NOTE: Change is NOT to be shipped for serial production until the supplier has received an APPROVED PSW
NORMA PPAP Requirements ("x" all applicable)
IMDS Control Plan Part Submission Warrant (PSW)
Engineering Change documents MSA Studies PPAP subcomponents
Customer Engineering Approval Dimensional Results & Marked Drawing
Design FMEA Material / Performance Test results
Process Flow Diagram SPC
Process FMEA Sample Parts
Additional or other requirements
Norma Product Engineering to Complete (answer Yes, No, N/A or enter text)
NORMA Approvals (depending on the type of change additional approvals may be needed and will be added to the list)
Date Approval (sign) Comment
Product Development Team leader
NORMA use only
NORMA relevant Quality responsible person or Supplier Quality Engineer to complete (answer Yes, No, N/A or enter text)
SCR is rejected (see below) Is a run at rate capability study required (Yes, No)?
Comments:
1. When submitting this request the Supplier must include a quality confirmation plan and a schedule. Request MUST be submited a minimum of 6 months prior to change.
2. Any parts received before NORMA PPAP approval are judged as non-conforming and will be charged back to the supplier.
Instructions for completing SUPPLIER CHANGE REQUEST (SCR)
Item Explanation
1 Originator/Date Name of the SCR issuer, Date when SCR was submitted to Norma
4 Proposed SP Ship Date Indicate when the proposed change will take effect at Serial production
5 Documentation change needed Indicate which documents are being revised to facilitate the change
6 Current Describe the current process, dimensions or attributes of the product. Include picture or sketch.
7 Proposed Change Describe the change to the process, dimensions or attributes of the product. Include picture or sketch.
8 Potential Risk(s) associated with change Describe potential risk(s) that might be associated with the change
Norma will fill out this section and send back to the supplier indicating PPAP level expected from the supplier
9 NORMA PPAP Requirements
before new parts or process is approved for serial production.
10 Additional or Other Requirements Norma will fill out this section and indicate any additional or other requirements needed
11 Assigned SCR Number Number to be issued by Norma when supplier submits SCR
REQUEST (SCR)
lanation
ted to Norma
t Serial production
ts SCR