Professional Documents
Culture Documents
Rate Analysis Based On MSR 2017 Name of Work:-Maintenance of Road Connecting Heikrumakhong Bazar To Umang Connecting Keirang Road
Rate Analysis Based On MSR 2017 Name of Work:-Maintenance of Road Connecting Heikrumakhong Bazar To Umang Connecting Keirang Road
Mean Lead
( 4.00 + 4.80 )/2 = 4.40 km
Say = 4.00 km
Transportation Charges
Lead involved (Source to work site)
(i) Stone metal above 40 mm Lead:- ( 317.00 - 290.00 )+ 4.00 + 2.0 = 33.00 km
(ii) Stone metal below 40 mm Lead:- ( 317.00 - 290.00 )+ 4.00 + 2.0 = 33.00 km
(iii) Bitumen ( 317.00 - 316.00 )+ 4.00 = 5.00 km
(iv) Sand gravel ( 317.00 - 298.00 )+ 4.00 + 1.0 = 24.00 km
(v) Sand ( 317.00 - 298.00 )+ 4.00 + 1.0 = 24.00 km
(vi) Steel/Cement ( 320.00 - 317.00 )+ 4.00 = 7.00 km
From source to Mixing plant
(i) Stone metal above 40 mm Lead:- ( 316.00 - 290.00 )+ 2.0 = 28.00 km
(ii) Bitumen = 1.00 km