You are on page 1of 4

Quantity Surveying & Cost Estimation CE-372

XEN Shahid Hussain

Question:
Reduced level (R.L) of ground along the centre line of a proposed road from chainage 10 to chainage 20 are given below. The formation level at the 10 th chainage is 107 and the
road is in downward gradient of 1 in 150 upto the chainage 14th and then the gradient changes to 1 in 100 downward. Formation width of road is 10 metre and the side slopes of
banking are 2:1 (Horizontal:Vertical). Length of chain is 30 metre.
a. Draw longitudinal section of the road and a typical cross-section.
b. Prepare an estimate of earthwork and price it as per SI 01/36 of MES SR 2009.
c. Find the area of the side slopes and the cost of laying burnt bricks laid on edge on the slopes as per Sch Item (SI) 12-11 of MES SR 2009.
Chainage: 10 11 12 13 14 15 16 17 18 19 20
R.L of Ground: 105.0 105.6 105.44 105.90 105.42 104.3 105.00 104.10 104.62 104.00 103.30
R.L of Formation : 107.00 at chainage 10th
Gradient : [----Down gradient 1 in 150--------][-------------------Down gradient 1 in 100 ------------]

Calculation of Formation levels when the slope is provided

Station Length Cummulative RL of Formation Slope Difference in elevation due to slope RL of formation
or between Length at start in Slope in SxL = RL of previous point - Diff in Remarks
Chainage stations, L (m) (m) fmn,S % (m) Elevation due to slope
(m) (m)

1 2 3 4 5 6 7 = Col 5 x Col 2 8 9

10 0 107 107 There are 10 sections


in this problem. Sec-1
is between station 10
11 30 30 1 in 150 0.667 (1/150) x 30 = 0.2 107.0 - 0.2 = 106.8 & station 11. Sec -2 is
between station 11 &
12 30 30+30 = 60 1 in 150 0.667 (1/150) x 30 = 0.2 106.8 - 0.2 = 106.6 station 12 and so on.
13 30 60+30 = 90 1 in 150 0.667 (1/150) x 30 = 0.2 106.6 - 0.2 = 106.4 Distance between each
section is 30 m.
14 30 90+30 = 120 1 in 150 0.667 (1/150) x 30 = 0.2 106.4 - 0.2 = 106.2

15 30 120+30= 150 1 in 100 1.000 (1/100) x 30 = 0.3 106.2 - 0.3 = 105.9

16 30 150+30= 180 1 in 100 1.000 (1/100) x 30 = 0.3 105.9 - 0.3 = 105.6

17 30 180+30= 210 1 in 100 1.000 (1/100) x 30 = 0.3 105.6 - 0.3 = 105.3

18 30 210+30= 240 1 in 100 1.000 (1/100) x 30 = 0.3 105.3 - 0.3 = 105.0

19 30 240+30= 270 1 in 100 1.000 (1/100) x 30 = 0.3 105.0 - 0.3 = 104.7

20 30 270+30= 300 1 in 100 1.000 (1/100) x 31 = 0.3 104.7 - 0.3 = 104.4


√((
𝑠𝑑) B
^2
+𝑑
^2 )
TYPICAL CROSS SECTION 1 d d
S

sd B sd sd

Calculation of Cut / Fill Quantities

Length RL RL Height/Depth Mean/ Width of Side Slope Side Total


between Length of of fmn Central Areas (Horz per Area Quantity
of Average Area
Station Stations Fmn Ground Filling Depth at (Rectangular) vert i.e (2 x triangular (Bd + sd2) x Ls
or top 1 in s) areas)
Chainage

Ls L FL NSL (Diff of FL & NSL) d B Bd s sd2 Bd + sd2 Banking Cutting


/Filling
m m m m m2 m2 m2 m3 m3

Col 1 Col 2 Col 3 Col 4 Col 5 Col 6 = Col 4 - Col 7 Col 8 Col 9 = Col 8 x Col 10 Col 11 = Col 10 x Col 12 = Col 13=Col 12 x Col 2
Col 5 Col 7 (Col 7) ^2 Col 9 + Col 11

10 0 107.0 105.0 2.00

11 30 30 106.8 105.6 1.20 (2+1.2)/2= 1.60 10.0 16.0 2 5.12 21.12 633.6 -

12 30 60 106.6 105.4 1.16 (1.2+1.16)/2= 1.18 10.0 11.8 2 2.78 14.58 437.5 -

13 30 90 106.4 105.9 0.50 (1.16+0.5)/2= 0.83 10.0 8.3 2 1.38 9.68 290.3 -

14 30 120 106.2 105.4 0.78 (0.5+0.78)/2= 0.64 10.0 6.4 2 0.82 7.22 216.6 -

15 30 150 105.9 104.3 1.60 (0.78+1.6)/2= 1.19 10.0 11.9 2 2.83 14.73 442.0 -

16 30 180 105.6 105.0 0.60 (1.6+0.6)/2= 1.10 10.0 11.0 2 2.42 13.42 402.6 -

17 30 210 105.3 104.1 1.20 (0.6+1.2)/2= 0.90 10.0 9.0 2 1.62 10.62 318.6 -

18 30 240 105.0 104.6 0.38 (1.2+0.38)/2= 0.79 10.0 7.9 2 1.25 9.15 274.4 -

19 30 270 104.7 104.0 0.70 (0.38+0.7)/2= 0.54 10.0 5.4 2 0.58 5.98 179.5 -

20 30 300 104.4 103.3 1.10 (0.7+1.1)/2= 0.90 10.0 9.0 2 1.62 10.62 318.6 -
Total Volume= 3513.8 cum
108

L-Section of Road Formation


107
Reduced Levels

107 106.8
106.6
106.4
106.2
105.9 105.9 Formation Profile Ground Profile
106
105.6 105.6
105.4 105.4
105.3
105.0 105.0 105
105 104.7
104.6
104.3 104.4
104.1 104.0
104
103.3

103

102

101
10 11 12 13 14 15 16 17 18 19 20
Chainage

Unpriced Bill of Quantities


Road Embankment
Ser No. Particular of Items Unit Quantity Rate Amount
1 Making Embankment, with the specified /approved soil
obtained from borrow excavation within one KM, incl
compaction in 150mm layers upto 90% Modified AASHTO
density, and dressing to required profile and shape as Cum 3513.8
specified.

Priced Bill of Quantities (Based on MES SR 2009)


Road Embankment

Shedule Rate Amount


Ser No. Particular of Items Unit Quantity Item
(Rs.) (Rs.)
(SI)
1 Making Embankment, with the specified /approved soil Cum 3513.8 01-36 284.23 998727.37
obtained from borrow excavation within one KM, incl
compaction in 150mm layers upto 90% Modified AASHTO
density, and dressing to required profile and shape as
specified.

(At Par Cost) Total (Rs.): 998727.37


Calculation of Areas of Side Slopes
side slope,s 2 sqrt (s2+1)= 2.236

Length RL Height/Depth Sloping


between Length of RL of Mean/ breadth
stations Fmn of filling Avg of side
ground Depth Area
Station slope of
or both side slopes
Chainage
Ls L FL NSL (Diff of GL & FL) d d√(s2+1) 2Ls x d√(s2+1)

m m m m m m m m2

1 2 3 4 5 6=4-5 7 8 = 2.236 x 9 = 2 x Col 2 x


Col 7 Col 8

10 - 0 107.0 105.0 2.00 - - -

11 30 30 106.8 105.6 1.20 (2+1.2)/2= 1.60 3.58 214.66

12 30 60 106.6 105.4 1.16 (1.2+1.16)/2= 1.18 2.64 158.31

13 30 90 106.4 105.9 0.50 (1.16+0.5)/2= 0.83 1.86 111.36

14 30 120 106.2 105.4 0.78 (0.5+0.78)/2= 0.64 1.43 85.87

15 30 150 105.9 104.3 1.60 (0.78+1.6)/2= 1.19 2.66 159.66

16 30 180 105.6 105.0 0.60 (1.6+0.6)/2= 1.10 2.46 147.58

17 30 210 105.3 104.1 1.20 (0.6+1.2)/2= 0.90 2.01 120.75

18 30 240 105.0 104.6 0.38 (1.2+0.38)/2= 0.79 1.77 105.99

19 30 270 104.7 104.0 0.70 (0.38+0.7)/2= 0.54 1.21 72.45

20 30 300 104.4 103.3 1.10 (0.7+1.1)/2= 0.90 2.01 120.75

Total Slant Area = 1297.37 m2

Priced Bill of Quantities (Based on MES SR 2009)


Burnt Bricks laid on Edge, laid, jointed and pointed in CM (1:6)

Rate Amount
Ser No. Particular of Items Unit Quantity SI
(Rs.) (Rs.)
1 Providing and Laying burnt bricks laid on edge in side slope, Sqm 1297.37 01-36 523.04 678576.40
laid, jointed and pointed in CM (1:6)

(At Par Cost) Total (Rs.): 678576.40