OHSMS-4.3.1-LST-0.1.4
2 Cable dressing in F/L Garage area is very poor Forklift Garage Proper cable dressing to be done Mohit Pandya 01.01.11 Pending
Diesel to be stored properly so that
Diesel was stored in improper condition in the forklift
3 garage area
Forklift Garage fire and spillage hazard can be Nimish Nikam 01.01.11 Pending
removed
Extinguisher should be accessible
4 Fire Extinuguisher is blocked by forklift battery Forklift Garage
and bettery to be removed
Nimish Nikam 01.01.11 completed
6 All the trenches are in open condition WTP-2 trench Cover to be provided Nimish Nikam 13.01.11 Pending
All the chemical dosing tanks installed without platform Platform to be provide to stand at
7 to stand (Caustic, HCL etc.)
WTP-2
the chemical dosing tanks
Nimish Nikam 13.01.11 Pending
Ladder at first floor is without proper hook and base Ladder to be provided with proper
8 support at first floor of WTP-2
WTP-2
hook at base support
Nimish Nikam 13.01.11 Pending
Fan for Operator is not having plug top and direct wire
9 is inserted in socket
WTP-2 Plugtop to be provided Mohit Pandya 13.01.11 completed
12 Rubber mat is not provided at both DC water panel WTP-2 Rubber mat to be provided Mohit Pandya 13.01.11 completed
15 Earthing is not visual on motor body Maaza Syrup Room Exteral earthing to be provided Rahul Saxena 20.01.11 Pending
Improper Trench cover is creating trip hazard on Maaza Trench cover to be repaired and
18 CIP room
Maaza CIP Room
place properly
Nimish Nikam 20.01.11 Pending
Improper electrical glanding at maaza pulp transfer Maaza Pulp Transfer
19 pump switch box room
proper glanding to be done Rahul Saxena 20.01.11 Pending
Hindustan Coca-Cola Beverages Pvt. Ltd.
OHSMS-4.3.1-LST-0.1.4
Maaza pulp transfer pump switch box is totally corroded Maaza Pulp Transfer Switch box to be repaired or
20 asn water immersion found inside room removed as it is not in use
Rahul Saxena 20.01.11 Pending
Exhuast fan switch board is hanging with one bolt and Maaza Pulp Transfer
21 water immersion found inside room
Switch box to be fixed properly Rahul Saxena 20.01.11 Pending
Locking arrangement to be
Filler Right side Door-1 doesn't have locking
25 arrangement
Maaza Filler provided by the means of magnetic Raghvendra Shukla 20.01.11 completed
switch or clamp
Locking arrangement to be
Filler Right side Door-2 doesn't have locking
26 arrangement
Maaza Filler provided by the means of magnetic Raghvendra Shukla 20.01.11 completed
switch or clamp
Locking arrangement to be
27 Filler middle Door-1 doesn't have locking arrangement Maaza Filler provided by the means of magnetic Raghvendra Shukla 20.01.11 completed
switch or clamp
Locking arrangement to be
28 Filler middle Door-2 doesn't have locking arrangement Maaza Filler provided by the means of magnetic Raghvendra Shukla 20.01.11 completed
switch or clamp
Fail-safe type Interlocking to be
Filler Right side Door-1 limit switch is not in working
29 condition and also not adequate
Maaza Filler provided which can not be defeat Rahul Saxena 20.01.11 Pending
easily
Fail-safe type Interlocking to be
Filler Right side Door-2 limit switch is not in working
30 condition and also not adequate
Maaza Filler provided which can not be defeat Rahul Saxena 20.01.11 Pending
easily
Fail-safe type Interlocking to be
Filler middle Door-1 limit switch is not in working
31 condition and also not adequate
Maaza Filler provided which can not be defeat Rahul Saxena 20.01.11 Pending
easily
Fail-safe type Interlocking to be
Filler middle Door-2 limit switch is not in working
32 condition and also not adequate
Maaza Filler provided which can not be defeat Rahul Saxena 20.01.11 Pending
easily
33 Maaza Crowner motor coupling guard is not provided Maaza Filler Coupling guard to be provided Raghvendra Shukla 20.01.11 Pending
Condensate drain point valve discharge line is not
Condensate drain point valve
34 provided in case of condensate release with steam Maaza Filler
discharge life to be extended
Raghvendra Shukla 20.01.11 completed
some one can get injured
Cam-Pusher guard is not proper (Hindges are welded Fixed type proper Zero Access m/c
35 and found open)
Maaza B/W
guarding to be provided
Raghvendra Shukla 20.01.11 Pending
37 Toe guard is not provided at the both side platforms Maaza B/W Toe Guards to be provided Raghvendra Shukla 20.01.11 completed
Hindustan Coca-Cola Beverages Pvt. Ltd.
OHSMS-4.3.1-LST-0.1.4
Loading end Introducer Supporting rotating gear chain Fixed type proper Zero Access m/c
38 is not having aguard
Maaza B/W
guarding to be provided
Raghvendra Shukla 20.01.11 Pending
Chain guard of Maaza date coder is totally rusted and Fixed type proper Zero Access m/c
40 damaged
Maaza Date Coder
guarding to be provided
Raghvendra Shukla 20.01.11 Pending
Maaza Caser guard is not proper - It is as good as no Fixed type proper Zero Access m/c
41 guard provided
Maaza caser
guarding to be provided
Raghvendra Shukla 20.01.11 Pending
Maaza Uncaser guard is not proper - It is as good as no Fixed type proper Zero Access m/c
42 guard provided
Maaza caser
guarding to be provided
Raghvendra Shukla 20.01.11 Pending
Cross over overplatform at caser outfeed conveyor is
43 totally damaged
Maaza caser Cross over platform to be repaired Raghvendra Shukla 20.01.11 Pending
chain guard is missing at manual paletizing station of Fixed type proper Zero Access m/c
44 maaza
Maaza Palletizing
guarding to be provided
Raghvendra Shukla 20.01.11 Pending
Level Indicator pipe is in broken condition at RGB 1
45 Bottle washer
RGB 1 B/W Level Indicator to be provided Raghvendra Shukla 22.01.11 completed
Swing gate of Cardboard storage near PET Utility is not PET Cardboard
46 working Storage
Swing gate to be repaired Nimish Nikam 22.01.11 completed
Rubber mat is not present in front of raw syrup room
47 electrical Panel
Raw Syrup Room Rubber mat to be provided Saurabh Trivedi 24.01.11 Pending
Limit Switch of Maaza Filler Left door is in bypass
48 condition
Maaza Filler Room Limit switch to be brought in line Rahul Saxena 24.01.11 Pending
Limit Switch of Maaza Filler Right door is in bypass
49 condition
Maaza Filler Room Limit switch to be brought in line Rahul Saxena 24.01.11 completed
Hot water inlet line to Maaza Pasteurizer is not having
50 insulation
Maaza Filler Room Isulation to be provided Ronak Pancholi 24.01.11 completed
Improper guard of Maaza Uncaser. It is not fixed and Proper fix type guard to be
51 purely human dependant
Maaza Uncaser
provided
Raghvendra Shukla 27.01.11 Pending
Improper guard of Maaza caser. It is not fixed and Proper fix type guard to be
52 purely human dependant
Maaza Caser
provided
Raghvendra Shukla 27.01.11 Pending
Secondary containment is not available in Diesel tank of Sencodary containment to be
53 D.G 4
D.G Room
provided
Prasanna Bhandary 27.01.11 completed
Secondary Containment with send
54 There is no containment for Oil Drum Storage room Oil Storage Area
filled to be provided
Ronak Pancholi 29.01.11 completed
55 New WTP stain platform toe guard is not available WTP - 2 Toe guard to be provided Prasanna Bhandary 29.01.11 completed
56 Toe guard is not available at first floor railing WTP - 2 Toe guard to be provided Prasanna Bhandary 4.02.11 completed
57 PPE box is not available WTP - 2 PPE box to be provided Ritesh Solanki 4.02.11 completed
58 JOG of PET Filler is not in working condition PET Filler - 120 BPM JOG to be repaired Rahul Saxena 4.02.11 completed
59 FD / ID Fan PanelRubber Mat - Not Present Brequette Boiler Rubber mat to be provided Saurabh Trivedi 4.02.11 completed
60 Soot Blower Control PanelRubber Mat - Not Present Brequette Boiler Rubber mat to be provided Saurabh Trivedi 4.02.11 completed
Hindustan Coca-Cola Beverages Pvt. Ltd.
OHSMS-4.3.1-LST-0.1.4
66 Oil Fired Boiler -1 PanelRubber Mat - Not Present Oil fired Boiler Rubber mat to be provided Saurabh Trivedi 18.02.11 completed
There is no adequate ladder or platform to see the level
67 at caustic tank of B/W RGB 1
RGB 1 B/W Lader or platform to be provided Raghvendra Shukla 18.02.11 Pending
68 Inlet pipe is to short at Caustic Tank B/W RGB 1 RGB 1 B/W Piep length to be increased Raghvendra Shukla 18.02.11 completed
69 Front door interlock of Blow Moulding is bypassed Blow Moulding Room Interlock to be made operational Rahul Saxena 18.02.11 Pending
Valve to be open and should
Safety shower main valve in CIP room found in close
70 condition
CIP Room remain open all the time. Optechs Ramesh Yelapure 18.02.11 completed
to be counceled
71 Pit in front of Chilling plant is open Roads & Drains Pit to be closed Srinivas Mantri 18.02.11 completed
72 Pit in front of briquette Boiler is open Roads & Drains Pit to be closed Srinivas Mantri 23.02.11 completed
73 Pit in front of CO2 Storage tank Roads & Drains Pit to be closed Srinivas Mantri 23.02.11 completed
74 Pit besides F.O Storage tank Roads & Drains Pit to be closed Srinivas Mantri 07.03.11 completed
Drain covers at Wrehouse Loading point is in broken Ware House FG
75 condition forklift may fall in it Loading
Cove to be provided Nimish Nikam 07.03.11 completed
Sugar Godown Electrical forklift charger socket is in
76 broken condition - Risk of Electrocution
Sugar Godown Socket to be changed Saurabh Trivedi 07.03.11 completed
Pipe is in hanging condition just at entrance of PCC
77 (LT) Room. Some one may hit at the time of entry
LT Room To be removed Srinivas Mantri 18.03.11 completed
Either switch box to be fixed
Switch box is in open condition with live supply.
78 Someone may get shock
HT Panel Room properly or Electrical supply to be Rahul Saxena 18.03.11 completed
isolated
Cable trench cover to be put
79 Cable trench cover plat is open in HT Panel Room HT Panel Room
properly
Rahul Saxena 23.03.11 completed
Interlock Sensot of pellatizer of 600 BPM line has
80 removed
600 BPM Line Sensor to be installed properly Manish Singh 23.03.11 completed
81 Bottle Washer Loading Table Chain guard is missing RGB 1 B/W Guard to be provided Raghvendra Shukla 23.03.11 completed
82 Bottle Washer Main Drive Chain guard is missing RGB 1 B/W Guard to be provided Raghvendra Shukla 02.04.11 completed
83 Bottle Washer Transmission Chain guard is missing RGB 2 B/W Guard to be provided Raghvendra Shukla 02.04.11 Pending
There is no railing besides the ladder of Fire Pump
84 House some one may fall down
Fire Pump House Barrication to be repaired Nimish Nikam 02.04.11 completed
Hindustan Coca-Cola Beverages Pvt. Ltd.
OHSMS-4.3.1-LST-0.1.4
There is no NRV/Flash Back arrestor in the Gas Cutting NRV/Flash Back arrestor to be
85 set
Engg. Workshop
provided
Nimish Nikam 11.04.11 completed
Drain covers besides Fill Inspection conveyor RGB 1 is
86 in damaged condition
RGB 1 Filling Hall Covers to be repaired Manish Singh 11.04.11 completed
Motor of Loading Conveyor of Line 1 is not having chain Loading Conveyor
87 guard Area
Guard to be fixed Raghvendra Shukla 11.04.11 completed
Indication light of the pellatizer is not in working
88 condition
RGB 2 Pellatizer Lights to be repaired Manoj Pal 11.04.11 Pending
Lights over the RGB pellatizer lifter is not in working
89 condition
RGB 2 Pellatizer Lights to be repaired Manoj Pal 11.04.11 completed
Cable tray between pellate out put conveyor and light
To be repaired and cables to be
90 panel is in broken condition and cables are in hanging RGB 2 Pellatizer
dressed properly
Manoj Pal 21.04.11 Pending
condition
Protection Barrier in front of pellatizer out put conveyor
91 is in broken condition
RGB 2 Pellatizer Barrier to be repaired Manish Singh 21.04.11 completed
Side Railign of Mazza bottle washer is in broken
92 condition
Maaza B/W Railing to be repaired Manish Singh 21.04.11 completed
Strom Drain cover at the middle of W/H Loading point is Ware House FG
94 in damaged condition. Fork-lift wheel may fall in it Loading
Cover to be repaired Nimish Nikam 28.04.11 completed
Swimming tubes are not available at Aeration Tank of Swimming tubes to be procured
96 ETP
ETP
and placed at ETP
Ritesh Solanki 28.04.11 completed
97 Caser miser motro dosing pump guard is not proper PET 120 Filler Proper Guard to be provided Manish Singh 05.05.11 Pending
front door left door interlock of blow moulding is PET 120 Blow
100 bypassed Moulding
Interlock to be taken in line Saurabh Trivedi 05.05.11 Pending
102 piston pump cover is bypassed PET 120 Filler Proper Guard to be provided Manish Singh 05.05.11 Pending
103 Glycol line pressure guage is not working Chilling plant To be replaced Ronak Pancholi 05.05.11 Pending