You are on page 1of 4

Date: / /2020

Water leakage weakly check list

If there is
leakage what is
Areas to be checked water Is there any the action Time
S. No leakage leakage? taken? comment taken
From borhole one to
1 concrate tank
From borhole two to
2 concrate tank
Raw water for cleaning in
3 production area
Raw water for cleaning in
4 water treatment area
5 In pump hose
6 Around bacth tank
7 In water treatment room
10 Boiler room
11 Creat washer
12 Bottle washer
13 Conveyor lubrication
14 Cooling tower
15 Chiller room
18 In water treatment room
19 In productin area (Mixer)
20 Simple syrup room
21 final syrup room
22 CIP room
23 Canteen
24 Males toilet and shawor
25 Females toilet and shawor
26 Staff toilet male
27 Staff toilet female
28 Fillet toilet
29 WWTP area
30 Grass land area
31 Manucipal line to canteen

Checked by: SIgnature:


Approved by: SIgnature:
Date: / /2020
Steam leakage weakly check list
If there is leakage what is the action
S. No Areas to be checked steam leakage Is there any leakage? taken? comment Time taken
1 Boiler room
2 Bottle washer
3 Sugar dissolving
4 CIP room
5 Water treatment room

Checked by: SIgnature:


Approved by: SIgnature:
Date: / /2020
Air leakage weakly check list
Areas to be checked Air Is there any If there is leakage what is Time
S. No leakage leakage? the action taken? comment taken
1 compressor room
2 Boiler room
3 Simple syrup room
4 Fainal syrup room
5 CIP room
6 Batch tank area
7 Production area wet area
8 Production area dry area

Checked by: SIgnature:


Approved by: SIgnature: