You are on page 1of 5

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/326676274

Drying time for transformer core and winding assembly

Article · August 2005

CITATIONS READS
0 2,183

8 authors, including:

Rohan Lucas Priyantha D. C. Wijayatunga


University of Moratuwa Asian Development Bank
131 PUBLICATIONS   383 CITATIONS    36 PUBLICATIONS   340 CITATIONS   

SEE PROFILE SEE PROFILE

Rukshika Pathberiya
LTLT
3 PUBLICATIONS   1 CITATION   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Condition Monitoring System for Outdoor Insulators View project

Magnetising Curves View project

All content following this page was uploaded by Rohan Lucas on 31 July 2018.

The user has requested enhancement of the downloaded file.


Drying Time for Transformer Core and Winding Assembly
J.R.Lucas*, P.D.C.Wijayatunga*, Kosala Gunawardhana#, Rukshika Pathberiya#
N.H.K.L.Sirisena*, J.A.Vitharana*, K.R.S.Dematagolla*, J.A.I.T.Jagoda*

*Department of Electrical Engineering, University of Moratuwa,


#
Lanka Transformer Limited, Angulana

ABSTRACT This mainly consists of insulation materials such as


The drying time of distribution transformer core- pressboard, paper, wood and insulating tape.
winding assembly, at the transformer plant, Lanka Degradation of transformer insulation which reduces
Transformers Limited is presently based on the high the withstand capability of insulation for mechanical
voltage rating. It is the normal practice to dry out the and electrical stresses is the main factor for
transformer core-winding assembly for twenty-four transformer failures, and presence of moisture leads
hours for 11 kV distribution transformers and thirty- to increase the rate of degradation.
six hours for 33 kV distribution transformers,
irrespective of the capacity. This has been decided
considering the total capacity of transformers kept in
the oven during the drying process. This achieves a
larger than required drying time, which has been
considered to have a higher safety margin. But, if the
exact drying time can be found by means of an
acceptable method then an efficient drying is
possible. Thus an in depth study has been carried out
which gives optimum drying out times for typical
distribution transformers.

Index Terms
Transformer, drying time, insulation, winding, core,
loss factor

1.0 Introduction

Figure 2 – Transformer Oven

The transformer core-winding assembly is put into


the oven (figure 2) for up to 36 hours to remove this
moisture.

It is required that the temperature inside the oven


should be kept at a defined value through out the
drying process in order to get complete bonding
Figure 1 – Core-winding assembly ready for ovening between windings and insulation and also to remove
the moisture inside the core-winding assembly.
Drying out of the transformer core-winding assembly
(shown in figure 1) is an extremely important aspect Since moisture evaporates at over 100oC, the oven
in transformer manufacturing. This should be done in temperature is set between 112oC to 120oC. It is
order to remove moisture from the core-winding heated up to a temperature above the ambient before
assembly. loading the transformer core assemblies.

Annual Conference of the IEE Sri Lanka – September 2003


14000
In s u l a t io n r e s is ta n c e - 1 0 0 / 3 3
Meggar reading(MΩ)
H V -E
(A v e r a g e c o r e t e m p e r a t u r e : 1 4 2 .3 2 )
12000
L V -E

10000 H V -L V

6 p e r. M o v . A v g .
8000 (H V -E )

6 p e r. M o v . A v g .
6000 ( L V -E )

6 p e r. M o v . A v g .
(H V -L V )
4000

2000

0
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42

ti m e ( h r s )

6000
In s u la tio n R e s is ta n c e -8 0 0 /1 1
o
(A v e r a g e c o re te m p e ra tu re :1 3 3 .4 1 C )
5000
H V -E
Meggar reading (MOhm)

4000 L V -E

H V -L V
3000
6 p e r. M o v . A v g . (H V -E )

6 p e r. M o v . A v g . (H V -L V )
2000

6 p e r. M o v . A v g . (L V -E )

1000

0
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42
t im e ( h r s )

Figure 3a: Insulation Resistance variation for 100 kVA/33 kV and 800 kVA/11 kV transformers

160

140
Temperature (oC)

120

100

80

60

40

20

0
0 5 10 15 20 25 30 35 40
Time (hrs)
Figure 3b: Temperature variation Inside the Oven for transformers in Figure 3a

Annual Conference of the IEE Sri Lanka – September 2003


1.1 Loss Factor of Insulation
2500
Insulation Resistance100KVA/33 (1)
The loss factor of the transformer Insulation is a

Meggar Reading (M Ohm)


2000

measure of its dielectric power loss. With the 1500

removal of moisture the dielectric power loss 1000

decreases and the insulation resistance will increase. 500


It thus provides information about the quality of the
0
insulation. The loss factor is independent of 0 3 6 9 12 15 18 21 24 27 30 33 36 39

insulation area or thickness, and increase with Time(Hrs)

contamination by moisture. In practice, however, it


is difficult to measure the loss factor during the 2000

drying out process. Thus the decrease in the moisture Insulation Resistance-100KVA/33 (2)

Meggar Reading (M Ohm)


content of the insulation is assessed by measuring 1500

insulation resistance. 1000

500

1.2 Transformer selection


0
0 3 6 9 12 15 18 21 24 27 30 33 36 39
Time (Hrs)
Distribution Transformers were selected for the
study, considering their high voltage ratings (11 kV
and 33 kV) and their capacities (100 kVA, 250 2500 LV-E
kVA,400 kVA,630 kVA,800 kVA). Insulation Resistance-630KVA/33

Meggar Reading (M Ohm)


2000 HV-E

1500
1.3 Performance
LV-HV

1000 6 per. Mov. Avg. (LV-HV)

o 500
The oven temperature was set at 120 C as it is 6 per. Mov. Avg. (HV-E)

required to maintain a safe bond between the 0


0 3 6 9 12 15 18 21 24 27 30 33 36 39
6 per. Mov. Avg. (LV-E)

conductor and the layer insulation. Temperature Time (Hrs)

variation inside the oven was observed through out


the experiment. This was done using temperature
2500
sensors placed inside the oven. The data obtained Insulation Resistance-250KVA/11

was stored in a Data Logger. The Insulation


Meggar Reading (M Ohm)

2000

Resistances throughout the drying process were 1500

measured using the Meggar Test Set. Drying was 1000


continued for 36 hours.
500

First the test was conducted for 2 types of 0


0 3 6 9 12 15 18 21 24 27 30 33 36 39
transformers while the normal production process Time(Hrs)

was going on. The test results were given in the


figure3a, and from that it can be observed that
insulation resistance has increased with time and after 3500
Insulation Resistance-400KVA/33

that tends to drop. 3000


Meggar Reading (M Ohm)

2500

During the test period oven was switched off after 2000

1500
about 16 hours to take out another set of transformers 1000
for tanking. Therefore temperature inside the oven 500
was dropped rapidly as shown in the figure 3b. It was 0

evident that the sudden increases in resistance of both 0 3 6 9 12 15 18 21


Time (Hrs)
24 27 30 33 36 39

transformers have occurred almost at the same time


as the switching off the oven.
160
When the oven is opened the moisture trapped inside 140

the oven can be released to the outside quickly and 120


100

this can be a reason for the above observation. In 80

order to clarify whether there is any relation between 60


40
the above observations, the test was repeated with 20

another set of transformers. Throughout the test the 0

0 3 6 9 12 15 18 21 24 27 30 33 36
oven was not switched off or opened. Results Ti me(hr s)
obtained for the tested transformers are shown in
Figure 4.
Figure 4: Insulation Resistance Variation
&Temperature variation inside the Oven

Annual Conference of the IEE Sri Lanka – September 2003


Although there is a peak in all of the above graphs 2.0 Conclusion
the insulation resistance value at the peak is not high
as the first set of transformers. So it was obvious that With finding out the required drying time for the
the sudden increase in insulation resistance is due to transformer core-winding assembly it is possible to
the opening of the oven. save the energy in the oven at the same time
achieving effective drying of transformer core-
Theoretically the insulation resistance should winding assembly.
increase up to a maximum value and thereafter it
should remain at that value with further drying. But Further studies should be carried out on the
according to the above graphs it is observed that the transformer drying process in order to supplement the
insulation resistances of all the tested transformers conclusion about the required drying time of
were reached to a maximum value and with further transformer core-winding assembly.
drying the theoretically expected variation couldn’t
be obtained.
3.0 Acknowledgements
As transformer core and winding assembly is highly
The authors wish to thank Dr.Rahula Athalage, Head
packed, the removed moisture can be trapped inside
Department of Mechanical Engineering, University
the assembly itself and this may be a reason for the
of Moratuwa for providing the data logger. They also
above deviation of the results from the theory.
wish to express their gratitude to Mr.Ruwan
From the test results it is reasonable to decide the Welagedara, Production Engineer, Mr. K.A.I.
required drying time to be the time when the Gunathunga, Testing Manager and the Technical staff
insulation resistance rises to the peak value. It can be of the transformer factory of Lanka Transformers
concluded that the drying time for the tested Limited for their valuable support. Last but not the
transformers to be in the range of 15 hours to 20 least, they would like to thank the staff and
hours. colleagues at the Department of Electrical
Engineering, University of Moratuwa who provided
In order to confirm this, another set of transformers
help in numerous ways.
of the same ratings were dried for the pre-determined
period, and they were subjected to the required
Routine Tests according to the IEC 60076 Standard. 4.0 References
The results were up to the standard and thereby it can
be concluded that the drying time can be reduced by a J&P Transformer Handbook, Martin J
significant time period. Heatchote, 12th Edition

Annual Conference of the IEE Sri Lanka – September 2003

View publication stats

You might also like