You are on page 1of 3

Doc.

No:RAISCO-WI-010-01
Rawae Al Amal Industrial Services Revision: 0
Date: 02-Apr-2020

Work Instruction

Title: Work Instruction

Dco.No.: RAISCO-WI-010-01

List of Revision

Issue Rev. Date Amended Pages Nature of Revision

1 0 02-04-2020 NIL For Implementation

QA/QC Manager
Prepared by
Designation Signature Date

Business Development Manager


Reviewed by
Designation Signature Date

RAISCO-WI-010-01 Rev.0 Page 1


Doc.No:RAISCO-WI-010-01
Rawae Al Amal Industrial Services Revision: 0
Date: 02-Apr-2020

Work Instruction
1.0 Purpose
The instruction explains the method of identification and traceability of the materials and
products.

2.0 Scope of Application


The scope of the procedure applicable for all pressure part materials at workshop.

3.0 Responsibility
Stores head along with storekeeper / material controller is responsible for identification and
traceability of the materials and products at works.

4.0 Instruction

On acceptance, raw materials are stored in the areas demarcated as below

 Materials under Inspection


 Rejected Materials
 Accepted Materials
 Customer Supplied Materials (CSM)

Identification of the product is traced through MRIR number written either on the material or on
the tag attached it.

On receipt of Plates, Pipes & Fittings etc., if the material found acceptable, job Number or P.O.
Number or Client name shall be punched / written on the material and during cutting the above
Job Number or P.O. Number or Client name shall be transferred to balance material for easy
traceability.

All rejected materials are identified through “REJECTED” stickers pasted on the material.

All materials under hold shall be pasted with “HOLD” stickers on the materials.

All repair welds during Radiography are shall be pasted with “REPAIR” stickers on the joint.

Stamp transfer shall be carried out on all pressure part materials > 6mm thickness before
processing / cutting.

RAISCO-WI-010-01 Rev.0 Page 2


Doc.No:RAISCO-WI-010-01
Rawae Al Amal Industrial Services Revision: 0
Date: 02-Apr-2020

Work Instruction
Stamp transfer shall be done as per the following details

 Job No. / Part No.


 Grade of the Material
 Plate No. / Heat No.

Material below 6m thickness shall be identified by engraving or by painting.

QC Inspector shall verify the stamp transfer is done correctly and put his stamp or sign near the
marked information. The same method shall be followed for job transfer.

5. Records

 Inspection and Test Plan


 MRIR
 Inspection Reports

6. Retention Period

2 Years.