Date: 21-07-2020

To: DJV
From: CJV
Re: PUHOI VIADUCT-INSTRUMENTATION MONITORING DATA #7

-------------------------------------------------------------------------------------------------------------------------

PUHOI VIADUCT MONITORING REPORT-07

1. PURPOSE

Monitoring survey pins were installed, and monitoring work carried out as per the IFC
drawing P2Wk-DRG-SE-18-0016-Rev.01.

2. REFERENCES

• Specification No. 650-SPEC-003-NX2-Rev2A


• Drawing No. P2Wk-DRG-SE-18-0016 Rev.01
• Drawing No. P2Wk-DRG-SE-18-0015 Rev.01

3. SUMMARY OF RESULTS

PUHOI VIADUCT – MONITORING RESULTS


Number Structure Element Vertical Action Level Differential Design Differential
Settlement (mm) (mm) Settlement Settlement-ULS
(mm) (mm)
1 North Abutment 0.5 15 0.5 10
2 Pier B 1 15 0.5 10
3 Pier C 2 15 1 10
4 Pier D 1 15 3 10
5 Pier E 0 15 1 10
6 Pier F 1 15 1 10
7 South Abutment 0.5 15 0.5 10
*note: Latest survey date is 13-07-2020

4. CONCLUSIONS

Measured total settlement of the survey pins are lower than the expected.

No significant impacts are expected from the measurements observed so far.

Document No: PUHOI VIADUCT SP -6 Date:21 July 2020 Page 1


ANNEX 1 – SETTLEMENT MONITORING PIN DETAILS
PUHOI VIADUCT
TOTAL STETTLEMENT PRIOR TO TOTAL SETTLEMENT FOLLOWING THE
DIFFERENTIAL SETTLEMENT (REFER NOTE11) DURING THE BRIDGES CONSTRUCTION PERIOD
SURVEY ID CONSTRUCTION ABUTMENT BEAM PLACEMENT OF BRIDGE BEAM
NUMBER TYPE POSITION (STRUCTURE_TYPE_POSITION_ INSTALLATION PHASE BACKGROUND
NUMBER) ALERT LEVEL ALARM LEVEL ACTION LEVEL ALERT LEVEL ALARM LEVEL ACTION LEVEL ALERT LEVEL ALARM LEVEL ACTION LEVEL ACTIVE CONST. CRITICAL CONST.
STATUS IF COMMENTS CONST. (Refer note
(mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (Refer note 6) (Refer note 7)
5)
01 SE_18_SMP_NA_01
SE_18_SMP_NA_02 During the surcharge period settlement shall
02
be monitored, with the designer to review the
03 SE_18_SMP_NA_03
Settlement results to confirm when adequate
04 North SE_18_SMP_NA_04 FOLLOWING STRIPPING AND PRIOR TO
Monitoring Plate consolidation settlement has been reached ---------- ---------- MONTHLY* WEEKLY TWICE WEEKLY
05 Abutment SE_18_SMP_NA_05 FILLING AT THE NORTH ABUTMENT
(SMP) (releasing hold on pilling works at the north
06 SE_18_SMP_NA_06 abutment). Estimated to settle 300mm during
07 SE_18_SMP_NA_07 4 to 6 months.
08 SE_18_SMP_NA_08

SE_18_SPSS_NA_01 INMEDIATELY FOLLOWING THE CASTING


09 North
OF THE ABUTMENT BEAM, PRIOR TO
Abutment PLACEMENT OF ANY BRIDGE BEAM
10 SE_18_SPSS_NA_02
11 SE_18_SPSS_PIER_01
Pier B
12 SE_18_SPSS_PIER_02
13 SE_18_SPSS_PIER_03
Pier C
14 SE_18_SPSS_PIER_04
Survey Pin INMEDIATELY FOLLOWING THE CASTING
15 SE_18_SPSS_PIER_05
Superstructure Pier D OF THE COLUMN, PRIOR TO PLACEMENT N/A 5 10 15 Refer to general Note 01 on DRG-SE-18-0002 MONTHLY WEEKLY TWICE WEEKLY
16 SE_18_SPSS_PIER_06 OF ANY BRIDGE BEAM
(SPSS)
17 SE_18_SPSS_PIER_07
Pier E
18 SE_18_SPSS_PIER_08
19 SE_18_SPSS_PIER_09
Pier F
20 SE_18_SPSS_PIER_10
SE_18_SPSS_SA_01 INMEDIATELY FOLLOWING THE CASTING
21 South
OF THE ABUTMENT BEAM, PRIOR TO
Abutment
SE_18_SPSS_SA_02 PPLACEMENT OF ANY BRIDGE BEAM
22
SE_18_SP_SA_01 During the MSE wall construction period,
23 Survey Pin MSE INMEDIATELY FOLLOWING COMPLETION
settlement shall be monitored, with the
Wall (SPMW) SE_18_SP_SA_02 OF FILLING TO FINISHED SURFACE LEVEL
24 designer to review the results to confirm when
South
adquate consolidation settlement has been ---------- ---------- MONTHLY** WEEKLY TWICE WEEKLY
Abutment SE_18_PR_SA_01 INMEDIATELY FOLLOWING COMPLETION
25 reached. Estimated to settle 200mm during 1-
Profilometer (PR) OF FILL TO 1.5 M ABOVE THE RAFT MSE
SE_18_PR_SA_02 WALL CONSTRUCTION 3 montho upon completion of MSE wall
26 construction.

* Weekly when monitoring settlement during the surcharge period


** Weekly, until the designer has confirmed that adequate consolidation settlement has occured

1
1 18
11 14
3
ANNEX 2 – SETTLEMENT MONITORING GRAPH
PUHOI TO WAKWORTH MOTORWAY PUHOI TO WAKWORTH MOTORWAY
STRUCTURES MONITORING REPORT STRUCTURES MONITORING REPORT
STRUCTURE PUHOI VIADUCT STRUCTURE PUHOI VIADUCT
ELEMENT NORTH ABUTMENT ELEMENT NORTH ABUTMENT
DATE 20/07/2020 DATE 20/07/2020

Monitoring Points

θ
SET 9
SET
10

Displacement Graph ( D z) Differential Graph ( D z)


SE_18_SPSS_NA_01
PUHOI VIADUCT- NORTH ABUTMENT PUHOI VIADUCT- NORTH ABUTMENT
Vertical Settlement (Dz) SE_18_SPSS_NA_02
Differential Settlement (Δz) With PIER B
0.020 0.020 SE_18_SPSS_NA
Reference

0.015 ALERT SE_18_SPSS_PIER B


0.015

ALARM Reference
0.010 0.010
ACTION

0.005 0.005
Displacemt (m)

Differential settlement(m)
0.000 0.000

-0.005 -0.005

-0.010 -0.010

-0.015 -0.015

-0.020 -0.020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020

12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020
DATES DATES
PUHOI TO WAKWORTH MOTORWAY PUHOI TO WAKWORTH MOTORWAY
STRUCTURES MONITORING REPORT STRUCTURES MONITORING REPORT
STRUCTURE PUHOI VIADUCT STRUCTURE PUHOI VIADUCT
ELEMENT PIER B ELEMENT PIER B
DATE 20/07/2020 DATE 20/07/2020

Monitoring Points

SET 11
SET 12

Displacement Graph ( D z) Differential Graph ( D z)


SE_18_SPSS_PIER_01
PUHOI-PIER B PUHOI-PIER B
Vertical Settlement (Dz) SE_18_SPSS_PIER_02
Differential Settlement (Δz) With NORTH ABT
0.020 0.020
Reference
SE_18_SPSS_PIER_B
0.015 ALERT
0.015
SE_18_SPSS_N ABT
ALARM
0.010 0.010
ACTION Reference

0.005 0.005
Displacemt (m)

Differential settlement (m)


0.000 0.000

-0.005 -0.005

-0.010 -0.010

-0.015 -0.015

-0.020 -0.020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020

12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020
DATES DATES
PUHOI TO WAKWORTH MOTORWAY PUHOI TO WAKWORTH MOTORWAY
STRUCTURES MONITORING REPORT STRUCTURES MONITORING REPORT
STRUCTURE PUHOI VIADUCT STRUCTURE PUHOI VIADUCT
ELEMENT PIER C ELEMENT PIER C
DATE 20/07/2020 DATE 20/07/2020

Monitoring Points

SET 13

θ
SET 14

Displacement Graph ( D z) Differential Graph ( D z)

PUHOI-PIER C SE_18_SPSS_PIER_03 PUHOI-PIER C


SE_18_SPSS_PIER_04
Vertical Settlement (Dz) Differential Settlement (Δz) With PIER B SE_18_SPSS_PIER_C
0.020 Reference
0.020
ALERT
ALARM
SE_18_SPSS_PIER_B
0.015 ACTION
0.015
Reference
0.010 0.010

0.005 0.005
Displacemt (m)

Differential settlement (m)


0.000 0.000

-0.005 -0.005

-0.010 -0.010

-0.015 -0.015

-0.020 -0.020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020

12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020
DATES DATES
PUHOI TO WAKWORTH MOTORWAY PUHOI TO WAKWORTH MOTORWAY
STRUCTURES MONITORING REPORT STRUCTURES MONITORING REPORT
STRUCTURE PUHOI VIADUCT STRUCTURE PUHOI VIADUCT
ELEMENT PIER D ELEMENT PIER D
DATE 20/07/2020 DATE 20/07/2020

Monitoring Points

SET 15
SET 16

Displacement Graph ( D z) Differential Graph ( D z)


SE_18_SPSS_PIER_05
PUHOI-PIER D PUHOI-PIER D
Vertical Settlement (Dz) SE_18_SPSS_PIER_06
Differential Settlement (Δz) With PIER C
0.020 0.020
Reference
SE_18_SPSS_PIER_D
ALERT SE_18_SPSS_PIER_C
0.015 0.015
ALARM Reference

0.010 Log. (SE_18_SPSS_PIER_D)


ACTION 0.010
Log. (SE_18_SPSS_PIER_C)

0.005 0.005
Displacemt (m)

Differential Settlement (m)


0.000 0.000

-0.005 -0.005

-0.010 -0.010

-0.015 -0.015

-0.020 -0.020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020

DATES DATES
PUHOI TO WAKWORTH MOTORWAY PUHOI TO WAKWORTH MOTORWAY
STRUCTURES MONITORING REPORT STRUCTURES MONITORING REPORT
STRUCTURE PUHOI VIADUCT STRUCTURE PUHOI VIADUCT
ELEMENT PIER E ELEMENT PIER E
DATE 20/07/2020 DATE 20/07/2020

Monitoring Points

SET 17
SET 18

Displacement Graph ( D z) Differential Graph ( D z)


SE_18_SPSS_PIER_07
PUHOI-PIER E SE_18_SPSS_PIER_08 PUHOI-PIER E
Vertical Settlement (Dz) Differential Settlement (Δz) With PIER D
0.020 Reference 0.020
SE_18_SPSS_PIER_E
ALERT
SE_18_SPSS_PIER_D
0.015 0.015
ALARM Reference
Log. (SE_18_SPSS_PIER_E)
0.010 ACTION
0.010 Log. (SE_18_SPSS_PIER_D)
Log. (SE_18_SPSS_PIER_D)

Differential settlement (m)


0.005 0.005
Displacemt (m)

0.000 0.000

-0.005 -0.005

-0.010 -0.010

-0.015 -0.015

-0.020 -0.020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020

12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020
DATES DATES
PUHOI TO WAKWORTH MOTORWAY PUHOI TO WAKWORTH MOTORWAY
STRUCTURES MONITORING REPORT STRUCTURES MONITORING REPORT
STRUCTURE PUHOI VIADUCT STRUCTURE PUHOI VIADUCT
ELEMENT PIER F ELEMENT PIER F
DATE 20/07/2020 DATE 20/07/2020

Monitoring Points

SET 19
SET 20

Displacement Graph ( D z) Dfferential Graph ( D z)

PUHOI-PIER F SE_18_SPSS_PIER_09 PUHOI-PIER F


Vertical Settlement (Dz) Differential Settlement (Δz) With PIER E
0.020 SE_18_SPSS_PIER_10
0.020
SE_18_SPSS_PIER_F
Reference
0.015 SE_18_SPSS_PIER_E
0.015
ALERT Reference

0.010 ALARM Log. (SE_18_SPSS_PIER_F)


0.010
Log. (SE_18_SPSS_PIER_E)
ACTION
0.005 0.005
Displacemt (m)

Differential settlement (m)


0.000 0.000

-0.005 -0.005

-0.010 -0.010

-0.015 -0.015

-0.020 -0.020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020

12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020
DATES DATES
PUHOI TO WAKWORTH MOTORWAY PUHOI TO WAKWORTH MOTORWAY
STRUCTURES MONITORING REPORT STRUCTURES MONITORING REPORT
STRUCTURE PUHOI VIADUCT STRUCTURE PUHOI VIADUCT
ELEMENT SOUTH ABUTMENT ELEMENT SOUTH ABUTMENT
DATE 20/07/2020 DATE 20/07/2020

Monitoring Points

SET 21

SET 20

Displacement Graph ( D z) Dfferential Graph ( D z)

SOUTH ABUTMENT SE_18_SPSS_SA_01


SOUTH ABUTMENT
Vertical Settlement (Dz) SE_18_SPSS_SA_02 Differential Settlement (Δz) With PIER F
0.020 0.020
Reference
SE_18_SPSS_SA
0.015 0.015
ALERT
SE_18_SPSS_PIER F
ALARM
0.010 0.010
ACTION Reference
0.005 0.005
Displacemt (m)

Differential settlement (m)


0.000 0.000

-0.005 -0.005

-0.010 -0.010

-0.015 -0.015

-0.020 -0.020
12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020

12/10/2019

20/01/2020

10/03/2020

29/04/2020

18/06/2020
1/12/2019

7/08/2020
DATES DATES