Professional Documents
Culture Documents
Risk Assessment-1 PDF
Risk Assessment-1 PDF
Site Principal
Business Unit Rock & Alluvium
Address
Angle Lane, Stratford. E15 1AG
Contractor (P/C)
McAleer & Rush Con. No: 13_0375
Revision 33
HSE Assessor Sally Lloyd-Raines Operation CFA PILING Date: 07/11/13 Ref. No:
Issued 04/10/12
Notes: If any of the following situations apply, append the relevant Risk Assessment.
Adjacent to Rail: Yes Contaminated Ground: No
Site Specific Hazards: (additional site specific hazards identified below, if any)
Piling Crew, visitors Equipment that is not required for current piling operations is to be stored
2 Congested Working and other operatives on 2 4 M outside of the piling area. Where spoil is to be loaded away, this is to be 1 4 L
site moved away from the piling rig before loading vehicles.
Foreman who uses mobile phone are only to do so in a place of safety and
when safe to do so. Mobile phones must not be used when engaged in
Use of Mobile phones or other Piling Crew, visitors
activities where distraction could pose a risk, e.g. rig manoeuvring.
3 mobile devices causing a and other operatives on 2 2 M 1 2 L
distraction from site hazards site
When using a Mobile phone, all operatives should move to a place of
safety, such as a designated area.
P/C to scan for, locate, expose, divert, protect as necessary all existing
underground services prior to the start of any piling operations and issue
Piling crew, visitors and
Striking services, electric "Permit to Dig".
other operatives on site
5 cables, gas mains, telecoms, 2 4 H 1 4 L
Nearby residents if gas
water supply, drainage. R&A to notify P/C of any pressure loss / anomalies whilst drilling / injecting
main
piles.
All works to cease if electric cable strike suspected - Rig operator to stay in
cab or Jump well clear,
Site and all walkways to be kept clear and tidy, with particular attention to
Piling Crew, visitors designated pedestrian routes. Materials to be stacked and stored properly.
6 Slips, trips and falls and other operatives on 2 3 L 1 3 L
site P/C to provide background safety lighting in periods of darkness in areas
used by R&A, including walkways and access routes
P/C to provide, install and maintain fencing and/or guard rails to prevent
Piling Crew, visitors
Drowning when working near R&A operatives from falling in to adjacent water. P/C to provide life jackets
7 and other operatives on 2 4 H 1 4 L
deep water and rescue plan.
site
HS&E Standard W04 is to be complied with in full.
All portable electrical equipment to be a maximum voltage of 110volts dc.
Banksmen to ensure that the lift path I route is clear of other site operatives
and overhead services in particular H.V Cables and overhead pipe racks.
Plant Manager to ensure that all rigs receive their 12-monthly thorough
Lifting operations.
examination and that any defects are corrected
Falling plant and materials, Piling Crew, visitors Foreman to ensure rig is inspected after rigging and LOLER register
Collisions with plant, persons and other operatives on 3 4 H completed. 1 4 L
9
and Overhead services site
Failure of lifting appliance R&A foreman is to ensure that all Lifting Accessories have been given an
examination every 6 months and certificates available.
Banksman I Slinger to assess all loads before they are lifted to ensure that
the Safe W orking Load of the lifting equipment is not exceeded at any point
during the lift
Foreman to check all plant, machinery and equipment to ensure that guards
are secured in place to prevent any physical contact with moving parts.
P/C or R&A to design platform, P/C to Install & Maintain Piling Platforms to
Plant operation
Piling Crew, visitors safely support bearing pressure of piling rig in it's Working Mode.
Contact between plant and
11 and other operatives on 4 4 H 1 4 L
persons such as to cause
site The Working Platform Certificate provided by Rock & Alluvium is to be
injury.
signed by the Principal Contractor and/or the Planning Supervisor and
returned prior to Piling Operations commencing; confirming the design is in
order and the platform construction is in accordance with the design.
Movement of Rig or mast while Piling Crew, visitors Before using ladder against rig, obtain clearance from rig driver so he is
14 ladder is propped against it. and other operatives on 2 4 M aware of what is happening. No drilling or extraction work is permitted while 1 4 L
site auger cleaning brushes are being serviced.
When piling operations are in close proximity to the site boundary, the
Principal Contractor is responsible for providing any exclusionIprotection
Piling Crew, visitors
Piling Work - Protection of measures necessary to protect the general public. PIC to provide, erect &
and other operatives on
adjacent premises and maintain polythene sheeting I debris netting to perimeter walls I fencing to
20 site 3 2 H 2 2 L
personnel when working near prevent Mud I Concrete I Slurry splashing members of the public; strictly in
MEMBERS OF
site boundary accordance with FPS I HSE Guidance on PUW ER (Regulations 11 & 12),
PUBLIC
section 4.3 CFA Piling :Exception
HS&E Standard S01 is to be complied with in full.
21 Creation of open bore caused Piling Crew, visitors 2 4 H Where a redundant bore is used to park an auger string that is not being 2 4 L
by use of additional bore to and other operatives on used, any empty bores must be covered whilst on site and backfilled before
park auger string where two site leaving site. The area must be thoroughly checked after the backfilling has
diameters being used been carried out and the area must be left at a similar level to the piling
platform to ensure that the empty bore has been suitably filled and not just
masked by spoil
22 Bursting of concrete hoses and Piling Crew, visitors 2 3 M Hoses to be inspected by pump man daily at start of shift. Damaged 1 3 L
or Hose joints causing damage and other operatives on sections are to be replaced.
and injury during concrete site All concrete hoses fitted to the mast of the piling rig must have whip checks
pumping fitted at all times. Joints to be secured by R Clips or Split Pins.
Rig "drop hoses" to be fitted with sleeved hoses for additional protection.
Newer sections of hoses are to be used adjacent to the rig and pump.
Hose runs to be planned to minimise trafficking over hoses. Hoses to be
buried under road.
23 Clearing concrete pumping Piling Crew, visitors 2 3 M All blowing out operations are to be under direct control of a trained Fore- 1 3 L
lines and auger at the end of a and other operatives on man, Foreman to remain at piling rig during procedure, banksman to control
shift by compressed air. site the compressor.
Rig lines to be blown out away from the perimeter fencing at all times.
Foreman to monitor concrete lines as the concrete moves through the lines,
when the ball passes the back of the piling rig the air flow should be turned
of and surplus air released through the exit valve.
24 Dealing with blockages in the Piling Crew, visitors 3 3 H Where the sponge ball will exit other than down the auger, a ball catcher 2 3 M
concrete pumping lines and other operatives on must be fitted to the free end of the hose run.
site To prevent the hose end "whipping", it must be restrained by fixing a strop
to the pipe and securing it e.g. the excavator lifting point or the rig.
Holding the hose down with an excavator bucket is not effective and should
not be used as the only means of restraint, although it can be used in
addition to the strop.
25 Falling from rig mast Person climbing 2 4 H Rigs are only to be climbed if mast has a fixed ladder. Full body harness 1 4 L
with double lanyard and hook connected to a fall arrestor system must be
used for this operation.
[In case of operative suspended from fall arrestor, Fire Brigade to be called
immediately by dialling 999 and Rescue commenced as detailed in Method
Statement MS-013]
If no ladder fixed (CM-70 and R-312) MEW P to be used. Operator to have
IPAF or CPCS Card and wear short restraint lanyard
26 Fall from tracks. Person climbing onto/ 2 3 M Do not climb tracks unnecessarily. 1 3 L
off tracks When both climbing and descending, use proper step.
27 Steelfixing of rebar cages for Piling Crew, visitors 3 3 H Steel-fixing Area to be demarked off and segregated from trafficked areas. 2 3 L
piling and other operatives on
site Heavy cages to be moved off stands or to piling area by crane or excavator.
Steelfixers
Correct lifting ring or secured helical to be used to hoist the cages into the
vertical position for insertion into the bore.
Only person qualified with an IPAF or CPCS certificate are to use MEW P.
28 Use of Mobile Elevated Work Piling Crew, visitors 3 4 H Full harness with short restrain lanyard to be used and attached to correct 2 4 L
Platform (MEWP), Risk of and other operatives on attachment point.
overturning site Only stand on the platform floor, not on the rails.
MEW P operator Check for presence of ramps, trenches, slopes, manhole covers, ground
obstructions, overhead cables, building projections, vehicles etc.
Before travelling MEW P ensure platform is in recommended travel position.
Only travel with an appointed banks-man and at correct speed
Before raising the platform, check that the machine is level and located on a
firm surface
Do not overload the platform or use it for lifting duties.
HS&E Standard P01 is to be complied with in full.
'LIVE RISKS' TO BE RECORDED B ELOW
High Risk Operation NO Temporary W orks NO The above control measures have been implemented
If Yes - refer to HS&E-STD-T01
Workplace Manager …………………………… Date ……………………
E1 Environmental Noise 2 2 L Piling Rig and ancillary equipment is to be kept in good me-
chanical order. Where damage or wear to silencing system
occurs, maintenance to receive priority.
E2 Ecological damage Damage to protected trees 2 2 L Trees needing protection to be fenced off by P/C with relevant
signeage.
E3 Water Pollution Contamination of watercourse 3 3 M P/C to install protective bunding to prevent water/slurry from
from silt laden groundwater entering watercourse.
generated by piling process
E4 Air pollution from Degeneration of air quality 2 2 L Plant to be kept in good mechanical order, machines to be 1 1 L
exhaust gasses switched off when not in use; avoid long idle times.
E5 Vandalism of hydrocar- Ground and water pollution 3 3 M All lubricants to be locked in container overnight and Weekend. 1 1 L
bons storage Bunded Diesel bowser to be lockable, including lockable hose
storage. To be locked outside site hours and when not in use
E6 Spillage of fuels and oils Ground and water pollution 3 3 M Fuel only to be stored in lockable bunded bowser or 205 litre 2 2 L
during recharging (45 gallon) drums on spillage trays. Refuelling to be via siphon
delivery hose from rig; engine to be switch off during refuelling.
Oil and lubricants to be filled by funnel.
Spill Kit to be available in case of spillage.
E7 Inadequate waste Visual Intrusion of litter 3 1 L R&A foreman to ensure that all general rubbish is placed in the 1 1 L
Management skips provided by P/C.
P/C to set up, Site W aste Management Plan, and brief to R&A
personnel
E8 Washing out ready- Ground and water contamina- 3 3 M If the subsoil is clay (impermeable) or there is an impermeable 2 2 L
mixed concrete and tion. layer of geo-textile beneath the piling platform, the wash-water
clearing out pump and may be discharged directly onto the hardcore platform.
concrete delivery hoses Where the ground is permeable and/or near to a water course,
at end of shift the P/C is to construct a lined pit/skip into which ready-mixed
concrete trucks can wash out.
An area of approximately 5m x 8m to have heavy gauge
visqueen under 300mm of crushed, to be made available for the
pump & agitator set-up.
Amendment Log
Likelihood
How often could the hazard occur? Consider the task, fre-
quency, duration, method of work,
employees involved.
Severity
How serious would the hazard's effects be if
realised? Consider the type of hazard, biological, ergonomic,
physical and chemical.
5.8 Additional Contact(s) Sally Lloyd-Raines, HSE Advisor, 01372 389 333
Assess Release
NO
CLEAN UP PROCEDURE
NO
ISOLATE
ABSORB
Use spill response equipment to absorb spill
Sand I earth may be used, temporarily
DISPOSE
Apply waste management procedures
REORDER
Replenish used spill response equipment
Client specific spill response procedures should be adhered to when working on client site(s) or when
stipulated in the contract.