Questionnaire for Static Evidence of Secondary Containment Systems

General project information


Project / Object = File name
Order placed by / Customer
Bid / Order number

Materials selection for outer pipe* PE 80 PE 100 PVC-U


X X X
Leak detection information optical N2 Cable Other
Type of monitoring* X X X
Overpressure difference [bar]
Underpressure [mbar]
No pressure* X

Additional system data* Installation location 1 Installation location 2

Above ground X In buildings X


In the ground X Outdoors X

Time period for temperature


change:
Ambient temperature: Max. Min. Max. Min.
Installation temperature: Max. Min. Max. Min.

Selection of Secondary Containment components




  X 90° elbow X 45° elbow XX T-red


Inner pipe: Outer pipe:
Material Material
Nominal diameter DN Nominal diameter DN
Outer diameter d Outer diameter d
Wall thickness e Wall thickness e
Nominal pressure rating PN Nominal pressure rating PN
Standard dimension ratio SDR Standard dimension ratio SDR

Jointing technology BF SF IR CT EF EC BF = Butt fusion SF = Socket fusion


Inner pipe* X X X X IR = Infrared CT = Cementing
Outer pipe* X X EF = Electrofusion EC = EPDM coupler

Operating Conditions
Flow media / Concentration Density: g/cm3

Total load time:


Maximum working temperature °C In percent %
Minimum working temperature °C In percent %
Maximum working pressure bar In percent %
Minimum working pressure bar In percent %

Required service life * (years) 10 X 25 X 50 X


* Please mark if applicable