Cost for 1600 cm = a+b+c+d 550.01
Rate per cm height per letter = (a+b+c +d)/1600 0.34
say 0.30
8.4 801 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign
138.00 29.81 Item No.
i) Excavation for foundation cum 0.216
3.13
4228.00 507.36 Item 12.8
ii) Cement concrete M15 grade cum 0.120
(A)
iii) Painting angle iron post two coats sqm 0.430 46.00 19.78 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 151.44 1.51 L-12
Mazdoor day 0.250 136.69 34.17 L-13
b) Material
45.00 855.00 M-179
Mild steel angle iron 75 x 75 x 6 mm kg 19.000
/1000
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 6064.00 2122.40 M-061
or
( ii ) 60 cm equilateral triangle sqm 0.156 6064.00 945.98 M-061
or
( iii ) 60 cm circular sqm 0.283 6064.00 1716.11 M-061
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 6064.00 2910.72 M-061
or
(v) 60 cm x 45 cm rectangular sqm 0.270 6064.00 1637.28 M-061
or
(vi ) 60 cm x 60 cm square sqm 0.360 6064.00 2183.04 M-061

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
or
( vii ) 90 cm high octagon sqm 0.672 6064.00 4075.01 M-061
c) Machinery
Tractor-trolley hour 0.010 282.50 2.83 P&M-053
(i) 90 cm equilateral triangle
d) Overhead charges @ 0.1 on (a+b+c) 301.59
e) Contractor's profit @ 0.1 on (a+b+c+d) 331.75
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4206.20
say 4206.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 0.1 on (a+b+c) 183.95
e) Contractor's profit @ 0.1 on (a+b+c+d) 202.34
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2782.74
say 2783.00
( iii ) 60 cm circular
d) Overhead charges @ 0.1 on (a+b+c) 260.96
e) Contractor's profit @ 0.1 on (a+b+c+d) 287.06
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3714.59
say 3715.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 0.1 on (a+b+c) 380.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 418.47
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5160.07
say 5160.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 0.1 on (a+b+c) 253.08
e) Contractor's profit @ 0.1 on (a+b+c+d) 278.39
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3619.21
say 3619.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 0.1 on (a+b+c) 307.66
e) Contractor's profit @ 0.1 on (a+b+c+d) 338.42
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4279.58
say 4280.00
( vii ) 90 cm high octagon
d) Overhead charges @ 0.1 on (a+b+c) 496.85
e) Contractor's profit @ 0.1 on (a+b+c+d) 546.54
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6568.86
say 6569.00
1.Any one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters

3. The depth of foundation and quantity of cement concrete


in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

Direction and Place Identification Signs upto 0.9 sqm Size


8.5 801
Board.

Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of high intensity
grade sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45 x 60
cm, 60 cm below ground level as per approved drawing

Unit = sqm
Taking output = 0.9 sqm
138.00 29.81 Item No.
i) Excavation for foundation cum 0.216
3.13

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4228.00 507.36 Item 12.8
ii) Cement concrete M15 grade cum 0.120
(A)
iii) Painting angle iron post two coats sqm 0.430 46.00 19.78 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 151.44 1.51 L-12
Mazdoor day 0.200 136.69 27.34 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 45.00 855.00 M-179
kg 19.000
metres long /1000
Aluminium sheeting fixed with encapsulated lens type 6064.00 5457.60 M-061
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 282.50 5.65 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 634.71
e) Contractor's profit @ 0.1 on (a+b+c+d) 698.18
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 8236.94
Rate per sqm (for sign having area upto 0.9 sqm) =
9152.16
(I+ii+iii+a+b+c+d+e)/0.90
say 9152.00
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more than
8.6 801
0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing
Unit = sqm
Taking output = 1.50 sqm
138.00 59.34 Item No.
i) Excavation for foundation cum 0.430
3.13
4228.00 1014.72 Item 12.8
ii) Cement concrete M15 grade cum 0.240
(A)
iii) Painting angle iron post 2 coats sqm 0.860 46.00 39.56 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 151.44 1.51 L-12
Mazdoor day 0.300 136.69 41.01 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 45.00 1710.00 M-179
kg 38.000
metres long, 2 nos /1000
Aluminium sheeting fixed with encapsulated lens type 6064.00 9096.00 M-061
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.

Page 5 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Machinery
Tractor-trolley hour 0.020 282.50 5.65 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1081.17
e) Contractor's profit @ 0.1 on (a+b+c+d) 1193.53
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 14242.49
Rate per sqm ( for sign having area more than 0.9 sqm) =
15824.99
( i+ii+iii+a+b+c+d+e)/1.50
say 15825.00
i) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 802 Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans
A Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 151.44 36.35 L-12
Blacksmith day 2.000 264.50 529.00 L-02
Mazdoor including for handling & fixing at site. day 4.000 136.69 546.76 L-13
b) Material
Aluminium alloy/galvanised steel including 5 per cent 54574.00 57302.70 M-060
tonne 1.050
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
573.03
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
8681.36
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 357.00 1071.00 P&M-013
Truck hour 0.500 315.27 157.64 P&M-057
d) Overhead charges @ 0.1 on (a+b+c) 6889.78
e) Contractor's profit @ 0.1 on (a+b+c+d) 7578.76
Rate per tonne = (a+b+c+d+e) 83366.37
say 83366.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 151.44 3.03 L-12
Blacksmith day 0.100 264.50 26.45 L-02
Mazdoor day 0.150 136.69 20.50 L-13
b) Material
Aluminium alloy plate,2 mm thick, fixed with high 425.00 425.00 M-059
sqm 1.000
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
0.50
ladders, pulleys, ropes etc
c) Overhead charges @ 0.1 on (a+b) 47.55
d) Contractor's profit @ 0.1 on (a+b+c) 52.30
Rate per sqm = (a+b+c+d) 575.33
say 575.00
1. The cost of excavation and foundation concrete for fixing
of vertical support system to be worked out separately as
Note
per the approved drawing/design and to be included in the
estimate.

Page 6 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.

Page 7 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 151.44 18.17 L-12
Painter day 2.000 223.36 446.72 L-18
Mazdoor day 1.000 136.69 136.69 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 117.16 702.96 M-132
Add for scaffolding @ 1 per cent of labour cost where
7.03
required
Add @ 5 per cent cost of labour and materials to 65.23
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 0.1 on (a+b) 137.68
d) Contractor's profit @ 0.1 on (a+b+c) 151.45
Cost for 40 sqm = a+b+c+d 1665.93
Rate per sqm = (a+b+c+d)/40 41.65

say 42.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 151.44 4.54 L-12
Painter day 0.450 223.36 100.51 L-18
Mazdoor day 0.250 136.69 34.17 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 192.81 241.01 M-131
Add @ 1 per cent on cost of material for scaffolding 2.41
Add @ 5 per cent cost of labour and materials to 19.01
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.
c) Overhead charges @ 0.1 on (a+b) 40.17
d) Contractor's profit @ 0.1 on (a+b+c) 44.18
Cost for 10 sqm = a+b+c+d 486.01
Rate per sqm= (a+b+c+d)/10 48.60
say 49.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 151.44 4.54 L-12
Painter day 0.500 223.36 111.68 L-18
Mazdoor day 0.200 136.69 27.34 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 192.81 289.22 M-131
Add @ 1 per cent on cost of material for scaffolding 2.89
Add @ 5 per cent cost of labour and materials to 21.64
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.

Page 8 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.1 on (a+b) 45.73
d) Contractor's profit @ 0.1 on (a+b+c) 50.30
Cost for 10 sqm = a+b+c+d 553.34
Rate per sqm = (a+b+c+d)/10 55.33
say 55.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats
8.11 803
on New Work
Painting lines, dashes, arrows etc on roads in two coats on
new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 151.44 13.63 L-12
Painter day 0.550 223.36 122.85 L-18
Mazdoor day 1.550 136.69 211.87 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 117.16 173.40 M-132
c) Overhead charges @ 0.1 on (a+b) 52.17
d) Contractor's profit @ 0.1 on (a+b+c) 57.39
Cost for 10 sqm = a+b+c+d 631.31
Rate per sqm= (a+b+c+d)/10 63.13
say 63.00
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 151.44 10.60 L-12
Painter day 0.350 223.36 78.18 L-18
Mazdoor day 1.350 136.69 184.53 L-13
b) Material
Road marking paint Litre 1.480 117.16 173.40 M-132
c) Overhead charges @ 0.1 on (a+b) 44.67
d) Contractor's profit @ 0.1 on (a+b+c) 49.14
Cost for 10 sqm = a+b+c+d 540.51
Rate per sqm = (a+b+c+d)/10 54.05
say 54.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats
8.12 803
on Old Work
Painting lines, dashes, arrows etc on roads in two coats on
old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 151.44 9.09 L-12
Painter Ist class day 0.300 223.36 67.01 L-18
Mazdoor day 1.250 136.69 170.86 L-13
b) Material
Road marking paint Litre 0.900 117.16 105.44 M-132
c) Overhead charges @ 0.1 on (a+b) 35.24
d) Contractor's profit @ 0.1 on (a+b+c) 38.76
Cost for 10 sqm = a+b+c+d 426.41
Rate per sqm = (a+b+c+d)/10 42.64
say 43.00
8.12 (ii) Up to 10 cm in width

Page 9 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 151.44 10.60 L-12
Painter Ist class day 0.350 223.36 78.18 L-18
Mazdoor day 1.350 136.69 184.53 L-13
b) Material
Road marking Paint Litre 0.900 117.16 105.44 M-132
c) Overhead charges @ 0.1 on (a+b) 37.88
d) Contractor's profit @ 0.1 on (a+b+c) 41.66
Cost for 10 sqm= a+b+c+d 458.29
Rate per sqm = (a+b+c+d)/10 45.83
say 46.00

Road Marking with Hot Applied Thermoplastic Compound


8.13 803
with Reflectorising Glass Beads on Bituminous Surface

Providing and laying of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.

Unit = sqm
Taking output = 640 sqm
a) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor day 2.000 136.69 273.38 L-13
b) Machinery
Road marking machine @ 80 sqm per hour hour 8.000 93.00 744.00 P&M-043
Tractor-trolley hour 8.000 282.50 2260.00 P&M-053
c) Material
Hot applied thermoplastic compound Litre 2000.000 150.00 300000.00 M-118
Reflectorising glass beads kg 200.000 75.00 15000.00 M-152
d) Overhead charges @ 0.1 on (a+b+c) 31828.50
e) Contractor's profit @ 0.1 on (a+b+c+d) 35011.34
Cost for 640 sqm = a+b+c+d+e 385124.79
Rate per sqm = a+b+c+d+e)/640 601.76
Add 1 % labour Cess 6.02
607.78
say 607.78
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
4228.00 9935.80 Item 12.8
a) M-15 grade of concrete cum 2.350
(A)
65.10 1437.43 Item 13.6 /
b) Steel reinforcement @ 5 kg per sqm kg 22.080
1000
138.00 231.84 Item No.
c) Excavation in soil for foundation cum 1.680
3.13
d) Painting two coats on concrete surface sqm 9.850 40.00 394.00 Item 8.8
e) Lettering on km post (average 30 letters of 10 cm per cm per 0.30 540.00 Item 8.3
1800.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.260 151.44 39.37 L-12

Page 10 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mason day 0.600 223.36 134.02 L-11
Mazdoor including loading/unloading day 6.000 136.69 820.14 L-13
g) Machinery
Tractor-trolley hour 6.000 282.50 1695.00 P&M-053
h) Overhead charges @ 0.1 on (f+g) 268.85
i) Contractor's profit @ 0.1 on (f+g+h) 295.74
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 15792.19

Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i ) /6 2632.03

say 2632.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
4228.00 15939.56 Item 12.8
a) M-15 grade of concrete cum 3.770
(A)
65.10 1713.46 Item 13.6 /
b) Steel reinforcement @ 5 kg per sqm kg 26.320
1000
138.00 382.26 Item No.
c) Excavation in soil for foundation cum 2.770
3.13
d) Painting two coats on concrete surface sqm 11.410 40.00 456.40 Item 8.8
e) Lettering on km post ( average 12 letters of 10 cm per cm per 0.30 504.00 Item 8.3
1680.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 151.44 48.46 L-12
Mason day 1.000 223.36 223.36 L-11
Mazdoor day 7.000 136.69 956.83 L-13
g) Machinery
Tractor-trolley hour 6.000 282.50 1695.00 P&M-053
h) Overhead charges @ 0.1 on (f+g) 292.37
i) Contractor's profit @ 0.1 on (f+g+h) 321.60
Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i)
22533.30
Rate for each ordinary km stone = (a+b+ c +d+e+f+g+h+j)
1609.52
/14
say 1610.00
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
4228.00 6680.24 Item 12.8
a) M-15 grade of concrete cum 1.580
(A)
65.10 4296.67 Item 13.6 /
b) Steel reinforcement @ 5 kg per sqm kg 66.000
1000
138.00 191.82 Item No.
c) Excavation in soil for foundation cum 1.390
3.13
d) Painting two coats on concrete surface sqm 6.270 40.00 250.80 Item 8.8
e) Lettering on km post (average 1 letter of 10 cm per cm per 0.30 99.00 Item 8.3
330.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.340 151.44 51.49 L-12
Mason day 1.500 223.36 335.04 L-11
Mazdoor day 7.000 136.69 956.83 L-13
g) Machinery
Tractor-trolley hour 6.000 282.50 1695.00 P&M-053
h) Overhead charges @ 0.1 on (f+g) 303.84
i) Contractor's profit @ 0.1 on (f+g+h) 334.22
Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+
15194.94
g+h+i)
Rate for each Hectometer stone = (a+b +c +d+e+f+ g+h+i)
460.45
33
say 460.00
The rate for excavation, cement concrete, steel
Note reinforcement, painting and lettering may be taken from
respective chapters.

Page 11 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
8.15 805 Road Delineators

Supplying and installation of delineators (road way


indicators, hazard markers, object markers), 80-100 cm high
above ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm dia
circular reflectorised panels at the top, buried or pressed into
the ground and conforming toIRC-79 and the drawings.

Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor for fixing day 1.000 136.69 136.69 L-13
b) Material
Cost of approved type of delineators from ISI certified 834.40 25032.00 M-091
each 30.000
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 2503.20
c) Overhead charges @ 0.1 on (a+b) 2767.79
d) Contractor's profit @ 0.1 on (a+b+c) 3044.57
Cost for 30 Nos. delineators = (a+b+ c+d) 33490.32
Rate per delineators = (a+b+c+d) /30 1116.34
say 1116.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.

8.16 806 Boundary pillar


Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
Unit = Each
Taking output = 57 Nos.
4228.00 5285.00 Item 12.8
a) M-15 grade of the boundary stone cum 1.250
(A)
65.10 5195.06 Item 13.6 /
b) Steel reinforcement kg 79.800
1000
138.00 1479.36 Item No.
c) Excavation in soil cum 10.720
3.13
0.30 684.00 Item 8.3
per letter
d) Lettering, each 10 cm high 2280.000
per cm high

Transportation and fixing


e) Labour
Mate day 0.570 151.44 86.32 L-12
Mazdoor day 14.250 136.69 1947.83 L-13
f) Machinery
Tractor-trolley hour 6.000 282.50 1695.00 P&M-053
g) Material
Stone spall cum 11.970 921.00 11024.37 M-008
h) Overhead charges @ 0.1 on (e+f+g) 1475.35
i) Contractor's profit @ 0.1 on (e+f+g+h) 1622.89
Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )
30495.18

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57 535.00

say 535.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.

8.17 807 G.I Barbed Wire Fencing 1.2 Metre High

Page 12 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Providing and fixing 1.2 metres high GI barbed wire fencing
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.090 151.44 13.63 L-12
Blacksmith day 0.250 264.50 66.13 L-02
Mazdoor day 2.000 136.69 273.38 L-13
b) Material
Barbed wire 335 metres length @ 9.38 kg per 100 65.56 2059.90 M-063
kg 31.420
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in 45.00 3622.50 M-179
kg 80.500
length @ 3.5 kg per metre /1000
Add for GI staple binding wire, drilling holes etc. @ 2 per
113.65
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 46.00 97.06 Item 8.9
sqm 2.110
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 0.1 on (a+b) 614.92
e) Contractor's profit @ 0.1 on (a+b+d) 676.41
Cost for 30 metres fencing = a+b+c+d+e 7537.57
Rate per metre = (a+b+c+d+e)/30 251.25
say 251.00
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
Note
design. The rate for these items may be taken from
respective chapters.
8.18 807 G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.120 151.44 18.17 L-12
Blacksmith day 0.400 264.50 105.80 L-02
Mazdoor day 2.500 136.69 341.73 L-13
b) Material
Barbed wire 428 metres length @ 9.38 kg per 100 65.56 2632.23 M-063
kg 40.150
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in 45.00 6840.00 M-179
kg 152.000
length @ 4.5 kg per metre /1000
Add for GI staple, binding wire, drilling holes etc. @ 2
189.44
per cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 46.00 182.16 Item 8.9
sqm 3.960
angle iron posts
d) Overhead charges @ 0.1 on (a+b) 1012.74
e) Contractor's profit @ 0.1 on (a+b+d) 1114.01
Cost for 30 metres fencing = a+b+c+d+e 12436.29
Rate per metre fencing = (a+b+c +d+e)/30 414.54
say 415.00

Page 13 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
Note
design. The rate for these items may be taken from
respective chapters.

8.19 Suggesti Fencing With Welded Steel Wire Fabric 75 mm x 50 mm


ve
Providing 1.20 metre high fencing with angle iron posts 50
mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner,
end and every 10th post to be strutted, provided with welded
steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts
etc. complete in all respects.
Unit = Running metre
Taking output = 30 m
a) Labour
Mate day 0.120 151.44 18.17 L-12
Welder day 1.000 264.50 264.50 L-02
Mazdoor day 2.000 136.69 273.38 L-13
b) Material
45.00 4770.00 M-179
i) Angle iron for posts 50 x 50 x 6 mm kg 106.000
/1000
45.00 1170.00 M-179
ii) Runner flat 50 x 5 mm kg 26.000
/1000
iii) Welded steel wire fabric 75x50 mm mesh @ 4 61.00 9211.00 M-191
kg 151.000
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg 293.000
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c) Machinery
Tractor-trolley hour 0.100 282.50 28.25 P&M-053
d) Painting
Painting two coats including priming sqm 8.000 46.00 368.00 Item 8.9
e) Overhead charges @ 0.1 on (a+b+c) 1573.53
f) Contractor's profit @ 0.1 on (a+b+c+e) 1730.88
Cost for 30 metre = a+b+c+d+e+f 19407.72
Rate per metre = (a+b+c+d+e+f)/30 646.92
say 647.00
i) Adopt any one type of welded steel wire fabric 75 x 50 mm
Note
or 75 x 25 mm as per approved design.
ii) The item of excavation and cement concrete in foundation
shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel
8.20 808
( ISMC series) 100 mm x 50 mm

Providing, fixing and erecting 50 mm dia steel pipe railing in


3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2
m centre to centre, complete as per approved drawings

Unit = Running metre


Taking output = 10metres
138.00 178.85 Item No.
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 cum 1.296
3.13
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x 4228.00 2739.74 Item 12.8
cum 0.648
0.3 (A)
iii) Painting of pipe sqm 4.710 46.00 216.66 Item 8.9
iv) Painting of channel section 6 nos,1.8 metres each 46.00 99.36 Item 8.9
sqm 2.160
0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate day 0.010 151.44 1.51 L-12
Mazdoor day 0.250 136.69 34.17 L-13
Plumber day 0.010 264.50 2.65 L-02
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 364.00 10920.00 M-175

Page 14 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Medium weight steel channel (ISMC series) 100 mm x 45.00 4471.20 M-179
kg 99.360
50 mm,10.8 metres length @ 9.2 kg per metre /1000
Add for drilling holes @ 2 per cent of cost of channels 89.42
c) Machinery
Tractor-trolley hour 0.040 282.50 11.30 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1875.36
e) Contractor's profit @ 0.1 on (a+b+c+d) 2062.89
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 22703.12
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2270.31
say 2270.00
Tubular Steel Railing on Precast RCC Posts, 1.2 m High
8.21 808
Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
138.00 178.85 Item No.
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 cum 1.296
3.13
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 0.6 4228.00 2739.74 Item 12.8
cum 0.648
x 0.3 (A)
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres 5317.00 1701.44 Item
cum 0.320
each 14.1(A)
iv) Painting of pipe sqm 4.710 46.00 216.66 Item 8.9
a) Labour
Mate day 0.014 151.44 2.12 L-12
Mazdoor day 0.350 136.69 47.84 L-13
Plumber day 0.010 264.50 2.65 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 364.00 10920.00 M-175
c) Machinery
Tractor-trolley hour 0.250 282.50 70.63 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1104.32
e) Contractor's profit @ 0.1 on (a+b+c+d) 1214.76
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 18199.00
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1819.90
say 1820.00
8.22 809 Reinforced Cement Concrete Crash Barrier

Provision of an Reinforced cement concrete crash barrier at


the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified

Unit = Linear metre


Taking output = 10 m
(i) a) M 20 grade concrete
5317.00 15951.00 Item
M 20 grade concrete cum 3.000
14.1(A)
b) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor day 1.000 136.69 136.69 L-13
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 45000.00 12600.00 M-082
Pre-moulded asphalt filler board sqm 0.320 425.00 136.00 M-144
d) Overhead charges @ 0.1 on (b+c) 1287.87
e) Contractor's profit @ 0.1 on (b+c+d) 1416.66
Cost for 10 metre = a+b+c+d+e 34687.71

Page 15 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per metre = (a+b+c+d+e)/10 3468.77
say 3469.00
i) Excavation and backfilling are incidental to work and not to
Note
be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
8.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail
to be fixed on the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 151.44 9.09 L-12
Blacksmith day 0.500 264.50 132.25 L-02
Mazdoor day 1.000 136.69 136.69 L-13
b) Machinery
Tractor-trolley hour 0.100 282.50 28.25 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section 45.00 1854.45 M-179
kg 41.210
railing,4.5 m in length /1000
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 45.00 3985.20 M-179
kg 88.560
16.4 kg per metre /1000
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 45.00 730.80 M-179
kg 16.240
16.4 kg per metre /1000
Nuts and bolts kg 20.000 64.07 1281.40 M-130
Add 25 per cent of the cost of material for fabrication, nuts,
1962.96
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c) 1012.11
e) Contractor's profit @ 0.1 on (a+b+c+d) 1113.32
Cost for 4.5 metre = a+b+c+d+e 12246.52
Rate per metre = (a+b+c+d+e)/4.5 2721.45
say 2721.00
8.23 B Type - B, "THRIE" : Metal Beam Crash Barrier
Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail
to be fixed on the vertical post with a space of channel
section 150 x 75 x 5 mm, 546 mm long complete as per
clause 810
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 151.44 9.09 L-12
Blacksmith day 0.500 264.50 132.25 L-02
Mazdoor day 1.000 136.69 136.69 L-13
b) Machinery
Tractor-trolley hour 0.100 282.50 28.25 P&M-053
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section 49.00 3574.06 M-088
kg 72.940
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 45.00 4428.00 M-179
kg 98.400
kg per metre /1000
45.00 1208.70 M-179
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860
/1000

Page 16 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Nuts and bolts kg 30.000 64.07 1922.10 M-130
Add 15 per cent of the cost of material for fabrication, nuts,
1669.93
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c) 1310.91
e) Contractor's profit @ 0.1 on (a+b+c+d) 1442.00
Cost for 4.5 metre = a+b+c+d+e 15861.97
Rate per metre= (a+b+c+d+e)/4.5 3524.88
say 3525.00
In the case of median crash barrier, 'W' metal beam or thrie
beam section should be provided on both sides of the
Note vertical posts fixed in the median. Extra provision for metal
beam railing and spacer is required to be made when fixed
in the median depending on approved design.
8.24 811 Road Traffic Signals electrically operated
Since it is a ready made item commercially produced and
erected by specialised firm in the electrical and electronic
Note field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved
design and drawing.
Suggesti
8.25 Flexible Crash Barrier, Wire Rope Safety Barrier
ve

Providing and erecting a wire rope safety barrier with vertical


posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and
0.65 m below ground level, split at the bottom for better grip,
embedded in M 15 grade cement concrete 450 x 450 x 450
mm, 1.50 m center to center and with 4 horizontal steel wire
rope 40 mm dia and anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15 grade cement
concrete foundation 2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long
at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the
bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation
and cement concrete.

Unit = Running metre


Taking output = 15 metre
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mazdoor day 2.000 136.69 273.38 L-13
Blacksmith day 1.000 264.50 264.50 L-02
b) Material
45.00 8550.00 M-179
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre kg 190.000
/1000
ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 45.00 2070.00 M-179
kg 46.000
x 11.50 /1000
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for 45.00 8478.00 M-179
kg 188.400
terminal posts @ 62.80 kg/sqm (2 x 1.5) /1000
iv) Steel wire rope 40 mm, including 7.50 per cent 61.00 3965.00 M-177
kg 65.000
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
1153.15
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface sqm 16.500 46.00 759.00 Item 8.9
d) Machinery
Tractor-trolley hour 0.250 282.50 70.63 P&M-053
e) Overhead charges @ 0.1 on (a+b+d) 2484.28
f) Contractor's profit @ 0.1 on (a+b+d+e) 2732.71
Cost for 15 m = a+b+c+d+e+f 30818.82
Rate per m = (a+b+c+d+e+f)/15 2054.59
say 2055.00
The items of excavations and cement concrete works will be
Note measured and included separately as per the approved
designs and drawings.
Suggesti
8.26 Anti-Glare Devices in Median
ve
A Plantation

Page 17 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Plantation of shrubs and plants of approved species in the
median. apart from cutting off glare from vehicle coming
from opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture.
Anti-glare screen with 25 mm steel pipe framework fixed with
B
circular and rectangular vans

Providing and erecting an anti - glare screen with 25 mm dia


vertical pipes fabricated and framed in the form of panels of
one metre length and 1.75 metre height fixed with circular
vane 250 mm dia at top and rectangular vane 600 x 300 mm
at the middle, made out of steel sheet of 3 mm thickness,
end vertical pipes of the panel made larger for embedding in
foundation concrete, applying 2 coats of paint on all exposed
surfaces, all as per approved design and drawings.

Unit = Running metre


Taking output = one metre
a) Labour
Mate day 0.004 151.44 0.61 L-12
Mazdoor day 0.100 136.69 13.67 L-13
b) Material
i) 25 mm steel pipe metre 16.000 182.00 2912.00 M-174
ii) MS sheet for 600 x 300 x 3 mm rectangular vane, 45.00 194.40 M-179
kg 4.320
one number @ 24kg/sqm /1000
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4 45.00 216.00 M-179
kg 4.800
numbers @ 24 kg/sqm /1000
Add 5 per cent cost of material for fabrication, welding,
166.12
bending, nuts, bolts etc
c) Painting
Applying 2 coats of painting on exposed surface sqm 1.830 46.00 84.18 Item 8.9
d) Overhead charges @ 0.1 on (a+b) 350.28
e) Contractor's profit @ 0.1 on (a+b+d) 385.31
Rate per metre = a+b+c+d+e 4322.56
say 4323.00
The items of excavation and cement concrete as per
Note
approved design to be measured and paid separately
8.26 C Anti-glare screen with rectangular vane of MS sheet

Providing and erecting anti - glare screen with rectangular


vanes of size 750 x 500 mm made from MS sheet, 3 mm
thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
450 to the direction of flow of traffic, 1.5 m center to center,
top edge of the screen 1.75 m above ground level, vertical
post firmly embedded in M-15 cement concrete foundation
0.60 m below ground level, applying 2 coats of paint on
exposed faces, all complete as per approved design and
drawings
Unit = Running metre
Taking output = 1.50 metre
a) Labour
Mate day 0.004 151.44 0.61 L-12
Mazdoor day 0.100 136.69 13.67 L-13
b) Material
45.00 476.10 M-179
i) Angle iron post,50 x 50 x 6 mm, length 2.35 m kg 10.580
/1000
45.00 405.00 M-179
ii) MS sheet 3 mm thick @ 24 kg/sqm kg 9.000
/1000
Add 5 per cent of cost of material for fabrication, nuts, bolts
44.06
etc
c) Machinery
Tractor-trolley hour 0.100 282.50 28.25 P&M-053
d) Painting
Applying 2 coats of painting sqm 0.850 46.00 39.10 Item 8.9
e) Overhead charges @ 0.1 on (a+b+c) 96.77
f) Contractor's profit @ 0.1 on (a+b+c+e) 106.44
Cost for 1.5 m = a+b+c+d+e+f 1209.99

Page 18 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per metre = (a+b+c+d+e+f)/1.50 806.66
say 807.00

The items of excavation and cement concrete as per


Note approved design to be measured and paid separately. Rate
of painting has been analaysed separately in this chapter.

Suggesti
8.27 Street Lighting
ve
Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly
in concrete foundation.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 151.44 4.54 L-12
Mazdoor day 0.500 136.69 68.35 L-13
Electrician day 0.250 264.50 66.13 L-02
b) Material
i) Steel circular hollow pole of standard specification for 1820.00 1820.00 M-171
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp each 1.000 1213.00 1213.00 M-168
Add 5 per cent of cost of material for holder, electric cable,
151.65
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel 46.00 264.50 Item 8.9
sqm 5.750
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel 46.00 212.98 Item 8.9
sqm 4.630
circular hollow pipe with overhang on one side
(i) For Fixing in Median
d) Overhead charges @ 0.1 on (a+b) 332.37
e) Contractor's profit @ 0.1 on (a+b+d) 365.60
Rate per light for fixing in Median= a+b+c+d+e 4286.13
say 4286.00
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 4234.61
say 4235.00
The items of excavation and cement concrete foundation will
be measured and included separately in the estimate as per
Note
approved design and drawing. The rate for painting has
been analysed in this chapter.
Suggesti
8.28 Lighting on Bridges
ve
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor day 0.400 136.69 54.68 L-13
Electrician day 0.200 264.50 52.90 L-02
b) Material
1213.00 1213.00 M-170
i) Steel circular hollow pole of standard specification for
each 1.000
street lighting to mount light at 5 m above deck level

ii) Sodium vapour lamp 70 watt each 1.000 1213.00 1213.00 M-168
Add 1 per cent of cost of material for holder, electric cable,
24.26
insulation, ladder, scaffolding etc
c) Painting

Page 19 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Providing two coats of alluminium paint over steel 46.00 126.96 Item 8.9
sqm 2.760
circular hollow pipe
d) Overhead charges @ 0.1 on (a+b) 256.09
e) Contractor's profit @ 0.1 on (a+b+d) 281.70
Rate per light = a+b+c+d+e 3225.61
say 3226.00
The items of cement concrete to be measured and paid
Note separately as per approved design. The rate for painting has
already been analysed in this chapter.
Suggesti
8.29 Cable Duct Across the Road
ve

Providing and laying of a reinforced cement concrete pipe


duct, 300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of slope to toe
of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and
sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m
thick layer of granular material free of rock pieces, outer to
outer distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row ducts,
joints to be made leak proof, invert level of duct to be above
higher than ground level to prevent entry of water and dirt,
all as per IRC: 98 - 1997 and approved drawings.

(i) Single row for one utility service


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in cement 5610.00 13239.60 Item 12.7
cum 2.360
mortar 1:6 for head wall both side (Addl) B)
b) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor day 1.000 136.69 136.69 L-13
Mazdoor skilled day 0.250 164.69 41.17 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 20.000 1149.00 22980.00 M-151
Granular soil with PI less than 6 for bedding and sides 727.79 5240.09 M-009
cum 7.200
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia each 9.000 146.00 1314.00 M-083
4152.00 83.04 Item 12.6
Cement mortar 1:2 for joints cum 0.020
(B)
d) Machinery
Tractor-trolley hour 0.500 282.50 141.25 P&M-053
e) Overhead charges @ 0.1 on (b+c+d) 2994.38
f) Contractor's profit @ 0.1 on (b+c+d+e) 3293.82
Cost for 20 metre = a+b+c+d+e+f 49471.61
Rate per metre = (a+b+c+d+e+f)/20 2473.58
say 2474.00
8.29 (ii) Double row for two utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 5610.00 18905.70 Item 12.7
cum 3.370
mortar 1:6 for head wall both sides. (Addl) B)
b) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor day 2.000 136.69 273.38 L-13
Mazdoor skilled day 0.250 164.69 41.17 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 40.000 1149.00 45960.00 M-151
Granular soil with PI less than 6 for bedding and sides 727.79 10480.18 M-009
cum 14.400
of pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia each 18.000 146.00 2628.00 M-083
4152.00 166.08 Item 12.6
Cement mortar 1:2 for joints cum 0.040
(B)
d) Machinery
Tractor-trolley hour 1.000 282.50 282.50 P&M-053
e) Overhead charges @ 0.1 on (b+c+d) 5983.89

Page 20 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
f) Contractor's profit @ 0.1 on (b+c+d+e) 6582.28
Cost for 20 metre = a+b+c+d+e+f 91310.75
Rate per metre = (a+b+c+d+e+f)/20 4565.54
say 4566.00
8.29 (iii) Triple rRow for three utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 5610.00 24571.80 Item 12.7
cum 4.380
mortar 1:6 for head wall both sides. (Addl) B)
b) Labour
Mate day 0.160 151.44 24.23 L-12
Mazdoor day 3.000 136.69 410.07 L-13
Mazdoor skilled day 1.000 164.69 164.69 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 60.000 1149.00 68940.00 M-151
Granular soil with PI less than 6 for bedding and sides 727.79 15720.26 M-009
cum 21.600
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia each 27.000 146.00 3942.00 M-083
4152.00 249.12 Item 12.6
Cement mortar 1:2 for joints cum 0.060
(B)
d) Machinery
Tractor-trolley hour 1.500 282.50 423.75 P&M-053
e) Overhead charges @ 0.1 on (b+c+d) 8987.41
f) Contractor's profit @ 0.1 on (b+c+d+e) 9886.15
Cost for 20 metre = a+b+c+d+e+f 133319.49
Rate per metre = (a+b+c+d+e+f)/20 6665.97
say 6666.00
1.Inspection chamber at both ends is the responsibility of the
Note
agency who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement
mortar to be adopted from respective clauses.
Suggesti
8.30 Highway Patrolling and Traffic Aid Post
ve
It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .
Suggesti Items Related to Underpass/ Subway/ Overhead Bridge/
8.31
ve Overhead Foot Bridge
The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved
designs and drawings
Suggesti
8.32 Traffic Control System and Communication System
ve
Providing a traffic control centre and communication system
including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system
and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In
case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived as per approved design and
drawing.
As regards the locations where such devices are required to
be installed, the traffic control authority should be consulted
to finalise the location
Suggesti
8.33 Gantry Mounted Variable Message Sign Board
ve

Page 21 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Providing and erecting gantry mounted variable message
sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per
clause 802.3
(i) Gantry Support System
Unit = tonne
Taking output=1 tonne
a) Labour
Mate day 0.120 151.44 18.17 L-12
Mazdoor day 2.000 136.69 273.38 L-13
Blacksmith day 1.000 264.50 264.50 L-02
b) Material
Alluminium alloy/galvanised steel including 5 per cent 54574.00 57302.70 M-060
tonne 1.050
wastage
Add 15 per cent of cost of material for fabrication and
8595.41
erection.
Add 1 per cent of cost of material for nuts, bolts and
573.03
welding
c) Machinery
Truck 10 tonne hour 1.000 315.27 315.27 P&M-057
d) Overhead charges @ 0.1 on (a+b+c) 6734.25
e) Contractor's profit @ 0.1 on (a+b+c+d) 7407.67
Rate per tonne = a+b+c+d+e 81484.37
say 81484.00
8.33 (ii) Message Display
Message display board 6 sqm electronically operated with
complete electronic fitments for flashing the pre-determined
messages.

This is a specilised commercial product and the lumpsum


rate including erection at site is required to be as certained
from the market and including in the rate analysis. The size
of the board will vary depending upon specific location.

The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above

Suggesti
8.34 Traffic Impact Attenuators at Abutments and Piers
ve
A With Scrap Tyres
Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 151.44 12.12 L-12
Mazdoor day 1.500 136.69 205.04 L-13
Blacksmith day 0.250 264.50 66.13 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 364.00 29120.00 M-161
20 mm steel wire rope kg 150.000 61.00 9150.00 M-176
Add 1 per cent of cost of wire rope for clamps etc. 91.50
c) Machinery
Tractor-trolley hour 3.000 282.50 847.50 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 3949.23
e) Contractor's profit @ 0.1 on (a+b+c+d) 4344.15
Cost for 20 sqm = a+b+c+d+e 47785.65
Rate per sqm = (a+b+c+d+e)/20 2389.28
say 2389.00
8.34 B Using Plastic/Steel Barrel, Filled with Sand

Page 22 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Provision and installation of traffic impact attenuator at
abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 151.44 19.69 L-12
Mazdoor day 3.000 136.69 410.07 L-13
Blacksmith day 0.250 264.50 66.13 L-02
b) Material
Plastic barrels each 50.000
or
Steel barrels each 50.000 79.00 3950.00 M-172
Sand cum 8.000 828.00 6624.00 M-004
20 mm steel wire rope kg 15.000 61.00 915.00 M-176
Add 1 per cent of cost of wire rope for clamps etc. 9.15
c) Machinery
Tractor-trolley hour 2.000 282.50 565.00 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1255.90
e) Contractor's profit @ 0.1 on (a+b+c+d) 1381.49
Cost for 20 sqm = a+b+c+d+e 15196.43
Rate per sqm = (a+b+c+d+e)/20 759.82
say 760.00
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-
determined time, thus absorbing the energy)

Providing and installing a patentend HI - DRO cell system as


a traffic impact attenuators, using plastic tubes 50 cm dia,
1.2 m in height, 25 mm opening at the top, placed in three
rows, filled with water and tied with a 20 mm steel wire rope

Unit = sqm
Taking output = 10sqm
a) Labour
Mate day 0.100 151.44 15.14 L-12
Mazdoor day 2.500 136.69 341.73 L-13
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 3639.00 145560.00 M-139
Cost of water KL 12.000 10.00 120.00 M-189
20 mm steel wire rope kg 100.000 61.00 6100.00 M-176
Add 1 per cent of cost of wire rope for clamps etc. 61.00
c) Machinery
Tractor-trolley hour 2.000 282.50 565.00 P&M-053
Water tanker6 KL capacity hour 2.000 200.00 400.00 P&M-060
d) Overhead charges @ 0.1 on (a+b+c) 15316.29
e) Contractor's profit @ 0.1 on (a+b+c+d) 16847.92
Cost for 10 sqm = a+b+c+d+e 185327.07
Rate per sqm = (a+b+c+d+e)/10 18532.71
say 18533.00
Suggesti
8.35 Road Markers/Road Stud with Lense Reflector
ve
Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic
surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as
per BS 873 part 4:1973
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 151.44 6.06 L-12

Page 23 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 1.000 136.69 136.69 L-13
b) Material
Aluminium studs 100 x 100 mm fitted with lense 546.00 27300.00 M-062
each 50.000
reflectors
Add 10 per cent of cost of material for fixing and installation 2730.00

c) Overhead charges @ 0.1 on (a+b) 3017.27


d) Contractor's profit @ 0.1 on (a+b+c) 3319.00
Cost for 50 studs = a+b+c+d 36509.02
Rate per studs = (a+b+c+d)/50 730.18
say 730.00
Suggesti
8.36 Traffic Cone
ve
Provision of red fluorescent with white reflective sleeve
traffic cone made of low density polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a
height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all
as per BS 873
Unit = Running metre
Taking output = 68 Nos.
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor day 0.500 136.69 68.35 L-13
b) Material
Traffic cones with 150 mm reflective sleeve each 68.000 243.00 16524.00 M-186
c) Machinery
Tractor-trolley hour 0.100 282.50 28.25 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1662.36
e) Contractor's profit @ 0.1 on (a+b+c+d) 1828.60
Cost for 68 Nos. = a+b+c+d+e 20114.58
Rate per metre = (a+b+c+d+e)/68 295.80
say 296.00
Suggesti
8.37 Roadside Amenities
ve
A Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage
system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual
site conditions
Parking areas and bus laybyes for trucks, buses and light
B
vehicles
Pricing of parking areas may be done for the quantities of
various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.
C Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per approved
dimensions in the drawings
Suggesti
8.38 Rumble Strips
ve
Provision of 15 nos rumble strips covered with premix
bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking
paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings

Page 24 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Suggesti
8.39 Policeman Umbrella
ve
Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed on
a raised platform, built on a central support of a steel pipe
100 mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel
parts to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork Quantities of these items to be cum
Cement Concrete calculated as per approved design and cum
cost added as per rates of these items
brick masonry or given in chapter 3 and 13 cum
stone masonry cum
Painting sqm 2.500
a) Labour
Mate day 0.090
Mazdoor day 1.000
Blacksmith day 1.000
Welder day 0.250
b) Material
Steel pipe 100 mm dia metre 3.500
Steel pipe 25 mm dia metre 10.000
CGI sheets kg 8.000
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500
d) Overheads @ per cent on (a+b+c)
e) Contractors Profit@ per cent on (a+b+c+d)
Rate per policeman umbrella = a+b+c+d+e
suggesti
8.40 High Mast Pole Lighting at Interchanges and Flyovers
ve

Providing and erecting a high mast pole lighting with 30 m


high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3 seconds
gust, as per IS:875 (Part 3) - 1978, fitted with a base flange,
door at the base of mast with heavy duty internal lock,
lantern carriage, suitable winching arrangement for safe
working load of 750 kg and high powered electrically driven
power tools for raising and lowering of lantern carriage,
flexible 8 core electric cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation obstruction lights on top of
the mast, all complete as per approved design and drawings

This is a specialised work and is generally done by firms


who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their tender
for checks by the Department. The cost of this work is
required to be worked out based on approved design,
drawings and estimate of the lowest tender. A separate
contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.

8.41 Toll Plaza


The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based
on the approved design and drawings:-
a) Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b) Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e) Provision of building to provide facility to toll plaza
personnel

Page 25 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
f) Toll plaza office equipment and furniture
g) Water supply, electricity, sanitation, septic-tank system
and drainage
h) Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard Data
Book
8.42 Safety Devices and Signs in Construction Zones

Provision and fixing of traffic signs for limited period at


suitable locations in construction zone comprising of warning
zone, approach transition zone, working zone and terminal
transition zone with a minimum distance of 60 cm from the
edge of the kerb in case of kerbed roads and 2 to 3 m from
the edge of the carriageway in case of un-kerbed roads, the
bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 60 mm x 60 mm x 6 mm angle
iron post, founded and installed as per approved design and
drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001

Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing

Page 26 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
ee) Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55-2001 and
IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
suggesti
8.43 Portable Barricade in Construction Zone
ve

Installation of a steel portable barricade with horizontal rail


300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white stripes,
150 mm in width at an angle of 450, 'A' frame painted with 2
coats of yellow paint, complete as per IRC:SP:55-2001

Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor day 0.250 136.69 34.17 L-13
Painter day 0.500 223.36 111.68 L-18
Welder day 0.250 264.50 66.13 L-02
b) Material
45.00 1125.00 M-179
Angle iron 45 x 45 x 5 mm kg 25.000
/1000
45.00 675.00 M-179
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000
/1000
Paint litre 0.500 192.81 96.41 M-131
Add 2 per cent of cost of steel for welding consumables,
36.00
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b) 214.74
d) Contractor's profit @ 0.1 on (a+b+c) 236.22
Rate per barricade = a+b+c+d 2598.37
say 2598.00
suggesti
8.44 Permanent Type Barricade in Construction Zone
ve
A With steel components
Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and white
strips, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor day 0.300 136.69 41.01 L-13
Painter day 0.600 223.36 134.02 L-18
Welder day 0.300 264.50 79.35 L-02
b) Material
45.00 675.00 M-179
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000
/1000
MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m 45.00 2250.00 M-179
kg 50.000
length /1000
Paint litre 1.000 192.81 192.81 M-131
Add 1 per cent of cost of steel for welding consumables,
58.50
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b) 343.83
d) Contractor's profit @ 0.1 on (a+b+c) 378.21
Rate per barricade = a+b+c+d 4160.29
say 4160.00
8.44 B With wooden components

Page 27 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 151.44 7.57 L-12
Mazdoor day 0.300 136.69 41.01 L-13
Painter day 0.600 223.36 134.02 L-18
Carpenter day 0.600 264.50 158.70 L-04
b) Material
Timber cum 0.180 24255.00 4365.90 M-185
Add 1 per cent of cost of timber for nuts & bolts, nails, etc. 43.66
c) Overhead charges @ 0.1 on (a+b) 475.09
d) Contractor's profit @ 0.1 on (a+b+c) 522.59
Rate per barricade = a+b+c+d 5748.53
say 5749.00
8.44 C With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 151.44 36.35 L-12
Mazdoor day 3.000 136.69 410.07 L-13
Painter day 1.000 223.36 223.36 L-18
Mason day 2.000 223.36 446.72 L-11
b) Material
Brick each 1800.000 4.42 7952.72 M-079
5.00 110.00 M-081
Cement kg 22.000
/1000
Sand cum 0.090 710.46 63.94 M-005
Paint litre 1.250 192.81 241.01 M-131
c) Overhead charges @ 0.1 on (a+b) 948.42
d) Contractor's profit @ 0.1 on (a+b+c) 1043.26
Rate per barricade = a+b+c+d 11475.85
say 11476.00
suggesti
8.45 Drum Delineator in Construction Zone
ve
Provision of metal drum/empty bitumen drum delineator, 300
mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white
100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as
per IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 151.44 3.03 L-12
Mazdoor day 0.250 136.69 34.17 L-13
Painter day 0.250 223.36 55.84 L-18
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen 79.00 79.00 M-172
each 1.000
drum
Paint litre 0.500 192.81 96.41 M-131
c) Overhead charges @ 0.1 on (a+b) 26.84
d) Contractor's profit @ 0.1 on (a+b+c) 29.53
Rate per drum delineator = a+b+c+d 324.82
say 325.00

Page 28 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
suggesti
8.46 Flagman
ve
Positioning of a smart flagman with a yellow vest and a
yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 151.44 6.06 L-12
Mazdoor day 1.000 136.69 136.69 L-13
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 91.00 91.00 M-099
Wooden staff for fastening of flag 25 mm dia, one m 122.00 122.00 M-196
each 1.000
long
c) Overhead charges @ 0.1 on (a+b) 35.57
d) Contractor's profit @ 0.1 on (a+b+c) 39.13
Rate per flagman = a+b+c+d 430.45
say 430.00

Page 29 of 264
CHAPTER-9
PIPE CULVERTS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
9.1 408 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 151.44 96.92 L-12
Mason day 1.000 223.36 223.36 L-11
Mazdoor day 15.000 136.69 2050.35 L-13
b) Material
40mm Aggregate at site cum 13.800 916.00 12640.80 M-055
Sand at site cum 6.900 710.46 4902.17 M-005
Cement at site tonne 3.300 5000.00 16500.00 M-081
Cost of water KL 18.000 10.00 180.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 233.00 1398.00 P&M-009
Generator set 33 KVA hour 6.000 406.80 2440.80 P&M-079
Water tanker6 KL capacity hour 3.000 200.00 600.00 P&M-060
d) Overhead charges @ 0.1 on (a+b+c) 4103.24
e) Contractor's profit @ 0.1 on (a+b+c+d) 4513.56
Cost for 15 cum = a+b+c+d+e 49649.21
Rate per cum = (a+b+c+d+e)/15 3309.95
say 3310.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.2 2900 Laying Reinforced Cement Concrete Pipe NP4 / Prestressed
Concrete Pipe on First Class Bedding in Single Row .

Laying Reinforced cement concrete pipe NP4/prestressed


concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length each )

A 1000 mm dia
a) Labour
Mate day 0.180 151.44 27.26 L-12
Mason day 0.500 223.36 111.68 L-11
Mazdoor day 4.000 136.69 546.76 L-13
b) Material
Sand at site cum 0.070 710.46 49.73 M-005
Cement at site tonne 0.050 5000.00 250.00 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 5000.00 62500.00 M-149
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 727.79 3275.06 M-009
c) Overhead charges @ 0.1 on (a+b) 6676.05
d) Contractor's profit @ 0.1 on (a+b+c) 7343.65
Cost for 12.5 metres = a+b+c+d 80780.19
Rate per metre = (a+b+c+d)/12.5 6462.42
say 6462.42
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.2 B 1200 mm dia
a) Labour
Mate day 0.280 151.44 42.40 L-12
Mason day 1.000 223.36 223.36 L-11

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 6.000 136.69 820.14 L-13
b) Material
Sand at site cum 0.090 710.46 63.94 M-005
Cement at site tonne 0.070 5000.00 350.00 M-081
RCC pipe NP-4/prestressed concrete pipe including metre 12.500 4452.00 55650.00 M-150
collar at site
Granular material passing 5-6 mm sieve for class cum 5.000 727.79 3638.95 M-009
bedding
c) Overhead charges @ 0.1 on (a+b) 6078.88
d) Contractor's profit @ 0.1 on (a+b+c) 6686.77
Cost for 12.5 metres = a+b+c+d 73554.44
Rate per metre= (a+b+c+d)/12.5 5884.36
say 5884.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 2900 Laying Reinforced Cement Concrete Pipe NP4 / Prestressed
Concrete Pipe on First Class Bedding in Double Row .

Laying Reinforced cement concrete pipe NP4 / prestressed


concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length each
in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.360 151.44 54.52 L-12
Mason day 1.000 223.36 223.36 L-11
Mazdoor day 8.000 136.69 1093.52 L-13
b) Material
Sand at site cum 0.140 710.46 99.46 M-005
Cement at site tonne 0.100 5000.00 500.00 M-081
RCC pipe NP-4/prestressed concrete pipe including metre 25.000 5000.00 125000.00 M-149
collar at site
Granular material passing 5.6 mm sieve for bedding cum 12.500 727.79 9097.38 M-009
c) Overhead charges @ 0.1 on (a+b) 13606.82
d) Contractor's profit @ 0.1 on (a+b+c) 14967.51
Cost for 12.5 metres = a+b+c+d 164642.57
Rate per metre = (a+b+c+d)/12.5 13171.41
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 13171.00
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 B 1200 mm dia
a) Labour
Mate day 0.560 151.44 84.81 L-12
Mason day 2.000 223.36 446.72 L-11
Mazdoor day 12.000 136.69 1640.28 L-13
b) Material
Sand at site cum 0.180 710.46 127.88 M-005
Cement at site tonne 0.140 5000.00 700.00 M-081

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
RCC pipe NP-4 /prestressed concrete pipe including metre 25.000 4452.00 111300.00 M-150
collar at site
Granular material passing 5-6 mm sieve for class cum 13.750 727.79 10007.11 M-009
bedding
c) Overhead charges @ 0.1 on (a+b) 12430.68
d) Contractor's profit @ 0.1 on (a+b+c) 13673.75
Cost for 12.5 metres = a+b+c+d 150411.23
Rate per metre= (a+b+c+d)/12.5 12032.90
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 12033.00
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

Page 3 of 264
CHAPTER-12
FOUNDATIONS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 151.44 21.20 L-12
Mazdoor day 3.50 136.69 478.42 L-13
b) Overhead charges @ 0.2 on (a) 99.92
c) Contractor's profit @ 0.1 on (a+b) 59.95
Cost for 10 cum = a+b+c 659.49
Rate per cum = (a+b+c)/10 65.95
say 66.00
Note 1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) A (ii) Depth 3 m to 6 m
a) Labour
Mate/Supervisor day 0.18 151.44 27.26 L-12
Mazdoor day 4.50 136.69 615.11 L-13
b) Overhead charges @ 0.2 on (a) 128.47
c) Contractor's profit @ 0.1 on (a+b) 77.08
Cost for 10 cum = a+b+c 847.92
Rate per cum = (a+b+c)/10 84.79
say 85.00
Note Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
12.1 (I) A (iii) Depth above 6 m
a) Labour
Mate/Supervisor day 0.24 151.44 36.35 L-12
Mazdoor day 6.00 136.69 820.14 L-13
b) Overhead charges @ 0.2 on (a) 171.30
c) Contractor's profit @ 0.1 on (a+b) 102.78
Cost for 10 cum = a+b+c 1130.56
Rate per cum = (a+b+c)/10 113.06
say 113.00
Note 1. Cost of dewatering may be added where required upto 20
per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 151.44 48.46 L-12
Mazdoor day 8.00 136.69 1093.52 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026
c) Overhead charges @ 0.2 on (a+b) 1790.80
d) Contractor's profit @ 0.1 on (a+b+c) 1074.48
Cost for 240 cum = a+b+c+d 11819.25
Rate per cum = (a+b+c+d)/240 49.25

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 49.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
12.1 (I) B (ii) Depth 3 m to 6 m

Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 151.44 48.46 L-12
Mazdoor day 8.00 136.69 1093.52 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026
c) Overhead charges @ 0.2 on (a+b) 1790.80
d) Contractor's profit @ 0.1 on (a+b+c) 1074.48
Cost for 210 cum = a+b+c+d 11819.25
Rate per cum = (a+b+c+d)/210 56.28
say 56.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B (iii) Depth above 6m

Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 151.44 60.58 L-12
Mazdoor day 10.00 136.69 1366.90 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026
c) Overhead charges @ 0.2 on (a+b) 1847.90
d) Contractor's profit @ 0.1 on (a+b+c) 1108.74
Cost for 180 cum = a+b+c+d 12196.11
Rate per cum = (a+b+c+d)/180 67.76
say 68.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 151.44 30.29 L-12
Mazdoor day 5.00 136.69 683.45 L-13
b) Overhead charges @ 0.2 on (a) 142.75
c) Contractor's profit @ 0.1 on (a+b) 85.65
Cost for 10 cum = a+b+c 942.13
Rate per cum = (a+b+c)/10 94.21
say 94.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) B Mechanical Means
Unit = cum
Taking output = 180 cum
a) Labour

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.24 151.44 36.35 L-12
Mazdoor day 6.00 136.69 820.14 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1302.00 7812.00 P&M-026
c) Overhead charges @ 0.2 on (a+b) 1733.70
d) Contractor's profit @ 0.1 on (a+b+c) 1040.22
Cost for 180 cum = a+b+c+d 11442.40
Rate per cum = (a+b+c+d)/180 63.57
say 64.00
Note 1.Cost of dewatering upto 10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 151.44 53.00 L-12
Driller day 0.50 264.50 132.25 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 8.00 136.69 1093.52 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 319.00 319.00 P&M-001
drilling.
c) Material
Blasting Material kg 3.50 146.00 511.00 M-104
Detonator electric each 14.00 14.56 203.84 M-094/100
d) Overhead charges @ 0.2 on (a+b+c) 475.75
e) Contractor's profit @ 0.1 on (a+b+c+d) 285.45
Cost for 10 cum = a+b+c+d+e 3139.94
Rate per cum = (a+b+c+d+e)/10 313.99
say 314.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering shall be
made as per site conditions.
12.1 IV Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.20 151.44 30.29 L-12
Mazdoor day 5.00 136.69 683.45 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 319.00 1914.00 P&M-001
breaker
c) Overhead charges @ 0.2 on (a+b) 525.55
d) Contractor's profit @ 0.1 on (a+b+c) 315.33
Cost for 10 cum = a+b+c+d 3468.61
Rate per cum = (a+b+c+d)/10 346.86
say 347.00
Note 1. Cost of dewatering upto10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 V Marshy Soil
Unit = cum

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.40 151.44 60.58 L-12
Mazdoor day 10.00 136.69 1366.90 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 282.50 754.28 P&M-053
c) Overhead charges @ 0.2 on (a+b) 436.35
d) Contractor's profit @ 0.1 on (a+b+c) 261.81
Cost for 10 cum = a+b+c+d 2879.91
Rate per cum = ( a+b+c+d)/ 10 287.99
say 288.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil
12.1 (V) B Mechanical Means
a) Labour
Mate day 0.08 151.44 12.12 L-12
Mazdoor for dressing sides, bottom and backfilling day 2.00 136.69 273.38 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1302.00 221.34 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 0.00 P&M-048
c) Overhead charges @ 0.2 on (a+b) 101.37
d) Contractor's profit @ 0.1 on (a+b+c) 60.82
Cost for 10 cum = a+b+c+d 669.02
Rate per cum = (a+b+c+d)/10 66.90
say 67.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 151.44 18.17 L-12
Mazdoor for dressing sides, bottom and backfilling day 3.00 136.69 410.07 L-13
b) Machinery
Tractor-trolley for transportation hour 2.00 282.50 565.00 P&M-053
c) Overhead charges @ 0.2 on (a+b) 198.65
d) Contractor's profit @ 0.1 on (a+b+c) 119.19
Cost for 6 cum = a+b+c+d 1311.08
Rate per cum = (a+b+c+d)/6 218.51
say 219.00
12.2 304 Filling Annular Space Around Footing in Rock
Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be
taken as per item 12.4.

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 151.44 1.51 L-12
Mazdoor day 0.30 136.69 41.01 L-13
b) Material
Sand (assuming 20 per cent voids) cum 1.20 476.80 572.16 M-006
c) Overhead charges @ 0.2 on (a+b) 122.94
d) Contractor's profit @ 0.1 on (a+b+c) 73.76
Rate per cum = a+b+c+d 811.38
say 811.00
12.4 2100 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum 255.94
a) Labour
Mate day 0.64 151.44 96.92 L-12
Mason day 1.00 223.36 223.36 L-11
Mazdoor day 15.00 136.69 2050.35 L-13
b) Material
40 mm Aggregate cum 13.50 916.00 12366.00 M-055
coarse Sand cum 6.75 710.46 4795.61 M-005
cement tonne 3.45 5000.00 17250.00 M-081
Cost of water KL 18.00 10.00 180.00 M-189
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Water tanker 6 KL capacity hour 2.00 200.00 400.00 P&M-060
d) Overhead charges @ 0.2 on (a+b+c) 8240.21
e) Contractor's profit @ 0.1 on (a+b+c+d) 4944.12
Cost for 15 cum = a+b+c+d+e 54385.37
Rate per cum = (a+b+c+d+e)/15 3625.69
say 3626.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
12.5 1300 Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per Drawing
and Technical Specifications.

Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 4.42 11045.45 M-079
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.20 3425.00 4110.00 Item 12.6
analysis) (A)
b) Labour
Mate day 0.48 151.44 72.69 L-12
Mason day 4.00 223.36 893.44 L-11
Mazdoor day 8.00 136.69 1093.52 L-13
c) Overhead charges @ 0.2 on (a+b) 3443.02
d) Contractor's profit @ 0.1 on (a+b+c) 2065.81
Cost for 5 cum = a+b+c+d 22723.93
Rate per cum (a+b+c+d)/5 4544.79
say 4545.00

Page 5 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)
analysis

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 5000.00 2550.00 M-081
Sand cum 1.05 710.46 745.98 M-005
b) Labour
Mate day 0.04 151.44 6.06 L-12
Mazdoor day 0.90 136.69 123.02 L-13
Total Material and Labour = (a+b) say 3425.00
Sub- (B) Cement Mortar1:2 (1cement :2 sand)
analysis
(Addl.)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 5000.00 3360.00 M-081
Sand cum 0.93 710.46 660.73 M-005
b) Labour
Mate day 0.04 151.44 6.06 L-12
Mazdoor day 0.90 136.69 123.02 L-13
Total Material and Labour = (a+b) say 4150.00
Sub- (C) Cement Mortar1:4 (1cement :4 sand)
analysis
(Addl.)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 5000.00 2016.00 M-081
Sand cum 1.12 710.46 795.72 M-005
b) Labour
Mate day 0.04 151.44 6.06 L-12
Mazdoor day 0.90 136.69 123.02 L-13
Total Material and Labour = (a+b) say 2941.00
Sub- (D) Cement Mortar1:6 (1cement :6 sand)
analysis
(Addl.)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 5000.00 1440.00 M-081
Sand cum 1.34 710.46 949.99 M-005
b) Labour
Mate day 0.04 151.44 6.06 L-12
Mazdoor day 0.90 136.69 123.02 L-13
Total Material and Labour = (a+b) say 2519.00
12.7 1400 Stone Masonry Work in Cement Mortar 1:3 in Foundation
complete as per Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 2705.04 14877.72 M-169

Page 6 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Through and bond stone each 35.00 14.45 505.86 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 3425.00 5137.50 Item 12.6
analysis) (A)
b) Labour
Mate day 0.66 151.44 99.95 L-12
Mason day 7.50 223.36 1675.20 L-11
Mazdoor day 9.00 136.69 1230.21 L-13
c) Overhead charges @ 0.2 on (a+b) 4705.29
d) Contractor's profit @ 0.1 on (a+b+c) 2823.17
Cost for 5 cum = a+b+c+d 31054.89
Rate per cum (a+b+c+d)/5 6210.98
say 6211.00
1405.3 (B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 2604.51 14324.81 M-148
Through and bond stone each 35.00 14.45 505.86 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.55 3425.00 5308.75 Item 12.6
analysis) (A)
b) Labour
Mate day 0.62 151.44 93.89 L-12
Mason day 6.00 223.36 1340.16 L-11
Mazdoor day 9.00 136.69 1230.21 L-13
c) Overhead charges @ 0.2 on (a+b) 4560.73
d) Contractor's profit @ 0.1 on (a+b+c) 2736.44
Cost for 5 cum = a+b+c+d 30100.85
Rate per cum (a+b+c+d)/5 6020.17
say 6020.00
Note The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
12.8 1500, Plain/Reinforced Cement Concrete in Open Foundation
1700 & complete as per Drawing and Technical Specifications.
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5000.00 20650.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 8.10 916.00 7419.60 M-055
20 mm Aggregate cum 4.05 1028.00 4163.40 M-053
10 mm Aggregate cum 1.35 1005.00 1356.75 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 63 KVA hour 6.00 535.00 3210.00 P&M-019
Per Cum Basic Cost of Labour, Material & Machinery 3080.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 1847.70
material, labour and machinery

Page 7 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.2 on (a+b+c+d) 9608.03
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 5764.82
Cost for 15 cum = a+b+c+d+e+f 63412.97
Rate per cum = (a+b+c+d+e+f)/15 4227.53
say 4228.00
Note Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 5000.00 25800.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 5.40 916.00 4946.40 M-055
20 mm Aggregate cum 5.40 1028.00 5551.20 M-053
10 mm Aggregate cum 2.70 1005.00 2713.50 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3390.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 2033.78
material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 10575.67
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6345.40
Cost for 15 cum = a+b+c+d+e+f 69799.44
Rate per cum = (a+b+c+d+e+f)/15 4653.30
say 4653.00
12.8 C RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 5000.00 26050.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3443.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 2065.49
e) Overhead charges @ 0.2 on (a+b+c+d) 10740.55
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6444.33
Cost for 15 cum = a+b+c+d+e+f 70887.66
Rate per cum = ( a+b+c+d+e+f )/15 4725.84
say 4726.00

Page 8 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 5000.00 208300.00 M-081
Coarse Sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Lead beyond 1 km, L-lead in km tonne.km 300L 2.03 610.20 P&M-050
Lead= 1
km
Concrete Pump hour 6 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3388.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 16260.23
material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 84553.21
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 50731.93
Cost for 120 cum = a+b+c+d+e+f 558051.18
Rate per cum = ( a+b+c+d+e+f )/120 4650.43
say 4650.00
12.8 D PCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 5000.00 29950.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 5.40 916.00 4946.40 M-055
20 mm Aggregate cum 5.40 1028.00 5551.20 M-053
10 mm Aggregate cum 2.70 1005.00 2713.50 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3667.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 2062.30
e) Overhead charges @ 0.2 on (a+b+c+d) 11411.38
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6846.83
Cost for 15 cum = a+b+c+d+e+f 75315.08
Rate per cum = ( a+b+c+d+e+f )/15 5021.01
say 5021.00
12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum

Page 9 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking Output = 120 cum
a) Material
Cement tonne 47.95 5000.00 239750.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
40 mm Aggregate cum 43.20 916.00 39571.20 M-055
20 mm Aggregate cum 43.20 1028.00 44409.60 M-053
10 mm Aggregate cum 21.60 1005.00 21708.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3614.00
(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. cost 16260.53
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 89974.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 53984.97
cost of 120 cum = a+b+c+d+e+f 593834.66
Rate per cum = (a+b+c+d+e+f)/120 4948.62
say 4949.00
12.8 E RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5000.00 30250.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3723.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 2093.90
e) Overhead charges @ 0.2 on (a+b+c+d) 11586.24
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6951.74
cost of 15 cum = a+b+c+d+e+f 76469.16
Rate per cum (a+b+c+d+e+f )/15 5097.94
say 5098.00
12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material

Page 10 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement tonne 48.38 5000.00 241900.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3668.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 16503.97
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 91321.96
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 54793.17
cost of 120 cum = a+b+c+d+e+f 602724.91
Rate per cum (a+b+c+d+e+f )/120 5022.71
say 5023.00
12.8 F PCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 5000.00 30400.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 5.40 916.00 4946.40 M-055
20 mm Aggregate cum 5.40 1028.00 5551.20 M-053
10 mm Aggregate cum 2.70 1005.00 2713.50 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3697.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost 1940.56
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 11477.03
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6886.22
cost of 15 cum = a+b+c+d+e+f 75748.39
Rate per cum (a+b+c+d+e+f )/15 5049.89
say 5050.00
12.8 F Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 5000.00 243000.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004

Page 11 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
40 mm Aggregate cum 43.20 916.00 39571.20 M-055
20 mm Aggregate cum 43.20 1028.00 44409.60 M-053
10 mm Aggregate cum 21.60 1005.00 21708.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3641.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost 15290.25
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 90430.89
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 54258.53
cost of 120 cum = a+b+c+d+e+f 596843.88
Rate per cum (a+b+c+d+e+f )/120 4973.70
say 4974.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5000.00 30500.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. cost 1963.05
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 11610.07
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6966.04
cost of 15 cum = a+b+c+d+e+f 76626.45
Rate per cum = (a+b+c+d+e+f)/15 5108.43
say 5108.00
12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 5000.00 244000.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051

Page 12 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3686.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 15477.20
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 91536.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 54921.96
cost of 120 cum = a+b+c+d+e+f 604141.58
Rate per cum (a+b+c+d+e+f )/120 5034.51
say 5035.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5000.00 31650.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 3816.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 1717.12
e) Overhead charges @ 0.2 on (a+b+c+d) 11790.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7074.53
cost of 15 cum = a+b+c+d+e+f 77819.81
Rate per cum = (a+b+c+d+e+f)/15 5187.99
say 5188.00
12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 5000.00 253200.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11

Page 13 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3762.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost of 13542.17
material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 92989.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 55793.76
cost of 120 cum = a+b+c+d+e+f 613731.34
Rate per cum = (a+b+c+d+e+f)/120 5114.43
say 5114.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
12.9 1200 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m dia.
Well.
A Assuming depth of water 1.0 m and height of island to be
1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 28.0 7033.60 M-092
Sand bags each 750.00 7.00 5250.00 M-159
b) Labour
Mate day 0.40 151.44 60.58 L-12
Mazdoor for filling sand bags, stitching and placing day 15.00 136.69 2050.35 L-13
c) Machinery
Crane with grab 1 cum capacity hour 20.00 853.00 17060.00 P&M-012
Consumables @ 2.5 per cent of (c) above 426.50
d) Overhead charges @ 0.2 on (a+b+c) 6376.21
e) Contractor's profit @ 0.1 on (a+b+c+d) 3825.72
Rate per No. (a+b+c+d+e) 42082.95
say 42083.00
Note It is assumed that earth will be available within the working
space of crane with grab bucket.
12.9 B Assuming depth of water 4.0 m and height of island 4.5 m.

Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 28.00 25320.96 M-092
Sand bags each 6000.00 7.00 42000.00 M-159
Wooden ballies 8" Dia and 9 m long each 95.00 91.00 8645.00 M-194
Wooden ballies 2" Dia for bracing metre 190.00 61.00 11590.00 M-193
b) Labour
Mate day 5.60 151.44 848.06 L-12
Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 136.69 2460.42 L-13

Mazdoor for bracing with 2" dia ballies day 12.00 136.69 1640.28 L-13

Page 14 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor for filling sand bags, stitching and placing day 110.00 136.69 15035.90 L-13
c) Machinery
Crane with grab 1 cum capacity hour 50.00 853.00 42650.00 P&M-012
Consumables and other arrangements for piling ballies @ 3754.77
2.5 per cent of (a+b+c).
d) Overhead charges @ 0.2 on (a+b+c) 30789.08
e) Contractor's profit @ 0.1 on (a+b+c+d) 18473.45
Rate per No. (a+b+c+d+e) 203207.91
say 203208.00
Note For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
12.9 C Providing and constructing one span service road to reach
island location from one pier location to another pier location

Assuming span length 30 m, width of service road 10m and


depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 28.00 12600.00 M-092
Sand bags each 300.00 7.00 2100.00 M-159
b) Labour
Mate day 0.24 151.44 36.35 L-12
Mazdoor for filling sand bags, stitching and placing day 6.00 136.69 820.14 L-13
c) Machinery
Front end Loader 1 cum capacity hour 27.00 806.00 21762.00 P&M-017
Tipper 5.5 cum capacity hour 28.00 339.00 9492.00 P&M-048
d) Overhead charges @ 0.2 on (a+b+c) 9362.10
e) Contractor's profit @ 0.1 on (a+b+c+d) 5617.26
Cost for 30 m (a+b+c+d+e) 61789.84
Rate per m (a+b+c+d+e)/30 2059.66
say 2060.00
12.10 1200 & Providing and Laying Cutting Edge of Mild Steel weighing 40
1900 kg per metre for Well Foundation complete as per Drawing
and Technical Specification.

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 45000.00 47250.00 M-179
cent wastage
Nuts & bolts Kg 20.00 64.07 1281.40 M-130
b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Mate day 1.32 151.44 199.90 L-12
Fitter day 5.50 230.00 1265.00 L-08
Blacksmith day 5.50 264.50 1454.75 L-02
Welder day 5.50 264.50 1454.75 L-02
Mazdoor day 16.50 136.69 2255.39 L-13
Electrodes, cutting gas and other consumables @ 10 per 4853.14
cent of cost of (a) above
c) Overhead charges @ 0.2 on (a+b) 12002.87
d) Contractor's profit @ 0.1 on (a+b+c) 7201.72
Rate per MT (a+b+c+d) 79218.91
say 79219.00
12.11 1200, Plain/Reinforced Cement Concrete, in Well Foundation
1500 & complete as per Drawing and Technical Specification.
1700

Page 15 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3443.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 688.60
e) Overhead charges @ 0.2 on (a+b+c+d) 826.32
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 495.79
Rate perm (a+b+c+d+e+f) 5453.71
say 5454.00
12.11 A (i) Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 3388.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 677.60
e) Overhead charges @ 0.2 on (a+b+c+d) 813.12
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 487.87
Rate perm (a+b+c+d+e+f) 5366.59
say 5367.00
12.11 A (ii) RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3723.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 744.60
e) Overhead charges @ 0.2 on (a+b+c+d) 893.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 536.11
Rate perm (a+b+c+d+e+f) 5897.23
say 5897.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 748.00
e) Overhead charges @ 0.2 on (a+b+c+d) 897.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 538.56
Rate perm (a+b+c+d+e+f) 5924.16
say 5924.00
12.11 A (iii) RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3816.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 763.20
e) Overhead charges @ 0.2 on (a+b+c+d) 915.84
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 549.50
Rate perm (a+b+c+d+e+f) 6044.54
say 6045.00
12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery 3838.00
(a+b+c)

Page 16 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) formwork @ 20 per cent of the cost of concrete 767.60
e) Overhead charges @ 0.2 on (a+b+c+d) 921.12
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 552.67
Rate perm (a+b+c+d+e+f) 6079.39
say 6079.00
Note. If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

12.11 B Well steining


(I) PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3080.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 308.00
e) Overhead charges @ 0.2 on (a+b+c+d) 677.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 406.56
Rate perm (a+b+c+d+e+f) 4472.16
say 4472.00
12.11 B (ii) PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3390.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 339.00
e) Overhead charges @ 0.2 on (a+b+c+d) 745.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.48
Rate perm (a+b+c+d+e+f) 4922.28
say 4922.00
12.11 B (iii) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3443.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 344.30
e) Overhead charges @ 0.2 on (a+b+c+d) 757.46
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 454.48
Rate perm (a+b+c+d+e+f) 4999.24
say 4999.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery 3388.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 338.80
e) Overhead charges @ 0.2 on (a+b+c+d) 745.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.22
Rate perm (a+b+c+d+e+f) 4919.38
say 4919.00
12.11 B (iv) PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3667.00
(a+b+c)

Page 17 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) formwork @ 10 per cent of the cost of concrete 366.70
e) Overhead charges @ 0.2 on (a+b+c+d) 806.74
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 484.04
Rate perm (a+b+c+d+e+f) 5324.48
say 5324.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iv)
Per Cum Basic Cost of Labour, Material & Machinery 3614.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 361.40
e) Overhead charges @ 0.2 on (a+b+c+d) 795.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 477.05
Rate perm (a+b+c+d+e+f) 5247.53
say 5248.00
'12.11 B (v) RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3723.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 372.30
e) Overhead charges @ 0.2 on (a+b+c+d) 819.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 491.44
Rate perm (a+b+c+d+e+f) 5405.80
say 5406.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(v)
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 374.00
e) Overhead charges @ 0.2 on (a+b+c+d) 822.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68
Rate perm (a+b+c+d+e+f) 5430.48
say 5430.00
'12.11 B (vi) PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3697.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 369.70
e) Overhead charges @ 0.2 on (a+b+c+d) 813.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 488.00
Rate perm (a+b+c+d+e+f) 5368.04
say 5368.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vi)
Per Cum Basic Cost of Labour, Material & Machinery 3641.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 364.10
e) Overhead charges @ 0.2 on (a+b+c+d) 801.02
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 480.61
Rate perm (a+b+c+d+e+f) 5286.73
say 5287.00
'12.11 B (vii) RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I Using Concrete Mixer

Page 18 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 374.00
e) Overhead charges @ 0.2 on (a+b+c+d) 822.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68
Rate perm (a+b+c+d+e+f) 5430.48
say 5430.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery 3686.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 368.60
e) Overhead charges @ 0.2 on (a+b+c+d) 810.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 486.55
Rate perm (a+b+c+d+e+f) 5352.07
say 5352.00
'12.11 B (viii) RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Case I Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 3816.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 381.60
e) Overhead charges @ 0.2 on (a+b+c+d) 839.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 503.71
Rate perm (a+b+c+d+e+f) 5540.83
say 5541.00
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 3838.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 383.80
e) Overhead charges @ 0.2 on (a+b+c+d) 844.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 506.62
Rate perm (a+b+c+d+e+f) 5572.78
say 5573.00
'12.11 B (ix) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 5000.00 258000.00 M-081
Coarse Sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
Admixture kg 206.00 44.70 9208.20 M-180
b) Labour
Mate day 0.84 151.44 127.21 L-12
Meson day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300xL 2.03 610.20 Lead= 1 ,
P&M-050
Concrete Pump hour 6.00 256.00 1536.00 P&M-007

Page 19 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 31028.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost 46541.40
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d) 102391.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 61434.65
cost of 120 cum = a+b+c+d+e+f 675781.14
Rate per cum = (a+b+c+d+e+f)/120 5631.51
say 5632.00
12.11 C C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 5000.00 27750.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 5.40 916.00 4946.40 M-055
20 mm Aggregate cum 5.40 1028.00 5551.20 M-053
10 mm Aggregate cum 2.70 1005.00 2713.50 M-051
Admixture Kg 18.60 44.70 831.42 M-180
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 357.00 2142.00 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 3719.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost 2489.66
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 11652.74


e) Contractor's profit @ 0.1 on (a+b+c+d) 6991.65
cost of 15 cum = a+b+c+d+e 76908.12
Rate per cum = (a+b+c+d+e)/15 5127.21
say 5127.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(i) pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 5000.00 222000.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
Admixture Kg 148.80 44.70 6651.36 M-180
b) Labour
Mate day 0.88 151.44 133.27 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery

Page 20 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3558.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 19332.88
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 89239.22


e) Contractor's profit @ 0.1 on (a+b+c+d) 53543.53
cost of 120 cum = a+b+c+d+e 588978.86
Rate per cum = (a+b+c+d+e)/120 4908.16
say 4908.00
'12.11 C (ii) PCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 5000.00 29950.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 5.40 916.00 4946.40 M-055
20 mm Aggregate cum 5.40 1028.00 5551.20 M-053
10 mm Aggregate cum 2.70 1005.00 2713.50 M-051
Admixture Kg 21.60 44.70 965.52 M-180
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 357.00 2142.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 3874.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 2606.37
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 12142.91


e) Contractor's profit @ 0.1 on (a+b+c+d) 7285.74
cost of 15 cum = a+b+c+d+e 80143.18
Rate per cum = (a+b+c+d+e)/15 5342.88
say 5343.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(ii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 5000.00 239400.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
Admixture Kg 172.80 44.70 7724.16 M-180

Page 21 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Labour
Mate day 0.88 151.44 133.27 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 20256.52
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 93118.51


e) Contractor's profit @ 0.1 on (a+b+c+d) 55871.11
cost of 120 cum = a+b+c+d+e 614582.16
Rate per cum = (a+b+c+d+e)/120 5121.52
say 5122.00
'12.11 C (iii) PCC Grade M30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 5000.00 30400.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 5.40 916.00 4946.40 M-055
20 mm Aggregate cum 5.40 1028.00 5551.20 M-053
10 mm Aggregate cum 2.70 1005.00 2713.50 M-051
Admixture Kg 21.60 44.70 965.52 M-180
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 357.00 2142.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 3904.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 2628.87
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 12237.41


e) Contractor's profit @ 0.1 on (a+b+c+d) 7342.44
cost of 15 cum = a+b+c+d+e 80766.88
Rate per cum = (a+b+c+d+e)/15 5384.46
say 5384.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Unit = cum
Taking output = 120 cum
a) Material

Page 22 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement tonne 48.64 5000.00 243200.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
Admixture Kg 172.80 44.70 7724.16 M-180
b) Labour
Mate day 0.88 151.44 133.27 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3743.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 20446.52
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 93916.51


e) Contractor's profit @ 0.1 on (a+b+c+d) 56349.91
cost of 120 cum = a+b+c+d+e 619848.96
Rate per cum = (a+b+c+d+e)/120 5165.41
say 5165.00
'12.11 C (iv) PCC Grade M35
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 5000.00 31450.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm Aggregate cum 5.40 916.00 4946.40 M-055
20 mm Aggregate cum 5.40 1028.00 5551.20 M-053
10 mm Aggregate cum 2.70 1005.00 2713.50 M-051
Admixture Kg 21.60 44.70 965.52 M-180
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 357.00 2142.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 3974.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 2681.37
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 12457.91


e) Contractor's profit @ 0.1 on (a+b+c+d) 7474.74
cost of 15 cum = a+b+c+d+e 82222.18
Rate per cum = (a+b+c+d+e)/15 5481.48

Page 23 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 5481.00
12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iv) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 5000.00 251400.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
Admixture Kg 172.80 44.70 7724.16 M-180
b) Labour
Mate day 0.88 151.44 133.27 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 2.03 610.20 P&M-050
lead in Kilometer Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 3812.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 20856.52
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 0.2 on (a+b+c) 95638.51


e) Contractor's profit @ 0.1 on (a+b+c+d) 57383.11
cost of 120 cum = a+b+c+d+e 631214.16
Rate per cum = (a+b+c+d+e)/120 5260.12
say 5260.00
12.11 D Intermediate plug
(i) Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3719.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 743.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 446.28
Rate per cum = (a+b+c+d+e) 4909.08
say 4909.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(i) pump
Per Cum Basic Cost of Labour, Material & Machinery 3558.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 711.60
e) Contractor's profit @ 0.1 on (a+b+c+d) 426.96
Rate per cum = (a+b+c+d+e) 4696.56
say 4697.00
'12.11 D (ii) Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3874.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 774.80

Page 24 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 464.88
Rate per cum = (a+b+c+d+e) 5113.68
say 5114.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 742.40
e) Contractor's profit @ 0.1 on (a+b+c+d) 445.44
Rate per cum = (a+b+c+d+e) 4899.84
say 4900.00
'12.11 D (iii) Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3904.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 780.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 468.48
Rate per cum = (a+b+c+d+e) 5153.28
say 5153.00
12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery 3743.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 748.60
e) Contractor's profit @ 0.1 on (a+b+c+d) 449.16
Rate per cum = (a+b+c+d+e) 4940.76
say 4941.00
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3080.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 616.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 369.60
Rate per cum = (a+b+c+d+e) 4065.60
say 4066.00
'12.11 E (ii) Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3390.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 678.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 406.80
Rate per cum = (a+b+c+d+e) 4474.80
say 4475.00
'12.11 E (iii) Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3667.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 733.40
e) Contractor's profit @ 0.1 on (a+b+c+d) 440.04
Rate per cum = (a+b+c+d+e) 4840.44
say 4840.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iii) pump

Page 25 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3614.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 722.80
e) Contractor's profit @ 0.1 on (a+b+c+d) 433.68
Rate per cum = (a+b+c+d+e) 4770.48
say 4770.00
'12.11 E (iv) Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 3697.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 739.40
e) Contractor's profit @ 0.1 on (a+b+c+d) 443.64
Rate per cum = (a+b+c+d+e) 4880.04
say 4880.00
12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete
(iv) pump
Per Cum Basic Cost of Labour, Material & Machinery 3641.00
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c) 728.20
e) Contractor's profit @ 0.1 on (a+b+c+d) 436.92
Rate per cum = (a+b+c+d+e) 4806.12
say 4806.00
12.11 F Well cap
(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 5000.00 25600.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Form Work @ 4 per cent of a+b+c 2047.49
d) Overhead charges @ 0.2 on (a+b+c) 10646.95
e) Contractor's profit @ 0.1 on (a+b+c+d) 6388.17
cost of 15 cum = a+b+c+d+e 70269.90
Rate per cum = (a+b+c+d+e)/15 4684.66
say 4685.00
12.11 F (i) Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 5000.00 204600.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11

Page 26 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20 P&M-050
Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Formwork @ 4 per cent of (a+b+c) 16112.23
d) Overhead charges @ 0.2 on (a+b+c) 83783.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 50270.17
cost of 120 cum = a+b+c+d+e 552971.82
Rate per cum = (a+b+c+d+e)/120 4608.10
say 4608.00
12.11 F (ii) RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5000.00 30250.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Form Work @ 3.75 per cent of a+b+c 2093.90
d) Overhead charges @ 0.2 on (a+b+c) 11586.24
e) Contractor's profit @ 0.1 on (a+b+c+d) 6951.74
cost of 15 cum = a+b+c+d+e 76469.16
Rate per cum = (a+b+c+d+e)/15 5097.94
say 5098.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 5000.00 242000.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )

Page 27 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20 P&M-050
Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Formwork @ 3.75 per cent of ( a+b+c) 16507.72
d) Overhead charges @ 0.2 on (a+b+c) 91342.71
e) Contractor's profit @ 0.1 on (a+b+c+d) 54805.62
cost of 120 cum = a+b+c+d+e 602861.86
Rate per cum = (a+b+c+d+e)/120 5023.85
say 5024.00
12.11 F (iii) RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5000.00 30500.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Formwork @ 3.5 per cent of (a+b+c) 1963.05
d) Overhead charges @ 0.2 on (a+b+c) 11610.07
e) Contractor's profit @ 0.1 on (a+b+c+d) 6966.04
cost of 15 cum = a+b+c+d+e 76626.45
Rate per cum = (a+b+c+d+e)/15 5108.43
say 5108.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 5000.00 243950.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20 P&M-050
Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Formwork @ 3.5 per cent of (a+b+c) 15475.45
d) Overhead charges @ 0.2 on (a+b+c) 91526.25

Page 28 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 54915.75
cost of 120 cum = a+b+c+d+e 604073.27
Rate per cum = (a+b+c+d+e)/120 5033.94
say 5034.00
12.11 F (iv) RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5000.00 31650.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Formwork @ 3 per cent of (a+b+c) 1717.12
d) Overhead charges @ 0.2 on (a+b+c) 11790.88
e) Contractor's profit @ 0.1 on (a+b+c+d) 7074.53
cost of 15 cum = a+b+c+d+e 77819.81
Rate per cum = (a+b+c+d+e)/15 5187.99
say 5188.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iv)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 5000.00 253200.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader (capacity 1 cum) hour 6.00 806.00 4836.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20 P&M-050
Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Formwork @ 3 per cent of (a+b+c) 13542.17
d) Overhead charges @ 0.2 on (a+b+c) 92989.60
e) Contractor's profit @ 0.1 on (a+b+c+d) 55793.76
cost of 120 cum = a+b+c+d+e 613731.34
Rate per cum = (a+b+c+d+e)/120 5114.43
say 5114.00

Page 29 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F (v) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 5000.00 261000.00 M-081
Coarse Sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
Admixture kg 206.00 44.70 9208.20 M-180
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader 1 cum capacity hour 6.00 806.00 4836.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300.L 2.03 610.20 P&M-050
Lead= 1
km
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Formwork @ 3 per cent on cost of concrete i.e. cost of 14052.42
material, labour and machinery
d) Overhead charges @ 0.2 on (a+b+c) 96493.29
e) Contractor's profit @ 0.1 on (a+b+c+d) 57895.97
cost of 120 cum = a+b+c+d+e 636855.69
Rate per cum = (a+b+c+d+e)/120 5307.13
say 5307.00
12.12 Section Sinking of 6 m external diameter well (other than pneumatic
1200 method of sinking) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 151.44 18.17 L-12
Sinker ( skilled ) day 1.00 164.69 164.69 L-15
Sinking helper ( semi-skilled ) day 2.00 230.00 460.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 1073.50 2147.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 214.70
c) Overhead charges @ 0.2 on (a+b) 600.91
d) Contractor's profit @ 0.1 on (a+b+c) 360.55
Rate per metre = (a+b+c+d) 3966.02
say 3966.00
12.12 A (ii) Beyond 3m upto 10m depth

Page 30 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 151.44 22.72 L-12
Sinker day 1.25 164.69 205.86 L-15
Sinking helper ( semi-skilled ) day 2.50 230.00 575.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1073.50 3220.50 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 322.05
c) Overhead charges @ 0.2 on (a+b) 869.23
d) Contractor's profit @ 0.1 on (a+b+c) 521.54
Rate per metre = (a+b+c+d) 5736.89
say 5737.00
12.12 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 6024.00
12th m 5% 6325.00
13th m 5% 6641.00
14th m 5% 6973.00
15th m 5% 7322.00
16th m 5% 7688.00
17th m 5% 8072.00
18th m 5% 8476.00
19th m 5% 8900.00
20th m 5% 9345.00
Total Cost from 10m upto 20m 75766.00
Avg Rate per metre 7577.00
12.12 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 10046.00 12055.00
22nd m 7.5% 10799.00 12959.00
23rd m 7.5% 11609.00 13931.00
24th m 7.5% 12480.00 14976.00
25th m 7.5% 13416.00 16099.00
26th m 7.5% 14422.00 17306.00
27th m 7.5% 15504.00 18605.00
28th m 7.5% 16667.00 20000.00
29th m 7.5% 17917.00 21500.00
30th m 7.5% 19261.00 23113.00
Total Cost from 20m upto 30m 142121.00 170544.00
Avg Rate per metre 14212.00 17054.00
12.12 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
31st m 10% 21187.00 25424.00
32nd 10% 23306.00 27967.00
33rd m 10% 25637.00 30764.00
34th m 10% 28201.00 33841.00
35th m 10% 31021.00 37225.00
36th m 10% 34123.00 40948.00
37th m 10% 37535.00 45042.00
38th m 10% 41289.00 49547.00
39th m 10% 45418.00 54502.00

Page 31 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
40th m 10% 49960.00 59952.00
Total Cost from 30m upto 40m 337677.00 405212.00
Avg Rate per metre 33768.00 40521.00
12.12 B Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 151.44 22.72 L-12
Sinker ( skilled ) day 1.50 164.69 247.04 L-15
Sinking helper ( semi-skilled ) day 2.25 230.00 517.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1073.50 3220.50 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 322.05
c) Overhead charges @ 0.2 on (a+b) 865.96
d) Contractor's profit @ 0.1 on (a+b+c) 519.58
Rate per metre = (a+b+c+d) 5715.34
say 5715.00
12.12 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 151.44 45.43 L-12
Sinker day 3.00 164.69 494.07 L-15
Sinking helper ( semi-skilled ) day 4.50 230.00 1035.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 740.15 1480.30 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 792.13
c) Overhead charges @ 0.2 on (a+b) 2057.59
d) Contractor's profit @ 0.1 on (a+b+c) 1234.55
Rate per metre = (a+b+c+d) 13580.07
say 13580.00
12.12 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 14259.00 14972.00
12th m 5% 14972.00 15721.00
13th m 5% 15721.00 16507.00
14th m 5% 16507.00 17332.00
15th m 5% 17332.00 18199.00
16th m 5% 18199.00 19109.00
17th m 5% 19109.00 20064.00
18th m 5% 20064.00 21067.00
19th m 5% 21067.00 22120.00
20th m 5% 22120.00 23226.00
Total Cost from 10m upto 20m 179350.00 188317.00
Avg Rate per metre 17935.00 18832.00
12.12 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 32 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b Add 5 per cent of cost for dewatering of the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
21st m 7.5% 23779.00 29724.00 31210.00
22nd m 7.5% 25562.00 31953.00 33551.00
23rd m 7.5% 27479.00 34349.00 36066.00
24th m 7.5% 29540.00 36925.00 38771.00
25th m 7.5% 31756.00 39695.00 41680.00
26th m 7.5% 34138.00 42673.00 44807.00
27th m 7.5% 36698.00 45873.00 48167.00
28th m 7.5% 39450.00 49313.00 51779.00
29th m 7.5% 42409.00 53011.00 55662.00
30th m 7.5% 45590.00 56988.00 59837.00
Total Cost from 20m upto 30m 336401.00 420504.00 441530.00
Avg Rate per metre 33640.00 42050.00 44153.00
12.12 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 50149.00 60179.00 63188.00
32nd 10% 55164.00 66197.00 69507.00
33rd m 10% 60680.00 72816.00 76457.00
34th m 10% 66748.00 80098.00 84103.00
35th m 10% 73423.00 88108.00 92513.00
36th m 10% 80765.00 96918.00 101764.00
37th m 10% 88842.00 106610.00 111941.00
38th m 10% 97726.00 117271.00 123135.00
39th m 10% 107499.00 128999.00 135449.00
40th m 10% 118249.00 141899.00 148994.00
Total Cost from 30m upto 40m 799245.00 959095.00 1007051.00
Avg Rate per metre 79925.00 95910.00 100705.00
12.12 C Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 151.44 139.32 L-12
Sinker ( skilled ) day 3.00 164.69 494.07 L-15
Sinking helper ( semi-skilled ) day 20.00 230.00 4600.00 L-14
Diver day 0.50 264.50 132.25 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1073.50 4294.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 740.15 2590.53 P&M-063
Consumables in sinking @ 10 per cent of (b) 688.45
Add for dewatering @ of 5 per cent of (a+b), if 646.93
required
c) Overhead charges @ 0.2 on (a+b) 2717.11
d) Contractor's profit @ 0.1 on (a+b+c) 1630.27
Rate per metre = (a+b+c+d) 17932.93
say 17933.00

Page 33 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.12 D Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 146.00 584.00 M-104
Electric Detonators each 18.00 14.56 262.08 M-094/100
b) Labour
Mate day 1.56 151.44 236.25 L-12
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 12.00 136.69 1640.28 L-13
Mazdoor (Skilled) day 4.00 164.69 658.76 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 740.15 1480.30 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 552.59
Consumables in sinking @ 10 per cent of cost of (b). 792.13
d) Overhead charges @ 0.2 on (a+b+c) 2648.50
e) Contractor's profit @ 0.1 on (a+b+c+d) 1589.10
Rate per metre = (a+b+c+d+e) 17480.11
say 17480.00
12.13 Section Sinking of 7 m external diameter well ( other than pneumatic
1200 method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 151.44 22.72 L-12
Sinker ( skilled ) day 1.25 164.69 205.86 L-15
Sinking helper ( semi-skilled ) day 2.50 230.00 575.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 1073.50 3488.88 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 348.89
c) Overhead charges @ 0.2 on (a+b) 928.27
d) Contractor's profit @ 0.1 on (a+b+c) 464.13
Rate per metre = (a+b+c+d) 6033.74
12.13 A (ii) Beyond 3m upto 10m depth 12067.49
Rate of sinking = 0.22 m per hour. say 12067.00
a) Labour
Mate day 0.18 151.44 27.26 L-12
Sinker day 1.50 164.69 247.04 L-15
Sinking helper ( semi-skilled ) day 3.00 230.00 690.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1073.50 4830.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 483.08
c) Overhead charges @ 0.2 on (a+b) 1255.62

Page 34 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 753.37
Rate per metre = (a+b+c+d) 8287.12
say 8287.00
12.13 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 8701.00
12th m 5% 9136.00
13th m 5% 9593.00
14th m 5% 10073.00
0.165 15th m 5% 10577.00
16th m 5% 11106.00
17th m 5% 11661.00
18th m 5% 12244.00
19th m 5% 12856.00
20th m 5% 13499.00
Total Cost from 10m upto 20m 109446.00
Avg Rate per metre 10945.00
12.13 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour). for Kentledge
21st m 7.5% 14511.00 17413.00
22nd m 7.5% 15599.00 18719.00
23rd m 7.5% 16769.00 20123.00
24th m 7.5% 18027.00 21632.00
25th m 7.5% 19379.00 23255.00
26th m 7.5% 20832.00 24998.00
27th m 7.5% 22394.00 26873.00
28th m 7.5% 24074.00 28889.00
29th m 7.5% 25880.00 31056.00
30th m 7.5% 27821.00 33385.00
Total Cost from 20m upto 30m 205286.00 246343.00
Avg Rate per metre 20529.00 24634.00
12.13 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 30603.00 36724.00
32nd 10% 33663.00 40396.00
33rd m 10% 37029.00 44435.00
34th m 10% 40732.00 48878.00
35th m 10% 44805.00 53766.00
36th m 10% 49286.00 59143.00
37th m 10% 54215.00 65058.00
38th m 10% 59637.00 71564.00
39th m 10% 65601.00 78721.00
40th m 10% 72161.00 86593.00
Total Cost from 30m upto 40m 487732.00 585278.00
Avg Rate per metre 48773.00 58528.00
12.13 B Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour

Page 35 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.18 151.44 27.26 L-12
Sinker ( skilled ) day 1.50 164.69 247.04 L-15
Sinking helper ( semi-skilled ) day 3.00 230.00 690.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1073.50 4830.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 483.08
d) Overhead charges @ 0.2 on (a+b) 1255.62
e) Contractor's profit @ 0.1 on (a+b+c) 753.37
Rate per metre = (a+b+c+d) 8287.12
say 8287.00
12.13 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 151.44 39.37 L-12
Sinker day 2.00 164.69 329.38 L-15
Sinking helper ( semi-skilled ) day 4.00 230.00 920.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 740.15 644.10 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 708.51
c) Overhead charges @ 0.2 on (a+b) 1816.47
d) Contractor's profit @ 0.1 on (a+b+c) 1089.88
Rate per metre = (a+b+c+d) 11988.72
say 11989.00
12.13 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 12588.00 13217.00
12th m 5% 13217.00 13878.00
13th m 5% 13878.00 14572.00
14th m 5% 14572.00 15301.00
15th m 5% 15301.00 16066.00
16th m 5% 16066.00 16869.00
17th m 5% 16869.00 17712.00
18th m 5% 17712.00 18598.00
19th m 5% 18598.00 19528.00
20th m 5% 19528.00 20504.00
Total Cost from 10m upto 20m 158329.00 166245.00
Avg Rate per metre 15833.00 16625.00
12.13 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 20993.00 26241.00 27553.00
32nd 7.5% 22567.00 28209.00 29619.00
33rd m 7.5% 24260.00 30325.00 31841.00
34th m 7.5% 26080.00 32600.00 34230.00
35th m 7.5% 28036.00 35045.00 36797.00

Page 36 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
36th m 7.5% 30139.00 37674.00 39558.00
37th m 7.5% 32399.00 40499.00 42524.00
38th m 7.5% 34829.00 43536.00 45713.00
39th m 7.5% 37441.00 46801.00 49141.00
40th m 7.5% 40249.00 50311.00 52827.00
Total Cost from 30m upto 40m 296993.00 371241.00 389803.00
Avg Rate per metre 29699.00 37124.00 38980.00
12.13 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 44274.00 53129.00 55785.00
32nd 10% 48701.00 58441.00 61363.00
33rd m 10% 53571.00 64285.00 67499.00
34th m 10% 58928.00 70714.00 74250.00
35th m 10% 64821.00 77785.00 81674.00
36th m 10% 71303.00 85564.00 89842.00
37th m 10% 78433.00 94120.00 98826.00
38th m 10% 86276.00 103531.00 108708.00
39th m 10% 94904.00 113885.00 119579.00
40th m 10% 104394.00 125273.00 131537.00
Total Cost from 30m upto 40m 705605.00 846727.00 889063.00
Avg Rate per metre 70561.00 84673.00 88906.00
12.13 C Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 151.44 87.84 L-12
Sinker ( skilled ) day 4.00 164.69 658.76 L-15
Sinking helper ( semi-skilled ) day 10.00 230.00 2300.00 L-14
Diver day 0.75 264.50 198.38 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1073.50 4830.75 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 740.15 2775.56 P&M-063
Consumables in sinking @ 10 per cent of (b) 760.63
Add for dewatering @ of 5 per cent of (a+b), if 542.56
required
c) Overhead charges @ 0.2 on (a+b) 2430.90
d) Contractor's profit @ 0.1 on (a+b+c) 1458.54
Rate per metre = (a+b+c+d) 16043.91
say 16044.00
12.13 D Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 146.00 1022.00 M-104
Electric Detonators each 30.00 14.56 436.80 M-094/100
b) Labour
Mate day 1.60 151.44 242.30 L-12

Page 37 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 18.00 136.69 2460.42 L-13
Mazdoor (Skilled) day 4.00 164.69 658.76 L-15
Diver day 0.50 264.50 132.25 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 740.15 1480.30 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 600.51
Consumables in sinking @ 10 per cent of cost of (b). 852.18
d) Overhead charges @ 0.2 on (a+b+c) 2984.33
e) Contractor's profit @ 0.1 on (a+b+c+d) 1790.60
Rate per metre = (a+b+c+d+e) 19696.58
say 19697.00
12.14 Section Sinking of 8 m external diameter well ( other than pneumatic
1200 method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 151.44 27.26 L-12
Sinker ( skilled ) day 1.50 164.69 247.04 L-15
Sinking helper ( semi-skilled ) day 3.00 230.00 690.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1073.50 4294.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 429.40
c) Overhead charges @ 0.2 on (a+b) 1137.54
d) Contractor's profit @ 0.1 on (a+b+c) 682.52
Rate per metre = (a+b+c+d) 7507.76
say 7508.00
12.14 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 151.44 37.86 L-12
Sinker day 1.75 164.69 288.21 L-15
Sinking helper ( semi-skilled ) day 3.50 230.00 805.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1073.50 5367.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 536.75
c) Overhead charges @ 0.2 on (a+b) 1407.06
d) Contractor's profit @ 0.1 on (a+b+c) 844.24
Rate per metre = (a+b+c+d) 9286.62
say 9287.00
12.14 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 9751.00
12th m 5% 10239.00

Page 38 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13th m 5% 10751.00
14th m 5% 11289.00
15th m 5% 11853.00
16th m 5% 12446.00
17th m 5% 13068.00
18th m 5% 13721.00
19th m 5% 14407.00
20th m 5% 15127.00
Total Cost from 10m upto 20m 122652.00
Avg Rate per metre 12265.00
12.14 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 16262.00 19514.00
22nd m 7.5% 17482.00 20978.00
23rd m 7.5% 18793.00 22552.00
24th m 7.5% 20202.00 24242.00
25th m 7.5% 21717.00 26060.00
26th m 7.5% 23346.00 28015.00
27th m 7.5% 25097.00 30116.00
28th m 7.5% 26979.00 32375.00
29th m 7.5% 29002.00 34802.00
30th m 7.5% 31177.00 37412.00
Total Cost from 20m upto 30m 230057.00 276066.00
Avg Rate per metre 23006.00 27607.00
12.14 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 34295.00 41154.00
32nd 10% 37725.00 45270.00
33rd m 10% 41498.00 49798.00
34th m 10% 45648.00 54778.00
35th m 10% 50213.00 60256.00
36th m 10% 55234.00 66281.00
37th m 10% 60757.00 72908.00
38th m 10% 66833.00 80200.00
39th m 10% 73516.00 88219.00
40th m 10% 80868.00 97042.00
Total Cost from 30m upto 40m 80868.00 97042.00
Avg Rate per metre 8087.00 9704.00
12.14 B Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 151.44 33.32 L-12
Sinker ( skilled ) day 2.00 164.69 329.38 L-15
Sinking helper ( semi-skilled ) hour 3.50 230.00 805.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of 5.50 1073.50 5904.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 590.43
c) Overhead charges @ 0.2 on (a+b) 1532.47

Page 39 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 919.48
Rate per metre = (a+b+c+d) 10114.33
say 10114.00
12.14 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 151.44 48.46 L-12
Sinker day 2.50 164.69 411.73 L-15
Sinking helper ( semi-skilled ) day 4.50 230.00 1035.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 740.15 2590.53 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 903.15
c) Overhead charges @ 0.2 on (a+b) 2285.97
d) Contractor's profit @ 0.1 on (a+b+c) 1371.58
Rate per metre = (a+b+c+d) 15087.42
say 15087.00
12.14 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 15842.00 16634.00
12th m 5% 16634.00 17466.00
13th m 5% 17466.00 18339.00
14th m 5% 18339.00 19256.00
15th m 5% 19256.00 20219.00
16th m 5% 20219.00 21230.00
17th m 5% 21230.00 22292.00
18th m 5% 22292.00 23407.00
19th m 5% 23407.00 24577.00
20th m 5% 24577.00 25806.00
Total Cost from 10m upto 20m 199262.00 209226.00
Avg Rate per metre 19926.00 20923.00
12.14 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 26420.00 33025.00 34676.00
32nd 7.5% 28402.00 35503.00 37278.00
33rd m 7.5% 30532.00 38165.00 40073.00
34th m 7.5% 32822.00 41028.00 43079.00
35th m 7.5% 35284.00 44105.00 46310.00
36th m 7.5% 37930.00 47413.00 49784.00
37th m 7.5% 40775.00 50969.00 53517.00
38th m 7.5% 43833.00 54791.00 57531.00
39th m 7.5% 47120.00 58900.00 61845.00
40th m 7.5% 50654.00 63318.00 66484.00
Total Cost from 30m upto 40m 373772.00 467217.00 490577.00
Avg Rate per metre 37377.00 46722.00 49058.00
12.14 B (v) Beyond 30m upto 40 m

Page 40 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 55719.00 66863.00 70206.00
32nd 10% 61291.00 73549.00 77226.00
33rd m 10% 67420.00 80904.00 84949.00
34th m 10% 74162.00 88994.00 93444.00
35th m 10% 81578.00 97894.00 102789.00
36th m 10% 89736.00 107683.00 113067.00
37th m 10% 98710.00 118452.00 124375.00
38th m 10% 108581.00 130297.00 136812.00
39th m 10% 119439.00 143327.00 150493.00
40th m 10% 131383.00 157660.00 165543.00
Total Cost from 30m upto 40m 888019.00 1065623.00 1118904.00
Avg Rate per metre 88802.00 106562.00 111890.00
12.14 C Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 151.44 102.98 L-12
Sinker ( skilled ) day 4.00 164.69 658.76 L-15
Sinking helper ( semi-skilled ) day 12.00 230.00 2760.00 L-14
Diver day 1.00 264.50 264.50 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1073.50 5367.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 740.15 2775.56 P&M-063
Consumables in sinking @ 10 per cent of (b) 814.31
Add for dewatering @ of 5 per cent of (a+b), if 637.18
required
c) Overhead charges @ 0.2 on (a+b) 2676.16
d) Contractor's profit @ 0.1 on (a+b+c) 1605.69
Rate per metre = (a+b+c+d) 17662.64
say 17663.00
12.14 D Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 146.00 1168.00 M-104
Electric Detonators each 32.00 14.56 465.92 M-094/100
b) Labour
Mate day 1.09 151.44 165.07 L-12
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 20.00 136.69 2733.80 L-13
Mazdoor (Skilled) day 4.00 164.69 658.76 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 740.15 1480.30 P&M-063
breaker/Jack hammer for drilling.

Page 41 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Dewatering @ 5 per cent of cost of (b+c), if required. 603.70
Consumables in sinking @ 10 per cent of cost of (b). 415.28
d) Overhead charges @ 0.2 on (a+b+c) 2945.39
e) Contractor's profit @ 0.1 on (a+b+c+d) 1767.23
Rate per metre = (a+b+c+d+e) 19439.58
say 19440.00
12.15 Section Sinking of 9 m external diameter well ( other than pneumatic
1200 method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 151.44 28.77 L-12
Sinker ( skilled ) day 1.50 164.69 247.04 L-15
Sinking helper ( semi-skilled ) day 3.25 230.00 747.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1073.50 4294.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 429.40
c) Overhead charges @ 0.2 on (a+b) 1149.34
d) Contractor's profit @ 0.1 on (a+b+c) 689.61
Rate per metre = (a+b+c+d) 7585.66
say 7586.00
12.15 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 151.44 40.89 L-12
Sinker day 1.75 164.69 288.21 L-15
Sinking helper ( semi-skilled ) day 4.00 230.00 920.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1073.50 5904.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 590.43
c) Overhead charges @ 0.2 on (a+b) 1548.75
d) Contractor's profit @ 0.1 on (a+b+c) 929.25
Rate per metre = (a+b+c+d) 10221.78
say 10222.00
12.15 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 10733.00
12th m 5% 11270.00
13th m 5% 11834.00
14th m 5% 12426.00
15th m 5% 13047.00
16th m 5% 13699.00
17th m 5% 14384.00
18th m 5% 15103.00
19th m 5% 15858.00
20th m 5% 16651.00
Total Cost from 10m upto 20m 135005.00
Avg Rate per metre 13501.00

Page 42 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.15 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 17899.83 21480.00
22nd m 7.5% 19242.00 23090.00
23rd m 7.5% 20685.00 24822.00
24th m 7.5% 22236.00 26683.00
25th m 7.5% 23904.00 28685.00
26th m 7.5% 25697.00 30836.00
27th m 7.5% 27624.00 33149.00
28th m 7.5% 29696.00 35635.00
29th m 7.5% 31923.00 38308.00
30th m 7.5% 34317.00 41180.00
Total Cost from 20m upto 30m 253223.83 303868.00
Avg Rate per metre 25322.00 30387.00
12.15 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 37748.70 45298.00
32nd 10% 41524.00 49829.00
33rd m 10% 45676.00 54811.00
34th m 10% 50244.00 60293.00
35th m 10% 55268.00 66322.00
36th m 10% 60795.00 72954.00
37th m 10% 66875.00 80250.00
38th m 10% 73563.00 88276.00
39th m 10% 80919.00 97103.00
40th m 10% 89011.00 106813.00
Total Cost from 30m upto 40m 601623.70 721949.00
Avg Rate per metre 60162.00 72195.00
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 151.44 36.35 L-12
Sinker ( skilled ) day 2.25 164.69 370.55 L-15
Sinking helper ( semi-skilled ) day 3.75 230.00 862.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1073.50 6172.63 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 617.26
c) Overhead charges @ 0.2 on (a+b) 1611.86
d) Contractor's profit @ 0.1 on (a+b+c) 967.11
Rate per metre = (a+b+c+d) 10638.26
say 10638.00
12.15 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 151.44 51.49 L-12
Sinker day 2.50 164.69 411.73 L-15
Sinking helper ( semi-skilled ) day 5.00 230.00 1150.00 L-14
b) Machinery

Page 43 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Hire & running charges of crane with grab bucket of hour 6.50 1073.50 6977.75 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.75 740.15 2775.56 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 975.33
c) Overhead charges @ 0.2 on (a+b) 2468.37
d) Contractor's profit @ 0.1 on (a+b+c) 1481.02
Rate per metre = (a+b+c+d) 16291.25
say 16291.00
12.15 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 17106.00 17961.00
12th m 5% 17961.00 18859.00
13th m 5% 18859.00 19802.00
14th m 5% 19802.00 20792.00
15th m 5% 20792.00 21832.00
16th m 5% 21832.00 22924.00
17th m 5% 22924.00 24070.00
18th m 5% 24070.00 25274.00
19th m 5% 25274.00 26538.00
20th m 5% 26538.00 27865.00
Total Cost from 10m upto 20m 215158.00 225917.00
Avg Rate per metre 21516.00 22592.00
12.15 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 28528.00 35660.00 37443.00
32nd 7.5% 30668.00 38335.00 40252.00
33rd m 7.5% 32968.00 41210.00 43271.00
34th m 7.5% 35441.00 44301.00 46516.00
35th m 7.5% 38099.00 47624.00 50005.00
36th m 7.5% 40956.00 51195.00 53755.00
37th m 7.5% 44028.00 55035.00 57787.00
38th m 7.5% 47330.00 59163.00 62121.00
39th m 7.5% 50880.00 63600.00 66780.00
40th m 7.5% 54696.00 68370.00 71789.00
Total Cost from 30m upto 40m 403594.00 504493.00 529719.00
Avg Rate per metre 40359.00 50449.00 52972.00
12.15 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 60166.00 72199.00 75809.00
32nd 10% 66183.00 79420.00 83391.00
33rd m 10% 72801.00 87361.00 91729.00
34th m 10% 80081.00 96097.00 100902.00

Page 44 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
35th m 10% 88089.00 105707.00 110992.00
36th m 10% 96898.00 116278.00 122092.00
37th m 10% 106588.00 127906.00 134301.00
38th m 10% 117247.00 140696.00 147731.00
39th m 10% 128972.00 154766.00 162504.00
40th m 10% 141869.00 170243.00 178755.00
Total Cost from 30m upto 40m 958894.00 1150673.00 1208206.00
Avg Rate per metre 95889.00 115067.00 120821.00
12.15 C Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 151.44 115.09 L-12
Sinker ( skilled ) day 4.00 164.69 658.76 L-15
Sinking helper ( semi-skilled ) day 14.00 230.00 3220.00 L-14
Diver day 1.20 264.50 317.40 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1073.50 6977.75 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 740.15 2960.60 P&M-063
Consumables in sinking @ 10 per cent of (b) 993.84
Add for dewatering @ of 5 per cent of (a+b), if 1524.34
required
c) Overhead charges @ 0.2 on (a+b) 3353.56
d) Contractor's profit @ 0.1 on (a+b+c) 2012.13
Rate per metre = (a+b+c+d) 22133.47
say 22133.00
12.15 D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 146.00 1460.00 M-104
Electric Detonators each 40.00 14.56 582.40 M-094/100
b) Labour
Mate day 1.17 151.44 177.18 L-12
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 22.00 136.69 3007.18 L-13
Mazdoor (Skilled) day 4.00 164.69 658.76 L-15
Diver day 1.00 264.50 264.50 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1073.50 7514.50 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.50 740.15 1850.38 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 703.38
Consumables in sinking @ 10 per cent of cost of (b). 470.27
d) Overhead charges @ 0.2 on (a+b+c) 3456.74
e) Contractor's profit @ 0.1 on (a+b+c+d) 2074.04
Rate per metre = (a+b+c+d+e) 22814.46
say 22814.00

Page 45 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.16 1200 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 151.44 30.29 L-12
Sinker ( skilled ) day 1.50 164.69 247.04 L-15
Sinking helper ( semi-skilled ) day 3.50 230.00 805.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1073.50 5367.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 536.75
c) Overhead charges @ 0.2 on (a+b) 1397.31
d) Contractor's profit @ 0.1 on (a+b+c) 838.39
Rate per metre = (a+b+c+d) 9222.28
say 9222.00
12.16 A (ii) Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 151.44 46.95 L-12
Sinker day 2.00 164.69 329.38 L-15
Sinking helper ( semi-skilled ) day 4.25 230.00 977.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1073.50 6172.63 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 617.26
c) Overhead charges @ 0.2 on (a+b) 1628.74
d) Contractor's profit @ 0.1 on (a+b+c) 977.25
Rate per metre = (a+b+c+d) 10749.70
say 10750.00
12.16 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 11287.00
12th m 5% 11851.00
13th m 5% 12444.00
14th m 5% 13066.00
15th m 5% 13719.00
16th m 5% 14405.00
17th m 5% 15125.00
18th m 5% 15881.00
19th m 5% 16675.00
20th m 5% 17509.00
Total Cost from 10m upto 20m 141962.00
Avg Rate per metre 14196.00
12.16 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 18822.00 22586.00

Page 46 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
22nd m 7.5% 20234.00 24281.00
23rd m 7.5% 21752.00 26102.00
24th m 7.5% 23383.00 28060.00
25th m 7.5% 25137.00 30164.00
26th m 7.5% 27022.00 32426.00
27th m 7.5% 29049.00 34859.00
28th m 7.5% 31228.00 37474.00
29th m 7.5% 33570.00 40284.00
30th m 7.5% 36088.00 43306.00
Total Cost from 20m upto 30m 266285.00 319542.00
Avg Rate per metre 26629.00 31954.00
12.16 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 39697.00 47636.00
32nd 10% 43667.00 52400.00
33rd m 10% 48034.00 57641.00
34th m 10% 52837.00 63404.00
35th m 10% 58121.00 69745.00
36th m 10% 63933.00 76720.00
37th m 10% 70326.00 84391.00
38th m 10% 77359.00 92831.00
39th m 10% 85095.00 102114.00
40th m 10% 93605.00 112326.00
Total Cost from 30m upto 40m 632674.00 759208.00
Avg Rate per metre 63267.00 75921.00
12.16 B Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 151.44 37.86 L-12
Sinker ( skilled ) day 2.50 164.69 411.73 L-15
Sinking helper ( semi-skilled ) day 5.50 230.00 1265.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 644.10
c) Overhead charges @ 0.2 on (a+b) 1759.94
d) Contractor's profit @ 0.1 on (a+b+c) 1055.96
Rate per metre = (a+b+c+d) 11615.58
say 11616.00
12.16 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 151.44 60.58 L-12
Sinker day 3.00 164.69 494.07 L-15
Sinking helper ( semi-skilled ) day 5.50 230.00 1265.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 740.15 2960.60 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 940.16
c) Overhead charges @ 0.2 on (a+b) 2432.28

Page 47 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 1459.37
Rate per metre = (a+b+c+d) 16053.06
say 16053.00
12.16 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 16856.00 17699.00
12th m 5% 17699.00 18584.00
13th m 5% 18584.00 19513.00
14th m 5% 19513.00 20489.00
15th m 5% 20489.00 21513.00
16th m 5% 21513.00 22589.00
17th m 5% 22589.00 23718.00
18th m 5% 23718.00 24904.00
19th m 5% 24904.00 26149.00
20th m 5% 26149.00 27456.00
Total Cost from 10m upto 20m 212014.00 222614.00
Avg Rate per metre 21201.00 22261.00
12.16 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 28110.00 35138.00 36895.00
32nd 7.5% 30218.00 37773.00 39662.00
33rd m 7.5% 32484.00 40605.00 42635.00
34th m 7.5% 34920.00 43650.00 45833.00
35th m 7.5% 37539.00 46924.00 49270.00
36th m 7.5% 40354.00 50443.00 52965.00
37th m 7.5% 43381.00 54226.00 56937.00
38th m 7.5% 46635.00 58294.00 61209.00
39th m 7.5% 50133.00 62666.00 65799.00
40th m 7.5% 53893.00 67366.00 70734.00
Total Cost from 30m upto 40m 397667.00 497085.00 521939.00
Avg Rate per metre 39767.00 49709.00 52194.00
12.16 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 59282.00 71138.00 74695.00
32nd 10% 65210.00 78252.00 82165.00
33rd m 10% 71731.00 86077.00 90380.85
34th m 10% 78904.00 94685.00 99419.25
35th m 10% 86794.00 104153.00 109360.65
36th m 10% 95473.00 114568.00 120296.40
37th m 10% 105020.00 126024.00 132325.20
38th m 10% 115522.00 138626.00 145557.30
39th m 10% 127074.00 152489.00 160113.45

Page 48 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
40th m 10% 139781.00 167737.00 176123.85
Total Cost from 30m upto 40m 944791.00 1133749.00 1190436.95
Avg Rate per metre 94479.00 113375.00 119044.00
12.16 C Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 151.44 130.24 L-12
Sinker ( skilled ) day 4.00 164.69 658.76 L-15
Sinking helper ( semi-skilled ) day 16.00 230.00 3680.00 L-14
Diver day 1.40 264.50 370.30 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1073.50 7514.50 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 740.15 3145.64 P&M-063
Consumables in sinking @ 10 per cent of (b) 1066.01
Add for dewatering @ 5 per cent of cost, if required 586.31
c) Overhead charges @ 0.2 on (a+b) 3430.35
d) Contractor's profit @ 0.1 on (a+b+c) 2058.21
Rate per metre = (a+b+c+d) 22640.32
say 22640.00
12.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 146.00 1606.00 M-104
Electric Detonators each. 44.00 14.56 640.64 M-094/100
b) Labour
Mate day 1.27 151.44 192.33 L-12
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 24.00 136.69 3280.56 L-13
Mazdoor (Skilled) day 4.00 164.69 658.76 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 1073.50 9124.75 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 740.15 2220.45 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 567.26
Consumables in sinking @ 10 per cent of cost of 1663.92
(b+c).
d) Overhead charges @ 0.2 on (a+b+c) 4109.96
e) Contractor's profit @ 0.1 on (a+b+c+d) 2465.98
Rate per metre = (a+b+c+d+e) 27125.73
say 27126.00
12.17 1200 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil

Page 49 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 151.44 31.80 L-12
Sinker ( skilled ) day 1.50 164.69 247.04 L-15
Sinking helper (semi-skilled) day 3.30 230.00 759.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 644.10
d) Overhead charges @ 0.2 on (a+b+c) 1624.59
e) Contractor's profit @ 0.1 on (a+b+c+d) 974.75
Cost for 0.5m = a+b+c+d 10722.28
Rate per metre = (a+b+c+d)/0.50 21444.55
say 21445.00
12.17 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 151.44 48.46 L-12
Sinker day 2.00 164.69 329.38 L-15
Sinking helper (semi-skilled) day 4.50 230.00 1035.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1073.50 4294.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 429.40
c) Overhead charges @ 0.2 on (a+b+c) 1227.25
d) Contractor's profit @ 0.1 on (a+b+c+d) 736.35
Cost for 0.5m = a+b+c+d 8099.84
Rate per metre = (a+b+c+d)/0.50 16199.68
say 16200.00
12.17 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 17010.00
12th m 5% 17861.00
13th m 5% 18754.00
14th m 5% 19692.00
15th m 5% 20677.00
16th m 5% 21711.00
17th m 5% 22797.00
18th m 5% 23937.00
19th m 5% 25134.00
20th m 5% 26391.00
Total Cost from 10m upto 20m 213964.00
Avg Rate per metre 21396.00
12.17 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 28370.00 34044.00
22nd m 7.5% 30498.00 36598.00
23rd m 7.5% 32785.00 39342.00
24th m 7.5% 35244.00 42293.00
25th m 7.5% 37887.00 45464.00
26th m 7.5% 40729.00 48875.00
27th m 7.5% 43784.00 52541.00
28th m 7.5% 47068.00 56482.00

Page 50 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
29th m 7.5% 50598.00 60718.00
30th m 7.5% 54393.00 65272.00
Total Cost from 20m upto 30m 401356.00 481629.00
Avg Rate per metre 40136.00 48163.00
12.17 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 59832.00 71798.00
32nd 10% 65815.00 78978.00
33rd m 10% 72397.00 86876.00
34th m 10% 79637.00 95564.00
35th m 10% 87601.00 105121.00
36th m 10% 96361.00 115633.00
37th m 10% 105997.00 127196.00
38th m 10% 116597.00 139916.00
39th m 10% 128257.00 153908.00
40th m 10% 141083.00 169300.00
Total Cost from 30m upto 40m 953577.00 1144290.00
Avg Rate per metre 95358.00 114429.00
12.17 B Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 151.44 39.37 L-12
Sinker ( skilled ) day 2.50 164.69 411.73 L-15
Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1073.50 5367.50 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 536.75
c) Overhead charges @ 0.2 on (a+b) 1455.07
d) Contractor's profit @ 0.1 on (a+b+c) 873.04
Cost for 0.5m = a+b+c+d 9603.46
Rate per metre = (a+b+c+d)/0.50 19206.92
say 19207.00
12.17 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 151.44 65.12 L-12
Sinker day 3.50 164.69 576.42 L-15
Sinking helper (semi-skilled) day 5.75 230.00 1322.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 740.15 3145.64 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 958.66
c) Overhead charges @ 0.2 on (a+b) 2501.87
d) Contractor's profit @ 0.1 on (a+b+c) 1501.12
Cost for 0.5m = a+b+c+d 16512.32
Rate per metre = (a+b+c+d)/0.50 33024.65
say 33025.00
12.17 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 51 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 34676.00 36410.00
12th m 5% 36410.00 38231.00
13th m 5% 38231.00 40143.00
14th m 5% 40143.00 42150.00
15th m 5% 42150.00 44258.00
16th m 5% 44258.00 46471.00
17th m 5% 46471.00 48795.00
18th m 5% 48795.00 51235.00
19th m 5% 51235.00 53797.00
20th m 5% 53797.00 56487.00
Total Cost from 10m upto 20m 436166.00 457974.00
Avg Rate per metre 43617.00 45797.00
12.17 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 57832.00 72290.00 75905.00
32nd 7.5% 62169.00 77711.00 81597.00
33rd m 7.5% 66832.00 83540.00 87717.00
34th m 7.5% 71844.00 89805.00 94295.00
35th m 7.5% 77232.00 96540.00 101367.00
36th m 7.5% 83024.00 103780.00 108969.00
37th m 7.5% 89251.00 111564.00 117142.00
38th m 7.5% 95945.00 119931.00 125928.00
39th m 7.5% 103141.00 128926.00 135372.00
40th m 7.5% 110877.00 138596.00 145526.00
Total Cost from 30m upto 40m 818147.00 1022683.00 1073817.00
Avg Rate per metre 81815.00 102268.00 107382.00
12.17 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 121965.00 146358.00 153676.00
32nd 10% 134162.00 160994.00 169044.00
33rd m 10% 147578.00 177094.00 185949.00
34th m 10% 162336.00 194803.00 204543.00
35th m 10% 178570.00 214284.00 224998.00
36th m 10% 196427.00 235712.00 247498.00
37th m 10% 216070.00 259284.00 272248.00
38th m 10% 237677.00 285212.00 299473.00
39th m 10% 261445.00 313734.00 329421.00
40th m 10% 287590.00 345108.00 362363.00
Total Cost from 30m upto 40m 1943820 2332583 2449213
Avg Rate per metre 194382.00 233258.00 244921.00
12.17 C Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m

Page 52 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 151.44 143.87 L-12
Sinker ( skilled ) day 4.25 164.69 699.93 L-15
Sinking helper (semi-skilled) day 18.00 230.00 4140.00 L-14
Diver day 1.50 264.50 396.75 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 1073.50 8588.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 740.15 3330.68 P&M-063
Consumables in sinking @ 10 per cent of (b) 1191.87
Add for dewatering @ 5 per cent of cost, if required 655.53
c) Overhead charges @ 0.2 on (a+b) 3829.32
d) Contractor's profit @ 0.1 on (a+b+c) 2297.59
Cost for 0.5m = a+b+c+d 25273.54
Rate per metre = (a+b+c+d)/0.50 50547.08
say 50547.00
12.17 D Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 146.00 1752.00 M-104
Electric Detonators each. 48.00 14.56 698.88 M-094/100
b) Labour
Mate day 1.35 151.44 204.44 L-12
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 26.00 136.69 3553.94 L-13
Mazdoor (Skilled) day 4.00 164.69 658.76 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1073.50 10735.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 740.15 2590.53 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 666.28
Consumables in sinking @ 10 per cent of cost of 1833.78
(b+c).
d) Overhead charges @ 0.2 on (a+b+c) 4657.75
e) Contractor's profit @ 0.1 on (a+b+c+d) 2794.65
Cost for 0.5m = a+b+c+d 30741.12
Rate per metre = (a+b+c+d)/0.50 61482.25
say 61482.00
12.18 1200 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 151.44 33.32 L-12

Page 53 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Sinker ( skilled ) day 1.75 164.69 288.21 L-15
Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1073.50 6441.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 644.10
c) Overhead charges @ 0.2 on (a+b) 1665.32
d) Contractor's profit @ 0.1 on (a+b+c) 999.19
Cost for 0.25m = a+b+c+d 10991.14
Rate per metre = (a+b+c+d)/0.25 43964.58
say 43965.00
12.18 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 151.44 56.03 L-12
Sinker day 2.50 164.69 411.73 L-15
Sinking helper (semi-skilled) day 4.75 230.00 1092.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1073.50 6977.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 697.78
c) Overhead charges @ 0.2 on (a+b) 1847.16
d) Contractor's profit @ 0.1 on (a+b+c) 1108.29
Cost for 0.25m = a+b+c+d 12191.23
Rate per metre = (a+b+c+d)/0.25 48764.93
say 48765.00
12.18 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 51203.00
12th m 5% 53763.00
13th m 5% 56451.15
14th m 5% 59273.71
15th m 5% 62237.39
16th m 5% 65349.26
17th m 5% 68616.73
18th m 5% 72047.56
19th m 5% 75649.94
20th m 5% 79432.44
Total Cost from 10m upto 20m 644024.18
Avg Rate per metre 64402.00
12.18 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 85390.00 102468.00
22nd m 7.5% 91794.00 110153.00
23rd m 7.5% 98679.00 118415.00
24th m 7.5% 106080.00 127296.00
25th m 7.5% 114036.00 136843.00
26th m 7.5% 122589.00 147107.00
27th m 7.5% 131783.00 158140.00
28th m 7.5% 141667.00 170000.00
29th m 7.5% 152292.00 182750.00
30th m 7.5% 163714.00 196457.00
Total Cost from 20m upto 30m 1208024.00 1449629.00
Avg Rate per metre 120802.00 144963.00

Page 54 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.18 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 180085.00 216102.00
32nd 10% 198094.00 237713.00
33rd m 10% 217903.00 261484.00
34th m 10% 239693.00 287632.00
35th m 10% 263662.00 316394.00
36th m 10% 290028.00 348034.00
37th m 10% 319031.00 382837.00
38th m 10% 350934.00 421121.00
39th m 10% 386027.00 463232.00
40th m 10% 424630.00 509556.00
Total Cost from 30m upto 40m 2870087 3444105
Avg Rate per metre 287009.00 344411.00
12.18 B Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 151.44 45.43 L-12
Sinker ( skilled ) day 3.00 164.69 494.07 L-15
Sinking helper (semi-skilled) day 4.50 230.00 1035.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1073.50 6709.38 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 670.94
c) Overhead charges @ 0.2 on (a+b) 1790.96
d) Contractor's profit @ 0.1 on (a+b+c) 1074.58
Cost for 0.25m = a+b+c+d 11820.36
Rate per metre = (a+b+c+d)/0.25 47281.42
say 47281.00
12.18 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 151.44 72.69 L-12
Sinker day 3.75 164.69 617.59 L-15
Sinking helper (semi-skilled) day 6.00 230.00 1380.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1073.50 8942.26 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 740.15 3330.68 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1227.29
c) Overhead charges @ 0.2 on (a+b) 3114.10
d) Contractor's profit @ 0.1 on (a+b+c) 1868.46
Cost for 0.25m = a+b+c+d 20553.06
Rate per metre = (a+b+c+d)/0.25 82212.25
say 82212.00
12.18 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

Page 55 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
11th m 5% 86323.00 90639.00
12th m 5% 90639.00 95171.00
13th m 5% 95171.00 99930.00
14th m 5% 99930.00 104927.00
15th m 5% 104927.00 110173.00
16th m 5% 110173.00 115682.00
17th m 5% 115682.00 121466.00
18th m 5% 121466.00 127539.00
19th m 5% 127539.00 133916.00
20th m 5% 133916.00 140612.00
Total Cost from 10m upto 20m 1085766.00 1140055.00
Avg Rate per metre 108577.00 114006.00
12.18 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 143960.00 179950.00 188948.00
32nd 7.5% 154757.00 193446.00 203118.00
33rd m 7.5% 166364.00 207955.00 218353.00
34th m 7.5% 178841.00 223551.00 234729.00
35th m 7.5% 192254.00 240318.00 252334.00
36th m 7.5% 206673.00 258341.00 271258.00
37th m 7.5% 222173.00 277716.00 291602.00
38th m 7.5% 238836.00 298545.00 313472.00
39th m 7.5% 256749.00 320936.00 336983.00
40th m 7.5% 276005.00 345006.00 362256.00
Total Cost from 30m upto 40m 2036612 2545764 2673053
Avg Rate per metre 203661.00 254576.00 267305.00
12.18 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 303606.00 364327.00 382543.00
32nd 10% 333967.00 400760.00 420798.00
33rd m 10% 367364.00 440837.00 462879.00
34th m 10% 404100.00 484920.00 509166.00
35th m 10% 444510.00 533412.00 560083.00
36th m 10% 488961.00 586753.00 616091.00
37th m 10% 537857.00 645428.00 677699.00
38th m 10% 591643.00 709972.00 745471.00
39th m 10% 650807.00 780968.00 820016.00
40th m 10% 715888.00 859066.00 902019.00
Total Cost from 30m upto 40m 4838703 5806443 6096765
Avg Rate per metre 483870.00 580644.00 609677.00
12.18 C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour

Page 56 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 1.06 151.44 160.53 L-12
Sinker ( skilled ) day 4.50 164.69 741.11 L-15
Sinking helper (semi-skilled) day 20.00 230.00 4600.00 L-14
Diver day 1.75 264.50 462.88 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1073.50 10735.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 740.15 3515.71 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1425.07
Add for dewatering @ 5 per cent, if required 783.79
c) Overhead charges @ 0.2 on (a+b) 4484.82
d) Contractor's profit @ 0.1 on (a+b+c) 2690.89
Cost for 0.25m = a+b+c+d 29599.78
Rate per metre = (a+b+c+d)/0.25 118399.14
say 118399.00
12.18 D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 146.00 2044.00 M-104
Electric detonator each. 56.00 14.56 815.36 M-094/100
b) Labour
Mate day 1.44 151.44 218.07 L-12
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 28.00 136.69 3827.32 L-13
Mazdoor (Skilled) day 4.50 164.69 741.11 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 1073.50 13418.75 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 740.15 2960.60 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 818.97
Consumables in sinking @ 10 per cent of (c). 1719.83
d) Overhead charges @ 0.2 on (a+b+c) 5431.83
e) Contractor's profit @ 0.1 on (a+b+c+d) 3259.10
Cost for 0.25m = a+b+c+d+e 35850.06
Rate per metre = (a+b+c+d+e)/0.25 143400.22
say 143400.00
12.19 1200 Sinking of Twin D Type well (other than pneumatic method
of sinking) through all types of strata namely sandy soil,
clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking
is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 151.44 30.29 L-12
Sinker ( skilled ) day 1.25 164.69 205.86 L-15

Page 57 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Sinking helper (semi-skilled) day 3.75 230.00 862.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1073.50 5904.25 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 590.43
c) Overhead charges @ 0.2 on (a+b) 1518.67
d) Contractor's profit @ 0.1 on (a+b+c) 911.20
Rate per metre = (a+b+c+d) 10023.19
say 10023.00
12.19 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 151.44 45.43 L-12
Sinker day 1.50 164.69 247.04 L-15
Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 1073.50 6312.18 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 631.22
c) Overhead charges @ 0.2 on (a+b) 1631.17
d) Contractor's profit @ 0.1 on (a+b+c) 978.70
Rate per metre = (a+b+c+d) 10765.74
say 10766.00
12.19 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 11304.00
12th m 5% 11869.00
13th m 5% 12462.00
14th m 5% 13085.00
15th m 5% 13739.00
16th m 5% 14426.00
17th m 5% 15147.00
18th m 5% 15904.00
19th m 5% 16699.00
20th m 5% 17534.00
Total Cost from 10m upto 20m 142169.00
Avg Rate per metre 14217.00
12.19 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge
21st m 7.5% 18849.00 22619.00
22nd m 7.5% 20263.00 24316.00
23rd m 7.5% 21783.00 26140.00
24th m 7.5% 23417.00 28100.00
25th m 7.5% 25173.00 30208.00
26th m 7.5% 27061.00 32473.00
27th m 7.5% 29091.00 34909.00
28th m 7.5% 31273.00 37528.00
29th m 7.5% 33618.00 40342.00
30th m 7.5% 36139.00 43367.00
Total Cost from 20m upto 30m 266667.00 320002.00
Avg Rate per metre 26667.00 32000.00
12.19 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 58 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge
31st m 10% 39753.00 47704.00
32nd 10% 43728.00 52474.00
33rd m 10% 48101.00 57721.00
34th m 10% 52911.00 63493.00
35th m 10% 58202.00 69842.00
36th m 10% 64022.00 76826.00
37th m 10% 70424.00 84509.00
38th m 10% 77466.00 92959.00
39th m 10% 85213.00 102256.00
40th m 10% 93734.00 112481.00
Total Cost from 30m upto 40m 633554.00 760265.00
Avg Rate per metre 63355.00 76027.00
12.19 B Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 151.44 39.37 L-12
Sinker ( skilled ) day 2.50 164.69 411.73 L-15
Sinking helper (semi-skilled) day 4.00 230.00 920.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1073.50 6709.38 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 670.94
c) Overhead charges @ 0.2 on (a+b) 1750.28
d) Contractor's profit @ 0.1 on (a+b+c) 1050.17
Rate per metre = (a+b+c+d) 11551.86
say 11552.00
12.19 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 151.44 68.15 L-12
Sinker day 3.25 164.69 535.24 L-15
Sinking helper (semi-skilled) day 6.00 230.00 1380.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 1073.50 7160.25 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 740.15 3330.68 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1049.09
c) Overhead charges @ 0.2 on (a+b) 2704.68
d) Contractor's profit @ 0.1 on (a+b+c) 1622.81
Rate per metre = (a+b+c+d) 17850.89
say 17851.00
12.19 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required
11th m 5% 18743.00 19680.00
12th m 5% 19680.00 20664.00
13th m 5% 20664.00 21697.00
14th m 5% 21697.00 22782.00
15th m 5% 22782.00 23921.00

Page 59 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16th m 5% 23921.00 25117.00
17th m 5% 25117.00 26373.00
18th m 5% 26373.00 27692.00
19th m 5% 27692.00 29077.00
20th m 5% 29077.00 30531.00
Total Cost from 10m upto 20m 235746.00 247534.00
Avg Rate per metre 23575.00 24753.00
12.19 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 31258.00 39073.00 41027.00
32nd 7.5% 33602.00 42003.00 44103.00
33rd m 7.5% 36122.00 45153.00 47411.00
34th m 7.5% 38831.00 48539.00 50966.00
35th m 7.5% 41743.00 52179.00 54788.00
36th m 7.5% 44874.00 56093.00 58898.00
37th m 7.5% 48240.00 60300.00 63315.00
38th m 7.5% 51858.00 64823.00 68064.00
39th m 7.5% 55747.00 69684.00 73168.00
40th m 7.5% 59928.00 74910.00 78656.00
Total Cost from 30m upto 40m 442203.00 552757.00 580396.00
Avg Rate per metre 44220.00 55276.00 58040.00
12.19 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 65921.00 79105.00 83060.00
32nd 10% 72513.00 87016.00 91367.00
33rd m 10% 79764.00 95717.00 100503.00
34th m 10% 87740.00 105288.00 110552.00
35th m 10% 96514.00 115817.00 121608.00
36th m 10% 106165.00 127398.00 133768.00
37th m 10% 116782.00 140138.00 147145.00
38th m 10% 128460.00 154152.00 161860.00
39th m 10% 141306.00 169567.00 178045.00
40th m 10% 155437.00 186524.00 195850.00
Total Cost from 30m upto 40m 1050602.00 1260722.00 1323758.00
Avg Rate per metre 105060.00 126072.00 132376.00
12.19 C Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 151.44 130.24 L-12
Sinker ( skilled ) day 4.50 164.69 741.11 L-15
Sinking helper (semi-skilled) day 15.00 230.00 3450.00 L-14
Diver day 1.50 264.50 396.75 L-07
b) Machinery

Page 60 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Hire & running charges of crane with grab bucket of hour 8.33 1073.50 8942.26 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 740.15 4440.90 P&M-063
Consumables in sinking @ 10 per cent of (b) 1338.32
Add for dewatering @ 5 per cent, if required 736.07
c) Overhead charges @ 0.2 on (a+b) 4035.13
d) Contractor's profit @ 0.1 on (a+b+c) 2421.08
Rate per metre = (a+b+c+d) 26631.84
say 26632.00
12.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 146.00 1460.00 M-104
Electric detonators each. 40.00 14.56 582.40 M-094/100
b) Labour
Mate day 1.34 151.44 202.93 L-12
Driller day 2.00 264.50 529.00 L-06
Blaster day 0.25 264.50 66.13 L-03
Mazdoor day 25.00 136.69 3417.25 L-13
Mazdoor (Skilled) day 4.25 164.69 699.93 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1073.50 10735.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 740.15 2220.45 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 893.53
Consumables in sinking @ 10 per cent of (b). 1384.90
d) Overhead charges @ 0.2 on (a+b+c) 4438.30
e) Contractor's profit @ 0.1 on (a+b+c+d) 2662.98
Rate per metre = (a+b+c+d+e) 29292.81
say 29293.00
12.20 1200 Pneumatic sinking of wells with equipment of approved
design, drawing and specifications worked by competent
and trained personnel and comprising of compression and
decompression chambers, reducers, two air locks separately
for men and plant & materials, arrangement for supply of
fresh air to working chambers, check valves, exhaust valves,
shafts made from steel plates of riveted construction not less
than 6 mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required, staircases
and 1 m wide landing plateforms with railing, arrangement
for compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations
and compliance with safety precautions as per IS:4138, all
as per clause1207.6 of MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.00 5217.00 41736.00 Item 12.8
equipment (Dimensions as per ground conditions). (H)
Rate may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 45000.00 21600.00 M-082
Blasting material
Gelatine 80 per cent Kg 1.50 146.00 219.00 M-104
Electric detonators each 6.00 14.56 87.36 M-094/100

Page 61 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Labour
Medical Officer day 0.50 304.20 152.10 L-16
Para medical personnel day 1.00 264.50 264.50 L-19
Mate day 1.86 151.44 281.68 L-12
Driller day 1.00 264.50 264.50 L-06
Blaster day 0.50 264.50 132.25 L-03
Mazdoor (for cutting, blasting, cleaning, removal of day 30.00 136.69 4100.70 L-13
Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter day 10.00 164.69 1646.90 L-15
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)

Diver day 4.00 264.50 1058.00 L-07


c) Machinery
(i) Induction, deinduction and erection of plant and hour 6.00 1000.00 6000.00 P&M-082
equipment including all components and accessories
for pneumatic method of well sinking.

Induction and deinduction L.S 100000.00


Erection at site and commissioning L.S 150000.00
Usage of plant and equipment for pneumatic method of hour 6.00 4170.00 25020.00 P&M-038
well sinking
Air compressor 250 cfm, 2 nos. hour 2x6 319.00 3828.00 P&M-001
Hire and running charges of crane of 15 tonne capacity hour 6.00 349.59 2097.56 P&M-072

Motorised barge of 20 tonne capacity hour 6.00 100.00 600.00 P&M-066


Boat to carry atleast 20 persons hour 6.00 100.00 600.00 P&M-066
Electric generating set 33 KVA hour 6.00 406.80 2440.80 P&M-079
Tipper 10 tonne capacity hour 6.00 339.00 2034.00 P&M-048
d) Overhead charges @ 0.2 on (a+b+c) 64485.47
e) Contractor's profit @ 0.1 on (a+b+c+d) 38691.28
Cost for 5 cum = a+b+c+d+e (see notes below)
Rate per cum = (a+b+c+d+e)/5
Note 1.The cost of induction, deinduction and erection of
equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will
be added to the cost indicated at (1) above to arrive at the
final rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.
12.21 1207 Sand Filling in Wells complete as per Drawing and Technical
Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 476.80 572.16 M-006
b) Labour
Mate day 0.01 151.44 1.51 L-12
Mazdoor day 0.30 136.69 41.01 L-13
c) Overhead charges @ 0.2 on (a+b) 122.94

Page 62 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 73.76
Rate per cum (a+b+c+d) 811.38
say 811.00
12.22 1200 & Providing Steel Liner 10 mm thick for Curbs and 6 mm thick
1900 for Steining of Wells including Fabricating and Setting out as
per Detailed Drawing.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 45000.00 47250.00 M-179
b) Labour
Mate day 1.24 151.44 187.79 L-12
Fitter day 6.00 230.00 1380.00 L-08
Blacksmith day 5.00 230.00 1150.00 L-01
Welder day 5.00 264.50 1322.50 L-02
Mazdoor day 10.00 136.69 1366.90 L-13
Electrodes, cutting gas and other consumables @ 5 2362.50
per cent on cost a (a) above.
c) Overhead charges @ 0.2 on (a+b) 11003.94
d) Contractor's profit @ 0.1 on (a+b+c) 6602.36
Rate for per MT (a+b+c+d) 72625.98
say 72626.00
12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 5260.00 34821.20 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5464.00 32784.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 357.00 178.50 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.30 806.00 241.80 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.30 339.00 101.70 P&M-048
bore hole
Bentonite kg 300.00 4.10 1230.00 M-071
c) Labour
Mate/Supervisor day 0.14 151.44 21.20 L-12
Mazdoor day 3.50 136.69 478.42 L-13
d) Overhead charges @ 0.2 on (b+c) 7007.12
e) Contractor's profit @ 0.1 on (b+c+d) 4204.27
Cost for 15 m = a+b+c+d+d+e 81068.21
Rate per metre (a+b+c+d+e)/15 5404.55
say 5405.00
12.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding
1100,16 Reinforcement complete as per Drawing and Technical
00 & Specifications and removal of excavated earth with all lifts
1700 and lead upto 1000 m.
Pile diameter-1000 mm

Page 63 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 5260.00 41291.00 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5464.00 32784.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 357.00 178.50 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.40 806.00 322.40 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.40 339.00 135.60 P&M-048
bore hole
Bentonite kg 350.00 4.10 1435.00 M-071
c) Labour
Mate/Supervisor day 0.16 151.44 24.23 L-12
Mazdoor day 4.00 136.69 546.76 L-13
d) Overhead charges @ 0.2 on (b+c) 7085.30
e) Contractor's profit @ 0.1 on (b+c+d) 4251.18
Cost for 10 m = a+b+c+d+d+e 88053.97
Rate per metre (a+b+c+d+e)/10 8805.40
say 8805.00
12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all lifts
and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 5260.00 53494.20 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5464.00 32784.00 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 357.00 178.50 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.50 806.00 403.00 P&M-017
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 339.00 169.50 P&M-048
bore hole
Bentonite kg 385.00 4.10 1578.50 M-071
c) Labour
Mate/Supervisor day 0.18 151.44 27.26 L-12
Mazdoor day 4.50 136.69 615.11 L-13
d) Overhead charges @ 0.2 on (b+c) 7151.17
e) Contractor's profit @ 0.1 on (b+c+d) 4290.70
Cost for 9 m = a+b+c+d+d+e 100691.94
Rate per metre (a+b+c+d+e)/9 11187.99
say 11188.00

Page 64 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.26 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35 cum 17.66 5260.00 92891.60 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 52.15 3650.50 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 61.00 3050.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5974.88 35849.25 P&M-085
acting pile driving hammer complete with power unit
and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 825.00 412.50 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 151.44 18.17 L-12
Mazdoor day 3.00 136.69 410.07 L-13
e) Overhead charges @ 0.2 on (b+c+d) 10585.30
f) Contractor's profit @ 0.1 on (b+c+d+e) 6351.18
Cost for 40 m = a+b+c+d+e 162754.57
Rate per metre (a+b+c+d+e)/40 4068.86
say 4069.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.27 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 5260.00 123873.00 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 52.15 3650.50 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 61.00 3050.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5974.88 35849.25 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 116.53 58.27 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.

Page 65 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Hire and running charges for light crane for lowering hour 0.50 357.00 178.50 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 151.44 24.23 L-12
Mazdoor day 4.00 136.69 546.76 L-13
e) Overhead charges @ 0.2 on (b+c+d) 10578.70
f) Contractor's profit @ 0.1 on (b+c+d+e) 6347.22
Cost for 30 m = a+b+c+d+e 193692.43
Rate per metre (a+b+c+d+e)/30 6456.41
say 6456.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.28 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
PCC Grade M35 cum 22.61 5260.00 118928.60 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 52.15 3650.50 M-124
iii) Steel helmet on top of casing head during driving Kg 50.00 61.00 3050.00 M-173
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5974.88 35849.25 P&M-085
acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 116.53 58.27 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 151.44 27.26 L-12
Mazdoor day 4.50 136.69 615.11 L-13
e) Overhead charges @ 0.2 on (b+c+d) 10557.28
f) Contractor's profit @ 0.1 on (b+c+d+e) 6334.37
Cost for 20 m = a+b+c+d+e 188606.62
Rate per metre (a+b+c+d+e)/20 9430.33
say 9430.00
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.29 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 500 mm
Unit = Running Meter

Page 66 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 5114.00 60242.92 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes Kg 240.00 59.60 14304.00 M-080
b) M.S. shoes Kg 105.00 37.00 3885.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 61.00 1830.00 M-173
during driving.
c) Machinery
Crane20 t capacity hour 6.00 466.13 2796.75 P&M-073
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.12 151.44 18.17 L-12
Mazdoor day 3.00 136.69 410.07 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 894.87
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) 6027.77
f) Contractor's profit @ 0.1 on (b+c+d+e) 3616.66
Cost for 60 m = a+b+c+d+e+f 100026.22
Rate per metre (a+b+c+d+e+f)/60 1667.10
say 1667.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.30 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 5114.00 112917.12 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes Kg 160.00 59.60 9536.00 M-080
b) M.S. shoes Kg 70.00 37.00 2590.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 40.00 61.00 2440.00 M-173
during driving.
c) Machinery
Crane 40 T capacity hour 6.00 932.25 5593.50 P&M-074
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.16 151.44 24.23 L-12
Mazdoor day 4.00 136.69 546.76 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 1396.48
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) 5625.39
f) Contractor's profit @ 0.1 on (b+c+d+e) 3375.24
Cost for 50 m = a+b+c+d+e+f 150044.72
Rate per metre (a+b+c+d+e+f)/50 3000.89
say 3001.00

Page 67 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.31 1100 & Driven precast vertical M35 grade R.C.C. Piles excluding
1700 Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 31.40 5114.00 160579.60 Item 12.11
(F) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.00 59.60 9536.00 M-080
b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 37.00 2590.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 50.00 61.00 3050.00 M-173
during driving.
c) Machinery
Crane 50 t capacity. hour 6.00 1279.00 7674.00 P&M-011
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.20 151.44 30.29 L-12
Mazdoor day 5.00 136.69 683.45 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 1901.43
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) 6293.03
f) Contractor's profit @ 0.1 on (b+c+d+e) 3775.82
Cost for 40 m = a+b+c+d+e+f 202113.63
Rate per metre (a+b+c+d+e+f)/40 5052.84
say 5053.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.32 1100&17 Driven precast vertical M35 grade R.C.C. Piles excluding
00 Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 5.40 5114.00 27615.60 Item 12.11
plug vide item no. 12.11( F ) (IV) (F) iv
b ) Material Pile shoes
a) C I shoes kg 240.00 59.60 14304.00 M-080
b) M. S shoes kg 105.00 37.00 3885.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 61.00 1830.00 M-173
during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 1237.50 7425.00 P&M-071
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.12 151.44 18.17 L-12
Mazdoor day 3.00 136.69 410.07 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 614.88
casting yard to work site and stacking, and other
imponderables during installation.

Page 68 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.2 on (b+c+d) 6897.42
f) Contractor's profit @ 0.1 on (b+c+d+e) 4138.45
Cost for 60 m = a+b+c+d+e+f 73138.60
Rate per metre (a+b+c+d+e+f)/60 1218.98
say 1219.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.33 1100 Driven precast vertical M35 grade R.C.C. Piles excluding
&1700 Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 12.50 5114.00 63925.00 Item 12.11
plug vide item no. 12.11( F ) (IV) (F) iv
b ) Material Pile shoes
a) C I shoes kg 160.00 59.60 9536.00 M-080
b) M. S shoes kg 70.00 37.00 2590.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 61.00 1830.00 M-173
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 466.13 2796.75 P&M-073
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.16 151.44 24.23 L-12
Mazdoor day 4.00 136.69 546.76 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 872.49
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) 4839.25
f) Contractor's profit @ 0.1 on (b+c+d+e) 2903.55
Cost for 50 m = a+b+c+d+e+f 95864.02
Rate per metre (a+b+c+d+e+f)/50 1917.28
say 1917.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.34 1100 Driven precast vertical M35 grade R.C.C. Piles excluding
&1700 Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 22.50 5114.00 115065.00 Item 12.11
plug vide item no. 13.11( F ) (IV) (F) iv
b ) Material
Pile shoes
a) C I shoes kg 160.00 59.60 9536.00 M-080
b) M. S shoes kg 70.00 37.00 2590.00 M-125
c) Steel helmet and cushion block on top of pile head Kg 30.00 61.00 1830.00 M-173
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 466.13 2796.75 P&M-073
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and accessories.

Page 69 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d ) Labour
Mate/Supervisor day 0.18 151.44 27.26 L-12
Mazdoor day 4.50 136.69 615.11 L-13
Add 1 per cent of (a+b+c) for carriage of piles from 1384.60
casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.2 on (b+c+d) 4955.94
f) Contractor's profit @ 0.1 on (b+c+d+e) 2973.57
Cost for 40 m = a+b+c+d+e+f 147774.22
Rate per metre (a+b+c+d+e+f)/40 3694.36
say 3694.00
Note The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
12.35 1100, Driven Vertical Steel Piles complete as per Drawing and &
1900 Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 tonnes 6.04 45000.00 271800.00 M-179
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 233.06 1398.38 P&M-071
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and other accessories.
c) Labour
Mate/Supervisor day 0.12 151.44 18.17 L-12
Mazdoor day 3.00 136.69 410.07 L-13
Add 0.5 per cent of (a+b+c) for providing steel 1398.13
helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and
other imponderables during installation.
d) Overhead charges @ 0.2 on (a+b+c) 56204.95
e) Contractor's profit @ 0.1 on (a+b+c+d) 33722.97
Cost for 70 m = a+b+c+d+e 370952.67
Rate per metre (a+b+c+d+e)/70 5299.32
say 5299.00
12.36 1100 Driven Vertical Steel Piles complete as per Drawing and &
&1900 Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 tonnes 5.83 45000.00 262350.00 M-179
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 233.06 1398.38 P&M-071
Vibrating Pile driving hammer complete with power unit hour 6.00 1000.00 6000.00 P&M-092
and accessories.
c) Labour
Mate/Supervisor day 0.14 151.44 21.20 L-12
Mazdoor day 3.50 136.69 478.42 L-13
Add 0.5 per cent of (a+b+c) for providing steel 1351.24
helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

d) Overhead charges @ 0.2 on (a+b+c) 54319.85


e) Contractor's profit @ 0.1 on (a+b+c+d) 32591.91

Page 70 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 60 m = a+b+c+d+e 358510.99
Rate per metre (a+b+c+d+e)/60 5975.18
say 5975.00
12.37 1100 Pile Load Test on single Vertical Pile in accordance with
IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 300.00
b) Lateral load test tonne 1.00 5000.00
Note Although, this item is incidental to work and is not required to
be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
12.38 1100, Cement Concrete for Reinforced Concrete in Pile Cap
1500 complete as per Drawing and Technical Specification
&1700
A RCC Grade M20
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.12 5000.00 25600.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 230.00 345.00 L-10
Mazdoor for concreting day 20.00 136.69 2733.80 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 2053.60
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 10678.72
e) Contractor's profit @ 0.1 on (a+b+c+d) 6407.23
Cost for 15 cum = a+b+c+d+e 70479.54
Rate per metre (a+b+c+d+e)/15 4698.64
say 4699.00
12.38A (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.12 5000.00 25600.00 M-081
Coarse sand cum 6.75 828.00 5589.00 M-004
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.16 151.44 24.23 L-12
Mason day 0.38 230.00 87.40 L-10
Mazdoor for concreting day 2.50 136.69 341.73 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002
Generator 100 KVA hour 0.75 762.75 572.06 P&M-080
Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049

Page 71 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.28 Lead =1
km & P&M-
050
Concrete Pump hour 0.75 256.00 192.00 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 2027.43
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 10542.62
e) Contractor's profit @ 0.1 on (a+b+c+d) 6325.57
Cost for 15 cum = a+b+c+d+e 69581.31
Rate per metre (a+b+c+d+e)/15 4638.75
say 4639.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 B RCC Grade M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 5000.00 29950.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 230.00 345.00 L-10
Mazdoor for concreting day 20.00 136.69 2733.80 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 2227.60
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 11583.52
e) Contractor's profit @ 0.1 on (a+b+c+d) 6950.11
Cost for 15 cum = a+b+c+d+e 76451.22
Rate per metre (a+b+c+d+e)/15 5096.75
say 5097.00
12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.99 5000.00 29950.00 M-081
Coarse sand cum 6.75 828.00 5589.00 M-004
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.16 151.44 24.23 L-12
Mason day 0.38 230.00 87.40 L-10
Mazdoor for concreting day 2.50 136.69 341.73 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002
Generator 125 KVA hour 0.75 652.00 489.00 P&M-018
Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.28 Lead =1
km & P&M-
050

Page 72 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Concrete Pump hour 0.75 256.00 192.00 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 2198.10
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 11430.15
e) Contractor's profit @ 0.1 on (a+b+c+d) 6858.09
Cost for 15 cum = a+b+c+d+e 75438.96
Rate per metre (a+b+c+d+e)/15 5029.26
say 5029.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 C RCC Grade M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 5000.00 30500.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 230.00 345.00 L-10
Mazdoor for concreting day 20.00 136.69 2733.80 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 2249.60
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 11697.92
e) Contractor's profit @ 0.1 on (a+b+c+d) 7018.75
Cost for 15 cum = a+b+c+d+e 77206.26
Rate per metre (a+b+c+d+e)/15 5147.08
say 5147.00
'12.38C (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.10 5000.00 30500.00 M-081
Coarse sand cum 6.75 828.00 5589.00 M-004
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.16 151.44 24.23 L-12
Mason day 0.38 230.00 87.40 L-10
Mazdoor for concreting day 2.50 136.69 341.73 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002
Generator 100 KVA hour 0.75 762.75 572.06 P&M-080
Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.28 Lead =1
km & P&M-
050
Concrete Pump hour 0.75 256.00 192.00 P&M-007

Page 73 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Formwork @ 4 per cent on cost of concrete i.e. cost 2223.43
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 11561.82
e) Contractor's profit @ 0.1 on (a+b+c+d) 6937.09
Cost for 15 cum = a+b+c+d+e 76308.03
Rate per metre (a+b+c+d+e)/15 5087.20
say 5087.00
Note The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
12.38 D RCC Grade M35
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.33 5000.00 31650.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.90 151.44 136.30 L-12
Mason day 1.50 230.00 345.00 L-10
Mazdoor day 20.00 136.69 2733.80 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 406.80 2440.80 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. cost 2295.60
of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.2 on (a+b+c) 11937.12
e) Contractor's profit @ 0.1 on (a+b+c+d) 7162.27
Cost for 15 cum = a+b+c+d+e 78784.98
Rate per metre (a+b+c+d+e)/15 5252.33
say 5252.00
'12.38D (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.33 5000.00 31650.00 M-081
Coarse sand cum 6.75 828.00 5589.00 M-004
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.16 151.44 24.23 L-12
Mason day 0.38 230.00 87.40 L-10
Mazdoor for concreting day 2.50 136.69 341.73 L-13
Mazdoor for breaking pile head, bending bars, cleaning day 1.00 136.69 136.69 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2232.00 1674.00 P&M-002
Generator 125 KVA hour 0.75 652.00 489.00 P&M-018
Loader (capacity 1 cum) hour 0.75 806.00 604.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 1017.00 2034.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 2.03 76.28 Lead =1
km & P&M-
050
Concrete Pump hour 0.75 256.00 192.00 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. cost 2266.10
of a) Material, b) Labour and c) Machinery

Page 74 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overhead charges @ 0.2 on (a+b+c) 11783.75
e) Contractor's profit @ 0.1 on (a+b+c+d) 7070.25
Cost for 15 cum = a+b+c+d+e 77772.72
Rate per metre (a+b+c+d+e)/15 5184.85
say 5185.00
12.39 1100&17 Levelling Course for Pile cap
00
Providing and laying of PCC M15 levelling course 100mm
thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5000.00 20650.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
40 mm aggregate cum 8.10 916.00 7419.60 M-055
20 mm Aggregate cum 4.05 1028.00 4163.40 M-053
10 mm Aggregate cum 1.35 1005.00 1356.75 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 230.00 345.00 L-10
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
d) Overhead charges @ 0.2 on (a+b+c) 9086.64
e) Contractor's profit @ 0.1 on (a+b+c+d) 5451.98
Cost for 15 cum = a+b+c+d+e 59971.82
Rate per metre (a+b+c+d+e)/15 3998.12
say 3998.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing and
Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 45000.00 47250.00 M-082

Binding wire Kg 6.00 100.00 600.00 M-072


b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate day 0.40 151.44 60.58 L-12
Blacksmith day 2.00 264.50 529.00 L-02
Mazdoor day 6.00 136.69 820.14 L-13
9851.94
5911.17
65022.83
say 65023.00
12.41 1600 Supplying, fitting and placing un-coated Mild steel
reinforcement complete in foundation as per drawing and
technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 47307.50 49672.88 M-126
Binding wire Kg 6.00 100.00 600.00 M-072
b) Labour for straightening, cutting, bending, shifting to
site, tying and placing in position
Mate day 0.43 151.44 65.12 L-12
Blacksmith day 2.25 264.50 595.13 L-02

Page 75 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 6.50 136.69 888.49 L-13
c) Overhead charges @ 0.2 on (a+b) 10364.32
d) Contractor's profit @ 0.1 on (a+b+c) 6218.59
Rate for per MT (a+b+c+d) 68404.52
say 68405.00

Page 76 of 264
CHAPTER-13
SUB-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.1 1300 & Brick masonry work in 1:3 in sub-structure complete
2200 excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 4.42 2209.09 M-079
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.24 3425.00 822.00 Item 12.6
analysis) (A)
b) Labour
Mate day 0.06 151.44 9.09 L-12
Mason day 0.80 0.00 L-11
Mazdoor day 0.80 136.69 109.35 L-13
Add for scaffolding @ 5 per cent of cost of material 157.48
and labour
c) Overhead charges @ 0.2 on (a+b) 661.40
d) Contractor's profit @ 0.1 on (a+b+c) 396.84
Rate per cum (a+b+c+d) 4365.25
say 4365.00
13.2 1300 & Pointing with cement mortar (1:3 ) on brick work in
2200 substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 3425.00 102.75 Item 12.6
b) Labour (A)
Mate day 0.04 151.44 6.06 L-12
Mason day 0.50 223.36 111.68 L-11
Mazdoor day 0.50 136.69 68.35 L-13
c) Overhead charges @ 0.2 on (a+b) 57.77
d) Contractor's profit @ 0.1 on (a+b+c) 34.66
Rate per 10 sqm (a+b+c+d) 381.26
say 381.00
Note Scaffolding is already included in item 13.1
13.3 1300 & Plastering with cement mortar (1:3 ) on brick work in sub-
2200 structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 3425.00 493.20 Item 12.6
(A)
b) Labour
Mate day 0.04 151.44 6.06 L-12
Mason day 0.50 223.36 111.68 L-11
Mazdoor day 0.50 136.69 68.35 L-13
c) Overhead charges @ 0.2 on (a+b) 135.86
d) Contractor's profit @ 0.1 on (a+b+c) 81.51
Rate per 10 sqm (a+b+c+d) 896.65
say 897.00
Note 1.Scaffolding is already included in item no. 13.1
2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
13.4 1400 & Stone masonry work in cement mortar 1:3 for substructure
2200 complete as per drawing and Technical Specifications

A Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 2604.51 2604.51 M-148
Through and bond stone No 7.00 14.45 101.17 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3425.00 1130.25 Item 12.6
(A)

Page 1 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Labour
Mate day 0.10 151.44 15.14 L-12
Mason day 1.20 223.36 268.03 L-11
Mazdoor day 1.20 136.69 164.03 L-13
Add for scaffolding @ 5 per cent of cost of a) 214.16
Material and b) Labour
c) Overhead charges @ 0.2 on (a+b) 899.46
d) Contractor's profit @ 0.1 on (a+b+c) 539.68
Rate per cum (a+b+c+d) 5936.43
say 5936.00
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 2604.51 2864.96 M-148
Through and bond stone each 7.00 14.45 101.17 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 3425.00 1027.50 Item 12.6
(A)
b) Labour
Mate day 0.12 151.44 18.17 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 1.50 136.69 205.04 L-13
Add for scaffolding @ 5 per cent of cost of material 227.59
and labour
c) Overhead charges @ 0.2 on (a+b) 955.89
d) Contractor's profit @ 0.1 on (a+b+c) 573.54
Rate per cum (a+b+c+d) 6308.91
say 6309.00
13.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 2705.04 3002.59 M-169
Through and bond stone each 7.00 14.45 101.17 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3425.00 1130.25 Item 12.6
(A)
b) Labour for masonry work
Mate day 0.20 151.44 30.29 L-12
Mason day 2.50 223.36 558.40 L-11
Mazdoor day 2.50 136.69 341.73 L-13
Add for scaffolding @ 5 per cent of cost of a) 258.22
Material and b) Labour
c) Overhead charges @ 0.2 on (a+b) 1084.53
d) Contractor's profit @ 0.1 on (a+b+c) 650.72
Rate per cum (a+b+c+d) 7157.90
say 7158.00
Note The labour already considered in the cement mortar have
been taken into account while providing these categories in
the stone masonry works.
13.5 1500, Plain/Reinforced cement concrete in sub-structure complete
1700 & as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
(p) Height upto 5m

Page 2 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 3080.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 308.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 677.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 406.56
Rate perm (a+b+c+d+e+f) 4472.16
say 4472.00
13.5 B PCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 3390.00 Item 12.8 (B) PCC
(a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 339.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 745.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.48
Rate perm (a+b+c+d+e+f) 4922.28
say 4922.00
13.5 C PCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3667.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 366.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 806.74
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 484.04
Rate perm (a+b+c+d+e+f) 5324.48
say 5324.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3614.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 361.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 795.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 477.05
Rate perm (a+b+c+d+e+f) 5247.53
say 5248.00
13.5 C (q) Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3667.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I

Page 3 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) formwork
Add 12 per cent of cost of material, labour and 12.00 440.04
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 73.34
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 836.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 501.65
Rate perm (a+b+c+d+e+f) 5518.10
say 5518.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3614.00
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 433.68
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 72.28
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 823.99
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 494.40
Rate perm (a+b+c+d+e+f) 5438.35
say 5438.00
13.5 C (r) Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3667.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 550.05
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 146.68
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 872.75
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 523.65
Rate perm (a+b+c+d+e+f) 5760.12
say 5760.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3614.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 542.10
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 144.56
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 860.13
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 516.08
Rate perm (a+b+c+d+e+f) 5676.87
say 5677.00
13.5 D PCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3697.00
(a+b+c) of Item 12.8 (F) Case I

Page 4 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) formwork
Add 10 per cent of cost of material, labour and 10.00 369.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 813.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 488.00
Rate perm (a+b+c+d+e+f) 5368.04
say 5368.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3641.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 364.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 801.02
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 480.61
Rate perm (a+b+c+d+e+f) 5286.73
say 5287.00
13.5 D (q) Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3697.00
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 443.64
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 73.94
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 842.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 505.75
Rate perm (a+b+c+d+e+f) 5563.25
say 5563.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3641.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 436.92
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 72.82
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 830.15
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 498.09
Rate perm (a+b+c+d+e+f) 5478.98
say 5479.00
13.5 D (r) Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3697.00
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 554.55
machinery (a+b+c) for Formwork

Page 5 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add 4 per cent of cost of material, Labour and 4.00 147.88
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 879.89
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 527.93
Rate perm (a+b+c+d+e+f) 5807.25
say 5807.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3641.00
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 546.15
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 145.64
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 866.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 519.93
Rate perm (a+b+c+d+e+f) 5719.28
say 5719.00
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3443.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 344.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 757.46
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 454.48
Rate perm (a+b+c+d+e+f) 4999.24
say 4999.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3388.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 338.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 745.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 447.22
Rate perm (a+b+c+d+e+f) 4919.38
say 4919.00
13.5 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3443.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 413.16
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 68.86
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 785.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 471.00
Rate perm (a+b+c+d+e+f) 5181.03

Page 6 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 5181.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3388.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 406.56
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 67.76
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 772.46
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 463.48
Rate perm (a+b+c+d+e+f) 5098.26
say 5098.00
13.5 E (r) Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3443.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 516.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 137.72
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 819.43
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 491.66
Rate perm (a+b+c+d+e+f) 5408.26
say 5408.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3388.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 508.20
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 135.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 806.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 483.81
Rate perm (a+b+c+d+e+f) 5321.87
say 5322.00
13.5 F RCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3723.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 372.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 819.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 491.44
Rate perm (a+b+c+d+e+f) 5405.80
say 5406.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II

Page 7 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 374.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 822.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68
Rate perm (a+b+c+d+e+f) 5430.48
say 5430.00
13.5 F (q) Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3723.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 439.31
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 67.01
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 845.87
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 507.52
Rate perm (a+b+c+d+e+f) 5582.71
say 5583.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 441.32
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 67.32
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 849.73
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 509.84
Rate perm (a+b+c+d+e+f) 5608.20
say 5608.00
13.5 F (r) Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3723.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 558.45
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 148.92
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 886.07
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 531.64
Rate perm (a+b+c+d+e+f) 5848.09
say 5848.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 561.00
machinery (a+b+c) for Formwork

Page 8 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add 4 per cent of cost of material, Labour and 4.00 149.60
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 890.12
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 534.07
Rate perm (a+b+c+d+e+f) 5874.79
say 5875.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 374.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 822.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.68
Rate perm (a+b+c+d+e+f) 5430.48
say 5430.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3686.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 368.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 810.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 486.55
Rate perm (a+b+c+d+e+f) 5352.07
say 5352.00
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 430.10
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 59.84
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 845.99
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 507.59
Rate perm (a+b+c+d+e+f) 5583.52
say 5584.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3686.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 423.89
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 58.98
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 833.77
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 500.26
Rate perm (a+b+c+d+e+f) 5502.90
say 5503.00

Page 9 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3740.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 523.60
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 130.90
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 878.90
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 527.34
Rate perm (a+b+c+d+e+f) 5800.74
say 5801.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3686.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and 14.00 516.04
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 129.01
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 866.21
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 519.73
Rate perm (a+b+c+d+e+f) 5716.99
say 5717.00
13.5 H RCC Grade M35
(p) Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3816.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 381.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 839.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 503.71
Rate perm (a+b+c+d+e+f) 5540.83
say 5541.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3838.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 383.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.2 on (a+b+c+d) 844.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 506.62
Rate perm (a+b+c+d+e+f) 5572.78
say 5573.00
13.5 H (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I

Page 10 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3816.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 11 per cent of cost of material, labour and 11.00 419.76
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 53.42
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 857.84
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 514.70
Rate perm (a+b+c+d+e+f) 5661.72
say 5662.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3838.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 422.18
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 53.73
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 862.78
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 517.67
Rate perm (a+b+c+d+e+f) 5694.36
say 5694.00
13.5 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3816.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 496.08
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 114.48
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 885.31
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 531.19
Rate perm (a+b+c+d+e+f) 5843.06
say 5843.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3838.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 498.94
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 115.14
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.2 on (a+b+c+d) 890.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 534.25
Rate perm (a+b+c+d+e+f) 5876.75
say 5877.00
Note The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use by the working parties.

Page 11 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percentage to be added has been reduced to
maintain the same cost for extra efforts.
13.6 Section Supplying, fitting and placing HYSD bar reinforcement in
1600 & sub-structure complete as per drawing and Technical
2200 Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 45000.00 47250.00 M-082

Binding wire kg 6.00 100.00 600.00 M-072


b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate day 0.34 151.44 51.49 L-12
Blacksmith day 2.00 264.50 529.00 L-02
Mazdoor day 6.50 136.69 888.49 L-13
c) Overhead charges @ 0.2 on (a+b) 9863.79
d) Contractor's profit @ 0.1 on (a+b+c) 5918.28
Rate for per MT (a+b+c+d) 65101.05
say 65101.00
13.7 1600 & Supplying, fitting and placing Mild steel reinforcement
2200 complete in sub-structure as per drawing and Technical
Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 47307.50 49672.88 M-126
Binding wire kg 6.00 100.00 600.00 M-072
b) Labour for straightening, cutting, bending, shifting to
site, tying and placing in position
Mate day 0.28 151.44 42.40 L-12
Blacksmith day 1.50 264.50 396.75 L-02
Mazdoor day 5.50 136.69 751.80 L-13
c) Overhead charges @ 0.2 on (a+b) 10292.76
d) Contractor's profit @ 0.1 on (a+b+c) 6175.66
Rate for per MT (a+b+c+d) 67932.25
say 67932.00
13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced
2200 concrete abutment, wing wall/ return wall with 100 mm dia
AC pipe, extending through the full width of the structure
with slope of 1V :20H towards drawing foce. Complete as
per drawing and Technical Specifications

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per metre 31.50 65.00 2047.50 M-056
cent )
Average length of weep hole is taken as one metre for the
purpose of estimating.
MS clamp each. 30.00 13.00 390.00 M-123
collar for AC pipe (average) taking 10% of above pipe each. 10.00 6.50 65.00 M-056/10
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3425.00 171.25 Item 12.6
(A)
b) Labour
Mate day 0.03 151.44 4.54 L-12
Mason day 0.50 223.36 111.68 L-11

Page 12 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 0.25 136.69 34.17 L-13
c) Overhead charges @ 0.2 on (a+b) 564.83
d) Contractor's profit @ 0.1 on (a+b+c) 338.90
Cost for 30 m = a+b+c+d 3727.87
Rate per m (a+b+c+d)/30 124.26
say 124.00
Note 1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work
and shall not be paid separately.
13.9 710.1.4. Back filling behind abutment, wing wall and return wall
of complete as per drawing and Technical Specification
IRC:78 &
2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 151.44 42.40 L-12
Mazdoor day 7.00 136.69 956.83 L-13
b) Material
Granular material cum 12.00 727.79 8733.48 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 101.70 254.25 P&M-086
Water Tanker hour 0.05 200.00 10.00 P&M-060
d) Overhead charges @ 0.2 on (a+b+c) 1999.39
e) Contractor's profit @ 0.1 on (a+b+c+d) 1199.64
Cost for 10 cum of granular backfill = a+b+c+d+e 13195.99
Rate per cum = (a+b+c+d+e)/10 1319.60
say 1320.00
13.9 B Sandy material
a) Labour
Mate day 0.28 151.44 42.40 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 136.69 956.83 L-13
b) Material
Sand cum 12.00 476.80 5721.60 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 101.70 254.25 P&M-086
Water Tanker hour 0.06 200.00 12.00 P&M-060
d) Overhead charges @ 0.2 on (a+b+c) 1397.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 838.45
Cost for 10 cum of sandy backfill = a+b+c+d+e 9222.95
Rate per cum = (a+b+c+d+e)/10 922.29
say 922.00
13.10 710.1.4. Providing and laying of Filter media with granular
of materials/stone crushed aggregates satisfying the
IRC:78 requirements laid down in clause 2504.2.2. of MoRTH
and specifications to a thickness of not less than 600 mm with
2200 smaller size towards the soil and bigger size towards the
wall and provided over the entire surface behind abutment,
wing wall and return wall to the full height compacted to a
firm condition complete as per drawing and Technical
Specification.

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 151.44 48.46 L-12

Page 13 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor for filling, watering, ramming etc. day 7.00 136.69 956.83 L-13
Mazdoor (Skilled) day 1.00 164.69 164.69 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 894.00 10728.00 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 200.00 12.00 P&M-060
d) Overhead charges @ 0.2 on (a+b+c) 2382.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 1429.20
cost for 10 cum of Fiter Media = a+b+c+d+e 15721.17
Rate per cum = (a+b+c+d+e)/10 1572.12
say 1572.00
13.11 2000, Supplying, fitting and fixing in position true to line and level
1000 & cast steel rocker bearing conforming to IRC: 83(Pt.-1)
2200 section IX and clause 2003 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 151.44 9.09 L-12
Mazdoor (Skilled) day 0.50 164.69 82.35 L-15
Mazdoor day 1.00 136.69 136.69 L-13
b) Material
Cast steel rocker bearing assembly of 250 tonne each. 1.00 50000.00 50000.00 M-065
design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 500.00
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 0.2 on (a+b) 10145.62
d) Contractor's profit @ 0.1 on (a+b+c) 6087.37
cost for 250 tonnes capacity bearing = a+b+c+d 66961.12
Rate per tonne capacity = (a+b+c+d)/250 267.84
say 268.00
13.12 2000 , Supplying, fitting and fixing in position true to line and level
1000 & forged steel roller bearing conforming to IRC: 83(Pt.-1)
2200 section IX and clause 2003 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 151.44 9.09 L-12
Mazdoor day 1.00 136.69 136.69 L-13
Mazdoor (Skilled) day 0.50 164.69 82.35 L-15
b) Material
Forged steel roller bearing of 250 tonne design load each. 1.00 41309.00 41309.00 M-067
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 413.09
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 0.2 on (a+b) 8390.04
d) Contractor's profit @ 0.1 on (a+b+c) 5034.03
cost for 250 tonnes capacity bearing = a+b+c+d 55374.28
Rate per tonne capacity = (a+b+c+d)/250 221.50
say 221.00

Page 14 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.13 2000 & Supplying, fitting and fixing in position true to line and level
2200 sliding plate bearing with PTFE surface sliding on stainless
steel complete including all accessories as per drawing and
Technical Specifications and BS: 5400, section 9.1 & 9.2 (for
PTFE) and clause 2004 of MoRTH Specifications.

Unit: one tonne capacity


Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 151.44 9.09 L-12
Mazdoor day 1.00 136.69 136.69 L-13
Mazdoor (Skilled) day 0.50 164.69 82.35 L-15
b) Material
PTFE sliding plate bearing assembly of 80 tonnes each. 1.00 16378.00 16378.00 M-069
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and 163.78
consumables.
c) Overhead charges @ 0.2 on (a+b) 3353.98
d) Contractor's profit @ 0.1 on (a+b+c) 2012.39
cost for 80 tonnes capacity bearing = a+b+c+d 22136.27
Rate per tonne capacity = (a+b+c+d)/80 276.70
say 277.00
13.14 2000 & Supplying, fitting and fixing in position true to line and level
2200 elastomeric bearing conforming to IRC: 83 (Part-II) section
IX and clause 2005 of MoRTH specifications complete
including all accessories as per drawing and Technical
Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 151.44 9.09 L-12
Mazdoor day 1.00 136.69 136.69 L-13
Mazdoor (Skilled) day 0.50 164.69 82.35 L-15
b) Material
Elastomeric bearing assembly consisting of 7 layers of each. 1.00 15000.00 15000.00 M-066
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete
with all components as per drawing and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 150.00
foundation anchorage bolts and consumables.
c) Overhead charges @ 0.2 on (a+b) 3075.62
d) Contractor's profit @ 0.1 on (a+b+c) 1845.37
cost for 19200cc of elastomeric bearing = a+b+c+d 20299.12
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 1.06

say 1.00
13.15 2000 & Supplying, fitting and fixing in position true to line and level
2200 sliding plate bearing with stainless steel plate sliding on
stainless steel plate with mild steel matrix complete including
all accessories as per drawing and Technical Specifications.

Unit: one tonne capacity


Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour

Page 15 of 264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.04 151.44 6.06 L-12
Mazdoor day 0.75 136.69 102.52 L-13
Mazdoor (Skilled) day 0.35 164.69 57.64 L-15
b) Material
Supply of sliding plate bearing of 80 tonne design each. 1.00 16378.00 16378.00 M-070
capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 163.78
foundation anchorage bolts and consumables.
c) Overhead charges @ 0.2 on (a+b) 3341.60
d) Contractor's profit @ 0.1 on (a+b+c) 2004.96
cost for 80 tonnes of capacity bearing = a+b+c+d 22054.56
275.68
say 276.00
13.16 2000 & Supplying, fitting and fixing in position true to line and level
2200 POT-PTFE bearing consisting of a metal piston supported
by a disc or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete assembly to
be of cast steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400, section
9.1 & 9.2 and clause 2006 of MoRTH Specifications
complete as per drawing and approved Technical
Specifications.

Unit: one tonne capacity 387.20


Considering a Pot bearing assembly of 250 tonne capacity
for this analysis.
a) Labour
Mate day 0.08 151.44 12.12 L-12
Mazdoor day 1.50 136.69 205.04 L-13
Mazdoor (Skilled) day 0.50 164.69 82.35 L-15
b) Material
Pot type bearing assembly consisting of a metal piston each. 1.00 41309.00 41309.00 M-068
supported by a disc, PTFE pads providing sliding
surfaces against stainless steel mating together with
cast steel assemblies/fabricated structural steel
assemblies duly painted with all components as per
clause 2006 and complete as per drawings and
Technical Specifications.

Add 1 per cent of cost of bearing assembly for 413.09


foundation anchorage bolts and consumables.
c) Overhead charges @ 0.2 on (a+b) 8404.32
d) Contractor's profit @ 0.1 on (a+b+c) 5042.59
cost for 250 tonnes capacity bearing = a+b+c+d 55468.49
Rate per tonne capacity = (a+b+c+d)/250 221.87
say 222.00

Page 16 of 264
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and Technical
1700 Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 5000.00 25600.00 M-081
Coarse sand cum 6.75 710.46 4795.61 M-005
20 mm Aggregate cum 8.10 1028.00 8326.80 M-053
10 mm Aggregate cum 5.40 1005.00 5427.00 M-051
b) Labour
Mate day 0.86 151.44 130.24 L-12
Mason day 1.50 223.36 335.04 L-11
Mazdoor day 20.00 136.69 2733.80 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 233.00 1398.00 P&M-009
Generator 33 KVA hour 6.00 406.80 2440.80 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 51188.00
15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 51188.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 10237.60
e) Overhead charges @ 0.2 on (a+b+c+d) 12285.12
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7371.07
Cost for 15 cum = a+b+c+d+e+f 81081.79
Rate per cum = (a+b+c+d+e+f)/15 5405.45
say 5405.00
14.1A (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 51188.00


15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 12797.00
e) Overhead charges @ 0.2 on (a+b+c+d) 12797.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7678.20
Cost for 15 cum = a+b+c+d+e+f 84460.20
Rate per cum = (a+b+c+d+e+f)/15 5630.68
say 5631.00
14.1A (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 51188.00


15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 15356.40
e) Overhead charges @ 0.2 on (a+b+c+d) 13308.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7985.33
Cost for 15 cum = a+b+c+d+e+f 87838.61
Rate per cum = (a+b+c+d+e+f)/15 5855.91
say 5856.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m

Page 1 of 264
Basic Cost of Labour, Material & Machinery (a+b+c) for 51188.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 12797.00
e) Overhead charges @ 0.2 on (a+b+c+d) 12797.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7678.20
Cost for 15 cum = a+b+c+d+e+f 84460.20
Rate per cum = (a+b+c+d+e+f)/15 5630.68
say 5631.00
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 51188.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 15356.40
e) Overhead charges @ 0.2 on (a+b+c+d) 13308.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7985.33
Cost for 15 cum = a+b+c+d+e+f 87838.61
Rate per cum = (a+b+c+d+e+f)/15 5855.91
say 5856.00
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 51188.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 17915.80
e) Overhead charges @ 0.2 on (a+b+c+d) 13820.76
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8292.46
Cost for 15 cum = a+b+c+d+e+f 91217.02
Rate per cum = (a+b+c+d+e+f)/15 6081.13
say 6081.00
14.1A Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 5000.00 204600.00 M-081
Coarse sand cum 54.00 828.00 44712.00 M-004
20 mm Aggregate cum 64.80 1028.00 66614.40 M-053
10 mm Aggregate cum 43.20 1005.00 43416.00 M-051
b) Labour
Mate day 0.84 151.44 127.21 L-12
Mason day 3.00 223.36 670.08 L-11
Mazdoor day 18.00 136.69 2460.42 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2232.00 13392.00 P&M-002
Generator 100 KVA hour 6.00 762.75 4576.50 P&M-080
Loader hour 6.00 806.00 4836.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1017.00 15255.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Concrete Pump hour 6.00 256.00 1536.00 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for 402806.00
120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 402806.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 80561.20
e) Overhead charges @ 0.2 on (a+b+c+d) 96673.44

Page 2 of 264
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 58004.06
Cost for 120 cum = a+b+c+d+e+f 638044.70
Rate per cum = (a+b+c+d+e+f)/120 5317.04
say 5317.00
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 402806.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 100701.50
e) Overhead charges @ 0.2 on (a+b+c+d) 100701.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 60420.90
Cost for 120 cum = a+b+c+d+e+f 664629.90
Rate per cum = (a+b+c+d+e+f)/120 5538.58
say 5539.00
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 402806.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 120841.80
e) Overhead charges @ 0.2 on (a+b+c+d) 104729.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 62837.74
Cost for 120 cum = a+b+c+d+e+f 691215.10
Rate per cum = (a+b+c+d+e+f)/120 5760.13
say 5760.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 402806.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 100701.50
e) Overhead charges @ 0.2 on (a+b+c+d) 100701.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 60420.90
Cost for 120 cum = a+b+c+d+e+f 664629.90
Rate per cum = (a+b+c+d+e+f)/120 5538.58
say 5539.00
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 402806.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 120841.80
e) Overhead charges @ 0.2 on (a+b+c+d) 104729.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 62837.74
Cost for 120 cum = a+b+c+d+e+f 691215.10
Rate per cum = (a+b+c+d+e+f)/120 5760.13
say 5760.00
14.1A (r)
Case II
(ii)
Height above 10m 402806.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 140982.10
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 108757.62
e) Overhead charges @ 0.2 on (a+b+c+d) 65254.57
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 717800.29
Cost for 120 cum = a+b+c+d+e+f 5981.67
Rate per cum = (a+b+c+d+e+f)/120 say 5982.00
14.1 B
Case I RCC Grade M25
Using Concrete Mixer
Unit = 1 cum

Page 3 of 264
Taking output = 15 cum
a) Material tonne 5.99 5000.00 29950.00 M-081
Cement cum 6.75 710.46 4795.61 M-005
Coarse sand cum 8.10 1028.00 8326.80 M-053
20 mm Aggregate cum 5.40 1005.00 5427.00 M-051
10 mm Aggregate
b) Labour day 0.86 151.44 130.24 L-12
Mate day 1.50 223.36 335.04 L-11
Mason day 20.00 136.69 2733.80 L-13
Mazdoor
c) Machinery hour 6.00 233.00 1398.00 P&M-009
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079
Generator 33 KVA 55538.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
15 cum
14.1B (i) For formwork and staging add the following:
Case I
(p) For solid slab super-structure, 20-30 per cent of (a+b+c)

Height upto 5m 55538.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 20.00 11107.60
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 13329.12
e) Overhead charges @ 0.2 on (a+b+c+d) 7997.47
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 87972.19
Cost for 15 cum = a+b+c+d+e+f 5864.81
Rate per cum = (a+b+c+d+e+f)/15 say 5865.00
14.1B (q)
Case I (i)

Height 5m to 10m 55538.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 13884.50
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 13884.50
e) Overhead charges @ 0.2 on (a+b+c+d) 8330.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 91637.70
Cost for 15 cum = a+b+c+d+e+f 6109.18
Rate per cum = (a+b+c+d+e+f)/15 say 6109.00
14.1B (r)
Case I (i)

Height above 10m 55538.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 16661.40
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 14439.88
e) Overhead charges @ 0.2 on (a+b+c+d) 8663.93
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95303.21
Cost for 15 cum = a+b+c+d+e+f 6353.55
Rate per cum = (a+b+c+d+e+f)/15 say 6354.00
14.1B (ii)
Case I
(p) For T-beam & slab, 25-35 per cent of (a+b+c)
Height upto 5m 55538.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 13884.50
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 13884.50
e) Overhead charges @ 0.2 on (a+b+c+d) 8330.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 91637.70
Cost for 15 cum = a+b+c+d+e+f 6109.18
Rate per cum = (a+b+c+d+e+f)/15 say 6109.00
14.1B (q)
Case I
(ii)

Page 4 of 264
Height 5m to 10m 55538.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 16661.40
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 14439.88
e) Overhead charges @ 0.2 on (a+b+c+d) 8663.93
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95303.21
Cost for 15 cum = a+b+c+d+e+f 6353.55
Rate per cum = (a+b+c+d+e+f)/15 say 6354.00
14.1B (r)
Case I
(ii)
Height above 10m 55538.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 19438.30
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 14995.26
e) Overhead charges @ 0.2 on (a+b+c+d) 8997.16
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 98968.72
Cost for 15 cum = a+b+c+d+e+f 6597.91
Rate per cum = (a+b+c+d+e+f)/15 say 6598.00
14.1B Case II
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material tonne 47.95 5000.00 239750.00 M-081
Cement cum 54.20 828.00 44877.60 M-004
Coarse sand cum 64.80 1028.00 66614.40 M-053
20 mm Aggregate cum 43.20 1005.00 43416.00 M-051
10 mm Aggregate
b) Labour day 0.84 151.44 127.21 L-12
Mate day 3.00 223.36 670.08 L-11
Mason day 18.00 136.69 2460.42 L-13
Mazdoor
c) Machinery hour 6.00 2232.00 13392.00 P&M-002
Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080
Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017
Loader
Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007
Concrete Pump 438122.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
14.1B (i) For formwork and staging add the following:
Case II
(p) For solid slab super-structure, 20-30 per cent of (a+b+c)

Height upto 5m 438122.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 20.00 87624.40
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 105149.28
e) Overhead charges @ 0.2 on (a+b+c+d) 63089.57
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 693985.25
Cost for 120 cum = a+b+c+d+e+f 5783.21
Rate per cum = (a+b+c+d+e+f)/120 say 5783.00
14.1B (q)
Case II
(i)
Height 5m to 10m 438122.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 109530.50
120 cum

Page 5 of 264
d) Formwork and staging 25 per cent of (a+b+c) 109530.50
e) Overhead charges @ 0.2 on (a+b+c+d) 65718.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 722901.30
Cost for 120 cum = a+b+c+d+e+f 6024.18
Rate per cum = (a+b+c+d+e+f)/120 say 6024.00
14.1B (r)
Case II
(i)
Height above 10m 438122.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 131436.60
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 113911.72
e) Overhead charges @ 0.2 on (a+b+c+d) 68347.03
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 751817.35
Cost for 120 cum = a+b+c+d+e+f 6265.14
Rate per cum = (a+b+c+d+e+f)/120 say 6265.00
14.1B (ii)
Case II
(p) For T-beam & slab, 25-35 per cent of (a+b+c)
Height upto 5m 438122.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 109530.50
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 109530.50
e) Overhead charges @ 0.2 on (a+b+c+d) 65718.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 722901.30
Cost for 120 cum = a+b+c+d+e+f 6024.18
Rate per cum = (a+b+c+d+e+f)/120 say 6024.00
14.1B (q)
Case II
(ii)
Height 5m to 10m 438122.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 131436.60
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 113911.72
e) Overhead charges @ 0.2 on (a+b+c+d) 68347.03
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 751817.35
Cost for 120 cum = a+b+c+d+e+f 6265.14
Rate per cum = (a+b+c+d+e+f)/120 say 6265.00
14.1B (r)
Case II
(ii)
Height above 10m 438122.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 153342.70
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 118292.94
e) Overhead charges @ 0.2 on (a+b+c+d) 70975.76
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 780733.40
Cost for 120 cum = a+b+c+d+e+f 6506.11
Rate per cum = (a+b+c+d+e+f)/120 say 6506.00
14.1 C
Case I RCC Grade M 30
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material tonne 6.10 5000.00 30500.00 M-081
Cement cum 6.75 710.46 4795.61 M-005
Coarse sand cum 8.10 1028.00 8326.80 M-053
20 mm Aggregate cum 5.40 1005.00 5427.00 M-051
10 mm Aggregate
b) Labour day 0.90 151.44 136.30 L-12
Mate day 1.50 223.36 335.04 L-11
Mason day 21.00 136.69 2870.49 L-13

Page 6 of 264
Mazdoor
c) Machinery hour 6.00 233.00 1398.00 P&M-009
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079
Generator 33 KVA 56231.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
15 cum
14.1C (i) For formwork and staging add the following:
Case I
(p) For solid slab super-structure, 20-30 per cent of (a+b+c)

Height upto 5m 56231.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 20.00 11246.20
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 13495.44
e) Overhead charges @ 0.2 on (a+b+c+d) 8097.26
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89069.90
Cost for 15 cum = a+b+c+d+e+f 5937.99
Rate per cum = (a+b+c+d+e+f)/15 say 5938.00
14.1C (q)
Case I (i)

Height 5m to 10m 56231.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 14057.75
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 14057.75
e) Overhead charges @ 0.2 on (a+b+c+d) 8434.65
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 92781.15
Cost for 15 cum = a+b+c+d+e+f 6185.41
Rate per cum = (a+b+c+d+e+f)/15 say 6185.00
14.1C (r)
Case I (i)

Height above 10m 56231.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 16869.30
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 14620.06
e) Overhead charges @ 0.2 on (a+b+c+d) 8772.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96492.40
Cost for 15 cum = a+b+c+d+e+f 6432.83
Rate per cum = (a+b+c+d+e+f)/15 say 6433.00
14.1C (ii)
Case I
(p) For T-beam & slab, 25-35 per cent of (a+b+c)
Height upto 5m 56231.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 14057.75
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 14057.75
e) Overhead charges @ 0.2 on (a+b+c+d) 8434.65
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 92781.15
Cost for 15 cum = a+b+c+d+e+f 6185.41
Rate per cum = (a+b+c+d+e+f)/15 say 6185.00
14.1C (q)
Case I
(ii)
Height 5m to 10m 56231.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 16869.30
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 14620.06
e) Overhead charges @ 0.2 on (a+b+c+d) 8772.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96492.40
Cost for 15 cum = a+b+c+d+e+f 6432.83
Rate per cum = (a+b+c+d+e+f)/15 say 6433.00

Page 7 of 264
14.1C (r)
Case I
(ii)
Height above 10m 56231.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 19680.85
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 15182.37
e) Overhead charges @ 0.2 on (a+b+c+d) 9109.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 100203.64
Cost for 15 cum = a+b+c+d+e+f 6680.24
Rate per cum = (a+b+c+d+e+f)/15 say 6680.00
14.1C Case II
Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material tonne 48.79 5000.00 243950.00 M-081
Cement cum 54.60 828.00 45208.80 M-004
Coarse sand cum 64.80 1028.00 66614.40 M-053
20 mm Aggregate cum 43.20 1005.00 43416.00 M-051
10 mm Aggregate
b) Labour day 0.88 151.44 133.27 L-12
Mate day 3.00 223.36 670.08 L-11
Mason day 19.00 136.69 2597.11 L-13
Mazdoor
c) Machinery hour 6.00 2232.00 13392.00 P&M-002
Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080
Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017
Loader
Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007
Concrete Pump 442796.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
14.1C (i) For formwork and staging add the following:
Case II
(p) For solid slab super-structure, 20-30 per cent of (a+b+c)

Height upto 5m 442796.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 20.00 88559.20
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 106271.04
e) Overhead charges @ 0.2 on (a+b+c+d) 63762.62
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 701388.86
Cost for 120 cum = a+b+c+d+e+f 5844.91
Rate per cum = (a+b+c+d+e+f)/120 say 5845.00
14.1C (q)
Case II
(i)
Height 5m to 10m 442796.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 110699.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 110699.00
e) Overhead charges @ 0.2 on (a+b+c+d) 66419.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 730613.40
Cost for 120 cum = a+b+c+d+e+f 6088.45
Rate per cum = (a+b+c+d+e+f)/120 say 6088.00
14.1C (r)
Case II
(i)
Height above 10m 442796.00

Page 8 of 264
Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 132838.80
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 115126.96
e) Overhead charges @ 0.2 on (a+b+c+d) 69076.18
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 759837.94
Cost for 120 cum = a+b+c+d+e+f 6331.98
Rate per cum = (a+b+c+d+e+f)/120 say 6332.00
14.1C (ii)
Case II
(p) For T-beam & slab, 25-35 per cent of (a+b+c)
Height upto 5m 442796.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 110699.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 110699.00
e) Overhead charges @ 0.2 on (a+b+c+d) 66419.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 730613.40
Cost for 120 cum = a+b+c+d+e+f 6088.45
Rate per cum = (a+b+c+d+e+f)/120 say 6088.00
14.1C (q)
Case II
(ii)
Height 5m to 10m 442796.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 132838.80
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 115126.96
e) Overhead charges @ 0.2 on (a+b+c+d) 69076.18
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 759837.94
Cost for 120 cum = a+b+c+d+e+f 6331.98
Rate per cum = (a+b+c+d+e+f)/120 say 6332.00
14.1C (r)
Case II
(ii)
Height above 10m 442796.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 154978.60
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 119554.92
e) Overhead charges @ 0.2 on (a+b+c+d) 71732.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 789062.47
Cost for 120 cum = a+b+c+d+e+f 6575.52
Rate per cum = (a+b+c+d+e+f)/120 say 6576.00
14.1 D
Case I RCC/PSC Grade M35
Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material tonne 6.33 5000.00 31650.00 M-081
Cement cum 6.75 710.46 4795.61 M-005
Coarse sand cum 8.10 1028.00 8326.80 M-053
20 mm Aggregate cum 5.40 1005.00 5427.00 M-051
10 mm Aggregate
b) Labour day 0.90 151.44 136.30 L-12
Mate day 1.50 223.36 335.04 L-11
Mason day 21.00 136.69 2870.49 L-13
Mazdoor
c) Machinery hour 6.00 233.00 1398.00 P&M-009
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079
Generator 33 KVA 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
15 cum
14.1D (i) For formwork and staging add the following:
Case I
(p) For solid slab super-structure, 18-28 per cent of (a+b+c)

Page 9 of 264
Height upto 5m 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 18.00 10328.58
15 cum
d) Formwork and staging 18 per cent of (a+b+c) 13541.92
e) Overhead charges @ 0.2 on (a+b+c+d) 8125.15
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89376.65
Cost for 15 cum = a+b+c+d+e+f 5958.44
Rate per cum = (a+b+c+d+e+f)/15 say 5958.00
14.1D (q)
Case I (i)

Height 5m to 10m 57381.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 23.00 13197.63
15 cum
d) Formwork and staging 23 per cent of (a+b+c) 14115.73
e) Overhead charges @ 0.2 on (a+b+c+d) 8469.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 93163.79
Cost for 15 cum = a+b+c+d+e+f 6210.92
Rate per cum = (a+b+c+d+e+f)/15 say 6211.00
14.1D (r)
Case I (i)

Height above 10m 57381.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 28.00 16066.68
15 cum
d) Formwork and staging 28 per cent of (a+b+c) 14689.54
e) Overhead charges @ 0.2 on (a+b+c+d) 8813.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96950.94
Cost for 15 cum = a+b+c+d+e+f 6463.40
Rate per cum = (a+b+c+d+e+f)/15 say 6463.00
14.1D (ii)
Case I
(p) For T-beam & slab, 23-33 per cent of (a+b+c)
Height upto 5m 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 23.00 13197.63
15 cum
d) Formwork and staging 23 per cent of (a+b+c) 14115.73
e) Overhead charges @ 0.2 on (a+b+c+d) 8469.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 93163.79
Cost for 15 cum = a+b+c+d+e+f 6210.92
Rate per cum = (a+b+c+d+e+f)/15 say 6211.00
14.1D (q)
Case I
(ii)
Height 5m to 10m 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 28.00 16066.68
15 cum
d) Formwork and staging 28 per cent of (a+b+c) 14689.54
e) Overhead charges @ 0.2 on (a+b+c+d) 8813.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 96950.94
Cost for 15 cum = a+b+c+d+e+f 6463.40
Rate per cum = (a+b+c+d+e+f)/15 say 6463.00
14.1D (r)
Case I
(ii)
Height above 10m 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 33.00 18935.73
15 cum
d) Formwork and staging 33 per cent of (a+b+c) 15263.35
e) Overhead charges @ 0.2 on (a+b+c+d) 9158.01
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 100738.08
Cost for 15 cum = a+b+c+d+e+f 6715.87
Rate per cum = (a+b+c+d+e+f)/15 say 6716.00

Page 10 of 264
14.1D (iii)
Case I
(p) For box girder and balanced cantilever, 38-58 per cent of
cost of concrete.
Height upto 5m 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 38.00 21804.78
15 cum
d) Formwork and staging 38 per cent of (a+b+c) 15837.16
e) Overhead charges @ 0.2 on (a+b+c+d) 9502.29
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 104525.23
Cost for 15 cum = a+b+c+d+e+f 6968.35
Rate per cum = (a+b+c+d+e+f)/15 say 6968.00
14.1D (q)
Case I
(iii)
Height 5m to 10m 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 48.00 27542.88
15 cum
d) Formwork and staging 48 per cent of (a+b+c) 16984.78
e) Overhead charges @ 0.2 on (a+b+c+d) 10190.87
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 112099.52
Cost for 15 cum = a+b+c+d+e+f 7473.30
Rate per cum = (a+b+c+d+e+f)/15 say 7473.00
14.1D (r)
Case I
(iii)
Height above 10m 57381.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 58.00 33280.98
15 cum
d) Formwork and staging 58 per cent of (a+b+c) 18132.40
e) Overhead charges @ 0.2 on (a+b+c+d) 10879.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 119673.81
Cost for 15 cum = a+b+c+d+e+f 7978.25
Rate per cum = (a+b+c+d+e+f)/15 say 7978.00
Case II
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material tonne 50.64 5000.00 253200.00 M-081
Cement cum 54.00 828.00 44712.00 M-004
Coarse sand cum 64.80 1028.00 66614.40 M-053
20 mm Aggregate cum 43.20 1005.00 43416.00 M-051
10 mm Aggregate
b) Labour day 0.88 151.44 133.27 L-12
Mate day 3.00 223.36 670.08 L-11
Mason day 19.00 136.69 2597.11 L-13
Mazdoor
c) Machinery hour 6.00 2232.00 13392.00 P&M-002
Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080
Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017
Loader
Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007
Concrete Pump 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
14.1D (i) For formwork and staging add the following:
Case II
(p) For solid slab super-structure, 18-28 per cent of (a+b+c)

Page 11 of 264
Height upto 5m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 18.00 81278.82
120 cum
d) Formwork and staging 18 per cent of (a+b+c) 106565.56
e) Overhead charges @ 0.2 on (a+b+c+d) 63939.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 703332.72
Cost for 120 cum = a+b+c+d+e+f 5861.11
Rate per cum = (a+b+c+d+e+f)/120 say 5861.00
14.1D (q)
Case II
(i)
Height 5m to 10m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 23.00 103856.27
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 111081.05
e) Overhead charges @ 0.2 on (a+b+c+d) 66648.63
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 733134.96
Cost for 120 cum = a+b+c+d+e+f 6109.46
Rate per cum = (a+b+c+d+e+f)/120 say 6109.00
14.1D (r)
Case II
(i)
Height above 10m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 28.00 126433.72
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 115596.54
e) Overhead charges @ 0.2 on (a+b+c+d) 69357.93
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 762937.19
Cost for 120 cum = a+b+c+d+e+f 6357.81
Rate per cum = (a+b+c+d+e+f)/120 say 6358.00
14.1D (ii)
Case II
(p) For T-beam & slab, 23-33 per cent of (a+b+c)
Height upto 5m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 23.00 103856.27
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 111081.05
e) Overhead charges @ 0.2 on (a+b+c+d) 66648.63
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 733134.96
Cost for 120 cum = a+b+c+d+e+f 6109.46
Rate per cum = (a+b+c+d+e+f)/120 say 6109.00
14.1D (q)
Case II
(ii)
Height 5m to 10m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 28.00 126433.72
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 115596.54
e) Overhead charges @ 0.2 on (a+b+c+d) 69357.93
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 762937.19
Cost for 120 cum = a+b+c+d+e+f 6357.81
Rate per cum = (a+b+c+d+e+f)/120 say 6358.00
14.1D (r)
Case II
(ii)
Height above 10m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 33.00 149011.17
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 120112.03
e) Overhead charges @ 0.2 on (a+b+c+d) 72067.22
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 792739.42
Cost for 120 cum = a+b+c+d+e+f 6606.16
Rate per cum = (a+b+c+d+e+f)/120 say 6606.00

Page 12 of 264
14.1D (iii)
Case II
(p) For box girder and balanced cantilever, 38-58 per cent of
cost of concrete.
Height upto 5m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 38.00 171588.62
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 124627.52
e) Overhead charges @ 0.2 on (a+b+c+d) 74776.51
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 822541.66
Cost for 120 cum = a+b+c+d+e+f 6854.51
Rate per cum = (a+b+c+d+e+f)/120 say 6855.00
14.1D (q)
Case II
(iii)
Height 5m to 10m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 48.00 216743.52
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 133658.50
e) Overhead charges @ 0.2 on (a+b+c+d) 80195.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 882146.13
Cost for 120 cum = a+b+c+d+e+f 7351.22
Rate per cum = (a+b+c+d+e+f)/120 say 7351.00
14.1D (r)
Case II
(iii)
Height above 10m 451549.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 58.00 261898.42
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 142689.48
e) Overhead charges @ 0.2 on (a+b+c+d) 85613.69
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 941750.59
Cost for 120 cum = a+b+c+d+e+f 7847.92
Rate per cum = (a+b+c+d+e+f)/120 say 7848.00
14.1 E
Case 1 PSC Grade M-40
Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material tonne 6.45 5000.00 32250.00 M-081
Cement cum 6.75 710.46 4795.61 M-005
Coarse sand cum 8.10 1028.00 8326.80 M-053
20 mm Aggregate cum 5.40 1005.00 5427.00 M-051
10 mm Aggregate kg 25.80 44.70 1153.26 M-180
Admixture @ 0.4 per cent of cement
b) Labour day 0.96 151.44 145.38 L-12
Mate day 2.00 223.36 446.72 L-11
Mason day 22.00 136.69 3007.18 L-13
Mazdoor
c) Machinery hour 6.00 233.00 1398.00 P&M-009
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 406.80 2440.80 P&M-079
Generator 33 KVA 59391.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
15 cum
14.1E (i) For formwork and staging add the following:
Case I
(p) For solid slab super-structure, 20-30 per cent of (a+b+c)

Height upto 5m 59391.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 20.00 11878.20
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 14253.84
e) Overhead charges @ 0.2 on (a+b+c+d) 8552.30

Page 13 of 264
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 94075.34
Cost for 15 cum = a+b+c+d+e+f 6271.69
Rate per cum = (a+b+c+d+e+f)/15 say 6272.00
14.1E (q)
Case I (i)

Height 5m to 10m 59391.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 14847.75
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 14847.75
e) Overhead charges @ 0.2 on (a+b+c+d) 8908.65
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 97995.15
Cost for 15 cum = a+b+c+d+e+f 6533.01
Rate per cum = (a+b+c+d+e+f)/15 say 6533.00
14.1E (r)
Case I (i)

Height above 10m 59391.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 17817.30
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 15441.66
e) Overhead charges @ 0.2 on (a+b+c+d) 9265.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 101914.96
Cost for 15 cum = a+b+c+d+e+f 6794.33
Rate per cum = (a+b+c+d+e+f)/15 say 6794.00
14.1E (ii)
Case I
(p) For T-beam & slab, 25-35 per cent of (a+b+c)
Height upto 5m 59391.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 25.00 14847.75
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 14847.75
e) Overhead charges @ 0.2 on (a+b+c+d) 8908.65
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 97995.15
Cost for 15 cum = a+b+c+d+e+f 6533.01
Rate per cum = (a+b+c+d+e+f)/15 say 6533.00
14.1E (q)
Case I
(ii)
Height 5m to 10m 59391.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 30.00 17817.30
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 15441.66
e) Overhead charges @ 0.2 on (a+b+c+d) 9265.00
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 101914.96
Cost for 15 cum = a+b+c+d+e+f 6794.33
Rate per cum = (a+b+c+d+e+f)/15 say 6794.00
14.1E (r)
Case I
(ii)
Height above 10m 59391.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 20786.85
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 16035.57
e) Overhead charges @ 0.2 on (a+b+c+d) 9621.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 105834.76
Cost for 15 cum = a+b+c+d+e+f 7055.65
Rate per cum = (a+b+c+d+e+f)/15 say 7056.00
14.1E Case II
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material tonne 51.60 5000.00 258000.00 M-081

Page 14 of 264
Cement cum 54.00 828.00 44712.00 M-004
Coarse sand cum 64.80 1028.00 66614.40 M-053
20 mm Aggregate cum 43.20 1005.00 43416.00 M-051
10 mm Aggregate kg 206.40 44.70 9226.08 M-180
Admixture @ 0.4 per cent of cement
b) Labour day 0.94 151.44 142.35 L-12
Mate day 3.50 223.36 781.76 L-11
Mason day 20.00 136.69 2733.80 L-13
Mazdoor
c) Machinery hour 6.00 2232.00 13392.00 P&M-002
Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080
Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017
Loader
Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007
Concrete Pump 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
14.1E (i) For formwork and staging add the following:
Case II
(p) For solid/voided slab super-structure, 18-28 per cent of
(a+b+c)
Height upto 5m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 18.00 83849.94
cum
d) Formwork and staging 18 per cent of (a+b+c) 109936.59
e) Overhead charges @ 0.2 on (a+b+c+d) 65961.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 725581.48
Cost for 15 cum = a+b+c+d+e+f 6046.51
Rate per cum = (a+b+c+d+e+f)/120 say 6047.00
14.1E (q)
Case II
(i)
Height 5m to 10m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 23.00 107141.59
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 114594.92
e) Overhead charges @ 0.2 on (a+b+c+d) 68756.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 756326.46
Cost for 120 cum = a+b+c+d+e+f 6302.72
Rate per cum = (a+b+c+d+e+f)/120 say 6303.00
14.1E (r)
Case II
(i)
Height above 10m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 28.00 130433.24
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 119253.25
e) Overhead charges @ 0.2 on (a+b+c+d) 71551.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 787071.44
Cost for 120 cum = a+b+c+d+e+f 6558.93
Rate per cum = (a+b+c+d+e+f)/120 say 6559.00
14.1E (ii)
Case II
(p) For T-beam & slab, 23-33 per cent of (a+b+c)
Height upto 5m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 23.00 107141.59
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 114594.92
e) Overhead charges @ 0.2 on (a+b+c+d) 68756.95

Page 15 of 264
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 756326.46
Cost for 120 cum = a+b+c+d+e+f 6302.72
Rate per cum = (a+b+c+d+e+f)/120 say 6303.00
14.1E (q)
Case II
(ii)
Height 5m to 10m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 28.00 130433.24
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 119253.25
e) Overhead charges @ 0.2 on (a+b+c+d) 71551.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 787071.44
Cost for 120 cum = a+b+c+d+e+f 6558.93
Rate per cum = (a+b+c+d+e+f)/120 say 6559.00
14.1E (r)
Case II
(ii)
Height above 10m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 33.00 153724.89
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 123911.58
e) Overhead charges @ 0.2 on (a+b+c+d) 74346.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 817816.41
Cost for 120 cum = a+b+c+d+e+f 6815.14
Rate per cum = (a+b+c+d+e+f)/120 say 6815.00
14.1E (iii)
Case II
(p) For cast-in-situ box girder, segment construction and
balanced cantilever, 38-58 per cent of cost of concrete.

Height upto 5m 465833.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 38.00 177016.54
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 128569.91
e) Overhead charges @ 0.2 on (a+b+c+d) 77141.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 848561.39
Cost for 120 cum = a+b+c+d+e+f 7071.34
Rate per cum = (a+b+c+d+e+f)/120 say 7071.00
14.1E (q)
Case II
(iii)
Height 5m to 10m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 48.00 223599.84
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 137886.57
e) Overhead charges @ 0.2 on (a+b+c+d) 82731.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 910051.35
Cost for 120 cum = a+b+c+d+e+f 7583.76
Rate per cum = (a+b+c+d+e+f)/120 say 7584.00
14.1E (r)
Case II
(iii)
Height above 10m 465833.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 58.00 270183.14
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 147203.23
e) Overhead charges @ 0.2 on (a+b+c+d) 88321.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 971541.30
Cost for 120 cum = a+b+c+d+e+f 8096.18
Rate per cum = (a+b+c+d+e+f)/120 say 8096.00
14.1F F
PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum

Page 16 of 264
a) Material tonne 55.80 5000.00 279000.00 M-081
Cement cum 54.00 828.00 44712.00 M-004
Coarse sand cum 64.80 1028.00 66614.40 M-053
20 mm Aggregate cum 43.20 1005.00 43416.00 M-051
10 mm Aggregate kg 223.20 44.70 9977.04 M-180
Admixture @ 0.4 per cent of cement
b) Labour day 0.94 151.44 142.35 L-12
Mate day 3.50 223.36 781.76 L-11
Mason day 20.00 136.69 2733.80 L-13
Mazdoor
c) Machinery hour 6.00 2232.00 13392.00 P&M-002
Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080
Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017
Loader
Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007
Concrete Pump 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
14.1F (i) For formwork and staging add the following:
(p) For solid slab/voided slab super-structure, 16-26 per cent
of cost of concrete (a+b+c)
Height upto 5m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 16.00 78013.44
120 cum
d) Formwork and staging 16 per cent of (a+b+c) 113119.49
e) Overhead charges @ 0.2 on (a+b+c+d) 67871.69
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 746588.62
Cost for 120 cum = a+b+c+d+e+f 6221.57
Rate per cum = (a+b+c+d+e+f)/120 say 6222.00
14.1F (q)
(i)
Height 5m to 10m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 21.00 102392.64
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 117995.33
e) Overhead charges @ 0.2 on (a+b+c+d) 70797.20
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 778769.16
Cost for 120 cum = a+b+c+d+e+f 6489.74
Rate per cum = (a+b+c+d+e+f)/120 say 6490.00
14.1F (r)
(i)
Height above 10m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 26.00 126771.84
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 122871.17
e) Overhead charges @ 0.2 on (a+b+c+d) 73722.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 810949.71
Cost for 120 cum = a+b+c+d+e+f 6757.91
Rate per cum = (a+b+c+d+e+f)/120 say 6758.00
14.1F (ii)
(p) For T-beam & slab including launching of precast girders by
launching truss upto 40 m span, 21-31 per cent of cost of
concrete.
Height upto 5m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 21.00 102392.64
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 117995.33
e) Overhead charges @ 0.2 on (a+b+c+d) 70797.20
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 778769.16

Page 17 of 264
Cost for 120 cum = a+b+c+d+e+f 6489.74
Rate per cum = (a+b+c+d+e+f)/120 say 6490.00
14.1F (q)
(ii)
Height 5m to 10m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 26.00 126771.84
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 122871.17
e) Overhead charges @ 0.2 on (a+b+c+d) 73722.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 810949.71
Cost for 120 cum = a+b+c+d+e+f 6757.91
Rate per cum = (a+b+c+d+e+f)/120 say 6758.00
14.1F (r)
(ii)
Height above 10m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 31.00 151151.04
120 cum
d) Formwork and staging 31 per cent of (a+b+c) 127747.01
e) Overhead charges @ 0.2 on (a+b+c+d) 76648.20
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 843130.25
Cost for 120 cum = a+b+c+d+e+f 7026.09
Rate per cum = (a+b+c+d+e+f)/120 say 7026.00
14.1F (iii)
(p) For cast-in-situ box girder, segmental construction and
balanced cantilever, 36-56 per cent of cost of concrete.

Height upto 5m 487584.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 36.00 175530.24
120 cum
d) Formwork and staging 36 per cent of (a+b+c) 132622.85
e) Overhead charges @ 0.2 on (a+b+c+d) 79573.71
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 875310.80
Cost for 120 cum = a+b+c+d+e+f 7294.26
Rate per cum = (a+b+c+d+e+f)/120 say 7294.00
14.1F (q)
(iii)
Height 5m to 10m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 46.00 224288.64
120 cum
d) Formwork and staging 46 per cent of (a+b+c) 142374.53
e) Overhead charges @ 0.2 on (a+b+c+d) 85424.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 939671.88
Cost for 120 cum = a+b+c+d+e+f 7830.60
Rate per cum = (a+b+c+d+e+f)/120 say 7831.00
14.1F (r)
(iii)
Height above 10m 487584.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 56.00 273047.04
120 cum
d) Formwork and staging 56 per cent of (a+b+c) 152126.21
e) Overhead charges @ 0.2 on (a+b+c+d) 91275.72
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1004032.97
Cost for 120 cum = a+b+c+d+e+f 8366.94
Rate per cum = (a+b+c+d+e+f)/120 say 8367.00
14.1 G
PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material tonne 58.80 5000.00 294000.00 M-081
Cement cum 54.00 828.00 44712.00 M-004
Coarse sand cum 64.80 1028.00 66614.40 M-053
20 mm Aggregate cum 43.20 1005.00 43416.00 M-051
10 mm Aggregate kg 235.20 44.70 10513.44 M-180

Page 18 of 264
Admixture @ 0.4 per cent of cement
b) Labour day 0.94 151.44 142.35 L-12
Mate day 3.50 223.36 781.76 L-11
Mason day 20.00 136.69 2733.80 L-13
Mazdoor
c) Machinery hour 6.00 2232.00 13392.00 P&M-002
Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080
Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017
Loader
Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007
Concrete Pump 503120.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
14.1G (i) For formwork and staging add the following:
(p) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

Height upto 5m 503120.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 176092.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 135842.40
e) Overhead charges @ 0.2 on (a+b+c+d) 81505.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 896559.84
Cost for 120 cum = a+b+c+d+e+f 7471.33
Rate per cum = (a+b+c+d+e+f)/120 say 7471.00
14.1G (q)
(i)
Height 5m to 10m 503120.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 45.00 226404.00
120 cum
d) Formwork and staging 45 per cent of (a+b+c) 145904.80
e) Overhead charges @ 0.2 on (a+b+c+d) 87542.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 962971.68
Cost for 120 cum = a+b+c+d+e+f 8024.76
Rate per cum = (a+b+c+d+e+f)/120 say 8025.00
14.1G (r)
(i)
Height above 10m 503120.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 55.00 276716.00
120 cum
d) Formwork and staging 55 per cent of (a+b+c) 155967.20
e) Overhead charges @ 0.2 on (a+b+c+d) 93580.32
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1029383.52
Cost for 120 cum = a+b+c+d+e+f 8578.20
Rate per cum = (a+b+c+d+e+f)/120 say 8578.00
14.1 H
PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material tonne 63.50 5000.00 317500.00 M-081
Cement cum 54.00 828.00 44712.00 M-004
Coarse sand cum 64.80 1028.00 66614.40 M-053
20 mm Aggregate cum 43.20 1005.00 43416.00 M-051
10 mm Aggregate kg 254.00 44.70 11353.80 M-180
Admixture @ 0.4 per cent of cement
b) Labour day 0.94 151.44 142.35 L-12
Mate day 3.50 223.36 781.76 L-11
Mason day 20.00 136.69 2733.80 L-13

Page 19 of 264
Mazdoor
c) Machinery hour 6.00 2232.00 13392.00 P&M-002
Batching Plant @ 20 cum/hour hour 6.00 762.75 4576.50 P&M-080
Generator 100 KVA hour 6.00 806.00 4836.00 P&M-017
Loader
Transit Mixer ( capacity 4.0 cu.m ) hour 15.00 1017.00 15255.00 P&M-049
Transit Mixer 4 cum capacity lead upto1 Km tonne.km 300L 2.03 610.20 Lead =1
km & P&M-
050
Lead beyond 1 Km, L - lead in Kilometer hour 6.00 256.00 1536.00 P&M-007
Concrete Pump 527460.00
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
14.1H (i) For formwork and staging add the following:
(p) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

Height upto 5m 527460.00


Basic Cost of Labour, Material & Machinery (a+b+c) for 35.00 184611.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 142414.20
e) Overhead charges @ 0.2 on (a+b+c+d) 85448.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 939933.72
Cost for 120 cum = a+b+c+d+e+f 7832.78
Rate per cum = (a+b+c+d+e+f)/120 say 7833.00
14.1H (q)
(i)
Height 5m to 10m 527460.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 45.00 237357.00
120 cum
d) Formwork and staging 45 per cent of (a+b+c) 152963.40
e) Overhead charges @ 0.2 on (a+b+c+d) 91778.04
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1009558.44
Cost for 120 cum = a+b+c+d+e+f 8412.99
Rate per cum = (a+b+c+d+e+f)/120 say 8413.00
14.1H (r)
(i)
Height above 10m 527460.00
Basic Cost of Labour, Material & Machinery (a+b+c) for 55.00 290103.00
120 cum
d) Formwork and staging 55 per cent of (a+b+c) 163512.60
e) Overhead charges @ 0.2 on (a+b+c+d) 98107.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 1079183.16
Cost for 120 cum = a+b+c+d+e+f 8993.19
Rate per cum = (a+b+c+d+e+f)/120 say 8993.00
Note
1.Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4 per cent of weight of cement may be added for
achieving desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
14.2 1600 3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
separately in the rate analysis.
Supplying, fitting and placing HYSD bar reinforcement in
super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT

Page 20 of 264
a) Material tonne 1.05 45000.00 47250.00 M-082
HYSD bars including 5 per cent for laps and wastage Kg 8.00 100.00 800.00 M-072

Binding wire
b) Labour for cutting, bending, tying and placing in day 0.44 151.44 66.63 L-12
position
Mate day 3.00 264.50 793.50 L-02
Blacksmith day 8.00 136.69 1093.52 L-13
Mazdoor 50004.00
Basic Cost of Labour & Material (a+b) 10000.73
c) Overhead charges @ 0.2 on (a+b) 6000.44
d) Contractor's profit @ 0.1 on (a+b+c) 66004.82
Rate per MT = a+b+c+d say 66005.00
14.3 1800
High tensile steel wires/strands including all accessories for
stressing, stressing operations and grouting complete as per
drawing and Technical Specifications

Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight =
0.377 MT)
a) Material tonne 0.39 57453.00 22119.41 M-119
H.T. Strand @ 9.42 kg/m including 2 per cent for metre 42.00 304.00 12768.00 M-165
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra each 2.00 6064.00 12128.00 M-187
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, tonne 0.125 5000.00 625.00 M-081
permanent wedges etc
Cement for grouting including 3 per cent wastage @ 2382.02
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

Add 0.50 per cent cost of material for Spacers,


Insulation tape and miscellaneous items
b) Labour
i) For making and fixing cables, anchorages day 0.16 151.44 24.23 L-12
Mate day 1.00 264.50 264.50 L-02
Blacksmith day 3.00 136.69 410.07 L-13
Mazdoor
ii) For prestressing day 0.05 151.44 7.57 L-12
Mate/Supervisor day 0.25 230.00 57.50 L-08
Prestressing operator / Fitter day 1.00 136.69 136.69 L-13
Mazdoor
iii) For grouting day 0.05 151.44 7.57 L-12
Mate/Supervisor day 0.25 223.36 55.84 L-11
Mason day 1.00 136.69 136.69 L-13
Mazdoor
c) Machinery hour 2.50 129.00 322.50 P&M-040
Stressing jack with pump hour 1.00 304.00 304.00 M-111
Grouting pump with agitator hour 3.50 406.80 1423.80 P&M-079
Generator 33 KVA. 630.19
d) Overhead charges @ 0.2 on (a+b+c) 378.12
e) Contractor's profit @ 0.1 on (a+b+c+d) 54181.70
Cost for 0.377 MT (a+b+c+d+e) 143718.03
Rate per MT = (a+b+c+d+e)/0.377 say 143718.00
Note
14.4 2702 Cost of HT steel has been taken for delivery at site. Hence
carriage has not been considered.
Providing and laying Cement concrete wearing coat M-30
grade including reinforcement complete as per drawing and
Technical Specifications
Unit = 1 cum
Taking output = 1 cum

Page 21 of 264
a) Material cum 1.00 3690.00 3690.00 Item
14.1(C)
Cement concrete M30 Grade Refer relevant item of tonne 0.075 50004.00 3750.30 Item 14.2 A
concrete in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
b) Labour day 0.15 136.69 20.50 L-13
Mazdoor for cleaning deck slab concrete surface. 1492.16
c) Overhead charges @ 0.2 on (a+b) 895.30
d) Contractor's profit @ 0.1 on (a+b+c) 9848.26
Rate per cum (a+b+c+d) say 9848.00
14.5 515 &
2702
Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in table 500-
29, prepared by using mastic cooker and laid to required
level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine
grained hard stone chipping of 9.5 mm nominal size at the
rate of 0.005cum per 10 sqm and at an approximate spacing
of 10 cm center to center in both directions, pressed into
surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum) assuming
a density of 2.3 tonnes/cum.
a) Labour day 0.49 151.44 74.21 L-12
Mate day 11.00 136.69 1503.59 L-13
Mazdoor day 1.25 164.69 205.86 L-15
Mazdoor (Skilled)
b) Machinery hour 0.06 357.00 21.42 P&M-031
Mechanical broom @ 1250 sqm per hour hour 0.06 319.00 19.14 P&M-001
Air compressor 250 cfm hour 6.00 62.00 372.00 P&M-030
Mastic cooker 1 tonne capacity hour 6.00 198.00 1188.00 P&M-005
Bitumen boiler 1500 litres capacity hour 1.00 282.50 282.50 P&M-053
Tractor for towing and positioning of mastic cooker and
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with tonne 0.204 55132.00 11246.93 M-074
coarse aggregates (based on mix design done by CRRI for a
specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent cum 0.39 476.80 185.95 M-021
by weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of tonne 0.36 4500.00 1620.00 M-188
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 =
0.39
iii) Lime stone dust filler with calcium carbonate content cum 0.55 1005.00 552.75 M-051
not less than 80 per cent by weight @ 17.92 per cent
by weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 cum 0.036 1213.00 43.67 M-142
per cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size for kg 1.05 55.13 57.89 M-
skid resistance = 72.46x0.005/10 = 0.036 074/1000
vi) Bitumen for coating of chips @ 2 per cent by weight 3474.78
= 0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg

d) Overhead charges @ 0.2 on (a+b+c) 2084.87


e) Contractor's profit @ 0.1 on (a+b+c+d) 22933.55
Cost for 72.46 sqm = a+b+c+d+e 316.50

Page 22 of 264
Rate per sqm = (a+b+c+d+e)/72.46 say 316.00
Note
1.The rates for 6 mm or any other thickness may be worked
out on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
14.6 2703, 5.The quantity of bitumen works out 17 per cent of the
1500, mastic asphalt blocks without aggregates and falls within the
1600 & standards laid down by MoRTH Specifications.
1700
Construction of precast RCC railing of M30 Grade,
aggregate size not exceeding 12 mm, true to line and grade,
tolerance of vertical RCC post not to exceed 1 in 500, centre
to centre spacing between vertical post not to exceed 2000
mm, leaving adequate space between vertical post for
expansion, complete as per approved drawings and
technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material cum 4.09 3690.00 15099.48 Item
14.1(C)
Cement concreteM30 Grade Refer relevant item of
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External 754.97
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).

Add 5 per cent of above cost for form work for casting tonne 0.87 50004.00 43253.46 Item 14.2 A
in casting yard.
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Refer MoRTH SD / 202. 2955.40
Add 5 per cent of (a) for handling and fixing of 12412.66
precast panels in position
b) Overhead charges @ 0.2 on (a) 7447.60
c) Contractor's profit @ 0.1 on (a+b) 81923.57
Rate for 48 m (a+b+c) 1706.74
Rate per metre (a+b+c)/48 say 1707.00
Note
1.Quantities of material have been adopted from standard
plans of MoRTH vide drawing no. SD/202.
14.7 2703, 2.48 m length is the total linear length adding both sides of
1500, 24 m span.
1600 &
1700
Construction of RCC railing of M30 Grade in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of
vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical
specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material cum 4.092 3690.00 15099.48 Item
14.1(C)

Page 23 of 264
Cement concreteM30 Grade Refer relevant item of
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External 1811.94
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).

Add 12 per cent of above cost for form work. tonne 0.87 50004.00 43253.46 Item 14.2 A

HYSD bar reinforcement Rate as per item No


14.2(Excluding OH & CP)
refer MoRTH SD / 202. 12032.98
b) Overhead charges @ 0.2 on (a) 7219.79
c) Contractor's profit @ 0.1 on (a+b) 79417.64
Rate for 48 m (a+b+c) 1654.53
Rate per metre (a+b+c)/48 say 1655.00
Note
1. Quantities of material have been adopted from standard
plans of MoRTH vide drawing no. SD/202.
14.8 2703.2 & 2. 48 m length is the total linear length adding both sides of
1900 24 m span.
Providing, fitting and fixing mild steel railing complete as per
drawing and Technical Specification

Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material: tonne 2.95 45000.00 132570.00 M-179
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 1.01 45000.00 45540.00 M-179
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 0.18 45000.00 8100.00 M-179
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.15 64070.00 9610.50 M-
130*1000
4) MS bolts, nuts and washers 9791.03
Add @ 5 per cent of cost of material for painting one 1958.21
shop coat with red oxide primer and three coats of
synthetic enamel paint and consumables to safeguard
against weathering and corrosion.
Add for cost of concrete for fixing vertical posts in the 1958.21
performed recess @ 1 per cent of cost of material.
Add for electricity charges, welding and drilling
equipment, electrodes and other consumables @ 1 per
cent of cost of material.
b) Labour day 2.80 151.44 424.03 L-12
Mate day 30.00 164.69 4940.70 L-15
Mazdoor (Skilled) day 40.00 136.69 5467.60 L-13
Mazdoor 44072.05
c) Overhead charges @ 0.2 on (a+b) 26443.23
d) Contractor's profit @ 0.1 on (a+b+c) 290875.55
Cost for 100 m steel railing = a+b+c+d 2908.76
Rate per metre (a+b+c+d)/100 say 2909.00
14.9 2705
Drainage Spouts complete as per drawing and Technical
specification
Unit = 1 No.
Taking output = 1 No.
a) Material Kg 4.00 46.53 186.10 M-
087/1000
Corrosion resistant Structural steel including 5 per cent metre 6.00 65.00 390.00 M-056
wastage
GI pipe 100mm dia each 6.00 13.00 78.00 M-110
GI bolt 10 mm Dia each 2.00 25.00 50.00 M-101
Galvanised MS flat clamp
b) Labour
For fabrication day 0.02 151.44 3.03 L-12

Page 24 of 264
Mate day 0.02 264.50 5.29 L-02
Skilled (Blacksmith, welder etc.) day 0.02 136.69 2.73 L-13
Mazdoor
For fixing in position day 0.01 151.44 1.51 L-12
Mate day 0.01 223.36 2.23 L-11
Mason day 0.20 136.69 27.34 L-13
Mazdoor 37.31
Add @ 5 per cent of cost of material and labour for 156.71
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
c) Overhead charges @ 0.2 on (a+b) 94.03
d) Contractor's profit @ 0.1 on (a+b+c) 1034.29
Rate per metre (a+b+c+d) say 1034.00
Note
1. In case of viaducts in urban areas, the drainage spouts
should be connected with suitably located pipelines to
discharge the surface run-off to drains provided at ground
level.
14.10 2700 2. In case of bridges, sufficient length of G.I Pipe shall be
provided to ensure that there is no splashing of water from
the drainage spout on the structure.
PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification

Unit = 1 cum
Taking output = 1 cum
Material cum 1.00 4066.00 4066.00 Item 12.8
(A)
Concrete, Rate as per item No. 12.8 (A) excluding say 4066.00
formworks
14.11 1500,16 Rate per cum
00,1700
& 2704
Reinforced cement concrete approach slab including
reinforcement and formwork complete as per drawing and
Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material cum 1.00 3686.00 3686.00 Item 12.8
(G)
Cement concreteM30 Grade Refer relevant item of 73.72
concrete in item 12.8(G)by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 (G) tonne 0.05 50004.00 2500.20 Item 14.2 A
except that form work may be added at the rate of 2
per cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No 1251.98
14.2(Excluding OH & CP)
b) Overhead charges @ 0.2 on (a) 751.19
c) Contractor's profit @ 0.1 on(a+b) 8263.09
Rate per cum (a+b+c) say 8263.00
Note
14.12 1600 The grade of reinforced cement concrete may be adopted as
M30 for severe conditions and M25 for moderate conditions.

Providing anti-corrosive treatment to HYSD reinforcement


with Fusion Bonded Epoxy Coating (FBEC)

Unit = 1 MT
Taking output = 1 MT
Note To be taken as per the prevailing market rates.

Page 25 of 264
14.13 1800 & Contractors generally do not have expertise for this item .
2300 The job is therefore, got done from specialised firms who
have the expertise in the field of construction chemicals. The
prevailing rate in the market is required to be ascertained
from the market and added in the cost estimate. Detailed
guidelines in this regard have been issued by MoRTH vide
their circular no. RW/NH-34041/44/91-S&R dated 21.3.2000.

Precast - pretensioned Girders


Providing, precasting, transportation and placing in position
precast pretensioned concrete girders as per drawing and
technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material tonne 0.47 5000.00 2350.00 M-081
Cement cum 0.45 828.00 372.60 M-004
Coarse sand cum 0.54 1028.00 555.12 M-053
20 mm Aggregate cum 0.36 1005.00 361.80 M-051
10 mm Aggregate Kg 1.88 44.70 84.04 M-180
Admixture @ 0.4 per cent of cement tonne 0.10 45000.00 4500.00 M-082
HYSD steel . tonne 0.06 57453.00 3447.18 M-119
HT strand with 5 per cent as wastage and extra length Litre 37.00 43.00 1591.00 M-122
for anchoring
LDO for steam curing 132.62
Add consumables such as binding wire, foam, packing
tape, shuttering oil, HDPE pipe for unbonding of
strand, bolt & nuts etc @ 1 per cent of material cost

b) Labour
(i) Cutting, bending, making reinforcement cage, placing in
position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete including day 0.06 151.44 9.09 L-12
laps and wastage
Mate day 0.35 164.69 57.64 L-15
Mazdoor (Skilled) day 1.40 136.69 191.37 L-13
Mazdoor
(ii) Cable cutting and threading in position including binding
by insulation tape with HDPE pipes etc., prestessing and
cutting of extra length of HT strand after de-stressing.

Taking quantity of HT strand 60 Kg/cum day 0.02 151.44 3.03 L-12


Mate day 0.14 164.69 23.06 L-15
Mazdoor (Skilled) day 0.50 136.69 68.35 L-13
Mazdoor
(iii) Erection and dismantling of shuttering
Taking shuttering area 10 sqm/cum of concrete day 0.12 151.44 18.17 L-12
Mate day 1.00 164.69 164.69 L-15
Mazdoor (Skilled) day 2.00 136.69 273.38 L-13
Mazdoor
(iv) Concreting by Batching plant and stationary concrete day 0.03 151.44 4.54 L-12
pump
Mate day 0.05 164.69 8.23 L-15
Mazdoor (Skilled) day 0.60 136.69 82.01 L-13
Mazdoor
(v) Steam curing and manual curing day 0.01 151.44 1.51 L-12
Mate day 0.35 136.69 47.84 L-13
Mazdoor
(vi) Handling of precast girder, stacking in stockyard and day 0.01 151.44 1.51 L-12
again loading in trailor
Mate day 0.25 136.69 34.17 L-13
Mazdoor
(vii) Placement of girders in position over pier caps including day 0.01 151.44 1.51 L-12
placement of sand jacks, channel, levelling etc.

Page 26 of 264
Mate day 0.06 164.69 9.88 L-15
Mazdoor (Skilled) day 0.24 136.69 32.81 L-13
Mazdoor
c) Machinery
i) At casting yard hour 0.05 762.75 38.14 P&M-080
Generator 100 KVA hour 0.05 2232.00 111.60 P&M-002
Batching Plant @ 20 cum/hour hour 0.10 1017.00 101.70 P&M-049
Transit Mixer 4 cum capacity hour 0.05 256.00 12.80 P&M-007
Concrete Pump stationary hour 0.10 853.00 85.30 P&M-012
Crane 35 tonne capacity hour 0.10 847.50 84.75 P&M-089
Trailor 30 tonne capacity hour 0.05 806.00 40.30 P&M-017
Loader
ii) For transportation and placement at site hour 0.15 853.00 127.95 P&M-012
Crane 35 tonne capacity tonne.km 2.5xL 0.68 1.70 Lead =1
km & P&M-
090
Trailer 30 tonne capacity for transporting to site.
(L - Lead in Kilometer) hour 0.15 847.50 127.13 P&M-089
Trailor 30 tonne capacity during placement. 745.09
Cost of formwork, steam curing arrangement, 3180.72
pretensioning arrangement etc @ 5 per cent of cost
material, labour and machinery
d) Overhead charges @ 0.2 on (a+b+c) 1908.43
e) Contractor's profit @ 0.1 on (a+b+c+d) 20992.75
Rate per cum = (a+b+c+d+e) say 20993.00
14.14 1700 &
1800
Providing and fixing Helical pipes in voided concrete slabs

Unit = 1 RM
Taking output = 1 RM
a) Material metre 1.00 2426.00 2426.00 M-117
Helical pipes 600mm diameter each 1.00 49.00 49.00 M-183
Tie rods 20mm diameter 123.75
Consumables for sealing joints etc.@ 5 per cent of cost of
material
b) Labour day 0.01 151.44 1.51 L-12
Mate day 0.05 230.00 11.50 L-08
Fitter day 0.20 136.69 27.34 L-13
Mazdoor 527.82
c) Overhead charges @ 0.2 on (a+b) 316.69
d) Contractor's profit @ 0.1 on (a+b+c) 3483.62
Rate per cum (a+b+c+d) say 3484.00
14.15 800
Crash Barriers
14.16 800 The rate analysis for rigid crash barrier in reinforced cement
concrete, semi-rigid crash barrier with metal beam and
flexible crash barrier with wire ropes have been made and
included in chapter-8 on Traffic and Transportation.

Painting on concrete surface


Providing and applying 2 coats of water based cement paint
to unplastered concrete surface after cleaning the surface of
dirt, dust, oil, grease, efflorescence and applying paint @ of
1 litre for 2 sqm.

Unit = sqm
Taking output = 10 sqm
a) Labour day 0.01 151.44 1.51 L-12
Mate day 0.25 223.36 55.84 L-18
Painter day 0.25 164.69 41.17 L-15
Mazdoor (Skilled)
b) Material Litres 5.00 31.00 155.00 M-190

Page 27 of 264
Water based paint of approved quality for cement 50.71
concrete surface
c) Overhead charges @ 0.2 on (a+b) 30.42
d) Contractor's profit @ 0.1 on (a+b+c) 334.66
Cost for 10 sqm (a+b+c+d) 33.47
Rate per sqm (a+b+c+d)/10 say 33.00
14.17 2604
Burried Joint
Providing and laying a burried expansion joint, expansion
gap being 20 mm, covered with 12 mm thick, 200 mm wide
galvanised weldable structural steel plate as per IS: 2062,
placed symmetrical to centre line of the joint, resting freely
over the top surface of the deck concrete, welding of 8 mm
dia. 100 mm long galvanised nails spaced 300 mm c/c along
the centre line of the plate, all as specified in clause 2604.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.02 151.44 3.03 L-12
Mate day 0.40 136.69 54.68 L-13
Mazdoor day 0.20 164.69 32.94 L-15
Mazdoor (Skilled)
b) Material kg 237.50 54.57 12961.33 M-
060/1000
Galvanised M.S plate 200 mm wide,12 mm thick @ 129.61
94.20 kg/sqm including 5 per cent wastage
Add 1 per cent of cost of steel plate cutting, welding 2636.32
consumables and galvanised nails.
c) Overhead charges @ 0.2 on (a+b) 1581.79
d) Contractor's profit @ 0.1 on (a+b+c) 17399.69
Cost for 12 m = (a+b+c+d) 1449.97
Rate per m = (a+b+c+d)/12 say 1450.00
Note
14.18 2605 Guidelines laid down vide the MoRTH circular No. RW/NH-
34059/1/96-S&R dated 30.11.2000 and subsequent
corrigendum dated 25.01.2001 may be reffered for
expansion joints.
(i) Filler joint
Providing & fixing 2 mm thick corrugated copper plate in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc. day 0.04 151.44 6.06 L-12
Mate day 0.50 136.69 68.35 L-13
Mazdoor day 0.50 164.69 82.35 L-15
Mazdoor (Skilled)
b) Material kg 55.00 290.55 15980.25 M-086
Copper plate - 12m long x 250 mm wide
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg. 3227.40
c) Overhead charges @ 0.2 on (a+b) 1936.44
d) Contractor's profit @ 0.1 on (a+b+c) 21300.84
Cost for 12 m = (a+b+c+d) 1775.07
Rate per m = (a+b+c+d)/12 say 1775.00
14.18 (ii)
Providing & fixing 20 mm thick compressible fibre board in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m

Page 28 of 264
a) Labour
For carrying, placing & fixing. day 0.008 151.44 1.21 L-12
Mate day 0.10 136.69 13.67 L-13
Mazdoor day 0.10 164.69 16.47 L-15
Mazdoor (Skilled)
b) Material sqm 3.00 486.00 1458.00 M-084
20 mm thick compressible fibre board 12 m long x 25
cm deep.
Area = 12 x 0.25 = 3 sqm 297.87
c) Overhead charges @ 0.2 on (a+b) 178.72
d) Contractor's profit @ 0.1 on (a+b+c) 1965.94
Cost for 12 m = (a+b+c+d) 163.83
Rate per m = (a+b+c+d)/12 say 164.00
14.18 (iii)
Providing and fixing in position 20 mm thick premoulded joint
filler in expansion joint for fixed ends of simply supported
spans not exceeding 10 m to cater for a horizontal
movement upto 20 mm, covered with sealant complete as
per drawing and technical specifications.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.01 151.44 1.51 L-12
Mate day 0.20 136.69 27.34 L-13
Mazdoor day 0.10 164.69 16.47 L-15
Mazdoor (Skilled)
b) Material sqm 3.60 965.00 3474.00 M-141
Premoulded joint filler 12 m long,20 mm thick and 300 703.86
mm deep.
c) Overhead charges @ 0.2 on (a+b) 422.32
d) Contractor's profit @ 0.1 on (a+b+c) 4645.50
Cost for 12 m = (a+b+c+d) 387.13
Rate per m = (a+b+c+d)/12 say 387.00
14.18 (iv)
Providing and filling joint sealing compound as per drawings
and technical specifications with coarse sand and 6 per cent
bitumen by weight
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a) Labour day 0.02 151.44 3.03 L-12
Mate day 0.50 136.69 68.35 L-13
Mazdoor day 0.10 164.69 16.47 L-15
Mazdoor (Skilled)
b) Material cum 0.012 710.46 8.53 M-005
Sand
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg cum 0.001 55132.00 55.13 M-074
Bitumen
16.8 x 0.06 = 1 kg 30.30
c) Overhead charges @ 0.2 on (a+b) 18.18
d) Contractor's profit @ 0.1 on (a+b+c) 199.98
Cost for 12 m = (a+b+c+d) 16.67
Rate per m = (a+b+c+d)/12 say 17.00
Note
For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,
14.19 2600 the rates at Sl. No. i), ii), iii) & iv) shall be added
Asphaltic Plug joint

Page 29 of 264
Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm to 100 mm, width
varying from 500 mm to 750 mm (in traffic direction),
covered with a closure plate of 200mm x 6mm of weldable
structural steel conforming to IS: 2062, asphaltic plug to
consist of polymer modified bitumen binder, carefully
selected single size aggregate of 12.5 mm nominal size and
a heat resistant foam caulking/backer rod, all as per
approved drawings and specifications.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.052 151.44 7.87 L-12
Mate day 1.00 136.69 136.69 L-13
Mazdoor day 0.30 164.69 49.41 L-15
Mazdoor (Skilled)
b) Material cum 0.75 1028.00 771.00 M-052
Crushed stone aggregate 12.5 mm nominal size kg 77.50 38.74 3002.35 M-078/
1000
2.4 Polymer modified bitumen kg 113.00 61.00 6893.00 M-103
Galvanised structural steel plate 200 mm wide,6 mm 108.60
thick, 12 m long (2.4 sqm) @ 47.10 kg/sqm including 5
per cent wastage
Add 1 per cent for welding and foam caulking/backer
rod and other incidentals.
c) Machinery hour 1.00 62.00 62.00 P&M-030
Mastic cooker 1 tonne capacity hour 0.50 460.00 230.00 P&M-044
Smooth 3-wheeled steel roller 8-10 capacity 2252.19
d) Overhead charges @ 0.2 on (a+b+c) 1351.31
e) Contractor's profit @ 0.1 on (a+b+c+d) 14864.42
Cost for 12 m asphalt plug joint = (a+b+c+d+e) 1238.70
Rate per m = (a+b+c+d+e)/12 say 1239.00
Note
14.20 2606 The nominal size of aggregates shall be 12.5 mm for depth
of joint upto 75 mm and 20 mm for joints of depth more than
75 mm.
Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric slab steel expansion
joint, catering to right or skew (less than 20 deg., moderately
curved with maximum horizontal movement upto 50 mm,
complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or
their authorised representative ensuring compliance to the
manufacturer's instructions for installation and clause 2606
of MoRTH specifications for road & bridge works.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.06 151.44 9.09 L-12
Mate day 1.00 136.69 136.69 L-13
Mazdoor day 0.50 164.69 82.35 L-15
Mazdoor (Skilled)
b) Material metre 12.00 6064.00 72768.00 M-093
Supply of elastomeric slab seal expansion joint 3638.40
assembly manufactured by using chloroprene,
elastomer for elastomeric slab unit conforming to
clause 915.1 of IRC: 83 (part II), complete as per
approved drawings and standard specification
conforming to clause 2606 of MoRT&H Specification
Add 5 per cent of cost of material for anchorage 15326.90
reinforcement, welding and other incidentals.
c) Overhead charges @ 0.2 on (a+b) 9196.14
d) Contractor's profit @ 0.1 on (a+b+c) 101157.57

Page 30 of 264
Cost for 12 m = (a+b+c+d) 8429.80
Rate per m = (a+b+c+d)/12 say 8430.00
14.21 2600
Compression Seal Joint
Providing and laying of compression seal joint consisting of
steel armoured nosing at two edges of the joint gap suitably
anchored to the deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer compressed and
fixed into the joint gap with special adhesive binder to cater
for a horizontal movement upto 40 mm and vertical
movement of 3 mm.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.036 151.44 5.45 L-12
Mate day 0.60 136.69 82.01 L-13
Mazdoor day 0.30 164.69 49.41 L-15
Mazdoor (Skilled)
b) Material kg 446.00 61.00 27206.00 M-103
1. Galvanised angle sections 100mm x 100mm of 1367.14
12mm thickness weldable structural steel as per IS:
2062, 2 nos. of 12 m length each @ 17.7 kg/m and 5
per cent wastage.
Add 5 per cent of cost of above for structural steel for metre 12.00 668.00 8016.00 M-143
anchorage, welding and other incidentals.
Preformed continuous chloroprene elastomer or closed 80.16
cell foam sealing element with high tear strength,
vulcanised in a single operation for the full length of a
joint to ensure water tightness.
Add 1 per cent of cost of sealing element for lubricant- 7361.24
cum-adhesive and other consumables.
c) Overhead charges @ 0.2 on (a+b) 4416.74
d) Contractor's profit @ 0.1 on (a+b+c) 48584.15
Cost for 12 m = (a+b+c+d) 4048.68
Rate per m = (a+b+c+d)/12 say 4049.00
Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
14.22 2607 3. The anchoring bars of the expansion joint assembly shall
be welded to the main reinforcement of the deck.
Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint catering
to maximum horizontal movement upto 70 mm, complete as
per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's
instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.05 151.44 7.57 L-12
Mate day 1.00 136.69 136.69 L-13
Mazdoor day 0.25 164.69 41.17 L-15
Mazdoor (Skilled)
b) Material metre 12.00 7500.00 90000.00 M-178
Supply of complete assembly of strip seal expansion 4509.27
joint comprising of edge beams, anchorage, strip seal
element and complete accessories as per approved
specifications and drawings.
Add 5 per cent of cost of material for anchorage 18938.94
reinforcement, welding and other incidentals.
c) Overhead charges @ 0.2 on (a+b) 11363.36

Page 31 of 264
d) Contractor's profit @ 0.1 on (a+b+c) 124997.01
Cost for 12 m = (a+b+c+d) 10416.42
Rate per m = (a+b+c+d)/12 say 10416.00
Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

14.23 2600 2. The concreting for joining the expansion joint assembly
with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal expansion
joint including anchorage catering to a horizontal movement
beyond 70 mm and upto 140mm, complete as per approved
drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.056 151.44 8.48 L-12
Mate day 1.00 136.69 136.69 L-13
Mazdoor day 0.40 164.69 65.88 L-15
Mazdoor (Skilled)
b) Material metre 12.00 1820.00 21840.00 M-127
Supply of a modular strip/box seal joint assembly 4410.21
comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.
c) Overhead charges @ 0.2 on (a+b) 2646.13
d) Contractor's profit @ 0.1 on (a+b+c) 29107.38
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 2425.62
Rate per m = (a+b+c+d)/12 say 2426.00
Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
14.24 2600 3. The anchoring bars of the expansion joint assembly shall
be welded to the main reinforcement of the deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal expansion
joint catering to a horizontal movement beyond 140mm and
upto 210mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.

Unit = Running meter


Taking output = 12 m
a) Labour day 0.07 151.44 10.60 L-12
Mate day 1.25 136.69 170.86 L-13
Mazdoor day 0.50 164.69 82.35 L-15
Mazdoor (Skilled)
b) Material metre 12.00 1820.00 21840.00 M-128
Supply of a modular box/box seal joint assembly 4420.76
containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system, all
steel sections protected against corrosion and installed
by the manufacturer or his authorised representative.

Page 32 of 264
c) Overhead charges @ 0.2 on (a+b) 2652.46
d) Contractor's profit @ 0.1 on (a+b+c) 29177.03
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 2431.42
Rate per m = (a+b+c+d)/12 say 2431.00
Note
1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.

Page 33 of 264

You might also like