S.

no Discration Nos Length With Depath Qty

Brick work 4.5" thick 2 12.00 0.75 8.50 204.00


4 4.00 0.75 8.50 136.00
deduction
Door -3 2.75 5.75 5.75 -47.44

292.56 292.56

PLASTING work 4.5" thick 4 12.00 0.75 8.50 408.00


8 4.00 0.75 8.50 272.00
deduction
Door -3 2.75 5.75 5.75 -47.44
632.56 632.56

Brick work 4.5" thick METRIAL


Brick 5 332.56 1662.8 6 9976.8
sand 0.043 292.56 12.6 65 817.7122
cement 0.01 292.56 2.9 350 1023.969
11818.48 11818.4809375

Plasting work 4.5" thick

sand 0.05 632.56 31.63 85 2688.391


cement 0.01 632.56 6.33 350 2213.969
4902.359 4902.359375

labour
mason 7 800 5600
M.l 7 500 3500
F.l 7 400 2800
sand 1000
brick 1000
13900 13900

wash psaing 850


2500
3350 3350
34895.97

Brick work 9" thick 3 32.00 0.75 9.50 684.00


4 17.00 0.75 9.50 484.50
deduction
Door -6 3.00 0.75 6.00 -81.00
Window -6 2.75 0.75 3.00 -37.13
1050.38 1050.38

Plaster 12mmm thick 6 32.00 0.75 9.50 1824.00


8 17.00 0.75 9.50 1292.00
deduction
Door -6 3.00 0.75 6.00 -108.00
Window -6 2.75 0.75 3.00 -49.50
2958.50 2958.50

Flooring
room1 3 9.91 10 297.3
room2 3 9.91 5.75 170.948
468.248 468.25

Meterial Qty
Brick work 1050.38 0.028 29.4105
PLASting 2958.50 0.092 272.182
Floring 468.25 0.092 43.07877

Brick Work
Brick 550 29.4105 6 97054.65 16175.78
Sand 0.2 29.4105 1350 7940.835 5.8821
Cement 1.92 29.4105 350 19763.86 56.46816
124759.3 124759.341

Labour
mason 7 2 800 11200
F.l 7 1 400 2800
M.l 7 1 500 3500
sand liftin 1500
brick lifting 2500
21500 21500

Plasting
sand 4.6 272.18 1350 1690250 1252.037
cement 1.06 272.182 350 100979.5 288.5129

Labour
mason 12 2 800 19200
F.l 12 1 400 4800
M.l 12 1 500 6000
sand liftin 2000
32000 32000

Flooring
10mm chicps 0.4 187.299 45 8428.455
sand 0.2 93.6495 62 5806.269
cement 1.5 19.6664 350 6883.238
21117.96 21117.96225
Labour
mason 2 2 800 3200
F.l 2 3 400 2400
M.l 2 1 500 1000
sand liftin 1500
10mm metal 1000
9100 9100

kitchen plat foorm 3 4500 13500 13500


Pumbing 12000 12000
Election 10000 10000

Door 6 5000 30000 30000


window 6 3000 18000 18000

toilet door 3 1500 4500 4500


toilet door 3 2500 7500 7500

shetes rakulu 3'X8' 144 800


pipe 32 18 60
2000
shead labour 20000 20000

328454.43

363350.39

no painting
no eletical
no site cleance charge
no shead rakulu metrial
no pipe charges metrial