China Petroleum Pipeline Bureau (Sudan)

中国石油天然气管道局(苏丹)

FAT and WPS PLAN

For

PROVISION OF PIPELINE REPAIR PHASE II

CPP

2th Oct. 2016

1/7
China Petroleum Pipeline Bureau (Sudan)
中国石油天然气管道局(苏丹)

CONTENT
1. INTRODUCTION...........................................................................................3

2. Prerequisite of FAT, WPS and WQT...........................................................3

3. Main Workloads...........................................................................................4

4. Witness Plan.................................................................................................5

5. FAT、WPS、WQT Schedule.......................................................................7

2/7
China Petroleum Pipeline Bureau (Sudan)
中国石油天然气管道局(苏丹)

1. INTRODUCTION

According to the requirements of the contract, before the commencement of the site

construction, the PMC and PDOC representative should witness the product

manufacture and the process of WPS. So CPP make this FAT and WPS plan and

schedule to arrange a efficient and reasonable witness.


Based on the agreement between CPP and RAM, the FAT of composite material(3X

Engg.) and the coating material(STOPAQ) will be arranged by RAM ENERGY. The

FAT of mechanical sleeve and witness of WPS, WQT will be executed by CPP in

China. The brief arrangement has been listed as follows.


ATTENTIVE Duration
ACTIVITY LOCATION NOTE
SCHEDULE

WPS China 15th Oct 2 Weeks in China

CPPE, CDT – Together with


WQT
China WPS
Mechanical
China 15th Oct 3-5 days
Sleeve FAT
RAM Energy
Composite will take
Monaco, 3X Eng.. 16th Oct. 10 days
FAT charge of this
job
RAM Energy
Netherland, will take
Coating FAT 20th Oct. 5 days
STOPAQ charge of this
job

2. Prerequisite of FAT, WPS and WQT

1. PMC and PDOC examine and approve the sleeve drawing;

3/7
China Petroleum Pipeline Bureau (Sudan)
中国石油天然气管道局(苏丹)

2. Procurement of mechanical sleeve raw material has been completed after sleeve

drawing has been approve;


3. Procurement of pipeline and fitting used in WPS has been completed. Experiment

platform has been prepared ready.


4. Mechanics Lab is ready and WPS and WQT plan has approved by PMC and

PDOC.
5. Welder is ready.

3. Main Workloads

1. FAT
1) Check the qualification and certificate of the factory;
2) Witness the manufacture procedures of mechanical sleeve including material

preparation, rolling, cutting ,milling, etc.

2. WPS
1) Material procurement;
2) Build experiment platform and establish circulation system;
3) Equipments are ready;
4) Welding sleeves;
5) NDT
6) Preparation of specimens;
7) Mechanical test;
8) Issue WPS and PQR
3. WQT

4/7
China Petroleum Pipeline Bureau (Sudan)
中国石油天然气管道局(苏丹)

1) 8 welders who participate in the WPS experiments will automatically

awarded the qualification.

4. Witness Plan

INDEX ACTIVITY DESCRIPTION DURATION LOCATION REMARK

Check the
qualification and
certificate of the Lang Fang
factory and city
1 FAT witness the 2-3 days He Bei
manufacture Province
procedures of Chin
mechanical
sleeve
8 welders who
National participate in
Witness dynamic
Lab, Lang the WPS
WPS and experiment
2 Fang city, experiments
platform, sleeve 2 days
WQT He Bei will
welding and
Province, automatically
recording data.
Chin awarded the
qualification.
National
Preparation Cut the
Lab, Lang
specimens as the
3 of Fang city,
requirements of 1
He Bei
specimens API1104 Annex
Province,
B
China
4 Mechanical As the 10 days China
requirements of Petroleum
Test
API1104 Annex Pipeline
B Research
Institute,
Lang Fang
5/7
China Petroleum Pipeline Bureau (Sudan)
中国石油天然气管道局(苏丹)

city,
He Bei
Province,
China
China
Petroleum
Pipeline
As the Research
Issue WPS
5 requirements of Institute,,
3 days
and PQR API1104 Annex Lang Fang
B city,
He Bei
Province,
China

6/7
China Petroleum Pipeline Bureau (Sudan)
中国石油天然气管道局(苏丹)

5. FAT、WPS、WQT Schedule

Item Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

Drawing Approval

Raw material procurement


for mechanical sleeve
Raw material procurement
for WPS
Sleeve manufacture

FAT

WPS and WQT experiment

Preparation of specimens

Mechanical test

Issue WPS and PQR

Note:Real arrangement in China may be adjusted by the requirements of PMC and PDOC and with slight difference with the schedule.