Professional Documents
Culture Documents
Engineer.Lead
Contract
Interfaces w.r.t. Interferences,
ISO - Specifications, MOM’s Drawings
Description Design - MB’s scope access, head Remarks.
procedures, - Commitments & ER Completeness
- Exclusions. room etc.,
- Code compliance.
Not
1. Thermal process SCS PK Not envisaged Not envisaged Not envisaged Not envisaged
envisaged
Not
2. Pressure Parts SCS PK Completed Completed Completed Completed BY IVY
envisaged
Not
3. Hot structures CHS PK Not envisaged Not envisaged Not envisaged Not envisaged
envisaged
Required Not
12. Turbine SCS PK Completed Not envisaged Not Envisaged
BVK Applicable.
NOTES:
1. Where audit is envisaged, each cell is divided into two rows explaining a) Requirement of audit and b) Person responsible for the activity.