This document contains a project schedule with 11 activities labeled A through K. It shows the preceding event, expected duration, total early start and finish times, time slack for each activity. Activity A has no preceding event and starts at time 0, with the subsequent activities following based on their predecessors' finish times and their expected durations, with the critical path having 0 time slack and passing through activities A, B, C, D, F, I, and K.
This document contains a project schedule with 11 activities labeled A through K. It shows the preceding event, expected duration, total early start and finish times, time slack for each activity. Activity A has no preceding event and starts at time 0, with the subsequent activities following based on their predecessors' finish times and their expected durations, with the critical path having 0 time slack and passing through activities A, B, C, D, F, I, and K.
This document contains a project schedule with 11 activities labeled A through K. It shows the preceding event, expected duration, total early start and finish times, time slack for each activity. Activity A has no preceding event and starts at time 0, with the subsequent activities following based on their predecessors' finish times and their expected durations, with the critical path having 0 time slack and passing through activities A, B, C, D, F, I, and K.
A - 2 2 2 0 ٧ B A 3 5 5 0 ٧ C B 4 9 9 0 ٧ D C 5 14 14 0 ٧ E C 4 13 14 1 F D, E 3 17 17 0 ٧ G F 4 21 23 2 H F 6 23 23 0 ٧ I G, H 5 28 28 0 ٧ J G 2 22 28 6 K I, J 4 32 32 0 ٧
Duration (Weeks) Activity Predecessors To TM TP Te A - 5 6 7 6 B - 1 3 5 3 C - 1 4 7 4 D A 1 2 3 2 E B 1 2 9 3 F C 1 5 9 5 G C 2 2 8 3 H E, F 4 4 10 5 I D 2 5 8 5 J H, G 2 2 8 3