PROGRESS REPORT N° 001

DATE : April 12, 2020

Project Title :
AUXILIARY BOILER UNIT
1) OVERALL PROGRESS SUMMARY

Payment status 15 %
Engineering 90%
Procurement 100%
Fabrication & assembly 100%
Inspection & testing factory 100%
Packing & delivery 100%
Construction work at site 0%
Cold & Hot Commissioning & start- 0%
up

2) FINANCE STATEMENT

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
Payment status 15 %
Caution de restitution advance 100 %
Caution de guarantee 100 %
LC 100 %

II. REASON FOR DELAY PROGRESS – N/A

3) ENGINEERING

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
Fans 100%
Basic Engineering 100%
Steam Drum 100%
Air & Flue Gas Ductwork incl. 100%
Stack
Main Steelwork 100%
Detail Engineering 100%
Firing Systems including Burners 100%
Miscellaneous Systems & 100%
Components
Boiler Pressure Parts 100%
Electrical & C&I 100%
Engineering for Civil Work 0%

II. REASON FOR DELAY PROGRESS – N/A


4) PROCUREMENT

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
Materials Procurement 100%
Materials Delivery 100%

II. REASON FOR DELAY PROGRESS – N/A

5) FABRICATION & ASSEMBLY

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
Main Steelwork 100%
Firing Systems including burners 100%
Air & Flue Gas Ductwork incl. Stack 100%
Miscellaneous Systems & 100%
Components
Pressure Part Manufacturing 100%
Fans 100%
Pressure Parts Material Supply 100%
Electrical & C&I 100%
Steam Drum Material Supply & 100%
Manaufacturing

II. REASON FOR DELAY PROGRESS – N/A

6) INSPECTION & TESTING FACTORY

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
NDT 100%
Pressure Tests 100%

II. REASON FOR DELAY PROGRESS – N/A


7) PACKING & DELIVERY

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
Packing 100%
Shipping preparations 100%
CFR port Oran 100%

II. REASON FOR DELAY PROGRESS – N/A

8) CONSTRUCTION WORK AT SITE

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
Erection of civil works 0%
Pre-Assembly of main Boiler Steel 0%
Structure Erection of main Boiler 0%
steel
Dismantling of the existing PGC 0%
Mounting of the new PGC 0%
Mounting of the Metal Frame 0%
Piping assembly 0%
Mounting of Instruments 0%

II. REASON FOR DELAY PROGRESS – N/A

9) COLD & HOT COMMISSIONING & START-UP

I. ACTIVITIES

CURRENT ACTIVITIES NEXT ACTIVITIES (PLAN)


ACTIVITIES DESCRIPION Previous % Current % Activities description
Cold & Hot Commissioning & start- 0%
up
Start-up 0%

II. REASON FOR DELAY PROGRESS – N/A


Fin
Project leader PMO
Mokhtar OUAMANE
H.Meknassi