Risk ID Priority WBS Responsible Person Risk Description Open Closed Impact Rating Rating Severity Mitigation Mitigation Mitigation Strategy Contingency Status Contract with Wilmont's cannot be Add schedule contingency in plan finalized in time for scheduled start 02-Jul-20 5 2 10 for contract negotiations to be 1 2 1.1.3 Katie O'Ryan of Project complete.
02-Jul-20 4 3 12 Add schedule contingency in plan
Design is not completed in a timely for design to be complete. Add 2 2 1.2.1 Eileen Seymour manner additional staff $4,000
Add schedule contingency in plan
02-Jul-20 4 3 12 Construction of Drones is not for construction to be complete. 3 2 1.3.1 William Holt completed in a timely manner Add additional staff $4,000
02-Jul-20 5 3 15 Add schedule contingency in plan
Delay in DroneTech system > 4 Weeks <1 week for system interface to be 4 1 1.4.1, 1.4.2, 1.4.3 Eileen Seymour interface to Wilmont's system delay delay complete. Add additional staff $8,000
Customer data is not protected 02-Jul-20 2 2 4 Double check system integrity
5 3 1.4.2 Eileen Seymour during regsitration process during customer registration Cost estimate is incorrect. Fund > 4 Weeks <1 week Consider a cost contingency of 02-Jul-20 5 3 15 6 1 1.2.2 Sandeep Vasu issues delay delay 10% over budget $25,000
Double check design. Flight
02-Jul-20 5 1 5 Drones fail to operate during Operations team to be involved 7 2 1.6.1 Gerald Hasper testing in design Alternate delivery methods to be Harsh weather affecting Drone 02-Jul-20 4 4 16 > 2 Weeks <1 week developed and standby in case of 8 1 1.6.4 Gerald Hasper Operations delay delay adverse weather $10,000 Double check packing system. Products delivery problem due to 02-Jul-20 4 2 8 Trial runs at DroneTech facility 9 2 1.3.2, 1.6.4 William Holt improper packing system before handover
All change orders to be
Wilmont's not accepting change 02-Jul-20 2 3 6 documented and approved prior 10 3 1.7.1, 1.7.2 Sandeep Vasu orders/variations to implementation Description Health, Safety Impact Rating Scale Cost Schedule Scope Quality and Environment 5 Very High > $ 100,000 > 4 Weeks delay Drone not operating 4 High < $ 75,000 > 2 Weeks delay Product damage 3 Moderate < $ 50,000 > 1 Week delay Drone performance affected 2 Low < $ 25,000 < 1 Week delay Compensation Required 1 Very Low < $ 10,000 1-2 days delay Corrections required
Likelihood Rating Scale Description
5 Nearly Certain > 80% probability of occuring 4 Likely 50-80% chance of occuring 3 Possible 21-49% chance of occuring 2 Unlikely 1-20% chance of occuring 1 Rare < 1% chance of occuring