ID Task Name Duration Start Finish Predecessors Resource 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter

Duration Start Finish Predecessors Resource 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Names Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
1 132 KV switchyard and associated works in M/s. CSOT,Thirupati. 249.5 days Wed 2/5/20 Fri 10/30/20
2 Purchase order stage 122.5 days Wed 2/5/20 Mon 6/15/20
3 Release of LOA 1 day Wed 2/5/20 Wed 2/5/20 CSOT CSOT
4 Submission of Bank guarantee 3 days Thu 2/6/20 Sun 2/9/20 3 SVEPL SVEPL
5 Payment of advance 7 days Sun 2/9/20 Sun 2/16/20 4 CSOT CSOT
6 Lock down period 13 days Mon 5/18/20 Sun 5/31/20 5
7 Quarantine Period for Shri vaari electricals workers 14 days Mon 6/1/20 Mon 6/15/20 6
8 CEIG drawing approval 30 days Tue 6/16/20 Fri 7/17/20
9 Preparation of drawings 15 days Tue 6/16/20 Wed 7/1/20 7 SVEPL SVEPL
10 Getting drawing approval 15 days Thu 7/2/20 Fri 7/17/20 9 CEIG CEIG
11 Ordering work 15 days Thu 2/6/20 Fri 2/21/20
12 Vendor finalisation 10 days Thu 2/6/20 Sun 2/16/20 3 SVEPL SVEPL
13 Release of PO for suppliers 5 days Mon 2/17/20 Fri 2/21/20 12 SVEPL SVEPL
14 Civil works 236.5 days Mon 2/17/20 Wed 10/28/20
15 Drawing stage 15 days Mon 2/17/20 Tue 3/3/20
16 Preparation of drawings 7 days Mon 2/17/20 Mon 2/24/20 5 SVEPL SVEPL
17 Submission of drawings for getting approval for construction 1 day Mon 2/24/20 Tue 2/25/20 16 SVEPL SVEPL
18 Approval of drawings by customer 7 days Tue 2/25/20 Tue 3/3/20 17 CSOT CSOT
19 Foundation works for All equipment except Transformer 60 days Tue 6/16/20 Wed 8/19/20
20 Setting out -Survey 2 days Tue 6/16/20 Wed 6/17/20 7,18 SVEPL SVEPL
21 Marking of foundations 2 days Thu 6/18/20 Fri 6/19/20 20 SVEPL SVEPL
22 Excavation 7 days Sat 6/20/20 Sat 6/27/20 21 SVEPL SVEPL
23 Sand filling &PCC 5 days Sat 6/27/20 Thu 7/2/20 22 SVEPL SVEPL
24 Shuttering 5 days Fri 7/3/20 Wed 7/8/20 23 SVEPL SVEPL
25 Reinforcement 5 days Wed 7/8/20 Mon 7/13/20 24 SVEPL SVEPL
26 First lift concreting 6 days Tue 7/14/20 Mon 7/20/20 25 SVEPL SVEPL
27 Shuttering 3 days Mon 7/20/20 Thu 7/23/20 26 SVEPL SVEPL
28 Reinforcement 5 days Thu 7/23/20 Tue 7/28/20 27 SVEPL SVEPL
29 Second lift concreting with fixing foundation bo 5 days Wed 7/29/20 Mon 8/3/20 28 SVEPL SVEPL
30 Curing 5 days Mon 8/3/20 Sat 8/8/20 29 SVEPL SVEPL
31 Back filling, levelling and compaction 5 days Sat 8/8/20 Thu 8/13/20 30 SVEPL SVEPL
32 Whitewashing 5 days Fri 8/14/20 Wed 8/19/20 31 SVEPL SVEPL
33 Foundation works for Transformer 56 days Tue 6/16/20 Fri 8/14/20
34 Setting out -Survey 2 days Tue 6/16/20 Wed 6/17/20 7,18 SVEPL SVEPL
35 Marking of foundations 2 days Thu 6/18/20 Fri 6/19/20 34 SVEPL SVEPL
36 Excavation 3 days Sat 6/20/20 Tue 6/23/20 35 SVEPL SVEPL
37 Sand filling &PCC 5 days Tue 6/23/20 Sun 6/28/20 36 SVEPL SVEPL
38 Reinforcement 3 days Mon 6/29/20 Wed 7/1/20 37 SVEPL SVEPL
39 Shuttering 3 days Thu 7/2/20 Sun 7/5/20 38 SVEPL SVEPL
40 Raft 3 days Sun 7/5/20 Wed 7/8/20 39 SVEPL SVEPL
41 First lift concreting 4 days Wed 7/8/20 Sun 7/12/20 40 SVEPL SVEPL
42 Shuttering 2 days Mon 7/13/20 Tue 7/14/20 41 SVEPL SVEPL
43 Second lift concreting with base plates 4 days Wed 7/15/20 Sun 7/19/20 42 SVEPL SVEPL
44 Curing 5 days Sun 7/19/20 Fri 7/24/20 43 SVEPL SVEPL
45 Excavation for retainer wall 2 days Fri 7/24/20 Sun 7/26/20 44 SVEPL SVEPL
46 Sand filling 2 days Mon 7/27/20 Tue 7/28/20 45 SVEPL SVEPL
47 PCC & flooring n construction of drain chamber 5 days Wed 7/29/20 Mon 8/3/20 46 SVEPL SVEPL
48 Construction of retainer wall 3 days Mon 8/3/20 Thu 8/6/20 47 SVEPL SVEPL
49 Back filling, levelling and compaction 3 days Thu 8/6/20 Sun 8/9/20 48 SVEPL SVEPL
50 Plastering 4 days Mon 8/10/20 Thu 8/13/20 49 SVEPL SVEPL
51 White washing 1 day Fri 8/14/20 Fri 8/14/20 50 SVEPL SVEPL
52 Construction of Control Room 93 days Tue 6/16/20 Wed 9/23/20
53 Excavation for columns 3 days Tue 6/16/20 Thu 6/18/20 7,18 SVEPL SVEPL
54 sand filing 2 days Fri 6/19/20 Sun 6/21/20 53 SVEPL SVEPL
55 PCC 2 days Sun 6/21/20 Tue 6/23/20 54 SVEPL SVEPL
56 Shuttering 3 days Tue 6/23/20 Fri 6/26/20 55 SVEPL SVEPL
57 Reinforcement 3 days Fri 6/26/20 Mon 6/29/20 56 SVEPL SVEPL
58 Mat concreting 3 days Tue 6/30/20 Thu 7/2/20 57 SVEPL SVEPL
59 Shuttering 3 days Fri 7/3/20 Mon 7/6/20 58 SVEPL SVEPL
60 Raising of columns upto plinth beam level 5 days Mon 7/6/20 Sat 7/11/20 59 SVEPL SVEPL
61 Reinforcement for plinth beam 2 days Sat 7/11/20 Mon 7/13/20 60 SVEPL SVEPL
62 Shuttering 4 days Tue 7/14/20 Fri 7/17/20 61 SVEPL SVEPL
63 Concreting 4 days Sat 7/18/20 Wed 7/22/20 62 SVEPL SVEPL
64 Raising of columns upto intermediate level 4 days Wed 7/22/20 Sun 7/26/20 63 SVEPL SVEPL
65 Reinforcement 4 days Mon 7/27/20 Thu 7/30/20 64 SVEPL SVEPL
66 shuttering 4 days Fri 7/31/20 Tue 8/4/20 65 SVEPL SVEPL
67 Laping of reinforcement 4 days Tue 8/4/20 Sat 8/8/20 66 SVEPL SVEPL
68 Concreting up the beam level and roofing 15 days Sat 8/8/20 Mon 8/24/20 67 SVEPL SVEPL
69 Brick work construction 15 days Tue 8/25/20 Wed 9/9/20 68 SVEPL SVEPL
70 Plastering 8 days Thu 9/10/20 Fri 9/18/20 69 SVEPL SVEPL
71 Whitewashing 5 days Fri 9/18/20 Wed 9/23/20 70 SVEPL SVEPL
72 Cable Trench 37 days Fri 8/14/20 Tue 9/22/20
73 Excavation 2 days Fri 8/14/20 Sun 8/16/20 50 SVEPL SVEPL
74 Sand filling 3 days Sun 8/16/20 Wed 8/19/20 73 SVEPL SVEPL
75 PCC 5 days Wed 8/19/20 Mon 8/24/20 74 SVEPL SVEPL
76 Shuttering 5 days Tue 8/25/20 Sun 8/30/20 75 SVEPL SVEPL
77 Reinforcement 2 days Sun 8/30/20 Tue 9/1/20 76 SVEPL SVEPL
78 Raft concreting 4 days Tue 9/1/20 Sat 9/5/20 77 SVEPL SVEPL
79 Shuttering 2 days Sat 9/5/20 Mon 9/7/20 78 SVEPL SVEPL
80 Side wall concreting 7 days Tue 9/8/20 Tue 9/15/20 79 SVEPL SVEPL
81 Curing 7 days Tue 9/15/20 Tue 9/22/20 80 SVEPL SVEPL
82 Fire barrier wall 41 days Fri 8/14/20 Sun 9/27/20
83 Excavation for columns 1 day Fri 8/14/20 Fri 8/14/20 50 SVEPL SVEPL
84 Sand filling 2 days Sat 8/15/20 Mon 8/17/20 83 SVEPL SVEPL
85 PCC 2 days Mon 8/17/20 Wed 8/19/20 84 SVEPL SVEPL
86 Shuttering 2 days Wed 8/19/20 Fri 8/21/20 85 SVEPL SVEPL
87 Reinforcement 2 days Fri 8/21/20 Sun 8/23/20 86 SVEPL SVEPL
88 Mat concreting 2 days Mon 8/24/20 Tue 8/25/20 87 SVEPL SVEPL
89 Shuttering 2 days Wed 8/26/20 Thu 8/27/20 88 SVEPL SVEPL
90 Raising of columns upto plinth beam level 2 days Fri 8/28/20 Sun 8/30/20 89 SVEPL SVEPL
91 Reinforcement for plinth beam 2 days Sun 8/30/20 Tue 9/1/20 90 SVEPL SVEPL
92 Shuttering 2 days Tue 9/1/20 Thu 9/3/20 91 SVEPL SVEPL
93 Concreting 2 days Thu 9/3/20 Sat 9/5/20 92 SVEPL SVEPL
94 Raising of columns up to intermediate level 2 days Sat 9/5/20 Mon 9/7/20 93 SVEPL SVEPL

Project: project schedule - R3 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: Wed 5/13/20

This schedule depends on the following. 1. Lock down lifted on 31.05.20. 2. Quarantine period upto 15.06.20. 3. Advance payment by CSOT before 18.05.20 Page 1
ID Task Name Duration Start Finish Predecessors Resource 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Names Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
95 Reinforcement 2 days Tue 9/8/20 Wed 9/9/20 94 SVEPL SVEPL
96 Shuttering 2 days Thu 9/10/20 Fri 9/11/20 95 SVEPL SVEPL
97 Lapping of reinforcement 2 days Sat 9/12/20 Mon 9/14/20 96 SVEPL SVEPL
98 Concreting up tie beam level 2 days Mon 9/14/20 Wed 9/16/20 97 SVEPL SVEPL
99 Curing 2 days Wed 9/16/20 Fri 9/18/20 98 SVEPL SVEPL
100 Brick work construction 2 days Fri 9/18/20 Sun 9/20/20 99 SVEPL SVEPL
101 Plastering 2 days Mon 9/21/20 Tue 9/22/20 100 SVEPL SVEPL
102 Curing 2 days Wed 9/23/20 Thu 9/24/20 101 SVEPL SVEPL
103 Whitewashing 2 days Fri 9/25/20 Sun 9/27/20 102 SVEPL SVEPL
104 Yard levelling works 8 days Fri 10/9/20 Sat 10/17/20
105 Filling of selected earth 2 days Fri 10/9/20 Sun 10/11/20 147 SVEPL SVEPL
106 Consolidation 3 days Sun 10/11/20 Wed 10/14/20 105 SVEPL SVEPL
107 Ramming 3 days Wed 10/14/20 Sat 10/17/20 106 SVEPL SVEPL
108 Fencing retainer wall 70 days Fri 8/14/20 Wed 10/28/20 49
109 Excavation 2 days Fri 8/14/20 Sun 8/16/20 50 SVEPL SVEPL
110 PCC 2 days Sun 8/16/20 Tue 8/18/20 109 SVEPL SVEPL
111 Brick work construction 2 days Tue 8/18/20 Thu 8/20/20 110 SVEPL SVEPL
112 Fixing of fencing posts 2 days Thu 8/20/20 Sat 8/22/20 111 SVEPL SVEPL
113 Plastering 2 days Sat 8/22/20 Mon 8/24/20 112 SVEPL SVEPL
114 Fixing of panels 2 days Tue 8/25/20 Wed 8/26/20 113 SVEPL SVEPL
115 Plastering 2 days Thu 8/27/20 Fri 8/28/20 114 SVEPL SVEPL
116 Whitewashing 2 days Sat 8/29/20 Mon 8/31/20 115 SVEPL SVEPL
117 Filling of blue metal 5 days Fri 10/23/20 Wed 10/28/20 116,155,156,157,158,159,160
SVEPL SVEPL
118 Foundation for yard flood light 7 days Fri 8/14/20 Fri 8/21/20 49
119 Excavation 1 day Fri 8/14/20 Fri 8/14/20 50 SVEPL SVEPL
120 PCC 1 day Sat 8/15/20 Sun 8/16/20 119 SVEPL SVEPL
121 Reinforcement 1 day Sun 8/16/20 Mon 8/17/20 120 SVEPL SVEPL
122 Shuttering 1 day Mon 8/17/20 Tue 8/18/20 121 SVEPL SVEPL
123 Concreting with foundation bolts 1 day Tue 8/18/20 Wed 8/19/20 122 SVEPL SVEPL
124 Curing 1 day Wed 8/19/20 Thu 8/20/20 123 SVEPL SVEPL
125 Whitewashing 1 day Thu 8/20/20 Fri 8/21/20 124 SVEPL SVEPL
126 Delivery of equipment 113 days Tue 6/16/20 Thu 10/15/20
127 Lattice type structurals 55 days Tue 6/16/20 Thu 8/13/20 7 SVEPL SVEPL
128 CT and PT 85 days Tue 6/16/20 Tue 9/15/20 7 SVEPL SVEPL
129 SF6 breaker 72 days Tue 6/16/20 Tue 9/1/20 7 SVEPL SVEPL
130 Lightning arrestor 72 days Tue 6/16/20 Tue 9/1/20 7 SVEPL SVEPL
131 35MVA,132/33KV Power transformer 113 days Tue 6/16/20 Thu 10/15/20 7 SVEPL SVEPL
132 Isolator 74 days Tue 6/16/20 Thu 9/3/20 7 SVEPL SVEPL
133 Psot Insulators 74 days Tue 6/16/20 Thu 9/3/20 7 SVEPL SVEPL
134 33 KV panels( Customer supply) 68 days Tue 6/16/20 Thu 8/27/20 7 SVEPL SVEPL
135 LT panels 68 days Tue 6/16/20 Thu 8/27/20 7 SVEPL SVEPL
136 C&R panels 72 days Tue 6/16/20 Tue 9/1/20 7 SVEPL SVEPL
137 Control cables & accessories 60 days Tue 6/16/20 Wed 8/19/20 7 SVEPL SVEPL
138 Cable tray and accessories 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
139 Earth flats and accessories 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
140 N2 system 73 days Tue 6/16/20 Wed 9/2/20 7 SVEPL SVEPL
141 Battery and Battery chargers 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
142 Safety items 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
143 other Sundry Items 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
144 Earthing works 22 days Tue 9/15/20 Thu 10/8/20
145 Excavation for earth mat 2 days Tue 9/15/20 Thu 9/17/20 80 SVEPL SVEPL
146 Earth flat laying 10 days Thu 9/17/20 Mon 9/28/20 145 SVEPL SVEPL
147 Earth mat termination 10 days Mon 9/28/20 Thu 10/8/20 146 SVEPL SVEPL
148 Tray works 17 days Tue 9/15/20 Sat 10/3/20
149 Tray support fabrication 10 days Tue 9/15/20 Fri 9/25/20 138,80 SVEPL SVEPL
150 Tray erection 7 days Sat 9/26/20 Sat 10/3/20 149 SVEPL SVEPL
151 Cabling 13 days Sat 10/3/20 Sat 10/17/20
152 Cable laying 7 days Sat 10/3/20 Sun 10/11/20 150 SVEPL SVEPL
153 Termination 6 days Sun 10/11/20 Sat 10/17/20 152 SVEPL SVEPL
154 Erection of equipment 75 days Mon 8/3/20 Thu 10/22/20
155 Lattice type structurals 7 days Fri 8/14/20 Fri 8/21/20 127 SVEPL SVEPL
156 CT and PT 4 days Tue 9/15/20 Sat 9/19/20 128 SVEPL SVEPL
157 SF6 breaker 3 days Tue 9/1/20 Fri 9/4/20 129 SVEPL SVEPL
158 Lightning arrestor 3 days Tue 9/1/20 Fri 9/4/20 130 SVEPL SVEPL
159 35MVA,132/33KV Power transformer 7 days Thu 10/15/20 Thu 10/22/20 131 SVEPL SVEPL
160 Isolator 5 days Thu 9/3/20 Tue 9/8/20 132 SVEPL SVEPL
161 Psot Insulators 3 days Thu 9/3/20 Sun 9/6/20 133 SVEPL SVEPL
162 LT panels 5 days Fri 8/28/20 Wed 9/2/20 135 SVEPL SVEPL
163 C&R panels 7 days Tue 9/1/20 Tue 9/8/20 136 SVEPL SVEPL
164 Control cables & accessories 10 days Wed 8/19/20 Sun 8/30/20 137 SVEPL SVEPL
165 Cable tray and accessories 7 days Mon 8/3/20 Mon 8/10/20 138 SVEPL SVEPL
166 Earth flats and accessories 10 days Mon 8/3/20 Thu 8/13/20 139 SVEPL SVEPL
167 N2 system 10 days Wed 9/2/20 Sun 9/13/20 140 SVEPL SVEPL
168 Battery and Battery chargers 4 days Mon 8/3/20 Fri 8/7/20 141 SVEPL SVEPL
169 Safety items 5 days Mon 8/3/20 Sat 8/8/20 142 SVEPL SVEPL
170 other Sundry Items 7 days Mon 8/3/20 Mon 8/10/20 143 SVEPL SVEPL
171 CEIG 7 days Fri 10/23/20 Fri 10/30/20
172 Arranging for inspection 1 day Fri 10/23/20 Fri 10/23/20 10,145,148,106,116,152,70,155,156,157,158,159,160,161,162,163,164,165,166,167,168,169,170,71,103,107,125
SVEPL SVEPL
173 Receipt of safety certificate 5 days Sat 10/24/20 Thu 10/29/20 172 SVEPL SVEPL
174 Precomissioning and testing 1 day Thu 10/29/20 Fri 10/30/20 173 SVEPL 10/30

Project: project schedule - R3 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: Wed 5/13/20

This schedule depends on the following. 1. Lock down lifted on 31.05.20. 2. Quarantine period upto 15.06.20. 3. Advance payment by CSOT before 18.05.20 Page 2

You might also like