SUBJECT:PROGRAM OF WORKS AND ACCOMPLISHMENT REPORT as of JULY 18, 2016

PERCENT
ITEM %
SCOPE OF WORKS WEIGHT QTY. UNIT PRICE (%)
NO.: ACCOMPLISHMENT
(%)

MOBILIZATION/DEMO
I 2% 1.0 75% 13,124.26 0.01 13,124.26
B., SAFETY & HEALTH

II EARTH WORKS 2% 1.0 100% 10,403.38 0.02 10,403.38


III CONCRETE WORKS 9% 1.0 98% 63,220.51 0.09 49,829.30
IV STEEL WORKS 11% 1.0 95% 75,224.41 0.11 59,290.50
V FORMWORKS 1% 1.0 100% 7,842.54 0.01 7,842.54
VI MASONRY WORKS 14% 1.0 100% 92,590.04 0.14 92,590.04
VII DOORS & WINDOWS 6% 1.0 80% 41,933.60 0.05 33,546.88
VIII ROOFING WORKS 11% 1.0 0% 74,264.09 - -
IX CARPENTRY WORKS 2% 1.0 100% 16,165.24 0.02 16,165.24
X ELECTRICAL WORKS 1% 1.0 50% 8,722.83 0.01 4,361.42
XI PLUMBING WORKS 13% 1.0 95% 90,269.29 0.13 85,755.83
XII SANITARY WORKS 3% 1.0 95% 17,285.61 0.02 16,421.33
XIII PAINTING WORKS 2% 1.0 50% 11,283.66 0.01 5,641.83
IXX TILE WORKS 7% 1.0 30% 47,695.47 0.02 14,308.64
XX HARDWARES 1% 1.0 0% 6,242.03 - -
EARTHWORKS FOR
XXI 1% 1.0 100% 4,001.30 0.01
(SEPTIC TANK) 4,001.30
CONCRETE WORKS
XXII 1% 1.0 100% 5,601.82 0.01
(SEPTIC TANK) 5,601.82
STEEL WORKS
XXIII 2% 1.0 100% 10,883.53 0.02
(SEPTIC TANK) 10,883.53
FORM WORKS
XXIV 1% 1.0 100% 9,923.22 0.01
(SEPTIC TANK) 9,923.22
MASONRY WORKS
XXV 3% 1.0 100% 19,046.18 0.03
(SEPTIC TANK) 19,046.18
INSTALLATION OF 3/4"
XXVI 1% 1.0 100% 8,802.86 0.01
PVC PIPES 8,802.86
REHABILITATION OF
XXVII 6% 1.0 50% 37,692.23 0.03
DEEP WELL 18,846.12
TOTAL 100% 672,218.10 0.75 473,261.95

PREPARED BY:

RAMIL ARTATES
Contractor/CSC BUILDERS
DATE: 18-Jul-16