Professional Documents
Culture Documents
Systems
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 2
Cable Derating Analysis
• Determines the proper size of cables to carry
the specified loads for new systems.
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 3
Cable Derating Analysis
•NEC Accepted -
Neher-McGrath Method
•IEC 287 Method
Steady-state temperature calculation
Cable sizing
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 4
Cable Ampacity
Fundamentals
Cable Ampacity is the current a conductor can carry
continuously under the conditions of use without
exceeding its temperature rating.
Watts = I2R
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 5
Cable Ampacity
Fundamentals
Various thermal barriers:
1. Conductor insulation
2. Air inside a duct
3. Duct wall
4. Soil surrounding an underground duct
5. Additional thermal insulation applied such as
polyurethane
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 6
Cable Ampacity
Fundamentals
Heat Transfer Equation
The rate of heat transfer is directly dependent on the difference
in temperature between the conductor (Tc) and the ambient
temperature (Ta)
Tc Ta (I 2 R).RHO
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 7
Heat Flow Model
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 8
Heat Flow Model
(Generalized)
RHO of Soil = 90
Ta = 20 oC
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 9
Heat Transfer Problem
Ultimate Unchanged Surrounding Environment
Adjustment Factor
Heat Flow
Immediate Surrounding Environment
(Actual Installation Conditions)
I' F x I
I’ = Allowable cable ampacity for the actual installation conditions
F = Cable Ampacity Adjustment Factor
I = Base Ampacity specified by cable manufacturer or NEC under an
isolated condition with a soil thermal resistively (RHO) of 90 and a
specified ambient temperature
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 11
Adjustment Factor
Composition
F Ft x F x Fg
th
Ft = Adjustment factor to account for the
differences in the ambient and
conductor temperatures from the
base case
Fth = Adjustment factor to account for the
difference in the soil thermal
resistivity from RHO of 90
Fg = Adjustment factor to account for
cable grouping
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 12
Duct Bank Example
I = 375 Amps 350 MCM
I = 450 Amps 500 MCM
Ft = 0.82 Ta from 20 C to 30 C
Tc from 90 C to 75 C
Fth = 0.9 RHO of 90 to 120
Fg = 0.479 350 MCM Cable
Fg = 0.478 500 MCM Cable
350 MCM
F = 0.82 x 0.90 x 0.479 = 0.354
500 MCM
F = 0.82 x 0.90 x 0.478 = 0.354
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 13
Neher-McGrath Equation
Tc (Ta ΔTd)
I = Ampacity (kA) I
Tc = Conductor temperature (Deg C) Rdc (1 Tc) Rca'
Ta = Ambient Temperature (Deg C)
Δ Td = Conductor temperature rise due to dielectric loss (Deg C)
Rdc = Conductor dc resistance (μΩ/ft)
Tc = Loss increment due to conductor skin & proximity effects
Rca’ = Thermal resistance between conductor & ambience (Ω-ft)
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 14
Neher-McGrath Example
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 15
Neher-McGrath Example
( n a) Rca Ri Rsd RE
Rsd
Ds b
Rca 17.071
Rsd 9.457 Rdc75 194
Emissivity ( 234.5 90)
E 0.95 Emissivity Rdc90 Rdc75
( 234.5 75)
Ds2 1.315 Conduit OD
Emissivity Rdc90 203.402
9.5 ( n)
RE ( 90 40)
[ 1 1.7 Ds2 ( E 0.41) ] I
RE 7.054 ( 203.5 Rca)
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 16
Cable Sizing
Determines the minimum size for each cable that will carry the
specified load current without violating the cable temperature
limit.
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 17
Cable Sizing Example
1. Load WKSHOP-EX4
2. Run Load Flow
3. Update Cable Load Amp
(Study Case)
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 18
Cable Sizing Based Voltage Drop
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 19
Cable Sizing Based on Ampacity
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 20
New UGS Presentations
• Project Editor – Presentation – Underground
Raceways - Right-Click – Create New
Double-click
to change
presentation
properties
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 21
UGS Presentation
• UGS presentation is
conceptually a cross-section
of cable raceways.
• Each UGS presentation is a
different cross-section of the
underground system.
• If you delete a raceway from a UGS presentation
into the Dumpster, the raceway can be added to
other UGS presentations as an existing raceway.
• In UGS, each presentation acts independently from
each other.
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 22
UGS Edit Toolbar
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 23
UGS Components
Heat Source
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 24
Inserting Cables
• Three main methods for adding cables to the existing
conduits:
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 25
Cable Representation
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 26
UGS Example
Duct Bank
X and Y = 30
Width = 15 Height = 8
Conduit
Conduit Size = 4
Y = 3.35
Pump Cable
From OLV
New Cable
5 kV Kerite 1/C
Operating Load = 200 Amps
Run Steady-State Temp Calc
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 27
UGS Large Example
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 28
Steady-State Calculation
Calculation Pre-Requisite: All cables have been carrying the specified load
long enough that the heat flow has reached its steady-state and no more
changes of temperature will occur throughout the raceway system.
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 29
Alarms and Warnings
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 30
Multiple Presentations
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 31
Uniform Ampacity -
Ampacity Calculation
Approach is based on the equal loading criterion for ampacity calculations.
Calculations determine the maximum allowable load currents when all the cables in
the system are equally loaded to the same percentage of their base loading.
Calculation Procedure
1. Determine initial loading level based on base ampacity.
2 Calculate cable temperature as in steady-state temperature calculation.
3. Check cable temperature values against the cable temperature limit.
If the temperature of the hottest cable is within close range of the temperature limit, the solution has been
reached. If not, adjust the cable loading uniformly at the same percentage, either increasing or decreasing
the loading in order to make the highest cable temperature come closer to the temperature limit. Then go
to back to step 2 to recalculate cable temperature.
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 32
Uniform Temperature -
Ampacity Calculation
Approach is based on the equal temperature criterion for ampacity calculations.
Determines the maximum allowable load currents when all the cables in the system have their
temperature within a small range of the temperature limit.
In the case where these conductors are not located in the same conduit/location, they may not have the
same temperature. When this situation occurs, the temperature of the hottest conductor in this cable
branch will be used to represent this cable branch.
Calculation Procedure
1. Determine an initial loading level based on the base ampacity from the Cable Library and using cable
derating factors for the given configuration.
2. Calculate cable temperature as in the steady-state temperature calculation.
3. Check cable temperature values against the cable temperature limit.
If temperature values of all cables are within close range of temperature limit, the solution has been
reached. If not, load change required for the cable temperature to approach the temperature limit based
on the gradient of cable temperature change is determined.
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 33
Cable Sizing Calculation
• The Cable Sizing Calculation determines the minimum size of each
cable that will carry the specified load current without violating the cable
temperature limit.
Calculates and then plots cable temperature variations as a function of time in accordance to load changes.
(Table of Ampacity versus Time)
The transient temperature calculations are based upon a dynamic thermal model of the raceway system,
constructed mainly from thermal resistance, thermal capacitance, and heat sources.
Thermal resistance is used to represent different thermal layers from cable conductor to ambient soil.
Thermal capacitance is used to represent the capability of each layer to absorb heat.
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 35
Example From NEC
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 36
NEC Duct Bank (Detail 2)
Depth= 30 in
Fill RHO = 60
1kV NEC Rubber2
1/C CU 3-phase
Magnetic
Class = 100%
Size = 350 AWG
Load = 284.5 Amps
per phase
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 37
NEC Duct Bank (Detail 3)
Depth = 30 in
Fill RHO = 60
1kVNEC Rubber2
1/C CU 3-phase
Magnetic
Class = 100%
Size = 750 AWG
Load = 334.9Amps
per phase
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 38
(Detail 2) in ETAP
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 39
Results for Detail 2
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 40
NEC (Detail 3) in ETAP
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 41
Results for Detail 3
© 1996-2009 Operation Technology, Inc. - Workshop Notes: Underground Raceway Systems Slide 42