You are on page 1of 1

In charge of Status

CIL FAT report of 44+64 towers 2.5.10, 2.2.1 Xen Mazhar - MDCC issued, In the PLI report need to add stubs PLI done earlier for 2.5.10 letter for pli submitted for 2.5.10

FAT report of 18 towers BR line Xen Mazhar - MDCC Issued for total 77 towers of 2.2.1 letter for pli couldn't submit due to nuts bolts issue of 2.2.1

FAT of 400kV stubs Xen Nur Mohammad - MDCC issued for 51 stubs of 2.01 PLI letter submitted

PAT of 4DL Xen Nur Mohammad - Report approved, need to issue letter for mass production Need to issue mass production letter from PGCB
Saidur Rahman
FAT of 400kV towers - 65 towers FAT nomination ongoing along with 45 stubs Need to check the nomintion enothi at dpd kaniz/ashoke
Manager HR
Nuts bolts issue of Barisal 2.2.10 XEN Humayun - 2 towers erection ongoing as reference for nuts bolts final qty. Monir will go to site
Nuts bolts issue of Barapukuria
Xen Mazhar - CIL will change the nuts bolts that have problem After nuts bolts issue solve need to submit pli letter
-Rangpur 2.2.1

ZTT FAT report of ACSR Grosbeak and Finch Xen Nur Mohammad - Report approved for ACSR grosbeak and finch Need to issue mdcc from pgcb

- Gross weight tolerance for grosbeak, finch submitted for approval

Nanjing Terui FAT report of fittings kfw, gtog Xen Mazhar - FAT report approved Need to issue mdcc for fittings on 12.11.2023

Xen Rahman - Need to give all approved drawings for fittings to project office

Jiangshu Tongguang 132kV OPGW and Fittings XEN shoeb - approved for 132kV documnets, 230kV documents submitted Need to collect seal signed documents from PGCB

230kV OPGW and Fittings XEN shoeb - submitted to PGCB

Hengtong FAT report SDE Rokon - Need to check, submission after 21.10.23 FAT report submitted

PLI Barisal 208 drums - solved solved

Sylhet 19 drums - solved solved

Kaliakoir 320 drums XEN Nur Mohammad - pli issue with store ground soling

Tangail drums XEN Nur Mohammad - need to talk with pgcb to fix date for pli

OPGW and Fittings kfw Xen Rahman - letter submitted but pgcb doesn't give any date

Chengdu 400kV fittings SDE Rokon/Nasir - Tension set resubmission, file in TLD Tesnion set comments reply, again comments, letter submitted

230kV fittings SDE Rokon/Nasir - clarification submitted , file in TLD 230kV clarification issue, again comments, letter submitted

- balance drawings of 230kV , 400kV fitttings from chengdu submitted to PGCB for approval

FAT nomination HR - Jiangshi Tower, waiting for GO, need to add quantity of another 12 towers for FAT kfw tower GO done, waiting for consultant visa issue

HR - OPGW and Fittings, nomination and GO done for 2 lines OPGW and Fittings already go to china

HR - Stubs of Phulpur line FAT nomination, pgcb letter no issued yet not done GO

HR - Stubs FAT nomination from Global Steel, need the quantity for FAT letter submitted, MD sir approval pending

Saidur Rahman
GSEL - FAT nomination of 118 stusb waiting for MD approval
Manager HR

You might also like