Question:
Reduced level (R.L) of ground along the centre line of a proposed road from chainage 10 to chainage 20 are given below. The formation level at the 10 th chainage is 107 and the
road is in downward gradient of 1 in 150 upto the chainage 14th and then the gradient changes to 1 in 100 downward. Formation width of road is 10 metre and the side slopes of
banking are 2:1 (Horizontal:Vertical). Length of chain is 30 metre.
a. Draw longitudinal section of the road and a typical cross-section.
b. Prepare an estimate of earthwork and price it as per SI 01/36 of MES SR 2009.
c. Find the area of the side slopes and the cost of laying burnt bricks laid on edge on the slopes as per Sch Item (SI) 12-11 of MES SR 2009.
Chainage: 10 11 12 13 14 15 16 17 18 19 20
R.L of Ground: 105.0 105.6 105.44 105.90 105.42 104.3 105.00 104.10 104.62 104.00 103.30
R.L of Formation : 107.00 at chainage 10th
Gradient : [----Down gradient 1 in 150--------][-------------------Down gradient 1 in 100 ------------]
Station Length Cummulative RL of Formation Slope Difference in elevation due to slope RL of formation
or between Length at start in Slope in SxL = RL of previous point - Diff in Remarks
Chainage stations, L (m) (m) fmn,S % (m) Elevation due to slope
(m) (m)
1 2 3 4 5 6 7 = Col 5 x Col 2 8 9
sd B sd sd
Col 1 Col 2 Col 3 Col 4 Col 5 Col 6 = Col 4 - Col 7 Col 8 Col 9 = Col 8 x Col 10 Col 11 = Col 10 x Col 12 = Col 13=Col 12 x Col 2
Col 5 Col 7 (Col 7) ^2 Col 9 + Col 11
11 30 30 106.8 105.6 1.20 (2+1.2)/2= 1.60 10.0 16.0 2 5.12 21.12 633.6 -
12 30 60 106.6 105.4 1.16 (1.2+1.16)/2= 1.18 10.0 11.8 2 2.78 14.58 437.5 -
13 30 90 106.4 105.9 0.50 (1.16+0.5)/2= 0.83 10.0 8.3 2 1.38 9.68 290.3 -
14 30 120 106.2 105.4 0.78 (0.5+0.78)/2= 0.64 10.0 6.4 2 0.82 7.22 216.6 -
15 30 150 105.9 104.3 1.60 (0.78+1.6)/2= 1.19 10.0 11.9 2 2.83 14.73 442.0 -
16 30 180 105.6 105.0 0.60 (1.6+0.6)/2= 1.10 10.0 11.0 2 2.42 13.42 402.6 -
17 30 210 105.3 104.1 1.20 (0.6+1.2)/2= 0.90 10.0 9.0 2 1.62 10.62 318.6 -
18 30 240 105.0 104.6 0.38 (1.2+0.38)/2= 0.79 10.0 7.9 2 1.25 9.15 274.4 -
19 30 270 104.7 104.0 0.70 (0.38+0.7)/2= 0.54 10.0 5.4 2 0.58 5.98 179.5 -
20 30 300 104.4 103.3 1.10 (0.7+1.1)/2= 0.90 10.0 9.0 2 1.62 10.62 318.6 -
Total Volume= 3513.8 cum
108
107 106.8
106.6
106.4
106.2
105.9 105.9 Formation Profile Ground Profile
106
105.6 105.6
105.4 105.4
105.3
105.0 105.0 105
105 104.7
104.6
104.3 104.4
104.1 104.0
104
103.3
103
102
101
10 11 12 13 14 15 16 17 18 19 20
Chainage
m m m m m m m m2
Rate Amount
Ser No. Particular of Items Unit Quantity SI
(Rs.) (Rs.)
1 Providing and Laying burnt bricks laid on edge in side slope, Sqm 1297.37 01-36 523.04 678576.40
laid, jointed and pointed in CM (1:6)