You are on page 1of 1

JHABUA POWER LIMITED

CPU PM COMPLIANCE SEPT-2020

Doc No. JPL/MTP/PM/07/17


S.NO Date PTW No PTW Issued By Remarks
Area Equipment CPU
Regeneration Building - CAUSTIC TRANSFER CUM
1 CPU 1 2-Sep-20
RECIRCULATION PUMP- "A"
Regeneration Building - CAUSTIC TRANSFER CUM
2 CPU RECIRCULATION PUMP -"B" 1 2-Sep-20

3 CPU Regeneration Building- CAUSTIC PREPARATIN TANK AGITATOR 1 4-Sep-20

4 CPU Regeneration Building- CAUSTIC MEASURING TANK AGITATOR 1 5-Sep-20

5 CPU DM Plant - DM WATER REGENERATION & TRANSFER PUMP - "A" 1 6-Sep-20

6 CPU DM Plant - DM WATER REGENERATION & TRANSFER PUMP - "B" 1 6-Sep-20

7 CPU Regeneration Building - REGENERATION AIR BLOWER- "A" 1 7-Sep-20

8 CPU Regeneration Building - REGENERATION AIR BLOWER- "B" 1 7-Sep-20

9 CPU CPU TG 0 METER - CPU AIR BLOWER- "A" 1 8-Sep-20


10 CPU CPU TG 0 METER - CPU AIR BLOWER- "B" 1 8-Sep-20
11 CPU Regeneration Building - ACID UNLOADING PUMP-"A" 1 9-Sep-20
12 CPU Regeneration Building - ACID UNLOADING PUMP-"B" 1 9-Sep-20
13 CPU Regeneration Building - CAUSTIC UNLOADING PUMP-"A" 1 10-Sep-20
14 CPU Regeneration Building - CAUSTIC UNLOADING PUMP-"B" 1 10-Sep-20
Regeneration Building - DILUTION HOT WATER TANK HEATER 1
15 CPU 1 12-Sep-20
&2
16 CPU Regeneration Building - ALL EXHUST FAN 1 23-Sep-20
17 CPU CPU Bulk hydrochloric acid Tank No.01 1 24-Sep-20
18 CPU Regeneration Building-ACID DOSING PUMP - "A" 1 28-Sep-20
19 CPU Regeneration Building-ACID DOSING PUMP - "B" 1 28-Sep-20
20 CPU Regeneration Building - CAUSTIC DOSING PUMP - "A" 1 30-Sep-20
21 CPU Regeneration Building - CAUSTIC DOSING PUMP - "B" 1 30-Sep-20
Total Submission
Total 21
Balance

PMPL Engineer Verified by JPL