Community Health Nursing- Group 3 Activity Plan

Project Title:

“Rehabilitation of Water System”

Description:

The project primarily intend is ensure availability of safe drinking water in every
household in Baranggay Camam-onan. and to eliminate the incidence of water-
borne diseases in the Barangay Camam-onan which was recorded at 30 cases of
skin diseases during the preceding year. The said barangay have their water
connections provided by the Municipality of Gigaquit. It will also augment LGU’s
undertaking in improving the water system of the baranggay, the LGU and DENR
and other partnership organizations will be in charge in ensuring the sound
implementation of the project and a direct partnership with the barangay Council
and its youth will also needed during the construction phase that will contribute
tolabor components of the project construction.

Objectives:

• Ensure availability of safe drinking water in every household in Barangay


Camam-onan.

• Aim to provide the 465 individuals in 96households in the barangay an access of


safe drinking water.

• Promote good health and help prevent from being afflicted by disease caused by
contaminated water.

In general, the project aimed at reducing water-borne diseases of the barangay. It


will promote good health and will ensure the availability of safe drinking water in
every household in the said barangay.

Content:

Activities and its Date

Activities Date People Involve

Conducting community consultation October –November 2020 Barangay


Camam-onan,
and barangay
council
Preparation, submission and approval October –November 2020 Office of the
of the required documents mayor
Project implementation January – April2021

 Conduct a Speakers from:


DOH, DPWH,
symposium LGU
concerning clean
water and
sanitation.
 Give awareness to January 2021
possible infection or
diseases due to water
contamination
 Introduce proper
basic hygiene to
people
 Introduce the project
proposal serve as
community
consultation
Arrival of supplies and materials January 2021 Barangay council
, people’s
organization
(youth,purok,
women)
Construction of the rehabilitation to January- March 2021 Barangay council
the water system , people’s
organization
(youth,purok,
women)
Liquidation of expenses March 2021 Barangay
Treasurer
Turn-over of project management March 2021 LGU, Barang gay
Council,DENR
Project monitoring March 2021 onwards Barangay council
and LGU
Project Management

Once the project is completed it will be turn over to the said Barangay and officials shall
be the over-all in-charge to its operation and maintenance, also collection of fees shall be
imposed ate the rate of 20.00 per household to cover the operation expense

Key outcomes by the end of the year 2020- 2021

By the end of 2021 the rehabilitation of water system is successfully implemented


achieving its goal on sustaining clean water and sanitation.

Learning Objectives:

• Educate people through symposium about water scarce resource and give
awareness about the relationship between water, proper sanitation, and to our
health also its corresponding prevention to the possible risk due to water
contamination.

Evaluation:
This project will not only help the community from their problem about clean
water but also it will prevent them from any infections and communicative
diseases. On evaluating this project survey will be conducted by DENR and LGU
expertise to ensure functionality and its safety use.

Budget Proposal:

PROJECT DETAILS

Project Name/Title

“Rehabilitation of Water System”

Project description

The project primarily intends is ensure availability of safe drinking water in


every household in Baranggay Camam-onan.and to eliminate the incidence of
water-borne diseases in the Barangay Camam-onan which was recorded at 30
cases of skin diseases during the preceding year. The said barangay have their
water connections provided by the Municipality of Gigaquit. It will also augment
LGU’s undertaking in improving the water system of the baranggay, the LGU and
DENR and other partnership organizations will be in charge in ensuring the sound
implementation of the project and a direct partnership with the barangay Council
and its youth will also needed during the construction phase that will contribute
tolabor components of the project construction.

Project Implementation:

January – April2021

Source of Fund

Source of Fund Amount Total


LGU or the Local Government 100, 000.00
Unit
Taganito Mining Company 150,000.00 310,000.00

Solicitation 50,000.00
Beneficiaries 10,000.00
(in-kind)

Expenses:

Conducting community consultation 3000.00

Preparation, submission and approval 5,000.00


of the required documents
Conduct a symposium concerning clean 5,000.00
water and sanitation.
Purchase of of supplies and materials 120,000.00
Construction of the rehabilitation
to the water system and its labor 160,000.00
Turn-over of project management 3,000.00
Project monitoring 5,000.00
Other Expenses 9,000.00

TOTAL Project Cost 310,000.00


Community Health Nursing- Group 3 Activity Plan

Project title: Free Check-up and Consultation

Description:

The Free Check-up are set up with a sacred aim to bring awareness amongst the deprived
population of the Barangay Bonifacio, Surigao City who have no access to basic healthcare
services or knowledge about the diseases they are suffering from. In this barangay there are some
residents lost their lives and have a serious diseases because they don’t have proper check-up and
consultation to a Physician.  So, Free Check-up provides free medical advice, medicine to the
unfortunate people and refers for specialized treatment. They need to attend these to get free
check-up and treatment.

Objectives:

The objective of conducting the health is to create awareness of general health is to create
awareness of general health among the people, provide general health care services and
counselling them on basic healthcare and hygiene.

To build a replicable model of healthcare in the Barangay Bonifacio, Surigao City,


ensuring all people in the target area has access to quality affordable healthcare.

Target group:
• Senior Group
• Children
• Women
• Those with health complications
• Local residents

Duration:
• 1 week every month

Pre-activity:
• Conduct an orientation about awareness to the people to have free check-up.
Partner Institutions:
• Local Government Unit
• Taganito Mining Company
• Department of Health

Content:

Activities and its Date

Activities Date People Involve

Preparation, submission and approval June- July 2020 DOH Caraga,


of the required documents Office of City
Mayor,Office of
Brgy officials
Solicitation to Taganito Mining August 2020 CHN group,
Corporation and other agencies DOH Caraga
Arrival of Supplies and Materials September 2020 Brgy officials,
DOH Caraga,
CHN group
Project implementation October 2020- September CHN group,
2021 DOH Caraga,
(once a month) Brgy Health
Center
 Conduct a symposium Speakers from:
DOH Caraga
concerning to
communicable
diseases and common
illness in the
community
 Give awareness to
possible infection or
diseases due to lack of
proper consultation
and check-up from a
Physician
 Introduce how to
avoid those diseases
and proper hygiene.
 Proper consultation
and check-up from a
Physician
 Distributing medicines
and vitamins

Turn-over of project management to October 2021 Brgy. Officials,


Brgy. Health Center and officials DOH Caraga,
CHN group
Project monitoring November 2021 onwards Brgy. Health
Center, CHN
group

Project Management

Once the project is completed and the cases of diseases on this barangay will be lessen
this group will only give some supply to the barangay health center, and the continue
monitoring in every households in span of 5 months.

Key outcomes by the end of the year 2020- 2021

By the end of 2021 every households in this barangay has knowledge on their local
diseases and have idea how to avoid those diseases.

Learning Objectives:

We are conducted by health professionals to carry out a limited health intervention


amongst the underprivileged community. The poor attend these to get free check-up and
treatment. Getting the appropriate kind of health checkup is vital for every human being and
while considering it, some important factors like age, lifestyle, family background, and risks are
taken into account.

Health examinations and tests at the early stages of the illness can help to cure it faster
and save a life before it can cause any damage. One can live longer and healthier only when the
individual gets the right kind of health check-up, screening, and treatments. Even the most basic
checkups can identify underlying illnesses.

Teaching-Learning Strategy:

Powerpoint Presentation and Video Presentation

Evaluation:

This project will not only help the community from their problem about their
diseases and illness but they will also learn how to avoid those diseases and be
healthy. On evaluating this project survey will be conducted by DOH and
Barangay Health Center expertise to ensure how and what are the other needs of
the community.

Budget Proposal:

PROJECT DETAILS

Project Name/Title

“Free Check-up and Consultation”

Project description

The Free Check-up are set up with a sacred aim to bring awareness amongst the deprived
population of the Barangay Bonifacio, Surigao City who have no access to basic healthcare
services or knowledge about the diseases they are suffering from. In this barangay there are some
residents lost their lives and have a serious diseases because they don’t have proper check-up and
consultation to a Physician.  So, Free Check-up provides free medical advice, medicine to the
unfortunate people and refers for specialized treatment. They need to attend these to get free
check-up and treatment.

Project Implementation:

October 2020 – September 2021

Source of Fund

Source of Fund Amount Total


DOH Caraga 30,000.00

Taganito Mining Company 70,000.00 120,000.00


Solicitation to other agencies 50,000.00

Expenses:

Preparation, submission and approval 5,000.00


for the required documents

Speaker for the symposium 5,000.00

Purchase of Medical Materials 50,000.00

Medicine and Vitamins 50,000.00

Transportation and Gasoline 5,000.00

Snacks and Foods 10,000.00

Turn-over of project management 5,000.00

Twice a Year project monitoring 15,000.00

Other Expenses 5,000.00

TOTAL Project Cost 150,000.00