ID Task Name Duration Start Finish Predecessors

Resource 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Names Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
1 132 KV switchyard and associated works in M/s. CSOT,Thirupati. 249.5 days Wed 2/5/20 Fri 10/30/20
2 Purchase order stage 122.5 days Wed 2/5/20 Mon 6/15/20
3 Release of LOA 1 day Wed 2/5/20 Wed 2/5/20 CSOT CSOT
4 Submission of Bank guarantee 3 days Thu 2/6/20 Sun 2/9/20 3 SVEPL SVEPL
5 Payment of advance 7 days Sun 2/9/20 Sun 2/16/20 4 CSOT CSOT
6 Lock down period 13 days Mon 5/18/20 Sun 5/31/20 5
7 Quarantine Period for Shri vaari electricals workers 14 days Mon 6/1/20 Mon 6/15/20 6
8 CEIG drawing approval 30 days Tue 6/16/20 Fri 7/17/20
9 Preparation of drawings 15 days Tue 6/16/20 Wed 7/1/20 7 SVEPL SVEPL
10 Getting drawing approval 15 days Thu 7/2/20 Fri 7/17/20 9 CEIG CEIG
11 Ordering work 15 days Thu 2/6/20 Fri 2/21/20
12 Vendor finalisation 10 days Thu 2/6/20 Sun 2/16/20 3 SVEPL SVEPL
13 Release of PO for suppliers 5 days Mon 2/17/20 Fri 2/21/20 12 SVEPL SVEPL
14 Civil works 236.5 days Mon 2/17/20 Wed 10/28/20
15 Drawing stage 15 days Mon 2/17/20 Tue 3/3/20
16 Preparation of drawings 7 days Mon 2/17/20 Mon 2/24/20 5 SVEPL SVEPL
17 Submission of drawings for getting approval for construction 1 day Mon 2/24/20 Tue 2/25/20 16 SVEPL SVEPL
18 Approval of drawings by customer 7 days Tue 2/25/20 Tue 3/3/20 17 CSOT CSOT
19 Foundation works for All equipment except Transformer 60 days Tue 6/16/20 Wed 8/19/20
20 Setting out -Survey 2 days Tue 6/16/20 Wed 6/17/20 7,18 SVEPL SVEPL
21 Marking of foundations 2 days Thu 6/18/20 Fri 6/19/20 20 SVEPL SVEPL
22 Excavation 7 days Sat 6/20/20 Sat 6/27/20 21 SVEPL SVEPL
23 Sand filling &PCC 5 days Sat 6/27/20 Thu 7/2/20 22 SVEPL SVEPL
24 Shuttering 5 days Fri 7/3/20 Wed 7/8/20 23 SVEPL SVEPL
25 Reinforcement 5 days Wed 7/8/20 Mon 7/13/20 24 SVEPL SVEPL
26 First lift concreting 6 days Tue 7/14/20 Mon 7/20/20 25 SVEPL SVEPL
27 Shuttering 3 days Mon 7/20/20 Thu 7/23/20 26 SVEPL SVEPL
28 Reinforcement 5 days Thu 7/23/20 Tue 7/28/20 27 SVEPL SVEPL
29 Second lift concreting with fixing foundation bo 5 days Wed 7/29/20 Mon 8/3/20 28 SVEPL SVEPL
30 Curing 5 days Mon 8/3/20 Sat 8/8/20 29 SVEPL SVEPL
31 Back filling, levelling and compaction 5 days Sat 8/8/20 Thu 8/13/20 30 SVEPL SVEPL
32 Whitewashing 5 days Fri 8/14/20 Wed 8/19/20 31 SVEPL SVEPL
33 Foundation works for Transformer 56 days Tue 6/16/20 Fri 8/14/20
34 Setting out -Survey 2 days Tue 6/16/20 Wed 6/17/20 7,18 SVEPL SVEPL
35 Marking of foundations 2 days Thu 6/18/20 Fri 6/19/20 34 SVEPL SVEPL
36 Excavation 3 days Sat 6/20/20 Tue 6/23/20 35 SVEPL SVEPL
37 Sand filling &PCC 5 days Tue 6/23/20 Sun 6/28/20 36 SVEPL SVEPL
38 Reinforcement 3 days Mon 6/29/20 Wed 7/1/20 37 SVEPL SVEPL
39 Shuttering 3 days Thu 7/2/20 Sun 7/5/20 38 SVEPL SVEPL
40 Raft 3 days Sun 7/5/20 Wed 7/8/20 39 SVEPL SVEPL
41 First lift concreting 4 days Wed 7/8/20 Sun 7/12/20 40 SVEPL SVEPL
42 Shuttering 2 days Mon 7/13/20 Tue 7/14/20 41 SVEPL SVEPL
43 Second lift concreting with base plates 4 days Wed 7/15/20 Sun 7/19/20 42 SVEPL SVEPL
44 Curing 5 days Sun 7/19/20 Fri 7/24/20 43 SVEPL SVEPL
45 Excavation for retainer wall 2 days Fri 7/24/20 Sun 7/26/20 44 SVEPL SVEPL
46 Sand filling 2 days Mon 7/27/20 Tue 7/28/20 45 SVEPL SVEPL
47 PCC & flooring n construction of drain chamber 5 days Wed 7/29/20 Mon 8/3/20 46 SVEPL SVEPL
48 Construction of retainer wall 3 days Mon 8/3/20 Thu 8/6/20 47 SVEPL SVEPL
49 Back filling, levelling and compaction 3 days Thu 8/6/20 Sun 8/9/20 48 SVEPL SVEPL
50 Plastering 4 days Mon 8/10/20 Thu 8/13/20 49 SVEPL SVEPL
51 White washing 1 day Fri 8/14/20 Fri 8/14/20 50 SVEPL SVEPL
52 Construction of Control Room 93 days Tue 6/16/20 Wed 9/23/20
53 Excavation for columns 3 days Tue 6/16/20 Thu 6/18/20 7,18 SVEPL SVEPL
54 sand filing 2 days Fri 6/19/20 Sun 6/21/20 53 SVEPL SVEPL
55 PCC 2 days Sun 6/21/20 Tue 6/23/20 54 SVEPL SVEPL
56 Shuttering 3 days Tue 6/23/20 Fri 6/26/20 55 SVEPL SVEPL
57 Reinforcement 3 days Fri 6/26/20 Mon 6/29/20 56 SVEPL SVEPL
58 Mat concreting 3 days Tue 6/30/20 Thu 7/2/20 57 SVEPL SVEPL
59 Shuttering 3 days Fri 7/3/20 Mon 7/6/20 58 SVEPL SVEPL
60 Raising of columns upto plinth beam level 5 days Mon 7/6/20 Sat 7/11/20 59 SVEPL SVEPL
61 Reinforcement for plinth beam 2 days Sat 7/11/20 Mon 7/13/20 60 SVEPL SVEPL
62 Shuttering 4 days Tue 7/14/20 Fri 7/17/20 61 SVEPL SVEPL
63 Concreting 4 days Sat 7/18/20 Wed 7/22/20 62 SVEPL SVEPL
64 Raising of columns upto intermediate level 4 days Wed 7/22/20 Sun 7/26/20 63 SVEPL SVEPL
65 Reinforcement 4 days Mon 7/27/20 Thu 7/30/20 64 SVEPL SVEPL
66 shuttering 4 days Fri 7/31/20 Tue 8/4/20 65 SVEPL SVEPL
67 Laping of reinforcement 4 days Tue 8/4/20 Sat 8/8/20 66 SVEPL SVEPL
68 Concreting up the beam level and roofing 15 days Sat 8/8/20 Mon 8/24/20 67 SVEPL SVEPL
69 Brick work construction 15 days Tue 8/25/20 Wed 9/9/20 68 SVEPL SVEPL
70 Plastering 8 days Thu 9/10/20 Fri 9/18/20 69 SVEPL SVEPL
71 Whitewashing 5 days Fri 9/18/20 Wed 9/23/20 70 SVEPL SVEPL
72 Cable Trench 37 days Fri 8/14/20 Tue 9/22/20
73 Excavation 2 days Fri 8/14/20 Sun 8/16/20 50 SVEPL SVEPL
74 Sand filling 3 days Sun 8/16/20 Wed 8/19/20 73 SVEPL SVEPL
75 PCC 5 days Wed 8/19/20 Mon 8/24/20 74 SVEPL SVEPL
76 Shuttering 5 days Tue 8/25/20 Sun 8/30/20 75 SVEPL SVEPL
77 Reinforcement 2 days Sun 8/30/20 Tue 9/1/20 76 SVEPL SVEPL
78 Raft concreting 4 days Tue 9/1/20 Sat 9/5/20 77 SVEPL SVEPL
79 Shuttering 2 days Sat 9/5/20 Mon 9/7/20 78 SVEPL SVEPL
80 Side wall concreting 7 days Tue 9/8/20 Tue 9/15/20 79 SVEPL SVEPL
81 Curing 7 days Tue 9/15/20 Tue 9/22/20 80 SVEPL SVEPL
82 Fire barrier wall 41 days Fri 8/14/20 Sun 9/27/20
83 Excavation for columns 1 day Fri 8/14/20 Fri 8/14/20 50 SVEPL SVEPL
84 Sand filling 2 days Sat 8/15/20 Mon 8/17/20 83 SVEPL SVEPL
85 PCC 2 days Mon 8/17/20 Wed 8/19/20 84 SVEPL SVEPL
86 Shuttering 2 days Wed 8/19/20 Fri 8/21/20 85 SVEPL SVEPL
87 Reinforcement 2 days Fri 8/21/20 Sun 8/23/20 86 SVEPL SVEPL
88 Mat concreting 2 days Mon 8/24/20 Tue 8/25/20 87 SVEPL SVEPL
89 Shuttering 2 days Wed 8/26/20 Thu 8/27/20 88 SVEPL SVEPL
90 Raising of columns upto plinth beam level 2 days Fri 8/28/20 Sun 8/30/20 89 SVEPL SVEPL
91 Reinforcement for plinth beam 2 days Sun 8/30/20 Tue 9/1/20 90 SVEPL SVEPL
92 Shuttering 2 days Tue 9/1/20 Thu 9/3/20 91 SVEPL SVEPL
93 Concreting 2 days Thu 9/3/20 Sat 9/5/20 92 SVEPL SVEPL
94 Raising of columns up to intermediate level 2 days Sat 9/5/20 Mon 9/7/20 93 SVEPL SVEPL

Project: project schedule - R3 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: Wed 5/13/20

This schedule depends on the following. 1. Lock down lifted on 31.05.20. 2. Quarantine period upto 15.06.20. 3. Advance payment by CSOT before 18.05.20 Page 1
ID Task Name Duration Start Finish Predecessors
Resource 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter
Names Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1
95 Reinforcement 2 days Tue 9/8/20 Wed 9/9/20 94 SVEPL SVEPL
96 Shuttering 2 days Thu 9/10/20 Fri 9/11/20 95 SVEPL SVEPL
97 Lapping of reinforcement 2 days Sat 9/12/20 Mon 9/14/20 96 SVEPL SVEPL
98 Concreting up tie beam level 2 days Mon 9/14/20 Wed 9/16/20 97 SVEPL SVEPL
99 Curing 2 days Wed 9/16/20 Fri 9/18/20 98 SVEPL SVEPL
100 Brick work construction 2 days Fri 9/18/20 Sun 9/20/20 99 SVEPL SVEPL
101 Plastering 2 days Mon 9/21/20 Tue 9/22/20 100 SVEPL SVEPL
102 Curing 2 days Wed 9/23/20 Thu 9/24/20 101 SVEPL SVEPL
103 Whitewashing 2 days Fri 9/25/20 Sun 9/27/20 102 SVEPL SVEPL
104 Yard levelling works 8 days Fri 10/9/20 Sat 10/17/20
105 Filling of selected earth 2 days Fri 10/9/20 Sun 10/11/20 147 SVEPL SVEPL
106 Consolidation 3 days Sun 10/11/20 Wed 10/14/20 105 SVEPL SVEPL
107 Ramming 3 days Wed 10/14/20 Sat 10/17/20 106 SVEPL SVEPL
108 Fencing retainer wall 70 days Fri 8/14/20 Wed 10/28/20 49
109 Excavation 2 days Fri 8/14/20 Sun 8/16/20 50 SVEPL SVEPL
110 PCC 2 days Sun 8/16/20 Tue 8/18/20 109 SVEPL SVEPL
111 Brick work construction 2 days Tue 8/18/20 Thu 8/20/20 110 SVEPL SVEPL
112 Fixing of fencing posts 2 days Thu 8/20/20 Sat 8/22/20 111 SVEPL SVEPL
113 Plastering 2 days Sat 8/22/20 Mon 8/24/20 112 SVEPL SVEPL
114 Fixing of panels 2 days Tue 8/25/20 Wed 8/26/20 113 SVEPL SVEPL
115 Plastering 2 days Thu 8/27/20 Fri 8/28/20 114 SVEPL SVEPL
116 Whitewashing 2 days Sat 8/29/20 Mon 8/31/20 115 SVEPL SVEPL
117 Filling of blue metal 5 days Fri 10/23/20 Wed 10/28/20 116,155,156,157,158,159,160
SVEPL SVEPL
118 Foundation for yard flood light 7 days Fri 8/14/20 Fri 8/21/20 49
119 Excavation 1 day Fri 8/14/20 Fri 8/14/20 50 SVEPL SVEPL
120 PCC 1 day Sat 8/15/20 Sun 8/16/20 119 SVEPL SVEPL
121 Reinforcement 1 day Sun 8/16/20 Mon 8/17/20 120 SVEPL SVEPL
122 Shuttering 1 day Mon 8/17/20 Tue 8/18/20 121 SVEPL SVEPL
123 Concreting with foundation bolts 1 day Tue 8/18/20 Wed 8/19/20 122 SVEPL SVEPL
124 Curing 1 day Wed 8/19/20 Thu 8/20/20 123 SVEPL SVEPL
125 Whitewashing 1 day Thu 8/20/20 Fri 8/21/20 124 SVEPL SVEPL
126 Delivery of equipment 113 days Tue 6/16/20 Thu 10/15/20
127 Lattice type structurals 55 days Tue 6/16/20 Thu 8/13/20 7 SVEPL SVEPL
128 CT and PT 85 days Tue 6/16/20 Tue 9/15/20 7 SVEPL SVEPL
129 SF6 breaker 72 days Tue 6/16/20 Tue 9/1/20 7 SVEPL SVEPL
130 Lightning arrestor 72 days Tue 6/16/20 Tue 9/1/20 7 SVEPL SVEPL
131 35MVA,132/33KV Power transformer 113 days Tue 6/16/20 Thu 10/15/20 7 SVEPL SVEPL
132 Isolator 74 days Tue 6/16/20 Thu 9/3/20 7 SVEPL SVEPL
133 Psot Insulators 74 days Tue 6/16/20 Thu 9/3/20 7 SVEPL SVEPL
134 33 KV panels( Customer supply) 68 days Tue 6/16/20 Thu 9/17/20 7 CSOT CSOT
135 LT panels 68 days Tue 6/16/20 Thu 8/27/20 7 SVEPL SVEPL
136 C&R panels 72 days Tue 6/16/20 Tue 9/1/20 7 SVEPL SVEPL
137 Control cables & accessories 60 days Tue 6/16/20 Wed 8/19/20 7 SVEPL SVEPL
138 Cable tray and accessories 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
139 Earth flats and accessories 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
140 N2 system 73 days Tue 6/16/20 Wed 9/2/20 7 SVEPL SVEPL
141 Battery and Battery chargers( Customer Supply) 45 days Tue 6/16/20 Mon 8/17/20 7 CSOT CSOT
142 Safety items 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
143 other Sundry Items 45 days Tue 6/16/20 Mon 8/3/20 7 SVEPL SVEPL
144 Earthing works 22 days Tue 9/15/20 Thu 10/8/20
145 Excavation for earth mat 2 days Tue 9/15/20 Thu 9/17/20 80 SVEPL SVEPL
146 Earth flat laying 10 days Thu 9/17/20 Mon 9/28/20 145 SVEPL SVEPL
147 Earth mat termination 10 days Mon 9/28/20 Thu 10/8/20 146 SVEPL SVEPL
148 Tray works 17 days Tue 9/15/20 Sat 10/3/20
149 Tray support fabrication 10 days Tue 9/15/20 Fri 9/25/20 138,80 SVEPL SVEPL
150 Tray erection 7 days Sat 9/26/20 Sat 10/3/20 149 SVEPL SVEPL
151 Cabling 13 days Sat 10/3/20 Sat 10/17/20
152 Cable laying 7 days Sat 10/3/20 Sun 10/11/20 150 SVEPL SVEPL
153 Termination 6 days Sun 10/11/20 Sat 10/17/20 152 SVEPL SVEPL
154 Erection of equipment 75 days Mon 8/3/20 Thu 10/22/20
155 Lattice type structurals 7 days Fri 8/14/20 Fri 8/21/20 127 SVEPL SVEPL
156 CT and PT 4 days Tue 9/15/20 Sat 9/19/20 128 SVEPL SVEPL
157 SF6 breaker 3 days Tue 9/1/20 Fri 9/4/20 129 SVEPL SVEPL
158 Lightning arrestor 3 days Tue 9/1/20 Fri 9/4/20 130 SVEPL SVEPL
159 35MVA,132/33KV Power transformer 7 days Thu 10/15/20 Thu 10/22/20 131 SVEPL SVEPL
160 Isolator 5 days Thu 9/3/20 Tue 9/8/20 132 SVEPL SVEPL
161 Psot Insulators 3 days Thu 9/3/20 Sun 9/6/20 133 SVEPL SVEPL
162 LT panels 5 days Fri 8/28/20 Wed 9/2/20 135 SVEPL SVEPL
163 C&R panels 7 days Tue 9/1/20 Tue 9/8/20 136 SVEPL SVEPL
164 Control cables & accessories 10 days Wed 8/19/20 Sun 8/30/20 137 SVEPL SVEPL
165 Cable tray and accessories 7 days Mon 8/3/20 Mon 8/10/20 138 SVEPL SVEPL
166 Earth flats and accessories 10 days Mon 8/3/20 Thu 8/13/20 139 SVEPL SVEPL
167 N2 system 10 days Wed 9/2/20 Sun 9/13/20 140 SVEPL SVEPL
168 Battery and Battery chargers 4 days Tue 8/18/20 Fri 8/21/20 141 SVEPL SVEPL
169 Safety items 5 days Mon 8/3/20 Sat 8/8/20 142 SVEPL SVEPL
170 other Sundry Items 7 days Mon 8/3/20 Mon 8/10/20 143 SVEPL SVEPL
171 CEIG 7 days Fri 10/23/20 Fri 10/30/20
172 Arranging for inspection 1 day Fri 10/23/20 Fri 10/23/20 10,145,148,106,116,152,70,155,156,157,158,159,160,161,162,163,164,165,166,167,168,169,170,71,103,107,125
SVEPL SVEPL
173 Receipt of safety certificate 5 days Sat 10/24/20 Thu 10/29/20 172 SVEPL SVEPL
174 Precomissioning and testing 1 day Thu 10/29/20 Fri 10/30/20 173 SVEPL 10/30

Project: project schedule - R3 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Date: Wed 5/13/20

This schedule depends on the following. 1. Lock down lifted on 31.05.20. 2. Quarantine period upto 15.06.20. 3. Advance payment by CSOT before 18.05.20 Page 2