Professional Documents
Culture Documents
Item Description
A. General Requirements:
B. Earthworks:
B.1 Excavation
Volume (Column-Footing) = ( 1.2m x 1.2m x 1.1m ) * 15
Volume (Wall Footing) = (60.32 - 15*0.3 ) * ( 0.55* 0.4 )
Volume (Septic Tank) = ( 3.7 * 1.5 * 1.3 )
*Materials:
Gravel Bedding
Filling Materials
*Labor:
1.00 Construction Foreman
5.00 Laborers
Site Clearing & Cleaning
*Equipment:
1.00 Plate Compactor
C. Concrete Works:
C.1 Footing
Volume = ( 0.3 * 1.2* 1.2 ) * 15
C.2 Column
Volume = ( 0.3 * 0.3 * 3.8 ) * 15
C.4 Slab
Volume = ( 126 * 0.1 )
*Materials:
Premium Cement (Using 40kg of Cement, Class A Mixture)
Washed Sand
Crushed Gravel
*Labor:
1.00 Construction Foreman
1.00 Mason
2.00 Laborer
D. Masonry Works:
Area (Net) of Wall = ( 257.4 - 34.53)
*Materials:
10 x 20 x 40 (cm) CHB
Premium Cement
Washed Sand
10mmØ x 6m DSB
#16 G.i Tie Wire
*Labor:
1.00 Construction Foreman
1.00 Mason
2.00 Laborers
*Equipment:
1.00 Dumptruck
*Materials:
Assorted CWN
1/2"x4'x8' Marine Plywood ( Cabinet )
1/4" x 4' x 8' Marine Plywood
2" x 2" x 12' Good Lumber
*Labor
1.00 Construction Foreman
1.00 Carpenter
2.00 Laborers
F. Steel Works:
*Materials:
Footing:
12mmØ x 6m DSB
#16 G.i Tie Wire
Column:
12mmØ x 6m DSB
10mmØ x 6m DSB
#16 G.i Tie Wire
Wallfooting:
#16 G.i Tie Wire
10mmØ x 6m DSB
Slab:
10mmØ x 6m DSB
#16 G.i Tie Wire
*Labor:
1.00 Construction Foreman
1.00 Steelman
2.00 Laborers
*Equipment
1.00 Bar Cutter
1.00 Bar Bender
G. Roofing Works:
Area
*Materials:
Trusses
welding rod
2.5mmx6mmx50mm Angle bar
2.4mmx5mmx40mm Angle bar
2"x3" C-Purlins
Roofing
Corrugated G.I Sheet 32" x 12"
Corrugated G.I Sheet 32" x 9'
G.I rivets
G.I washers
Plain G.I sheets
Lead washers
*Labor:
1.00 Construction Foreman
3.00 Laborers
*Equipment:
1.00 Welding Machine
H. Tile Works:
*Materials:
20cm x 20cm Glazed Wall Tiles
40cm x 40cm Glazed Wall Tiles
20cm x 20cm Unglazed Floor Tiles
40 kg - Ordinary Cement Mortar
White Cement
*Labor:
1.00 Construction Foreman
1.00 Mason
2.00 Laborer
I. Painting Works:
Area = 113.14+140
*Materials:
Acrylic Latex Paint
Skin Coating
Surface Primer
Neutralizer
Primer and Enamel Paint
Paint Thinner
Sand Paper #120
Paint Roller #9
Paint Brush #4
Paint Brush #3
*Labor:
1.00 Construction Foreman
2.00 Painters
1.00 Laborers
J. Electrical Works:
Material10
*Labor:
Septic Tank
Volume (Concrete) = 3.7*1.5*1.3
A = 3.7*1.3
*Materials:
Kitchen Sink ( medium )
Lavatory
Faucet
Shower
Floor Drain ( #4 )
water closet
#4 Elbow PVC 90 degrees
water supply PVC pipe 4" φ
soil PVC pipe 4" φ
coupling ( #4 )
4" φ TEE pipe
clean out
*Labor:
1.00 Construction Foreman
1.00 Plumber
1.00 Mason
1.00 Laborers
*Equipment:
-
*Materials:
1/4'' x 4' x 8' Ord. Plywood
2" x 2'' x 12' Coco Lumber
2'' x 3'' x 12' Coco Lumber
Asstd CWN
*Labor:
1.00 Construction Foreman
2.00 Carpenters
4.00 Laborers
*Labor:
1.00 Construction foreman
2.00 Carpenters
4.00 Laborers
*Equipment:
-
SUMMARY
A. General Requirements:
B. Earthworks:
C. Concrete Works:
D. Masonry Works:
E. Ceiling & Carpentry Works:
F. Steel Works:
G. Roofing Works:
H. Tile Works:
I. Painting Works:
J. Electrical Works:
K. Plumbing Works:
L. Formworks & Scaffoldings:
M. Doors & Windows:
TOTAL DIRECT COST
lippines
S ORIENTAL
o City
ny, Inc.
COST ESTIMATE
OREY COMMERCIAL BUILDING
n, Cagayan de Oro city
117.32 cu.m
25.95 cu.m
12.28
7.22
45.45 cu.m
18.39 cu.m
51.32 cu.m
2.16 cu.m
25.73 cu.m
6.48 cu.m
5.13 cu.m
1.52 cu.m
12.60 cu.m
222.87 sq.m
222.87 sq.m
126.00 sq.m
126.00 sq.m
105.40 sq.m
158.16 sq.m
120.00 sq.m
6.00 sq.m
32.16 sq.m
253.14 sq.m
253.14 sq.m
- - -
Php 16,521.00
7.22 cu.m
4.81 sq.m
- - - -
Php -
- - - -
Php
8,000.00
38,355.40
156,647.75
217,987.75
135,503.20
75,348.65
74,595.40
88,000.75
21,016.00
20,929.65
46,001.00
36,351.25
154,232.25
TOTAL DIRECT COST 1,072,969.05
PERT - CPM DIAGRAM LEGEND:
Program Evaluation and Review Technique
Critical Path Method
0 4
START EARTHWORKS
0 0
0 35
GENERAL REQUIREMENTS
0 0
ES D EF ES = Early Start D = Duration Time
Activity EF = Early Finish S = Slack Time
LS S LF LS = Late Start
LF = Late Finish Unit = Days
4 4 3 7 7 3 10
ARTHWORKS FORMWORKS STEEL WORKS
4 4 0 7 7 0 10
35
AL REQUIREMENTS
35
10 5 15 15 5 20
CONCRETE WORKS MASONRY WORKS
10 0 15 15 0 20
15 4 19
ROOFING WORKS
23 8 27
20 4 24
PLUMBING WORKS
27 7 31
20 3 23 23 3 26
ELECTRICAL WORKS DOORS & WINDOWS
20 0 23 23 0 26
19 4 23
CEILING & CARPENTRY WORKS
27 8 31
26 5 31 31 4 35
TILE WORKS PAINTING WORKS END
26 0 31 31 0 35
ITEM # DESCRIPTION / ACTIVITIES QTY UNIT COST
I. General Requirements 1.00 lot 8,000.00
II. Earthworks 117.32 cu.m. 38,355.40
III. Concrete Works 25.73 cu.m. 156,647.75
IV. Masonry Works 222.87 sq.m. 217,987.75
V. Ceiling & Carpentry Works 126.00 sq.m. 135,503.20
VI. Steel Works 48.00 kgs 75,348.65
VII. Roofing Works 105.40 sq.m. 74,595.40
VIII. Tile Works 158.16 sq.m. 88,000.75
IX. Painting Works 253.14 sq.m. 21,016.00
X. Electrical Works 1.00 lot 20,929.65
XI. Plumbing Works 1.00 lot 46,001.00
XII. Formworks & Scaffoldings 1802.00 bd.ft. 36,351.25
XIII. Doors & Windows 59.00 sets 154,232.25
TOTAL COST: 1,072,969.05
PHYSICAL ACCOMPLISHMENT
CASH FLOW
W
RELATIVE WEIGHT(%) DURATIONS (DAYS) 1 2
0.75% 35 0.0002 0.0002
3.57% 4 0.0089 0.0089
14.60% 5
20.32% 5
12.63% 4
7.02% 3
6.95% 4
8.20% 5
1.96% 4
1.95% 3
4.29% 4
3.39% 3
14.37% 3
100%
MANPOWER W
Construction Foreman
Masons
Carpenters
Steelmen
Painters
Electrical
Plumbers
Laborers
EQUIPMENT
Plate Compactor
Dumptruck
Bar Cutter
Bar Bender
Welding Machine
Week 1
3 4 5 6 7 8 9
0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002
0.0089 0.0089
0.0234 0.0234
Week 1
Week 2
10 11 12 13 14 15
0.0002 0.0002 0.0002 0.0002 0.0002 0.0002
0.0234
Week 2
Week 3
16 17 18 19 20 21
0.0002 0.0002 0.0002 0.0002 0.0002 0.0002
0.0065
0.0107
Week 3
Week 4
22 23 24 25 26 27
0.0002 0.0002 0.0002 0.0002 0.0002 0.0002
0.0316 0.0316
0.0164
0.0065 0.0065
0.0107 0.0107 0.0107
Week 4
Week 5
28 29 30 31 32 33
0.0002 0.0002 0.0002 0.0002 0.0002 0.0002
Week 5
Week 1
34 35 1 2 3
0.0002 0.0002 0.01 228.57 228.57 228.57
0.04 9588.85 9588.85 9588.85
0.15
0.20
0.13
0.07
0.07
0.08
0.0049 0.0049 0.02
0.02
0.04
0.03
0.14
1.00
0.0051 0.0051
0.99 1.00
5482.57 5482.57
1,067,486.48 1,072,969.05
Week 1 Week 2
4 5 6 7 8 9 10 11
228.57 228.57 228.57 228.57 228.57 228.57 228.57 228.57
9588.85
31329.55
43597.55
33875.80 33875.80 33875.80 33875.80
17600.15
PHYSICAL ACCOMPLISHMENT
CASH FLOW
W
RELATIVE WEIGHT(%) DURATIONS (DAYS) 1 2
0.75% 35 0.0002 0.0002
3.57% 4 0.0089 0.0089
14.60% 5
20.32% 5
12.63% 4
7.02% 3
6.95% 4
8.20% 5
1.96% 4
1.95% 3
4.29% 4
3.39% 3
14.37% 3
100%
0.0234 0.0234
0.0234
0.0065
0.0107
0.0316 0.0316
0.0164
0.0065 0.0065
0.0107 0.0107 0.0107
0.0051 0.0051
0.99 1.00
5482.57 5482.57
1,067,486.48 1,072,969.05